PEKERJAAN :
ALAMAT :
REKAPTULASI RENCANA ANGGARAN BIAYA
HARGA TOTAL
NO URAIAN PEKERJAAN
(Rp)
TOTAL Rp15,450,625.36
DI BULATKAN Rp16,000,000.00
Terbilang :
RENCANA ANGGARAN BIAYA (RAB)
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
HARGA
VOLUME HARGA TOTAL
NO URAIAN PEKERJAAN SATUAN SATUAN
(Rp) (Rp) (Rp)
(Vol) (HSP) = ( Vol x HSP )
I PEKERJAAN PERSIAPAN Rp1,000,000
1 Pembersihan dan Perataan Lahan - m2 4,550 Rp0
2 Pengukuran & Pemasangan Bouwplank - m' 55,030 Rp0
3 Pembuatan Steger/Perancah dari Bambu - m2 328,452 Rp0
4 Penyediaan Air & Listrik Kerja 1.00 ls 1,000,000 Rp1,000,000
HARGA
VOLUME HARGA TOTAL
NO URAIAN PEKERJAAN SATUAN SATUAN
(Rp) (Rp) (Rp)
VIII PEKERJAAN PENUTUP LANTAI Rp0
1 Pemasangan Keramik 50x50 - m2 186,595 Rp0
2 Pemasangan Keramik 25x25 - Kamar Mandi - m2 156,092 Rp0
3 Pemasangan Keramik 25x25 - Teras - m2 156,092 Rp0
4 Pemasangan Plint Keramik - m' 49,920 Rp0
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan m2 Rp4,550
2 Pengukuran & Pemasangan Bouwplank m' Rp55,030
3 Pembuatan Steger/Perancah dari Bambu m2 Rp328,452
4 Penyediaan Air & Listrik Kerja ls Rp1,000,000
IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu m3 Rp6,626,300
2 Pemasangan Balok Gording, Nok, Kait Angin m3 Rp8,763,400
3 Pemasangan Rangka Atap m2 Rp142,830
4 Pemasangan Atap m2 Rp63,260
5 Pemasangan Bubungan m' Rp99,727
6 Pemasangan List Plank m' Rp124,950
7 Pemasangan Talang Air m' Rp101,520
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)
X PEKERJAAN FINISHING
1 Pengecetan Dinding Dalam m2 Rp19,173
2 Pengecetan Dinding Luar m2 Rp19,173
3 Pengecetan Kusen Pintu & Jendela m2 Rp36,160
4 Pengecetan Daun Pintu & Jendela m2 Rp36,160
5 Pengecetan Plafond m2 Rp36,160
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)
1 Pemasangan Kaca 5mm m2 Rp124,188
2 Pemasangan Kaca 7mm m2 Rp183,448
3 Pasangan Kunci bh Rp126,850
4 Pemasangan Engsel Pintu bh Rp22,938
5 Pemasangan Grendel Jendela bh Rp31,410
6 Pemasangan Kait Angin Jendela bh Rp22,850
7 Pemasangan Engsel Jendela bh Rp26,955
1.1.f (c) 1 m2 Pembersihan dan Pengupasan Permukaan Tanah (Striping) s.d. Tanaman 2cm
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu 5/7 (Rawa) m3
Paku 2"-3" kg
Kayu Papan 3/20 (Rawa) m3
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Bambu diameter 6-8/600 cm Batang
Tali ijuk m3
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Catatan: Pembuatan steger/perancah secara sewa dapat menggunakan analisis bidang SDA.
