REKAPITULASI

RAP PAUD DAYCARE


No. URAIAN PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN Rp 45,380,672.82
II PEKERJAAN TANAH Rp 22,348,859.00
III PEKERJAAN STRUKTUR Rp 363,661,000.00
IV PEKERJAAN PASANGAN DINDING Rp 423,450,912.96
VI PEK. LANTAI & DINDING KERAMIK Rp 142,310,215.52
VII PEKERJAAN PINTU DAN JENDELA Rp 396,567,572.75
IX PEKERJAAN INSTALASI LISTRIK Rp 22,731,820.92
X PEKERJAAN SANITASI Rp 88,544,907.00
XI PEKERJAAN PENGECATAN Rp 27,938,066.00
XII PEKERJAAN ATAP Rp 45,767,208.26
XIII PEKERJAAN SECONDARY SKIN,CANOPY DAN TANGGA BESI Rp 423,082,900.00
XV PEKERJAAN PEMBERSIHAN Rp 6,500,000.00

TOTAL BIAYA Rp 2,008,284,135.22


A.2 BIAYA BANGUNAN
Dibulatkan Rp 2,008,000,000.00
Terbilang: Satu Milyar Delapan Ratus Lima Puluh Satu Juta Rupiah
2 LUAS BANGUNAN 300.00 m2
RENCANA ANGGARAN BIAYA ( RAB )
DAYCARE
VOLUME BIAYA BANGUNAN

HARGA SATUAN MATERIAL JUMLAH HARGA


No. URAIAN PEKERJAAN SAT. VOLUME
(Rp)
(Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan & Pengukuran kav. Ls 1.00 Rp 6,500,000.00 Rp 6,500,000.00
3 Pas. Bouwplank m' 53.90 Rp 110,123.80 Rp 5,935,672.82
5 Kantor dan Gudang Sementara
- Direksi Keet m2 12.00 Rp 585,000.00 Rp 7,020,000.00
- Gudang Sementara dan Los kerja dilapangan m2 6.00 Rp 487,500.00 Rp 2,925,000.00
6 Air Kerja (instalasi, Pompa, tangki, dll) Ls 1.00 Rp 6,500,000.00 Rp 6,500,000.00
7 Listrik kerja Ls 1.00 Rp 1,500,000.00 Rp 1,500,000.00
9 Pekerjaan pagar sementara Ls 1.00 Rp 15,000,000.00 Rp 15,000,000.00

Rp 45,380,672.82
II PEKERJAAN TANAH
1 Pek. Galian Pondasi Garis m3 38.64 Rp 125,000.00 Rp 4,829,600.00
2 Pek. Galian Tanah Pondasi Poer m3 60.75 Rp 135,000.00 Rp 8,201,250.00
3 Pek. Urugan Kembali Galian m3 24.85 Rp 165,000.00 Rp 4,099,705.50
4 Pek. Urugan Pasir Bawah Pondasi Poer tebal 5cm m3 20.25 Rp 257,694.00 Rp 5,218,303.50

Rp 22,348,859.00
III PEKERJAAN STRUKTUR
1 Pek. Pondasi Poer 150/150/25 m3 10.13 Rp 3,250,000.00 Rp 32,906,250.00
2 Pek. Sloof S1 20/40 (Beton K 225) m3 4.83 Rp 2,500,000.00 Rp 12,074,000.00
3 Pek. Sloof S2 20/30 (Beton K 250) m3 2.45 Rp 2,500,000.00 Rp 6,124,500.00
4 Pek. Sloof 15/20 (Beton K 250) m3 0.17 Rp 2,500,000.00 Rp 412,500.00
5 Pek. K1 Baja IWF 350 x 175 mm dan perakitan btg 9.00 Rp 12,000,000.00 Rp 108,000,000.00
6 Pek. K2 Baja IWF 300 x 150 mm dan perakitan btg 2.00 Rp 8,500,000.00 Rp 17,000,000.00
7 Pek. K3 Baja IWF 200 x 100 mm dan perakitan btg 2.00 Rp 4,500,000.00 Rp 9,000,000.00
8 Pek. B1 Baja IWF 300 x 150 mm dan perakitan btg 5.00 Rp 8,500,000.00 Rp 42,500,000.00
9 Pek. B2 Baja IWF 250 x 125 mm dan perakitan btg 2.00 Rp 6,500,000.00 Rp 13,000,000.00
10 Pek. B3 Baja IWF 200x 100 mm dan perakitan btg 7.00 Rp 4,500,000.00 Rp 31,500,000.00
11 Pek. B3 Baja IWF 150x 7.5 mm dan perakitan btg 5.00 Rp 3,500,000.00 Rp 17,500,000.00
12 Pek. Kolom Praktis 15/15 Beton K225) m3 0.95 Rp 2,500,000.00 Rp 2,362,500.00
13 Pek. Plat Lantai CITICON m3 27.50 Rp 2,500,000.00 Rp 68,750,000.00
14 Pek. Lantai Kerja Pondasi Poer Teb. 5 cm m3 2.03 Rp 1,250,000.00 Rp 2,531,250.00

