Anda di halaman 1dari 188

RENCANA ANGGARAN BIAYA

PEKERJAAN :

PEMBANGUNAN RUMAH 1 TYPE 78 M2

ALAMAT :
REKAPTULASI RENCANA ANGGARAN BIAYA

BANGUNAN : RUMAH 1 LANTAI


TYPE : RUMAH TYPE 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA TOTAL
NO URAIAN PEKERJAAN
(Rp)

I PEKERJAAN PERSIAPAN Rp1,000,000.00


II PEKERJAAN TANAH & PONDASI Rp0.00
III PEKERJAAN BETON Rp2,935,309.29
IV PEKERJAAN ATAP Rp0.00
V PEKERJAAN PASANGAN DINDING Rp0.00
VI PEKERJAAN PINTU & JENDELA Rp245,000.00
VII PEKERJAAN PLAFOND Rp0.00
VIII PEKERJAAN PENUTUP LANTAI Rp0.00
IX PEKERJAAN INSTALASI LISTRIK & AIR Rp10,270,316.06
X PEKERJAAN FINISHING Rp0.00
XI PEKERJAAN KUNCI & KACA Rp0.00
XII PEKERJAAN LANDSCAPE Rp1,000,000.00

TOTAL Rp15,450,625.36

DI BULATKAN Rp16,000,000.00

Terbilang :
RENCANA ANGGARAN BIAYA (RAB)
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA
VOLUME HARGA TOTAL
NO URAIAN PEKERJAAN SATUAN SATUAN
(Rp) (Rp) (Rp)
(Vol) (HSP) = ( Vol x HSP )
I PEKERJAAN PERSIAPAN Rp1,000,000
1 Pembersihan dan Perataan Lahan - m2 4,550 Rp0
2 Pengukuran & Pemasangan Bouwplank - m' 55,030 Rp0
3 Pembuatan Steger/Perancah dari Bambu - m2 328,452 Rp0
4 Penyediaan Air & Listrik Kerja 1.00 ls 1,000,000 Rp1,000,000

II PEKERJAAN TANAH & PONDASI Rp0


1 Galian Tanah Pondasi - m3 46,750 Rp0
2 Pemasangan pondasi batu belah campuran 1SP : 4PP - m3 687,173 Rp0
3 Pasir Urug Bawah Pondasi - m3 121,100 Rp0
4 Pemasangan Batu kosong (anstamping) - m3 372,540 Rp0
5 Urugan Kembali Bekas Galian - m3 45,500 Rp0
6 Pemadatan Tanah per 20cm - m3 45,500 Rp0

III PEKERJAAN BETON Rp2,935,309


1 Pekerjaan Sloof - m3 3,434,560 Rp0
2 Pekerjaan Kolom - m3 5,546,060 Rp0
3 Pekerjaan Ring Balk - m3 5,663,210 Rp0
4 Pengecoran Plat Dak - m3 800,754 Rp0
5 Bekisting Plat Dak - m2 408,610 Rp0
6 Pembesian Plat Dak 241.57 kg 12,151 Rp2,935,309

IV PEKERJAAN ATAP Rp0


1 Pemasangan Kontruksi Kuda-kuda Kayu - m3 6,626,300 Rp0
2 Pemasangan Balok Gording, Nok, Kait Angin - m3 8,763,400 Rp0
3 Pemasangan Rangka Atap - m2 142,830 Rp0
4 Pemasangan Atap - m2 63,260 Rp0
5 Pemasangan Bubungan - m' 99,727 Rp0
6 Pemasangan List Plank - m' 124,950 Rp0
7 Pemasangan Talang Air - m' 101,520 Rp0

V PEKERJAAN PASANGAN DINDING Rp0


1 Pemasangan Dinding Bata Merah - m2 108,551 Rp0
2 Pemasangan Plester Dinding - m2 32,144 Rp0
3 Pemasangan Acian Dinding - m2 27,135 Rp0

VI PEKERJAAN PINTU & JENDELA Rp245,000


1 Pembuatan dan pemasangan Kusen Pintu & Jendela (Kayu Jati) - m3 16,183,500 Rp0
2 Pembuatan & Pemasangan Daun Pintu (Kayu Jati) - m2 1,727,500 Rp0
3 Pembuatan & Pemasangan Daun Jendela Kaca (Kayu Jati) - m2 700,200 Rp0
4 Pemasangan Pintu PVC 1.00 bh 245,000 Rp245,000

VII PEKERJAAN PLAFOND Rp0


1 Pemasangan Rangka Plafond - m2 81,610 Rp0
2 Pemasangan Plafond Gypsum - m2 43,318 Rp0
3 Pemasangan List Plafond Gypsum - m' 33,006 Rp0
RENCANA ANGGARAN BIAYA (RAB)
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA
VOLUME HARGA TOTAL
NO URAIAN PEKERJAAN SATUAN SATUAN
(Rp) (Rp) (Rp)
VIII PEKERJAAN PENUTUP LANTAI Rp0
1 Pemasangan Keramik 50x50 - m2 186,595 Rp0
2 Pemasangan Keramik 25x25 - Kamar Mandi - m2 156,092 Rp0
3 Pemasangan Keramik 25x25 - Teras - m2 156,092 Rp0
4 Pemasangan Plint Keramik - m' 49,920 Rp0

IX PEKERJAAN INSTALASI LISTRIK & AIR Rp10,270,316


1 Titik Lampu 14.00 bh 151,056 Rp2,114,778
2 Lampu Downlight 11.00 bh 35,000 Rp385,000
3 Lampu Fitting 3.00 bh 30,000 Rp90,000
4 Stop Kontak 1 Lubang 5.00 bh 18,000 Rp90,000
5 Stop Kontak 2 Lubang 1.00 bh 25,000 Rp25,000
6 Stop Kontak 3 Lubang 1.00 bh 35,000 Rp35,000
7 Saklar Single 5.00 bh 15,000 Rp75,000
8 Saklar Double 3.00 bh 20,000 Rp60,000
9 Pemasangan MCB 1.00 bh 236,900 Rp236,900
10 Pipa Air Bersih 3/4" 36.84 m' 19,480 Rp717,643
11 Pipa Air Kotor 4" 20.49 m' 92,780 Rp1,900,784
12 Pipa Air Bekas 3" 20.32 m' 74,555 Rp1,514,734
13 Wastafel 1.00 bh 381,013 Rp381,013
14 Kran Dinding 3.00 bh 65,850 Rp197,550
15 Kran Sink 1.00 bh 129,850 Rp129,850
16 Floor Drain 1.00 bh 510,800 Rp510,800
17 Bak Mandi 1.00 bh 797,900 Rp797,900
18 Closet Jongkok 1.00 bh 409,500 Rp409,500
19 Bak Control 1.00 pcs 598,863 Rp598,863

X PEKERJAAN FINISHING Rp0


1 Pengecetan Dinding Dalam - m2 19,173 Rp0
2 Pengecetan Dinding Luar - m2 19,173 Rp0
3 Pengecetan Kusen Pintu & Jendela - m2 36,160 Rp0
4 Pengecetan Daun Pintu & Jendela - m2 36,160 Rp0
5 Pengecetan Plafond - m2 36,160 Rp0

XI PEKERJAAN KUNCI & KACA Rp0


1 Pemasangan Kaca 5mm - m2 124,188 Rp0
2 Pemasangan Kaca 7mm - m2 183,448 Rp0
3 Pasangan Kunci - bh 126,850 Rp0
4 Pemasangan Engsel Pintu - bh 22,938 Rp0
5 Pemasangan Grendel Jendela - bh 31,410 Rp0
6 Pemasangan Kait Angin Jendela - bh 22,850 Rp0
7 Pemasangan Engsel Jendela - bh 26,955 Rp0

XII PEKERJAAN LANDSCAPE Rp1,000,000


1 Pembuatan & Perapihan Taman 1.00 ls 1,000,000 Rp1,000,000
HARGA SATUAN PEKERJAAN (HSP)
Ref : AHS SNI 2022 & AHS SNI 2016
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)

I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan m2 Rp4,550
2 Pengukuran & Pemasangan Bouwplank m' Rp55,030
3 Pembuatan Steger/Perancah dari Bambu m2 Rp328,452
4 Penyediaan Air & Listrik Kerja ls Rp1,000,000

II PEKERJAAN TANAH & PONDASI


1 Galian Tanah Pondasi m3 Rp46,750
2 Pemasangan pondasi batu belah campuran 1SP : 4PP m3 Rp687,173
3 Pasir Urug Bawah Pondasi m3 Rp121,100
4 Pemasangan Batu kosong (anstamping) m3 Rp372,540
5 Urugan Kembali Bekas Galian m3 Rp45,500
6 Pemadatan Tanah per 20cm m3 Rp45,500

III PEKERJAAN BETON


1 Pekerjaan Sloof m3 Rp3,434,560
2 Pekerjaan Kolom m3 Rp5,546,060
3 Pekerjaan Ring Balk m3 Rp5,663,210
4 Pengecoran Plat Dak m3 Rp800,754
5 Bekisting Plat Dak m2 Rp408,610
6 Pembesian Plat Dak kg Rp12,151

IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu m3 Rp6,626,300
2 Pemasangan Balok Gording, Nok, Kait Angin m3 Rp8,763,400
3 Pemasangan Rangka Atap m2 Rp142,830
4 Pemasangan Atap m2 Rp63,260
5 Pemasangan Bubungan m' Rp99,727
6 Pemasangan List Plank m' Rp124,950
7 Pemasangan Talang Air m' Rp101,520

V PEKERJAAN PASANGAN DINDING


1 Pemasangan Dinding Bata Merah m2 Rp108,551
2 Pemasangan Plester Dinding m2 Rp32,144
3 Pemasangan Acian Dinding m2 Rp27,135

VI PEKERJAAN PINTU & JENDELA


1 Pembuatan dan pemasangan Kusen Pintu & Jendela (Kayu Jati) m3 Rp16,183,500
2 Pembuatan & Pemasangan Daun Pintu (Kayu Jati) m2 Rp1,727,500
3 Pembuatan & Pemasangan Daun Jendela Kaca (Kayu Jati) m2 Rp700,200
4 Pemasangan Pintu PVC bh Rp245,000
HARGA SATUAN PEKERJAAN (HSP)
Ref : AHS SNI 2022 & AHS SNI 2016
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)

VII PEKERJAAN PLAFOND


1 Pemasangan Rangka Plafond m2 Rp81,610
2 Pemasangan Plafond Gypsum m2 Rp43,318
3 Pemasangan List Plafond Gypsum m' Rp33,006

VIII PEKERJAAN PENUTUP LANTAI


1 Pemasangan Keramik 50x50 m2 Rp186,595
2 Pemasangan Keramik 25x25 - Kamar Mandi m2 Rp156,092
3 Pemasangan Keramik 25x25 - Teras m2 Rp156,092
4 Pemasangan Plint Keramik m' Rp49,920

IX PEKERJAAN INSTALASI LISTRIK & AIR


1 Titik Lampu bh Rp151,056
2 Lampu Downlight bh Rp35,000
3 Lampu Fitting bh Rp30,000
4 Stop Kontak 1 Lubang bh Rp18,000
5 Stop Kontak 2 Lubang bh Rp25,000
6 Stop Kontak 3 Lubang bh Rp35,000
7 Saklar Single bh Rp15,000
8 Saklar Double bh Rp20,000
9 Pemasangan MCB bh Rp236,900
10 Pipa Air Bersih 3/4" m' Rp19,480
11 Pipa Air Kotor 4" m' Rp92,780
12 Pipa Air Bekas 3" m' Rp74,555
13 Wastafel bh Rp381,013
14 Bak Cuci Piring bh Rp207,400
15 Kran Dinding bh Rp65,850
16 Kran Sink bh Rp129,850
17 Floor Drain bh Rp510,800
18 Bak Mandi bh Rp797,900
19 Closet Jongkok bh Rp409,500
20 Bak Control pcs Rp598,863

X PEKERJAAN FINISHING
1 Pengecetan Dinding Dalam m2 Rp19,173
2 Pengecetan Dinding Luar m2 Rp19,173
3 Pengecetan Kusen Pintu & Jendela m2 Rp36,160
4 Pengecetan Daun Pintu & Jendela m2 Rp36,160
5 Pengecetan Plafond m2 Rp36,160

XI PEKERJAAN KUNCI & KACA


HARGA SATUAN PEKERJAAN (HSP)
Ref : AHS SNI 2022 & AHS SNI 2016
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN
(Rp)
1 Pemasangan Kaca 5mm m2 Rp124,188
2 Pemasangan Kaca 7mm m2 Rp183,448
3 Pasangan Kunci bh Rp126,850
4 Pemasangan Engsel Pintu bh Rp22,938
5 Pemasangan Grendel Jendela bh Rp31,410
6 Pemasangan Kait Angin Jendela bh Rp22,850
7 Pemasangan Engsel Jendela bh Rp26,955

XII PEKERJAAN LANDSCAPE


1 Pembuatan & Perapihan Taman ls Rp1,000,000
ANALISA HARGA SATUAN PEKERJAAN
SUMBER : PERMENPU NO 1 TAHUN 2022 & PERMENPU 2016
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

A.1.1.1. HARGA SATUAN PEKERJAAN PERSIAPAN

1.1.f (c) 1 m2 Pembersihan dan Pengupasan Permukaan Tanah (Striping) s.d. Tanaman 2cm
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.2.2.1.4. Pengukuran dan Pemasangan 1 m’ Bouwplank


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN
Kayu 5/7 (Rawa) m3
Paku 2"-3" kg
Kayu Papan 3/20 (Rawa) m3

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.1.1.1.11. Pembuatan1 m2 Steger/Perancah dari Bambu s.d. Tinggi 6 meter


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN
Bambu diameter 6-8/600 cm Batang
Tali ijuk m3

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Catatan: Pembuatan steger/perancah secara sewa dapat menggunakan analisis bidang SDA.

A.1.5.1. HARGA SATUAN PEKERJAAN TANAH


Catatan: Tanah hasil galian disimpan dekat lubang galian.

1.7.1.a (c) Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m Untuk Volume s.d. 200 m3 Dalam S
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Batu belah m3
Semen portland Kg
Pasir Pasang m3

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN
Pasir Urug m3

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.3.2.1.9. Pemasangan 1 m3 Batu Kosong (Aanstamping) untuk Pondasi Gedung


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Batu Belah m3
Pasir Urug m3
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

1.7.2.a (c) Pengurugan Kembali 1 m3 Galian Tanah


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

1.7.2.c (c) Pemadatan Tanah 1 m3 per 20 cm dengan alat Timbris


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

1.7.2.e (c) Pengurugan dan Pemadatan 1 m3 Sirtu


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Mandor L.04 OH
JUMLAH HARGA TENA

B BAHAN
Pasir Urug m3
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


Catatan:
Bobot isi pasir : 1400 kg/m3, bulking factor pasir : 20%
Bobot isi Kerikil : 1350 kg/m3

A.4.1.1.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Rawa m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.1.1.30 Membuat 1 m3 kolom beton bertulang (200 kg besi + bekisting)


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang kayu L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
Kayu Rawa 4/6 M3
Plywood 9 mm uk. 120 x 240 mm Lbr
Kayu Dolken Ø 8-10/400 cm Batang

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.1.1.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Tukang kayu L.02 OH
Tukang besi L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu kelas III ( Pinus ) m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu pecah mesin 2-3 cm m3
Kayu Kalimantan ( Meranti Batu ) 5/7 & 4/6 (ikat) m3
Plywood 9 mm uk. 120 x 240 mm Lbr
Dolken kayu Ø 8-10/400 cm Batang
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.1.1.7. Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)


NO URAIAIAN KODE SATUAN

A TENAGA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland Kg
Pasir beton Kg
Kerikil (Maks 30mm) Kg
Air Liter
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 15%
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.22. Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Kayu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH

JUMLAH HARGA TENAGA KERJA


B BAHAN
Papan kayu kelas III m3
Paku 5 cm - 12 cm Kg
Minyak bekisting Liter
Balok kayu kelas II m3
Plywood tebal 9 mm Lbr
Dolken kayu galam, ( 8-10) cm panjang 4m Batang

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.1.1.17.a Pembesian 1 kg dengan besi polos atau besi ulir


NO URAIAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Besi L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH

JUMLAH HARGA TENAGA KERJA


B BAHAN
Besi beton (polos/ulir) kg
Kawat beton kg

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

HARGA SATUAN PEKERJAAN ATAP & RANGKA ATAP

A.4.6.1.13. Pemasangan 1 m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas I, II dan III B


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.15. Pemasangan 1 m3 Konstruksi Gordeng, Kayu kelas II


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.16.e Pemasangan 1 m2 rangka atap genteng Palentong, kayu kelas II ( Kayu Kamper
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Kaso 5/7 cm m3
Kayu Reng 2 x 3 cm m3
Paku Biasa kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n1 m2
Atap
Genteng
Palentong A.4.5.2.3. Pemasangan1 m2 Atap Genteng Palentong Besar/Morando
Besar/Mor
ando
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Genteng palentong besar (morando) Buah
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.5.2.4. Pemasangan 1 m’ Bubung Genteng Palentong Kecil


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Genteng bubung Buah
Semen Portlan Kg
Pasir pasang M3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.22. Pemasangan 1 m’ Lisplank Ukuran (3 x 30) cm, Kayu Kelas I atau Kelas II
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan kayu m3
Paku 5 dan 7 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Seng plat m
Paku Biasa kg
Kayu Papan Jati m3
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN PASANGAN DINDING

A.4.4.1.11 Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm tebal ½ Batu Campuran
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Bata merah buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.4.2.19. Pemasangan 1 m2 Berapen 1SP : 5PP Tebal 15 mm


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Semen portland Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.4.2.27. Pemasangan 1 m2 acian.


