Anda di halaman 1dari 34

SEMINAR HASIL

KERJA PRAKTIK
PEMBANGUNAN GEDUNG RAWATAN PARU RSUD
M.ZEIN PAINAN

OLEH :
DIANA DWI SYAFIRA
1710923002
DOSEN PEMBIMBING :
Dr.Eng. FEBRIN ANAS ISMAIL,M.T
NIP. 196302211988031002
Insert the Subtitle of Your Presentation
Lokasi Proyek
Data Umum Proyek
Sumber Dana
Nama Proyek Dana Alokasi Khusus ( DAK )
Pembangunan Gedung Rawatan Paru APBD Tahun 2020.
RSUD M.Zein Painan

Nilai Kontrak
Lokasi Rp 6.794.299.000,-

RSUD. Dr. Muhammad Zein Painan Jl. A.


Rivai Painan Kab. Pesisir Selatan - Waktu Pelaksanaan
180 (Seratus Delapan Puluh) Hari
Sumatera Barat Kelender

No. Kontrak Kontraktor Pelaksana


PT. Debitindo Jaya
SPK/06/APBD-DAK/ RSUD-PS/VII-2020

Tanggal Kontrak Konsultan Pengawas


03 Juli 2020 CV. Entance Consultant

Jenis Kontrak Konsultan Perancana


Unit Price CV.Andes Engineering
Consultan
Hubungan Organisasi Proyek
Get a modern PowerPoint Presentation that is beautifully designed. I hope and I
believe that this Template will your Time.

Owner
Dinas Pengelolaan
Sumber Daya Air

Text

Konsultan Pengawas Kontraktor


CV. Kaharoshitama PT. Ady Permana
Engineering Putratama
Keterangan :ontent Here
I believe Template will your Time, Mon
colors, Hubungan Formal

Hubungan Koordinasind Tex


Presentation that is beautifully designe
Struktur Organisasi
STRUKTUR ORGANISASI PT. DEBITINDO JAYA
PEKERJAAN PEMBANGUNAN GEDUNG RAWAT PARU RUMAH SAKIT DR. M. ZEIN

ARI NUGROHO
Project Mana ger

Eko Retno W
Keua nga n

Eko Retno W Hermawan HS


Admin Si te Manager

Logistic Surveyor Pengawas Lapangn Mekanikal Electrical


Stevanus Riyan Mulyana Riyan Mulyana BAGIO
Sudayat Susetyo

Disetujui Oleh Diperiksa Diajukan Oleh


Pejabat Pembuat Komitmen Konsultan Pengawas Kontraktor Pelaksana

SILVIA IKHLAS Ssi, Apt, Mars YUHER FIRMANDES, ST ARI NUGROHO, S.Kom
Nip. 19770409 200701 2 001 CV. ANDES CONSULTING ENGINEERING PT. DEBITINDO JAYA
Sistem Pelaporan

Laporan Mingguan
Proses Seleksi dan Penunjukan Kontraktor

STEP 1
STEP 2
STEP 1 Terpilih 3 kontraktor dari hasil
evaluasi penawaran
STEP 3

Pelelangan umum
dilakukan oleh LPSE diikuti
oleh 65 peserta melalui STEP 2 P.T Debitindo Jaya terpilih
STEP 3
sebagai pemenang lelang
web
lpse.pesisirselatankab.go.id STEP 2
Metoda Pelaksanaan

Pekerjaan Sloof
01

Pekerjaan Kolom 02
Pekerjaan Balok
03

Pekerjaan Plat lantai 04


Pekerjaan Tangga
05
Pekerjaan Ramp
06
Peralatan

Excavator Mixer Truck Concrete Pump Truck vibrator Concrete Pemotong kayu

Manual Bar Bender Bar Cutter Mesin Molen Pompa Air


Pekerjaan Bekisting Sloof Bekisting Balok

Bekisting
• bekisting digunakan untuk cetakan yang dibuat pada

pengecoran supaya pada pengerjaan pengecoran tidak

ada peberubahan bentuk elemen struktur yang di

kehendaki
Bekisting Plat lantai Bekisting Kolom
• Langkah langkah pekerjaan bekisting:

1. Pengajuan material bekisting

2. penyediaan material bekisting

3. prosese fabrikasi cetakan di workshop

4. pemasangan bekisting
Bekisting Tangga Bekisting RAMP

Perancah
Pekerjaan Pembesian
Adapun Langkah langkah yang
dikerjakan pada saat Pekerjaan
Pembesian yaitu: Pembesian Kolom Pembesian Balok
•Pengajuan Pekerjaan Pembesian
•Pengajuan shop drawing dan
sample contoh besi yang akan
dipakai
•Pemesanan dan Pengadaan
Mterial besi
•Penumpukan sementara
•Fabrikasi pembesian di Workshop
•Pemasangan Pembesian di lokasi
Pekerjaan Pembesian Plat lantai
•Pengecekan
Fabrikasi besi

Cakar ayam
Beton Tahu
PembesianSloof PembesianTangga Pembesian RAMP
Pekerjaan
Pengecoran
Tahap pengerjaan Pengecoran:
1. Pengajuan bahan
2. Job mix design
3. Penyedian bahan dasar beton
4. Persiapan Peralatan Beton
5. Persiapan lahan
pengecoran(cek)
6. Pelaksanaan pengecoran
Permasalahan Lapangan

•Kait tulangan sengkang tidak sesuai dengan spesifikasi


teknis.

Pelaksanaan pengecoran yang terhambat dan berhenti sementara


Pengendalian Mutu dan
Jadwal
Uji Slump KEGIATAN : PEMBANGUNAN RUANG RAWATAN
JADWAL PELAKSANAAN
Kontrak No : SPK/06/APBD-DAK/ RSUD-PS/VII-2020
PEKERJAAN : PEMBANGUNAN GEDUNG RAWATAN PARU Tanggal Kontrak : 03 Juli 2020
LOKASI : RSUD Dr. M. ZEIN PAINAN KEC. IV JURAI Nilai Kontrak : Rp 6.794.299.000,-

BOBOT MINGGU KE- Persenta


NO. URAIAN PEKERJAAN
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 si Bobot

100%
I. PEKERJAAN PENDAHULUAN 1.58
II. PEKERJAAN PONDASI 8.26
III. PEKERJAAN BETON STRUKTUR LANTAI I 17.39
IV. PEKERJAAN BETON STRUKTUR LANTAI II 13.63
V. PEKERJAAN BETON STRUKTUR LANTAI III 5.19
VI. PEKERJAAN KAP ATAP 3.58
VII. PEKERJAAN DINDING BATA RINGAN 5.97
VIII. PEKERJAAN PELAPIS DINDING, KOLOM DAN PLAT DAK 7.81
IX. PEKERJAAN PLAFOND 6.18
X. PEKERJAAN LANTAI 6.48
XI. PEKERJAAN PINTU DAN JENDELA 5.72
XII. PEKERJAAN PENGECATAN 2.35
XIII. PEKERJAAN INSTALASI LITRIK 3.07
XIV. PEKERJAAN INSTALASI AIR 2.76
XV. PEKERJAAN OKSIGEN SENTRAL 6.29
XVI. PEKERJAAN INSTALASI FIRE ALARM 0.78
XVII. PEKERJAAN INSTALASI PENANGKAL PETIR 0.69
XVIII. PEKERJAAN PERLENGKAPAN LUAR 2.26
JUMLAH 100.00
BOBOT PERMINGGU 1.48 0.15 0.55 0.21 3.79 2.81 0.59 1.32 1.48 2.83 1.39 2.20 5.75 5.85 3.96 6.29 7.28 8.44 6.29 4.00 5.98 8.41 5.87 9.56 3.41 0.09
RENCANA
BOBOT AKUMULATIF 1.48 1.63 2.18 2.39 6.19 9.00 9.58 10.91 12.39 15.22 16.61 18.81 24.56 30.41 34.37 40.67 47.94 56.38 62.68 66.68 72.66 81.07 86.94 96.51 99.91 100.00
BOBOT PERMINGGU 0.84 1.60 2.54 4.08 5.97 1.10 1.75 4.16 3.61 2.29 4.72
REALISASI
BOBOT AKUMULATIF 0.84 2.44 4.98 9.06 15.03 16.14 17.89 22.04 25.65 27.94 32.67
TERCEPAT 0.81 2.81 6.67 8.85 7.14 8.30 11.14 13.27 12.73 16.06
TERLAMBAT -0.64
Catatan:
- Waktu Pelaksanaan 180 Hari Kelender Disetujui Oleh: Dibuat oleh:
- Minggu Ke-26 Terpakai 5 Hari Kuasa Pengguna Aggaran Konsultan Pengawas
RSUD Dr. MUHAMMAD ZEIN CV. ENTRANCE CONSULTANT

SILVIA IKHLAS, SSI,APT,MARS SAPRIMAN, A.Md.QS, ST


Nip. 19770409 200701 2 001 Inspector

Kurva S
Penerapan K3 di
Proyek
PekerjaTanpa Perangkat K3
Tugas
Khusus
Tugas Khusus
BACKUP DATA (MC-0) BACKUP DATA (MC-0)
KEGIATAN : PEMBANGUNAN RUANG RAWATAN KEGIATAN : PEMBANGUNAN RUANG RAWATAN
PEKERJAAN : PEMBANGUNAN GEDUNG RAWATAN PARU PEKERJAAN : PEMBANGUNAN GEDUNG RAWATAN PARU
LOKASI : KECAMATAN IV JURAI KABUPATEN PESISIR SELATAN LOKASI : KECAMATAN IV JURAI KABUPATEN PESISIR SELATAN

