PLAN ACTIVITY MAINTENANCE ROAD SECTION 2

PT. KAPUAS BARA UTAMA


SIMPANG JULUKAN (KM 0) - PIT KBU (KM 45)
PT. MITRA BARITO LUMBUNG ENERGI
UPDATE: 18 FEBRUARI 2024

WORK DIMENSI KEBUTUHAN


NO. LOCATION START HEAVY EQUIPMENT MATERIAL
DURATION
P L T SATUAN VOLUME SATUAN
A SECTION 2 (KM 16 - KM 30)
31 Pemukiman 1 - Km 16 19 Februari 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 30 7 1,0 m 210 m³
35 Penyempitan Mamput - Km 17+500 20 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 8 1,0 m 160 m³
38 Semoning - Km 19+750 20 Februari 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 30 6 0,5 m 90 m³
39 Tanjakan Semoning - Km 20+ 21 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 15 5 1,0 m 75 m³
40 Mantahap - Km 20+500 21 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 12 6 1,0 m 72 m³
41 Pondok Tunggal - Km 21 21 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 5 0,5 m 50 m³
42 Tanjakan 22 22 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 15 3 0,5 m 23 m³
43 Tanjakan Budi - Km 23 22 Februari 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 30 8 0,5 m 120 m³
44 Tanjakan Budi 2 - Km 23 22 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 25 5 0,5 m 63 m³
46 Uteng Isnawati 2 - Km 23 23 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 15 8 0,3 m 36 m³
47 Camp Karet - Km 24 24 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 30 7 1,0 m 210 m³
48 Patah Pinggang - Km 24+500 24 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 7 10 1,0 m 70 m³
49 Jembatan Rungup - Km 25+ 24 Februari 2024 2 HARI EXCAVATOR, VIBRO, LOWBOY, GRADER BASECOURSE 2 2 0,5 m 2 m³
51 Tanjakan Raung - Km 25+750 26 Februari 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 40 8 0,5 m 160 m³
52 Tanjakan Raung - Km 26 27 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 6 1,0 m 60 m³
53 Km 26+ 28 Februari 2024 2 HARI EXCAVATOR, VIBRO, GRADER, LOWBOY BASECOURSE 2 2 0,5 m 2 m³
54 Tanjakan Amat - Km 26+500 01 Maret 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 5 1,0 m 75 m³
55 Tanjakan Amat 2 - Km 26+500 01 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 10 8 0,5 m 40 m³
61 Tanjakan Dalbo 1 - Km 27+500 03 Maret 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 7 1,0 m 70 m³
62 Tanjakan Dalbo 2 - Km 27+500 03 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 8 0,5 m 80 m³
63 Tanjakan Dalbo 3 - Km 27+500 03 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 10 6 1,0 m 60 m³
64 Km 27+750 03 Maret 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 15 10 1,0 m 150 m³
67 Tikungan Sinyal - Km 28+ 05 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 8 1,0 m 160 m³
68 Tikungan Taji - Km 29 06 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 15 6 1,0 m 90 m³
WORK DIMENSI KEBUTUHAN
NO. LOCATION START HEAVY EQUIPMENT MATERIAL
DURATION
P L T SATUAN VOLUME SATUAN
69 Tikungan Taji 1 - Km 29+ 06 Maret 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 5 5 0,5 m 13 m³
73 Tikungan Taji 5 - Km 29+ 07 Maret 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 6 1,0 m 60 m³
75 Km 29+500 07 Maret 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 8 1,0 m 80 m³
TOTAL 1 2280 m³
B SECTION 3 (KM 31 - KM 45)
84 Pabrik Sawit 4 - Km 31+750 26 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 15 1,0 m 150 m³
86 Putri Gunung 2 - Km 31+800 25 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 10 1,0 m 200 m³
87 Jembatan Waluyo - Km 32 25 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 5 5 0,3 m 8 m³
90 Waluyo 3 - Km 32+ 24 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 10 1,0 m 100 m³
91 Waluyo 4 - Km 32+ 24 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 20 5 1,0 m 100 m³
92 Waluyo 5 - Km 32+ 23 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 5 1,0 m 75 m³
94 Tanjakan Dodi - Km 34 23 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 8 1,0 m 80 m³
95 Tanjakan Dodi - Km 34 22 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 20 7 0,5 m 70 m³
96 Penyempitan Gorong2 - Km 34+500 22 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 8 5 1,0 m 40 m³
97 Penyempitan Gorong2 - Km 34+500 22 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 5 6 0,5 m 15 m³
98 Telawang - Km 36+250 21 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 10 0,5 m 50 m³
99 Turunan Santi 2 - Km 36+500 21 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 10 1,0 m 150 m³
100 Turunan Santi - Km 38+250 21 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 10 0,5 m 50 m³
101 Turunan Santi - Km 38+500 20 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 8 0,5 m 40 m³
102 Turunan Santi - 38+500 20 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 4 0,5 m 20 m³
103 Turunan Santi - 38+750 20 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 4 0,3 m 18 m³
104 Turunan Santi - 38+750 20 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 8 0,3 m 24 m³
105 Turunan Santi - Km 38+800 19 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 5 8 0,5 m 20 m³
106 Turunan Santi - Km 38+800 19 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 5 5 0,5 m 13 m³
107 Bukit Santi - Km 39+ 19 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 5 5 0,5 m 13 m³
108 Tikungan Ancau - Km 40+ 18 Februari 2024 2 HARI EXCAVATOR, VIBRO BASECOURSE 50 6 0,3 m 90 m³
109 Tikungan Ancau 2 - Km 40+ 18 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 10 1,0 m 150 m³
110 Tikungan Ancau 3 - Km 40+ 18 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 10 8 1,0 m 80 m³
111 Km 41+500 17 Februari 2024 2 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 40 6 1,0 m 240 m³
WORK DIMENSI KEBUTUHAN
NO. LOCATION START HEAVY EQUIPMENT MATERIAL
DURATION
P L T SATUAN VOLUME SATUAN
112 Km 41+750 17 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 40 6 1,0 m 240 m³
114 Penyempitan Sengketa - Km 42+250 16 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 20 5 0,5 m 50 m³
115 Penyempitan Sengketa - Km 42+300 16 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 10 5 1,0 m 50 m³
116 Penyempitan Sengketa - Km 42+300 16 Februari 2024 1 HARI EXCAVATOR, VIBRO BASECOURSE 15 6 0,5 m 45 m³
117 Km 42+750 16 Februari 2024 1 HARI GRADER, EXCAVATOR, VIBRO BASECOURSE 10 10 0,5 m 50 m³
TOTAL 2 2230 m³

KEBUTUHAN MATERIAL BASECOURSE/LPB TOTAL 1 + TOTAL 2 4509 m³