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Semen portland Kg
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
Pemasanga
n 1 m2 F HARGA SATUAN PEKERJAAN (D+E)
Dinding
bata
Berongga
Ekspose
12x11x24
dengan
Mortar
A.4.4.1.24. Pemasangan 1 m Dinding bata Berongga Ekspose 12x11x24 dengan Mortar Tip
2

Tipe S,fc’
12, 5 Mpa
( Setara
Campuran NO URAIAN KODE SATUAN
1SP : 3PP)

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata berongga buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.4.1.23. Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24 dengan Mortar Tipe N,fc’ 5,2 Mp
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata terawang buah
Semen portland Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN KAYU & KACA

A.4.6.1.1. Pembuatan dan Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kel
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Balok - Kusen m3
Paku 10 cm Kg
Lem kayu Kg
JUMLAH HARG
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.5. Pembuatan 1 m2 Daun Pintu Panel, Kayu Kelas I atau II


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kayu Papan Jati m3
Lem kayu Kg
JUMLAH HARG
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.6. Pembuatan 1 m2 Pintu dan Jendela Kaca, Kayu Kelas I atau II


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Papan Jati m3
Lem kayu Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.1.8. Pembuatan 1 m Daun pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup
2

NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Papan m3
Paku 1 cm - 2,5 cm Kg
Lem kayu Kg
Plywood tebal 4 mm Ukuran (90 x 220) Lembar
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN PLAFOND

A.4.6.1.20. Pemasangan 1 m2 Rangka Langit-Langit (60 x 60) cm, Kayu Kelas II atau III
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu Kaso 5 x 7 cm m3
Paku 7- 10 cm Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m2
Langit-
Langit
Papan
Gipsum,
A.4.5.1.7. Pemasangan 1 m2 Langit-Langit Papan Gipsum, Tebal 9 mm
Tebal 9

NO URAIAN KODE SATUAN


mm

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan gipsum 120x240 cm Lembar
Paku sekrup Kg
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m’ List
Langit-
Langit
Kayu
A.4.5.1.9.b Pemasangan 1 m’ list langit-langit gypsum profil 15 cm
profil

NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
List Gipsum Profil 15 cm Pj. 2.00 m' m'
Tepung gypsum kg
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN PENUTUP LANTAI & DINDING


Pemasanga
n 1m2
Lantai
Keramik
Ukuran 30
A.4.4.3.36. Pemasangan 1m2 Lantai Keramik Ukuran 50cm x 50cm
s.d. <40cm

NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Keramik 50 x 50 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1m2
Lantai
Keramik
Ukuran 20
A.4.4.3.35. Pemasangan 1m2 Lantai Keramik Ukuran 20 s.d. <30cm
s.d. <30cm

NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kramik 25 x 25 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1m2
Lantai
Keramik
Ukuran 20
A.4.4.3.35. Pemasangan 1m2 Lantai Keramik Ukuran 20 s.d. <30cm
s.d. <30cm
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kramik 20x20 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARG
C PERALATAN

JUMLAH HARGA PE
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m2
Dinding
Porselen
10cm x
A.4.4.3.48. Pemasangan 1 m2 Dinding Porselen 10cm x 20cm
20cm

NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Porslen Buah
Semen portland Kg
Pasir pasang m3
Semen warna Kg
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
Pemasanga
n 1 m’
Plint
Keramik
Ukuran 20 A.4.4.3.40. Pemasangan 1 m’ Plint Keramik Ukuran 20 s.d. <30 cm
s.d. <30
cm
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plint keramik Buah
Semen portland Kg
Semen warna Kg
Pasir pasang m3
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN INSTALASI LISTRIK & AIR

A.6.2.1.1. Pemasangan 1 Buah Titik Lampu


NO URAIAN KODE SATUAN

A TENAGA KERJA
Upah % bahan
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Las Dop Buah
Klem Buah
Mangkok Buah
Saklar Buah
Fitting Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.6.1.1.1. Pemasangan 1 buah MCCB


NO URAIAN KODE SATUAN

A TENAGA KERJA
Upah %
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Klem biasa Buah
MCCB (Boks MCB) Buah
MCB Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.27. Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3/4”


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 3/4” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.32. Pemasangan 1 m’ Pipa PVC tipe AW Diameter 4”


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 4” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.31. Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3”


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Pipa PVC 3” m
Perlengkapan Ls
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.5. Pemasangan 1 Buah Wastafel


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Wastafel Lengkap Unit
Semen portland Kg
Pasir pasang m3

JUMLAH HARGA BAHAN


C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.33. Pemasangan 1 buah Bak Cuci Piring Stainlessteel


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bak cuci piring Unit
Waterdrain Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.35. Pemasangan 1 buah Kran Diameter ½” atau ¾ ”


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kran air Buah
Sealtape Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.35A Pemasangan 1 buah Kran Sink


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kran Sink Buah
Sealtape Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.36 Pemasangan 1 buah Floor Drain


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Floor drain Unit
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.8. Pemasangan 1buah Bak Mandi Pasangan Bata Volume 0,30 m3


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata merah Buah
Semen portland Kg
Pasir pasang m3
Porselen 11x11 bh
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.2. Pemasangan 1 Buah Closet Jongkok Porselen


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Closet jongkok Unit
Pasangan bata 1PC:3PS m2
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1.1. Pemasangan 1 Buah Closet Duduk/Monoblock


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat dasar Kg
Pengencer L
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang batu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata merah bh
Semen portland Kg
Pasir pasang M3
Pasir beton M3
Batu Splite (2-3cm) M3
Besi Beton Kg

JUMLAH HARGA BAHAN


C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

( Estimasi ) Pemasangan 1 m3 Septictank & Sumur Resapan


NO URAIAN KODE SATUAN

A TENAGA KERJA
Tukang Gali L.01 OH
Tukang Pasang L.02 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Bata Merah
Semen Portland

JUMLAH HARGA BAHAN


C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN FINISHING

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penu
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penu
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat pe
NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang cat L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN KUNCI & KACA

A.4.6.2.17. Pemasangan 1 m2 Kaca Polos Tebal 5 mm


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kaca tebal 5mm m2
Silicone Sealant 300 ml Tube
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.17. Pemasangan 1 m2 Kaca Polos Tebal 7 mm


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kaca tebal 7mm m2
Silicone Sealant 300 ml Tube
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.2. Pemasangan 1 Buah Kunci Tanam Biasa


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Kunci tanam Buah
JUMLAH HARG
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.5. Pemasangan 1 Buah Engsel Pintu


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Engsel pintu Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.11. Pemasangan 1 Buah Kunci Slot (Grendel) untuk Jendela


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kunci slot Buah
JUMLAH HARGA BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.9. Pemasangan 1 Buah Kait Angin


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kait angin Buah
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

A.4.6.2.6. Pemasangan 1 Buah Engsel Jendela Kupu-Kupu


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang kayu L.02 OH
Kepala tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENA
B BAHAN
Engsel Buah
JUMLAH HARG
C PERALATAN

D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)

PEKERJAAN LANDSCAPE

A.4.1.1.2 Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)


NO URAIAN KODE SATUAN

A TENAGA KERJA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH HARGA TENAGA KERJA
B BAHAN
Semen portland kg
Pasir Beton kg
Batu Splite (2-3cm) kg
Air Liter
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Biaya Umum & Keuntungan (maksimum 15%)
F HARGA SATUAN PEKERJAAN (D+E)
TUAN PEKERJAAN
UN 2022 & PERMENPU 2016

PE - 78 M2

(Striping) s.d. Tanaman 2cm


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.050 Rp 80,000 Rp 4,000


0.005 Rp 110,000 Rp 550
JUMLAH HARGA TENAGA KERJA Rp 4,550

Rp -
Rp -
JUMLAH HARGA BAHAN Rp -

JUMLAH HARGA PERALATAN

Rp 4,550
0% Rp -
Rp 4,550

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.100 Rp 80,000 Rp 8,000


0.100 Rp 100,000 Rp 10,000
0.010 Rp 110,000 Rp 1,100
0.005 Rp 110,000 Rp 550
JUMLAH HARGA TENAGA KERJA Rp 19,650
0.012 Rp 1,700,000 Rp 20,400
0.020 Rp 14,000 Rp 280
0.007 Rp 2,100,000 Rp 14,700
JUMLAH HARGA BAHAN Rp 35,380

JUMLAH HARGA PERALATAN

Rp 55,030
0% Rp -
Rp 55,030

nggi 6 meter
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

1.000 Rp 80,000 Rp 80,000


2.000 Rp 100,000 Rp 200,000
0.200 Rp 110,000 Rp 22,000
0.050 Rp 110,000 Rp 5,500
JUMLAH HARGA TENAGA KERJA Rp 307,500

1.250 Rp 12,000 Rp 15,000


0.186 Rp 32,000 Rp 5,952
JUMLAH HARGA BAHAN Rp 20,952

JUMLAH HARGA PERALATAN

Rp 328,452
0% Rp -
Rp 328,452

Volume s.d. 200 m3 Dalam Satu Lokasi


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.550 Rp 80,000 Rp 44,000


0.025 Rp 110,000 Rp 2,750
JUMLAH HARGA TENAGA KERJA Rp 46,750

Rp -
Rp -
Rp -
JUMLAH HARGA BAHAN Rp -

JUMLAH HARGA PERALATAN

Rp 46,750
0% Rp -
Rp 46,750

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.000 Rp 80,000 Rp 80,000


0.750 Rp 100,000 Rp 75,000
0.075 Rp 110,000 Rp 8,250
0.075 Rp 110,000 Rp 8,250
RJA Rp 171,500

1.200 Rp 190,000 Rp 228,000


163.000 Rp 1,180 Rp 192,340
0.520 Rp 183,333 Rp 95,333
Rp -
Rp 515,673

N
Rp 687,173
0% Rp -
Rp 687,173

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.300 Rp 80,000 Rp 24,000


0.010 Rp 110,000 Rp 1,100
JUMLAH HARGA TENAGA KERJA Rp 25,100

1.200 Rp 80,000 Rp 96,000


Rp -
JUMLAH HARGA BAHAN Rp 96,000

JUMLAH HARGA PERALATAN

Rp 121,100
0% Rp -
Rp 121,100

Pondasi Gedung
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.780 Rp 80,000 Rp 62,400


0.390 Rp 100,000 Rp 39,000
0.039 Rp 110,000 Rp 4,290
0.039 Rp 110,000 Rp 4,290
RJA Rp 109,980

1.200 Rp 190,000 Rp 228,000


0.432 Rp 80,000 Rp 34,560
Rp 262,560

N
Rp 372,540
0% Rp -
Rp 372,540

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.500 Rp 80,000 Rp 40,000


0.050 Rp 110,000 Rp 5,500
JUMLAH HARGA TENAGA KERJA Rp 45,500
Rp -
Rp -
JUMLAH HARGA BAHAN Rp -

JUMLAH HARGA PERALATAN

Rp 45,500
0% Rp -
Rp 45,500

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.500 Rp 80,000 Rp 40,000


0.050 Rp 110,000 Rp 5,500
JUMLAH HARGA TENAGA KERJA Rp 45,500

JUMLAH HARGA BAHAN Rp -

JUMLAH HARGA PERALATAN

Rp 45,500
Rp -
Rp 45,500

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.250 Rp 80,000 Rp 20,000


0.025 Rp 110,000 Rp 2,750
JUMLAH HARGA TENAGA KERJA Rp 22,750

1.200 Rp 80,000 Rp 96,000


Rp -
JUMLAH HARGA BAHAN Rp 96,000
JUMLAH HARGA PERALATAN

Rp 118,750
0% Rp -
Rp 118,750

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

5.650 Rp 80,000 Rp 452,000


0.275 Rp 100,000 Rp 27,500
1.560 Rp 100,000 Rp 156,000
1.400 Rp 100,000 Rp 140,000
0.323 Rp 110,000 Rp 35,530
0.283 Rp 110,000 Rp 31,130
JUMLAH HARGA TENAGA KERJA Rp 842,160

0.270 Rp 1,700,000 Rp 459,000


2.000 Rp 14,000 Rp 28,000
0.600 Rp 9,000 Rp 5,400
210.000 Rp 10,000 Rp 2,100,000
3.000 Rp 18,000 Rp 54,000
336.000 Rp 1,100 Rp 369,600
0.540 Rp 200,000 Rp 108,000
0.810 Rp 230,000 Rp 186,300
JUMLAH HARGA BAHAN Rp 2,592,400

JUMLAH HARGA PERALATAN


Rp 3,434,560
0% Rp -
Rp 3,434,560

bekisting)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

7.050 Rp 80,000 Rp 564,000


0.275 Rp 100,000 Rp 27,500
1.650 Rp 100,000 Rp 165,000
2.100 Rp 100,000 Rp 210,000
0.403 Rp 110,000 Rp 44,330
0.353 Rp 110,000 Rp 38,830
RJA Rp 1,049,660

4.000 Rp 14,000 Rp 56,000


2.000 Rp 9,000 Rp 18,000
212.000 Rp 10,000 Rp 2,120,000
4.500 Rp 18,000 Rp 81,000
336.000 Rp 1,100 Rp 369,600
0.540 Rp 200,000 Rp 108,000
0.810 Rp 230,000 Rp 186,300
0.150 Rp 4,200,000 Rp 630,000
3.500 Rp 145,000 Rp 507,500
20.000 Rp 21,000 Rp 420,000
Rp -
Rp 4,496,400

N
Rp 5,546,060
0% Rp -
Rp 5,546,060

bekisting)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

6.350 Rp 80,000 Rp 508,000


0.275 Rp 100,000 Rp 27,500
1.650 Rp 100,000 Rp 165,000
1.400 Rp 100,000 Rp 140,000
0.333 Rp 110,000 Rp 36,630
0.318 Rp 110,000 Rp 34,980
RJA Rp 912,110
0.320 Rp 1,700,000 Rp 544,000
3.200 Rp 14,000 Rp 44,800
1.600 Rp 9,000 Rp 14,400
210.000 Rp 10,000 Rp 2,100,000
3.000 Rp 18,000 Rp 54,000
336.000 Rp 1,100 Rp 369,600
0.540 Rp 200,000 Rp 108,000
0.810 Rp 230,000 Rp 186,300
0.140 Rp 4,200,000 Rp 588,000
2.800 Rp 145,000 Rp 406,000
16.000 Rp 21,000 Rp 336,000
Rp 4,751,100

N
Rp 5,663,210
0% Rp -
Rp 5,663,210

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.650 Rp 80,000 Rp 132,000


0.275 Rp 100,000 Rp 27,500
0.028 Rp 110,000 Rp 3,080
0.083 Rp 110,000 Rp 9,130
UMLAH TENAGA KERJA Rp 171,710

371.000 1,180 Rp 437,780


698.000 143 Rp 99,714
1,047.000 83 Rp 87,250
215.000 20 Rp 4,300
UMLAH HARGA BAHAN Rp 629,044
Rp -
JUMLAH HARGA ALAT Rp -
Rp 800,754
0% Rp -
Rp 800,754

Bangunan Gedung
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.660 Rp 80,000 Rp 52,800


0.330 Rp 100,000 Rp 33,000
0.033 Rp 110,000 Rp 3,630
0.033 Rp 110,000 Rp 3,630

RJA Rp 93,060

0.040 Rp 1,700,000 Rp 68,000


0.400 Rp 15,000 Rp 6,000
0.200 Rp 9,000 Rp 1,800
0.015 Rp 4,200,000 Rp 63,000
0.350 Rp 145,000 Rp 50,750
6.000 Rp 21,000 Rp 126,000
Rp -
Rp 315,550

N
Rp 408,610
0% Rp -
Rp 408,610

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.007 Rp 80,000 Rp 560


0.007 Rp 100,000 Rp 700
0.001 Rp 110,000 Rp 77
0.000 Rp 110,000 Rp 44

RJA Rp 1,381

1.050 Rp 10,000 Rp 10,500


0.015 Rp 18,000 Rp 270
Rp -
Rp 10,770
N
Rp 12,151
0% Rp -
Rp 12,151

nal, Kayu Kelas I, II dan III Bentang Sampai Dengan 6 Meter


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

4.000 Rp 80,000 Rp 320,000


12.000 Rp 100,000 Rp 1,200,000
1.200 Rp 110,000 Rp 132,000
0.200 Rp 110,000 Rp 22,000
RJA Rp 1,674,000

1.100 Rp 4,200,000 Rp 4,620,000


15.000 Rp 14,500 Rp 217,500
5.600 Rp 20,500 Rp 114,800
Rp 4,952,300

Rp -
Rp -
Rp 6,626,300
0% Rp -
Rp 6,626,300

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

2.400 Rp 80,000 Rp 192,000


7.200 Rp 100,000 Rp 720,000
0.720 Rp 110,000 Rp 79,200
0.120 Rp 110,000 Rp 13,200
RJA Rp 1,004,400

1.100 Rp 6,800,000 Rp 7,480,000


15.000 Rp 14,500 Rp 217,500
3.000 Rp 20,500 Rp 61,500
Rp 7,759,000

Rp -
Rp -
Rp 8,763,400
0% Rp -
Rp 8,763,400

ayu kelas II ( Kayu Kamper )