NO. SKETSA URAIAN PERHITUNGAN VOL PEM STN NO. SKETSA URAIAN PERHITUNGAN VOL PEM STN
I. PEKERJAAN BETON STRUKTUR LANTAI I I. PEKERJAAN BETON STRUKTUR LANTAI I
1 Pek. Beton Sloof Type S1 uk. 30 x 45 cm (K-250) 1 Pek. Beton Sloof Type S1 uk. 30 x 45 cm (K-250)
- Beton Ready Mix K-250 9,72 9,72 M3 - Beton Ready Mix K-250 9,72 9,72 M3
[lebar] [tinggi] [panjang] [lebar] [tinggi] [panjang]
[ 0,30 x 0,45 ] x 72,00 = 9,72 [ 0,30 x 0,45 ] x 72,00 = 9,72
- Pembesian 1.646,79 1.646,79 Kg - Pembesian 1.646,79 1.646,79 Kg
[jumlah Tul ] [panjang] [jumlah] [koef D16] [jumlah Tul ] [panjang] [jumlah] [koef D16]
Tul- utama tump [ 9,00 x 40,00 ] x 1,00 x 1,58 = 568,17 Tul- utama tump [ 9,00 x 40,00 ] x 1,00 x 1,58 = 568,17
Tul- utama lap [ 9,00 x 40,00 ] x 1,00 x 1,58 = 568,17 Tul- utama lap [ 9,00 x 40,00 ] x 1,00 x 1,58 = 568,17
[panjang] [jarak begel] [panjang] [koef Ø10] [panjang] [jarak begel] [panjang] [koef Ø10]
Begel tump [ 36,00 / 0,10 ] x 1,38 x 0,62 = 306,28 Begel tump [ 36,00 / 0,10 ] x 1,38 x 0,62 = 306,28
Begel lap [ 36,00 / 0,15 ] x 1,38 x 0,62 = 204,18 Begel lap [ 36,00 / 0,15 ] x 1,38 x 0,62 = 204,18
1.646,79 1.646,79
- Bekisting 64,80 64,80 M2 - Bekisting 64,80 64,80 M2
[ 0,45 x 2,00 ] x 72,00 = 64,80
[ 0,45 x 2,00 ] x 72,00 = 64,80
2 Pek. Beton Sloof Type S2 uk. 25 x 45 cm (K-250)
2 Pek. Beton Sloof Type S2 uk. 25 x 45 cm (K-250)
- Beton Ready Mix K-250 10,35 10,35 M3 - Beton Ready Mix K-250 10,35 10,35 M3
[lebar] [tinggi] [panjang]
[lebar] [tinggi] [panjang]
[ 0,25 x 0,45 ] x 92,00 = 10,35 [ 0,25 x 0,45 ] x 92,00 = 10,35
- Pembesian 1.745,11 1.745,11 Kg
- Pembesian 1.745,11 1.745,11 Kg
[jumlah Tul ] [panjang] [jumlah] [koef D16]
[jumlah Tul ] [panjang] [jumlah] [koef D16]
Tul- utama tump [ 7,00 x 51,60 ] x 1,00 x 1,58 = 570,06
Tul- utama tump [ 7,00 x 51,60 ] x 1,00 x 1,58 = 570,06
Tul- utama lap [ 7,00 x 51,60 ] x 1,00 x 1,58 = 570,06
Tul- utama lap [ 7,00 x 51,60 ] x 1,00 x 1,58 = 570,06
[panjang] [jarak begel] [panjang] [koef Ø10]
[panjang] [jarak begel] [panjang] [koef Ø10]
Begel tump [ 46,00 / 0,10 ] x 1,28 x 0,62 = 363,00
Begel tump [ 46,00 / 0,10 ] x 1,28 x 0,62 = 363,00
Begel lap [ 46,00 / 0,15 ] x 1,28 x 0,62 = 242,00
Begel lap [ 46,00 / 0,15 ] x 1,28 x 0,62 = 242,00
1.745,11
1.745,11
- Bekisting 82,80 82,80 M2
- Bekisting 82,80 82,80 M2
[ 0,45 x 2,00 ] x 92,00 = 82,80
[ 0,45 x 2,00 ] x 92,00 = 82,80
3 Pek. Beton Sloof Type S3 uk. 20 x 35 cm (K-250) 3 Pek. Beton Sloof Type S3 uk. 20 x 35 cm (K-250)
- Beton Ready Mix K-250 5,48 5,48 M3 - Beton Ready Mix K-250 5,48 5,48 M3
[lebar] [ting i] [panjang] [lebar] [tinggi] [panjang]
[ 0,20 x 0,35 ] x 78,33 = 5,48
[ 0,20 x 0,35 ] x 78,33 = 5,48
- Pembesian 1.110,08 1.110,08 Kg
- Pembesian 1.110,08 1.110,08 Kg [jumlah Tul ] [panjang] [jumlah] [koef D16]
[jumlah Tul ] [panjang] [jumlah] [koef D16] Tul- utama tump [ 5,00 x 45,35 ] x 1,00 x 1,58 = 357,87
Tul- utama tump [ 5,00 x 45,35 ] x 1,00 x 1,58 = 357,87 Tul- utama lap [ 5,00 x 45,35 ] x 1,00 x 1,58 = 357,87
Tul- utama lap [ 5,00 x 45,35 ] x 1,00 x 1,58 = 357,87
[panjang] [jarak begel] [panjang] [koef Ø10]
Begel tump [ 39,16 / 0,10 ] x 0,98 x 0,62 = 236,61
[panjang] [jarak begel] [panjang] [koef Ø10]
Begel lap [ 39,16 / 0,15 ] x 0,98 x 0,62 = 157,74
Begel tump [ 39,16 / 0,10 ] x 0,98 x 0,62 = 236,61 1.110,08
Begel lap [ 39,16 / 0,15 ] x 0,98 x 0,62 = 157,74 - Bekisting 54,83 54,83 M2
1.110,08 [ 0,35 x 2,00 ] x 78,33 = 54,83
- Bekisting 54,83 54,83 M2
[ 0,35 x 2,00 ] x 78,33 = 54,83 4 Pek. Beton Sloof Type SA uk.15 x 20 cm (K-175)
- Beton K175 0,95 0,95 M3
[lebar] [tinggi] [panjang]
4 Pek. Beton Sloof Type SA uk.15 x 20 cm (K-175)
[ 0,15 x 0,20 ] x 31,55 = 0,95
- Beton K175 0,95 0,95 M3
[lebar] [ting i] [panjang] - Pembesian 189,09 189,09 Kg
[ 0,15 x 0,20 ] x 31,55 = 0,95 [jumlah Tul ] [panjang] [jumlah] [koef D12]
Tul- utama tump [ 4,00 x 17,34 ] x 1,00 x 0,89 = 61,56
- Pembesian 189,09 189,09 Kg Tul- utama lap [ 4,00 x 17,34 ] x 1,00 x 0,89 = 61,56
[jumlah Tul ] [panjang] [jumlah] [koef D12]
Tul- utama tump [ 4,00 x 17,34 ] x 1,00 x 0,89 = 61,56 [panjang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 15,78 / 0,10 ] x 0,64 x 0,39 = 39,59
Tul- utama lap [ 4,00 x 17,34 ] x 1,00 x 0,89 = 61,56 Begel lap [ 15,78 / 0,15 ] x 0,64 x 0,39 = 26,39
189,09
[panjang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 15,78 / 0,10 ] x 0,64 x 0,39 = 39,59 - Bekisting 12,62 12,62 M2
Begel lap [ 15,78 / 0,15 ] x 0,64 x 0,39 = 26,39 [ 0,20 x 2,00 ] x 31,55 = 12,62
189,09
5 Pek. Beton Kolom Type K1 uk. 40 x 50 cm (K-250)
- Beton Ready Mix K-250 28,00 28,00 M3
- Bekisting 12,62 12,62 M2
[panjang] [lebar] [tinggi] [jumlah]
[ 0,20 x 2,00 ] x 31,55 = 12,62 [ 0,40 x 0,50 ] x 4,00 x 35,00 = 28,00

5 Pek. Beton Kolom Type K1 uk. 40 x 50 cm (K-250) - Pembesian 5.319,52 5.319,52 Kg


- Beton Ready Mix K-250 28,00 28,00 M3 [jumlah] [panjang] [koef D16] [jumlah]
[panjang] [lebar] [tinggi] [jumlah] Tul- utama tump [ 14,00 x 2,33 ] x 1,58 x 35,00 = 1.798,01
[ 0,40 x 0,50 ] x 4,00 x 35,00 = 28,00 Tul- utama lap [ 14,00 x 2,33 ] x 1,58 x 35,00 = 1.798,01

[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]


- Pembesian 5.319,52 5.319,52 Kg Begel tump [ 1,78 / 0,10 ] x 1,68 x 0,62 x 35,00 = 643,44
[jumlah] [panjang] [koef D16] [jumlah] Begel lap [ 1,78 / 0,15 ] x 1,68 x 0,62 x 35,00 = 428,96
Tul- utama tump [ 14,00 x 2,33 ] x 1,58 x 35,00 = 1.798,01
Tul- utama lap [ 14,00 x 2,33 ] x 1,58 x 35,00 = 1.798,01 [panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Hoop tump [ 1,78 / 0,10 ] x 1,02 x 0,62 x 35,00 = 390,66
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] Hoop lap [ 1,78 / 0,15 ] x 1,02 x 0,62 x 35,00 = 260,44
Begel tump [ 1,78 / 0,10 ] x 1,68 x 0,62 x 35,00 = 643,44 5.319,52
Begel lap [ 1,78 / 0,15 ] x 1,68 x 0,62 x 35,00 = 428,96 - Bekisting 223,65 223,65 M2
[ 0,90 x 2,00 ] x 3,55 x 35,00 = 223,65
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Hoop tump [ 1,78 / 0,10 ] x 1,02 x 0,62 x 35,00 = 390,66
Hoop lap [ 1,78 / 0,15 ] x 1,02 x 0,62 x 35,00 = 260,44
5.319,52

- Bekisting 223,65 223,65 M2


[ 0,90 x 2,00 ] x 3,55 x 35,00 = 223,65
Tugas Khusus 6 Pek. Beton Kolom Type K3 uk. 35 x 35 cm (K-250)
- Beton Ready Mix K-250

[
[panjang]
0,35 x
[lebar]
0,35 ] x
[tinggi]
4,00 x
[jumlah]
9,00 = 4,41
4,41 4,41 M3

- Pembesian 882,73 882,73 Kg


6 Pek. Beton Kolom Type K3 uk. 35 x 35 cm (K-250)
- Beton Ready Mix K-250 4,41 4,41 M3 [jumlah] [panjang] [koef D16] [jumlah]
[panjang] [lebar] [tinggi] [jumlah] Tul- utama tump [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20
[ 0,35 x 0,35 ] x 4,00 x 9,00 = 4,41
Tul- utama lap [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20
- Pembesian 882,73 882,73 Kg
[jumlah] [panjang] [koef D16] [jumlah] [panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Tul- utama tump [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20
Tul- utama lap [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20 Begel tump [ 1,83 / 0,10 ] x 1,28 x 0,62 x 9,00 = 129,61
Begel lap [ 1,83 / 0,15 ] x 1,28 x 0,62 x 9,00 = 86,41
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Begel tump [ 1,83 / 0,10 ] x 1,28 x 0,62 x 9,00 = 129,61
Begel lap [ 1,83 / 0,15 ] x 1,28 x 0,62 x 9,00 = 86,41 [panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Hoop tump [ 1,83 / 0,10 ] x 0,82 x 0,62 x 9,00 = 83,03
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Hoop tump [ 1,83 / 0,10 ] x 0,82 x 0,62 x 9,00 = 83,03 Hoop lap [ 1,82 / 0,15 ] x 0,82 x 0,62 x 9,00 = 55,28
Hoop lap [ 1,82 / 0,15 ] x 0,82 x 0,62 x 9,00 = 55,28 882,73
882,73