1.7.1.a (c) Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m Untuk Volume s.d. 200 m3 Dalam S
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Batu belah m3
Semen portland Kg
Pasir Pasang m3
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Pasir Urug m3
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Batu Belah m3
Pasir Urug m3
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Pasir Urug m3
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Rawa m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang kayu L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
Kayu Rawa 4/6 M3
Plywood 9 mm uk. 120 x 240 mm Lbr
Kayu Dolken Ø 8-10/400 cm Batang
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu kelas III ( Pinus ) m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu pecah mesin 2-3 cm m3
Kayu Kalimantan ( Meranti Batu ) 5/7 & 4/6 (ikat) m3
Plywood 9 mm uk. 120 x 240 mm Lbr
Dolken kayu Ø 8-10/400 cm Batang
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland Kg
Pasir beton Kg
Kerikil (Maks 30mm) Kg
Air Liter
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 15%
F Harga Satuan Pekerjaan (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang Kayu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
A TENAGA KERJA
Pekerja L.01 OH
Tukang Besi L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.6.1.16.e Pemasangan 1 m2 rangka atap genteng Palentong, kayu kelas II ( Kayu Kamper
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Kaso 5/7 cm m3
Kayu Reng 2 x 3 cm m3
Paku Biasa kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n1 m2
Atap
Genteng
Palentong A.4.5.2.3. Pemasangan1 m2 Atap Genteng Palentong Besar/Morando
Besar/Mor
ando
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Genteng palentong besar (morando) Buah
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Genteng bubung Buah
Semen Portlan Kg
Pasir pasang M3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.6.1.22. Pemasangan 1 m’ Lisplank Ukuran (3 x 30) cm, Kayu Kelas I atau Kelas II
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan kayu m3
Paku 5 dan 7 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Seng plat m
Paku Biasa kg
Kayu Papan Jati m3
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.4.1.11 Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm tebal ½ Batu Campuran
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Bata merah buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Semen portland Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Semen portland Kg
JUMLAH HARGA BAHAN
C PERALATAN
Tipe S,fc’
12, 5 Mpa
( Setara
Campuran NO URAIAN KODE SATUAN
1SP : 3PP)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata berongga buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN
A.4.4.1.23. Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24 dengan Mortar Tipe N,fc’ 5,2 Mp
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata terawang buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN
A.4.6.1.1. Pembuatan dan Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kel
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Balok - Kusen m3
Paku 10 cm Kg
Lem kayu Kg
JUMLAH HARG
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Papan Jati m3
Lem kayu Kg
JUMLAH HARG
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Papan Jati m3
Lem kayu Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.6.1.8. Pembuatan 1 m Daun pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup
2
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Papan m3
Paku 1 cm - 2,5 cm Kg
Lem kayu Kg
Plywood tebal 4 mm Ukuran (90 x 220) Lembar
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
PEKERJAAN PLAFOND
A.4.6.1.20. Pemasangan 1 m2 Rangka Langit-Langit (60 x 60) cm, Kayu Kelas II atau III
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Kaso 5 x 7 cm m3
Paku 7- 10 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m2
Langit-
Langit
Papan
Gipsum,
A.4.5.1.7. Pemasangan 1 m2 Langit-Langit Papan Gipsum, Tebal 9 mm
Tebal 9
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan gipsum 120x240 cm Lembar
Paku sekrup Kg
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang Kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
List Gipsum Profil 15 cm Pj. 2.00 m' m'
Tepung gypsum kg
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Keramik 50 x 50 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1m2
Lantai
Keramik
Ukuran 20
A.4.4.3.35. Pemasangan 1m2 Lantai Keramik Ukuran 20 s.d. <30cm
s.d. <30cm
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kramik 25 x 25 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1m2
Lantai
Keramik
Ukuran 20
A.4.4.3.35. Pemasangan 1m2 Lantai Keramik Ukuran 20 s.d. <30cm
s.d. <30cm
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kramik 20x20 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN
JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m2
Dinding
Porselen
10cm x
A.4.4.3.48. Pemasangan 1 m2 Dinding Porselen 10cm x 20cm
20cm
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Porslen Buah
Semen portland Kg
Pasir pasang m3
Semen warna Kg
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plint keramik Buah
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN
A TENAGA KERJA
Upah % bahan
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Las Dop Buah
Klem Buah
Mangkok Buah
Saklar Buah
Fitting Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Upah %