Rp 363,661,000.00
IV PEKERJAAN PASANGAN DINDING
LANTAI 1
1 Pek. Pas. Batu Bata Dinding Bata Ringan m2 203.18 Rp 185,000.00 Rp 37,587,375.00
2 Pek. Plesteran Dinding 1:4 m3 406.35 Rp 95,000.00 Rp 38,603,250.00
3 Pek. Acian Dinding MU 200 tebal 1,5 mm m4 406.35 Rp 60,000.00 Rp 24,381,000.00
4 Pek. Pas. Partisi Kaca tebal 5 mm m2 12.60 Rp 450,000.00 Rp 5,670,000.00
5 Pek. Pas. Frame Aluminium Partisi Kaca m' 16.75 Rp 185,000.00 Rp 3,098,750.00
6 Pek. Dinding Sandwich Panel & Pemasangan m2 127.05 Rp 396,290.50 Rp 50,348,708.03
7 Pekerjaan Roster m3 10.63 Rp 430,000.00 Rp 4,568,750.00

LANTAI 2
1 Pek. Dinding Sandwich Panel & Pemasangan m2 263.55 Rp 396,290.50 Rp 104,442,361.28
2 Pekerjaan Roster m2 20.13 Rp 430,000.00 Rp 8,653,750.00

LANTAI 3
1 Pek. Dinding Sandwich Panel m2 118.83 Rp 396,290.50 Rp 47,089,218.66
2 Pek. Pas. Frame Aluminium Dinding Kaca m' 222.90 Rp 185,000.00 Rp 41,236,500.00
3 Pek. Pas. Partisi Kaca tebal 5 mm m2 109.15 Rp 450,000.00 Rp 49,117,500.00
4 Pekerjaan Roster m2 20.13 Rp 430,000.00 Rp 8,653,750.00

Rp 423,450,912.96
VI PEK. LANTAI & DINDING KERAMIK
LANTAI 1
1 Pek. Beton Lantai Kerja tebal 3 cm m3 2.92 Rp 1,239,343.11 Rp 3,619,501.57
2 Pek. Pasir Pasang Bawah Lantai tebal 10 cm m3 9.74 Rp 257,694.00 Rp 2,508,651.09
3 Pek. Lantai Granit 60/60 (Polished Finish) m2 88.35 Rp 294,930.48 Rp 26,057,107.91
5 Pek. Lantai Keramik KM 30x30 m2 9.00 Rp 269,762.65 Rp 2,427,863.89
6 Pek. Dinding Keramik KM 30/60 tinggi 150 cm m2 60.00 Rp 388,307.76 Rp 23,298,465.60
HARGA SATUAN MATERIAL JUMLAH HARGA
No. URAIAN PEKERJAAN SAT. VOLUME
(Rp)
(Rp)
1 2 3 4 5 6