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.100 Rp 80,000 Rp 8,000


0.100 Rp 100,000 Rp 10,000
0.010 Rp 110,000 Rp 1,100
0.005 Rp 110,000 Rp 550
RJA Rp 19,650

0.014 Rp 6,800,000 Rp 95,200


0.004 Rp 6,800,000 Rp 24,480
0.250 Rp 14,000 Rp 3,500
Rp 123,180

Rp -
Rp -
Rp 142,830
0% Rp -
Rp 142,830

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.150 Rp 80,000 Rp 12,000


0.075 Rp 100,000 Rp 7,500
0.008 Rp 110,000 Rp 880
0.008 Rp 110,000 Rp 880
RJA Rp 21,260

12.000 Rp 3,500 Rp 42,000


Rp 42,000
Rp -
N Rp -
Rp 63,260
0% Rp -
Rp 63,260

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.400 Rp 80,000 Rp 32,000


0.200 Rp 100,000 Rp 20,000
0.020 Rp 110,000 Rp 2,200
0.002 Rp 110,000 Rp 220
JUMLAH HARGA TENAGA KERJA Rp 54,420

4.000 Rp 7,500 Rp 30,000


8.000 Rp 1,180 Rp 9,440
0.032 Rp 183,333 Rp 5,867
JUMLAH HARGA BAHAN Rp 45,307

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 99,727
0% Rp -
Rp 99,727

u Kelas I atau Kelas II


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.100 Rp 80,000 Rp 8,000


0.200 Rp 100,000 Rp 20,000
0.020 Rp 110,000 Rp 2,200
0.005 Rp 110,000 Rp 550
RJA Rp 30,750

0.011 Rp 8,500,000 Rp 93,500


0.050 Rp 14,000 Rp 700
Rp 94,200
Rp -
Rp -
Rp 124,950
0% Rp -
Rp 124,950

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.200 Rp 80,000 Rp 16,000


0.200 Rp 100,000 Rp 20,000
0.020 Rp 110,000 Rp 2,200
0.001 Rp 110,000 Rp 110
RJA Rp 38,310

1.050 Rp 22,000 Rp 23,100


0.015 Rp 14,000 Rp 210
0.019 Rp 2,100,000 Rp 39,900
Rp 63,210

Rp -
Rp -
Rp 101,520
0% Rp -
Rp 101,520

m tebal ½ Batu Campuran 1SP : 6PP


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.200 Rp 80,000 Rp 16,000


0.080 Rp 100,000 Rp 8,000
0.010 Rp 110,000 Rp 1,100
0.015 Rp 110,000 Rp 1,650
JUMLAH HARGA TENAGA KERJA Rp 26,750

70 Rp 900 Rp 63,000
8.320 Rp 1,180 Rp 9,818
0.049 Rp 183,333 Rp 8,983
JUMLAH HARGA BAHAN Rp 81,801

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 108,551
0% Rp -
Rp 108,551

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.150 Rp 80,000 Rp 12,000


0.075 Rp 100,000 Rp 7,500
0.008 Rp 110,000 Rp 880
0.008 Rp 110,000 Rp 880
JUMLAH HARGA TENAGA KERJA Rp 21,260

5.184 Rp 1,180 Rp 6,117


0.026 Rp 183,333 Rp 4,767
JUMLAH HARGA BAHAN Rp 10,884

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 32,144
0% Rp -
Rp 32,144

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.150 Rp 80,000 Rp 12,000 24.576


0.091 Rp 100,000 Rp 9,100 24.576
0.010 Rp 110,000 Rp 1,100
0.010 Rp 110,000 Rp 1,100
RJA Rp 23,300 Rp5,871,600

3.250 Rp 1,180 Rp 3,835


Rp -
Rp 3,835

Rp -
N Rp -
Rp 27,135
0% Rp -
Rp 27,135

12x11x24 dengan Mortar Tipe S,fc’ 12, 5 Mpa ( Setara Campuran 1SP : 3PP)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.300 Rp 80,000 Rp 24,000


0.150 Rp 100,000 Rp 15,000
0.015 Rp -
0.015 Rp -
RJA Rp 39,000 Rp9,828,000

70.000 Rp 1,857 Rp 130,000


14.000 Rp 1,180 Rp 16,520
0.032 Rp 183,333 Rp 5,867
Rp 152,387

Rp -
N Rp -
Rp 191,387
0% Rp -
Rp 191,387

ngan Mortar Tipe N,fc’ 5,2 Mpa ( Setara Campuran 1SP : 4PP)
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.300 Rp 80,000 Rp 24,000


0.100 Rp 100,000 Rp 10,000
0.010 Rp 110,000 Rp 1,100
0.015 Rp -
RJA Rp 35,100

30.000 Rp 1,857 Rp 55,714


11.000 Rp 1,180 Rp 12,980
0.035 Rp 183,333 Rp 6,417
Rp 75,111

Rp -
N Rp -
Rp 110,211
0% Rp -
Rp 110,211

an Kusen Jendela, Kayu Kelas I


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

7.000 Rp 80,000 Rp 560,000


21.000 Rp 100,000 Rp 2,100,000
2.100 Rp 110,000 Rp 231,000
0.350 Rp 110,000 Rp 38,500
JUMLAH HARGA TENAGA KERJA Rp 2,929,500

1.100 Rp 12,000,000 Rp 13,200,000


1.250 Rp 14,000 Rp 17,500
1.000 Rp 36,500 Rp 36,500
JUMLAH HARGA BAHAN Rp 13,254,000

Rp -
Rp -
Rp 16,183,500
0% Rp -
Rp 16,183,500

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.000 Rp 80,000 Rp 80,000


3.000 Rp 100,000 Rp 300,000
6.300 Rp 110,000 Rp 693,000
0.050 Rp 110,000 Rp 5,500
JUMLAH HARGA TENAGA KERJA Rp 1,078,500

0.040 Rp 16,000,000 Rp 640,000


0.500 Rp 18,000 Rp 9,000
JUMLAH HARGA BAHAN Rp 649,000

Rp -
Rp -
Rp 1,727,500
0% Rp -
Rp 1,727,500

I atau II
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.500 Rp 80,000 Rp 40,000


2.400 Rp 100,000 Rp 240,000
0.240 Rp 110,000 Rp 26,400
0.040 Rp 110,000 Rp 4,400
RJA Rp 310,800

0.024 Rp 16,000,000 Rp 384,000


0.300 Rp 18,000 Rp 5,400
Rp 389,400

Rp -
Rp -
Rp 700,200
0% Rp -
Rp 700,200

ngka Kayu Kelas II Tertutup (Lebar Sampai 90 cm)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.700 Rp 80,000 Rp 56,000


2.100 Rp 100,000 Rp 210,000
0.210 Rp 110,000 Rp 23,100
0.035 Rp -
RJA Rp 289,100
0.025 Rp 8,500,000 Rp 212,500
0.030 Rp 14,000 Rp 420
0.500 Rp 18,000 Rp 9,000
1.000 Rp 55,000 Rp 55,000
Rp 276,920

Rp -
Rp -
Rp 566,020
0% Rp -
Rp 566,020

m, Kayu Kelas II atau III


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.200 Rp 80,000 Rp 16,000


0.300 Rp 100,000 Rp 30,000
0.030 Rp 110,000 Rp 3,300
0.010 Rp 110,000 Rp 1,100
RJA Rp 50,400

0.016 Rp 1,700,000 Rp 27,710


0.250 Rp 14,000 Rp 3,500
Rp 31,210

Rp -
Rp -
Rp 81,610
0% Rp -
Rp 81,610

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.100 Rp 80,000 Rp 8,000


0.100 Rp 100,000 Rp 10,000
0.005 Rp 110,000 Rp 550
0.005 Rp 110,000 Rp 550
RJA Rp 19,100

0.364 Rp 62,000 Rp 22,568


0.110 Rp 15,000 Rp 1,650
Rp 24,218

Rp -
N Rp -
Rp 43,318
0% Rp -
Rp 43,318

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.050 Rp 80,000 Rp 4,000


0.050 Rp 100,000 Rp 5,000
0.005 Rp 110,000 Rp 550
0.003 Rp 110,000 Rp 330
RJA Rp 9,880

1.050 Rp 22,000 Rp 23,100


0.010 Rp 2,600 Rp 26
Rp 23,126

Rp -
N Rp -
Rp 33,006
0% Rp -
Rp 33,006

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.700 Rp 80,000 Rp 56,000


0.350 Rp 100,000 Rp 35,000
0.035 Rp 110,000 Rp 3,850
0.035 Rp 110,000 Rp 3,850
JUMLAH HARGA TENAGA KERJA Rp 98,700

1.050 Rp 72,000 Rp 75,600


10.000 Rp 1,180 Rp 11,800
0.045 Rp 11,000 Rp 495
0.500 Rp 183,333 Rp 91,667
JUMLAH HARGA BAHAN Rp 87,895

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 186,595
0% Rp -
Rp 186,595

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.700 Rp 80,000 Rp 56,000


0.350 Rp 100,000 Rp 35,000
0.035 Rp 110,000 Rp 3,850
0.035 Rp 110,000 Rp 3,850
JUMLAH HARGA TENAGA KERJA Rp 98,700

1.050 Rp 42,500 Rp 44,625


10.400 Rp 1,180 Rp 12,272
0.045 Rp 11,000 Rp 495
0.500 Rp 183,333 Rp 91,667
JUMLAH HARGA BAHAN Rp 57,392

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 156,092
0% Rp -
Rp 156,092
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.700 Rp 80,000 Rp 56,000


0.350 Rp 100,000 Rp 35,000
0.035 Rp 110,000 Rp 3,850
0.035 Rp 110,000 Rp 3,850
JUMLAH HARGA TENAGA KERJA Rp 98,700

1.050 Rp 42,500 Rp 44,625


10.400 Rp 1,180 Rp 12,272
0.045 Rp 11,000 Rp 495
0.500 Rp 183,333 Rp 91,667
JUMLAH HARGA BAHAN Rp 57,392

Rp -
JUMLAH HARGA PERALATAN Rp -
Rp 156,092
0% Rp -
Rp 156,092

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.900 Rp 80,000 Rp 72,000


0.450 Rp 100,000 Rp 45,000
0.045 Rp 110,000 Rp 4,950
0.045 Rp -
RJA Rp 121,950

53.000 Rp 1,040 Rp 55,120


9.300 Rp 1,180 Rp 10,974
0.018 Rp 300,000 Rp 5,400
2.750 Rp 11,000 Rp 30,250
Rp 101,744

Rp -
N Rp -
Rp 223,694
0% Rp -
Rp 223,694

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.090 Rp 80,000 Rp 7,200


0.090 Rp 100,000 Rp 9,000
0.035 Rp 110,000 Rp 3,850
0.035 Rp 110,000 Rp 3,850
RJA Rp 23,900

5.300 Rp 4,500 Rp 23,850


1.140 Rp 1,180 Rp 1,345
0.025 Rp 11,000 Rp 275
0.003 Rp 183,333 Rp 550
Rp 26,020

Rp -
N Rp -
Rp 49,920
0% Rp -
Rp 49,920

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.100 Rp 14,956 Rp 1,496


RJA Rp 1,496

3.000 Rp 5,000 Rp 15,000


10.000 Rp 3,100 Rp 31,000
2.000 Rp 15,000 Rp 30,000
2.000 Rp 20,000 Rp 40,000
3.000 Rp 220 Rp 660
24.000 Rp 100 Rp 2,400
1.000 Rp 3,000 Rp 3,000
1.000 Rp 20,000 Rp 20,000
1.000 Rp 7,500 Rp 7,500
Rp 149,560

Rp -
Rp -
Rp 151,056
0% Rp -
Rp 151,056

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

20.000 Rp 1,000 Rp 20,000


RJA Rp 20,000

3.000 Rp 5,000 Rp 15,000


15.000 Rp 3,100 Rp 46,500
1.000 Rp 15,000 Rp 15,000
2.000 Rp 500 Rp 1,000
24.000 Rp 100 Rp 2,400
1.000 Rp 11,000 Rp 11,000
2.000 Rp 63,000 Rp 126,000
Rp 216,900

Rp -
Rp -
Rp 236,900
0% Rp -
Rp 236,900

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.036 Rp 80,000 Rp 2,880


0.060 Rp 100,000 Rp 6,000
0.006 Rp 110,000 Rp 660
0.002 Rp 110,000 Rp 220
RJA Rp 9,760
1.200 Rp 6,000 Rp 7,200
35%xpipa Rp 2,520 Rp 2,520
Rp 9,720

Rp -
Rp -
Rp 19,480
0% Rp -
Rp 19,480

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.081 Rp 80,000 Rp 6,480


0.135 Rp 100,000 Rp 13,500
0.014 Rp 110,000 Rp 1,485
0.004 Rp 110,000 Rp 440
RJA Rp 21,905

1.200 Rp 43,750 Rp 52,500


35%xpipa Rp 18,375 Rp 18,375
Rp 70,875

Rp -
Rp -
Rp 92,780
0% Rp -
Rp 92,780

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.081 Rp 80,000 Rp 6,480


0.135 Rp 100,000 Rp 13,500
0.014 Rp 110,000 Rp 1,485
0.004 Rp 110,000 Rp 440
RJA Rp 21,905

1.200 Rp 32,500 Rp 39,000


35%xpipa Rp 13,650 Rp 13,650
Rp 52,650

Rp -
Rp -
Rp 74,555
0% Rp -
Rp 74,555

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.200 Rp 80,000 Rp 96,000


1.450 Rp 100,000 Rp 145,000
0.150 Rp 110,000 Rp 16,500
0.060 Rp 110,000 Rp 6,600
RJA Rp 264,100

1.200 Rp 90,000 Rp 108,000


6.000 Rp 1,180 Rp 7,080
0.010 Rp 183,333 Rp 1,833

Rp 116,913

Rp -
Rp -
Rp 381,013
0% Rp -
Rp 381,013

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.030 Rp 80,000 Rp 2,400


0.300 Rp 100,000 Rp 30,000
0.030 Rp -
0.015 Rp -
RJA Rp 32,400
1.000 Rp 145,000 Rp 145,000
1.000 Rp 30,000 Rp 30,000
Rp 175,000

Rp -
Rp -
Rp 207,400
0% Rp -
Rp 207,400

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.010 Rp 80,000 Rp 800


0.400 Rp 100,000 Rp 40,000
0.040 Rp 110,000 Rp 4,400
0.005 Rp 110,000 Rp 550
RJA Rp 45,750

1.000 Rp 20,000 Rp 20,000


0.025 Rp 4,000 Rp 100
Rp 20,100

Rp -
Rp -
Rp 65,850
0% Rp -
Rp 65,850

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.010 Rp 80,000 Rp 800


0.400 Rp 100,000 Rp 40,000
0.040 Rp 110,000 Rp 4,400
0.005 Rp 110,000 Rp 550
RJA Rp 45,750
1.000 Rp 84,000 Rp 84,000
0.025 Rp 4,000 Rp 100
Rp 84,100

Rp -
Rp -
Rp 129,850
0% Rp -
Rp 129,850

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

6.010 Rp 80,000 Rp 480,800


0.100 Rp -
0.010 Rp -
0.005 Rp -
RJA Rp 480,800

1.000 Rp 30,000 Rp 30,000


Rp 30,000

Rp -
Rp -
Rp 510,800
0% Rp -
Rp 510,800

me 0,30 m3
HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

1.000 Rp 80,000 Rp 80,000


2.000 Rp 100,000 Rp 200,000
0.300 Rp 110,000 Rp 33,000
0.030 Rp 110,000 Rp 3,300
RJA Rp 316,300

150.000 Rp 900 Rp 135,000


120.000 Rp 1,180 Rp 141,600
0.300 Rp 183,333 Rp 55,000
300 Rp 500 Rp 150,000
Rp 481,600

Rp -
Rp -
Rp 797,900
0% Rp -
Rp 797,900

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.000 Rp 80,000 Rp 80,000


1.500 Rp 100,000 Rp 150,000
0.150 Rp 110,000 Rp 16,500
0.160 Rp 110,000 Rp 17,600
RJA Rp 264,100

1.000 Rp 140,000 Rp 140,000


0.036 Rp 150,000 Rp 5,400
Rp 145,400

Rp -
Rp -
Rp 409,500
0% Rp -
Rp 409,500

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.500 Rp 80,000 Rp 40,000


1.100 Rp 100,000 Rp 110,000
0.010 Rp -
0.160 Rp -
RJA Rp 150,000

0.300 Rp 700,000 Rp 210,000


0.010 Rp -
Rp 210,000

Rp -
Rp -
Rp 360,000
0% Rp -
Rp 360,000

m x45cm tinggi 50 cm 0.10125


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

3.200 Rp 80,000 Rp 256,000


1.150 Rp 100,000 Rp 115,000
0.011 Rp 110,000 Rp 1,210
0.016 Rp 110,000 Rp 1,760
RJA Rp 373,970

70.00 Rp 900 Rp 63,000


77.00 Rp 1,180 Rp 90,860
0.13 Rp 183,333 Rp 23,833
0.09 Rp 200,000 Rp 18,000
0.02 Rp 160,000 Rp 3,200
2.60 Rp 10,000 Rp 26,000
Rp -
Rp 224,893