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Klem biasa Buah
MCCB (Boks MCB) Buah
MCB Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 3/4” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 4” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 3” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Wastafel Lengkap Unit
Semen portland Kg
Pasir pasang m3
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bak cuci piring Unit
Waterdrain Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kran air Buah
Sealtape Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kran Sink Buah
Sealtape Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Floor drain Unit
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata merah Buah
Semen portland Kg
Pasir pasang m3
Porselen 11x11 bh
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Closet jongkok Unit
Pasangan bata 1PC:3PS m2
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat dasar Kg
Pengencer L
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata merah bh
Semen portland Kg
Pasir pasang M3
Pasir beton M3
Batu Splite (2-3cm) M3
Besi Beton Kg
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Tukang Gali L.01 OH
Tukang Pasang L.02 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata Merah
Semen Portland
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
PEKERJAAN FINISHING
A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penu
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penu
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN
A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kaca tebal 5mm m2
Silicone Sealant 300 ml Tube
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kaca tebal 7mm m2
Silicone Sealant 300 ml Tube
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kunci tanam Buah
JUMLAH HARG
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Engsel pintu Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kunci slot Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kait angin Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Engsel Buah
JUMLAH HARG
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
PEKERJAAN LANDSCAPE
A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Semen portland kg
Pasir Beton kg
Batu Splite (2-3cm) kg
Air Liter
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
TUAN PEKERJAAN
UN 2022 & PERMENPU 2016
PE - 78 M2
Rp -
Rp -
JUMLAH HARGA BAHAN Rp -
Rp 4,550
0% Rp -
Rp 4,550
Rp 55,030
0% Rp -
Rp 55,030
nggi 6 meter
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp 328,452
0% Rp -
Rp 328,452
Rp -
Rp -
Rp -
JUMLAH HARGA BAHAN Rp -
Rp 46,750
0% Rp -
Rp 46,750
N
Rp 687,173
0% Rp -
Rp 687,173
Rp 121,100
0% Rp -
Rp 121,100
Pondasi Gedung
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
N
Rp 372,540
0% Rp -
Rp 372,540
Rp 45,500
0% Rp -
Rp 45,500
Rp 45,500
Rp -
Rp 45,500
Rp 118,750
0% Rp -
Rp 118,750
bekisting)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
N
Rp 5,546,060
0% Rp -
Rp 5,546,060
bekisting)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
N
Rp 5,663,210
0% Rp -
Rp 5,663,210
Bangunan Gedung
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
RJA Rp 93,060
N
Rp 408,610
0% Rp -
Rp 408,610
RJA Rp 1,381
Rp -
Rp -
Rp 6,626,300
0% Rp -
Rp 6,626,300
Rp -
Rp -
Rp 8,763,400
0% Rp -
Rp 8,763,400
Rp -
Rp -
Rp 142,830
0% Rp -
Rp 142,830
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 99,727
0% Rp -
Rp 99,727
Rp -
Rp -
Rp 101,520
0% Rp -
Rp 101,520
70 Rp 900 Rp 63,000
8.320 Rp 1,180 Rp 9,818
0.049 Rp 183,333 Rp 8,983
JUMLAH HARGA BAHAN Rp 81,801
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 108,551
0% Rp -
Rp 108,551
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 32,144
0% Rp -
Rp 32,144
Rp -
N Rp -
Rp 27,135
0% Rp -
Rp 27,135
12x11x24 dengan Mortar Tipe S,fc’ 12, 5 Mpa ( Setara Campuran 1SP : 3PP)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp -
N Rp -
Rp 191,387
0% Rp -
Rp 191,387
ngan Mortar Tipe N,fc’ 5,2 Mpa ( Setara Campuran 1SP : 4PP)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp -
N Rp -
Rp 110,211
0% Rp -
Rp 110,211
Rp -
Rp -
Rp 16,183,500
0% Rp -
Rp 16,183,500
Rp -
Rp -
Rp 1,727,500
0% Rp -
Rp 1,727,500
I atau II
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp -
Rp -
Rp 700,200
0% Rp -
Rp 700,200
Rp -
Rp -
Rp 566,020
0% Rp -
Rp 566,020
Rp -
Rp -
Rp 81,610
0% Rp -
Rp 81,610
Rp -
N Rp -
Rp 43,318
0% Rp -
Rp 43,318
Rp -
N Rp -
Rp 33,006
0% Rp -
Rp 33,006
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 186,595
0% Rp -
Rp 186,595
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 156,092
0% Rp -
Rp 156,092
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 156,092
0% Rp -
Rp 156,092
Rp -
N Rp -
Rp 223,694
0% Rp -
Rp 223,694
Rp -
N Rp -
Rp 49,920
0% Rp -
Rp 49,920
Rp -
Rp -
Rp 151,056
0% Rp -
Rp 151,056
Rp -
Rp -
Rp 236,900
0% Rp -
Rp 236,900
Rp -
Rp -
Rp 19,480
0% Rp -
Rp 19,480
Rp -
Rp -
Rp 92,780
0% Rp -
Rp 92,780
Rp -
Rp -
Rp 74,555
0% Rp -
Rp 74,555
Rp 116,913
Rp -
Rp -
Rp 381,013
0% Rp -
Rp 381,013
Rp -
Rp -
Rp 207,400
0% Rp -
Rp 207,400
Rp -
Rp -
Rp 65,850
0% Rp -
Rp 65,850
Rp -
Rp -
Rp 129,850
0% Rp -
Rp 129,850
Rp -
Rp -
Rp 510,800
0% Rp -
Rp 510,800
me 0,30 m3
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)
Rp -
Rp -
Rp 797,900
0% Rp -
Rp 797,900
Rp -
Rp -
Rp 409,500
0% Rp -
Rp 409,500
Rp -
Rp -
Rp 360,000
0% Rp -
Rp 360,000
Rp -
Rp -
Rp 598,863
0% Rp -
Rp 598,863
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 175,000
0% Rp -
Rp 175,000
Rp -
Rp -
Rp 19,173
0% Rp -
