ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pagar sementara dari seng gelombang tinggi 2 m


SATUAN PEMBAYARAN : m1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 70,000.00 28,000.00


2 Tukang Kayu L08 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0200 85,000.00 1,700.00

JUMLAH HARGA TENAGA 46,300.00

B BAHAN

1 Dolken Kayu Dia 8 cm M089 btg 1.2500 20,000.00 25,000.00


2 Portland Cement (PC) M037 kg 2.5000 1,400.00 3,500.00
3 Atap Seng Gelombang 210x80x2 M178 lbr 1.2000 51,000.00 61,200.00
4 Pasir Cor M004 m3 0.0050 85,000.00 425.00
5 Stenslah/batu pecah tangan 2/3 M014 m3 0.0090 128,000.00 1,152.00
6 Usuk : 5/7 M061 m3 0.0720 1,000,000.00 72,000.00
7 Paku Kayu Segala Ukuran M140 kg 0.0600 13,500.00 810.00
8 Cat Catylac M410 kg 0.4500 19,000.00 8,550.00

JUMLAH HARGA BAHAN 172,637.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 218,937.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pembuatan direksi kit, gudang semen dan alat-alat
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 2.0000 70,000.00 140,000.00
2 Tukang Kayu L08 Org/hr 1.0000 75,000.00 75,000.00
3 Tukang Batu L07 Org/hr 1.0000 75,000.00 75,000.00
4 Kepala Tukang Kayu L03 Org/hr 0.3000 80,000.00 24,000.00
5 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 318,250.00


B BAHAN
1 Balok M062 m3 0.1800 3,000,000.00 540,000.00
2 Paku Kayu Segala Ukuran M140 kg 0.3000 13,500.00 4,050.00
2 Portland Cement (PC) M037 kg 35.0000 1,400.00 49,000.00
3 Pasir Pasang M002 m3 0.1500 82,000.00 12,300.00
4 Pasir Cor M004 m3 0.1000 85,000.00 8,500.00
5 Stenslah/batu pecah tangan 2/3 M014 m3 0.1500 128,000.00 19,200.00
6 Bata Merah M022 bh 30.0000 550.00 16,500.00
7 Atap Seng Gelombang 210x80x2 M178 lbr 0.5000 51,000.00 25,500.00
8 Kaca Polos tebal 5 mm M271 m2 0.1500 125,000.00 18,750.00
9 Multiplek 6 mm M216 m2 1.5000 75,000.00 112,500.00
10 Grendel pintu sekualitas SOLID M262 bh 2.0000 42,000.00 84,000.00
11 Engsel Pintu sekualitas SOLID ( 1 psng 2 bhM257 psng 2.0000 86,250.00 172,500.00

JUMLAH HARGA BAHAN 1,062,800.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,381,050.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pembersihan lapangan dan perataan
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000 70,000.00 7,000.00


2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 11,250.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 11,250.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pengukuran dan pemasangan bouwplank
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000 70,000.00 7,000.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 15,725.00

B BAHAN

1 Usuk : 5/7 M061 m3 0.0120 3,000,000.00 36,000.00


2 Paku Kayu Segala Ukuran M140 kg 0.0200 13,500.00 270.00
3 Papan (3x20) cm M064 m3 0.0070 4,560,000.00 31,920.00

JUMLAH HARGA BAHAN 68,190.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 83,915.00

JENIS PEKERJAAN : 1 m3 Bongkaran tembok bata merah


A. TENAGA

1 Pekerja Biasa L17 Org/hr 6.6670 70,000.00 466,690.00


2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.3330 85,000.00 28,305.00

JUMLAH HARGA TENAGA 494,995.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 494,995.00


JENIS PEKERJAAN : 1 m2 Bongkaran atap
A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.1000 70,000.00 77,000.00


2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 81,250.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 81,250.00


JENIS PEKERJAAN : 1 m2 Bongkaran lantai
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.2000 70,000.00 14,000.00
2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0100 85,000.00 850.00

JUMLAH HARGA TENAGA 14,850.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 14,850.00


JENIS PEKERJAAN : 1 m2 Bongkaran plafon
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000 70,000.00 14,000.00


2 Tukang Kayu L08 Org/hr 0.0600 80,000.00 4,800.00
3 Kepala Tukang Kayu L03 Org/hr 0.0060 80,000.00 480.00
4 Mandor L01 Org/hr 0.0100 65,000.00 650.00

JUMLAH HARGA TENAGA 19,930.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 19,930.00


JENIS PEKERJAAN : 1 m3 Bongkaran beton bertulang
A. TENAGA

1 Pekerja Biasa L17 Org/hr 6.6670 70,000.00 466,690.00


2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.3330 85,000.00 28,305.00

JUMLAH HARGA TENAGA 494,995.00


B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 494,995.00

JENIS PEKERJAAN : 1 m3 Buang Bongkaran


A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000 70,000.00 7,000.00


2 Tukang Kayu L08 Org/hr 0.1000 80,000.00 8,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 65,000.00 650.00
4 Mandor L01 Org/hr 0.0050 65,000.00 325.00

JUMLAH HARGA TENAGA 15,975.00


B BAHAN
Artco Sorong bh 0.1000 425,000.00 42,500.00

JUMLAH HARGA BAHAN 42,500.00


C PERALATAN
Sewa truk angkut bh 0.4000 90,000.00 36,000.00

JUMLAH HARGA PERALATAN 36,000.00

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 94,475.00

JENIS PEKERJAAN : 1 m2 Bongkaran Kusen


A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.2000 70,000.00 14,000.00
2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0100 85,000.00 850.00

JUMLAH HARGA TENAGA 14,850.00


B BAHAN

JUMLAH HARGA BAHAN 10,000.00


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 24,850.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Galian tanah pondasi batu kali
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6400 70,000.00 44,800.00


2 Tukang Kayu L08 Org/hr - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0400 85,000.00 3,400.00

JUMLAH HARGA TENAGA 48,200.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN bh/hr 0.2000 50000.00 10,000.00

JUMLAH HARGA PERALATAN 10,000.00

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 58,200.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Galian tanah pondasi foot plate
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 0.7260 70,000.00 50,820.00


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr ### - 80,000.00 -
4 Mandor L01 Org/hr ### 0.0520 85,000.00 4,420.00

JUMLAH HARGA TENAGA 55,240.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 55,240.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Galian tanah pondasi strouss
SATUAN PEMBAYARAN : m1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 0.7350 70,000.00 51,450.00


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr ### - 80,000.00 -
4 Mandor L01 Org/hr ### 0.0730 85,000.00 6,205.00

JUMLAH HARGA TENAGA 57,655.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN
1 Sewa Alat Pondasi Strouss M825 Bh/hr 0.0500 175,000.00 8,750.00

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 57,655.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Urugan kembali tanah galian pondasi
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 0.1920 70,000.00 13,440.00


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr ### - 80,000.00 -
4 Mandor L01 Org/hr ### 0.0190 85,000.00 1,615.00

JUMLAH HARGA TENAGA 15,055.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 15,055.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemadatan tanah
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 70,000.00 -


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Operator L20 Org/hr ### 0.1000 65,000.00 6,500.00
4 Mandor L01 Org/hr ### 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 10,750.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN
1 Mesin Stamper M824 Alt/hr 0.0350 350,000.00 12,250.00

JUMLAH HARGA PERALATAN 12,250.00

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 23,000.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Urugan pasir
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 0.3000 70,000.00 21,000.00


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr ### - 80,000.00 -
4 Mandor L01 Org/hr ### 0.0100 85,000.00 850.00

JUMLAH HARGA TENAGA 21,850.00

B BAHAN

1 Pasir Urug M001 m3 1.0000 69,000.00 69,000.00

JUMLAH HARGA BAHAN 69,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 90,850.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Urugan tanah/sirtu
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr ### 0.2500 75,000.00 18,750.00


2 Tukang Kayu L08 Org/hr ### - 75,000.00 -
3 Kepala Tukang Kayu L03 Org/hr ### - 80,000.00 -
4 Mandor L01 Org/hr ### 0.0250 85,000.00 2,125.00

JUMLAH HARGA TENAGA 20,875.00

B BAHAN

1 Tanah Urug M006 m3 1.2000 60,000.00 72,000.00

JUMLAH HARGA BAHAN 72,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 92,875.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang pondasi batu kosong/Aanstamping
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.7800 70,000.00 54,600.00
2 Tukang Batu L07 Org/hr 0.3900 75,000.00 29,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0390 80,000.00 3,120.00
4 Mandor L01 Org/hr 0.0390 85,000.00 3,315.00

JUMLAH HARGA TENAGA 90,285.00


B BAHAN
1 Batu Belah Kali M011 m3 1.2000 105,000.00 126,000.00
2 Pasir Urug M001 m3 0.3000 69,000.00 20,700.00

JUMLAH HARGA BAHAN 146,700.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 236,985.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pondasi batu kali, 1 Pc : 2 Ps
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 1.5000 70,000.00 105,000.00
2 Tukang Batu L07 Org/hr 0.6000 75,000.00 45,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0600 80,000.00 4,800.00
4 Mandor L01 Org/hr 0.0750 85,000.00 6,375.00

JUMLAH HARGA TENAGA 161,175.00


B BAHAN
1 Batu Belah Kali M011 m3 1.1000 105,000.00 115,500.000
2 Portland Cement (PC) M037 kg 267.0000 1,400.00 373,800.000
3 Pasir Pasang M002 m3 0.4270 82,000.00 35,014.000

JUMLAH HARGA BAHAN 524,314.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 685,489.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pondasi batu kali, 1 Pc : 6 Ps
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 1.5000 70,000.00 105,000.00
2 Tukang Batu L07 Org/hr 0.6000 75,000.00 45,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0600 80,000.00 4,800.00
4 Mandor L01 Org/hr 0.0750 85,000.00 6,375.00

JUMLAH HARGA TENAGA 161,175.00


B BAHAN
1 Batu Belah Kali M011 m3 1.1000 105,000.00 115,500.000
2 Portland Cement (PC) M037 kg 117.0000 1,400.00 163,800.000
3 Pasir Pasang M002 m3 0.4270 82,000.00 35,014.000

JUMLAH HARGA BAHAN 314,314.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 475,489.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.3200 70,000.00 22,400.00
2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0150 85,000.00 1,275.00

JUMLAH HARGA TENAGA 31,975.00


B BAHAN
1 Bata Merah M022 bh 70.0000 550.00 38,500.00
2 Portland Cement (PC) M037 kg 14.3700 1,400.00 20,118.00
3 Pasir Pasang M002 m3 0.0400 82,000.00 3,280.00

JUMLAH HARGA BAHAN 61,898.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 93,873.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 2.0500 70,000.00 143,500.00
2 Tukang Batu L07 Org/hr 0.6000 75,000.00 45,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0600 80,000.00 4,800.00
4 Mandor L01 Org/hr 0.0960 85,000.00 8,160.00

JUMLAH HARGA TENAGA 201,460.00


B BAHAN
1 Bata Merah M022 bh 450.0000 550.00 247,500.00
2 Portland Cement (PC) M037 kg 92.3700 1,400.00 129,318.00
3 Pasir Pasang M002 m3 0.2500 82,000.00 20,500.00