- Bekisting 44,42 44,42 M2 - Bekisting 44,42 44,42 M2


[ 0,70 x 2,00 ] x 3,53 x 9,00 = 44,42 [ 0,70 x 2,00 ] x 3,53 x 9,00 = 44,42
7 Pek. Beton Kolom Type K4 uk. 30 x 30 cm (K-250)
- Beton Ready Mix K-250 0,95 0,95 M3 7 Pek. Beton Kolom Type K4 uk. 30 x 30 cm (K-250)
[panjang] [lebar] [tinggi] [jumlah]
[ 0,30 x 0,30 ] x 5,65 x 1 = 0,51 - Beton Ready Mix K-250 0,95 0,95 M3
[ 0,30 x 0,30 ] x 4,95 x 1 = 0,45 [panjang] [lebar] [tinggi] [jumlah]
0,95
- Pembesian 143,83 143,83 Kg
[ 0,30 x 0,30 ] x 5,65 x 1 = 0,51
[jumlah] [panjang] [koef D13] [jumlah] [ 0,30 x 0,30 ] x 4,95 x 1 = 0,45
Tul- utama tump [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55 0,95
Tul- utama lap [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55
- Pembesian 143,83 143,83 Kg
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] [jumlah] [panjang] [koef D13] [jumlah]
Begel tump [ 2,68 / 0,10 ] x 1,08 x 0,62 x 1,00 = 17,81
Begel lap [ 2,67 / 0,15 ] x 1,08 x 0,62 x 1,00 = 11,86
Tul- utama tump [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55
76,77 Tul- utama lap [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55
- Pembesian
[jumlah] [panjang] [koef D13] [jumlah] [panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Tul- utama tump [ 8,00 x 2,48 ] x 1,04 x 1,00 = 20,63 Begel tump [ 2,68 / 0,10 ] x 1,08 x 0,62 x 1,00 = 17,81
Tul- utama lap [ 8,00 x 2,48 ] x 1,04 x 1,00 = 20,63
Begel lap [ 2,67 / 0,15 ] x 1,08 x 0,62 x 1,00 = 11,86
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] 76,77
Begel tump [ 2,33 / 0,10 ] x 1,08 x 0,62 x 1,00 = 15,48
Begel lap [ 2,33 / 0,15 ] x 1,08 x 0,62 x 1,00 = 10,32
67,06 - Pembesian
[jumlah] [panjang] [koef D13] [jumlah]
- Bekisting 12,00 12,00 M2
Tul- utama tump [ 8,00 x 2,48 ] x 1,04 x 1,00 = 20,63
[ 0,60 x 2 ] x 5,35 x 1,00 = 6,42 Tul- utama lap [ 8,00 x 2,48 ] x 1,04 x 1,00 = 20,63
[ 0,60 x 2 ] x 4,65 x 1,00 = 5,58
12,00
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
8 Pek. Beton Kolom Type K5 uk. 20 x 20 cm (K-250) Begel tump [ 2,33 / 0,10 ] x 1,08 x 0,62 x 1,00 = 15,48
- Beton Ready Mix K-250 0,64 0,64 M3
[panjang] [lebar] [tinggi] [jumlah] Begel lap [ 2,33 / 0,15 ] x 1,08 x 0,62 x 1,00 = 10,32
[ 0,20 x 0,20 ] x 4,00 x 4,00 = 0,64 67,06
- Pembesian 119,78 119,78 Kg
[jumlah] [panjang] [koef D13] [jumlah]
Tul- utama tump [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34 - Bekisting 12,00 12,00 M2
Tul- utama lap [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34
[ 0,60 x 2 ] x 5,35 x 1,00 = 6,42
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] [ 0,60 x 2 ] x 4,65 x 1,00 = 5,58
Begel tump [ 1,90 / 0,10 ] x 0,68 x 0,62 x 4,00 = 31,86
Begel lap [ 1,90 / 0,15 ] x 0,68 x 0,62 x 4,00 = 21,24
12,00
119,78
8 Pek. Beton Kolom Type K5 uk. 20 x 20 cm (K-250)
- Bekisting 11,28 11,28 M2
[ 0,40 x 2,00 ] x 3,53 x 4,00 = 11,28 - Beton Ready Mix K-250 0,64 0,64 M3
[panjang] [lebar] [tinggi] [jumlah]
[ 0,20 x 0,20 ] x 4,00 x 4,00 = 0,64

- Pembesian 119,78 119,78 Kg


[jumlah] [panjang] [koef D13] [jumlah]
Tul- utama tump [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34
Tul- utama lap [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34

[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]


Begel tump [ 1,90 / 0,10 ] x 0,68 x 0,62 x 4,00 = 31,86
Begel lap [ 1,90 / 0,15 ] x 0,68 x 0,62 x 4,00 = 21,24
119,78

- Bekisting 11,28 11,28 M2


[ 0,40 x 2,00 ] x 3,53 x 4,00 = 11,28
9 Pek. Beton Kolom Praktis Type KP uk. 13 x 13 cm (K-175)

Tugas Khusus
- Beton K-175 1.38 1.38 M3
[panjang] [lebar] [tinggi] [jumlah]
[ 0.13 x 0.13 ] x 3.55 x 23.00 = 1.38

- Pembesian 299.29 299.29 Kg


[jumlah] [panjang] [koef D10] [jumlah]
Tul- utama tump [ 4.00 x 1.78 ] x 0.62 x 23.00 = 100.67
Tul- utama lap [ 4.00 x 1.78 ] x 0.62 x 23.00 = 100.67

[panjang] [jarak begel] [panjang] [koef Ø8] [jumlah]


6 Pek. Beton Kolom Type K3 uk. 35 x 35 cm (K-250)
Begel tump [ 1.78 / 0.15 ] x 0.46 x 0.39 x 23.00 = 48.97
- Beton Ready Mix K-250
[panjang] [lebar] [tinggi] [jumlah]
4,41 4,41 M3 Begel lap [ 1.78 / 0.15 ] x 0.46 x 0.39 x 23.00 = 48.97
[ 0,35 x 0,35 ] x 4,00 x 9,00 = 4,41
299.29
- Pembesian 882,73 882,73 Kg
[jumlah] [panjang] [koef D16] [jumlah]
Tul- utama tump [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20
Tul- utama lap [ 8,00 x 2,33 ] x 1,58 x 9,00 = 264,20 - Bekisting 21.23 21.23 M2
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] [ 0.26 x 1.00 ] x 3.55 x 23.00 = 21.23
Begel tump [ 1,83 / 0,10 ] x 1,28 x 0,62 x 9,00 = 129,61
Begel lap [ 1,83 / 0,15 ] x 1,28 x 0,62 x 9,00 = 86,41

[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah] 10 Pek. Beton Balok Type B1 uk. 30 x 45 cm (K-250)
Hoop tump [ 1,83 / 0,10 ] x 0,82 x 0,62 x 9,00 = 83,03
Hoop lap [ 1,82 / 0,15 ] x 0,82 x 0,62 x 9,00 = 55,28 - Beton Ready Mix K-250 9.72 9.72 M3
882,73

- Bekisting 44,42 44,42 M2


[lebar] [tinggi] [panjang]
[ 0,70 x 2,00 ] x 3,53 x 9,00 = 44,42 [ 0.30 x 0.45 ] x 72.00 = 9.72
7 Pek. Beton Kolom Type K4 uk. 30 x 30 cm (K-250)
- Beton Ready Mix K-250 0,95 0,95 M3
[panjang] [lebar] [tinggi] [jumlah]
[ 0,30 x 0,30 ] x 5,65 x 1 = 0,51 - Pembesian 1,646.79 1,646.79 Kg
[ 0,30 x 0,30 ] x 4,95 x 1 = 0,45
0,95 [jumlah] [panjang] [jumlah] [koef D16]
- Pembesian 143,83 143,83 Kg
[jumlah] [panjang] [koef D13] [jumlah] Tul- utama tump [ 9.00 x 40.00 ] x 1.00 x 1.58 = 568.17
Tul- utama tump [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55
Tul- utama lap [ 8,00 x 2,83 ] x 1,04 x 1,00 = 23,55 Tul- utama lap [ 9.00 x 40.00 ] x 1.00 x 1.58 = 568.17
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Begel tump [ 2,68 / 0,10 ] x 1,08 x 0,62 x 1,00 = 17,81
Begel lap [ 2,67 / 0,15 ] x 1,08 x 0,62 x 1,00 = 11,86 [panjang] [jarak begel] [panjang] [koef Ø10]
76,77

- Pembesian
Begel tump [ 36.00 / 0.10 ] x 1.38 x 0.62 = 306.28
Tul- utama tump [
[jumlah]
8,00 x
[panjang]
2,48 ] x
[koef D13]
1,04 x
[jumlah]
1,00 = 20,63
Begel lap [ 36.00 / 0.15 ] x 1.38 x 0.62 = 204.18
Tul- utama lap [ 8,00 x 2,48 ] x 1,04 x 1,00 = 20,63
1,646.79
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Begel tump [ 2,33 / 0,10 ] x 1,08 x 0,62 x 1,00 = 15,48
Begel lap [ 2,33 / 0,15 ] x 1,08 x 0,62 x 1,00 = 10,32
67,06 - Bekisting 68.40 68.40 M2
[ 0.30 + 0.65 ] x 72.00 = 68.40
- Bekisting 12,00 12,00 M2
[ 0,60 x 2 ] x 5,35 x 1,00 = 6,42
[ 0,60 x 2 ] x 4,65 x 1,00 = 5,58
12,00 11 Pek. Beton Balok Type B2 uk. 25 x 45 cm (K-250)
8 Pek. Beton Kolom Type K5 uk. 20 x 20 cm (K-250)
- Beton Ready Mix K-250 0,64 0,64 M3
- Beton Ready Mix K-250 10.35 10.35 M3
[
[panjang]
0,20 x
[lebar]
0,20 ] x
[tinggi]
4,00 x
[jumlah]
4,00 = 0,64
[lebar] [tinggi] [panjang]
- Pembesian 119,78 119,78 Kg [ 0.25 x 0.45 ] x 92.00 = 10.35
[jumlah] [panjang] [koef D13] [jumlah]
Tul- utama tump [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34
Tul- utama lap [ 4,00 x 2,00 ] x 1,04 x 4,00 = 33,34
- Pembesian 1,745.11 1,745.11 Kg
[panjang] [jarak begel] [panjang] [koef Ø10] [jumlah]
Begel tump [ 1,90 / 0,10 ] x 0,68 x 0,62 x 4,00 = 31,86 [jumlah] [panjang] [jumlah] [koef D16]
Begel lap [ 1,90 / 0,15 ] x 0,68 x 0,62 x 4,00 = 21,24
119,78 Tul- utama tump [ 7.00 x 51.60 ] x 1.00 x 1.58 = 570.06
- Bekisting 11,28 11,28 M2 Tul- utama lap [ 7.00 x 51.60 ] x 1.00 x 1.58 = 570.06
[ 0,40 x 2,00 ] x 3,53 x 4,00 = 11,28

[panjang] [jarak begel] [panjang] [koef Ø10]


Begel tump [ 46.00 / 0.10 ] x 1.28 x 0.62 = 363.00
Begel lap [ 46.00 / 0.15 ] x 1.28 x 0.62 = 242.00
1,745.11

- Bekisting 82.80 82.80 M2


[ 0.25 + 0.65 ] x 92.00 = 82.80
Tugas Khusus 12 Pek. Beton Balok Type B3 uk. 20 x 35 cm (K-250)
- Beton Ready Mix K-250
[lebar] [tinggi] [panjang]
3,56 3,56 M3

[ 0,20 x 0,35 ] x 50,80 = 3,56

- Pembesian 728,45 728,45 Kg


[jumlah] [panjang] [jumlah] [koef D16]
Tul- utama tump [ 5,00 x 29,95 ] x 1,00 x 1,58 = 236,34
Tul- utama lap [ 5,00 x 29,95 ] x 1,00 x 1,58 = 236,34

[panjang] [jarak begel] [panjang] [koef Ø10]