LANTAI 2
HARGA SATUAN MATERIAL JUMLAH HARGA
No. URAIAN PEKERJAAN SAT. VOLUME
(Rp)
(Rp)
1 2 3 4 5 6
1 Pek. Beton Lantai Kerja tebal 3 cm m3 2.99 Rp 1,239,343.11 Rp 3,701,298.21
2 Pek. Lantai Granit 60/60 (Polished Finish) m2 90.00 Rp 294,930.48 Rp 26,543,743.20
4 Pek. Lantai Keramik KM 30x30 m2 5.80 Rp 269,762.65 Rp 1,564,623.40
5 Pek. Dinding Keramik KM 30/60 tinggi 150 cm m2 38.00 Rp 388,307.76 Rp 14,755,694.88

LANTAI 3
1 Pek. Beton Lantai Kerja tebal 3 cm m3 2.99 Rp 1,239,343.11 Rp 3,701,298.21
2 Pek. Lantai Granit 60/60 (Polished Finish) m2 95.00 Rp 294,930.48 Rp 28,018,395.60
4 Pek. Lantai Keramik KM 30x30 m2 3.00 Rp 269,762.65 Rp 809,287.96
5 Pek. Dinding Keramik KM 30/60 tinggi 150 cm m2 13.66 Rp 388,307.76 Rp 5,304,284.00

Rp 142,310,215.52
VII PEKERJAAN PINTU DAN JENDELA
ARSITEKTUR LT.1 ,LT.2 & LT.3
P1 - Pintu Kaca Frameless dengan Kaca Tempered 12 mm Uk 140 cm x 240 cm x 10
3 Unit 2.00 Rp 18,030,768.00 Rp 36,061,536.00
mm, termasuk Push&Pull Handle, Floor Hinge (hardware ex.Dekson)

P4 - Pintu Panel Aluminium + Frame Aluminium Powder Coating putih Uk 80 cm x 240 cm


4 Unit 19.00 Rp 4,547,250.00 Rp 86,397,750.00
x 10 cm, Termasuk Push and Pull Handle, Floor Hinge (Hardwere ex Dekson)

J1 - Jendela kaca Tipe Fixed Window + Frame Alum Powder Coating putih 160cm x
6 Unit 11.00 Rp 16,499,906.25 Rp 181,498,968.75
220cm x 10 cm, termasuk Push & Pull Handle, Floor Hinge (hardware ex.Dekson)

J2 - Jendela kaca Tipe Fixed Window + Frame Alum Powder Coating putih 160cm x
7 Unit 4.00 Rp 14,882,437.50 Rp 59,529,750.00
160cm x 10 cm, termasuk Push & Pull Handle, Floor Hinge (hardware ex.Dekson)

J3 - Jendela kaca Tipe Swing Window + Frame Alum Powder Coating putih 100cm x
9 Unit 4.00 Rp 3,269,892.00 Rp 13,079,568.00
240cm x 10 cm, termasuk Push & Pull Handle, Floor Hinge (hardware ex.Dekson)

11 V1 - Ventilasi Kaca Uk 60 x 50 cm Unit 8.00 Rp 2,500,000.00 Rp 20,000,000.00

Rp 396,567,572.75
IX PEKERJAAN INSTALASI LISTRIK
LANTAI 1
1 Instalasi Titik Lampu YC945 NEW DOWNLIGHT OUTBOW Titik 16.00 Rp 350,000.00 Rp 5,600,000.00
2 Instalasi Titik Lampu TL Titik 10.00 Rp 250,000.00 Rp 2,500,000.00
5 Pas. Stop Kontak Panasonic Bh 10.00 Rp 67,300.59 Rp 673,005.90
6 Pas. Saklar Ganda Panasonic Bh 10.00 Rp 78,072.00 Rp 780,720.00
7 Pas. Saklar Tunggal Panasonic Bh 5.00 Rp 59,297.10 Rp 296,485.50
8 Pas. Mcb Bh 1.00 Rp 252,935.61 Rp 252,935.61
9 Pas. Kotak Mcb Bh 1.00 Rp 88,761.75 Rp 88,761.75
10 Pas. Arde Bh 1.00 Rp 203,216.31 Rp 203,216.31