JUMLAH HARGA BAHAN 397,318.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 598,778.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Plesteran 1 Pc : 3 Ps, tebal 20 mm
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.2500 70,000.00 17,500.00
2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0125 85,000.00 1,062.50

JUMLAH HARGA TENAGA 35,162.50


B BAHAN
1 Portland Cement (PC) M037 kg 10.8000 1,400.00 15,120.00
2 Pasir Pasang M002 m3 0.0260 82,000.00 2,132.00

JUMLAH HARGA BAHAN 17,252.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 52,414.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Plesteran beton 1 Pc : 3 Ps, tebal 15 mm
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.2600 70,000.00 18,200.00
2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0130 85,000.00 1,105.00

JUMLAH HARGA TENAGA 35,905.00


B BAHAN

1 Portland Cement (PC) M037 kg 7.0700 1,400.00 9,898.00


2 Pasir Pasang M002 m3 0.0210 82,000.00 1,722.00

JUMLAH HARGA BAHAN 11,620.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 47,525.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Patelahan bata merah tebal 1/4 bata, 1 Pc : 3 Ps
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.2200 70,000.00 15,400.00
2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0150 85,000.00 1,275.00

JUMLAH HARGA TENAGA 24,975.00


B BAHAN
1 Bata Merah M022 bh 29.0000 550.00 15,950.00
2 Portland Cement (PC) M037 kg 14.3700 1,400.00 20,118.00
3 Pasir Pasang M002 m3 0.0400 82,000.00 3,280.00

JUMLAH HARGA BAHAN 39,348.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 64,323.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Plesteran 1 Pc : 3 Ps, tebal 20 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2500 70,000.00 17,500.00


2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0125 85,000.00 1,062.50

JUMLAH HARGA TENAGA 35,162.50

B BAHAN

1 Portland Cement (PC) M037 kg 10.8000 1,400.00 15,120.00


2 Pasir Pasang M002 m3 0.0260 82,000.00 2,132.00

JUMLAH HARGA BAHAN 17,252.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 52,414.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Plesteran beton 1 Pc : 3 Ps, tebal 15 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2600 70,000.00 18,200.00


2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0130 85,000.00 1,105.00

JUMLAH HARGA TENAGA 35,905.00

B BAHAN

1 Portland Cement (PC) M037 kg 7.0700 1,400.00 9,898.00


2 Pasir Pasang M002 m3 0.0210 82,000.00 1,722.00

JUMLAH HARGA BAHAN 11,620.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 47,525.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Benangan
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr - 70,000.00 -


2 Tukang Batu L07 Org/hr 0.1200 75,000.00 9,000.00
3 Kepala Tukang Batu L02 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr - 85,000.00 -

JUMLAH HARGA TENAGA 9,000.00

B BAHAN

1 Portland Cement (PC) M037 kg 6.5000 1,400.00 9,100.00


2 Pasir Pasang M002 m3 0.0210 82,000.00 1,722.00

JUMLAH HARGA BAHAN 10,822.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 19,822.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pondasi foot plate beton bertulang (300 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 3.9000 70,000.00 273,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 1.0400 75,000.00 78,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.2450 80,000.00 19,600.00
6 Mandor L01 Org/hr 0.1650 85,000.00 14,025.00

JUMLAH HARGA TENAGA 489,625.00


B BAHAN

1 Balok M062 m3 0.2000 3,000,000.00 600,000.00


2 Paku Kayu Segala Ukuran M140 kg 1.5000 13,500.00 20,250.00
3 Minyak bekisting M474 ltr 0.4000 3,162.50 1,265.00
4 Besi Beton Polos M112 kg 300.0000 7,000.00 2,100,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 3,323,215.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 3,812,840.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pondasi strouss beton bertulang (200 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 3.9000 70,000.00 273,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 1.0400 75,000.00 78,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.2450 80,000.00 19,600.00
6 Mandor L01 Org/hr 0.1650 85,000.00 14,025.00

JUMLAH HARGA TENAGA 489,625.00


B BAHAN

1 Balok M062 m3 0.2000 3,000,000.00 600,000.00


2 Paku Kayu Segala Ukuran M140 kg 1.5000 13,500.00 20,250.00
3 Minyak bekisting M474 ltr 0.4000 3,162.50 1,265.00
4 Besi Beton Polos M112 kg 200.0000 7,000.00 1,400,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 2,623,215.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 3,112,840.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Kolom beton bertulang (300 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 7.3000 75,000.00 547,500.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 3.3000 75,000.00 247,500.00
4 Tukang Besi/Baja L09 Org/hr 2.1000 75,000.00 157,500.00
5 Kepala Tukang Batu L02 Org/hr 0.5700 80,000.00 45,600.00
6 Mandor L01 Org/hr 0.2500 85,000.00 21,250.00

JUMLAH HARGA TENAGA 1,045,600.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.4000 3,000,000.00 1,200,000.00


2 Paku Kayu Segala Ukuran M140 kg 4.0000 13,500.00 54,000.00
3 Minyak bekisting M474 ltr 2.0000 50,000.00 100,000.00
4 Besi Beton Polos M112 kg 300.0000 7,000.00 2,100,000.00
5 Kawat Beton/Bendrat RRT M135 kg 4.5000 10,400.00 46,800.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.1500 3,000,000.00 450,000.00
10 Multiplek 9 mm M217 m2 3.5000 45,738.00 160,083.00
11 Dolken Kayu Dia 8 cm M089 btg 20.0000 20,000.00 400,000.00

JUMLAH HARGA BAHAN 5,089,183.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 6,134,783.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Kolom praktis beton bertulang (15 x 15) cm
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 7.3000 70,000.00 511,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 3.3000 75,000.00 247,500.00
4 Tukang Besi/Baja L09 Org/hr 2.1000 75,000.00 157,500.00
5 Kepala Tukang Batu L02 Org/hr 0.5700 80,000.00 45,600.00
6 Mandor L01 Org/hr 0.2500 85,000.00 21,250.00

JUMLAH HARGA TENAGA 1,009,100.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.0700 3,000,000.00 210,000.00


2 Paku Kayu Segala Ukuran M140 kg 3.0000 13,500.00 40,500.00
3 Besi Beton Polos M112 kg 250.0000 7,000.00 1,750,000.00
4 Kawat Beton/Bendrat RRT M135 kg 4.5000 10,400.00 46,800.00
5 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
6 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
7 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 2,625,600.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 3,634,700.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Sloof beton bertulang (200 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 4.8500 70,000.00 339,500.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 1.5600 75,000.00 117,000.00
4 Tukang Besi/Baja L09 Org/hr 1.4000 75,000.00 105,000.00
5 Kepala Tukang Batu L02 Org/hr 0.3310 80,000.00 26,480.00
6 Mandor L01 Org/hr 0.1700 85,000.00 14,450.00

JUMLAH HARGA TENAGA 628,680.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.2700 3,000,000.00 810,000.00


2 Paku Kayu Segala Ukuran M140 kg 2.0000 13,500.00 27,000.00
3 Minyak bekisting M474 ltr 0.6000 3,162.50 1,897.50
4 Besi Beton Polos M112 kg 200.0000 7,000.00 1,400,000.00
5 Kawat Beton/Bendrat RRT M135 kg 3.0000 10,400.00 31,200.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 2,848,397.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 3,477,077.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Balok struktur beton bertulang (200 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.9600 70,000.00 417,200.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.8000 75,000.00 210,000.00
4 Tukang Besi/Baja L09 Org/hr 1.4000 75,000.00 105,000.00
5 Kepala Tukang Batu L02 Org/hr 0.4550 80,000.00 36,400.00
6 Mandor L01 Org/hr 0.2080 85,000.00 17,680.00

JUMLAH HARGA TENAGA 812,530.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.3200 3,000,000.00 960,000.00


2 Paku Kayu Segala Ukuran M140 kg 3.2000 13,500.00 43,200.00
3 Minyak bekisting M474 ltr 1.6000 3,162.50 5,060.00
4 Besi Beton Polos M112 kg 200.0000 7,000.00 1,400,000.00
5 Kawat Beton/Bendrat RRT M135 kg 3.0000 10,400.00 31,200.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.1400 3,000,000.00 420,000.00
10 Multiplek 9 mm M217 m2 2.8000 45,738.00 128,066.40
11 Dolken Kayu Dia 8 cm M089 btg 16.0000 20,000.00 320,000.00

JUMLAH HARGA BAHAN 3,885,826.40

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,698,356.40


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Balok latei beton bertulang (150 kg besi + bekisting)
SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 5.8000 70,000.00 406,000.00
2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.8000 75,000.00 210,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.4200 80,000.00 33,600.00
6 Mandor L01 Org/hr 0.1850 85,000.00 15,725.00

JUMLAH HARGA TENAGA 770,325.00


B BAHAN
1 Papan (2x20) cm M063 m3 0.3200 3,000,000.00 960,000.00
2 Paku Kayu Segala Ukuran M140 kg 3.2000 13,500.00 43,200.00
3 Minyak bekisting M474 ltr 1.6000 3,162.50 5,060.00
4 Besi Beton Polos M112 kg 150.0000 7,000.00 1,050,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.1200 3,000,000.00 360,000.00
10 Multiplek 9 mm M217 m2 2.8000 45,738.00 128,066.40
11 Dolken Kayu Dia 8 cm M089 btg 32.0000 20,000.00 640,000.00

JUMLAH HARGA BAHAN 3,788,026.40

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,558,351.40

ANALISA HARGA SATUAN

JENIS PEKERJAAN : Plat lantai beton bertulang (150 kg besi + bekisting)


SATUAN PEMBAYARAN : m3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 5.6000 70,000.00 392,000.00
2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.6400 75,000.00 198,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.4000 80,000.00 32,000.00
6 Mandor L01 Org/hr 0.1930 85,000.00 16,405.00

JUMLAH HARGA TENAGA 743,405.00


B BAHAN
1 Papan (2x20) cm M063 m3 0.2400 3,000,000.00 720,000.00
2 Paku Kayu Segala Ukuran M140 kg 3.2000 13,500.00 43,200.00
3 Minyak bekisting M474 ltr 1.6000 3,162.50 5,060.00
4 Besi Beton Polos M112 kg 175.0000 7,000.00 1,225,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.2000 3,000,000.00 600,000.00
10 Multiplek 9 mm M217 m2 2.9000 45,738.00 132,640.20
11 Dolken Kayu Dia 8 cm M089 btg 24.0000 20,000.00 480,000.00

JUMLAH HARGA BAHAN 3,807,600.20

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,551,005.20


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Tangga beton bertulang (200 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.6000 70,000.00 392,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.3000 75,000.00 172,500.00
4 Tukang Besi/Baja L09 Org/hr 1.4000 75,000.00 105,000.00
5 Kepala Tukang Batu L02 Org/hr 0.4050 80,000.00 32,400.00
6 Mandor L01 Org/hr 0.2020 85,000.00 17,170.00

JUMLAH HARGA TENAGA 745,320.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.2500 3,000,000.00 750,000.00


2 Paku Kayu Segala Ukuran M140 kg 3.0000 13,500.00 40,500.00
3 Minyak bekisting M474 ltr 1.2000 3,162.50 3,795.00
4 Besi Beton Polos M112 kg 200.0000 7,000.00 1,400,000.00
5 Kawat Beton/Bendrat RRT M135 kg 3.0000 10,400.00 31,200.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.1050 3,000,000.00 315,000.00
10 Multiplek 9 mm M217 m2 2.5000 45,738.00 114,345.00
11 Dolken Kayu Dia 8 cm M089 btg 14.0000 20,000.00 280,000.00