Rp -
Rp -
Rp 598,863
0% Rp -
Rp 598,863

HARGA JUMLAH HARGA


KOEFISIEN ANALISA
SATUAN (Rp) (Rp)
vol
0.500 Rp 200,000 Rp 100,000 8
0.500 Rp 150,000 Rp 75,000 8
Rp -
RJA Rp 175,000

Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -

Rp -
Rp -
Rp 175,000
0% Rp -
Rp 175,000

apis cat dasar, 2 lapis cat penutup)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.020 Rp 80,000 Rp 1,600


0.063 Rp 100,000 Rp 6,300
0.006 Rp 110,000 Rp 693
0.003 Rp 110,000 Rp 330
RJA Rp 8,923

0.100 Rp 12,500 Rp 1,250


0.100 Rp 25,000 Rp 2,500
0.260 Rp 25,000 Rp 6,500
Rp 10,250
Rp -
Rp -
Rp 19,173
0% Rp -
Rp 19,173

apis cat dasar, 2 lapis cat penutup)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.020 Rp 80,000 Rp 1,600


0.063 Rp 100,000 Rp 6,300
0.006 Rp 110,000 Rp 693
0.003 Rp 110,000 Rp 330
RJA Rp 8,923

0.100 Rp 12,500 Rp 1,250


0.100 Rp 25,000 Rp 2,500
0.260 Rp 25,000 Rp 6,500
Rp 10,250

Rp -
Rp -
Rp 19,173
0% Rp -
Rp 19,173

1 lapis cat dasar, 2 lapis cat penutup)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.070 Rp 80,000 Rp 5,600


0.009 Rp 100,000 Rp 900
0.006 Rp 110,000 Rp 660
0.003 Rp 110,000 Rp 330
RJA Rp 7,490

0.200 Rp 15,000 Rp 3,000


0.150 Rp 11,000 Rp 1,650
0.170 Rp 36,500 Rp 6,205
0.260 Rp 60,000 Rp 15,600
0.010 Rp 7,500 Rp 75
0.030 Rp 50,000 Rp 1,500
0.200 Rp 3,200 Rp 640
Rp 28,670
Rp -
Rp -
Rp 36,160
0% Rp -
Rp 36,160

1 lapis cat dasar, 2 lapis cat penutup)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.070 Rp 80,000 Rp 5,600


0.009 Rp 100,000 Rp 900
0.006 Rp 110,000 Rp 660
0.003 Rp 110,000 Rp 330
RJA Rp 7,490

0.200 Rp 15,000 Rp 3,000


0.150 Rp 11,000 Rp 1,650
0.170 Rp 36,500 Rp 6,205
0.260 Rp 60,000 Rp 15,600
0.010 Rp 7,500 Rp 75
0.030 Rp 50,000 Rp 1,500
0.200 Rp 3,200 Rp 640
Rp 28,670

Rp -
Rp -
Rp 36,160
0% Rp -
Rp 36,160

1 lapis cat dasar, 2 lapis cat penutup)


HARGA JUMLAH HARGA
KOEFISIEN
SATUAN (Rp) (Rp)

0.070 Rp 80,000 Rp 5,600


0.009 Rp 100,000 Rp 900
0.006 Rp 110,000 Rp 660
0.003 Rp 110,000 Rp 330
RJA Rp 7,490

0.200 Rp 15,000 Rp 3,000


0.150 Rp 11,000 Rp 1,650
0.170 Rp 36,500 Rp 6,205
0.260 Rp 60,000 Rp 15,600
0.010 Rp 7,500 Rp 75
0.030 Rp 50,000 Rp 1,500
0.200 Rp 3,200 Rp 640
Rp 28,670

Rp -
Rp -
Rp 36,160
0% Rp -
Rp 36,160

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.015 Rp 80,000 Rp 1,200


0.150 Rp 100,000 Rp 15,000
0.015 Rp 110,000 Rp 1,650
0.001 Rp 110,000 Rp 88
RJA Rp 17,938

1.100 Rp 95,000 Rp 104,500


0.050 Rp 35,000 Rp 1,750
Rp 106,250

Rp -
Rp -
Rp 124,188
0% Rp -
Rp 124,188

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.015 Rp 80,000 Rp 1,200


0.150 Rp 100,000 Rp 15,000
0.015 Rp 110,000 Rp 1,650
0.001 Rp 110,000 Rp 88
RJA Rp 17,938
1.100 Rp 150,000 Rp 165,000
0.050 Rp 10,200 Rp 510
Rp 165,510

Rp -
Rp -
Rp 183,448
0% Rp -
Rp 183,448

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.010 Rp 80,000 Rp 800


0.500 Rp 100,000 Rp 50,000
0.050 Rp 110,000 Rp 5,500
0.005 Rp 110,000 Rp 550
JUMLAH HARGA TENAGA KERJA Rp 56,850

1.000 Rp 70,000 Rp 70,000


JUMLAH HARGA BAHAN Rp 70,000

Rp -
Rp -
Rp 126,850
0% Rp -
Rp 126,850

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.015 Rp 80,000 Rp 1,200


0.150 Rp 100,000 Rp 15,000
0.015 Rp 110,000 Rp 1,650
0.001 Rp 110,000 Rp 88
RJA Rp 17,938

1.000 Rp 5,000 Rp 5,000


Rp 5,000
Rp -
Rp -
Rp 22,938
0% Rp -
Rp 22,938

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.020 Rp 80,000 Rp 1,600


0.200 Rp 100,000 Rp 20,000
0.020 Rp 110,000 Rp 2,200
0.001 Rp 110,000 Rp 110
RJA Rp 23,910

1.000 Rp 7,500 Rp 7,500


Rp 7,500

Rp -
Rp -
Rp 31,410
0% Rp -
Rp 31,410

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.015 Rp 80,000 Rp 1,200


0.150 Rp 100,000 Rp 15,000
0.015 Rp 110,000 Rp 1,650
0.008 Rp -
RJA Rp 17,850

1.000 Rp 5,000 Rp 5,000


Rp 5,000

Rp -
Rp -
Rp 22,850
0% Rp -
Rp 22,850

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

0.010 Rp 80,000 Rp 800


0.100 Rp 100,000 Rp 10,000
0.010 Rp 110,000 Rp 1,100
0.001 Rp 110,000 Rp 55
JUMLAH HARGA TENAGA KERJA Rp 11,955

1.000 Rp 15,000 Rp 15,000


JUMLAH HARGA BAHAN Rp 15,000

Rp -
Rp -
Rp 26,955
0% Rp -
Rp 26,955

HARGA JUMLAH HARGA


KOEFISIEN
SATUAN (Rp) (Rp)

1.650 Rp 80,000 Rp 132,000


0.275 Rp 100,000 Rp 27,500
0.028 Rp 110,000 Rp 3,080
0.083 Rp -
RJA Rp 162,580

276.000 Rp 1,180 Rp 325,680


828.000 Rp 1,100 Rp 910,800
1,012.000 Rp 164 Rp 166,257
215.000 Rp 20 Rp 4,300
Rp 1,407,037
Rp -
Rp -
Rp 1,569,617
0% Rp -
Rp 1,569,617
1 1 0.040690104
1 2 0.081380208
ANALISA

hari org per hari


4 1 200,000 800,000 0.50 800000
4 1 150,000 600,000 0.50 600000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA

1 L.01 Pekerja OH 80,000


2 L.02 Tukang OH 100,000
3 L.02 Tukang Batu OH 100,000
4 L.02 Tukang Kayu OH 100,000
5 L.02 Tukang Besi OH 100,000
6 L.02 Tukang Las OH 100,000
7 L.02 Tukang Listrik OH 100,000
8 L.03 Kepala Tukang OH 110,000
9 L.04 Mandor OH 110,000

NO KODE BAHAN SATUAN HARGA MIN

1 BAHAN DASAR
A BATU KALI
1 Bulat Utuh m3 170,000
2 Bulat Belah m3 190,000
3 Pecah 10/15 m3 200,000
4 Pecah 5/7 m3 210,000
5 Pecah 3/5 m3 220,000
B KERIKIL
1 Timbun m3 150,000
2 Sawur/Koral m3 150,000
3 Beton 0,5/1 m3 235,000
4 Beton 1/2 m3 240,000
5 Beton 2/3 m3 230,000
6 Biasa m3 160,000
7 Tras Giling m3 220,000
C BATU BATA
ex lokal bh 900
Bata Expose bh 1,857
D PASIR
1 Urug m3 80,000
2 Pasang m3 183,333
3 Beton m3 200,000
E TANAH
1 Padas m3 80,000
2 Liat m3 75,000
F KAPUR
1 Pasang m3 300,000
2 Semen Merah m3 180,000
G PORTLAND CEMENT
1 Merk | 40 kg zak 44,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
2 Merk | 1 kg kg 1,100
3 Merk | 50 kg zak 59,000
4 Merk | 1 kg kg 1,180
5 Merk II 40 kg zak 46,000
6 Merk II 1 kg kg 1,150
7 Merk Il 50 kg zak 55,000
5 Semen Putih 40 kg zak 80,000
6 Semen Putih 50 kg zak 88,000
7 Semen warna kg 11,000
I1 BAHAN PENUTUP ATAP
A SIRAP(100 lbr) pak 180,000
B GENTENG BETON
1 Genteng Beton Warna standard bh 3,800
2 Genteng Beton Warna Special bh 5,100
3 Genteng Beton Warna Khusus bh 5,500
4 Kerpus Beton Warna Standard bh 6,700
5 Kerpus Beton Warna Special bh 6,600
6 Kerpus Beton Warna Khusus bh 10,500
C GENTENG TANAH LIAT
1 Vlaam/Plentong bh 1,900
2 Kodok bh 2,500
3 Kodok Glasur bh 3,500
4 Nok kerpus Kodok bh 5,200
5 Nok kerpus Kodok Glasur bh 7,500
6 Plentong super besar 18 bh/m2 bh 2,850
7 Nok kerpus plentong super bh 5,500
D GENTENG KACA
1 Vlaam tebal 2 mm bh 9,800
2 Vlaam tebal 3 mm bh 10,200
3 Kodok tebal 2 m bh 10,000
4 Kodok tebal 3 mm bh
E Asbes 6 1/2(Asbes Gelombang Besar) bh
1 200 cmX 102 cmX5mm bh 62,000
2 225 cmX 102 cmX5mm bh 74,000
3 250 cmX 102 cmX5mm bh 72,000
4 200 cmX 102 cmX6mm bh 68,000
5 225 cmX 102 cmX6mm bh 76,000
6 250 cm X 102 cmX6mm bh 86,000
F Asbes 14(Asbes Gelombang Kecil)
1 150 cm X 105 cm X4mm bh 42,000
2 180 cmX 105 cm X4mm bh 51,000
3 210 cm X 105 cm X4mm bh 58,000
4 240cm X 105 cm X 4mm bh 62,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
5 270 cm X 105 cm X 4 mm bh 66,000
6 300 cmX 105 cmX4 mm bh 75,000
ONDULINE:95 cmx 200cmx0.3mm lbr 160,000
ONDUVILLA:40cmx 106 cmx 0,3mm lbr 95,000
7 NOK Jabes nok
Kerpus Genteng bh 31,000
Stel Besar bh 45,000
Paten Besar bh 39,000
8 Nokstel gelombang harflex
Stel Besar bh 45,000
Patent Besar bh 21,000
Plat besar bh 49,000
9 NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cmx 50 cmx0,3mm lbr 115,000
G ASBES PLAT
100cmX100 cmX 3mm bh 15,500
100cmX 100 cmX4mm bh 17,000
50 cm X 200 cm X 2,8 mm bh 13,000
40 cm X 200 cm X 2,8mm bh 12,000
FIBER PLAT
uk.100cmx 100cmx 4mm lbr 25,000
unt Plafond uk.120cmx240cmx4mm lbr 75,000
unt Plafond uk.122cmx244cmx4mm lbr
GRC BOARD 77,000
uk.122cmx244cmx 5mm lbr 100,000
uk.122cmx244cmx 6mm lbr 130,000
uk.122cmx244cmx8mm lbr 199,500
uk.122cmx 244cmx 10mm lbr 255,000
H FIBRE GLASS(JABES)
180X92cm bh 56,000
200X 92cm bh 80,000
250X92 cm bh 84,000
180x105cm bh 66,000
210x105 cm bh 86,000
250x105 cm bh 84,000
1 SENG PLAT
BJLS 0,18 lebar 55 cm m' 22,000
BJLS 0,20x 90 lebar 55 cm m' 23,000
BJLS 0,28 lebar 55 cm m' 33,000
BJLS 0,30x 90 lebar 55 cm m' 31,000
J SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 40,000
BJLS 0,20 panjang 180 cm lbr 48,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
BJLS 0,30 panjang 180 cm lbr 62,000
BJLS 0,40 panjang 180 cm lbr 70,000

lll. BAHAN KAYU


1 JATI
Papan m3 16,000,000
Balok/pesagen m3 12,000,000
2 KAMPER
Papan 2X20X400 m3 8,500,000
Balok/pesagen m3 6,800,000
3 KRUING
Papan 2X20X400 m3 6,800,000
Balok/pesagen 4X6X400 m3 6,500,000
4 MERANTI
Papan 2X20X400 m3 5,900,000
Balok/pesagen 6X12X400 m3 4,200,000
5 LANAN
Papan 2X20X200 m3 2,100,000
Balok/pesagen 5X7X400 m3 1,700,000
6 BENGKIRAI
Papan 2X20X400 m3 9,250,000
Balok/pesagen 6X12X400 m3 8,500,000
7 DOLKEN
Sedang 8x10x400 cm bt 21,000
Kecil 6x7x400 cm bt 18,000
Besar 10x12x400 cm bt 31,000
Kayu cetakan m3 1,800,000
Kayu bakar m3 180,000
Bambu bt 12,000

IV. BAHAN PENUTUP DINDING /LANTAI


1 UBIN(TEGEL BIASA)
PC polos
30x30 cm m2 33,000
20x20cm m2 31,000
PC warna
30x30cm m2 34,000
20x20cm m2 31,000
Teraso
30x30 cm m2 52,000
2 TEGEL PLINT
PC warna 10X 20 cm bh 5,000
PC abu-abu 15x20 bh 4,500
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
3 UBIN PORSELIN
Lokal
11 X11 putih dos 36,000
11 X11 warna dos 40,000
Lokal
15x15 putih dos 37,000
15 X 15 warna dos 39,000
4 MOZAIK PORSELIN
10x20cm m2 52,000
10x20cm buah 1,040
15x15cm m2 51,000
20x20 cm m2 55,000
20x20 cm buah 2,200
20x25cm m2 53,000
5 Keramik
30x30 cm m2 42,500
30x30 cm dus 42,500
20x20cm m2 55,000
33x33 cm m2 60,000
25x25 cm m2 54,000
15x20 cm m2 56,000
40x40 cm dus 99,000
50x50 dus 72,000
8 Parquet Jati m2 290,000
9 Batu Maros m2 115,000
10 Batu Tempel Hitam m2 105,000
11 GRANITO
40x40 cm m2 160,000
30x30 cm m2 180,000
10 Marmer m2 320,000

V. BAHAN CETAK
A BUIS BETON Ø
1 10cm-100 cm bh 35,000
2 20 cm-100 cm bh 45,000
3 30 cm-100 cm bh 75,000
4 50cm-100 cm bh 135,000
5 60 cm-100 cm bh 165,000
6 70 cm-100 cm bh 180,000
7 10 cm-100 cm bh 22,000
8 15 cm-100cm bh 24,500
9 20 cm-100 cm bh 28,000
10 30 cm-100 cm bh 44,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
11 50 cm-100 cm bh
B LUBANG ANGIN (ROSTER)PC+PASIR
1 10x20cm bh 8,000
2 20x20cm bh 9,000
3 25x25cm bh 10,200
4 30x30 cm bh 12,000
5 15x25cm bh 9,250
6 15x30cm bh 10,200