9 Pek. Beton Kolom Praktis Type KP uk. 13 x 13 cm (K-175) Begel tump [ 25,40 / 0,10 ] x 0,98 x 0,62 = 153,46
- Beton K-175 1.38 1.38 M3 Begel lap [ 25,40 / 0,15 ] x 0,98 x 0,62 = 102,31
[panjang] [lebar] [tinggi] [jumlah] 728,45
[ 0.13 x 0.13 ] x 3.55 x 23.00 = 1.38
- Bekisting 33,02 33,02 M2
- Pembesian 299.29 299.29 Kg [ 0,20 + 0,45 ] x 50,80 = 33,02
[jumlah] [panjang] [koef D10] [jumlah]
Tul- utama tump [ 4.00 x 1.78 ] x 0.62 x 23.00 = 100.67 13 Pek. Beton Balok Type B4 uk. 20 x 30 cm (K-250)
Tul- utama lap [ 4.00 x 1.78 ] x 0.62 x 23.00 = 100.67 - Beton Ready Mix K-250 0,52 0,52 M3
[lebar] [tinggi] [panjang]
[panjang] [jarak begel] [panjang] [koef Ø8] [jumlah] [ 0,20 x 0,30 ] x 8,70 = 0,52
Begel tump [ 1.78 / 0.15 ] x 0.46 x 0.39 x 23.00 = 48.97
Begel lap [ 1.78 / 0.15 ] x 0.46 x 0.39 x 23.00 = 48.97
- Pembesian 90,39 90,39 Kg
[jumlah] [panjang] [jumlah] [koef D13]
299.29
Tul- utama tump [ 5,00 x 4,90 ] x 1,00 x 1,04 = 25,53
Tul- utama lap [ 5,00 x 4,90 ] x 1,00 x 1,04 = 25,53
- Bekisting 21.23 21.23 M2
[ 0.26 x 1.00 ] x 3.55 x 23.00 = 21.23
[panjang] [jarak begel] [panjang] [koef Ø10]
Begel tump [ 4,35 / 0,10 ] x 0,88 x 0,62 = 23,60
10 Pek. Beton Balok Type B1 uk. 30 x 45 cm (K-250)
Begel lap [ 4,35 / 0,15 ] x 0,88 x 0,62 = 15,73
- Beton Ready Mix K-250 9.72 9.72 M3
90,39
[lebar] [tinggi] [panjang]
[ 0.30 x 0.45 ] x 72.00 = 9.72
- Bekisting 5,22 5,22 M2
[ 0,20 + 0,40 ] x 8,70 = 5,22
- Pembesian 1,646.79 1,646.79 Kg
[jumlah] [panjang] [jumlah] [koef D16]
14 Pek. Beton Balok Anak Type BA uk. 13 x 13 cm (K-175)
Tul- utama tump [ 9.00 x 40.00 ] x 1.00 x 1.58 = 568.17
- Beton K-175 0,71 0,71 M3
Tul- utama lap [ 9.00 x 40.00 ] x 1.00 x 1.58 = 568.17
[lebar] [tinggi] [panjang]
[ 0,13 x 0,13 ] x 41,86 = 0,71
[panjang] [jarak begel] [panjang] [koef Ø10]
Begel tump [ 36.00 / 0.10 ] x 1.38 x 0.62 = 306.28
- Pembesian 172,37 172,37 Kg
Begel lap [ 36.00 / 0.15 ] x 1.38 x 0.62 = 204.18
[jumlah] [panjang] [jumlah] [koef D10]
1,646.79 Tul- utama tump [ 4,00 x 23,88 ] x 1,00 x 0,62 = 58,88
Tul- utama lap [ 4,00 x 23,88 ] x 1,00 x 0,62 = 58,88
- Bekisting 68.40 68.40 M2
[ 0.30 + 0.65 ] x 72.00 = 68.40 [panjang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 20,93 / 0,15 ] x 0,50 x 0,39 = 27,31
11 Pek. Beton Balok Type B2 uk. 25 x 45 cm (K-250) Begel lap [ 20,93 / 0,15 ] x 0,50 x 0,39 = 27,31
- Beton Ready Mix K-250 10.35 10.35 M3 172,37
[lebar] [tinggi] [panjang]
[ 0.25 x 0.45 ] x 92.00 = 10.35 - Bekisting 10,88 10,88 M2
[ 0,13 x 2 ] x 41,86 = 10,88
- Pembesian 1,745.11 1,745.11 Kg
[jumlah] [panjang] [jumlah] [koef D16]
Tul- utama tump [ 7.00 x 51.60 ] x 1.00 x 1.58 = 570.06
Tul- utama lap [ 7.00 x 51.60 ] x 1.00 x 1.58 = 570.06

[panjang] [jarak begel] [panjang] [koef Ø10]


Begel tump [ 46.00 / 0.10 ] x 1.28 x 0.62 = 363.00
Begel lap [ 46.00 / 0.15 ] x 1.28 x 0.62 = 242.00
1,745.11

- Bekisting 82.80 82.80 M2


[ 0.25 + 0.65 ] x 92.00 = 82.80
Tugas Khusus
12 Pek. Beton Balok Type B3 uk. 20 x 35 cm (K-250)
- Beton Ready Mix K-250 3,56 3,56 M3
15 Pek. B eton B alok Latey Type BL uk. 13 x 20 cm (K-175)
- Beton K- 175 2,28 2,28 M3
[lebar] [tinggi] [ panjang]
[ 0,13 x 0,20 ] x 87,62 = 2 ,28

[lebar] [tinggi] [panjang] - Pem besian


[jum lah] [ panjang] [jumlah] [koef D12]
520,05 520,05 Kg

Tul- utama tump [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174 ,18

[ 0,20 x 0,35 ] x 50,80 = 3,56 Tul- utama lap [ 4,00

[ panjang]
x 49,05

[jarak begel]
] x 1,00

[ panjang]
x 0,89

[koef Ø8]
= 174 ,18

Begel tump [ 43,81 / 0,10 ] x 0,60 x 0,39 = 103 ,02


Begel lap [ 43,81 / 0,15 ] x 0,60 x 0,39 = 68,68
520 ,05

- Pembesian 728,45 728,45 Kg - Bekis ting


[ 0,20 x 2,00 ] x 87,62 = 35,05
35,05 35, 05 M2

15 Pek. B eton P lat Lantai tebal = 12,5 cm (K-250)

[jumlah] [panjang] [jumlah] [koef D16] - Beton Ready M ix K-250

I [
[X ]
3,500 x
[Y ]
4,750 ] x
[jumlah]
12,00 = 199,50
34,72 34, 72 M3

Tul- utama tump [ 5,00 x 29,95 ] x 1,00 x 1,58 = 236,34


[ 2,700 x 4,750 ] x 1,00 = 12,83
[ 3,600 x 2,250 ] x 5,00 = 40,50
[ 2,800 x 2,250 ] x 1,00 = 6,30
[ 1,880 x 2,250 ] x 1,00 = 4,23

Tul- utama lap [ 5,00 x 29,95 ] x 1,00 x 1,58 = 236,34 II [ 3,600 x 2,780 ] x 1,00 =
263,36

10,01
[ 0,700 x 3,680 ] x 2,00 = 5,15
[ 4,000 x 0,700 ] x 1,00 = 2,80 +
17,96
[luas t ot al] x [t ebal]

[panjang] [jarak begel] [panjang] [koef Ø10] I


II
=
=
263,355
17,960
x
x
0,125
0,100
=
=
32,92
1,80
34,72

Begel tump [ 25,40 / 0,10 ] x 0,98 x 0,62 = 153,46 - Pem besian


I arah -x
arah-y
=
=
3,500
4,750
4.648,05 4. 648,05 Kg

jumlah = 12,000

Begel lap [ 25,40 / 0,15 ] x 0,98 x 0,62 = 102,31 [


[
[ bentang]
3,500
4,750
/
/
[jarak besi]
0,150
0,150
]
]
x
x
[ panjang]
4,85
3,60
x
x
[koef Ø10]
0,62
0,62
x
x
[jumlah]
12,00
12,00
=
=
837,21
843,37 +

728,45 [
[ berat]
1.680,58 x
[lapi s]
2,000 ] = 3.361,16
1. 680,58

arah -x = 2,700
arah-y = 4,750
jumlah = 1,000

- Bekisting 33,02 33,02 M2


[ bentang] [jarak besi] [ panjang] [koef Ø10] [jumlah]
[ 2,700 / 0,150 ] x 4,85 x 0,62 x 1 ,00 = 53,82
[ 4,750 / 0,150 ] x 2,80 x 0,62 x 1 ,00 = 54,66 +
108,48

[ 0,20 + 0,45 ] x 50,80 = 33,02 [


[ berat]
108,48 x
[lapi s]
2,000 ] = 216,97

arah -x = 3,600
arah-y = 2,250
jumlah = 5,000
[ bentang] [jarak besi] [ panjang] [koef Ø10] [jumlah]

13 Pek. Beton Balok Type B4 uk. 20 x 30 cm (K-250)


[ 3,600 / 0,150 ] x 2,35 x 0,62 x 5 ,00 = 173,85
[ 2,250 / 0,150 ] x 3,70 x 0,62 x 5 ,00 = 171,08 +
344,93
[ berat] [lapi s]

- Beton Ready Mix K-250 0,52 0,52 M3 [ 344,93

arah -x
x

=
2,000

2,800
] = 689,86

arah-y = 2,250

[lebar] [tinggi] [panjang] [


jumlah
[ bentang]
2,800
=

/
1,000
[jarak besi]
0,150 ] x
[ panjang]
2,35 x
[koef Ø10]
0,62 x
[jumlah]
1 ,00 = 27,04

[ 0,20 x 0,30 ] x 8,70 = 0,52


[ 2,250 / 0,150 ] x 2,90 x 0,62 x 1 ,00 = 26,82 +
53,86
[ berat] [lapi s]
[ 53,86 x 2,000 ] = 107,72

arah -x = 1,880
arah-y = 2,250

- Pembesian 90,39 90,39 Kg [


jumlah
[ bentang]
1,880
=

/
1,000
[jarak besi]
0,150 ] x
[ panjang]
2,35 x
[koef Ø10]
0,62 x
[jumlah]
1 ,00 = 18,16

[jumlah] [panjang] [jumlah] [koef D13]


[ 2,250 / 0,150 ] x 1,98 x 0,62 x 1 ,00 = 18,31 +
36,47
[ berat] [lapi s]
[ 36,47 x 2,000 ] = 72,94

Tul- utama tump [ 5,00 x 4,90 ] x 1,00 x 1,04 = 25,53 II arah -x = 3,600
arah-y = 2,780

Tul- utama lap [ 5,00 x 4,90 ] x 1,00 x 1,04 = 25,53 [


jumlah
[ bentang]
3,600
=

/
1,000
[jarak besi]
0,150 ] x
[ panjang]
2,88 x
[koef Ø8]
0,39 x
[jumlah]
1 ,00 = 27,27
[ 2,780 / 0,150 ] x 3,70 x 0,39 x 1 ,00 = 27,06 +
54,33
[ berat] [lapi s]
[ 54,328 x 2,000 ] = 108,66

[panjang] [jarak begel] [panjang] [koef Ø10] arah -x


arah-y
=
=
0,700
3,680

Begel tump [ 4,35 / 0,10 ] x 0,88 x 0,62 = 23,60


jumlah = 2,000
[ bentang] [jarak besi] [ panjang] [koef Ø8] [jumlah]
[ 0,700 / 0,150 ] x 3,78 x 0,39 x 2 ,00 = 13,92
[ 3,680 / 0,150 ] x 0,80 x 0,39 x 2 ,00 = 15,49 +

Begel lap [ 4,35 / 0,15 ] x 0,88 x 0,62 = 15,73 [


[ berat]
29,408 x
[lapi s]
2,00 ] = 58,82
29,41

90,39 arah -x
arah-y
jumlah
=
=
=
4,000
0,700
1,000
[ bentang] [jarak besi] [ panjang] [koef Ø8] [jumlah]
[ 4,000 / 0,150 ] x 0,80 x 0,39 x 1 ,00 = 8,42
[ 0,700 / 0,150 ] x 4,10 x 0,39 x 1 ,00 = 7,55 +
15,97

- Bekisting 5,22 5,22 M2 [


[ berat]
15,967 x
[lapi s]
2,00 ] = 31,93

Volume Total = 3 .361,16

[ 0,20 + 0,40 ] x 8,70 = 5,22 216,97


689,86
107,72
72,94
108,66
58,82
31,93 +

14 Pek. Beton Balok Anak Type BA uk. 13 x 13 cm (K-175) - Bekis ting


4 .648,05

294,44 294,44 M2
Keluasan Lantai = 281,32

- Beton K-175 0,71 0,71 M3 Keliling Lantai = 13,13


294,44

[lebar] [tinggi] [panjang]


[ 0,13 x 0,13 ] x 41,86 = 0,71

- Pembesian 172,37 172,37 Kg


[jumlah] [panjang] [jumlah] [koef D10]
Tul- utama tump [ 4,00 x 23,88 ] x 1,00 x 0,62 = 58,88
Tul- utama lap [ 4,00 x 23,88 ] x 1,00 x 0,62 = 58,88

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 20,93 / 0,15 ] x 0,50 x 0,39 = 27,31
Begel lap [ 20,93 / 0,15 ] x 0,50 x 0,39 = 27,31
172,37

