TIME SCHEDULLE
PEKERJAAN PEMBANGUNAN RUMAH UNGARAN

HARGA SAT JML HARGA JML TOTAL


NO URAIAN PEKERJAAN VOLUME SAT
(Rp) (Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 157.50 m2 Rp 4,500.00 Rp 708,750.00
2 Pasangan bouplang 42.00 m1 Rp 27,540.00 Rp 1,156,680.00
3 Pas Carpot 22.00 m2 Rp 54,500.00 Rp 1,199,000.00
Rp 3,064,430.00 Rp 3,064,430.00

II PEKERJAAN TANAH DAN PASIR


1 Galian tnh Pondasi 42.20 m3 Rp 18,105.00 Rp 764,031.00
2 Urug tanah kembali 10.55 m3 Rp 5,560.00 Rp 58,658.00
3 Urug tanah peninggian level bang. 33.60 m3 Rp 30,000.00 Rp 1,008,000.00
4 Urug pasir bwh lantai 5.60 m3 Rp 91,900.00 Rp 514,640.00
Rp 2,345,329.00 Rp 2,345,329.00

III PEKERJAAN PASANGAN


1 Pas Pondasi bt kali 1:5 30.38 m3 Rp 326,760.00 Rp 9,928,275.84
2 Pas Rollag Bata 1:5 7.00 m' Rp 9,354.08 Rp 65,478.56
3 Pas Dinding 1/2 bata 1:5 255.00 m2 Rp 46,770.40 Rp 11,926,452.00
4 Pek Plesteran dan Acian dinding 510.00 m2 Rp 22,918.70 Rp 11,688,537.00
5 Pek Sponengan 315.00 m1 Rp 4,630.00 Rp 1,458,450.00
6 Permainan lis beton segitiga depan kuse 3.00 ls Rp 1,500,000.00 Rp 4,500,000.00
6 Permainan lis beton teras depan 1.00 ls Rp 1,500,000.00 Rp 1,500,000.00
Rp 39,567,193.40 Rp 39,567,193.40

IV PEKERJAAN BETON
1 Pek Sloof Beton 15/20 1:2:3 2.53 m3 Rp 2,908,150.00 Rp 7,363,435.80
2 Pek Kolom Beton Bulat depan 1:2:3 4.00 bh Rp 1,000,000.00 Rp 4,000,000.00
3 Pek Kolom Beton 15/15 1:2:3 2.21 m3 Rp 3,908,685.00 Rp 8,618,650.43
4 Pek Balok Beton 15/20 1 : 2 : 3 2.53 m3 Rp 3,908,685.00 Rp 9,896,790.42
5 Pek Beton Plat belakang 1.68 m3 Rp 3,908,685.00 Rp 6,566,590.80
6 Pek Rabat Beton 1:3:5 102.00 m2 Rp 11,459.35 Rp 1,168,853.70
Rp 37,614,321.15 Rp 37,614,321.15

V PEKERJAAN KERAMIK
1 Pas Lantai keramik 40x40 kw I 76.00 m2 Rp 94,086.40 Rp 7,150,566.40
2 Pas Lantai keramik KM Anti Slip 40x40 k 13.00 m2 Rp 94,086.40 Rp 1,223,123.20
3 Pas Dinding Keramik KM 20x25 kw I 28.00 m2 Rp 84,364.00 Rp 2,362,192.00
4 Pas Lis keramik KM 16.00 m1 Rp 30,000.00 Rp 480,000.00
5 Pas Granit Teras depan 6.00 m2 Rp 200,000.00 Rp 1,200,000.00
6 Pas Granit meja dapur
Rp 11,215,881.60 Rp 11,215,881.60

VI PEKERJAAN KUSEN PINTU DAN JENDELA


1 Pas Pintu P1 (Pintu satu daun) 5.00 bh
Pas Kusen kayu bangkire 6/15 26.00 m1 Rp 75,000.00 Rp 1,950,000.00
Pas Daun Pintu 5.00 bh Rp 750,000.00 Rp 3,750,000.00
Pas Slot 5.00 bh Rp 65,000.00 Rp 325,000.00
Pas Engsel 4" 7.50 psg Rp 8,500.00 Rp 63,750.00

2 Pas Pintu P2 (Pintu kamar mandi) 2.00 bh


Pas Kusen aluminium coklat 3" 15.00 m1 Rp 65,000.00 Rp 975,000.00
Pas Daun Pintu 2.00 bh Rp 750,000.00 Rp 1,500,000.00
Pas Jendela atas pintu 2.00 bh Rp 250,000.00 Rp 500,000.00

3 Pas Pintu Jendela Utama


Pas Kusen kayu bangkire 6/15 11.00 m1 Rp 75,000.00 Rp 825,000.00
Pas Daun Pintu 5.00 bh Rp 750,000.00 Rp 3,750,000.00
Pas Handel Pintu Utama 2.00 psg Rp 80,000.00 Rp 160,000.00
Pas Spanolet 1.00 bh Rp 55,000.00 Rp 55,000.00
Pas Engsel 4" 4.00 psg Rp 8,500.00 Rp 34,000.00
Pas Daun jendela 2.00 bh Rp 300,000.00 Rp 600,000.00
Pas Engsel 3" 2.00 psg Rp 7,500.00 Rp 15,000.00
Pas gerendel jago 2.00 bh Rp 7,500.00 Rp 15,000.00
Pas kait angin 2.00 bh Rp 6,500.00 Rp 13,000.00

