ENGINEERING - PRODUKSI

PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI


2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255.00 BCM 19,659.00 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500.40 BCM 2,359.08 TON
PIT / BLOCK : B Selatan / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Loading OB KURANG : 511,754.60 BCM 17,299.92 TON
HALAMAN : 1 / 11 2-Dec ## 29
Day Shift Night Shift

BLOK 9-15

PIT SELATAN

- EX 1250 - 08 - EX 950 - 05 - EX 950 - 06


- Freedig Soil - Loading OB blasting - Loading OB blasting
- Hauler : 6 Unit - Hauler : 4 Unit - Hauler : 4 Unit
- Distance : 2100 m - Distance : 1100 m - Distance : 1100 m
- Dumpingan : disposal soil - Dumpingan : IPD EX BUMA - Dumpingan : IPD EX BUMA
- Reminder : Ramp ke arah utara

EX 1250-08
EX 950-05 EX 950-06

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diterima Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Selatan / PER DAY : 22,250.20 BCM 786 TON
CLASSIFICATION : Aliran Air KURANG : 511,755 BCM 17,300 TON
HALAMAN : 2 / 11 25-Dec ##
Day Shift Night Shift

BLOK 9-15

DEWATERING

Arah aliran air


Outlet Pumping

Pompa KSB 150-02 pumping Area sump / yang Area sump / yang
Blokade Air tidak ditenggelamkan
utara (sump blok 22) ditenggelamkan
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 946,219 BCM 54,106 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Selatan / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Area Drill and Blast KURANG : 901,719 BCM 51,747 TON
HALAMAN : 3 / 11 25-Dec ##
Day Shift Night Shift

DNB

Area plan blasting & Area plan blasting &


drilling drilling
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Selatan / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Dumpingan KURANG : 511,755 BCM 17,300 TON
HALAMAN : 4 / 11 2-Nov ##
Day Shift Night Shift

DISPOSAL

Dumpingan OB
- dari Fleet 950 -04
- Reminder : Ramp to RL +75

OB
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Disposal Soil KURANG : 901,719 BCM 17,300 TON
HALAMAN : 5 / 11 2-Nov ## 23
Day Shift Night Shift

DISPOSAL SOIL

Soil
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Selatan / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Hgh Risk Area KURANG : 511,755 BCM 17,300 TON
HALAMAN : 6 / 11 20-Oct ##
Day Shift Night Shift

BLOK 9-11

AREA HIGH RISK

Area High Risk


ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Utara / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Loading OB KURANG : 511,755 BCM 17,300 TON
HALAMAN : 7 / 11 25-Dec ##
Day Shift Night Shift

BLOCK 25-28

PIT B

EX 950 - 09

EX 950 - 09

STEP 2 (PERALIHAN) STEP 1


- EX 950 - 09 - EX 950 - 09
- Loading OB blasting - Loading OB blasting
- Hauler : 6 Unit - Hauler : 6 Unit
- Distance : 2100 m - Distance : 2400 m

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 556,255 BCM 19,659 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Utara / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Aliran air KURANG : 511,755 BCM 17,300 TON
HALAMAN : 8 / 11 25-Dec ##
Day Shift Night Shift

BLOK 24-28

DEWATERING

Arah Aliran Air

Bundwall Pompa KSB 200 - 02 Transfer Area yang di


Outlet pumping ke Blok 22 melalui paritan di tenggelamkan
lowwal
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 946,219 BCM 54,106 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Utara / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Area Drill and Blast KURANG : 901,719 BCM 51,747 TON
HALAMAN : 9 / 11 25-Dec ##
Day Shift Night Shift

Plan Blasting

Area plan blasting &


drilling
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 01-02 Januari 2023 PLAN : 946,219 BCM 54,106 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 44,500 BCM 2,359 TON
PIT / BLOCK : B Utara / PER DAY : 22,250.20 BCM 786.36 TON
CLASSIFICATION : Dumpingan KURANG : 901,719 BCM 51,747 TON
HALAMAN : 10 / 11 25-Dec ##
Day Shift Night Shift

DISPOSAL

Dumpingan dari fleet selatan (Fleet 09)

OB
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

GENERAL JOB LIST

No JOB LIST START DATE OVERDUE

Elevasi sump :

1 SUMP -24 = 4.476

2 SUMP -22 = 12.21

3 SUMP -14 = 16.62

4 SUMP -09 = 13.31

Aktivitas ketika hujan :

1 Re-sloping HW Blok 29 bench 30-20, blok 26-27 bench 30, blok 10-11 bench 30

2 Blokade air dari jalan ke pit

General