- Bekisting 10,88 10,88 M2


[ 0,13 x 2 ] x 41,86 = 10,88
Tugas Khusus
15 Pek. Beton Balok Latey Type BL uk. 13 x 20 cm (K-175)
- Beton K-175 2,28 2,28 M3
[lebar] [tinggi] [panjang]
[ 0,13 x 0,20 ] x 87,62 = 2,28

- Pembesian 520,05 520,05 Kg


[jumlah] [panjang] [jumlah] [koef D12]
Tul- utama tump [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18
Tul- utama lap [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 43,81 / 0,10 ] x 0,60 x 0,39 = 103,02
Begel lap [ 43,81 / 0,15 ] x 0,60 x 0,39 = 68,68
520,05

- Bekisting 35,05 35,05 M2


[ 0,20 x 2,00 ] x 87,62 = 35,05

15 Pek. Beton Plat Lantai tebal = 12,5 cm (K-250)


- Beton Ready Mix K-250 34,72 34,72 M3
[X] [Y] [jumlah]
I [ 3,500 x 4,750 ] x 12,00 = 199,50
[ 2,700 x 4,750 ] x 1,00 = 12,83
[ 3,600 x 2,250 ] x 5,00 = 40,50
[ 2,800 x 2,250 ] x 1,00 = 6,30
[ 1,880 x 2,250 ] x 1,00 = 4,23
263,36

II [ 3,600 x 2,780 ] x 1,00 = 10,01


[ 0,700 x 3,680 ] x 2,00 = 5,15
[ 4,000 x 0,700 ] x 1,00 = 2,80 +
17,96
[luas total] x [tebal]
I = 263,355 x 0,125 = 32,92
II = 17,960 x 0,100 = 1,80
34,72

- Pembesian 4.648,05 4.648,05 Kg


I arah -x = 3,500
arah-y = 4,750
jumlah = 12,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 3,500 / 0,150 ] x 4,85 x 0,62 x 12,00 = 837,21
[ 4,750 / 0,150 ] x 3,60 x 0,62 x 12,00 = 843,37 +
1.680,58
[berat] [lapis]
[ 1.680,58 x 2,000 ] = 3.361,16

arah -x = 2,700
arah-y = 4,750
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 2,700 / 0,150 ] x 4,85 x 0,62 x 1,00 = 53,82
[ 4,750 / 0,150 ] x 2,80 x 0,62 x 1,00 = 54,66 +
108,48
[berat] [lapis]
[ 108,48 x 2,000 ] = 216,97

arah -x = 3,600
arah-y = 2,250
jumlah = 5,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 3,600 / 0,150 ] x 2,35 x 0,62 x 5,00 = 173,85
[ 2,250 / 0,150 ] x 3,70 x 0,62 x 5,00 = 171,08 +
344,93
[berat] [lapis]
[ 344,93 x 2,000 ] = 689,86

arah -x = 2,800
arah-y = 2,250
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 2,800 / 0,150 ] x 2,35 x 0,62 x 1,00 = 27,04
[ 2,250 / 0,150 ] x 2,90 x 0,62 x 1,00 = 26,82 +
53,86
[berat] [lapis]
[ 53,86 x 2,000 ] = 107,72

arah -x = 1,880
arah-y = 2,250
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 1,880 / 0,150 ] x 2,35 x 0,62 x 1,00 = 18,16
[ 2,250 / 0,150 ] x 1,98 x 0,62 x 1,00 = 18,31 +
36,47
[berat] [lapis]
[ 36,47 x 2,000 ] = 72,94

II arah -x = 3,600
arah-y = 2,780
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
[ 3,600 / 0,150 ] x 2,88 x 0,39 x 1,00 = 27,27
[ 2,780 / 0,150 ] x 3,70 x 0,39 x 1,00 = 27,06 +
54,33
[berat] [lapis]
[ 54,328 x 2,000 ] = 108,66

arah -x = 0,700
arah-y = 3,680
jumlah = 2,000
[bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
[ 0,700 / 0,150 ] x 3,78 x 0,39 x 2,00 = 13,92
[ 3,680 / 0,150 ] x 0,80 x 0,39 x 2,00 = 15,49 +
29,41
[berat] [lapis]
[ 29,408 x 2,00 ] = 58,82

arah -x = 4,000
arah-y = 0,700
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
[ 4,000 / 0,150 ] x 0,80 x 0,39 x 1,00 = 8,42
[ 0,700 / 0,150 ] x 4,10 x 0,39 x 1,00 = 7,55 +
15,97
[berat] [lapis]
[ 15,967 x 2,00 ] = 31,93

Volume Total = 3.361,16


216,97
689,86
107,72
72,94
108,66
58,82
31,93 +
4.648,05

- Bekisting 294,44 294,44 M2


Keluasan Lantai = 281,32
Keliling Lantai = 13,13
294,44
15 Pek. Beton Balok Latey Type BL uk. 13 x 20 cm (K-175)
- Beton K-175 2,28 2,28 M3
[lebar] [tinggi] [panjang]
[ 0,13 x 0,20 ] x 87,62 = 2,28

Tugas Khusus
- Pembesian 520,05 520,05 Kg
[jumlah] [panjang] [jumlah] [koef D12]
Tul- utama tump [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18
Tul- utama lap [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 43,81 / 0,10 ] x 0,60 x 0,39 = 103,02
Begel lap [ 43,81 / 0,15 ] x 0,60 x 0,39 = 68,68
520,05

- Bekisting 35,05 35,05 M2


[ 0,20 x 2,00 ] x 87,62 = 35,05

15 Pek. Beton Plat Lantai tebal = 12,5 cm (K-250)


15 Pek. Beton Balok Latey Type BL uk. 13 x 20 cm (K-175) - Beton Ready Mix K-250 34,72 34,72 M3
- Beton K-175 2,28 2,28 M3 [X] [Y] [jumlah]
[lebar] [tinggi] [panjang]
[ 0,13 x 0,20 ] x 87,62 = 2,28
I [ 3,500 x 4,750 ] x 12,00 = 199,50
[ 2,700 x 4,750 ] x 1,00 = 12,83
- Pembesian 520,05 520,05 Kg [ 3,600 x 2,250 ] x 5,00 = 40,50
[jumlah] [panjang] [jumlah] [koef D12]
Tul- utama tump [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18 [ 2,800 x 2,250 ] x 1,00 = 6,30
Tul- utama lap [ 4,00 x 49,05 ] x 1,00 x 0,89 = 174,18 [ 1,880 x 2,250 ] x 1,00 = 4,23
263,36
[pa njang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 43,81 / 0,10 ] x 0,60 x 0,39 = 103,02
Begel lap [ 43,81 / 0,15 ] x 0,60 x 0,39 = 68,68 II [ 3,600 x 2,780 ] x 1,00 = 10,01
520,05 [ 0,700 x 3,680 ] x 2,00 = 5,15
- Bekisting 35,05 35,05 M2 [ 4,000 x 0,700 ] x 1,00 = 2,80 +
[ 0,20 x 2,00 ] x 87,62 = 35,05 17,96
15 Pek. Beton Plat Lantai teba l = 12,5 cm (K-250)
[luas total] x [tebal]
- Beton Ready Mix K-250 34,72 34,72 M3 I = 263,355 x 0,125 = 32,92
[X] [Y] [jumlah] II = 17,960 x 0,100 = 1,80
I [ 3,500 x 4,750 ] x 12,00 = 199,50
[ 2,700 x 4,750 ] x 1,00 = 12,83 34,72
[ 3,600 x 2,250 ] x 5,00 = 40,50
[ 2,800 x 2,250 ] x 1,00 = 6,30 - Pembesian 4.648,05 4.648,05 Kg
[ 1,880 x 2,250 ] x 1,00 = 4,23
263,36 I arah -x = 3,500
arah-y = 4,750
II [ 3,600 x 2,780 ] x 1,00 = 10,01 jumlah = 12,000
[ 0,700 x 3,680 ] x 2,00 = 5,15
[ 4,000 x 0,700 ] x 1,00 = 2,80 + [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
17,96 [ 3,500 / 0,150 ] x 4,85 x 0,62 x 12,00 = 837,21
[luas total] x [tebal] [ 4,750 / 0,150 ] x 3,60 x 0,62 x 12,00 = 843,37 +
I = 263,355 x 0,125 = 32,92
II = 17,960 x 0,100 = 1,80 1.680,58
34,72 [berat] [lapis]
- Pembesian 4.648,05 4.648,05 Kg
[ 1.680,58 x 2,000 ] = 3.361,16
I arah -x = 3,500
arah-y = 4,750 arah -x = 2,700
jumlah = 12,000
[benta ng] [jarak besi] [panjang] [koe f Ø10] [jumlah] arah-y = 4,750
[ 3,500 / 0,150 ] x 4,85 x 0,62 x 12,00 = 837,21 jumlah = 1,000
[ 4,750 / 0,150 ] x 3,60 x 0,62 x 12,00 = 843,37 + [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
1.680,58
[berat] [lapis] [ 2,700 / 0,150 ] x 4,85 x 0,62 x 1,00 = 53,82
[ 1.680,58 x 2,000 ] = 3.361,16 [ 4,750 / 0,150 ] x 2,80 x 0,62 x 1,00 = 54,66 +
108,48
arah -x = 2,700
arah-y = 4,750 [berat] [lapis]
jumlah = 1,000 [ 108,48 x 2,000 ] = 216,97
[benta ng] [jarak besi] [panjang] [koe f Ø10] [jumlah]
[ 2,700 / 0,150 ] x 4,85 x 0,62 x 1,00 = 53,82
[ 4,750 / 0,150 ] x 2,80 x 0,62 x 1,00 = 54,66 + arah -x = 3,600
108,48 arah-y = 2,250
[berat] [lapis]
[ 108,48 x 2,000 ] = 216,97
jumlah = 5,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
arah -x = 3,600 [ 3,600 / 0,150 ] x 2,35 x 0,62 x 5,00 = 173,85
arah-y = 2,250
jumlah = 5,000 [ 2,250 / 0,150 ] x 3,70 x 0,62 x 5,00 = 171,08 +
[benta ng] [jarak besi] [panjang] [koe f Ø10] [jumlah] 344,93
[ 3,600 / 0,150 ] x 2,35 x 0,62 x 5,00 = 173,85 [berat] [lapis]
[ 2,250 / 0,150 ] x 3,70 x 0,62 x 5,00 = 171,08 +
344,93 [ 344,93 x 2,000 ] = 689,86
[berat] [lapis]
[ 344,93 x 2,000 ] = 689,86 arah -x = 2,800
arah -x = 2,800 arah-y = 2,250
arah-y = 2,250 jumlah = 1,000
jumlah = 1,000 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[benta ng] [jarak besi] [panjang] [koe f Ø10] [jumlah]
[ 2,800 / 0,150 ] x 2,35 x 0,62 x 1,00 = 27,04 [ 2,800 / 0,150 ] x 2,35 x 0,62 x 1,00 = 27,04
[ 2,250 / 0,150 ] x 2,90 x 0,62 x 1,00 = 26,82 + [ 2,250 / 0,150 ] x 2,90 x 0,62 x 1,00 = 26,82 +
53,86
[berat] [lapis]
53,86
[ 53,86 x 2,000 ] = 107,72 [berat] [lapis]
[ 53,86 x 2,000 ] = 107,72
arah -x = 1,880
arah-y = 2,250
jumlah = 1,000 arah -x = 1,880
[benta ng] [jarak besi] [panjang] [koe f Ø10] [jumlah]
[ 1,880 / 0,150 ] x 2,35 x 0,62 x 1,00 = 18,16 arah-y = 2,250
[ 2,250 / 0,150 ] x 1,98 x 0,62 x 1,00 = 18,31 + jumlah = 1,000
36,47 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[berat] [lapis]
[ 36,47 x 2,000 ] = 72,94 [ 1,880 / 0,150 ] x 2,35 x 0,62 x 1,00 = 18,16
[ 2,250 / 0,150 ] x 1,98 x 0,62 x 1,00 = 18,31 +
36,47
II arah -x = 3,600
arah-y = 2,780 [berat] [lapis]
jumlah = 1,000 [ 36,47 x 2,000 ] = 72,94
[benta ng] [jarak besi] [panjang] [koe f Ø8] [jumlah]
[ 3,600 / 0,150 ] x 2,88 x 0,39 x 1,00 = 27,27
[ 2,780 / 0,150 ] x 3,70 x 0,39 x 1,00 = 27,06 +
54,33 II arah -x = 3,600
[berat] [lapis]
[ 54,328 x 2,000 ] = 108,66 arah-y = 2,780
jumlah = 1,000
arah -x = 0,700 [bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
arah-y = 3,680
jumlah = 2,000 [ 3,600 / 0,150 ] x 2,88 x 0,39 x 1,00 = 27,27
[benta ng] [jarak besi] [panjang] [koe f Ø8] [jumlah] [ 2,780 / 0,150 ] x 3,70 x 0,39 x 1,00 = 27,06 +
[ 0,700 / 0,150 ] x 3,78 x 0,39 x 2,00 = 13,92 54,33
[ 3,680 / 0,150 ] x 0,80 x 0,39 x 2,00 = 15,49 +
29,41 [berat] [lapis]
[berat] [lapis] [ 54,328 x 2,000 ] = 108,66
[ 29,408 x 2,00 ] = 58,82