VI. BAHAN BESI


a Besi beton polos kg 10,000
b Besi beton prestress kg 13,000
C Besi beton ulir kg 11,000
2 BESI PLAT
a Besi Strip kg 14,500
3 BESI PROFIL Besi Profil kg 15,000
a BAJA RINGAN
GALVALUM lebar:7,5cm tebal:1mm btg 135,000
type CT 75 lebar:7,5cm tebal:0.75mm btg 105,000
type CT 75 lebar:7,5cm tebal:0,65mm btg 95,000
b type RT 12 tinggi:3,5 cm,tebal:0,45mm btg 50,000
type RT 10 tinggi:3,0 cm,tebal :0,45mm btg 45,000
C HOLLOW GALVANIS LIPAT
tinggi 2 cm;tebal:0,3mm btg 20,000
tinggi 4 cm;tebal:0,3mm btg 27,000
4 JARING-JARING BAJA
a Diameter 4-15 kg 14,000
b Diameter 6-15 kg 14,000
C Kawat Bronjong kg 12,500
5 BESI SIKU L
a 40x40x4 btg 217,500
b 50x50x5 btg 337,500
C 60x60x6 btg 308,750
6 KAWAT
a Ikat beton/bendrat kg 18,000
-Harmonika 12 X 45 mm m2 20,000
-Harmonika 12 X 24 mm m2 22,000
-Harmonika 14 X 30 mm m2 19,000
-Harmonika 14 X 35 mm m2 17,500
-Kawat Nyamuk Nylon m2 12,000
-Kawat Kasa m2 12,000
-Saringan pasir m2 14,500
-Kawat loket m2 11,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
-Kawat duri rol 75,000
-Kawat bronjong kg 15,000

VII. BAHAN PIPA


1 Pipa PVC SII SCJ,S-12,5(10 bar)
Pipa PVC DN 20(1/2")AW JIS,panjang btg 20,000
Pipa PVC DN 25(3/4") AW JIS, panjang btg 24,000
Pipa PVC DN 32( 1" AW JIS, panjang 4 btg 29,000
Pipa PVC DN 40(11/2"), panjang 4 m btg 54,000
Pipa PVC DN 63(2"),panjang 4 m btg 77,000
Pipa PVC DN 90(3"),panjang 4 m btg 130,000
Pipa PVC DN 110( 4"),panjang 4 m btg 175,000
Pipa PVC DN 160(6"), panjang 4 m btg 423,000
Pipa PVC DN 200(8"),panjang 4 m btg 68,000
Pipa PVC DN 250(10"),panjang 4 m btg 1,025,000
Pipa PVC DN 315(12"),panjang 4m btg 1,390,000
2 Pipa Medium A Galvanis-SII
Pipa Medium Galvanis 0,50",panjang 6 btg 160,000
Pipa Medium Galvanis 0,75",panjang 6 btg 190,000
Pipa Medium Galvanis 1",panjang 6 m btg 310,000
Pipa Medium Galvanis 1,25",panjang 6m btg 385,000
Pipa Medium Galvanis 1,50",panjang 6 btg 445,000
Pipa Medium Galvanis 2",panjang 6 m btg 595,000
Pipa Medium Galvanis 2,50",panjang 6 btg 730,000
Pipa Medium Galvanis 3",panjang 6 m btg 980,000
Pipa Medium Galvanis 4",panjang 6 m btg 1,435,000
Pipa Medium Galvanis 5" btg 1,900,000
Pipa Medium Galvanis 6" btg

VIll. BAHAN LANGIT-LANGIT


1 AKUSTIK-uk:
30x30 lbr 5,200
30x60 lbr 12,700
60x120 lbr 40,500
List Kayu Profil m' 4,800
2 SOFT BOARD-uk:4'X 8' lbr 62,000
Gypsum tebal 9mm lbr 62,000
List Kayu Gypsum 15cm, pjg 2m m' 22,000
Tepung Gypsum kg 2,600
3 HARD BOARD-uk:4'X 8' lbr 60,000
GYPROC uk.120cmx240cmx9mm
4 PLY WOOD
Teak wood
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
a 90x210x3mm lbr 42,500
b 120x240x3mm lbr 85,000
C 90x210x4mm lbr 55,000
d 90x210x9mm lbr 145,000
e 90x210x12mm lbr 175,000
f 90x210x15mm Ibr 220,000
g 90x210x18mm lbr 275,000
Tripleks
a 120x240x3 lbr 50,000
b 120x240x4 lbr 60,000
C 120x240x6 lbr 70,000
Multipleks
a 120x240x9mm lbr 140,000
b 120x240x12mm lbr 160,000
C 120x240x15mm lbr 200,000
d 120x240x18mm lbr 220,000
Formika ukuran pintu lbr 52,000

IX. BAHAN FINISHING


A KAYU
1 Menie kg 15,000
2 Dempul plamur kg 11,000
3 Ambril/amplas lbr 3,200
4 tu Apung kg 5,000
5 Cat dasar kg 36,500
6 Emco kg 56,000
7 Yunior 66 (nippon paint) kg 58,000
8 Koas bh 7,500
9 Deculux kg 60,000
10 Siralax ons 27,000
11 Spiritus Itr 14,000
12 Plitur jadi Itr 42,000
Pengencer Cat kg 50,000
B TEMBOK
1 Kalkarium kg 4,000
2 Kapur sirih kg 4,500
3 Plamur kg 12,500
4 Cat Tembok kg 25,000
5 Sintex 5kg 115,000
6 Danabride 5kg 110,000
7 Catylac 5kg 120,000
8 Mowilex 2,50kg 290,000
C BESI
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
1 Menie kg 28,000
2 Cat mengkilat kg 58,000
3 Cat kg 36,000
4 Thinner A ltr 25,000
5 Minyak cat ltr 18,000
6 Thinner Super ltr 32,000
7 Residu (teer/aspal) drum 75,000
Fibre glass (tanki air)
a kapasitas 550 liter. bh 1,050,000
b kapasitas 1100 liter. bh 1,800,000
C Lem Aica Aibon kg 32,000

X. BAHAN KACA
1 POLOS
3mm m2 85,000
5mm m2 95,000
2 ES KABUR
3mm m2 105,000
5mm m2 120,000
3 RAY BAND
3mm m2 90,000
5mm m2 105,000
Silicone Sealant 300 ml tube 35,000

XI. BAHAN INSTALASI LISTRIK


1 KABEL LISTRIK
a NYA:.1X11/2 mm2 m' 3,100
A SPLN LMK
a 1 X21/2 mm2 m' 3,750
b 1X4mm2 m' 5,800
C 1X6mm2 m' 8,600
d NYY:.2X11/2 mm2 m' 8,700
a 2X21/2 mm2 m' 14,200
b 2x4mm2 m' 25,250
C 2X6mm2 m' 34,200
d 3x1 1/2 mm2 m' 12,500
e 3 X 2 1/2 mm2 m' 19,000
f 3X4mm2 m' 34,000
g 3X6mm2 m' 48,000
h NYM:2x11/2 m' 6,800
C SPLN 42-2LMK
a 2x2 1/2 mm2 m' 10,200
b 2X4 mm2 m' 21,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
C 3x11/2 mm2 ㎡' 12,500
d 3x21/2mm2 m' 19,200
e 3X4mm2 m' 31,000
f 3X6mm2 m' 43,000
2 SKAKELAR
a Out bauw Seri bh 20,000
b Out bauw Engkel bh 15,000
C In bauw Seri bh 17,500
d In bauw Engsel bh 15,000
3 FUSE BOX(SEKERING KASA)
a 1 group bh 130,000
b 2 group bh 230,000
C 3 group bh 320,000
4 STEKER-
a Biasa bh 10,000
b Arde bh 17,500
C T Biasa bh 15,000
d T dengan Arde bh 18,000
5 FITING
a Flaon bh 7,500
b Gantung bh 7,500
C Kap
Kombinasi bh 5,000
d AK
STOP KONT bh 35,000
6 ih
Arde Outbow put
a hitam bh 12,500
b Arde Outbow bh 7,500
C Arde IB bh 15,000
d Arde Put bh 31,000
Las Dop bh 220
Klem Listrik bh 100
Mangkok Listrik bh 3,000
Pipa Listrik 5-8 inc btg 5,000
L Bow Listrik bh 500
Box MCB bh 11,000
MCB bh 63,000

XII ALAT-ALAT PENGUNCI & PENGGANTUNG


1 TANAM
a Union
Union::1X slag bh 70,000
2X slag bh 90,000
b Yale: 1X slag bh 80,000
Yale :2X slag bh 125,000
b Kuda : 1X slag bh 50,000
NO KODE JENIS BAHAN / PEKERJA SATUAN HARGA
Kuda: 2 X slag bh 70,000
2 ENGSEL DAN GERENDEL
a Engsel Angin bh 15,000
b Kuou-kupu biasa bh 2,250
C Nylon kupu-kupu bh 5,000
REKAP VOLUME
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO URAIAN PEKERJAAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan 0.00 m2
2 Pengukuran & Pemasangan Bouwplank 0.00 m'
3 Pembuatan Steger/Perancah dari Bambu 0.00 m2
4 Penyediaan Air & Listrik Kerja 1.00 ls

II PEKERJAAN TANAH & PONDASI


1 Galian Tanah Pondasi 0.00 m3
2 Pemasangan pondasi batu belah campuran 1SP : 4PP 0.00 m3
3 Pasir Urug Bawah Pondasi 0.00 m3
4 Pemasangan Batu kosong (anstamping) 0.00 m3
5 Urugan Kembali Bekas Galian 0.00 m3
6 Pemadatan Tanah per 20cm 0.00 m3

III PEKERJAAN BETON BERTULANG


1 Pekerjaan Sloof 0.00 m3
2 Pekerjaan Kolom 0.00 m3
3 Pekerjaan Ring Balk 0.00 m3
4 Pengecoran Plat Dak 0.00 m3
5 Bekisting Plat Dak 0.00 m2
6 Pembesian Plat Dak 241.57 kg

IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu 0.00 m3
2 Pemasangan Balok Gording, Nok, Kait Angin 0.00 m3
3 Pemasangan Rangka Atap 0.00 m2
4 Pemasangan Atap 0.00 m2
5 Pemasangan Bubungan 0.00 m'
6 Pemasangan List Plank 0.00 m'
7 Pemasangan Talang Air 0.00 m'

V PEKERJAAN PASANGAN DINDING


1 Pemasangan Dinding Bata Merah 0.00 m2
2 Pemasangan Plester Dinding 0.00 m2
3 Pemasangan Acian Dinding 0.00 m2

VI PEKERJAAN PINTU & JENDELA


1 Pembuatan dan pemasangan Kusen Pintu & Jendela (Kayu Jati) 0.00 m3
2 Pembuatan & Pemasangan Daun Pintu (Kayu Jati) 0.00 m2
3 Pembuatan & Pemasangan Daun Jendela Kaca (Kayu Jati) 0.00 m2
4 Pemasangan Pintu PVC 1.00 bh
REKAP VOLUME
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO URAIAN PEKERJAAN VOLUME SATUAN

VII PEKERJAAN PLAFOND


1 Pemasangan Rangka Plafond 0.00 m2
2 Pemasangan Plafond Gypsum 0.00 m2
3 Pemasangan List Plafond Gypsum 0.00 m'

VIII PEKERJAAN PENUTUP LANTAI


1 Pemasangan Keramik 50x50 0.00 m2
2 Pemasangan Keramik 25x25 - Kamar Mandi 0.00 m2
3 Pemasangan Keramik 25x25 - Teras 0.00 m2
4 Pemasangan Plint Keramik 0.00 m'

IX PEKERJAAN INSTALASI LISTRIK & PLUMBING


1 Titik Lampu 14.00 pcs
2 Lampu Downlight 11.00 pcs
3 Lampu Fitting 3.00 pcs
4 Stop Kontak 1 Lubang 5.00 pcs
5 Stop Kontak 2 Lubang 1.00 pcs
6 Stop Kontak 3 Lubang 1.00 pcs
7 Saklar Single 5.00 pcs
8 Saklar Double 3.00 pcs
9 Pemasangan MCB 1.00 pcs
10 Pipa Air Bersih 3/4" 36.84 m'
11 Pipa Air Kotor 4" 20.49 m'
12 Pipa Air Bekas 2,5" 20.32 m'
13 Wastafel 1.00 pcs
14 Kran Dinding 3.00 pcs
15 Kran Sink 1.00 pcs
16 Floor Drain 1.00 pcs
17 Bak Mandi 1.00 pcs
18 Closet Jongkok 1.00 pcs
19 Bak Control 1.00 pcs

X PEKERJAAN FINISHING
1 Pengecetan Dinding Dalam 0.00 m2
2 Pengecetan Dinding Luar 0.00 m2
3 Pengecetan Kusen Pintu & Jendela 0.00 m2
4 Pengecetan Daun Pintu & Jendela 0.00 m2
5 Pengecetan Plafond 0.00 m2

XI PEKERJAAN KUNCI & KACA


1 Pemasangan Kaca 5mm 0.00 m2
2 Pemasangan Kaca 7mm 0.00 m2
REKAP VOLUME
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO URAIAN PEKERJAAN VOLUME SATUAN

3 Pasangan Kunci 0.00 bh


4 Pemasangan Engsel Pintu 0.00 bh
5 Pemasangan Grendel Jendela 0.00 bh
6 Pemasangan Kait Angin Jendela 0.00 bh
7 Pemasangan Engsel Jendela 0.00 bh

XII PEKERJAAN LANDSCAPE


1 Pembuatan & Perapihan Taman 1.00 ls
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan Volume Total = 0.00 m2
Panjang (P) = m Rumus = PxL
Lebar (L) = m Volume = 0.00 m2

2 Pengukuran & Pemasangan Bouwplank Volume Total = 0.00 m'


Panjang (P) = m Rumus = 2 x (P + L)
Lebar (L) = m Volume = 0.00 m2

3 Pembuatan Steger/Perancah dari Bambu Volume Total = 0.00 m2


Panjang (P) = m Rumus = PxLxQ
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

II PEKERJAAN TANAH & PONDASI


1 Galian Tanah Pondasi Volume Total = 0.00 m3
Galian Pondasi(A)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m

Galian Pondasi (B)


Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m

Galian Pondasi (C)


Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m

2 Pemasangan Pondasi Volume Total = 0.00 m3


Pondasi(A)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m

Pondasi (B)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Pondasi (C)
Panjang (P) = m Rumus = (L1+L2)/2 x P x T
Lebar (L1) = m Volume = 0.00 m3
Lebar (L2) = m
Tinggi (T) = m

3 Pemasangan Pasir Urug Volume Total = 0.00 m3

Pondasi (A)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

Pondasi (B)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

Pondasi (C)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

4 Pemasangan Batu kosong (anstamping) Volume Total = 0.00 m3


Pondasi (A)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

Pondasi (B)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

5 Urugan Kembali Bekas Galian Volume Total = 0.00 m3


Vol Galian = m3 Rumus = 1/3 x Vol Galian
Volume = 0.00 m3

6 Pemadatan Tanah per 20cm di bawah Lantai Volume Total = 0.00 m3

Elv 0.00
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3

Elv +0.100
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Elv -0.100
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3

Elv -0.05
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3

Elv -0.2
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3

Elv -0.35
Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3

7 Pengurugan & Pemadatan dengan Sirtu Volume Total = 0.00 m3


Area (A) = m2 Rumus = AxT
Tinggi (T) = m Volume = 0.00 m3
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

III PEKERJAAN BETON

1 Volume Beton Sloof Uk. 15/20 Volume Total = 0.00 m3


Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

2 Volume Kolom Uk. 150/150 Volume Total = 0.00 m3


Tinggi = 3,85 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

Tinggi =3,35 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

Tinggi =3,15 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

Tinggi =0,6 m
Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

Tinggi =0,663 m (diatas Ring Balk +4.000)


Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

Tinggi =2,500 (Kolom Gunung2)


Tinggi (T) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Panjang (P) = m
Jumlah (Q) = pcs

3 Volume Ring Balk Volume Total = 0.00 m3


RB.1 (+ 4.000 )
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Tinggi (T) = m

RB.2 (+ 3.500 )
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

RB.3 (+ 3.300 )
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

BG (Balok Gunung)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

BL (Balok Latiu)
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

4 Volume Beton Plat Dak Volume Total = 0.00 m3


Plat Dak Teras
Luas (A) = m2 Rumus = PxT
Tebal (T) = m Volume = 0.00 m3

Plat Dak Belakang


Luas (A) = m2 Rumus = PxT
Tebal (T) = m Volume = 0.00 m3

Plat Kanopi
Luas (A) = m2 Rumus = PxT
Tebal (T) = m Volume = 0.00 m3

5 Volume Bekisting Plat Dak Volume Total = 0.00 m2


Plat Dak Teras
Luas (A) = m2 Rumus = A
Plat Dak Belakang
Luas (A) = m2 Rumus = A
Plat Kanopi
Luas (A) = m2 Rumus = A

6 Volume Besi Plat Dak Volume Total = 241.57 kg

III PEKERJAAN ATAP


1 Pemasangan 1 m3 konstruksi kuda-kuda Kayu Volume Total = 0.00 m3
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Kayu 8/12
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

Kayu 5/10
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

2 Pemasangan Balok Gording, Nok Volume Total = 0.00 m3


Kayu 8/12
Panjang (P) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

Kayu 6/12
Panjang (P) = m Rumus = PxLxTxQ
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m

4 Pemasangan Rangka Atap Volume Total = 0.00 m2


Bidang All
Area (A) = m2 Rumus = A
Volume = 0.00 m2

5 Pemasangan Genteng Palentong Besar Volume Total = 0.00 m2

Luas Rangka Atap (A) = m2 Rumus = A


Volume = 0.00 m2

6 Pemasangan Genteng Bubungan Volume Total = 0.00 m'


Panjang (P) = m Rumus = P
Volume = 0.00 m'

