2019

Mining Division

P T S E M E N B AT U R A JA
(PERSERO) TBK

PIT CONTROL
REKAMAN DOKUMEN LAPORAN RENCANA
DAN REALISASI TAMBANG PT SEMEN
BATURAJA DESEMBER 2019
Realisasi produksi Batukapur, Clay, dan Overburden

Material Target Produksi Realisasi bulanan


Desember 2019 30 Desember 2019
BTA I 190.000 115.259,78
BK BTA II 209.000 170.998,86
SM 100.000 103.617,68
BTA I 17.000 8.147,14
CLAY BTA II 22.000 12.354,90
BLAST 4.906,16
Overburden NONBLAST 53.990,75 96.336,26
Tambang I
SM 68.000 27.664,72
Overburden BLAST
Tambang II 37.968,17
NON BLAST

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 1


WEEKLY PRODUKSI BATUKAPUR , CLAY & OVERBURDEN
BTA I – II ( 24 DES – 30 DES 2019 )
BATURAJA I BATURAJA II
TANGGAL BATUKAPUR CLAY BATUKAPUR CLAY
TARGET REALISASI TARGET REALISASI TARGET REALISASI TARGET REALISASI
24/12/2019 4.935,48 321,56 419,35 - 7.766,67 313,86 766,67 -
25/12/2019 4.935,48 - 419,35 - 7.766,67 6.831,78 766,67 1.005,74
26/12/2019 4.935,48 600,82 419,35 - 7.766,67 8.358,30 766,67 644,10
27/12/2019 4.935,48 71,80 419,35 - 7.766,67 7.171,20 766,67 649,42
28/12/2019 4.935,48 820,10 419,35 - 7.766,67 7.161,56 766,67 546,60
29/12/2019 4.935,48 441,14 419,35 - 7.766,67 7.914,86 766,67 163,32
30/12/2019 4.935,48 155,24 419,35 - 7.766,67 5.455,20 766,67 -
TOTAL 2.410,66 - 43.206,76 3.009,18

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 2


TAMBANG I TAMBANG II
TANGGAL
OB BLAST OB NB OB BLAST OB NB
24/12/2019 490,40 1.439,54 - -
25/12/2019 - 5.234,16 - -
26/12/2019 - 3.195,78 - -
27/12/2019 - 1.842,40 - -
28/12/2019 - 2.000 - -
29/12/2019 1.687,74 3.559,70 - -
30/12/2019 2.728.02 2.191,84 - -
TOTAL 4.906,16 19.463,42 - -

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 3


RENCANA LOKASI BLASTING,INVENTORI LUBANG BOR DAN
INVENTORI MATERIAL BATUKAPUR, DESEMBER 2019

Lokasi blasting STANDBY

Inventori lubang bor 190 + 36 + 571


Inventori material blasting 57.849,43
Inventori material SM 26.000

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 4


Target HM bulan Desember dan realisasi hingga 30 Desember 2019

250 250 250 250

230.5

201.2 205.4
200 200 200 200

150 150
Axis Title

100

50

0
JTI 01 JTI 02 JTI DOZER KS 01 KS 02 KS DOZER KS COMPACTOR
TARGET 200 200 200 250 250 250 150
REALISASI 230.5 201.2 205.4 250 250.5 250.7 150

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 5


PLAN PRODUKSI DAN LOKASI BLASTING 31 Desember 2019

57/63A
42/80 HG OB NB
BTA II
57/39A
OB NB

57/28
OB BLAST

49/42 HG
BTA II 39/2A HG
BTA II
39/2A HG
BTA II

60/36
OB NB 60/43
PSP OB NB
PSP

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 6


PLAN PENGAMBILAN OB TAMABANG II
31 DESEMBER 2019

AF11 AF11

AF11

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 7


Ploting rencana Alat development 31 Desember 2019

JTI 01 MERAPIKAN DUMPINGAN MATERIAL CLAY DI STOCKROOM CLAY.


JTI 02 REPAIR LOKASI BLASTING 57/81.
DOZER JTI MENDORONG MATERIAL OB DI DISPOSAL 4.
KS 01 BONGKAR MATERIAL BLASTING DI BLOK AC11 TAMBANG BTA2.
KS 02 REPAIR LOKASI BLASTING 49/36.
DOZER KS MENDORONG MATERIAL OB DI DISPOSAL 4.
COMPACT PEMADATAN JALAN HAULING BK,CLAY & DISPOSAL 4

PT Semen Baturaja (Persero) Tbk www.presentationgo.com 8


PT Semen Baturaja (Persero) Tbk www.presentationgo.com 9