arah -x = 4,000 arah -x = 0,700


arah-y = 0,700 arah-y = 3,680
jumlah = 1,000
[benta ng] [jarak besi] [panjang] [koe f Ø8] [jumlah]
jumlah = 2,000
[ 4,000 / 0,150 ] x 0,80 x 0,39 x 1,00 = 8,42 [bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
[ 0,700 / 0,150 ] x 4,10 x 0,39 x 1,00 = 7,55 + [ 0,700 / 0,150 ] x 3,78 x 0,39 x 2,00 = 13,92
15,97
[berat] [lapis] [ 3,680 / 0,150 ] x 0,80 x 0,39 x 2,00 = 15,49 +
[ 15,967 x 2,00 ] = 31,93 29,41
[berat] [lapis]
Volume Total = 3.361,16
216,97 [ 29,408 x 2,00 ] = 58,82
689,86
107,72 arah -x = 4,000
72,94
108,66 arah-y = 0,700
58,82 jumlah = 1,000
31,93 + [bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
4.648,05
[ 4,000 / 0,150 ] x 0,80 x 0,39 x 1,00 = 8,42
- Bekisting 294,44 294,44 M2 [ 0,700 / 0,150 ] x 4,10 x 0,39 x 1,00 = 7,55 +
Keluasan Lantai = 281,32
Keliling Lantai = 13,13
15,97
294,44 [berat] [lapis]
[ 15,967 x 2,00 ] = 31,93

Volume Total = 3.361,16


216,97
689,86
107,72
72,94
108,66
58,82
31,93 +
4.648,05

- Bekisting 294,44 294,44 M2


Keluasan Lantai = 281,32
Keliling Lantai = 13,13
294,44
16 Pek. Beton Ram tebal = 12,5 cm (K-250)
- Beton Ready Mix K-250 14,04 14,04 M3

Tugas Khusus
[panjang] [lebar] [tebal]
- Plat Ram [ 1,70 x 40,36 ] x 0,125 = 8,58
- Bordes 1 [ 3,50 x 2,10 ] x 0,125 = 0,92
- Bordes 2 [ 1,70 x 2,50 ] x 0,125 = 0,53 +
- Bordes 3 [ 3,50 x 2,10 ] x 0,125 = 0,92
- Bordes 4 [ 1,70 x 2,50 ] x 0,125 = 0,53 +
11,48
[lebar] [tinggi] [panjang] [jumlah]
- Balok B5 Ram [ 0,15 x 0,20 ] x 3,35 x 4,00 = 0,40
- Balok B5 Ram [ 0,15 x 0,20 ] x 1,48 x 8,00 = 0,36
16 Pek. Beton Ram tebal = 12,5 cm (K-250) - Balok BA Ram [ 0,13 x 0,13 ] x 106,92 x 1,00 = 1,81
- Beton Ready Mix K-250 14,04 14,0 4 M3
[panjang] [lebar] [te bal] 2,56
- Plat Ram [ 1,70 x 40,36 ] x 0,125 = 8,58
- Bordes 1 [ 3,50 x 2,10 ] x 0,125 = 0,92
- Bordes 2 [ 1,70 x 2,50 ] x 0,125 = 0,53 +
- Bordes 3 [ 3,50 x 2,10 ] x 0,125 = 0,92
- Pembesian 2.633,25 2.633,25 Kg
- Bordes 4 [ 1,70 x 2,50 ] x 0,125 = 0,53
11,48
+ - Plat Ram arah -x = 1,700
[lebar] [tinggi ] [panj ang] [jumlah] arah-y = 40,360
- Bal ok B5 Ram [ 0,15 x 0,20 ] x 3,35 x 4,00 = 0,40
- Bal ok B5 Ram [ 0,15 x 0,20 ] x 1,48 x 8,00 = 0,36 jumlah = 1,000
- Bal ok BA Ram [ 0,13 x 0,13 ] x 106,92 x 1,00 = 1,81
2,56 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
- Pembesian 2 .6 33,25 2 .633 ,25 Kg [ 40,360 / 0,150 ] x 1,80 x 0,62 x 1,00 = 298,58
- Pla t Ra m arah -x = 1,700
arah-y = 40,360
jumlah
[be ntang]
= 1,000
[jarak be si] [panjang] [koef Ø10] [juml ah]
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
[ 40,360 / 0,150 ] x 1,80 x 0,62 x 1,00 = 298,58 [ 1,700 / 0,150 ] x 40,46 x 1,04 x 1,00 = 477,75 +
[be ntang] [jarak be si] [panjang] [koef Ø13] [juml ah] 776,34
[ 1,700 / 0,150 ] x 40,46 x 1,04 x 1,00 = 477,75 +
776,34 [berat] [lapis]
[
[be rat]
776,336 x
[lapi s]
2,00 ] = 1.552,67
[ 776,336 x 2,00 ] = 1.552,67
- Bordes 1 arah -x = 3,500
arah-y = 2,100 - Bordes 1 arah -x = 3,500
jumlah = 1,000
[be ntang] [jarak be si] [panjang] [koef Ø10] [juml ah] arah-y = 2,100
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07
jumlah = 1,000
[be ntang] [jarak be si] [panjang] [koef Ø13] [juml ah]
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[be rat] [lapi s]
84,56 [ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07
[ 84,555 x 2,00 ] = 169,11

- Bordes 2 arah -x = 1,700 [bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
arah-y = 2,500
jumlah = 1,000 [ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
[be ntang] [jarak be si] [panjang] [koef Ø10] [juml ah]
[ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50 84,56
[be ntang] [jarak be si] [panjang] [koef Ø13] [juml ah]
[berat] [lapis]
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70
49,20
+ [ 84,555 x 2,00 ] = 169,11
[be rat] [lapi s]
[ 49,196 x 2,00 ] = 98,39
- Bordes 2 arah -x = 1,700
- Bordes 3 arah -x = 3,500
arah-y = 2,100 arah-y = 2,500
jumlah = 1,000
[be ntang] [jarak be si] [panjang] [koef Ø10] [juml ah]
jumlah = 1,000
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[be ntang] [jarak be si] [panjang] [koef Ø13] [juml ah] [ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
84,56
[be rat] [lapi s]
[ 84,555 x 2,00 ] = 169,11 [bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
- Bordes 4 arah -x = 1,700 [ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
arah-y
jumlah
=
=
2,500
1,000
49,20
[
[be ntang]
2,500 /
[jarak be si]
0,150 ] x
[panjang]
1,80 x
[koef Ø10]
0,62 x
[juml ah]
1,00 = 18,50
[berat] [lapis]
[ 49,196 x 2,00 ] = 98,39
[be ntang] [jarak be si] [panjang] [koef Ø13] [juml ah]
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
49,20
[be rat] [lapi s] - Bordes 3 arah -x = 3,500
[ 49,196 x 2,00 ] = 98,39
arah-y = 2,100
- Balok B5 Ra m
Tul- utama tump [
[juml ah]
4,00 x
[panjang]
6,70 ] x
[jumlah]
1,00 x
[koef D12]
0,89 = 23,79
jumlah = 1,000
Tul- utama l ap [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[panj ang] [jarak begel] [panj ang] [ko ef Ø8] [ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07
Bege l tump [ 6,70 / 0,10 ] x 0,64 x 0,39 = 16,81
Be gel lap [ 6,70 / 0,15 ] x 0,64 x 0,39 = 11,21
75,61
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
- Balok B5 Ra m
Tul- utama tump [
[juml ah]
4,00 x
[panjang]
5,92 ] x
[jumlah]
1,00 x
[koef D12]
0,89 = 21,02
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
Tul- utama l ap [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02 84,56
[panj ang] [jarak begel] [panj ang] [ko ef Ø8] [berat] [lapis]
Bege l tump [ 5,92 / 0,10 ] x 0,64 x 0,39 = 14,86
Be gel lap [ 5,92 / 0,15 ] x 0,64 x 0,39 = 9,90 [ 84,555 x 2,00 ] = 169,11
66,80

- Balok BA Ra m
Tul- utama tump [
[juml ah]
4,00 x
[panjang]
53,46 ] x
[jumlah]
1,00 x
[koef D10]
0,62 = 131,83
- Bordes 4 arah -x = 1,700
Tul- utama l ap [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83 arah-y = 2,500
[panj ang] [jarak begel] [panj ang] [ko ef Ø8] jumlah = 1,000
Bege l tump [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
Be gel lap [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75 [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
403,16
Volume Total = 1.552,67 [ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50
169,11
98,39
169,11
98,39
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
75,61 [ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
66,80
403,16 + 49,20
2.633,25
[berat] [lapis]
- Bek isting Plat 91,81 91,8 1 M2
[panjang] [lebar] [ 49,196 x 2,00 ] = 98,39
- Plat Ram [ 40,36 x 1,70 ] = 68,61
- Bordes 1 [ 2,10 x 3,50 ] = 7,35
- Bordes 2 [ 2,50 x 1,70 ] = 4,25 - Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]
- Bordes 3 [ 2,10 x 3,50 ] = 7,35
- Bordes 4 [ 2,50 x 1,70 ] = 4,25 + Tul- utama tump [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79
91,81
Tul- utama lap [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79
- Bek isting Balok 35,37 35,3 7 M2
- Balok B5 Ram [ 0,15 + 0,15 ] x 13,40 = 4,02
- Balok B5 Ram [ 0,15 + 0,15 ] x 11,84 = 3,55
[panjang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 6,70 / 0,10 ] x 0,64 x 0,39 = 16,81
Begel lap [ 6,70 / 0,15 ] x 0,64 x 0,39 = 11,21
75,61

- Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02
Tul- utama lap [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 5,92 / 0,10 ] x 0,64 x 0,39 = 14,86
Begel lap [ 5,92 / 0,15 ] x 0,64 x 0,39 = 9,90
66,80

- Balok BA Ram [jumlah] [panjang] [jumlah] [koef D10]


Tul- utama tump [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83
Tul- utama lap [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
Begel lap [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
403,16
Volume Total = 1.552,67
169,11
98,39
169,11
98,39
75,61
66,80
403,16 +
2.633,25

- Bekisting Plat 91,81 91,81 M2


[panjang] [lebar]
- Plat Ram [ 40,36 x 1,70 ] = 68,61
- Bordes 1 [ 2,10 x 3,50 ] = 7,35
- Bordes 2 [ 2,50 x 1,70 ] = 4,25
- Bordes 3 [ 2,10 x 3,50 ] = 7,35
- Bordes 4 [ 2,50 x 1,70 ] = 4,25 +
91,81