Rp 19,173
Rp -
Rp -
Rp 36,160
0% Rp -
Rp 36,160
Rp -
Rp -
Rp 36,160
0% Rp -
Rp 36,160
Rp -
Rp -
Rp 124,188
0% Rp -
Rp 124,188
Rp -
Rp -
Rp 183,448
0% Rp -
Rp 183,448
Rp -
Rp -
Rp 126,850
0% Rp -
Rp 126,850
Rp -
Rp -
Rp 31,410
0% Rp -
Rp 31,410
Rp -
Rp -
Rp 22,850
0% Rp -
Rp 22,850
Rp -
Rp -
Rp 26,955
0% Rp -
Rp 26,955
1 BAHAN DASAR
A BATU KALI
1 Bulat Utuh m3 170,000
2 Bulat Belah m3 190,000
3 Pecah 10/15 m3 200,000
4 Pecah 5/7 m3 210,000
5 Pecah 3/5 m3 220,000
B KERIKIL
1 Timbun m3 150,000
2 Sawur/Koral m3 150,000
3 Beton 0,5/1 m3 235,000
4 Beton 1/2 m3 240,000
5 Beton 2/3 m3 230,000
6 Biasa m3 160,000
7 Tras Giling m3 220,000
C BATU BATA
ex lokal bh 900
Bata Expose bh 1,857
D PASIR
1 Urug m3 80,000
2 Pasang m3 183,333
3 Beton m3 200,000
E TANAH
1 Padas m3 80,000
2 Liat m3 75,000
F KAPUR
1 Pasang m3 300,000
2 Semen Merah m3 180,000
G PORTLAND CEMENT
1 Merk | 40 kg zak 44,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
2 Merk | 1 kg kg 1,100
3 Merk | 50 kg zak 59,000
4 Merk | 1 kg kg 1,180
5 Merk II 40 kg zak 46,000
6 Merk II 1 kg kg 1,150
7 Merk Il 50 kg zak 55,000
5 Semen Putih 40 kg zak 80,000
6 Semen Putih 50 kg zak 88,000
7 Semen warna kg 11,000
I1 BAHAN PENUTUP ATAP
A SIRAP(100 lbr) pak 180,000
B GENTENG BETON
1 Genteng Beton Warna standard bh 3,800
2 Genteng Beton Warna Special bh 5,100
3 Genteng Beton Warna Khusus bh 5,500
4 Kerpus Beton Warna Standard bh 6,700
5 Kerpus Beton Warna Special bh 6,600
6 Kerpus Beton Warna Khusus bh 10,500
C GENTENG TANAH LIAT
1 Vlaam/Plentong bh 1,900
2 Kodok bh 2,500
3 Kodok Glasur bh 3,500
4 Nok kerpus Kodok bh 5,200
5 Nok kerpus Kodok Glasur bh 7,500
6 Plentong super besar 18 bh/m2 bh 2,850
7 Nok kerpus plentong super bh 5,500
D GENTENG KACA
1 Vlaam tebal 2 mm bh 9,800
2 Vlaam tebal 3 mm bh 10,200
3 Kodok tebal 2 m bh 10,000
4 Kodok tebal 3 mm bh
E Asbes 6 1/2(Asbes Gelombang Besar) bh
1 200 cmX 102 cmX5mm bh 62,000
2 225 cmX 102 cmX5mm bh 74,000
3 250 cmX 102 cmX5mm bh 72,000
4 200 cmX 102 cmX6mm bh 68,000
5 225 cmX 102 cmX6mm bh 76,000
6 250 cm X 102 cmX6mm bh 86,000
F Asbes 14(Asbes Gelombang Kecil)
1 150 cm X 105 cm X4mm bh 42,000
2 180 cmX 105 cm X4mm bh 51,000
3 210 cm X 105 cm X4mm bh 58,000
4 240cm X 105 cm X 4mm bh 62,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
5 270 cm X 105 cm X 4 mm bh 66,000
6 300 cmX 105 cmX4 mm bh 75,000
ONDULINE:95 cmx 200cmx0.3mm lbr 160,000
ONDUVILLA:40cmx 106 cmx 0,3mm lbr 95,000
7 NOK Jabes nok
Kerpus Genteng bh 31,000
Stel Besar bh 45,000
Paten Besar bh 39,000
8 Nokstel gelombang harflex
Stel Besar bh 45,000
Patent Besar bh 21,000
Plat besar bh 49,000
9 NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cmx 50 cmx0,3mm lbr 115,000
G ASBES PLAT
100cmX100 cmX 3mm bh 15,500
100cmX 100 cmX4mm bh 17,000
50 cm X 200 cm X 2,8 mm bh 13,000
40 cm X 200 cm X 2,8mm bh 12,000
FIBER PLAT
uk.100cmx 100cmx 4mm lbr 25,000
unt Plafond uk.120cmx240cmx4mm lbr 75,000
unt Plafond uk.122cmx244cmx4mm lbr
GRC BOARD 77,000
uk.122cmx244cmx 5mm lbr 100,000
uk.122cmx244cmx 6mm lbr 130,000
uk.122cmx244cmx8mm lbr 199,500
uk.122cmx 244cmx 10mm lbr 255,000
H FIBRE GLASS(JABES)
180X92cm bh 56,000
200X 92cm bh 80,000
250X92 cm bh 84,000
180x105cm bh 66,000
210x105 cm bh 86,000
250x105 cm bh 84,000
1 SENG PLAT
BJLS 0,18 lebar 55 cm m' 22,000
BJLS 0,20x 90 lebar 55 cm m' 23,000
BJLS 0,28 lebar 55 cm m' 33,000
BJLS 0,30x 90 lebar 55 cm m' 31,000
J SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 40,000
BJLS 0,20 panjang 180 cm lbr 48,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
BJLS 0,30 panjang 180 cm lbr 62,000
BJLS 0,40 panjang 180 cm lbr 70,000
V. BAHAN CETAK
A BUIS BETON Ø
1 10cm-100 cm bh 35,000
2 20 cm-100 cm bh 45,000
3 30 cm-100 cm bh 75,000
4 50cm-100 cm bh 135,000
5 60 cm-100 cm bh 165,000
6 70 cm-100 cm bh 180,000
7 10 cm-100 cm bh 22,000
8 15 cm-100cm bh 24,500
9 20 cm-100 cm bh 28,000
10 30 cm-100 cm bh 44,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
11 50 cm-100 cm bh
B LUBANG ANGIN (ROSTER)PC+PASIR
1 10x20cm bh 8,000
2 20x20cm bh 9,000
3 25x25cm bh 10,200
4 30x30 cm bh 12,000
5 15x25cm bh 9,250
6 15x30cm bh 10,200
X. BAHAN KACA
1 POLOS
3mm m2 85,000
5mm m2 95,000
2 ES KABUR
3mm m2 105,000
5mm m2 120,000
3 RAY BAND
3mm m2 90,000
5mm m2 105,000
Silicone Sealant 300 ml tube 35,000
I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan 0.00 m2
2 Pengukuran & Pemasangan Bouwplank 0.00 m'
3 Pembuatan Steger/Perancah dari Bambu 0.00 m2
4 Penyediaan Air & Listrik Kerja 1.00 ls
IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu 0.00 m3
2 Pemasangan Balok Gording, Nok, Kait Angin 0.00 m3
3 Pemasangan Rangka Atap 0.00 m2
4 Pemasangan Atap 0.00 m2
5 Pemasangan Bubungan 0.00 m'
6 Pemasangan List Plank 0.00 m'
7 Pemasangan Talang Air 0.00 m'
X PEKERJAAN FINISHING
1 Pengecetan Dinding Dalam 0.00 m2
2 Pengecetan Dinding Luar 0.00 m2
3 Pengecetan Kusen Pintu & Jendela 0.00 m2
4 Pengecetan Daun Pintu & Jendela 0.00 m2
5 Pengecetan Plafond 0.00 m2
I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan Volume Total = 0.00 m2
Panjang (P) = m Rumus = PxL
Lebar (L) = m Volume = 0.00 m2
Pondasi (B)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Pondasi (C)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m
Pondasi (A)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Pondasi (B)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Pondasi (C)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Pondasi (B)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Elv 0.00