7 Pemasangan 1 m' List Plank uk. 3x20cm Volume Total = 0.00 m'
Panjang (P) = m Rumus = P
Volume = 0.00 m'

8 Pemasangan 1 m' Talang Air Volume Total = 0.00 m'


Panjang (P) = m Rumus = P
Volume = 0.00 m'

IV PEKERJAAN DINDING
1 Pemasangan Dinding Bata Merah Volume Total = 0.00 m2

Level +4.000
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Panjang (P) = m Rumus = PxT


Tinggi (T) = m Volume = 0.00 m2

Level +3500
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Level +3300
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Level +2450
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Level +1450
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Gunung-Gunung 1
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2

Gunung-Gunung 2
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2

Gunung-Gunung 3
Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2

Dinding Atas Ring Balk


Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2

Dinding Diatas Taman


Area (A) = m Rumus = AxQ
Jumlah (Q) = pcs Volume = 0.00 m2

Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs

Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs

Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang R.Shalat
Lebar (L) = m Rumus = -(P x L x Q)
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Tinggi (T) = m Volume = 0.00 m2


Jumlah (Q) = pcs

Ruang Tamu
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

2 Pemasangan Plester Dinding Volume Total = 0.00 m2


Volume Bata = m2 Rumus = (Volume Bata x 2)-Vol tdk plester
Volume tdak di plester = m2 Volume = 0.00 m2

3 Pemasangan Acian Dinding Volume Total = 0.00 m2

4 Pemasangan Bata Roster Terakota Volume Total = 0.00 m2


Volume Bata = m2 Rumus = Vol Bata
Volume = 0.00 m2

V PEKERJAAN KAYU
1 Volume Kusen Kayu Pintu & Jendela Volume Total = 0.00 m3
Kusen D-01
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen D-02
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen DW
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen DS
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen W-01
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Jumlah (Q) = pcs

Kusen W.02
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen W.03
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen W.04
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen BV-1
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

Kusen BV.2
Panjang (P) = m Rumus = (P x L x T x Q )
Lebar (L) = m Volume = 0.00 m3
Tinggi (T) = m
Jumlah (Q) = pcs

2 Volume Daun Pintu Volume Total = 0.00 m2


Daun.P D-01
Tinggi (T) = m Rumus = (P x L x Q )
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Daun.P D-02
Tinggi (T) = m Rumus = (P x L x Q )
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Daun.P DW
Tinggi (T) = m Rumus = (P x L x Q )
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

3 Volume Daun Pintu & Jendela Kaca Volume Total = 0.00 m2


Jendela Pintu DW
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs

Pintu DS
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.01
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.02
Luas 1 (L1) = m2 Rumus = (L1+L2) x Q
luas 2 (L2) = m2 Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.03
Luas 1 (L1) = m Rumus = (L1+L2) x Q
luas 2 (L2) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.04
Luas 1 (L1) = m Rumus = (L1+L2) x Q
luas 2 (L2) = m Volume = 0.00 m2
Jumlah (Q) = pcs

V PEKERJAAN PLAFOND

1 Pemasangan Rangka Plafond Volume Total = 0.00 m2


Area (A) = m2 Rumus = A
Volume = 0.00 m2

2 Pemasangan Plafond Volume Total = 0.00 m2


Vol Rangka = m2 Rumus = A
Volume = 0.00 m2

3 Pemasangan List Plafond Volume Total = 0.00 m'


Panjang (P1) = m' Rumus =Panjang Total
Panjang (P2) = m' Volume = 0.00 m
Panjang (P3) = m'
Panjang (P4) = m'
Panjang (P5) = m'
Panjang (P6) = m'
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Panjang (P7) = m'


Panjang (P8) = m'
Panjang (P9) = m'
Panjang (P10) = m'

V PEKERJAAN PENUTUP LANTAI

1 Pemasangan Kramik 50x50 Volume Total = 0.00 m2


Area (A1) = m2 Rumus = A1
Volume = 0.00 m2

2 Pemasangan Kramik (25 x 25) - Kamar Mandi Volume Total = 0.00 m2


Area (A1) = m2 Rumus = A1
Volume = 0.00 m2

3 Pemasangan Kramik (25 x 25) - Teras Volume Total = 0.00 m2


Area (A1) = m2 Rumus = A1+A2
Volume = 0.00 m2

4 Plint Keramik Hitam Volume Total = 0.00 m'


Panjang = m Rumus = P
Volume = 0.00 m2

V PEKERJAAN INSTALASI LISTRIK & PLUMBING


1 Titik Lampu Volume Total = 14 pcs
2 Lampu Downlight Volume Total = 11 pcs
3 Lampu Fitting Volume Total = 3 pcs
4 Stop Kontak 1 Lubang Volume Total = 5 pcs
5 Stop Kontak 2 Lubang Volume Total = 1 pcs
6 Stop Kontak 3 Lubang Volume Total = 1 pcs
7 Saklar Single Volume Total = 5 pcs
8 Saklar Double Volume Total = 3 pcs
9 Pemasangan MCB Volume Total = 1 pcs
10 Meter Box PLN Volume Total = 1 pcs
11 Pipa Air Bersih 3/4" Volume Total = 37 m'
12 Pipa Air Kotor 4" Volume Total = 20 m'
13 Pipa Air Bekas 2,5" Volume Total = 20 m'
14 Wastafel Volume Total = 1 pcs
15 Kran Dinding Volume Total = 3 pcs
16 Kran Sink Volume Total = 1 pcs
17 Floor Drain Volume Total = 1 pcs
18 Bak Mandi Volume Total = 1 pcs
19 Closet Jongkok Volume Total = 1 pcs
20 Bak Control Volume Total = 1 pcs

V PEKERJAAN FINISHING
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 Pengecetan Dinding Dalam Volume Total = 0.00 m2

Level +3.200
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Level +4.400
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs

Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs

Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang BV.2
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang R.Shalat
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Ruang Tamu
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

2 Pengecetan Dinding Luar Volume Total = 0.00 m2

Tampak Depan Lv +4.589


Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Tampak Depan Level +3.660


Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Samping Kanan 1
Area (A) = m Rumus = A
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Volume = 0.00 m2

Samping Kanan 2
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Samping Kanan 3
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Samping Kiri 1
Area (A) = m Rumus = A
Volume = 0.00 m2

Samping Kiri 2
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Belakang 1
Area (A) = m Rumus = A
Volume = 0.00 m2
Belakang 1
Panjang (P) = m Rumus = PxT
Tinggi (T) = m Volume = 0.00 m2

Lubang D.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang D.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang D.03
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang DW
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Lubang DS
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.01
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.02
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang W.03
Lebar (L1) = m Rumus = -(P1 x L1 x Q1)+(P2 x L2 x Q2 )
Tinggi (T1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Lebar (L2) = m
Tinggi (T2) = m
Jumlah (Q2) = pcs

Lubang W.04
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang BV
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Lubang BV.2
Lebar (L) = m Rumus = -(P x L x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

3 Pengecetan Kusen Pintu & Jendela Volume Total = 0.00 m2


Pintu D.01
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Pintu D.02
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Pintu DW
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Pintu DS
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.01
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.02
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Tinggi (T) = m Volume = 0.00 m2


Jumlah (Q) = pcs

Jendela W.03
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela W.04
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela BV
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela BV.2
Panjang (P) = m Rumus = ((P x L x 2 ) + ( P x T x 2 )) x Q
Lebar (L) = m Volume = 0.00 m2
Tinggi (T) = m
Jumlah (Q) = pcs
Pengurang
Panjang (P) = m Rumus = - (P x T x Q)
Tinggi (T) = m Volume = 0.00 m2
Jumlah (Q) = pcs

4 Pengecetan Daun Pintu & Jendela Volume Total = 0.00 m2


Luas Daun Pintu (A) = m2 Rumus = (Ax2)
Volume = 0.00 m2
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

5 Pengecetan Plafond Volume Total = 0.00 m2


Vol Plafond = m2 Rumus = Vol Plafond
Volume = 0.00 m2

V PEKERJAAN KUNCI & KACA


1 Pemasangan Kaca 5mm Volume Total = 0.00 m2
Pintu D.01
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Pintu DW
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs

Jendela W.01
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs

Jendela W.02
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs

Jendela W.03
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
Lebar (L2) = m
Jumlah (Q2) = pcs

Jendela W.04
Panjang (P1) = m Rumus = (P1 x L2 x Q2) + (P2 x L2 x Q2)
Lebar (L1) = m Volume = 0.00 m2
Jumlah (Q1) = pcs
Panjang (P2) = m
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

Lebar (L2) = m
Jumlah (Q2) = pcs

Jendela BV.1
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

Jendela BV.2
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

2 Pemasangan Kaca 7mm Volume Total = 0.00 m2


Pintu DS
Panjang (P) = m Rumus = PxLxT
Lebar (L) = m Volume = 0.00 m2
Jumlah (Q) = pcs

2 Pemasangan Kunci Volume Total = 0.00 pcs


Pintu D.01 = pcs
Pintu D.02 = pcs
Pintu DW = pcs

3 Pemasangan Engsel Pintu Volume Total = 0.00 pcs


Pintu D.01 = pcs
Pintu D.02 = pcs
Pintu DW = pcs

4 Pemasangan Grendel Jendela Volume Total = 0.00 pcs


DW = pcs
W.01 = pcs
W.02 = pcs
W.03 = pcs
W.04 = pcs

5 Pemasangan Kait Angin Jendela Volume Total = 0.00 pcs


DW = pcs
W.01 = pcs
W.02 = pcs
W.03 = pcs
W.04 = pcs

6 Pemasangan Engsel Jendela Volume Total = 0.00 pcs


DW = pcs
W.01 = pcs
URAIAN PERHITUNGAN
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

W.02 = pcs
W.03 = pcs
W.04 = pcs
NO URAIAN PEKERJAAN SAT.
a b d

I PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan Lahan m2
2 Pengukuran & Pemasangan Bouwplank m'
a Kayu 5/7 (Rawa) m3
b Paku 2"-3" kg
c Kayu Papan 3/20 (Rawa) m3

3 Pembuatan Steger/Perancah dari Bambu m2


Bambu diameter 6-8/600 cm Batang
Tali ijuk m3

4 Penyediaan Air & Listrik Kerja ls

II PEKERJAAN TANAH & PONDASI


1 Galian Tanah Pondasi m3
2 Pemasangan pondasi batu belah campuran 1SP : 4PP m3
Batu belah m3
Semen portland Kg
Pasir Pasang m3

3 Pasir Urug Bawah Pondasi m3


Pasir Urug m3

4 Pemasangan Batu kosong (anstamping) m3


Batu Belah m3
Pasir Urug m3

5 Urugan Kembali Bekas Galian m3


6 Pemadatan Tanah per 20cm m3
7 Pengurugan & Pemadatan dengan Sirtu m3
Pasir Urug m3

III PEKERJAAN BETON


1 Pekerjaan Sloof m3
Kayu Rawa m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3

2 Pekerjaan Kolom m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu Splite (2-3cm) m3
Kayu Rawa 4/6 M3
Plywood 9 mm uk. 120 x 240 mm Lbr
Kayu Dolken Ø 8-10/400 cm Batang

3 Pekerjaan Ring Balk m3


Kayu kelas III ( Pinus ) m3
Paku kg
Minyak Bekisting Liter
Besi beton (polos/ulir) kg
Kawat beton kg
Semen Portland kg
Pasir Beton m3
Batu pecah mesin 2-3 cm m3
Kayu Kalimantan ( Meranti Batu ) 5/7 & 4/6 (ikat) m3
Plywood 9 mm uk. 120 x 240 mm Lbr
Dolken kayu Ø 8-10/400 cm Batang

4 Pengecoran Plat Dak m3


Semen Portland Kg
Pasir beton Kg
Kerikil (Maks 30mm) Kg
Air Liter

5 Bekisting Plat Dak m2


Papan kayu kelas III m3
Paku 5 cm - 12 cm Kg
Minyak bekisting Liter
Balok kayu kelas II m3
Plywood tebal 9 mm Lbr
Dolken kayu galam, ( 8-10) cm panjang 4m Batang

6 Pembesian Plat Dak kg


Besi beton (polos/ulir) kg
Kawat beton kg

7 Pengecoran Plat Kanopi m3


Semen portland kg
Pasir Beton kg
Batu Splite (2-3cm) kg
Air Liter

8 Bekisting Plat Kanopi m2


Kayu Rawa m3
Paku 5 - 12 cm kg
Minyak Bekisting Liter
Plywood 9 mm uk. 120 x 240 mm Lbr
Kayu Dolken Ø 8-10/400 cm Batang

9 Pembesian Plat Kanopi kg


Besi beton (polos/ulir) kg
Kawat beton kg

IV PEKERJAAN ATAP
1 Pemasangan Kontruksi Kuda-kuda Kayu m3
Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg

2 Pemasangan Balok Gording, Nok, Kait Angin m3


Kayu Balok Rangka Atap m3
Besi Strip tebal 5 mm Kg
Paku 12 cm Kg

3 Pemasangan Rangka Atap m2


Kayu Kaso 5/7 cm m3
Kayu Reng 2 x 3 cm m3
Paku Biasa kg

4 Pemasangan Atap m2
Genteng palentong besar (morando) Buah

5 Pemasangan Bubungan m'


Genteng bubung Buah
Semen Portlan Kg
Pasir pasang M3

6 Pemasangan List Plank m'


Papan kayu m3
Paku 5 dan 7 cm Kg

7 Pemasangan Talang Air m'


Seng plat m
Paku Biasa kg
Kayu Papan Jati m3

V PEKERJAAN PASANGAN DINDING


1 Pemasangan Dinding Bata Merah m2
Bata merah buah
Semen portland Kg
Pasir pasang m3

2 Pemasangan Plester Dinding m2


Semen portland Kg
Pasir pasang m3

3 Pemasangan Acian Dinding m2


Semen portland Kg

4 Pemasangan Bata Roster m2


Bata terawang buah
Semen portland Kg
Pasir pasang m3
VI PEKERJAAN KAYU
1 Pembuatan dan pemasangan Kusen Pintu & Jendela (Kayu Jati) m3
Kayu Balok - Kusen m3
Paku 10 cm Kg
Lem kayu Kg

2 Pembuatan & Pemasangan Daun Pintu (Kayu Jati) m2


Kayu Papan Jati m3
Lem kayu Kg

3 Pembuatan & Pemasangan Daun Jendela Kaca (Kayu Jati) m2


Kayu Papan Jati m3
Lem kayu Kg

4 Pemasangan Pintu PVC bh


Pintu Pvc bh

VII PEKERJAAN PLAFOND


1 Pemasangan Rangka Plafond (Kayu) m2
Kayu Kaso 5 x 7 cm m3
Paku 7- 10 cm Kg

2 Pemasangan Plafond Gypsum m2


Papan gipsum 120x240 cm Lembar
Paku sekrup Kg

3 Pemasangan List Plafond Gypsum m'


List Gipsum Profil 15 cm Pj. 2.00 m' m'
Tepung gypsum kg

VIII PEKERJAAN PENUTUP LANTAI


1 Pemasangan Keramik 50x50 m2
Keramik 50 x 50 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3
2 Pemasangan Keramik 30x30 m2
Kramik 25 x 25 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3

3 Pemasangan Keramik Kamar Mandi m2


Kramik 20x20 Dus
Semen portland Kg
Semen warna Kg
Pasir pasang m3

4 Pemasangan Keramik Dinding Kamar Mandi m2


Porslen Buah
Semen portland Kg
Pasir pasang m3
Semen warna Kg

5 Pemasangan Plint Keramik m'


Plint keramik Buah
Semen portland Kg
Semen warna Kg
Pasir pasang m3

IX PEKERJAAN INSTALASI LISTRIK & AIR


1 Pemasangan Titik Lampu bh
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Las Dop Buah
Klem Buah
Mangkok Buah
Saklar Buah
Fitting Buah
2 Lampu Downlight pcs
3 Lampu Fitting pcs
4 Stop Kontak 1 Lubang pcs
5 Stop Kontak 2 Lubang pcs
6 Stop Kontak 3 Lubang pcs
7 Saklar Single pcs
8 Saklar Double pcs
9 Pemasangan MCB
Pipa listrik 5/8" btg
Kabel m
T Dus Buah
L Bow Buah
Klem biasa Buah
MCCB (Boks MCB) Buah
MCB Buah
10 Err:509 pcs
11 Pipa Air Bersih 3/4"
Pipa PVC 3/4” m
12 Pipa Air Kotor 4"
Pipa PVC 4” m
13 Pipa Air Bekas 2,5"
Pipa PVC 3” m
14 Wastafel pcs
15 Err:509 Err:509
16 Kran Dinding pcs
17 Kran Sink pcs
18 Floor Drain pcs
19 Bak Mandi
Bata merah Buah
Semen portland Kg
Pasir pasang m3
Porselen 11x11 bh
20 Closet Jongkok
Closet jongkok Unit
Pasangan bata 1PC:3PS m2
21 ### Err:509
22 ### Err:509
23 Bak Control
Bata merah bh
Semen portland Kg
Pasir pasang M3
Pasir beton M3
Batu Splite (2-3cm) M3
Besi Beton Kg
X PEKERJAAN FINISHING
1 Pengecetan Dinding Dalam m2
Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg

