ENGINEERING - PRODUKSI

PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI


2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000.00 BCM 27,000.00 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,334.77 BCM 9,182.35 TON
PIT / BLOCK : B Selatan / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Loading OB dan Coal Getting B2 KURANG : 421,665.23 BCM 17,817.65 TON
HALAMAN : 1 / 11 2-Dec ## 29
Day Shift Night Shift

BLOK 9-16

PIT SELATAN

- EX 950-07 STEP 1 STEP 1


- Loading Soil - EX 950 - 05 - EX 950 - 04
- Hauler : 6 Unit - Loading OB - Loading lumpur
- Distance : 2100 m - Hauler : 5 Unit - Hauler : 5 Unit
- Dumpingan : Disposal Soil - Distance : 1350 m - Distance : 1300 m
- Dumpingan : IPD EX BUMA - Dumpingan : IPD EX BUMA

EX 950-04
EX 1250-08
EX 950-05 EX 950-04

STEP 2
STEP 2 - EX 480-08
- EX 1250-08 - EX 950 - 04
- EX 950-05 - Coal Getting B2
- Loading pasir - Ekspose B1
- Loading Lumpur - Hauler : 5 Unit
- Hauler : 6 Unit - Hauler : 5 Unit
- Hauler : 5 Unit - Distance : 3000 m
- Distance : 2100 m - Distance : 1300 m
- Distance :1000 m - Dumpingan : ROM PII
- Dumpingan : Disposal IPD - Dumpingan : IPD EX BUMA

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diterima Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Selatan / PER DAY : 25,210.78 BCM 9,182 TON
CLASSIFICATION : Aliran Air KURANG : 421,665 BCM 17,818 TON
HALAMAN : 2 / 11 25-Dec ##
Day Shift Night Shift

BLOK 9-15

DEWATERING

Arah aliran air

Pompa KSB 150-02


Area sump / yang Area sump / yang pumping ke paritan
Blokade Air
ditenggelamkan tidak ditenggelamkan lowwal mengarah
sump besar
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Selatan / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Area Drill and Blast KURANG : 421,665 BCM 17,818 TON
HALAMAN : 3 / 11 25-Dec ##
Day Shift Night Shift

DNB

Area plan blasting &


drilling
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Selatan / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Dumpingan KURANG : 421,665 BCM 17,818 TON
HALAMAN : 4 / 11 2-Nov ##
Day Shift Night Shift

DISPOSAL

Dumpingan OB
- dari Fleet 950 - 05, 06
- Reminder : To RL +48
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Disposal Soil KURANG : 421,665 BCM 17,818 TON
HALAMAN : 5 / 11 2-Nov ## 23
Day Shift Night Shift

DISPOSAL SOIL

Soil
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Selatan / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Hgh Risk Area KURANG : 421,665 BCM 17,818 TON
HALAMAN : 6 / 11 20-Oct ##
Day Shift Night Shift

BLOK 9-11

AREA HIGH RISK

Area High Risk


ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Utara / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Loading OB dan Coal Getting B2 KURANG : 421,665 BCM 17,818 TON
HALAMAN : 7 / 11 25-Dec ##
Day Shift Night Shift

BLOCK 25-28

PIT B

EX 950 - 09
EX 950 - 09

STEP 1 STEP 2 (PERALIHAN)


- EX 950 - 09 - EX 950 - 09
- Loading OB Blasting / Ekposes B1 - Loading OB Blasting/ Ekpose B1
- Hauler : 6 Unit - Hauler : 5 Unit
- Distance : 2100 m - Distance : 2200 m
- Dumpingan : OPD Tanggul - Dumpingan : OPD Tanggul

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Utara / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Aliran air KURANG : 421,665 BCM 17,818 TON
HALAMAN : 8 / 11 25-Dec ##
Day Shift Night Shift

BLOK 24-28

DEWATERING

Arah Aliran Air

Pompa KSB 200 - 02 Transfer


Area yang di ke Blok 22 melalui paritan di Area yang tidak di
Bundwall Outlet pumping
tenggelamkan lowwal tenggelamkan
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 27,000 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Utara / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Area Drill and Blast KURANG : 421,665 BCM 17,818 TON
HALAMAN : 9 / 11 25-Dec ##
Day Shift Night Shift

Plan Blasting

Area plan blasting &


drilling
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 09-10 Januari 2023 PLAN : 633,000 BCM 54,106 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 211,335 BCM 9,182 TON
PIT / BLOCK : B Utara / PER DAY : 25,210.78 BCM 9,182.35 TON
CLASSIFICATION : Dumpingan KURANG : 421,665 BCM 44,924 TON
HALAMAN : 10 / 11 25-Dec ##
Day Shift Night Shift

DISPOSAL

Dumpingan OB dari fleet selatan (Fleet 09)

OB
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT PADA IDI
2022

GENERAL JOB LIST

No JOB LIST START DATE OVERDUE

Elevasi sump :

1 SUMP -22 = 13.232

2 SUMP -14 = 15.141

3 SUMP -09 = 9.14

Aktivitas ketika hujan :

1 Re-sloping HW Blok 29 bench 30-20, blok 26-27 bench 30, blok 10-11 bench 30

2 Blokade air dari jalan ke pit

General