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
Elv +0.100
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Elv -0.100
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
Elv -0.05
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
Elv -0.2
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
Elv -0.35
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
Tinggi =3,35 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs
Tinggi =3,15 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs
Tinggi =0,6 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs
Tinggi (T) = m
RB.2 (+ 3.500 )
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
RB.3 (+ 3.300 )
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
BG (Balok Gunung)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
BL (Balok Latiu)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Plat Kanopi
Luas (A) = m2 Rumus = PxT
Tebal (T) = m Volume = 0.00 m3
Kayu 8/12
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Kayu 5/10
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Kayu 6/12
Panjang (P) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
7 Pemasangan 1 m' List Plank uk. 3x20cm Volume Total = 0.00 m'
Panjang (P) = m Rumus = P
Volume = 0.00 m'
IV PEKERJAAN DINDING
1 Pemasangan Dinding Bata Merah Volume Total = 0.00 m2
Level +4.000
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Level +3500
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Level +3300
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Level +2450
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Level +1450
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Gunung-Gunung 1
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2
Gunung-Gunung 2
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2
Gunung-Gunung 3
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2
Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang R.Shalat
Lebar (L) = m Rumus = -(P x L x Q)
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Ruang Tamu
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
V PEKERJAAN KAYU
1 Volume Kusen Kayu Pintu & Jendela Volume Total = 0.00 m3
Kusen D-01
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen D-02
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen DW
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen DS
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen W-01
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Kusen W.02
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen W.03
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen W.04
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen BV-1
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Kusen BV.2
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs
Daun.P D-02
Tinggi (T) = m Rumus = (P x L x Q )
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Daun.P DW
Tinggi (T) = m Rumus = (P x L x Q )
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Pintu DS
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.01
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.02
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.03
Luas 1 (L1) = m Rumus = (L1+L2) x Q
luas 2 (L2) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.04
Luas 1 (L1) = m Rumus = (L1+L2) x Q
luas 2 (L2) = m Volume = 0.00 m2
Jumlah (Q) = pcs
V PEKERJAAN PLAFOND
V PEKERJAAN FINISHING
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Level +3.200
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Level +4.400
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang BV.2
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang R.Shalat
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Ruang Tamu
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Samping Kanan 1
Area (A) = m Rumus = A
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Volume = 0.00 m2
Samping Kanan 2
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Samping Kanan 3
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Samping Kiri 1
Area (A) = m Rumus = A
Volume = 0.00 m2
Samping Kiri 2
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Belakang 1
Area (A) = m Rumus = A
Volume = 0.00 m2
Belakang 1
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2
Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang BV.2
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Pintu D.02
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Pintu DW
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Pintu DS
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.01
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.02
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Jendela W.03
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela W.04
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela BV
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela BV.2
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Pintu DW
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs
Jendela W.01
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs
Jendela W.02
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs
Jendela W.03
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs
Jendela W.04
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
Lebar (L2) = m
Jumlah (Q2) = pcs
Jendela BV.1
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Jendela BV.2
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs
W.02 = pcs
W.03 = pcs
W.04 = pcs
NO URAIAN PEKERJAAN SAT.
