No.

Jenis Pekerjaan

Biaya (Rp)

Durasi (Minggu) Bobot (%)

Minggu
1

PEKERJAAN PERSIAPAN (A)

14,548,605.94

2.0

6.2

PEKERJAAN PONDASI (B)

16,981,338.44

1.0

7.3

PEKERJAAN BETON (C)

77,378,289.12

1.0

33.1

PEKERJAAN DINDING DAN PLESTERAN (D)

56,868,234.07

2.0

24.4

PEKERJAAN ATAP (E)

15,776,668.93

1.0

6.8

6.76

PEKERJAAN LANTAI (F)

3,978,493.01

1.0

1.7

1.70

PEKERJAAN PLUMBING (G)

5,716,378.80

1.0

2.4

PEKERJAAN MEKANIKAL ELEKTRIKAL (H)

14,727,650.00

2.0

6.3

PEKERJAAN PLAFON (I)

10,191,750.64

1.0

4.4

10

PEKERJAAN PINTU JENDELA (J)

5,352,883.24

1.0

2.3

11

PEKERJAAN FINISHING (K)

11,920,200.91

1.0

Jumlah

No.

233,440,493.10

3.1

3.1
7.27
33.15
12.18

3.15

12.18

3.15
4.3659

5.1
100.00

PRESTASI PER MINGGU

3.1

3.1

7.3

33.1

15.3

15.3

12.8

PRESTASI KUMULATIF

3.1

6.2

13.5

46.7

62.0

77.3

90.2

Jenis Pekerjaan

Tergantung pada

PEKERJAAN PERSIAPAN (A)

PEKERJAAN PONDASI (B)

PEKERJAAN BETON (C)

PEKERJAAN DINDING DAN PLESTERAN (D)

PEKERJAAN ATAP (E)

PEKERJAAN LANTAI (F)

PEKERJAAN PLUMBING (G)

PEKERJAAN MEKANIKAL ELEKTRIKAL (H)

PEKERJAAN PLAFON (I)

10

PEKERJAAN PINTU JENDELA (J)

11

PEKERJAAN FINISHING (K)

D,E

KURVA S
Minggu ke1
2
3
4
5
6
7
8

Jumlah Bobot Rencana


3.1
6.2
13.5
46.7
62.0
77.3
90.2
100.0

100

90
80
70
60
50
40
2.45

30
20

2.29
5.11

9.8
100.0

10
0