LANTAI 2
1 Instalasi Titik Lampu YC945 NEW DOWNLIGHT OUTBOW Titik 13.00 Rp 350,000.00 Rp 4,550,000.00
2 Instalasi Titik Lampu TL Titik 4.00 Rp 250,000.00 Rp 1,000,000.00
4 Pas. Stop Kontak Panasonic Bh 7.00 Rp 67,300.59 Rp 471,104.13
5 Pas. Saklar Ganda Panasonic Bh 2.00 Rp 78,072.00 Rp 156,144.00
6 Pas. Saklar Tunggal Panasonic Bh 5.00 Rp 59,297.10 Rp 296,485.50

LANTAI 3
1 Instalasi Titik Lampu YC945 NEW DOWNLIGHT OUTBOW Titik 12.00 Rp 350,000.00 Rp 4,200,000.00
2 Instalasi Titik Lampu TL Titik 3.00 Rp 250,000.00 Rp 750,000.00
4 Pas. Stop Kontak Panasonic Bh 8.00 Rp 67,300.59 Rp 538,404.72
5 Pas. Saklar Ganda Panasonic Bh 1.00 Rp 78,072.00 Rp 78,072.00
6 Pas. Saklar Tunggal Panasonic Bh 5.00 Rp 59,297.10 Rp 296,485.50

Rp 22,731,820.92
X PEKERJAAN SANITASI
LANTAI 1
1 Pas. Kloset Duduk ex. Toto Bh 4.00 Rp 2,716,330.00 Rp 10,865,320.00
2 Portable potty seat for kids with stairs Bh 3.00 Rp 660,000.00 Rp 1,980,000.00
3 Pas. Washtafelex. Toto Bh 8.00 Rp 1,643,185.50 Rp 13,145,484.00
4 Pas. Keran Air Bh 5.00 Rp 111,064.60 Rp 555,323.00
5 Pas. Floor Drain Bh 4.00 Rp 60,463.00 Rp 241,852.00
6 Pas. Pipa Galvanis 3/4'' Ls 1.00 Rp 1,800,000.00 Rp 1,800,000.00
7 Pas. Pipa PVC dia. 3” (Air Bekas) Ls 1.00 Rp 1,905,300.00 Rp 1,905,300.00
8 Pas. Pipa PVC dia. 4” (Air Kotor) Ls 1.00 Rp 2,009,700.00 Rp 2,009,700.00
9 Pas. Samb. Pipa PVC dia. 3/4'' Elbow Ls 1.00 Rp 1,174,500.00 Rp 1,174,500.00
10 Pas. Samb. Pipa PVC dia. 3/4'' Tee Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
HARGA SATUAN MATERIAL JUMLAH HARGA
No. URAIAN PEKERJAAN SAT. VOLUME
(Rp)
(Rp)
1 2 3 4 5 6
11 Pas. Samb. Pipa PVC dia. 3” Elbow Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
12 Pas. Samb. Pipa PVC dia. 3” Tee Ls 1.00 Rp 652,500.00 Rp 652,500.00
13 Lem Pipa Ls 1.00 Rp 1,435,500.00 Rp 1,435,500.00
HARGA SATUAN MATERIAL JUMLAH HARGA
No. URAIAN PEKERJAAN SAT. VOLUME
(Rp)
(Rp)
1 2 3 4 5 6

LANTAI 2
1 Pas. Kloset Duduk ex. Toto Bh 3.00 Rp 2,716,330.00 Rp 8,148,990.00
2 Portable potty seat for kids with stairs Bh 3.00 Rp 660,000.00 Rp 1,980,000.00
3 Pas. Washtafelex. Toto Bh 5.00 Rp 1,643,185.50 Rp 8,215,927.50
4 Pas. Keran Air Bh 5.00 Rp 111,064.60 Rp 555,323.00
5 Pas. Floor Drain Bh 5.00 Rp 60,463.00 Rp 302,315.00
6 Pas. Pipa Galvanis 3/4'' Ls 1.00 Rp 1,800,000.00 Rp 1,800,000.00
7 Pas. Pipa PVC dia. 3” (Air Bekas) Ls 1.00 Rp 1,905,300.00 Rp 1,905,300.00
8 Pas. Pipa PVC dia. 4” (Air Kotor) Ls 1.00 Rp 2,009,700.00 Rp 2,009,700.00
9 Pas. Samb. Pipa PVC dia. 3/4'' Elbow Ls 1.00 Rp 1,174,500.00 Rp 1,174,500.00
10 Pas. Samb. Pipa PVC dia. 3/4'' Tee Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
11 Pas. Samb. Pipa PVC dia. 3” Elbow Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
12 Pas. Samb. Pipa PVC dia. 3” Tee Ls 1.00 Rp 652,500.00 Rp 652,500.00
13 Lem Pipa Ls 1.00 Rp 1,435,500.00 Rp 1,435,500.00