a b d
I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan m2
2 Pengukuran & Pemasangan Bouwplank m'
a Kayu 5/7 (Rawa) m3
b Paku 2"-3" kg
c Kayu Papan 3/20 (Rawa) m3
2 Pekerjaan Kolom m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
Kayu Rawa 4/6 M3
Plywood 9 mm uk. 120 x 240 mm Lbr
Kayu Dolken Ø 8-10/400 cm Batang
IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu m3
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg
4 Pemasangan Atap m2
Genteng palentong besar (morando) Buah
5 Pengecetan Plafond m2
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
3 Pasangan Kunci bh
4 Pemasangan Engsel Pintu bh
5 Pemasangan Grendel Jendela bh
6 Pemasangan Kait Angin Jendela bh
7 Pemasangan Engsel Jendela bh
0.00 m2
0.00
0.01 0.00 0.00 m3 0.00 m3
0.02 0.00 0.00 kg 0.00 kg
0.01 0.00 0.00 m3 0.00 m3
0.00
1.25 0.00 0.00 Batang 0.00 Batang
0.19 0.00 0.00 m3 0.00 m3
1.00 0.00 ls
0.00
1.20 0.00 0.00 m3 0.00 m3
163.00 0.00 - Kg - kg/50kg
0.52 0.00 0.00 m3 0.00 m3
0.00
1.20 0.00 0.00 m3 0.00 m3
0.00
1.20 0.00 0.00 m3 0.00 m3
0.43 0.00 0.00 m3 0.00 m3
Err:509
1.20 Err:509 Err:509 m3 Err:509 m3
0.00
0.27 0.00 0.00 m3 0.00 m3
2.00 0.00 0.00 kg 0.00 kg
0.60 0.00 0.00 Liter 0.00 Liter
210.00 0.00 0.00 kg 0.00 kg
3.00 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3
0.00
4.00 0.00 0.00 kg 0.00 kg
2.00 0.00 0.00 Liter 0.00 Liter
212.00 0.00 0.00 kg 0.00 kg
4.50 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3
0.15 0.00 0.00 M3 0.00 M3
3.50 0.00 0.00 Lbr 0.00 Lbr
20.00 0.00 0.00 Batang 0.00 Batang
0.00
0.32 0.00 0.00 m3 0.00 m3
3.20 0.00 0.00 kg 0.00 kg
1.60 0.00 0.00 Liter 0.00 Liter
210.00 0.00 0.00 kg 0.00 kg
3.00 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3
0.14 0.00 0.00 m3 0.00 m3
2.80 0.00 0.00 Lbr 0.00 Lbr
16.00 0.00 0.00 Batang 0.00 Batang
0.00
371.00 0.00 0.00 Kg - kg/50kg
698.00 0.00 0.00 Kg 0.00 m3
1047.00 0.00 0.00 Kg 0.00 m3
215.00 0.00 0.00 Liter 0.00 Liter
0.00
0.04 0.00 0.00 m3 0.00 m3
0.40 0.00 0.00 Kg 0.00 Kg
0.20 0.00 0.00 Liter 0.00 Liter
0.02 0.00 0.00 m3 0.00 m3
0.35 0.00 0.00 Lbr 0.00 Lbr
6.00 0.00 0.00 Batang 0.00 Batang
241.57
1.05 241.57 253.65 kg 253.65 kg
0.02 241.57 3.62 kg 3.62 kg
Err:509
371.00 Err:509 Err:509 kg Err:509 kg/50kg
698.00 Err:509 Err:509 kg Err:509 m3
1047.00 Err:509 Err:509 kg Err:509 m3
215.00 Err:509 Err:509 Liter Err:509 Liter
Err:509
0.04 Err:509 Err:509 m3 Err:509 m3
0.40 Err:509 Err:509 kg Err:509 kg
0.20 Err:509 Err:509 Liter Err:509 Liter
0.35 Err:509 Err:509 Lbr Err:509 Lbr
6.00 Err:509 Err:509 Batang Err:509 Batang
Err:509
1.05 Err:509 Err:509 kg Err:509 kg
0.02 Err:509 Err:509 kg Err:509 kg
0.00
1.10 0.00 0.00 m3 0.00 m3
15.00 0.00 0.00 Kg 0.00 Kg
5.60 0.00 0.00 Kg 0.00 Kg
0.00
1.10 0.00 0.00 m3 0.00 m3
15.00 0.00 0.00 Kg 0.00 Kg
3.00 0.00 0.00 Kg 0.00 Kg
0.00
0.01 0.00 0.00 m3 0.00 m3
0.00 0.00 0.00 m3 0.00 m3
0.25 0.00 0.00 kg 0.00 kg
0.00
12.00 0.00 0.00 Buah 0.00 Buah
0.00
4.00 0.00 0.00 Buah 0.00 Buah
8.00 0.00 0.00 Kg - kg/50kg