2 Pengecetan Dinding Luar m2


Plamur Tembok Kg
Cat tembok / cat dasar Kg
Cat Penutup Tembok Kg

3 Pengecetan Kusen Pintu & Jendela m2


Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr

4 Pengecetan Daun Pintu & Jendela m2


Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr

5 Pengecetan Plafond m2
Cat menie Kg
Plamur Kayu Kg
Cat dasar ( meni kayu ) Kg
Cat Warna ( Kayu ). Kg
Kuas cat 3" Buah
Pengencer Kg
Amplas Lbr

XI PEKERJAAN KUNCI & KACA


1 Pemasangan Kaca Jendela 5mm m2
Kaca tebal 5mm m2
Silicone Sealant 300 ml Tube

2 Pemasangan Kaca Jendela 7mm


Kaca tebal 7mm m2
Silicone Sealant 300 ml Tube

3 Pasangan Kunci bh
4 Pemasangan Engsel Pintu bh
5 Pemasangan Grendel Jendela bh
6 Pemasangan Kait Angin Jendela bh
7 Pemasangan Engsel Jendela bh

XII PEKERJAAN LANDSCAPE


1 Pembuatan & Perapihan Taman ls
VOLUME
KOEF. VOL BAHAN SATUAN VOL. SAT.
PEK
c e f = (c x e) g h i

0.00 m2
0.00
0.01 0.00 0.00 m3 0.00 m3
0.02 0.00 0.00 kg 0.00 kg
0.01 0.00 0.00 m3 0.00 m3

0.00
1.25 0.00 0.00 Batang 0.00 Batang
0.19 0.00 0.00 m3 0.00 m3

1.00 0.00 ls

0.00
1.20 0.00 0.00 m3 0.00 m3
163.00 0.00 - Kg - kg/50kg
0.52 0.00 0.00 m3 0.00 m3

0.00
1.20 0.00 0.00 m3 0.00 m3

0.00
1.20 0.00 0.00 m3 0.00 m3
0.43 0.00 0.00 m3 0.00 m3

Err:509
1.20 Err:509 Err:509 m3 Err:509 m3

0.00
0.27 0.00 0.00 m3 0.00 m3
2.00 0.00 0.00 kg 0.00 kg
0.60 0.00 0.00 Liter 0.00 Liter
210.00 0.00 0.00 kg 0.00 kg
3.00 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3

0.00
4.00 0.00 0.00 kg 0.00 kg
2.00 0.00 0.00 Liter 0.00 Liter
212.00 0.00 0.00 kg 0.00 kg
4.50 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3
0.15 0.00 0.00 M3 0.00 M3
3.50 0.00 0.00 Lbr 0.00 Lbr
20.00 0.00 0.00 Batang 0.00 Batang

0.00
0.32 0.00 0.00 m3 0.00 m3
3.20 0.00 0.00 kg 0.00 kg
1.60 0.00 0.00 Liter 0.00 Liter
210.00 0.00 0.00 kg 0.00 kg
3.00 0.00 0.00 kg 0.00 kg
336.00 0.00 0.00 kg - kg/50kg
0.54 0.00 0.00 m3 0.00 m3
0.81 0.00 0.00 m3 0.00 m3
0.14 0.00 0.00 m3 0.00 m3
2.80 0.00 0.00 Lbr 0.00 Lbr
16.00 0.00 0.00 Batang 0.00 Batang

0.00
371.00 0.00 0.00 Kg - kg/50kg
698.00 0.00 0.00 Kg 0.00 m3
1047.00 0.00 0.00 Kg 0.00 m3
215.00 0.00 0.00 Liter 0.00 Liter

0.00
0.04 0.00 0.00 m3 0.00 m3
0.40 0.00 0.00 Kg 0.00 Kg
0.20 0.00 0.00 Liter 0.00 Liter
0.02 0.00 0.00 m3 0.00 m3
0.35 0.00 0.00 Lbr 0.00 Lbr
6.00 0.00 0.00 Batang 0.00 Batang

241.57
1.05 241.57 253.65 kg 253.65 kg
0.02 241.57 3.62 kg 3.62 kg

Err:509
371.00 Err:509 Err:509 kg Err:509 kg/50kg
698.00 Err:509 Err:509 kg Err:509 m3
1047.00 Err:509 Err:509 kg Err:509 m3
215.00 Err:509 Err:509 Liter Err:509 Liter

Err:509
0.04 Err:509 Err:509 m3 Err:509 m3
0.40 Err:509 Err:509 kg Err:509 kg
0.20 Err:509 Err:509 Liter Err:509 Liter
0.35 Err:509 Err:509 Lbr Err:509 Lbr
6.00 Err:509 Err:509 Batang Err:509 Batang

Err:509
1.05 Err:509 Err:509 kg Err:509 kg
0.02 Err:509 Err:509 kg Err:509 kg

0.00
1.10 0.00 0.00 m3 0.00 m3
15.00 0.00 0.00 Kg 0.00 Kg
5.60 0.00 0.00 Kg 0.00 Kg

0.00
1.10 0.00 0.00 m3 0.00 m3
15.00 0.00 0.00 Kg 0.00 Kg
3.00 0.00 0.00 Kg 0.00 Kg

0.00
0.01 0.00 0.00 m3 0.00 m3
0.00 0.00 0.00 m3 0.00 m3
0.25 0.00 0.00 kg 0.00 kg

0.00
12.00 0.00 0.00 Buah 0.00 Buah

0.00
4.00 0.00 0.00 Buah 0.00 Buah
8.00 0.00 0.00 Kg - kg/50kg
0.03 0.00 0.00 M3 0.00 M3

0.00
0.01 0.00 0.00 m3 0.00 m3
0.05 0.00 0.00 Kg 0.00 Kg

0.00
1.05 0.00 0.00 m 0.00 m
0.02 0.00 0.00 kg 0.00 kg
0.02 0.00 0.00 m3 0.00 m3

0.00
70.00 0.00 0.00 buah - buah
8.32 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 m3 0.00 m3

0.00
5.18 0.00 0.00 Kg - kg/50kg
0.03 0.00 0.00 m3 0.00 m3

0.00
3.25 0.00 0.00 Kg - kg/50kg

0.00
30.00 0.00 0.00 buah 0.00 buah
11.00 0.00 0.00 Kg 0.00 kg/50kg
0.04 0.00 0.00 m3 0.00 m3
0.00
1.10 0.00 0.00 m3 - m3
1.25 0.00 0.00 Kg - Kg
1.00 0.00 0.00 Kg - Kg

0.00
0.04 0.00 0.00 m3 - m3
0.50 0.00 0.00 Kg - Kg

0.00
0.02 0.00 0.00 m3 - m3
0.30 0.00 0.00 Kg - Kg

1.00 bh
1.00 1.00 1.00 bh 1.00 bh

0.00
0.02 0.00 0.00 m3 - m3
0.25 0.00 0.00 Kg - Kg

0.00
0.36 0.00 0.00 Lembar - Lembar
0.11 0.00 0.00 Kg - Kg

0.00
1.05 0.00 0.00 m' - m'
0.01 0.00 0.00 kg - kg

0.00
1.05 0.00 0.00 Dus - Dus
10.00 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3
0.00
1.05 0.00 0.00 Dus - Dus
10.40 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3

0.00
1.05 0.00 0.00 Dus - Dus
10.40 0.00 0.00 Kg - kg/50kg
0.05 0.00 0.00 Kg - Kg
0.50 0.00 0.00 m3 - m3

0.00
53.00 0.00 0.00 Buah - Buah
9.30 0.00 0.00 Kg - zak/50kg
0.02 0.00 0.00 m3 - m3
2.75 0.00 0.00 Kg - Kg

5.30 0.00 0.00 Buah - Buah


1.14 0.00 0.00 Kg - Kg
0.03 0.00 0.00 Kg - Kg
0.00 0.00 0.00 m3 - m3

14.00
3.00 14.00 42.00 btg 42.00 btg
10.00 14.00 140.00 m 140.00 m
2.00 14.00 28.00 Buah 28.00 Buah
2.00 14.00 28.00 Buah 28.00 Buah
3.00 14.00 42.00 Buah 42.00 Buah
24.00 14.00 336.00 Buah 336.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
1.00 14.00 14.00 Buah 14.00 Buah
pcs 11.00 pcs
pcs 3.00 pcs
pcs 5.00 pcs
pcs 1.00 pcs
pcs 1.00 pcs
pcs 5.00 pcs
pcs 3.00 pcs
1.00
3.00 1.00 3.00 btg 3.00 btg
15.00 1.00 15.00 m 15.00 m
1.00 1.00 1.00 Buah 1.00 Buah
2.00 1.00 2.00 Buah 2.00 Buah
24.00 1.00 24.00 Buah 24.00 Buah
1.00 1.00 1.00 Buah 1.00 Buah
2.00 1.00 2.00 Buah 2.00 Buah
pcs 1.00 pcs

1.20 36.84 44.21 m 44.21 m

1.20 20.49 24.58 m 24.58 m

1.20 20.32 24.38 m 24.38 m


pcs 1.00 pcs
Err:509 Err:509 Err:509
pcs 3.00 pcs
pcs 1.00 pcs
pcs 1.00 pcs
1.00
150.00 1.00 150.00 Buah 150.00 Buah
120.00 1.00 120.00 Kg 120.00 Kg
0.30 1.00 0.30 m3 0.30 m3
300.00 1.00 300.00 bh 300.00 bh
1.00
1.00 1.00 1.00 Unit 1.00 Unit
0.04 1.00 0.04 m2 0.04 m2
Err:509 Err:509 Err:509
Err:509 Err:509 Err:509
1.00
70.00 1.00 70.00 bh 70.00 bh
77.00 1.00 77.00 Kg 1.54 zak/50kg
0.13 1.00 0.13 M3 0.13 M3
0.09 1.00 0.09 M3 0.09 M3
0.02 1.00 0.02 M3 0.02 M3
2.60 1.00 2.60 Kg 2.60 Kg
0.00
0.10 0.00 0.00 Kg - Kg
0.10 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg

0.00
0.10 0.00 0.00 Kg - Kg
0.10 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg

0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr

0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr

0.00
0.20 0.00 0.00 Kg - Kg
0.15 0.00 0.00 Kg - Kg
0.17 0.00 0.00 Kg - Kg
0.26 0.00 0.00 Kg - Kg
0.01 0.00 0.00 Buah - Buah
0.03 0.00 0.00 Kg - Kg
0.20 0.00 0.00 Lbr - Lbr

0.00
1.10 0.00 0.00 m2 - lbr
0.05 0.00 0.00 Tube - Tube

0.00
1.10 0.00 0.00 m2 - lbr
0.05 0.00 0.00 Tube - Tube

1.00 0.00 0.00 bh - bh


1.00 0.00 0.00 bh - bh
1.00 0.00 0.00 bh - bh
1.00 0.00 0.00 bh - bh
1.00 0.00 0.00 bh - bh
KETERANGAN
j

249,600,000
KEBUTUHAN MATERIAL
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO MATERIAL VOLUME SATUAN KETERANGAN

1 Bata merah 220 pcs


2 Batu belah - m3
3 Batu Splite (2-3cm) Err:509 m3
4 Besi 8 btg
5 Besi 10 btg
6 Besi 12 btg
7 Kawat beton Err:509 kg
8 Besi Strip tebal 5 mm - kg
9 Cat dasar ( meni kayu ) - kg
10 Cat menie - kg
11 Cat Penutup Tembok - kg
12 Cat tembok / cat dasar - kg
13 Cat Warna ( Kayu ). - kg
14 Closet jongkok 1.00 pcs
15 Fitting 14.00 pcs
16 Floor Drain 1.00 pcs
17 Genteng bubung - pcs
18 Genteng palentong besar (morando) - pcs
19 Kabel 155 m'
20 Kaca tebal 5mm - lbr
21 Kaca tebal 7mm - lbr
22 Kayu Balok - Kusen - m3
23 Kayu Balok Rangka Atap - m3
24 Kayu Kaso 5 x 7 cm - m3
25 Kayu Kaso 5/7 cm - m3
26 Kayu Reng 2 x 3 cm - m3
27 Kayu Papan Jati - m3
28 Kayu Rawa Err:509 m3
29 Kayu Rawa 4/6 - m3
30 Kayu 5/7 (Rawa) - m3
31 Kayu Papan 3/20 (Rawa) - m3
32 Kayu Dolken Ø 8-10/400 cm Err:509 btg
33 Bambu diameter 6-8/600 cm - btg
34 Klem 336 bh
35 Klem biasa 24 bh
36 Kran Dinding 3.00 pcs
37 Kran Sink 1.00 pcs
38 Kran Wastafel - pcs
39 Kuas cat 3" - pcs
40 L Bow 30.00 pcs
41 Lampu Downlight 11.00 pcs
42 Lampu Fitting 3.00 pcs
43 Las Dop 42.00 pcs
44 Lem kayu - kg
45 Mangkok 14.00 pcs
KEBUTUHAN MATERIAL
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO MATERIAL VOLUME SATUAN KETERANGAN


46 MCB 1.00 pcs
47 MCCB (Boks MCB) 1.00 pcs
48 Meter Box PLN - pcs
49 Minyak Bekisting Err:509 liter
50 Paku - kg
51 Paku 7- 10 cm - kg
52 Paku 10 cm - kg
53 Paku 12 cm - kg
54 Paku 2"-3" - kg
55 Paku 5 - 12 cm Err:509 kg
56 Paku 5 dan 7 cm - kg
57 Paku Biasa - kg
58 Paku sekrup - kg
59 Papan gipsum 120x240 cm - lbr
60 Pasangan Kunci - pcs
61 Pasir Beton Err:509 m3
62 Pasir Pasang 0 m3
63 Pasir Urug Err:509 m3
64 Pemasangan Engsel Jendela - pcs
65 Pemasangan Engsel Pintu - pcs
66 Pemasangan Grendel Jendela - pcs
67 Pemasangan Kait Angin Jendela - pcs
68 Pengencer - Liter
69 Pintu Pvc 1.00 pcs
70 Pipa listrik 5/8" 45.00 m'
71 Pipa PVC 1” - m'
72 Pipa PVC 3” 24.38 m'
73 Pipa PVC 4” 24.58 m'
74 Plamur Kayu - kg
75 Plamur Tembok - kg
76 Plywood 9 mm uk. 120 x 240 mm Err:509 lbr
77 Porselen 11x11 300 pcs
78 Porslen - pcs
79 Saklar 14 pcs
80 Saklar Double 3 pcs
81 Saklar Single 5 pcs
82 Semen portland Err:509 zak
83 Semen warna - zak
84 Seng plat - lbr
85 Silicone Sealant 300 ml 1.00 tube
86 Stop Kontak 1 Lubang 5.00 pcs
87 Stop Kontak 2 Lubang 1.00 pcs
88 Stop Kontak 3 Lubang 1.00 pcs
89 T Dus 29.00 pcs
90 Tali ijuk - kg
91 Keramik 50 x 50 - dus
KEBUTUHAN MATERIAL
BANGUNAN : RUMAH 1 LANTAI
TYPE : RUMAH TYPE - 78 M2
LOKASI :-
PEMILIK :-
TAHUN : TAHUN 2022

NO MATERIAL VOLUME SATUAN KETERANGAN


92 Kramik 25 x 25 - dus
93 Kramik 20x20 - dus
92 Wastafel 1.00 pcs
VOLUME KEBUTUHAN BESI UNTUK ORDER MATERIAL

VOLUME BESI
NO ITEM PEKERJAAN
6 8
kg kg

1 Pek. Sloof - 142.74


2 Pek. Kolom 262.60
3 Pek. Ring Balk - 258.73
4 Pek. Plat Dak - -

- 664.06
Dalam Batang - 140

NO DIAMETER BESI VOLUME BESI SATUAN


kg kg

1 Besi Ø6 - btg
2 Besi Ø8 144 btg
3 Besi Ø10 33 btg
4 Besi Ø12 102 btg
ERIAL

VOLUME BESI
10 12
kg kg

- 294.35
- 760.30
239.15 -
- -

239.15 1,054.64
32 99

-
6,501,051.00
2,330,993.00
11,216,700.00
FORMAT VOLUME PEKERJAAN PONDASI FOO

DIMENSI
NO TYPE QTY
PANJANG LEBAR TINGGI BETON BEKISTING
mm mm mm m3 m2
x y h

0 - -

1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
15 - -
AAN PONDASI FOOTPLAT (CAKAR AYAM)

VOLUME
PASIR LANTAI PASIR BUANG URUGAN
BESI GALIAN
URUG KERJA URUG TANAH KEMBALI
kg m3 m3 m3 m3 m2 m2
(1/3xGalian)

- -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
INPUT PEMBESIAN
Selimut Tul Atas X Tul Bawah X Tul Atas Y Tul Bawah X
Dia jarak Dia jarak Dia jarak Dia jarak
mm mm mm mm mm mm mm mm mm

40 D16 150 16 100 13 200 13 150


VOLUME BESI PER DIAMETER

Tul Peminggang D6 D8 D10 D13 D16 D19 D22 D25


Dia qty
mm pcs kg kg kg kg kg kg kg kg

- - - - - - - -

10 2 - - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
D29 D32 Tul Atas-X Tul Bawah-X
dia panjang jarak qty berat dia panjang jarak
kg kg mm mm mm kg mm mm mm