LANTAI 3
1 Pas. Kloset Duduk ex. Toto Bh 1.00 Rp 2,716,330.00 Rp 2,716,330.00
3 Pas. Washtafelex. Toto Bh 3.00 Rp 1,643,185.50 Rp 4,929,556.50
4 Pas. Keran Air Bh 5.00 Rp 111,064.60 Rp 555,323.00
5 Pas. Floor Drain Bh 1.00 Rp 60,463.00 Rp 60,463.00
6 Pas. Pipa Galvanis 3/4'' Ls 1.00 Rp 1,800,000.00 Rp 1,800,000.00
7 Pas. Pipa PVC dia. 3” (Air Bekas) Ls 1.00 Rp 1,905,300.00 Rp 1,905,300.00
8 Pas. Pipa PVC dia. 4” (Air Kotor) Ls 1.00 Rp 2,009,700.00 Rp 2,009,700.00
9 Pas. Samb. Pipa PVC dia. 3/4'' Elbow Ls 1.00 Rp 1,174,500.00 Rp 1,174,500.00
10 Pas. Samb. Pipa PVC dia. 3/4'' Tee Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
11 Pas. Samb. Pipa PVC dia. 3” Elbow Ls 1.00 Rp 1,226,700.00 Rp 1,226,700.00
12 Pas. Samb. Pipa PVC dia. 3” Tee Ls 1.00 Rp 652,500.00 Rp 652,500.00
13 Lem Pipa Ls 1.00 Rp 1,435,500.00 Rp 1,435,500.00

Rp 88,544,907.00
XI PEKERJAAN PENGECATAN
LANTAI 1
1 Pek. Cat Tembok m2 406.35 Rp 68,753.70 Rp 27,938,066.00

Rp 27,938,066.00
XII PEKERJAAN ATAP
1 Pek. Rangka Atap m2 98.00 Rp 212,010.18 Rp 20,776,997.40
2 Pas. Atap Genteng
a Pas. Genteng Metal m2 98.00 Rp 216,334.95 Rp 21,200,825.10
b Pas. Bubungan Genteng m' 8.80 Rp 181,335.05 Rp 1,595,748.44
4 Pek. Plat Atap Beton Tebal 12 cm m3 1.77 Rp 1,239,343.11 Rp 2,193,637.31

Rp 45,767,208.26
XII PEKERJAAN SECONDARY SKIN,CANOPY DAN TANGGA BESI
1 Pek. Partisi Hollow Stips Area Tangga Tinggi 250 cm m' 300.00 Rp 777,828.00 Rp 233,348,400.00
2 Pel. Pergola Tangga m2 15.00 Rp 1,065,300.00 Rp 15,979,500.00
3 Pek. Railing Besi Strips Tangga indoor m' 78.00 Rp 860,000.00 Rp 67,080,000.00
4 Pekerjaan Tangga Besi Indoor m' 26.40 Rp 2,500,000.00 Rp 66,000,000.00
5 Pekerjaan Tangga Besi Outdoor m' 16.27 Rp 2,500,000.00 Rp 40,675,000.00

Rp 423,082,900.00
XV PEKERJAAN PEMBERSIHAN
1 Pembersihan Sisa Bahan Bangunan Ls 1.00 Rp 6,500,000.00 Rp 6,500,000.00
Rp 6,500,000.00
JUMLAH TOTAL Rp 2,008,284,135.22