4 Pas Jendela J1 5.00 bh


Pas Kusen kayu bangkire 6/15 37.50 m1 Rp 75,000.00 Rp 2,812,500.00
Pas Daun jendela 5.00 bh Rp 300,000.00 Rp 1,500,000.00
Pas Engsel 3" 5.00 psg Rp 7,500.00 Rp 37,500.00
Pas gerendel jago 5.00 bh Rp 7,500.00 Rp 37,500.00
Pas kait angin 5.00 bh Rp 6,500.00 Rp 32,500.00

5 Pas Jendela J2 1.00 bh


Pas Kusen kayu bangkire 6/15 4.50 m1 Rp 75,000.00 Rp 337,500.00
Pas Daun jendela 1.00 bh Rp 300,000.00 Rp 300,000.00
Pas Engsel 3" 1.00 psg Rp 7,500.00 Rp 7,500.00
Pas gerendel jago 1.00 bh Rp 7,500.00 Rp 7,500.00
Pas kait angin 1.00 bh Rp 6,500.00 Rp 6,500.00
7 Pas Roster kayu bangkirei 20x20 35.00 bh Rp 50,000.00 Rp 1,750,000.00
Rp 21,359,750.00 Rp 21,359,750.00

VII PEKERJAAN PLAFOND


1 Pas Plafond ternit dicoumpon 135.50 m2 Rp 65,000.00 Rp 8,807,500.00
Rp 8,807,500.00 Rp 8,807,500.00

IX PEKERJAAN INSTALASI AIR KOTOR


1 Pas Pipa PVC 4" Maspion KM 23.00 m1 Rp 69,750.00 Rp 1,604,250.00
2 Pas Pipa PVC 3" Maspion KM 23.00 m1 Rp 41,850.00 Rp 962,550.00
3 Pas Fllor Drain Stainless 3.00 bh Rp 22,800.00 Rp 68,400.00
4 Pas tmp sabun 2.00 bh Rp 35,000.00 Rp 70,000.00
5 Septic tank dan peresapan 1.00 ls Rp 4,305,760.65 Rp 4,305,760.65
6 Pas Kloset jongkok 1.00 bh Rp 210,780.00 Rp 210,780.00
7 Pas Kloset duduk 1 piece standar cina 1.00 unit Rp 1,022,935.00 Rp 1,022,935.00
8 Pas washbak dapur 1.00 bh Rp 245,860.00 Rp 245,860.00
9 Pas meja dapur 1.00 ls Rp 500,000.00 Rp 500,000.00
10 Pas jet shower pd tiap km 2.00 bh Rp 60,000.00 Rp 120,000.00
Rp 9,110,535.65 Rp 9,110,535.65

PEKERJAAN INSTALASI AIR BERSIH


1 Pipa PVC 1/2" 26.00 m1 Rp 7,322.00 Rp 190,372.00
2 Pas Kran Dobel shower 2.00 bh Rp 90,000.00 Rp 180,000.00
3 Pas Shower tangkai 2.00 bh Rp 150,000.00 Rp 300,000.00
4 Pas Kran Dapur 1/2" 1.00 bh Rp 65,000.00 Rp 65,000.00
Rp 735,372.00 Rp 735,372.00

X PEKERJAAN PENGECATAN
1 Pek Cat Dinding Catylac 510.00 m2 Rp 14,856.00 Rp 7,576,560.00
2 Pek Cat Plafon Catylac 135.50 m2 Rp 14,856.00 Rp 2,012,988.00
3 Pek Cat Lisplang m1
4 Pek melamin Kusen m1
5 Pek melamin Daun Pintu bh
6 Pek melamin Daun Jendela m1
7 Pek melamin roster 35.00 bh
Rp 9,589,548.00 Rp 9,589,548.00

XI PEKERJAAN ATAP DEPAN


1 Pas Rangka Atap Baja Ringan 169.38 m2 Rp 130,000.00 Rp 22,018,750.00
2 Pas Genteng kanmuri glasur natural 169.38 m2 Rp 83,300.00 Rp 14,108,937.50
3 Pas Bubungan genteng glasur natural 44.50 m1 Rp 100,864.00 Rp 4,488,448.00
4 Pas seng talang 9.00 m1 Rp 13,000.00 Rp 117,000.00
5 Pas Lisplang dobel woodplang 34.00 m1 Rp 25,000.00 Rp 850,000.00
Rp 41,583,135.50 Rp 41,583,135.50

JUMLAH TOTAL PEKERJAAN GEDUNG Rp 184,992,996.30

Prestasi Tiap Minggu Rencana


Prestasi Komulatif Rencana
Prestasi Tiap Minggu Realisasi
Prestasi Komulatif Realisasi