- -

- - D16 (240) 150 1 - D16 (240) 100


- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
- - D0 - - 0 - D0 - -
HITUNGAN PEMBESIAN

ul Bawah-X Tul Atas-Y Tul Bawah-Y


qty berat dia panjang jarak qty berat dia panjang jarak
kg mm mm mm kg mm mm mm

1 - D13 (240) 200 1 - D13 (240) 150


0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
0 - D0 - - 0 - - -
ul Bawah-Y Tul Peminggang
qty berat dia panjang jarak qty berat
kg mm mm mm kg

1 - D10 400 2 -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
NAMA PROYEK :
JENIS PEKERJAAN :
KET LANTAI :

Data Balok

Ket As / Type
No Ket Lebar Tinggi Panjang Qty
Kode Balok
mm mm mm mm

1 Sloof Arah Hor SLF 150 200 79650 1


2 Sloof Arah Hor SLF
3 Sloof Arah Hor SLF
4 Sloof Arah Hor SLF
5 Sloof Arah Hor SLF
6 Sloof Arah Hor SLF
7 Sloof Arah Hor SLF
8 Sloof Arah Ver SLF
9 Sloof Arah Ver SLF
10 Sloof Arah Ver SLF
11 Sloof Arah Ver SLF
12 Sloof Arah Ver SLF

1 Ring Balk All RB.1 120 150 69800 1


2 Ring Balk All RB.2 120 150 14030 1
3 Ring Balk All RB.3 120 150 9850 1
4 Ring Balk All BG 120 120 41170 1
5 Ring Balk All BL 120 120 4500 1
6
7
8
9
10
11
12
13
14
14
15
Volume
Selimut Tul Utama Atas
Tebal Bekisting Bekisting Beton
Beton Besi
Plat Bawah Samping Dia Kanan Tengah

mm m3 m2 m2 kg mm mm qty qty

182.9177 4 5 6 7
2.39 11.95 31.86 437.08

0 2.39 11.95 31.86 437.08 ### 25 12 2 2


0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -
0 - - - -

2.34 16.72 39.06 497.88

0 1.26 8.38 20.94 273.48 25 10 2 2


0 0.25 1.68 4.21 55.72 25 10 2 2
0 0.18 1.18 2.96 38.71 25 10 2 2
0 0.59 4.94 9.88 116.87 25 8 2 2
0 0.06 0.54 1.08 13.11 25 8 2 2
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
RUMUS PERHITUNGAN PEMB

Data Pembesian
ama Atas Tul Utama Bawah Begel
Kiri Dia Kanan Tengah Kiri Dia N Kanan Tengah Kiri

qty dia qty qty qty mm qty jarak jarak jarak

8 9 10 11 12 13 14 15 16 17

2 12 2 2 2 8 1 150 150 150

2 10 2 2 2 8 1 150 150 150


2 10 2 2 2 8 1 150 150 150
2 10 2 2 2 8 1 150 150 150
2 8 2 2 2 8 1 150 150 150
2 8 2 2 2 8 1 150 150 150
HITUNGAN PEMBESIAN BALOK

Detail Hitungan dan Rumus Pembesian


Tulangan Utama Atas Tulangan Utama Bawah
pjg Pjg pjg
Dia Laping qty berat Dia Laping Pjg Total qty
murni Total murni
mm mm mm qty mm kg mm mm mm qty mm

D12 80010 480 6 82890 2 147.17 D12 80010 480 6 82890 2


D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0

D10 70100 400 5 72100 2 88.90 D10 70100 400 5 72100 2


D10 14330 400 1 14730 2 18.16 D10 14330 400 1 14730 2
D10 10150 0 0 10150 2 12.51 D10 10150 0 0 10150 2
D8 41410 320 3 42370 2 33.44 D8 41410 320 3 42370 2
D8 4740 0 0 4740 2 3.74 D8 4740 0 0 4740 2
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
D0 0 0 0 0 0 0.00 D0 0 0 0 0 0
BERAT BESI PER DIAMTER TUJUANNYA

embesian
Volume Besi
awah Tul Begel

berat Dia panjang qty berat 6 8 10 12

kg mm mm kg kg kg kg kg

0.00 142.74 0.00 294.35

147.17 D8 680 532 142.74 - 142.74 - 294.35


0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -

0.00 258.73 239.15 0.00

88.90 D8 520 466 95.68 - 95.68 177.80 -


18.16 D8 520 95 19.40 - 19.40 36.32 -
12.51 D8 520 67 13.68 - 13.68 25.03 -
33.44 D8 460 275 50.00 - 116.87 - -
3.74 D8 460 31 5.63 - 13.11 - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -
0.00 D0 0 0 0.00 - - - -

0.00 401.46 239.15 294.35


0 85 32 28
55 32
DIAMTER TUJUANNYA UNTUK ORDER MATERIAL BESI BETON

Volume Besi per Diamter

D13 D16 D19 D22 D25 D29 D32 D40

kg kg kg kg kg kg kg kg

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0 0 0 0 0 0 0 0
437.08 437.08 0.00

497.88 497.88 0.00


DETAIL HITUNGAN VOLUME PEKERJAAN KOLOM

DIMENSI VOLUME INPUT PEMBESIAN


TYPE
NO KET LANTAI QTY
KOLOM PANJANG LEBAR TINGGI BESI Tul Utama Tul Sengkang
Selimut
Beton jarak Jarak
mm mm mm kg Penjang Laping Dia qty Dia
Tump Lap
karan

1,022.90

1 Lantai 1 KP 150 150 3850 23 510.55 25 144 - 12 4 8 100 150


2 Lantai 1 KP 150 150 3350 3 137.37 25 144 - 12 4 8 100 150
3 Lantai 1 KP 150 150 3150 3 129.81 25 144 - 12 4 8 100 150
4 Lantai 1 KP 150 150 600 2 22.21 25 144 - 12 4 8 100 150
5 Lantai 1 KP 150 150 663 4 47.60 25 144 - 12 4 8 100 150
6 Lantai 1 KG 150 150 2500 5 175.35 25 144 - 12 4 8 100 150

Note : Tex Merah bisa di edit (di input)


INPUT DATA DIMENSI

Dimensi
Tebal
No Type Plat Luas Berat
Plat X Y Arah X
dia. pjg
mm mm mm m2 kg mm' mm'
0 1 2 3 4 5 6

241.57
1 PL-1 100 1425 3,650 5.20 93.43 10 1,425
2 PL-2 120 1675 3950 6.62 114.45 10 1,675
3 PL-3 100 450 1600 0.72 14.65 10 450
4 PL-3 100 450 2150 0.97 19.04 10 450
5 - - - -
6 - - - -
7 - - - -
8 - - - -
9 - - - -
10 - - - -
11 - - - -
DETAIL HITUNGAN PEMBESIAN
Tul Utama Atas Tul Utama Bawa
Arah X Arah Y Arah X
qty berat dia. pjg qty berat dia. pjg qty
mm' kg mm' mm' mm' kg mm' mm' mm'

25 21.96 10 3,650 11 24.75 10 1,425 25


27 27.88 10 3,950 12 29.22 10 1,685 27
12 3.33 10 1,600 4 3.95 10 460 12
15 4.16 10 2,150 4 5.30 10 460 15
0 - - - 0 - - - 0
0 - - - 0 - - - 0
0 - - - 0 - - - 0
0 - - - 0 - - - 0
0 - - - 0 - - - 0
0 - - - 0 - - - 0
0 - - - 0 - - - 0
VOLUME BESI BETON PER
Tul Utama Bawah 6 8 10 12
hX Arah Y
berat dia. pjg qty berat
kg mm' mm' mm' kg kg kg kg kg

- -
21.96 10 3,650 11 24.75 - - 93.43 -
28.05 10 3,960 12 29.30 - - 114.45 -
3.40 10 1,610 4 3.97 - - 14.65 -
4.25 10 2,160 4 5.33 - - 19.04 -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
- - - 0 - - - - -
LUME BESI BETON PER DIAMTER
13 16 19 22 25

kg kg kg kg kg

- - - - - 93.43 93.43 -
- - - - - 114.45 114.45 -
- - - - - 14.65 14.65 -
- - - - - 19.04 19.04 -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
VOLUME STRUKTUR TANGGA

DIMENSI

Dimensi Jumlah Juml


Type ah
P (m) L (m) T (m) Tang
ga

TANGGA Type 1, Lt GF - Lt 2
Bordes A 2.70 1.40 0.15 1 1
1 1
1 1
1 1
1 1

Bordes B 2.70 2.50 0.15 1 1


1 1
1 1
1 1
1 1

Anak Tangga 1.4 0.33 0.18 12 1


12 1
12 1

Plat Tangga 2.0 1.4 0.15 2 1


2 1
2 1

Kolom K5 0.4 0.2 2.2 2 1


2 1
2 1
2 1

Kolom K5 0.4 0.2 1.1 1 1


1 1
1 1
1 1

Balok 200x300 2.7 0.2 0.3 3 1


3 1
3 1

Balok 300x500 0.9 0.3 0.5 1 1


1 1
1 1

Balok 300x500 2.1 0.3 0.5 1 1


1 1
1 1

TANGGA Type 1, Lt GF - Lt 2
DETAIL PEMBESIAN
Selimut Jarak Jumlah
Nama Tulangan Dia Kg/m
Beton Tulangan Tulangan

Tul Atas Arah X (Panjang) 0.04 D 10 0.62 0.15 11


Tul Bawah Arah X (Panjang) 0.04 D 10 0.62 0.15 11
Tul Atas Arah Y (Lebar) 0.04 D 13 1.04 0.15 19
Tul Atas Bawah Arah Y (Lebar) 0.04 D 13 1.04 0.15 19

Tul Atas Arah X (Panjang) 0.04 D 10 0.62 0.15 18


Tul Bawah Arah X (Panjang) 0.04 D 10 0.62 0.15 18
Tul Atas Arah Y (Lebar) 0.04 D 13 1.04 0.15 19
Tul Atas Bawah Arah Y (Lebar) 0.04 D 13 1.04 0.15 19

Tul Atas Arah X (Panjang) 0.04 D 13 1.04 0.15 20


Tul Atas Arah Y (Lebar) 0.04 D 10 0.62 0.15 30

Tul Utama 0.04 16 1.58 4


Tul Sengkang Tump 0.04 10 0.62 0.10 12
Tul Sengkang Lap 0.04 10 0.62 0.20 7

Tul Utama 0.04 16 1.58 4


Tul Sengkang Tump 0.04 10 0.62 0.10 7
Tul Sengkang Lap 0.04 10 0.62 0.20 4

Tul Utama 0.04 16 1.58 6


Tul Sengkang 0.04 10 0.62 0.10 28

Tul Utama 0.04 19 2.23 10


Tul Sengkang 0.04 13 1.04 0.10 10

Tul Utama 0.04 19 2.23 11


Tul Sengkang 0.04 13 1.04 0.10 22
ETAIL PEMBESIAN
Panjang Tulangan Berat Vol Total
Panjang Tekukan Kait Besi Ld Panjang Besi Besi
Murni (40d) Total (Kg) (Kg)

x2 kiri kanan 128.29 128.29


2.6 0.30 2.92 19.80 19.80
2.6 0.30 2.92 19.80 19.80
1.3 0.40 0.52 2.24 44.34 44.34
1.3 0.40 0.52 2.24 44.34 44.34
ke arah balok ke arah plat tangga
x2 kiri kanan 197.04 197.04
2.6 0.30 2.92 32.40 32.40
2.6 0.30 2.92 32.40 32.40
2.4 0.40 0.52 3.34 66.12 66.12
2.4 0.40 0.52 3.34 66.12 66.12
ke arah balok ke arah plat tangga

200.15 200.15
1.9 0.52 0.52 3.48 145.03 145.03
1.3 0.11 1.49 55.12 55.12
ke arah bordes
58.58 58.58
2.5 0.19 2.65 33.48 33.48
1.0 0.06 1.10 16.28 16.28
1.0 0.06 1.10 8.82 8.82

16.75 16.75
1.4 0.19 1.55 9.80 9.80
1.0 0.06 1.10 4.41 4.41
1.0 0.06 1.10 2.54 2.54

136.91 136.91
2.7 0.52 3.19 90.74 90.74
0.8 0.06 0.90 46.17 46.17

57.69 57.69
0.9 0.92 1.86 41.31 41.31
1.4 0.08 1.52 16.39 16.39

110.10 110.10
2.1 0.92 3.05 74.77 74.77
1.4 0.08 1.52 35.33 35.33
Besi Beton ( kg )
8 10 13 16 19 22
D8 D10 D13 D16 D19 D22

0.00 19.80 0.00 0.00 0.00 0.00


0.00 19.80 0.00 0.00 0.00 0.00
0.00 0.00 44.34 0.00 0.00 0.00
0.00 0.00 44.34 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00

0.00 32.40 0.00 0.00 0.00 0.00


0.00 32.40 0.00 0.00 0.00 0.00
0.00 0.00 66.12 0.00 0.00 0.00
0.00 0.00 66.12 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 145.03 0.00 0.00 0.00


0.00 55.12 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 33.48 0.00 0.00
0.00 16.28 0.00 0.00 0.00 0.00
0.00 8.82 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 9.80 0.00 0.00
0.00 4.41 0.00 0.00 0.00 0.00
0.00 2.54 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 90.74 0.00 0.00
0.00 46.17 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 41.31 0.00
0.00 0.00 16.39 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 74.77 0.00
0.00 0.00 35.33 0.00 0.00 0.00

- 237.74 417.67 134.02 116.07 -


25 29 32
D25 D8 D32

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

- - - 905.50
-
VOLUME PERHITUNGAN BESI PROFIL ( BAJA )

Berat Jenis Panjang Qty


No Item Pekerjaan Jenis Baja
kg/m3 m
Berat total
kg
PERHITUNGAN VOLUME KAYU

PEK. KONTRUKSI KUDA-KUDA KAYU


NO NAMA ITEM UKURAN KAYU PANJANG QTY
mm

1 Kuda-Kuda A Kaki Kuda-Kuda 8/12 3620 1


2 Kuda-Kuda A Balok Tarik 8/12 2120 2
3 Kuda-Kuda A Balok Pengerat 5/10 878 2
4 Kuda-Kuda A Balok Gantung 8/12 1570 1
5 Kuda-Kuda A Balok Gapit 5/10 1745 2
6
7 Kuda-Kuda B Kaki Kuda-Kuda 8/12 2265 1
8 Kuda-Kuda B Balok Tarik 8/12 2380 1
9 Kuda-Kuda B Balok Pengerat 5/10 1017 1
10 Kuda-Kuda B Balok Gapit 5/10 958 2

8/12
5/10
Note : Kebutuhan Kayu 8/12 Panjang 3 meter 6 btg
Kebutuhan Kayu 6/12 Panjang 3 meter 4 btg

PEK. KONTRUKSI ATAP (GORDING, NOK, MURPLAT DLL)


NO NAMA ITEM UKURAN KAYU PANJANG QTY
mm

1 Murplat Balok Murplat 8/12 19051 1


2 Gording Balok Gording 6/12 31512 1
3 Nok Balok Nok 6/12 18081 1
4 Penyangga Balok Penyangga 6/12 3908 1
5
6
7
8
9
10

8/12
6/12
Note : Kebutuhan Kayu 8/12 Panjang 3 meter 7 btg
Kebutuhan Kayu 6/12 Panjang 3 meter 19 btg

PEK. USUK & RENG KAYU


NO ITEM UKURAN KAYU PANJANG QTY
mm

1
2
3
4

1
2
3
4

4/6
2/3
Note : Kebutuhan Kaso Kayu 4/6 Panjang 3 meter - btg
Kebutuhan Reng Kayu 2/3 Panjang 3 meter 0 btg
PANJANG
TOTAL
mm

3,620
4,240
1,756
1,570
3,490
-
2,265
2,380
1,017
1,916

14,075
8,179

PANJANG
TOTAL
mm

19,051
31,512
18,081
3,908
-
-
-
-
-
-

19,051
53,501
PANJANG
TOTAL
mm

-
-
-
-
-
-
-
-
-

-
-
-
-
LIST MATERIAL

NO NAMA MATERIAL SATUAN HARGA

1 Semen Biasa zak/50kg


2 Semen Warna zak/50kg
3 Pasir Cor m3
4 Pasir Urug m3
5 Besi 6 btg/12m
6 Besi 8 btg/12m
7 Besi 10 btg/12m
8 Besi 12 btg/12m
9 Batu Split m3
10 Polywood 9mm lbr
11 Kayu Dolken btg/4m
12 Keramik 40 x 40 dus
13 Keramik 20 x 20 (KM) dus
14 Cat Interior kaleng
15 Cat Exterior kaleng
16 Genteng Coklat Tua pcs
17 Kayu Usuk 5/7 btg
18 Kayu Reng 2/3 btg
19
20
21
22
23
Jumlah Waktu harga total
6 60 150,000 54,000,000
4 60 100,000 24,000,000
1 60 100,000 6,000,000

84,000,000

Anda mungkin juga menyukai