0.03 0.00 0.00 M3 0.00 M3
0.00
0.01 0.00 0.00 m3 0.00 m3
0.05 0.00 0.00 Kg 0.00 Kg
0.00
1.05 0.00 0.00 m 0.00 m
0.02 0.00 0.00 kg 0.00 kg
0.02 0.00 0.00 m3 0.00 m3
0.00
70.00 0.00 0.00 buah - buah
8.32 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 m3 0.00 m3
0.00
5.18 0.00 0.00 Kg - kg/50kg
0.03 0.00 0.00 m3 0.00 m3
0.00
3.25 0.00 0.00 Kg - kg/50kg
0.00
30.00 0.00 0.00 buah 0.00 buah
11.00 0.00 0.00 Kg 0.00 kg/50kg
0.04 0.00 0.00 m3 0.00 m3
0.00
1.10 0.00 0.00 m3 - m3
1.25 0.00 0.00 Kg - Kg
1.00 0.00 0.00 Kg - Kg
0.00
0.04 0.00 0.00 m3 - m3
0.50 0.00 0.00 Kg - Kg
0.00
0.02 0.00 0.00 m3 - m3
0.30 0.00 0.00 Kg - Kg
1.00 bh
1.00 1.00 1.00 bh 1.00 bh
0.00
0.02 0.00 0.00 m3 - m3
0.25 0.00 0.00 Kg - Kg
0.00
0.36 0.00 0.00 Lembar - Lembar
0.11 0.00 0.00 Kg - Kg
0.00
1.05 0.00 0.00 m' - m'
0.01 0.00 0.00 kg - kg
0.00
1.05 0.00 0.00 Dus - Dus
10.00 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3
0.00
1.05 0.00 0.00 Dus - Dus
10.40 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3
0.00
1.05 0.00 0.00 Dus - Dus
10.40 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3
0.00
53.00 0.00 0.00 Buah - Buah
9.30 0.00 0.00 Kg - zak/50kg
0.02 0.00 0.00 m3 - m3
2.75 0.00 0.00 Kg - Kg
14.00
3.00 14.00 42.00 btg 42.00 btg
10.00 14.00 140.00 m 140.00 m
2.00 14.00 28.00 Buah 28.00 Buah
2.00 14.00 28.00 Buah 28.00 Buah
3.00 14.00 42.00 Buah 42.00 Buah
24.00 14.00 336.00 Buah 336.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
pcs 11.00 pcs
pcs 3.00 pcs
pcs 5.00 pcs
pcs 1.00 pcs
pcs 1.00 pcs
pcs 5.00 pcs
pcs 3.00 pcs
1.00
3.00 1.00 3.00 btg 3.00 btg
15.00 1.00 15.00 m 15.00 m
1.00 1.00 1.00 Buah 1.00 Buah
2.00 1.00 2.00 Buah 2.00 Buah
24.00 1.00 24.00 Buah 24.00 Buah
1.00 1.00 1.00 Buah 1.00 Buah
2.00 1.00 2.00 Buah 2.00 Buah
pcs 1.00 pcs
0.00
0.10 0.00 0.00 Kg - Kg
0.10 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr
0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr
0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr
0.00
1.10 0.00 0.00 m2 - lbr
0.05 0.00 0.00 Tube - Tube
0.00
1.10 0.00 0.00 m2 - lbr
0.05 0.00 0.00 Tube - Tube
249,600,000
KEBUTUHAN MATERIAL
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022
VOLUME BESI
NO ITEM PEKERJAAN
6 8
kg kg
- 664.06
Dalam Batang - 140
1 Besi Ø6 - btg
2 Besi Ø8 144 btg
3 Besi Ø10 33 btg
4 Besi Ø12 102 btg
ERIAL
VOLUME BESI
10 12
kg kg
- 294.35
- 760.30
239.15 -
- -
239.15 1,054.64
32 99
-
6,501,051.00
2,330,993.00
11,216,700.00
FORMAT VOLUME PEKERJAAN PONDASI FOO
DIMENSI
NO TYPE QTY
PANJANG LEBAR TINGGI BETON BEKISTING
mm mm mm m3 m2
x y h
0 - -
1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
15 - -
AAN PONDASI FOOTPLAT (CAKAR AYAM)
VOLUME
PASIR LANTAI PASIR BUANG URUGAN
BESI GALIAN
URUG KERJA URUG TANAH KEMBALI
kg m3 m3 m3 m3 m2 m2
(1/3xGalian)
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
INPUT PEMBESIAN
Selimut Tul Atas X Tul Bawah X Tul Atas Y Tul Bawah X
Dia jarak Dia jarak Dia jarak Dia jarak
mm mm mm mm mm mm mm mm mm