JUMLAH HARGA BAHAN 3,513,140.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,258,460.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Ring balok beton bertulang (15 x 20) cm
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.100 70,000.00 7,000.00


2 Tukang Batu L07 Org/hr 0.033 75,000.00 2,475.00
3 Tukang Kayu L08 Org/hr 0.033 75,000.00 2,475.00
4 Tukang Besi/Baja L09 Org/hr 0.033 75,000.00 2,475.00
5 Kepala Tukang Batu L02 Org/hr 0.010 80,000.00 800.00
6 Mandor L01 Org/hr 0.005 85,000.00 425.00

JUMLAH HARGA TENAGA 15,650.00


B BAHAN

1 Papan (2x20) cm M063 m3 0.3000 3,000,000.00 900,000.00


2 Paku Kayu Segala Ukuran M140 kg 4.0000 13,500.00 54,000.00
3 Besi Beton Polos M112 kg 175.0000 7,000.00 1,225,000.00
4 Kawat Beton/Bendrat RRT M135 kg 4.0000 10,400.00 41,600.00
5 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
6 Pasir Cor M004 m3 0.0520 85,000.00 4,420.00
7 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 2,759,120.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 2,774,770.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Rabat beton
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 4.9000 70,000.00 343,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 1.0400 75,000.00 78,000.00
4 Kepala Tukang Batu L02 Org/hr 0.2450 80,000.00 19,600.00
5 Mandor L01 Org/hr 0.1650 85,000.00 14,025.00

JUMLAH HARGA TENAGA 480,875.00

B BAHAN

1 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00


2 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
3 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00

JUMLAH HARGA BAHAN 578,300.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,059,175.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Plat talang beton bertulang (150 kg besi + bekisting)
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.6000 70,000.00 392,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.6400 75,000.00 198,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.4000 80,000.00 32,000.00
6 Mandor L01 Org/hr 0.1930 85,000.00 16,405.00

JUMLAH HARGA TENAGA 743,405.00

B BAHAN

1 Papan (2x20) cm M063 m3 0.2400 3,000,000.00 720,000.00


2 Paku Kayu Segala Ukuran M140 kg 3.2000 13,500.00 43,200.00
3 Minyak bekisting M474 ltr 1.6000 3,162.50 5,060.00
4 Besi Beton Polos M112 kg 120.0000 7,000.00 840,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.2000 3,000,000.00 600,000.00
10 Multiplek 9 mm M217 m2 2.9000 45,738.00 132,640.20
11 Dolken Kayu Dia 8 cm M089 btg 24.0000 20,000.00 480,000.00

JUMLAH HARGA BAHAN 3,422,600.20

C PERALATAN
JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,166,005.20

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Rephel beton
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.6000 70,000.00 392,000.00


2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Tukang Kayu L08 Org/hr 2.6400 75,000.00 198,000.00
4 Tukang Besi/Baja L09 Org/hr 1.0500 75,000.00 78,750.00
5 Kepala Tukang Batu L02 Org/hr 0.4000 80,000.00 32,000.00
6 Mandor L01 Org/hr 0.1930 85,000.00 16,405.00

JUMLAH HARGA TENAGA 743,405.00

B BAHAN

1 Papan (2x20) cm M063 m3 0.2400 3,000,000.00 720,000.00


2 Paku Kayu Segala Ukuran M140 kg 3.2000 13,500.00 43,200.00
3 Minyak bekisting M474 ltr 1.6000 3,162.50 5,060.00
4 Besi Beton Polos M112 kg 115.0000 7,000.00 805,000.00
5 Kawat Beton/Bendrat RRT M135 kg 2.2500 10,400.00 23,400.00
6 Portland Cement (PC) M037 kg 323.0000 1,400.00 452,200.00
7 Pasir Cor M004 m3 0.5200 85,000.00 44,200.00
8 Batu pecah mesin 2/3 M019 m3 0.7800 105,000.00 81,900.00
9 Balok M062 m3 0.2000 3,000,000.00 600,000.00
10 Multiplek 9 mm M217 m2 2.9000 45,738.00 132,640.20
11 Dolken Kayu Dia 8 cm M089 btg 24.0000 20,000.00 480,000.00

JUMLAH HARGA BAHAN 3,387,600.20

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 4,131,005.20


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Rangka plafon metal furing
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1800 70,000.00 12,600.00


2 Tukang Kayu L08 Org/hr 0.3200 75,000.00 24,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0320 80,000.00 2,560.00
4 Mandor L01 Org/hr 0.0090 85,000.00 765.00

JUMLAH HARGA TENAGA 39,925.00

B BAHAN

1 Rangka metal furing M517 m2 1.1000 33,000.00 36,300.00


2 Sekrup Segala Ukuran M145 bh 0.0600 950.00 57.00

JUMLAH HARGA BAHAN 36,357.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 76,282.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Langit-langit gypsum board, tebal 9 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700 70,000.00 4,900.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0035 85,000.00 297.50

JUMLAH HARGA TENAGA 13,497.50

B BAHAN

1 Soft Board M212 lbr 0.3500 60,000.00 21,000.000


2 Paku Kayu Segala Ukuran M140 kg 0.0300 13,500.00 405.000
3 Sekrup Segala Ukuran M145 bh 0.3900 950.00 370.500

JUMLAH HARGA BAHAN 21,775.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 35,273.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Langit-langit kalsiboard, tebal 9 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700 70,000.00 4,900.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0035 85,000.00 297.50

JUMLAH HARGA TENAGA 13,497.50

B BAHAN

1 Kalsiboard M656 m2 0.3500 110,000.00 38,500.000


2 Paku Kayu Segala Ukuran M140 kg 0.0300 13,500.00 405.000
3 Sekrup Segala Ukuran M145 bh 0.3900 950.00 370.500

JUMLAH HARGA BAHAN 39,275.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 52,773.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : List langit-langit gypsum
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0500 70,000.00 3,500.00


2 Tukang Kayu L08 Org/hr 0.0500 75,000.00 3,750.00
3 Kepala Tukang Kayu L03 Org/hr 0.0050 80,000.00 400.00
4 Mandor L01 Org/hr 0.0030 85,000.00 255.00

JUMLAH HARGA TENAGA 7,905.00

B BAHAN

1 List Gypsum M211 m' 1.1000 18,000.00 19,800.00


2 Lem Kayu M422 Ltr 0.0500 20,437.50 1,021.88

JUMLAH HARGA BAHAN 20,821.88

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 28,726.88

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Rangka Partisi
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1800 70,000.00 12,600.00


2 Tukang Kayu L08 Org/hr 0.3200 75,000.00 24,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0320 80,000.00 2,560.00
4 Mandor L01 Org/hr 0.0090 85,000.00 765.00
JUMLAH HARGA TENAGA 39,925.00

B BAHAN

1 Rangka kayu kamper 60x60 M675 unit 1.8000 38,000.00 68,400.00


2 Paku segala ukuran M146 kg 0.0600 11,000.00 660.00

JUMLAH HARGA BAHAN 69,060.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 108,985.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Penutup Partisi gypsum board, tebal 9 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700 70,000.00 4,900.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0035 85,000.00 297.50

JUMLAH HARGA TENAGA 13,497.50

B BAHAN

1 Soft Board M212 lbr 0.7500 60,000.00 45,000.000


2 Paku Kayu Segala Ukuran M140 kg 0.0600 13,500.00 810.000
3 Sekrup Segala Ukuran M145 bh 0.8000 950.00 760.000

JUMLAH HARGA BAHAN 46,570.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 60,067.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang lantai keramik ukuran 60 x 60 cm warna/motif
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6000 70,000.00 42,000.00


2 Tukang Batu L07 Org/hr 0.4000 75,000.00 30,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0300 80,000.00 2,400.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 76,950.00

B BAHAN

1 Keramik Lantai 60 x 60 cm warna/motif M318 m2 1.1000 70,000.00 77,000.00


2 Portland Cement (PC) M037 kg 9.8000 1,400.00 13,720.00
3 Pasir Pasang M002 m3 0.0215 82,000.00 1,763.00
4 Portland Cement (PC) Warna M039 kg 1.3000 5,000.00 6,500.00

JUMLAH HARGA BAHAN 98,983.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 175,933.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang lantai keramik ukuran 60 x 60 cm putih
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6000 70,000.00 42,000.00


2 Tukang Batu L07 Org/hr 0.4000 75,000.00 30,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0300 80,000.00 2,400.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 76,950.00

B BAHAN

1 Keramik Lantai 60 x 60 cm putih M318 m2 1.1000 125,000.00 137,500.00


2 Portland Cement (PC) M037 kg 9.8000 1,400.00 13,720.00
3 Pasir Pasang M002 m3 0.0215 82,000.00 1,763.00
4 Portland Cement (PC) Warna M039 kg 1.3000 5,000.00 6,500.00

JUMLAH HARGA BAHAN 159,483.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 236,433.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang lantai keramik KM ukuran 25 x 40 cm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00
2 Tukang Batu L07 Org/hr 0.3500 75,000.00 26,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 75,000.00

B BAHAN

1 Keramik Dinding 25 x 40 cm M323 m2 1.0000 65,000.00 65,000.00


2 Portland Cement (PC) M037 kg 11.3800 1,400.00 15,932.00
3 Pasir Pasang M002 m3 0.0420 82,000.00 3,444.00
4 Portland Cement (PC) Warna M039 kg 1.5000 5,000.00 7,500.00

JUMLAH HARGA BAHAN 91,876.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 166,876.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding keramik ukuran 20 x 25 cm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6000 70,000.00 42,000.00


2 Tukang Batu L07 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0450 80,000.00 3,600.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 85,650.00

B BAHAN

1 Keramik Dinding 25 x 40 cm M327 m2 1.1000 45,000.00 49,500.00


2 Portland Cement (PC) M037 kg 9.3000 1,400.00 13,020.00
3 Pasir Pasang M002 m3 0.0180 82,000.00 1,476.00
4 Portland Cement (PC) Warna M039 kg 1.5000 5,000.00 7,500.00

JUMLAH HARGA BAHAN 71,496.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 157,146.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang plint keramik artistik 5 x 20 cm
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0900 70,000.00 6,300.00


2 Tukang Batu L07 Org/hr 0.0900 75,000.00 6,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0090 80,000.00 720.00
4 Mandor L01 Org/hr 0.0045 85,000.00 382.50

JUMLAH HARGA TENAGA 14,152.50

B BAHAN

1 Plint keramik artistik 5 x 20 M315 m1 1.0000 5,500.00 5,500.00


2 Portland Cement (PC) M037 kg 0.8500 1,400.00 1,190.00
3 Pasir Pasang M002 m3 0.0022 82,000.00 180.40
4 Portland Cement (PC) Warna M039 kg 0.0800 5,000.00 400.00

JUMLAH HARGA BAHAN 7,270.40

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 21,422.90

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang plint keramik lantai ukuran 10 x 40 cm
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.9000 70,000.00 63,000.00


