ID Task URAIAN PEKERJAAN DURASI PEKERJAAN PEKERJAAN FREE 2017

Mode SEBELUM SESUDAH SLACK


Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '
19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1
1 136 days 0 days
2 Pekerjan Persiapan 70 days 0 days
3 Pembersihan Lapangan 2 days 4SS 0 days
4 Membuat Gudang/Los 3 days 3SS 5 0 days
5 Bouplank dan Pengukuran 2 days 4 7 0 days
6 Pekerjaan Pondasi 28 days 0 days
7 Menggali Tanah 5 days 5 8FS+1 day 0 days
8 Menurunkan Sumuran 12 days 7FS+1 day 9 0 days
9 Timbunan Kembali 10 days 8 12FS+2 days 0 days
10 Pekerjaan Lantai 1 67 days 0 days
11 Pekerjaan Beton 40 days 0 days
12 Mencor Sloof 5 days 9FS+2 days 13FS+3 days 0 days
13 Mencor Kolom 18 days 12FS+3 days 14FS+2 days 0 days
14 Mencor Balok 5 days 13FS+2
15FS+3
days days,29SS,17FS+2
0 days
days
15 Mencor Tangga 4 days 14FS+3 days 61 days
16 Pekerjaan Dinding 20 days 34 days
17 Memasang Bata 20 days 14FS+2 days 18FF,20 0 days
18 Plesteran 14 days 17FF 46 days
19 Pekerjaan Plafon 12 days 34 days
20 Memasang Rangka 5 days 17 21,23SS,26 0 days
21 Memasang Penutup Triplek 7 days 20 34 days
22 Pekerjaan Lantai 10 days 36 days
23 Memasang Keramik dan Tegel 10 days 20SS 25SS+2 days 0 days
24 Pekerjaan Cat 8 days 36 days
25 Mencat Dinding 5 days 23SS+2 days 39 days
26 Mencat Plafon 5 days 20 36 days
27 Pekerjaan Lantai 2 73 days 0 days
28 Pekerjaan Beton 35 days 0 days
29 Mencor Lantai 2 7 days 14SS 30FS+3 days 0 days
30 Mencor Kolom 18 days 29FS+3 days 31FS+2 days 0 days
31 Mencor Balok 5 days 30FS+2 days 33FS+1 day 0 days
32 Pekerjaan Dinding 20 days 0 days
33 Memasang bata 20 days 31FS+1 day 34FF 0 days
34 Plesteran 7 days 33FF 36,41,44SS 0 days
35 Pekerjaan Plafon 17 days 0 days
36 Memasang Rangka 10 days 34 37,39SS,42 0 days
37 Memasang Penutup Triplek 7 days 36 45FF 0 days
38 Pekerjaan Lantai 10 days 7 days
39 Memasang Keramik dan Tegel 10 days 36SS 7 days

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: TUGAS
Milestone Inactive Summary Start-only Critical Progress
Date: Fri 4/7/17
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 1
ID Task URAIAN PEKERJAAN DURASI PEKERJAAN PEKERJAAN FREE 2017
Mode SEBELUM SESUDAH SLACK
Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '
19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1
40 Pekerjaan Cat 15 days 2 days
41 Mencat Dinding 5 days 34 12 days
42 Mencat Plafon 5 days 36 2 days
43 Pekerjaan Atap 24 days 0 days
44 Memasang Kuda-Kuda 14 days 34SS 10 days
45 Gording, Rusak,Reng, Genteng, dan 14 days 37FF 0 days
Talang

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: TUGAS
Milestone Inactive Summary Start-only Critical Progress
Date: Fri 4/7/17
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline