KONSULTAN MANAGEMENT KONSTRUKSI

PEKERJAAN FASILITAS OPERASI KERETA API (FASOPKA)


STASIUN KRAMASAN
WILAYAH DIVRE III PALEMBANG

Sabtu, 20 April 2024


PT. YODYA KARYA (PERSERO)
P R O G R E S P E K E R J A A N FA S O P K A
S TA S I U N K R A M A S A N
Kurva S Pekerjaan Fasopka

BOBOT KUMULATIF RENCANA


BOBOT KUMULATIF REALISASI

MINGGU

KUMULATIF KUMULATIF
MINGGU RENCANA (%) REALISASI (%) DEVIASI (%)
RENCANA (%) REALISASI (%)

70 3,110 78,078 4,908 85,913 +7,835


69 1,211 79,289 0,000 85,913 +6,624
Realisasi Pekerjaan Fasopka pada Tanggal 19 April 2024

No LAPORAN KEGIATAN HARIAN VOLUME KONTRAK TARGET PENYELESAIAN PROGRAM RENCANA KERJA REALISASI PEKERJAAN

A. PEKERJAAN PERSIAPAN

- Izin Kerja - Izin Kerja


1. SMK3L 1 Ls Setiap Hari
- Safety Talk - Safety Talk
Realisasi Pekerjaan Fasopka pada Tanggal 19 April 2024

No RENCANA HARIAN REALISASI PEKERJAAN

A. PERSIAPAN KEGIATAN UCO STAGING 1 KRAMASAN

Telah dilakukan Test Ganjalan Wesel Sebanyak 5 Wesel (Wesel 13C/W.23C, Wesel 23B/W.13A, Wesel 23A/W.43B,
Wesel 33A, Wesel 21C) Kegiatannya adalah sebagai berikut:
1. Setting Manual Kerapatan Lidah Wesel
2. Melakukan Korespondensi Antara Lapangan dan VDU
1. Test Ganjalan Wesel
3. Test Kerapatan Lidah 3mm Masuk, 4mm Gagal Balik
4. Test Slip Motor Kopling Berfungsi
5. Test Handcrank dimasukkan Tidak Ada Pergerakan
6. Melakukan Pengukuran (Tegangan, Arus, Lebar Lidah Buka dan Lebar Jalur Lidah Wesel)
Dokumentasi Pekerjaan Fasopka pada Tanggal 19 April 2024

Test Ganjalan Wesel Sebanyak 5 Wesel (Wesel 13C/W.23C,


Wesel 23B/W.13A, Wesel 23A/W.43B, Wesel 33A, Wesel
21C)
Timeline Persiapan UCO Staging 1 Kramasan
Jumlah Tenaga Kerja Pekerjaan FASOPKA Kramasan
Tanggal 19 April 2024

JUMLAH TENAGA
Project Manager : Hadir (1 Orang)
Laporan Cuaca
Site Manager : Hadir (2 Orang) Tanggal Waktu Cuaca
Seketaris : Hadir (1 Orang)
19-04-2024 08.00 – 17.00 Cerah
Manager ADM dan QA : Hadir (1 Orang)
QC : Hadir (1 Orang)
SHE Officer : Hadir (1 Orang)
SPV : Hadir (3 Orang)
Tenaga Kerja Lapangan : Hadir (15 Orang)

LAPORAN SHE
Accident : Nihil
Incident : Nihil
Nearmiss : Nihil
JUMLAH TENAGA KERJA KANTOR DAN LAPANGAN MK PT. YODYA KARYA
PEKERJAAN FASOPKA EMPLASEMEN KRAMASAN 19 April 2024

TENAGA AHLI TENAGA PENDUKUNG

1 Team Leader Hadir 1 Admin Hadir


Site Inspector Signalling &
2 Signalling & SCADA Engineer Hadir 2 Resign belum ada pengganti
Telecomunication
3 Telecomunication Engineer Hadir 3 Site Inspector Safety Hadir
4 Ahli Quantity & Quality Engineer 1 Hadir 4 Document Control Hadir
5 Ahli Quantity & Quality Engineer 2 Hadir 5 Drafter Cad 1 Hadir
6 6 Driver 1 Hadir
Ahli K3 Konstruksi Hadir
7 Safety & Reliability Engineer Hadir
Rencana Pekerjaan Fasopka pada Tanggal 21 April 2024

No RENCANA HARIAN

A. PERSIAPAN KEGIATAN UCO STAGING 1 KRAMASAN