2 Tukang Batu L07 Org/hr 0.0900 75,000.00 6,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0090 80,000.00 720.00
4 Mandor L01 Org/hr 0.0045 85,000.00 382.50

JUMLAH HARGA TENAGA 70,852.50

B BAHAN

1 Plint Keramik Lantai 10 x 40 cm M326 m1 2.5000 7,500.00 18,750.00


2 Portland Cement (PC) M037 kg 1.6500 1,400.00 2,310.00
3 Pasir Pasang M002 m3 0.0032 82,000.00 262.40
4 Portland Cement (PC) Warna M039 kg 0.1000 5,000.00 500.00

JUMLAH HARGA BAHAN 21,822.40

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 92,674.90

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu candi
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00


2 Tukang Batu L07 Org/hr 0.5500 75,000.00 41,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 90,000.00

B BAHAN

1 Batu Candi M826 m2 1.0500 126,500.00 132,825.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 152,145.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 242,145.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu kewal besar
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.3000 70,000.00 91,000.00


2 Tukang Batu L07 Org/hr 1.8000 75,000.00 135,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 231,350.00

B BAHAN

1 Batu Kewal 0 m2 1.0500 165,000.00 173,250.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 192,570.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 423,920.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu andesit 15/30
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00


2 Tukang Batu L07 Org/hr 0.5500 75,000.00 41,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 90,000.00

B BAHAN

1 Batu Andesit 15/30 0 m2 1.0500 120,000.00 126,000.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 145,320.00


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 235,320.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu andesit 2/30
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00


2 Tukang Batu L07 Org/hr 0.5500 75,000.00 41,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 90,000.00

B BAHAN

1 Batu Andesit 2/30 0 m2 1.0500 135,000.00 141,750.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 161,070.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 251,070.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu paras putih
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00


2 Tukang Batu L07 Org/hr 0.5500 75,000.00 41,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 90,000.00

B BAHAN

1 Batu Paras putih 0 m2 1.0500 85,000.00 89,250.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 108,570.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 198,570.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang dinding batu Slate Coopre 30/30
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.6200 70,000.00 43,400.00
2 Tukang Batu L07 Org/hr 0.5500 75,000.00 41,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0350 80,000.00 2,800.00
4 Mandor L01 Org/hr 0.0300 85,000.00 2,550.00

JUMLAH HARGA TENAGA 90,000.00

B BAHAN

1 Batu Slate Cooper 30/30 0 m2 1.0500 397,000.00 416,850.00


2 Portland Cement (PC) M037 kg 11.7500 1,400.00 16,450.00
3 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 436,170.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 526,170.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang paving stone (blok)
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 70,000.00 35,000.00


2 Tukang Batu L07 Org/hr 0.2500 75,000.00 18,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0250 80,000.00 2,000.00
4 Mandor L01 Org/hr 0.0250 85,000.00 2,125.00

JUMLAH HARGA TENAGA 57,875.00

B BAHAN

1 Paving K 300, t = 6 cm M036 m2 1.1000 42,550.00 46,805.00


2 Pasir Pasang M002 m3 0.0350 82,000.00 2,870.00

JUMLAH HARGA BAHAN 49,675.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 107,550.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang Monoblok Sekualitas Toto
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 3.3000 70,000.00 231,000.00


2 Tukang Batu L07 Org/hr 1.1000 75,000.00 82,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0010 80,000.00 80.00
4 Mandor L01 Org/hr 0.1600 85,000.00 13,600.00

JUMLAH HARGA TENAGA 327,180.00

B BAHAN

1 Monoblok Toto cw 520 J M231 Unit 1.0000 1,650,000.00 1,650,000.00


2 Perlengkapan 0.0600 99,000.00 5,940.00

JUMLAH HARGA BAHAN 1,655,940.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,983,120.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang urinoir
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000 70,000.00 70,000.00


2 Tukang Batu L07 Org/hr 1.0000 75,000.00 75,000.00
3 Kepala Tukang Batu L02 Org/hr 0.1000 80,000.00 8,000.00
4 Mandor L01 Org/hr 0.1000 85,000.00 8,500.00

JUMLAH HARGA TENAGA 161,500.00

B BAHAN

1 Urinoir Keramik M246 bh 1.0000 1,650,000.00 1,650,000.00


2 Perlengkapan 0.3000 495,000.00 148,500.00
3 Portland Cement (PC) M037 kg 6.0000 1,400.00 8,400.00
4 Pasir Pasang M002 m3 0.0100 82,000.00 820.00

JUMLAH HARGA BAHAN 1,807,720.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,969,220.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang wastafel kw. A
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.2000 70,000.00 84,000.00


2 Tukang Batu L07 Org/hr 1.4500 75,000.00 108,750.00
3 Kepala Tukang Batu L02 Org/hr 0.1500 80,000.00 12,000.00
4 Mandor L01 Org/hr 0.1000 85,000.00 8,500.00

JUMLAH HARGA TENAGA 213,250.00

B BAHAN

1 Wastafel Komplit (Kran + Sipon ) Kw. A M248 Unit 1.0000 378,062.50 378,062.50
2 Perlengkapan 0.1200 45,367.50 5,444.10
3 Portland Cement (PC) M037 kg 6.0000 1,400.00 8,400.00
4 Pasir Pasang M002 m3 0.0100 82,000.00 820.00

JUMLAH HARGA BAHAN 392,726.60

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 605,976.60

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang tempat sabun keramik
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 9,425.00

B BAHAN

1 Tempat Sabun Keramik sekualitas TOTO M249 bh 1.0000 75,000.00 75,000.00

JUMLAH HARGA BAHAN 75,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 84,425.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang pipa beton, diameter 30 cm
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3800 75,000.00 28,500.00


2 Tukang Batu L07 Org/hr 0.1900 75,000.00 14,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0190 80,000.00 1,520.00
4 Mandor L01 Org/hr 0.0190 85,000.00 1,615.00

JUMLAH HARGA TENAGA 45,885.00

B BAHAN

1 Buis Beton U Dia 0.30 m M053 bh 1.100 45,630.00 50,193.000


2 Bata Merah M022 bh 123.750 550.00 68,062.500
3 Portland Cement (PC) M037 kg 5.150 1,400.00 7,210.000
4 Pasir Pasang M002 m3 0.031 82,000.00 2,501.000
5 Pasir Urug M001 m3 0.035 69,000.00 2,380.500

JUMLAH HARGA BAHAN 130,347.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 176,232.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang bak kontrol pasangan batu bata
ukuran (45 x 45) tinggi 50 cm
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.4200 70,000.00 99,400.00


2 Tukang Batu L07 Org/hr 0.4730 75,000.00 35,475.00
3 Kepala Tukang Batu L02 Org/hr 0.0470 80,000.00 3,760.00
4 Mandor L01 Org/hr 0.0710 85,000.00 6,035.00

JUMLAH HARGA TENAGA 144,670.00

B BAHAN

1 Bata Merah M022 bh 112.5000 550.00 61,875.00


2 Portland Cement (PC) M037 kg 77.0000 1,400.00 107,800.00
3 Pasir Pasang M002 m3 0.1300 82,000.00 10,660.00
4 Stenslah/batu pecah tangan 2/3 M014 m3 0.0200 128,000.00 2,560.00
5 Besi Beton Polos M112 kg 2.6000 7,000.00 18,200.00
6 Pasir Cor M004 m3 0.0900 85,000.00 7,650.00

JUMLAH HARGA BAHAN 208,745.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 353,415.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 3/4"
SATUAN PEMBAYARAN : m'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0360 70,000.00 2,520.00


2 Tukang Batu L07 Org/hr 0.0600 75,000.00 4,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0060 80,000.00 480.00
4 Mandor L01 Org/hr 0.0018 85,000.00 153.00

JUMLAH HARGA TENAGA 7,653.00

B BAHAN

1 Keramik Dinding 20 x 20 cm M335 m2 0.3000 50,000.00 15,000.00


2 Perlengkapan 0.3500 17,500.00 6,125.00

JUMLAH HARGA BAHAN 21,125.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 28,778.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 3"
SATUAN PEMBAYARAN : m'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0810 70,000.00 5,670.00


2 Tukang Batu L07 Org/hr 0.1350 75,000.00 10,125.00
3 Kepala Tukang Batu L02 Org/hr 0.0135 80,000.00 1,080.00
4 Mandor L01 Org/hr 0.0041 85,000.00 348.50

JUMLAH HARGA TENAGA 17,223.50

B BAHAN

1 Pipa PVC tipe AW Dia 3 " M340 Ljr 0.3000 115,000.00 34,500.00
2 Perlengkapan 0.3500 40,250.00 14,087.50

JUMLAH HARGA BAHAN 48,587.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 65,811.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 2,5"
SATUAN PEMBAYARAN : m'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.0810 70,000.00 5,670.00
2 Tukang Batu L07 Org/hr 0.1350 75,000.00 10,125.00
3 Kepala Tukang Batu L02 Org/hr 0.0135 80,000.00 1,080.00
4 Mandor L01 Org/hr 0.0041 85,000.00 348.50

JUMLAH HARGA TENAGA 17,223.50

B BAHAN

1 Pipa PVC d 2,5" M340 Ljr 0.3000 78,000.00 23,400.00


2 Perlengkapan 0.3500 27,300.00 9,555.00

JUMLAH HARGA BAHAN 32,955.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 50,178.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 4"
SATUAN PEMBAYARAN : m'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0810 70,000.00 5,670.00


2 Tukang Batu L07 Org/hr 0.1350 75,000.00 10,125.00
3 Kepala Tukang Batu L02 Org/hr 0.0135 80,000.00 1,080.00
4 Mandor L01 Org/hr 0.0041 85,000.00 348.50

JUMLAH HARGA TENAGA 17,223.50

B BAHAN

1 Pipa PVC tipe AW Dia 4 " M341 Ljr 0.3000 165,000.00 49,500.00
2 Perlengkapan 0.3500 57,750.00 20,212.50

JUMLAH HARGA BAHAN 69,712.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 86,936.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : pasang kran air diameter 3/4"
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 9,425.00

B BAHAN

1 Kran Air 3/4 " M236 bh 1.0000 57,461.25 57,461.25


2 Seal Tape / TBA M481 bh 0.0250 13,397.50 334.94

JUMLAH HARGA BAHAN 57,796.19

C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 67,221.19

ANALISA HARGA SATUAN


JENIS PEKERJAAN : pasang kran wastafel
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 9,425.00

B BAHAN

1 Kran Wastafel M236 bh 1.0000 165,000.00 165,000.00


2 Seal Tape / TBA M481 bh 0.0250 13,397.50 334.94

JUMLAH HARGA BAHAN 165,334.94

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 174,759.94

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang Syphon Wastafel
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Batu L07 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Batu L02 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 9,425.00

B BAHAN

1 Syphon Wastafel M250 bh 1.0000 102,000.00 102,000.00

JUMLAH HARGA BAHAN 102,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 111,425.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang kaca wastafel

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150 70,000.00 1,050.00


2 Tukang Batu L07 Org/hr 0.1500 75,000.00 11,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0150 80,000.00 1,200.00
4 Mandor L01 Org/hr 0.0008 85,000.00 63.75