- Bekisting Balok 35,37 35,37 M2


- Balok B5 Ram [ 0,15 + 0,15 ] x 13,40 = 4,02
- Balok B5 Ram [ 0,15 + 0,15 ] x 11,84 = 3,55
Tugas Khusus 16 Pek. B eton Ram tebal = 12,5 cm (K -250)
- Beto n R eady M ix K- 250

- Plat Ram
- Bordes 1
- Bordes 2
- Bordes 3
- Bordes 4

- Balok B 5 Ram
- Balok B 5 Ram
- Balok B A Ram

- Pembes ian
- Plat Ram
[
[
[
[
[

[
[
[
[p anjang]
1,70
3,50
1,70
3,50
1,70

[lebar]
x
x
x
x
x

0,15
0,15
0,13

arah -x
x
x
x

=
[ lebar]
40,36
2,10
2,50
2,10
2,50

[t in ggi]
0,20
0,20
0,13

1,700
]
]
]
]
]

]
]
]
x
x
x
x
x

x
x
x
[tebal]
0,125
0,125
0,125
0,125
0,125

[ panjan g]
3,35
1,48
106,92
x
x
x
[jumlah]
4,00
8,00
1,00
=
=
=
=
=

=
=
=
8,58
0,92
0,53
0,92
0,53
11,48

0,40
0,36
1,81
2,56
+

+
14,04

2.633,25
14,04

2. 633,25
M3

Kg

arah-y = 40,360
jumlah = 1,000
[b ent ang] [ jarak besi] [pan jan g] [koef Ø10] [jumlah]
[ 40,36 0 / 0,150 ] x 1,80 x 0,62 x 1,00 = 298,58

16 Pek. Beton Ram tebal = 12,5 cm (K-250) [b ent ang] [ jarak besi] [pan jan g] [koef Ø13] [jumlah]
[ 1,700 / 0,150 ] x 40,46 x 1,04 x 1,00 = 477,75 +
- Beton Ready Mix K-250 14,04 14,04 M3 776,34
[panjang] [lebar] [tebal] [b erat] [ lap is]
- Plat Ram [ 1,70 x 40,36 ] x 0,125 = 8,58 [ 776,336 x 2,00 ] = 1.552,67

- Bordes 1 [ 3,50 x 2,10 ] x 0,125 = 0,92 - Bordes 1 arah -x = 3,500


- Bordes 2 [ 1,70 x 2,50 ] x 0,125 = 0,53 + arah-y = 2,100
jumlah = 1,000
- Bordes 3 [ 3,50 x 2,10 ] x 0,125 = 0,92 [b ent ang] [ jarak besi] [pan jan g] [koef Ø10] [jumlah]
- Bordes 4 [ 1,70 x 2,50 ] x 0,125 = 0,53 + [ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07

11,48 [b ent ang] [ jarak besi] [pan jan g] [koef Ø13] [jumlah]
[lebar] [tinggi] [panjang] [jumlah] [ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
84,56
- Balok B5 Ram [ 0,15 x 0,20 ] x 3,35 x 4,00 = 0,40 [b erat] [ lap is]
- Balok B5 Ram [ 0,15 x 0,20 ] x 1,48 x 8,00 = 0,36 [ 84,55 5 x 2,00 ] = 169,11
- Balok BA Ram [ 0,13 x 0,13 ] x 106,92 x 1,00 = 1,81 - Bordes 2 arah -x = 1,700
2,56 arah-y = 2,500
jumlah = 1,000
[b ent ang] [ jarak besi] [pan jan g] [koef Ø10] [jumlah]
- Pembesian 2.633,25 2.633,25 Kg [ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50
- Plat Ram arah -x = 1,700 [b ent ang] [ jarak besi] [pan jan g] [koef Ø13] [jumlah]
arah-y = 40,360 [ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
49,20
jumlah = 1,000 [b erat] [ lap is]
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] [ 49,19 6 x 2,00 ] = 98,39
[ 40,360 / 0,150 ] x 1,80 x 0,62 x 1,00 = 298,58
- Bordes 3 arah -x = 3,500
arah-y = 2,100
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] jumlah = 1,000
[b ent ang] [ jarak besi] [pan jan g] [koef Ø10] [jumlah]
[ 1,700 / 0,150 ] x 40,46 x 1,04 x 1,00 = 477,75 + [ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07
776,34
[b ent ang] [ jarak besi] [pan jan g] [koef Ø13] [jumlah]
[berat] [lapis] [ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 +
[ 776,336 x 2,00 ] = 1.552,67 84,56
[b erat] [ lap is]
[ 84,55 5 x 2,00 ] = 169,11
- Bordes 1 arah -x = 3,500
- Bordes 4 arah -x = 1,700
arah-y = 2,100 arah-y = 2,500
jumlah = 1,000 jumlah = 1,000
[b ent ang] [ jarak besi] [pan jan g] [koef Ø10] [jumlah]
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] [ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07
[b ent ang] [ jarak besi] [pan jan g] [koef Ø13] [jumlah]
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] 49,20
[b erat] [ lap is]
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 + [ 49,19 6 x 2,00 ] = 98,39
84,56
[berat] [lapis] - Balo k B5 Ram [jumlah] [p an jang] [ jumla h] [koef D12]
Tul- ut am a tump [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79
[ 84,555 x 2,00 ] = 169,11 Tul- utama lap [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79

[panj ang ] [jarak begel] [ panjan g] [koef Ø8]


- Bordes 2 arah -x = 1,700 Begel t um p [ 6,70 / 0,10 ] x 0,64 x 0,39 = 16,81
arah-y = 2,500 Begel lap [ 6,70 / 0,15 ] x 0,64 x 0,39 = 11,21
75,61
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] - Balo k B5 Ram [jumlah] [p an jang] [ jumla h] [koef D12]
Tul- ut am a tump [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02
[ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50 Tul- utama lap [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02

[panj ang ] [jarak begel] [ panjan g] [koef Ø8]


[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] Begel t um p [ 5,92 / 0,10 ] x 0,64 x 0,39 = 14,86
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 + Begel lap [ 5,92 / 0,15 ] x 0,64 x 0,39 = 9,90
66,80
49,20
[berat] [lapis] - Balok BA Ram [jumlah] [p an jang] [ jumla h] [koef D10]
Tul- ut am a tump [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83
[ 49,196 x 2,00 ] = 98,39 Tul- utama lap [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83

[panj ang ] [jarak begel] [ panjan g] [koef Ø8]


- Bordes 3 arah -x = 3,500 Begel t um p [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
arah-y = 2,100 Begel lap [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
403,16
jumlah = 1,000 Volume Tot al = 1.552,67
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] 169,11
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07 98,39
169,11
98,39
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] 75,61
66,80
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 + 403,16 +
84,56 2.633,25

[berat] [lapis] - Bekisting Plat 91,81 91,81 M2


[ 84,555 x 2,00 ] = 169,11 [p anjang] [ lebar]
- P lat Ram [ 40,36 x 1,70 ] = 68,61
- B ordes 1 [ 2,10 x 3,50 ] = 7,35
- Bordes 4 arah -x = 1,700 - B ordes 2 [ 2,50 x 1,70 ] = 4,25
- B ordes 3 [ 2,10 x 3,50 ] = 7,35
arah-y = 2,500 - B ordes 4 [ 2,50 x 1,70 ] = 4,25 +
jumlah = 1,000 91,81
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] - Bekisting Balo k 35,37 35,37 M2
[ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50 - Balok B5 Ram [ 0,15 + 0,15 ] x 13,40 = 4,02
- Balok B5 Ram [ 0,15 + 0,15 ] x 11,84 = 3,55

[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]


[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 +
49,20
[berat] [lapis]
[ 49,196 x 2,00 ] = 98,39

- Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79
Tul- utama lap [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 6,70 / 0,10 ] x 0,64 x 0,39 = 16,81
Begel lap [ 6,70 / 0,15 ] x 0,64 x 0,39 = 11,21
75,61

- Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02
Tul- utama lap [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 5,92 / 0,10 ] x 0,64 x 0,39 = 14,86
Begel lap [ 5,92 / 0,15 ] x 0,64 x 0,39 = 9,90
66,80

- Balok BA Ram [jumlah] [panjang] [jumlah] [koef D10]


Tul- utama tump [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83
Tul- utama lap [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
Begel lap [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
403,16
Volume Total = 1.552,67
169,11
98,39
169,11
98,39
75,61
66,80
403,16 +
2.633,25

- Bekisting Plat 91,81 91,81 M2


[panjang] [lebar]
- Plat Ram [ 40,36 x 1,70 ] = 68,61
- Bordes 1 [ 2,10 x 3,50 ] = 7,35
- Bordes 2 [ 2,50 x 1,70 ] = 4,25
- Bordes 3 [ 2,10 x 3,50 ] = 7,35
- Bordes 4 [ 2,50 x 1,70 ] = 4,25 +
91,81

- Bekisting Balok 35,37 35,37 M2


- Balok B5 Ram [ 0,15 + 0,15 ] x 13,40 = 4,02
- Balok B5 Ram [ 0,15 + 0,15 ] x 11,84 = 3,55
Tugas Khusus
16 Pek. Beton Ram tebal = 12,5 cm (K-250)
- Beton Ready Mix K-250
[panjang] [lebar] [tebal]
14,04 14,04 M3
- Balok BA Ram [ 0,13 + 0,13 ] x 106,92 = 27,80
- Plat Ram [ 1,70 x 40,36 ] x 0,125 = 8,58 35,37
- Bordes 1 [ 3,50 x 2,10 ] x 0,125 = 0,92
- Bordes 2 [ 1,70 x 2,50 ] x 0,125 = 0,53 + 17 Pek. Beton Tangga t.125 cm (K-250)
- Bordes 3 [ 3,50 x 2,10 ] x 0,125 = 0,92 - Beton Ready Mix K-250 2,74 2,74 M3
- Bordes 4 [ 1,70 x 2,50 ] x 0,125 = 0,53 + [panjang] [lebar] [tebal]
11,48 - Plat Tangga [ 7,00 x 1,26 ] x 0,125 = 1,10
[lebar] [tinggi] [panjang] [jumlah] - Bordes [ 2,87 x 1,36 ] x 0,125 = 0,49
- Balok B5 Ram [ 0,15 x 0,20 ] x 3,35 x 4,00 = 0,40 1,59
- Balok B5 Ram [ 0,15 x 0,20 ] x 1,48 x 8,00 = 0,36 [lebar] [tinggi] [panjang] [jumlah]
- Balok BA Ram [ 0,13 x 0,13 ] x 106,92 x 1,00 = 1,81 - Balok B5 Tangga [ 0,15 x 0,20 ] x 2,87 x 1,00 = 0,09
2,56 - Balok BA Tangga [ 0,13 x 0,13 ] x 9,97 x 1,00 = 0,17
0,25
- Pembesian 2.633,25 2.633,25 Kg [Penampang] [Panjang] [jumlah]
- Plat Ram arah -x = 1,700 - Anak Tangga [ 0,03 x 1,50 ] x 22,00 = 0,89
arah-y = 40,360
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] - Pembesian 405,41 405,41 Kg
[ 40,360 / 0,150 ] x 1,80 x 0,62 x 1,00 = 298,58 - Plat Tangga arah -x = 1,260
arah-y = 7,000
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 1,700 / 0,150 ] x 40,46 x 1,04 x 1,00 = 477,75 +
[ 7,00 / 0,150 ] x 1,36 x 0,62 x 1,00 = 39,13
776,34
[berat] [lapis]
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
[ 776,336 x 2,00 ] = 1.552,67
[ 1,26 / 0,150 ] x 7,10 x 1,04 x 1,00 = 62,14 +
101,27
- Bordes 1 arah -x = 3,500
[berat] [lapis]
arah-y = 2,100
[ 101,265 x 2 ] = 202,53
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
- Bordes arah -x = 1,360
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07 arah-y = 2,870
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] [bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 + [ 2,870 / 0,150 ] x 1,46 x 0,62 x 1,00 = 17,22
84,56
[berat] [lapis] [bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
[ 84,555 x 2,00 ] = 169,11 [ 1,360 / 0,150 ] x 2,97 x 1,04 x 1,00 = 28,06 +
45,28
- Bordes 2 arah -x = 1,700 [berat] [lapis]
arah-y = 2,500 [ 45,278 x 2 ] = 90,56
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] - Balok B5 Tangga [jumlah] [panjang] [jumlah] [koef D12]
[ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50 Tul- utama tump [ 4,00 x 1,44 ] x 1,00 x 0,89 = 5,10
Tul- utama lap [ 4,00 x 1,44 ] x 1,00 x 0,89 = 5,10
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 + [panjang] [jarak begel] [panjang] [koef Ø8]
49,20 Begel tump [ 1,44 / 0,10 ] x 0,64 x 0,39 = 3,60
[berat] [lapis] Begel lap [ 1,44 / 0,15 ] x 0,64 x 0,39 = 2,40
[ 49,196 x 2,00 ] = 98,39 16,19