- - - - - - - -
10 2 - - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
D29 D32 Tul Atas-X Tul Bawah-X
dia panjang jarak qty berat dia panjang jarak
kg kg mm mm mm kg mm mm mm
- -
1 - D10 400 2 -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
NAMA PROYEK :
JENIS PEKERJAAN :
KET LANTAI :
Data Balok
Ket As / Type
No Ket Lebar Tinggi Panjang Qty
Kode Balok
mm mm mm mm
mm m3 m2 m2 kg mm mm qty qty
182.9177 4 5 6 7
2.39 11.95 31.86 437.08
Data Pembesian
ama Atas Tul Utama Bawah Begel
Kiri Dia Kanan Tengah Kiri Dia N Kanan Tengah Kiri
8 9 10 11 12 13 14 15 16 17
embesian
Volume Besi
awah Tul Begel
kg mm mm kg kg kg kg kg
kg kg kg kg kg kg kg kg
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
1,022.90
Dimensi
Tebal
No Type Plat Luas Berat
Plat X Y Arah X
dia. pjg
mm mm mm m2 kg mm' mm'
0 1 2 3 4 5 6
241.57
1 PL-1 100 1425 3,650 5.20 93.43 10 1,425
2 PL-2 120 1675 3950 6.62 114.45 10 1,675
3 PL-3 100 450 1600 0.72 14.65 10 450
4 PL-3 100 450 2150 0.97 19.04 10 450
5 - - - -
6 - - - -
7 - - - -
8 - - - -
9 - - - -
10 - - - -
11 - - - -
DETAIL HITUNGAN PEMBESIAN
Tul Utama Atas Tul Utama Bawa
Arah X Arah Y Arah X
qty berat dia. pjg qty berat dia. pjg qty
mm' kg mm' mm' mm' kg mm' mm' mm'
- -
21.96 10 3,650 11 24.75 - - 93.43 -
28.05 10 3,960 12 29.30 - - 114.45 -
3.40 10 1,610 4 3.97 - - 14.65 -
4.25 10 2,160 4 5.33 - - 19.04 -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
LUME BESI BETON PER DIAMTER
13 16 19 22 25
kg kg kg kg kg
- - - - - 93.43 93.43 -
- - - - - 114.45 114.45 -
- - - - - 14.65 14.65 -
- - - - - 19.04 19.04 -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
VOLUME STRUKTUR TANGGA
DIMENSI
TANGGA Type 1, Lt GF - Lt 2
Bordes A 2.70 1.40 0.15 1 1
1 1
1 1
1 1
1 1
TANGGA Type 1, Lt GF - Lt 2
DETAIL PEMBESIAN
Selimut Jarak Jumlah
Nama Tulangan Dia Kg/m
Beton Tulangan Tulangan
200.15 200.15
1.9 0.52 0.52 3.48 145.03 145.03
1.3 0.11 1.49 55.12 55.12
ke arah bordes
58.58 58.58
2.5 0.19 2.65 33.48 33.48
1.0 0.06 1.10 16.28 16.28
1.0 0.06 1.10 8.82 8.82
16.75 16.75
1.4 0.19 1.55 9.80 9.80
1.0 0.06 1.10 4.41 4.41
1.0 0.06 1.10 2.54 2.54
136.91 136.91
2.7 0.52 3.19 90.74 90.74
0.8 0.06 0.90 46.17 46.17
57.69 57.69
0.9 0.92 1.86 41.31 41.31
1.4 0.08 1.52 16.39 16.39
110.10 110.10
2.1 0.92 3.05 74.77 74.77
1.4 0.08 1.52 35.33 35.33
Besi Beton ( kg )
8 10 13 16 19 22
D8 D10 D13 D16 D19 D22
- - - 905.50
-
VOLUME PERHITUNGAN BESI PROFIL ( BAJA )
8/12
5/10
Note : Kebutuhan Kayu 8/12 Panjang 3 meter 6 btg
Kebutuhan Kayu 6/12 Panjang 3 meter 4 btg
8/12
6/12
Note : Kebutuhan Kayu 8/12 Panjang 3 meter 7 btg
Kebutuhan Kayu 6/12 Panjang 3 meter 19 btg
1
2
3
4
1
2
3
4
4/6
2/3
Note : Kebutuhan Kaso Kayu 4/6 Panjang 3 meter - btg
Kebutuhan Reng Kayu 2/3 Panjang 3 meter 0 btg
PANJANG
TOTAL
mm
3,620
4,240
1,756
1,570
3,490
-
2,265
2,380
1,017
1,916
14,075
8,179
PANJANG
TOTAL
mm
19,051
31,512
18,081
3,908
-
-
-
-
-
-
19,051
53,501
PANJANG
TOTAL
mm
-
-
-
-
-
-
-
-
-
-
-
-
-
LIST MATERIAL
84,000,000