Check Point GIS 4 IKN
Check Point GIS 4 IKN
2. GIS Compartment.
Erection : Finish
Jointing : Finish
Wiring : Target selesai 20 April 2024
Pengisian GAS : Target selesai 20 April 2024
Pengujian SF6 : Target selesai 20 April 2024
Pengujian Density Meter : Target selesai 20 April 2024 (Start pengujian 16 April 2024)
Individual Test – SAT : Target selesai 28 April 2024
HV Test : Target 29 April 2024
Joint CVT : Target 4 Mei 2024
Joint Terminasi Trafo : Target 21 April 2024
3. Mobilisasi Manpower
Tim Jointing Prysmian (5 org) : Target Onsite 21 April 2024
Tim Hitachi RCP (3 org) : Target Onsite 20 April 2024
Tim Hitachi SAS (2 org) : Target Onsite 20 April 2024
Tim Hitachi Telecom (1 org) : Target Onsite 22 April 2024
Tim Komisioning (5 org) : Target Onsite 16 April 2024
Alat Uji / Komisioning : Target Onsite 16 April 2024
Tim Sipil (Min 40 orang) : Target Onsite 21 April 2024
PLN menyampaikan bahwa Kontraktor harus berkomitmen untuk mobilisasi manpower dan
tim teknis dari pabrikan terkait sesuai jadwal tersebut di atas untuk memastikan GIS 4 IKN
dapat selesai dan energize paling lambat pada bulan Mei 2024.
4. Pekerjaan E/M
Wiring RCP : Target 20 April 2024 (untuk bay Kariangau 1,2, Coupler, Trafo 1,2)
Pulling HV & MV : Target dimulai 05 April 2024
Erection Support 20 kV Trafo : Target 10 April 2024
Erection Flexible Busbar : Target 05 Mei 2024, posisi belum onsite, ETD 17 April 2024
Stringing Konduktor to CSE : Target 05 Mei 2024
Notulen