- Bordes 3 arah -x = 3,500 - Balok BA Tangga [jumlah] [panjang] [jumlah] [koef D10]
arah-y = 2,100 Tul- utama tump [ 4,00 x 4,99 ] x 1,00 x 0,62 = 12,29
jumlah = 1,000 Tul- utama lap [ 4,00 x 4,99 ] x 1,00 x 0,62 = 12,29
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 2,100 / 0,150 ] x 3,60 x 0,62 x 1,00 = 31,07 [panjang] [jarak begel] [panjang] [koef Ø8]
Begel tump [ 4,99 / 0,15 ] x 0,50 x 0,39 = 6,50
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] Begel lap [ 4,99 / 0,15 ] x 0,50 x 0,39 = 6,50
[ 3,500 / 0,150 ] x 2,20 x 1,04 x 1,00 = 53,48 + 37,59
84,56
[berat] [lapis] - Anak Tangga [jumlah] [panjang] [jumlah] [koef D10]
[ 84,555 x 2,00 ] = 169,11 Tul- utama [ 1,00 x 1,50 ] x 22,00 x 0,62 = 20,34

- Bordes 4 arah -x = 1,700 [panjang] [jarak begel] [panjang] [koef Ø8]


arah-y = 2,500 Begel [ 1,50 / 0,15 ] x 9,68 x 0,39 = 38,19
jumlah = 1,000 58,54
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah] Volume Total = 202,53
[ 2,500 / 0,150 ] x 1,80 x 0,62 x 1,00 = 18,50 90,56
16,19
[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah] 37,59
[ 1,700 / 0,150 ] x 2,60 x 1,04 x 1,00 = 30,70 + 58,54 +
49,20 405,41
[berat] [lapis]
[ 49,196 x 2,00 ] = 98,39

- Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79
Tul- utama lap [ 4,00 x 6,70 ] x 1,00 x 0,89 = 23,79

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 6,70 / 0,10 ] x 0,64 x 0,39 = 16,81
Begel lap [ 6,70 / 0,15 ] x 0,64 x 0,39 = 11,21
75,61

- Balok B5 Ram [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02
Tul- utama lap [ 4,00 x 5,92 ] x 1,00 x 0,89 = 21,02

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 5,92 / 0,10 ] x 0,64 x 0,39 = 14,86
Begel lap [ 5,92 / 0,15 ] x 0,64 x 0,39 = 9,90
66,80

- Balok BA Ram [jumlah] [panjang] [jumlah] [koef D10]


Tul- utama tump [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83
Tul- utama lap [ 4,00 x 53,46 ] x 1,00 x 0,62 = 131,83

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
Begel lap [ 53,46 / 0,15 ] x 0,50 x 0,39 = 69,75
403,16
Volume Total = 1.552,67
169,11
98,39
169,11
98,39
75,61
66,80
403,16 +
2.633,25

- Bekisting Plat 91,81 91,81 M2


[panjang] [lebar]
- Plat Ram [ 40,36 x 1,70 ] = 68,61
- Bordes 1 [ 2,10 x 3,50 ] = 7,35
- Bordes 2 [ 2,50 x 1,70 ] = 4,25
- Bordes 3 [ 2,10 x 3,50 ] = 7,35
- Bordes 4 [ 2,50 x 1,70 ] = 4,25 +
91,81

- Bekisting Balok 35,37 35,37 M2


- Balok B5 Ram [ 0,15 + 0,15 ] x 13,40 = 4,02
- Balok B5 Ram [ 0,15 + 0,15 ] x 11,84 = 3,55
- Balok BA Ram [ 0,13 + 0,13 ] x 106,92 = 27,80
35,37

Tugas Khusus
17 Pek. Beton Tangga t.125 cm (K-250)
- Beton Ready Mix K-250 2,74 2,74 M3
[panjang] [lebar] [tebal]
- Plat Tangga [ 7,00 x 1,26 ] x 0,125 = 1,10
- Bordes [ 2,87 x 1,36 ] x 0,125 = 0,49
1,59
[lebar] [tinggi] [panjang] [jumlah]
- Balok B5 Tangga [ 0,15 x 0,20 ] x 2,87 x 1,00 = 0,09
- Balok BA Tangga [ 0,13 x 0,13 ] x 9,97 x 1,00 = 0,17
0,25
[Penampang] [Panjang] [jumlah]
- Anak Tangga [ 0,03 x 1,50 ] x 22,00 = 0,89

- Pembesian 405,41 405,41 Kg


- Plat Tangga arah -x = 1,260
arah-y = 7,000
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 7,00 / 0,150 ] x 1,36 x 0,62 x 1,00 = 39,13

[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]


[ 1,26 / 0,150 ] x 7,10 x 1,04 x 1,00 = 62,14 +
101,27
[berat] [lapis]
[ 101,265 x 2 ] = 202,53

- Bordes arah -x = 1,360


arah-y = 2,870
jumlah = 1,000
[bentang] [jarak besi] [panjang] [koef Ø10] [jumlah]
[ 2,870 / 0,150 ] x 1,46 x 0,62 x 1,00 = 17,22

[bentang] [jarak besi] [panjang] [koef Ø13] [jumlah]


[ 1,360 / 0,150 ] x 2,97 x 1,04 x 1,00 = 28,06 +
45,28
[berat] [lapis]
[ 45,278 x 2 ] = 90,56

- Balok B5 Tangga [jumlah] [panjang] [jumlah] [koef D12]


Tul- utama tump [ 4,00 x 1,44 ] x 1,00 x 0,89 = 5,10
Tul- utama lap [ 4,00 x 1,44 ] x 1,00 x 0,89 = 5,10

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 1,44 / 0,10 ] x 0,64 x 0,39 = 3,60
Begel lap [ 1,44 / 0,15 ] x 0,64 x 0,39 = 2,40
16,19

- Balok BA Tangga [jumlah] [panjang] [jumlah] [koef D10]


Tul- utama tump [ 4,00 x 4,99 ] x 1,00 x 0,62 = 12,29
Tul- utama lap [ 4,00 x 4,99 ] x 1,00 x 0,62 = 12,29

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel tump [ 4,99 / 0,15 ] x 0,50 x 0,39 = 6,50
Begel lap [ 4,99 / 0,15 ] x 0,50 x 0,39 = 6,50
37,59

- Anak Tangga [jumlah] [panjang] [jumlah] [koef D10]


Tul- utama [ 1,00 x 1,50 ] x 22,00 x 0,62 = 20,34

[panjang] [jarak begel] [panjang] [koef Ø8]


Begel [ 1,50 / 0,15 ] x 9,68 x 0,39 = 38,19
58,54
Volume Total = 202,53
90,56
16,19
37,59
58,54 +
405,41
- Bekisting Plat 12,72 12,72 M2

Tugas Khusus
[panjang] [lebar]
- Plat Tangga [ 7,00 x 1,26 ] = 8,82
- Bordes [ 2,87 x 1,36 ] = 3,90
12,72

- Bekisting Balok 3,45 3,45 M2


- Balok B5 Ram [ 0,15 + 0,15 ] x 2,87 = 0,86
- Balok BA Ram [ 0,13 + 0,13 ] x 9,97 = 2,59
3,45
- Anak Tangga [jumlah] [panjang] [jumlah] [koef D10]
Tul- utama [ 1,00 x 1,50 ] x 22,00 x 0,62 = 20,34 - Bekisting Anak tangga 3,96 3,96 M2
[ 0,18 x 22,00 ] = 3,96

[panjang] [jarak begel] [panjang] [koef Ø8] 18 Pek. Beton Plat Kanopi tebal = 8 cm (K-175)
Begel [ 1,50 / 0,15 ] x 9,68 x 0,39 = 38,19 - Beton K-175 1,26 1,26 M3
58,54 [lebar] [panjang] [tebal]
Volume Total = 202,53 [ 0,55 x 28,70 ] x 0,08 = 1,26
90,56 - Pembesian 90,74 90,74 Kg
16,19 - arah -x = 0,55
37,59 arah-y = 28,700
jumlah = 1,000
58,54 + [bentang] [jarak besi] [panjang] [koef Ø8] [jumlah]
405,41 [ 28,70 / 0,150 ] x 0,65 x 0,39 x 1,00 = 49,07
[ 0,55 / 0,150 ] x 28,80 x 0,39 x 1,00 = 41,67 +
90,74
[berat] [lapis]
[ 90,736 x 1,00 ] = 90,74

- Bekisting 12,88 12,88 M2


[lebar] [panjang]
[ 0,65 x 28,70 ] x 1,00 = 18,66
Kesimpulan
• Penunjukan kontraktor dengan pelelangan umum melalui e-procurement
dengan lpse
• Jenis kontrak yang digunakan yaitu kontrak harga satuan (unit price)
dengan durasi pekerjaan selama 180 hari kalender .
• Dalam pelaksanaan pengawasan, pihak konsultan pengawas rutin
melakukan pengawasan di lapangan secara langsung.
• Sistem pelaporan proyek berupa laporan harian,mingguan dan bulanan .
• Para pekerja tidak menyadari pentingnya penggunaan alat pelindung diri
(APD), oleh karena itu K3 dalam proyek ini bisa dikatakan tidak memadai.
Kesimpulan
•Terjadi keterlambatan dalam pekerjaan proyek pada minggu pertama pengerjaan yang
disebabkan oleh suatu masalah yaitu pada saat pengerjaan galian pondasi pada bagian
belakang,terdapat pipa PDAM didalam tanah,sehingga untuk membuat pondasi pada area
tersebut pipa harus dikeluarkan dan dipindahkan ke tempat lain.Namun untuk progress
pekerjaan pada minggu selanjutnya mengalami percepatan dan tidak mendapatkan masalah
yang berarti

•Terdapat beberapa tindakan yang dilakukan pihak kontraktor agar pekerjaan yang dilakukan
sesuai dengan target dan waktu yang sudah ditentukan, diantaranya menambah waktu
pekerjaan, mengoptimalisasi pekerja dan melakukan efesiensi pekerja terhadap pekerjan yang
dilakukan
Saran
• Diharapkan pihak kontraktor bertindak tegas terhadap tenaga kerja yang
tidak mentaati K3.
• Mahasiswa kerja praktek sebaiknya terlebih dahulu memahami teori yang
relevan dengan pekerjaan yang sedang dilaksanakan
• Diharapkan mahasiswa kerja praktek lebih aktif dalam mengamati dan
bertanya agar memperoleh ilmu dengan optimal
THANK YOU