Anda di halaman 1dari 9

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 294,0 HP
3. Kapasitas Cp 60,0 T/Jam
4. Alat a. Umur Ekonomis A 10,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1.600,0 Jam
c. Harga Alat B 3.135.000.000,0 Rupiah

5 Kapastas tangki aspal Ca 30.000,00 liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 313.500.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,16324 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 287.854,91 Rupiah
W

b. Asuransi, dll = 0,002 x B F 3.918,75 Rupiah


W

Biaya Pasti per Jam = (E+F) G 291.773,66 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H1 564.127,20 Rupiah
Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 8.058.960,00 Rupiah Khusus AMP
dan aspal (Oil Heater)
Bahan Bakar Pemanas Aspal =1/1000 *Ca*Ms H3 479.700,00

2. Pelumas = (2.5%-3%) x Pw x Mp I 169.638,00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 122.461


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 244.921,88 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 60.900,00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 9.729.308,01 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 10.021.081,67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Rp./liter
5. Bahan Bakar Solar Ms 15.990,00 Rp./liter
6. Minyak Pelumas Mp 23.080,00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan bakar Batubara 500,00 Rp/kg
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3 - 4 m3 E08
2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 6,0 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 394.500.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 39.450.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 46.914,42 Rupiah
W

b. Asuransi, dll = 0,002 x B F 394,50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 47.308,92 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 191.880,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 57.700,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 12.328


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 24.656,25 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 335.464,38 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 382.773,30 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 6 - 8 m3 E09
2. Tenaga Pw 190,0 HP
3. Kapasitas Cp 12,0 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 580.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 58.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 68.974,31 Rupiah
W

b. Asuransi, dll = 0,002 x B F 580,00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 69.554,31 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 364.572,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 109.630,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 18.125 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 36.250,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 577.477,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 647.031,31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135,0 HP
3. Kapasitas Cp 10.800,0 -
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 3.121.189.500 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 312.118.950 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 371.175,67 Rupiah
W

b. Asuransi, dll = 0,002 x B F 3.121,19 Rupiah


W

Biaya Pasti per Jam = (E+F) G 374.296,86 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 259.038,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 77.895,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 97.537 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 195.074,34 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 678.444,52 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 1.052.741,38 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 82,0 HP
3. Kapasitas Cp 8,1 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.804.324.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 180.432.400 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 214.572,42 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.804,32 Rupiah


W

Biaya Pasti per Jam = (E+F) G 216.376,74 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 157.341,60 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 47.314,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 56.385 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 112.770,25 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 422.710,98 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 639.087,72 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 4.000,0 Liter
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 105.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 10.500.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 12.486,73 Rupiah
W

b. Asuransi, dll = 0,002 x B F 105,00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 12.591,73 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 191.880,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 57.700,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 3.281 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 6.562,50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 308.323,75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 320.915,48 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 72,4 HP
3. Kapasitas Cp 10,0 Ton
4. Alat Baru : a. Umur Ekonomis A 6,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1.600,0 Jam
c. Harga Alat B 2.723.248.752 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 272.324.875 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,23008 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 352.440,69 Rupiah
W

b. Asuransi, dll = 0,002 x B F 3.404,06 Rupiah


W

Biaya Pasti per Jam = (E+F) G 355.844,75 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 138.921,12 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 41.774,80 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 106.377


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 212.753,81 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 548.726,63 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 904.571,38 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. E18
2. Tenaga Pw 100,5 HP
3. Kapasitas Cp 9,0 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.480.564.250 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 148.056.425 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 176.070,51 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.480,56 Rupiah


W

Biaya Pasti per Jam = (E+F) G 177.551,08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 192.839,40 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 57.988,50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 46.268 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 92.535,27 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 438.530,80 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 616.081,87 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 82,0 HP
3. Kapasitas Cp 7,050 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.344.512.400 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 134.451.240 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26427 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 159.891,06 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.344,51 Rupiah


W

Biaya Pasti per Jam = (E+F) G 161.235,57 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 157.341,60 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 47.314,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 42.016 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 84.032,03 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 28.600,00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20.300,00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 379.603,64 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 540.839,21 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,07 % / Tahun
2. Upah Operator / Sopir U1 28.600,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20.300,00 Rp./Jam
4. Bahan Bakar Bensin Mb 11.990,00 Liter
5. Bahan Bakar Solar Ms 15.990,00 Liter
6. Minyak Pelumas Mp 23.080,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi