BAR CHART

ID 0 1 2 3 4 5 6 7 8 9 10 11 Task Name REHABULITASI KANTOR BKBPIA 1 MULAI 2 PEKERJAAN. PERSIAPAN 3 PEKERJAAN TANAH 4 PEKERJAAN PONDASI DAN PASANGAN 5 PEKERJAAN BETON 6 PEKERJAAN KAYU, ATAP DAN LANGIT-LANGIT 7 PEKERJAAN BESI, KACA, CAT DAN LABURAN 8 PEKERJAAN SANITAIR 9 PEKERJAAN INSTALASI LISTRIK 10 PEKERJAAN PERLENGKAPAN 11 SELESAI Duration une 2012 July 2012 August 2012 Septe Jun 3, '12 Jun 10, '12 Jun 17, '12 Jun 24, '12 Jul 1, '12 Jul 8, '12 Jul 15, '12 Jul 22, '12 Jul 29, '12 Aug 5, '12 Aug 12, '12 Aug 19, '12 Aug 26, '12 Sep S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T T F S SM T 90 days 6/4 0 days 90 days 7 days 11 days 9 days 61 days 26 days 21 days 7 days 7 days 9/1 0 days

Task

Milestone Summary Project Summary

External Tasks External Milestone Deadline

Project: REHABULITASI KANTOR BKBPIA Date: Wed 5/2/12

Split Progress