JUMLAH HARGA TENAGA 13,563.75

B BAHAN

1 Kaca Cermin tebal 5 mm M278 m2 1.0000 142,168.75 142,168.75


2 Perlengkapan 0.1000 142,168.75 14,216.88

JUMLAH HARGA BAHAN 156,385.63

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 169,949.38

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang Saluran Pembuangan Limbah
SATUAN PEMBAYARAN : m'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2500 70,000.00 17,500.00


2 Tukang Batu L07 Org/hr 0.7500 75,000.00 56,250.00
3 Kepala Tukang Batu L02 Org/hr 0.0250 80,000.00 2,000.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 75,962.50

B BAHAN

1 Media Saluran M341 bh 1.0000 165,000.00 165,000.00


2 Perlengkapan 0.7000 115,500.00 80,850.00
3 Penutup saluran 0.2500 145,000.00 36,250.00

JUMLAH HARGA BAHAN 282,100.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 358,062.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang septictank dan resapan
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 20.0000 70,000.00 1,400,000.00


2 Tukang Batu L07 Org/hr 25.0000 75,000.00 1,875,000.00
3 Kepala Tukang Batu L02 Org/hr 12.0000 80,000.00 960,000.00
4 Mandor L01 Org/hr 5.3000 85,000.00 450,500.00

JUMLAH HARGA TENAGA 4,685,500.00

B BAHAN
1 Bata Merah M022 bh 1,000.0000 550.00 550,000.00
2 Portland Cement (PC) M037 kg 350.0000 1,400.00 490,000.00
3 Pasir Pasang M002 m3 3.1000 82,000.00 254,200.00
4 Stenslah/batu pecah tangan 2/3 M014 m3 0.1300 128,000.00 16,640.00
5 Besi Beton Polos M112 kg 100.0000 7,000.00 700,000.00
6 Pasir Cor M004 m3 0.2000 85,000.00 17,000.00

JUMLAH HARGA BAHAN 2,027,840.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 6,713,340.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pemasangan Stop Kontak
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 70,000.00 35,000.00


2 Tukang Listrik L11 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Listrik L06 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 80,750.00

B BAHAN

1 Kabel NYA 2 x 2.5 mm M437 m1 15.0000 7,500.00 112,500.00


2 Stop Kontak ex. Brocco M439 bh 1.0000 27,500.00 27,500.00
3 T dos PVC M443 bh 1.0000 2,500.00 2,500.00
4 Pipa PVC 5/8" M444 Ljr 0.6500 7,187.50 4,671.88

JUMLAH HARGA BAHAN 147,171.88

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 227,921.88

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemasangan titik lampu TL 2x20 Watt inbow (komplit) + saklar
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 70,000.00 35,000.00


2 Tukang Listrik L11 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Listrik L06 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 80,750.00

B BAHAN

1 Lampu TL 2 x 40 Watt Inbow M829 unit 1.0000 325,000.00 325,000.00


2 Kabel NYA 2 x 2.5 mm M437 m1 20.0000 7,500.00 150,000.00
3 Saklar Ganda M830 bh 1.0000 23,500.00 23,500.00
4 Isolator M442 m1 15.0000 750.00 11,250.00
5 T dos PVC M443 bh 2.0000 2,500.00 5,000.00
6 Pipa PVC 5/8" M444 Ljr 1.0000 7,187.50 7,187.50
7 Las doof M441 bh 6.0000 7,500.00 45,000.00

JUMLAH HARGA BAHAN 566,937.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 647,687.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pemasangan titik lampu XL 18 Watt + saklar
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 70,000.00 35,000.00


2 Tukang Listrik L11 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Listrik L06 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 80,750.00

B BAHAN

1 Lampu XL 18 Watt M454 bh 1.0000 34,571.88 34,571.88


2 Kabel NYA 2 x 2.5 mm M437 m1 10.0000 7,500.00 75,000.00
3 Saklar tunggal ex. Brocco Type Gracio M440 bh 1.0000 21,500.00 21,500.00
4 Isolator M442 m1 4.0000 750.00 3,000.00
5 T dos PVC M443 bh 1.0000 2,500.00 2,500.00
6 Pipa PVC 5/8" M444 Ljr 1.0000 7,187.50 7,187.50
7 Fiting Flafond M445 bh 1.0000 9,271.88 9,271.88
8 Las doof M441 bh 4.0000 7,500.00 30,000.00

JUMLAH HARGA BAHAN 183,031.26

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 263,781.26

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemasangan titik lampu XL 23 Watt + saklar
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 70,000.00 35,000.00


2 Tukang Listrik L11 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Listrik L06 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 80,750.00

B BAHAN

1 Lampu XL 23 Watt M455 bh 1.0000 35,808.13 35,808.13


2 Kabel NYA 2 x 2.5 mm M437 m1 10.0000 7,500.00 75,000.00
3 Saklar tunggal ex. Brocco Type Gracio M440 bh 1.0000 21,500.00 21,500.00
4 Isolator M442 m1 4.0000 750.00 3,000.00
5 T dos PVC M443 bh 2.0000 2,500.00 5,000.00
6 Pipa PVC 5/8" M444 Ljr 1.0000 7,187.50 7,187.50
7 Fiting Flafond M445 bh 1.0000 9,271.88 9,271.88
8 Las doof M441 bh 4.0000 7,500.00 30,000.00

JUMLAH HARGA BAHAN 186,767.51

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 267,517.51


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pemasangan Sekering 3 Group
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.2800 70,000.00 89,600.00


2 Tukang Listrik L11 Org/hr 0.1280 75,000.00 9,600.00
3 Kepala Tukang Listrik L06 Org/hr 0.0125 80,000.00 1,000.00
4 Mandor L01 Org/hr 0.0125 85,000.00 1,062.50

JUMLAH HARGA TENAGA 101,262.50

B BAHAN

1 Zekering Kast Lokal 3 Group M448 Unit 1.0000 23,500.00 23,500.00


2 Kabel NYA 4.0 mm M438 m1 12.0000 22,000.00 264,000.00
3 Pipa PVC 5/8" M444 Ljr 3.0000 7,187.50 21,562.50

JUMLAH HARGA BAHAN 309,062.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 410,325.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemasangan Penangkal Petir
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.0000 70,000.00 140,000.00


2 Tukang Listrik L11 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Listrik L06 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0500 85,000.00 4,250.00

JUMLAH HARGA TENAGA 185,750.00

B BAHAN

1 Pipa Arde M460 m' 6.0000 107,956.25 647,737.50


2 Keramik Dinding 20 x 20 cm M334 m2 10.0000 50,000.00 500,000.00
3 Shock Galvanis Dia 1/2 " M384 bh 1.0000 3,399.69 3,399.69
4 Pipa Galvanis Dia 1" M378 Ljr 0.2500 180,000.00 45,000.00
4 Splits Dia 1 " M512 bh 1.0000 75,900.00 75,900.00
5 Timah M513 kg 0.5000 430,100.00 215,050.00
6 Kawat BC M514 m1 80.0000 44,275.00 3,542,000.00

JUMLAH HARGA BAHAN 5,029,087.19

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 5,214,837.19


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pengecatan tembok baru eksterior (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup)
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Cat L10 Org/hr 0.0630 75,000.00 4,725.00
3 Kepala Tukang Cat L05 Org/hr 0.0063 80,000.00 504.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 6,841.50

B BAHAN

1 Plamir Tembok M403 kg 0.1000 8,925.00 892.50


2 Cat Dasar Tembok M412 kg 0.1000 18,000.00 1,800.00
3 Cat Tembok WaterShieild " DULUX" M415 kg 0.2600 96,800.00 25,168.00

JUMLAH HARGA BAHAN 27,860.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 34,702.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pengecatan permukaan baja dengan meni besi
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Cat L10 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Cat L05 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0100 85,000.00 850.00

JUMLAH HARGA TENAGA 18,850.00

B BAHAN

1 Cat dasar besi M413 kg 0.1000 33,062.50 3,306.25


2 Kuas M421 bh 0.0100 11,212.50 112.13
3 Minyak Cat M406 ltr 0.1000 15,711.88 1,571.19

JUMLAH HARGA BAHAN 4,989.56

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 23,839.56


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pekerjaan waterproofing
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Cat L10 Org/hr 0.0630 75,000.00 4,725.00
3 Kepala Tukang Cat L05 Org/hr 0.0063 80,000.00 504.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 6,841.50

B BAHAN

1 Waterproofing M418 kg 0.3600 180,000.00 64,800.00

JUMLAH HARGA BAHAN 64,800.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 71,641.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pekerjaan coating
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Cat L10 Org/hr 0.0630 75,000.00 4,725.00
3 Kepala Tukang Cat L05 Org/hr 0.0063 80,000.00 504.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 6,841.50

B BAHAN

1 Coating batu alam M567 ltr 0.3600 51,750.00 18,630.00


2 Minyak cat M406 Ltr 0.3600 15,711.88 5,656.28

JUMLAH HARGA BAHAN 24,286.28

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 31,127.78


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pengecatan interior dan plafon baru (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup)
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0600 70,000.00 4,200.00


2 Tukang Cat L10 Org/hr 0.0930 75,000.00 6,975.00
3 Kepala Tukang Cat L05 Org/hr 0.0263 80,000.00 2,104.00
4 Mandor L01 Org/hr 0.0125 85,000.00 1,062.50

JUMLAH HARGA TENAGA 14,341.50

B BAHAN

1 Plamir Tembok M403 kg 0.3000 8,925.00 2,677.50


2 Cat Dasar Tembok M412 kg 0.2000 18,000.00 3,600.00
3 Cat Tembok Catylac M550 kg 0.2600 19,000.00 4,940.00
4 Perlengkapan Plamir 2,500.00 2,500.00

JUMLAH HARGA BAHAN 13,717.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 28,059.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang kaca polos, tebal 5 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150 70,000.00 1,050.00


2 Tukang Kayu L08 Org/hr 0.1500 75,000.00 11,250.00
3 Kepala Tukang Kayu L03 Org/hr 0.0150 80,000.00 1,200.00
4 Mandor L01 Org/hr 0.0008 85,000.00 63.75

JUMLAH HARGA TENAGA 13,563.75

B BAHAN

1 Kaca Polos tebal 5 mm M271 m2 1.1000 125,000.00 137,500.00

JUMLAH HARGA BAHAN 137,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 151,063.75

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang engsel pintu
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150 70,000.00 1,050.00


2 Tukang Kayu L08 Org/hr 0.1500 75,000.00 11,250.00
3 Kepala Tukang Kayu L03 Org/hr 0.0150 80,000.00 1,200.00
4 Mandor L01 Org/hr 0.0008 85,000.00 63.75

JUMLAH HARGA TENAGA 13,563.75

B BAHAN

1 Engsel Pintu sekualitas SOLID ( 1 psng 2 bhM257 psng 1.0000 86,250.00 86,250.00

JUMLAH HARGA BAHAN 86,250.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 99,813.75


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang kunci tanam pintu
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Kayu L08 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0050 85,000.00 425.00

JUMLAH HARGA TENAGA 39,425.00

B BAHAN

1 Kunci Tanam sekualitas Dekson M254 bh 1.0000 125,000.00 125,000.00

JUMLAH HARGA BAHAN 125,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 164,425.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pegangan pintu/door holder
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0500 70,000.00 3,500.00


