OPR/F-029

Area : PEDAYAK WEST

Shift : S02 S01

PERINTAH KERJA HARIAN Tanggal : 16/06/2023 17/06/2023

DARI : PSV 2 Dept. Head KEPADA : TEMBUSAN : Engineering Dept. Lokasi kerja : PEDAYAK WEST

KONTROL
No. LOKASI / UNIT INSTRUKSI KERJA KODE BAHAYA LAPORAN PELAKSANAAN PROGRESS
BAHAYA

1. Prioritas Loading di bukit 140 utara-selatan, dumping tssp c Shift I :


TOPSOIL ROMA ,EX2376, EX2374, 2. Clearing area jalan roma tembus disposal Cadas 2 PTO, SAP,
1 EX922,DZ956,DZ147,DZ149,, 3. Fokus pembentukan akses tembus ke ke disposal cadas 2 B
Mensespam
4. 2 PC Fokus di sayap dan badan Jalan Roma Shift II :

1. LAODING TOPSOIL SESUAI ACUAN STAGE PLAN - Shift I :


TOPSOIL CADAS - TSSP L ,EX2361,
DUMOING KE TSSP L PTO, SAP,
2 EX310,EX802,DZ 964 LC DZ 969 LC
2. DZ SUPORT FRONT DAN JALAN B
Ex 2361 Loading top soil progres jalan ke hidros 3 Mensespam
DZ 752 LC DZ 654,,
3. DZ SPREADING TSSP L Shift II : Ex 310 Loading top soil sisi krik 70%
Ex 802 General pelebaran jalan

1. LOADING TOPSOIL SESUAI ACUAN Di Wet Area Shift I :


Block Dump Hydros Series 2
HYDROS SERIES 2,EX2402,EX292, PTO, SAP,
3 Ex.906 CSA Dz.967 Dz.146 ,,
2. DZ SUPORT FRONT TSSP ENGGANG B
Mensespam
3. Dumping di TSSP enggang,
Shift II :

Shift I : PTO, SAP, JSA,


TOPSOIL HELIOS ,EX319,EX2396, 1.LOADING TOPSOIL SESUAI ACUAN STAGE PLAN
4 EX2370,Dz 656 Dz 1210 t Dz 755 Dz 2. DUMPING KE TSSP ENGGANG B Mensespam, FCI,
852 DZ655,, 3. DZ SUPORT FRONT DAN JALAN
Shift II : DCI

Shift I : PTO, SAP, JSA,


1.LOADING TOPSOIL SESUAI ACUAN STANGE PLAN
TOPSOIL HYDROS 3,EX317 ,
5 EX2345,EX 923,DZ954 Dz128 ,,
2. DUMPING KE BARIER B Mensespam, FCI,
3.DZ SUPORT JALAN
Shift II : DCI

Shift I :
6 PEDAYAK WEST ,,,,,

Shift II :

Shift I :
7 ,,,,

Shift II :

Shift I :
8 ,,,,

Shift II :

Shift I :
9 ,,,,

Shift II :

Shift I :
10 ,,,,

Shift II :

Shift I :
11 ,,,,

Shift II :

Shift I :
12 ,,,,

Shift II :

Shift I :
13 ,,,,

Shift II :

Shift I :
14 ,,,,

Shift II :

Plan Service :
Catatan : Pastikan selalu melakukan inspeksi dan observasi dan membuat SAP 1Pama
dan segera follow up deviasi yang ada.

Dibuat Tanda Tangan : Dilaporkan (GL Shift 1) Tanda Tangan : Dilaporkan (GL Shift 2) Tanda Tangan :

Oleh :
Oleh :

61121066

Oleh : ANDI YULIUS


Kepada : Group Leader
Kepada : Pit Service Kepada : Pit Service
Dept.Head Dept.Head