2 Tukang Kayu L08 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 45,212.50

B BAHAN

1 Handel pintu stainless sekualitas Dekson l M266 psng 1.0000 125,000.00 125,000.00

JUMLAH HARGA BAHAN 125,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 170,212.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang door closer
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0500 70,000.00 3,500.00


2 Tukang Kayu L08 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0500 80,000.00 4,000.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 45,212.50

B BAHAN

1 Door Closer M264 bh 1.0000 147,343.75 147,343.75

JUMLAH HARGA BAHAN 147,343.75

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 192,556.25

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang kunci tanam kamar mandi
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0050 70,000.00 350.00


2 Tukang Kayu L08 Org/hr 0.5000 75,000.00 37,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0050 80,000.00 400.00
4 Mandor L01 Org/hr 0.0025 85,000.00 212.50

JUMLAH HARGA TENAGA 38,462.50

B BAHAN

1 Kunci Pintu Kamar Mandi sekualitas SES/S M255 bh 1.0000 76,500.00 76,500.00

JUMLAH HARGA BAHAN 76,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 114,962.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang engsel jendela
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0005 85,000.00 42.50

JUMLAH HARGA TENAGA 9,042.50

B BAHAN

1 Engsel Jendela sekualitas SOLID ( 1 psng 2M258 psng 1.0000 57,500.00 57,500.00

JUMLAH HARGA BAHAN 57,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 66,542.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang grendel jendela
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0005 85,000.00 42.50

JUMLAH HARGA TENAGA 9,042.50

B BAHAN

1 Grendel jendela M263 bh 1.0000 21,500.00 21,500.00

JUMLAH HARGA BAHAN 21,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 30,542.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang hak angin
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Kayu L08 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0100 85,000.00 850.00

JUMLAH HARGA TENAGA 18,850.00

B BAHAN

1 Hak Angin ( sikuitan ) sekualitas SOLID M259 psng 1.0000 28,750.00 28,750.00

JUMLAH HARGA BAHAN 28,750.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 47,600.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang kaca buram, tebal 5 mm
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0250 70,000.00 1,750.00


2 Tukang Kayu L08 Org/hr 0.2500 75,000.00 18,750.00
3 Kepala Tukang Kayu L03 Org/hr 0.0250 80,000.00 2,000.00
4 Mandor L01 Org/hr 0.0013 85,000.00 106.25

JUMLAH HARGA TENAGA 22,606.25

B BAHAN

1 Kaca Buram tebal 5 mm M275 m2 1.1000 140,343.13 154,377.44

JUMLAH HARGA BAHAN 154,377.44

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 176,983.69


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang kaca bouven rangka aluminium
SATUAN PEMBAYARAN : m2
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.6500 75,000.00 48,750.00
2 Tukang Batu L07 Org/hr 0.6500 75,000.00 48,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0650 80,000.00 5,200.00
4 Mandor L01 Org/hr 0.0320 85,000.00 2,720.00

JUMLAH HARGA TENAGA 105,420.00


B BAHAN
1 Kusen Aluminium Coklat M126 m1 2.4000 115,922.53 278,214.07
2 Perlengkapan 0.2500 278,214.07 69,553.52
3 Kaca buram M275 m2 1.0000 140,343.13 140,343.13

JUMLAH HARGA BAHAN 488,110.72

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 593,530.72

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang Railling besi
SATUAN PEMBAYARAN : m1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.0810 30,000.00 2,430.00
2 Tukang Batu L07 Org/hr 0.1350 47,500.00 6,412.50
3 Kepala Tukang Batu L02 Org/hr 0.0135 55,000.00 742.50
4 Mandor L01 Org/hr 0.0041 60,000.00 246.00
JUMLAH HARGA TENAGA 9,831.00
B BAHAN
1 Pipa GI 1 1/4 " M536 ljr 0.3300 225,500.00 74,415.00
2 Perlengkapan 0.3500 78,925.00 27,623.75
JUMLAH HARGA BAHAN 102,038.75
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 111,869.75

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang grendel tanam pintu
SATUAN PEMBAYARAN : bh
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100 70,000.00 700.00


2 Tukang Kayu L08 Org/hr 0.1000 75,000.00 7,500.00
3 Kepala Tukang Kayu L03 Org/hr 0.0100 80,000.00 800.00
4 Mandor L01 Org/hr 0.0005 85,000.00 42.50

JUMLAH HARGA TENAGA 9,042.50


B BAHAN

1 Grendel pintu tanam M836 unit 1.0000 83,500.00 83,500.00

JUMLAH HARGA BAHAN 83,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 92,542.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pemasangan Baja Profil WF
SATUAN PEMBAYARAN : Kg
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00
2 Tukang Besi/Baja L09 Org/hr 0.0300 75,000.00 2,250.00
3 Kepala Tukang Besi L04 Org/hr 80,000.00
4 Mandor L01 Org/hr 85,000.00

JUMLAH HARGA TENAGA 3,650.00


B BAHAN
1 Baja Profil (WF/ C) M116 kg 1.0500 29,500.00 30,975.00
2 Elektroda M473 kg 0.0220 20,125.00 442.75
3 Sewa Mesin las M490 hr 0.0220 158,125.00 3,478.75

JUMLAH HARGA BAHAN 34,896.50


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 38,546.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemasangan Baja Canal C
SATUAN PEMBAYARAN : Kg
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00
2 Tukang Besi/Baja L09 Org/hr 0.0300 75,000.00 2,250.00
3 Kepala Tukang Besi L04 Org/hr 80,000.00 -
4 Mandor L01 Org/hr 85,000.00

JUMLAH HARGA TENAGA 3,650.00


B BAHAN
1 Baja Profil (WF/ C) M116 kg 1.0500 29,500.00 30,975.00
2 Elektroda M473 kg 0.0220 20,125.00 442.75
3 Sewa Mesin las M490 hr 0.0220 158,125.00 3,478.75

JUMLAH HARGA BAHAN 34,896.50


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 38,546.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pemasangan Baut Anker Baja
SATUAN PEMBAYARAN : Bh
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00
2 Tukang Besi/Baja L09 Org/hr 0.0300 75,000.00 2,250.00
3 Kepala Tukang Besi L04 Org/hr 80,000.00 -
4 Mandor L01 Org/hr 85,000.00 -

JUMLAH HARGA TENAGA 3,650.00


B BAHAN
1 Baut Segala Ukuran M146 kg 2.0400 13,800.00 28,152.00
2 Angker Bar f 22 mm M117 kg 1.0000 12,937.50 12,937.50

JUMLAH HARGA BAHAN 41,089.50


C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 44,739.50


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Ikatan Angin/Trekstang
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Besi/Baja L09 Org/hr 0.0300 75,000.00 2,250.00
3 Kepala Tukang Besi L04 Org/hr 80,000.00 -
4 Mandor L01 Org/hr 85,000.00

JUMLAH HARGA TENAGA 3,650.00

B BAHAN

1 Besi Beton Polos M112 kg 1.0500 7,000.00 7,350.00


2 Elektroda M473 kg 0.0220 20,125.00 442.75
3 Sewa Mesin las M490 hr 0.0220 158,125.00 3,478.75

JUMLAH HARGA BAHAN 11,271.50

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 14,921.50

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Plendes
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200 70,000.00 1,400.00


2 Tukang Besi/Baja L09 Org/hr 0.0300 75,000.00 2,250.00
3 Kepala Tukang Besi L04 Org/hr 80,000.00 -
4 Mandor L01 Org/hr 85,000.00

JUMLAH HARGA TENAGA 3,650.00

B BAHAN

1 Baja Profil (WF/ C) M116 kg 1.0500 20,328.13 21,344.54


2 Elektroda M473 kg 0.0220 20,125.00 442.75
3 Sewa Mesin las M490 hr 0.0220 158,125.00 3,478.75

JUMLAH HARGA BAHAN 25,266.04

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 28,916.04


ANALISA HARGA SATUAN
KODE ANALISA : A.318
JENIS PEKERJAAN : Pasang atap genteng beton
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500 70,000.00 10,500.00


2 Tukang Kayu L08 Org/hr 0.0750 75,000.00 5,625.00
3 Kepala Tukang Kayu L03 Org/hr 0.0080 80,000.00 640.00
4 Mandor L01 Org/hr 0.0080 85,000.00 680.00

JUMLAH HARGA TENAGA 17,445.00

B BAHAN

1 Genteng Beton Cira M833 bh 14.0000 5,500.00 77,000.00

JUMLAH HARGA BAHAN 77,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 94,445.00

ANALISA HARGA SATUAN


KODE ANALISA : A.323
JENIS PEKERJAAN : Pasang bubung genteng beton
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 70,000.00 28,000.00


2 Tukang Kayu L08 Org/hr 0.3500 75,000.00 26,250.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0020 85,000.00 170.00

JUMLAH HARGA TENAGA 56,020.00

B BAHAN

1 Bubung genteng keramik M834 bh 5.0000 14,500.00 72,500.00


2 Portland Cement (PC) M037 kg 8.0000 1,400.00 11,200.00
3 Pasir Pasang M002 m3 0.0320 82,000.00 2,624.00

JUMLAH HARGA BAHAN 86,324.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 142,344.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang usuk dan reng baja ringan
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 70,000.00 28,000.00


2 Tukang Kayu L08 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0020 85,000.00 170.00

JUMLAH HARGA TENAGA 44,770.00

B BAHAN

1 Usuk dan reng baja ringan M832 m2 1.1000 115,000.00 126,500.00


2 Sekrup segala ukuran M145 bh 8.0000 950.00 7,600.00

JUMLAH HARGA BAHAN 134,100.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 178,870.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang lisplank dan rangka
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 70,000.00 28,000.00


2 Tukang Kayu L08 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0020 85,000.00 170.00

JUMLAH HARGA TENAGA 44,770.00

B BAHAN

1 Usuk baja ringan M832 m2 0.4500 110,000.00 49,500.00


2 Sekrup segala ukuran M145 bh 8.0000 950.00 7,600.00
3 Lisplank woodplank M835 ljr 0.5000 32,000.00 16,000.00

JUMLAH HARGA BAHAN 73,100.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 117,870.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang Rangka besi siku
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 70,000.00 28,000.00


2 Tukang Kayu L08 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0020 85,000.00 170.00

JUMLAH HARGA TENAGA 44,770.00

B BAHAN

1 Besi siku M740 m1 1.0000 54,500.00 54,500.00

JUMLAH HARGA BAHAN 54,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 99,270.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang rangka atap baja
SATUAN PEMBAYARAN : kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0060 70,000.00 420.00


2 Tukang Besi/Baja L09 Org/hr 0.0600 75,000.00 4,500.00
3 Kepala Tukang Besi L04 Org/hr 0.0060 80,000.00 480.00
4 Mandor L01 Org/hr 0.0030 85,000.00 255.00

JUMLAH HARGA TENAGA 5,655.00

B BAHAN

1 Baja Profil (WF/ C) M116 kg 1.1000 20,328.13 22,360.94


2 Cat Dasar Besi M413 kg 0.0800 33,062.50 2,645.00

JUMLAH HARGA BAHAN 25,005.94

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 30,660.94

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang Kusen Alluminium Coklat
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000 70,000.00 70,000.00


2 Tukang Batu L07 Org/hr - 75,000.00 -
3 Kepala Tukang Batu L02 Org/hr - 80,000.00 -
4 Mandor L01 Org/hr 0.0052 85,000.00 442.00

JUMLAH HARGA TENAGA 70,442.00

B BAHAN

1 Kusen Alumunium Coklat sekualitas YKK 4" M126 m1 1.0000 75,000.00 75,000.00
2 Perlengkapan 0.1500 75,000.00 11,250.00

JUMLAH HARGA BAHAN 86,250.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 156,692.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang jendela kaca rangka aluminium coklat
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6500 75,000.00 48,750.00


2 Tukang Batu L07 Org/hr 0.6500 75,000.00 48,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0650 80,000.00 5,200.00
4 Mandor L01 Org/hr 0.0320 85,000.00 2,720.00

JUMLAH HARGA TENAGA 105,420.00

B BAHAN

1 Jendela Alumunium Coklat sekualitas YKK M503 m1 4.1000 65,375.00 268,037.50


2 Perlengkapan 0.2500 268,037.50 67,009.38
3 Kaca polos 5 mm M271 m2 0.8500 125,000.00 106,250.00

JUMLAH HARGA BAHAN 441,296.88

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 546,716.88

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pintu fiber KM/WC
SATUAN PEMBAYARAN : m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0500 70,000.00 73,500.00


2 Tukang Batu L07 Org/hr 1.0500 75,000.00 78,750.00
3 Kepala Tukang Batu L02 Org/hr 0.1050 80,000.00 8,400.00
4 Mandor L01 Org/hr 0.0052 85,000.00 442.00

JUMLAH HARGA TENAGA 161,092.00

B BAHAN

1 Pintu Fiber KM M128 m2 1.0000 250,000.00 250,000.00

JUMLAH HARGA BAHAN 250,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 411,092.00


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang talang tegak pipa PVC f 4"
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1200 70,000.00 8,400.00


2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0010 85,000.00 85.00

JUMLAH HARGA TENAGA 25,085.00

B BAHAN

1 Pipa PVC tipe D Dia 4 " M351 Ljr 0.2500 163,067.13 40,766.78
2 Lem Pipa PVC M423 kg 0.1000 29,325.00 2,932.50
3 Knee PVC Dia 4 " M375 bh 0.2500 19,470.94 4,867.74
4 Tee PVC Dia 1 1/4 " M367 bh 0.2500 6,000.00 1,500.00

JUMLAH HARGA BAHAN 50,067.02

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 75,152.02

ANALISA HARGA SATUAN


JENIS PEKERJAAN : Pasang pintu
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.8000 75,000.00 60,000.00


2 Tukang Batu L07 Org/hr 0.6500 75,000.00 48,750.00
3 Kepala Tukang Batu L02 Org/hr 0.0650 80,000.00 5,200.00
4 Mandor L01 Org/hr 0.0320 85,000.00 2,720.00

JUMLAH HARGA TENAGA 116,670.00

B BAHAN

1 Slimar Kayu M675 m1 7.6000 126,000.00 957,600.00


2 Perlengkapan 0.3500 957,600.00 335,160.00
3 HPL M275 m2 2.4000 140,343.13 336,823.51

JUMLAH HARGA BAHAN 1,629,583.51

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,746,253.51


ANALISA HARGA SATUAN
JENIS PEKERJAAN : Pasang pagar besi hollow
SATUAN PEMBAYARAN : m1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1200 70,000.00 8,400.00


2 Tukang Batu L07 Org/hr 0.2000 75,000.00 15,000.00
3 Kepala Tukang Batu L02 Org/hr 0.0200 80,000.00 1,600.00
4 Mandor L01 Org/hr 0.0010 85,000.00 85.00

JUMLAH HARGA TENAGA 25,085.00

B BAHAN

1 Pagar besi M123 m2 1.1000 250,000.00 275,000.00


2 Perlengkapan 0.2500 598,500.00 149,625.00
3 Cat dasar besi M413 kg 0.2500 33,062.50 8,265.63
4 Cat besi M416 kg 0.2500 48,875.00 12,218.75

JUMLAH HARGA BAHAN 445,109.38

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 470,194.38


DAFTAR UPAH
TAHUN ANGGARAN 2011

KODE URAIAN SATUAN UPAH (Rp.) KETERANGAN

L01 Mandor Org/hr 85,000.00


L02 Kepala Tukang Batu Org/hr 80,000.00
L03 Kepala Tukang Kayu Org/hr 80,000.00
L04 Kepala Tukang Besi Org/hr 80,000.00
L05 Kepala Tukang Cat Org/hr 80,000.00
L06 Kepala Tukang Listrik Org/hr 80,000.00
L07 Tukang Batu Org/hr 75,000.00
L08 Tukang Kayu Org/hr 75,000.00
L09 Tukang Besi/Baja Org/hr 75,000.00
L10 Tukang Cat Org/hr 75,000.00
L11 Tukang Listrik Org/hr 75,000.00
L12 Tukang Pipa Org/hr 75,000.00
L13 Tukang Plitur Org/hr 75,000.00
L14 Tukang Taman Org/hr 75,000.00
L15 Tukang Aspal Org/hr 75,000.00
L16 Pembantu Tukang Org/hr 75,000.00
L17 Pekerja Biasa Org/hr 70,000.00
L18 Penjaga Malam Org/hr 70,000.00
L19 Sopir Org/hr 75,000.00
L20 Operator Org/hr 65,000.00
L21 Mekanik Org/hr 65,000.00
L22 Pembantu Sopir Org/hr 65,000.00
L23 Pembantu Operator Org/hr 65,000.00
L24 Pembantu Mekanik Org/hr 65,000.00
L25 Juru Ukur Org/hr 70,000.00
L26 Engineer dan Crew Ls 400,000.00
DAFTAR HARGA BAHAN BANGUNAN
TAHUN ANGGARAN 2011

NO. KODE BAHAN BANGUNAN SATUAN HARGA

I. TANAH DAN PASIR


1 M001 Pasir Urug 1 m3 69,000.00
2 M002 Pasir Pasang 1 m3 82,000.00
3 M003 Pasir Hitam 1 m3 85,000.00
4 M004 Pasir Cor 1 m3 85,000.00
5 M005 Pasir Silika 1 m3 7,489.38
6 M006 Tanah Urug 1 m3 60,000.00
7 M007 Sirtu 1 m3 60,000.00
8 M008 Tanah Urug Taman/Katel 1 m3 60,000.00
9 M009 Tanah Liat 1 m3 42,923.75
II. BATU, BATA DAN BETON BLOCK
1 M010 Batu Belah Gunung 1 m3 85,000.00
2 M011 Batu Belah Kali 1 m3 105,000.00
3 M012 Batu Kali 1 m3 100,280.00
4 M013 Stenslah/batu pecah tangan 1/2 1 m3 128,700.00
5 M014 Stenslah/batu pecah tangan 2/3 1 m3 128,000.00
6 M015 Stenslah/batu pecah tangan 3/5 1 m3 113,300.00
7 M016 Stenslah/batu pecah tangan 4/6 - 5/7 1 m3 103,000.00
8 M017 Batu pecah mesin 1/1 1 m3 188,025.00
9 M018 Batu pecah mesin 1/2 1 m3 183,597.50
10 M019 Batu pecah mesin 2/3 1 m3 105,000.00
11 M020 Batu pecah mesin 3/5 1 m3 159,648.75
12 M021 Batu pecah mesin 4/6 - 5/7 1 m3 142,945.00
13 M022 Bata Merah 1 bh 550.00
14 M027 Batu Teraso 1 kg 2,026.88
15 M028 Batu Palimanan 1 m2 76,561.25
16 M029 Batu Tempel Hitam 1 m2 48,113.13
17 M036 Paving K 300, t = 6 cm 1 m2 42,550.00
III. SEMEN
1 M037 Portland Cement (PC) 1 kg 1,400.00
2 M038 Portland Cement (PC) Putih 1 kg 2,285.63
3 M039 Portland Cement (PC) Warna 1 kg 5,000.00
4 M040 Portland Cement (PC) Grouting 1 kg 6,138.13
IV. BUIS BETON
1 M044 Buis Beton Dia 0.20 m 1 bh 30,532.50
2 M045 Buis Beton Dia 0.30 m 1 bh 55,630.00
3 M046 Buis Beton Dia 0.40 m 1 bh 50,945.00
4 M051 Buis Beton Dia 1.00 m 1 bh 235,405.00
5 M052 Buis Beton U Dia 0.20 m 1 bh 28,103.13
6 M053 Buis Beton U Dia 0.30 m 1 bh 45,630.00
VIII. KAYU
Kayu Borneo
1 M054 Reng : 2/3, 3/5 1 m3 4,364,250.00
2 M055 Usuk : 5/7 1 m3 4,364,250.00
3 M056 Balok 1 m3 4,364,250.00
4 M057 Papan (2x20) cm 1 m3 4,628,750.00
5 M058 Papan (3x20) cm 1 m3 4,628,750.00
6 M059 Papan (3x30) cm 1 m3 4,628,750.00
Kayu Meranti
7 M060 Reng : 2/3, 3/5 1 m3 3,300,000.00
8 M061 Usuk : 5/7 1 m3 3,000,000.00
9 M062 Balok 1 m3 3,000,000.00
10 M063 Papan (2x20) cm 1 m3 3,000,000.00
11 M064 Papan (3x20) cm 1 m3 4,560,000.00
12 M065 Papan (3x30) cm 1 m3 4,560,000.00
Kayu Kruing
13 M066 Reng : 2/3, 3/5 1 m3 4,250,000.00
14 M067 Usuk : 5/7 1 m3 5,057,690.00
15 M068 Balok 1 m3 6,600,000.00
16 M069 Papan (2x20) cm 1 m3 4,400,000.00
17 M070 Papan (3x20) cm 1 m3 4,000,000.00
18 M071 Papan (3x30) cm 1 m3 4,000,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

Kayu Bengkirai
19 M072 Reng : 2/3, 3/5 1 m3 4,364,250.00
20 M073 Usuk : 5/7 1 m3 4,364,250.00
21 M074 Balok 1 m3 4,364,250.00
22 M075 Papan (2x20) cm 1 m3 4,628,750.00
23 M076 Papan (3x20) cm 1 m3 4,628,750.00
24 M077 Papan (3x30) cm 1 m3 4,628,750.00
Kayu Kamper
25 M078 Reng : 2/3, 3/4 1 m3 8,525,000.00
26 M079 Usuk : 4/6, 5/7 1 m3 8,525,000.00
27 M080 Balok 1 m3 9,200,000.00
28 M081 Papan (2x20) cm 1 m3 8,525,000.00
29 M082 Papan (3x20) cm 1 m3 8,525,000.00
30 M083 Papan (3x30) cm 1 m3 8,525,000.00
Kayu Lain-lain
31 M084 Sirap 1 m3 5,422,250.00
32 M085 Bakar 1 m3 5,752,875.00
33 M086 Kayu Albasiah 1 m3 6,414,125.00
34 M087 Kayu Ramin 1 m3 7,406,000.00
35 M088 Bambu Dia 10 cm 1 btg 20,400.00
36 M089 Dolken Kayu Dia 8 cm 1 btg 20,000.00
37 M090 List Kayu Profil 1 m1 13,800.00
38 M091 List Kayu 2/4 1 m3 2,777,250.00
39 M092 Gedeg (2.00 x 3.00) m 1 lbr 33,062.50
40 M093 Bilik Bambu 1 m2 66,125.00
Kayu Jati Ex. Malang
41 M094 Reng : 2/3, 3/5 1 m3 11,902,500.00
42 M095 Usuk : 5/7 1 m3 11,902,500.00
43 M096 Balok 1 m3 11,902,500.00
44 M097 Papan (2x20) cm 1 m3 13,225,000.00
45 M098 Papan (3x20) cm 1 m3 13,225,000.00
46 M099 Papan (3x30) cm 1 m3 13,225,000.00
Kayu Jati Ex. Madiun/Ngawi
47 M100 Reng : 2/3, 3/5 1 m3 15,208,750.00
48 M101 Usuk : 5/7 1 m3 15,208,750.00
49 M102 Balok 1 m3 15,208,750.00
50 M103 Papan (2x20) cm 1 m3 15,208,750.00
51 M104 Papan (3x20) cm 1 m3 15,208,750.00
52 M105 Papan (3x30) cm 1 m3 15,208,750.00
Kayu Jati Ex. Bojonegoro
53 M106 Reng : 2/3, 3/5 1 m3 19,837,500.00
54 M107 Usuk : 5/7 1 m3 19,837,500.00
55 M108 Balok 1 m3 19,837,500.00
56 M109 Papan (2x20) cm 1 m3 19,837,500.00
57 M110 Papan (3x20) cm 1 m3 19,837,500.00
58 M111 Papan (3x30) cm 1 m3 19,837,500.00
VI BESI DAN ALUMINIUM
1 M112 Besi Beton Polos 1 kg 7,000.00
2 M113 Besi Beton Ulir 1 kg 7,500.00
3 M114 Besi Strip 1 kg 13,800.00
4 M115 Besi Beugel/Kawel 1 kg 11,787.50
5 M116 Baja Profil (WF/ C) 1 kg 20,328.13
6 M117 Angker Bar f 22 mm 1 kg 12,937.50
7 M118 Kabel prestressed 1 kg 31,481.25
8 M122 Rolling Door 1 m2 1,231,937.50
9 M123 Pagar Besi 1 m2 599,437.50
10 M124 Pintu Pagar besi 1 m2 710,843.75
11 M125 Kusen Alumunium Putih sekualitas YKK 4 " 1 m1 100,100.00
12 M126 Kusen Alumunium Coklat sekualitas YKK 4" 1 m1 115,922.53
13 M127 Pintu Aluminium 1 m2 250,000.00
14 M128 Pintu Fiber KM 1 m2 250,000.00
15 M135 Kawat Beton/Bendrat RRT 1 kg 10,400.00
16 M140 Paku Kayu Segala Ukuran 1 kg 13,500.00
17 M141 Paku Seng Segala Ukuran 1 kg 15,093.75
18 M142 Paku Asbes Segala Ukuran 1 bh 546.25
19 M143 Paku Sumbat Segala Ukuran 1 bh 865.38
20 M144 Paku Kait Segala Ukuran 1 bh 575.00
21 M145 Sekrup Segala Ukuran 1 bh 950.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

22 M146 Baut Segala Ukuran 1 kg 13,800.00


23 M147 Paku Keling 1 bh 3,148.13
24 M148 Kawel 1 kg
VII ATAP GENTENG
1 M154 Genteng sekualitas Kanmuri 1 bh 7,850.00
2 M155 Genteng Kaca 1 bh 15,525.00
3 M161 Bubung Genteng sekualitas Kanmuri 1 bh 13,750.00
VIII ATAP SENG/ASBES
1 M174 Seng plat BJLS 30 L = 0.45 M 1 m' 25,645.00
2 M175 Seng plat BJLS 30 L = 0.60 M 1 m' 30,072.50
3 M176 Seng plat BJLS 30 L = 0.90 M 1 m' 41,170.00
4 M177 Seng plat BJLS 28 (90 x 180) cm lbr 69,258.75
5 M178 Atap Seng Gelombang 210x80x2 1 lbr 51,000.00
6 M179 Bubung Seng Gelombang lbr 78,027.50
7 M180 Roof Light Fibreglass 1 m2 81,851.25
8 M181 Atap Polycarbonat 1 m2 119,628.75
9 M182 Asbes Gelombang (3.00 x 1.05) m x 4 mm 1 lbr 98,210.00
10 M183 Asbes Gelombang (2.70 x 1.05) m x 4 mm 1 lbr 90,620.00
11 M184 Asbes Gelombang (2.40 x 1.05) m x 4 mm 1 lbr 78,522.00
12 M185 Asbes Gelombang (2.10 x 1.05) m x 4 mm 1 lbr 69,506.00
13 M186 Asbes Gelombang (1.50 x 1.05) m x 4 mm 1 lbr 52,842.50
14 M187 Asbes Gelombang (2.50 x 0.92) m x 5 mm 1 lbr 99,693.50
15 M188 Asbes Gelombang (2.25 x 0.92) m x 5 mm 1 lbr 86,392.31
16 M189 Asbes Gelombang (2.00 x 0.92) m x 5 mm 1 lbr 76,453.44
17 M190 Asbes Gelombang (1.80 x 0.92) m x 5 mm 1 lbr 58,149.75
18 M191 Asbes Gelombang (3.00 x 1.08) m x 6 mm 1 lbr 117,840.50
19 M192 Asbes Gelombang (2.70 x 1.08) m x 6 mm 1 lbr 108,767.00
20 M193 Asbes Gelombang (2.10 x 1.08) m x 6 mm 1 lbr 83,425.31
26 M199 Bubung Paten 1.05 m 1 lbr 44,073.75
27 M200 Bubung Paten 1.08 m 1 lbr 47,502.19
28 M201 Bubung Stel Rata 0.92 m 1 lbr 37,777.50
29 M202 Bubung Stel Rata 1.05 m 1 lbr 40,925.63
30 M203 Asbes (1,00 x 1,00) m x 6 mm 1 lbr 7,187.50
31 M204 Asbes (1,00 x 1,00) m x 5 mm 1 lbr 6,440.00
32 M205 Asbes (1,00 x 1,00) m x 4 mm 1 lbr 6,267.50
33 M206 Asbes (1,00 x 1,00) m x 3,5 mm 1 lbr 7,475.00
34 M207 Akustik (30 x 30) cm 1 lbr
35 M208 Akustik (30 x 60) cm 1 lbr 10,680.63
36 M209 Akustik (60 x 120) cm 1 lbr 40,925.63
37 M210 Harplek 4 mm 1 m2 56,666.25
38 M211 List Gypsum 1 m' 18,000.00
39 M212 Soft Board 1 lbr 60,000.00
40 M213 Gypsum Board sekualitas Jayaboard 1 lbr 90,000.00
IX. KAYU OLAHAN
1 M214 Triplek 3 mm 1 m2 48,000.00
2 M215 Triplek 4 mm 1 m2 55,000.00
3 M216 Multiplek 6 mm 1 m2 75,000.00
4 M217 Multiplek 9 mm 1 m2 45,738.00
5 M218 Multiplek 10 mm 1 m2 154,100.00
6 M219 Multiplek 12 mm 1 m2 176,065.00
7 M220 Multiplek 18 mm 1 m2 67,500.00
8 M227 Teakwood (30 x 60) cm x 4 mm 1 lbr 8,150.63
9 M228 Teakwood (60 x 120) cm x 4 mm 1 lbr 28,951.25
10 M229 Teakwood (120 x 240) cm x 4 mm 1 lbr 92,345.00
X. PERLENGKAPAN KAMAR MANDI
1 M230 Kloset Jongkok sekualitas TOTO 1 Unit 230,000.00
2 M231 Kloset Duduk TOTO Standard 1 Unit 1,750,000.00
3 M232 Kloset Jongkok Lux 1 Unit 314,812.50
4 M233 Kloset Duduk Lux 1 Unit 1,637,025.00
5 M234 Kloset Jongkok Teraso 1 bh 62,962.50
6 M235 Kran Air 1/2 " ex. TOTO 1 bh 85,000.00
7 M236 Kran Air 3/4 " 1 bh 57,461.25
8 M237 Bak Mandi Teraso 1 bh 117,875.00
9 M238 Bak Mandi Fibre 1 bh 282,325.00
10 M239 Bak Mandi Plastik 1 bh 179,975.00
11 M240 Bak Mandi Porselin 1 bh 2,203,687.50
12 M241 Kran Bathub Panas dan dingin 1 bh 368,575.00
13 M242 Bak Cuci Piring Teraso 1 bh 205,275.00
14 M243 Bak Cuci Piring Stainless 1 bh 650,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA
NO. KODE BAHAN BANGUNAN SATUAN HARGA

15 M244 Badkip Porselen 1 bh 944,437.00


16 M245 Urinoir sekualitas TOTO 1 bh 1,650,000.00
17 M246 Urinoir Keramik 1 bh 1,250,000.00
18 M247 Wastafel Komplit sekualitas TOTO Type Claston LW 781 J 1 Unit 747,500.00
19 M248 Wastafel Komplit (Kran + Sipon ) Kw. A 1 Unit 378,062.50
20 M249 Tempat Sabun Keramik sekualitas TOTO 1 bh 75,000.00
21 M250 Afor Stainless 1 bh 50,558.75
22 M251 Afor Plastic 1 bh 14,087.50
23 M252 Kaca Wastafel 1 bh 62,962.50
XI ALAT-ALAT PENGGANTUNG
1 M253 Kunci Tanam sekualitas SOLID 1 bh 150,000.00
2 M254 Kunci Tanam sekualitas Dekson 1 bh 356,500.00
3 M255 Kunci Pintu Kamar Mandi sekualitas SES/SOLID 1 bh 76,500.00
4 M256 Kunci pintu, Stainless steel ex. SOLID 1 unit 287,500.00
5 M257 Engsel Pintu sekualitas SOLID ( 1 psng 2 bh ) 1 psng 86,250.00
6 M258 Engsel Jendela sekualitas SOLID ( 1 psng 2 bh ) 1 psng 57,500.00
7 M259 Hak Angin ( sikuitan ) sekualitas SOLID 1 psng 28,750.00
8 M260 Spring Knip 10,350.00
9 M261 Kait Angin 1 bh 8,337.50
10 M262 Grendel pintu sekualitas SOLID 1 bh 42,000.00
11 M263 Grendel jendela 1 bh 21,500.00
12 M264 Door Closer 1 bh 147,343.75
13 M265 Slot/Kunci Pintu 1 bh 25,000.00
14 M266 Handel pintu stainless sekualitas Dekson l = 30 cm 1 psng 392,000.00
15 M267 Door Stop 1 bh 31,050.00
16 M268 Rel Pintu Dorong 1 bh 113,490.63
17 M269 Kunci Lemari 1 bh 12,031.88
VII KACA
1 M270 Kaca es tebal 6 mm 1 m2 116,325.00
2 M271 Kaca Polos tebal 5 mm 1 m2 125,000.00
3 M272 Kaca Polos tebal 8 mm 1 m2 171,084.06
4 M273 Kaca temperd tebal 12 mm 1 m2 660,000.00
5 M274 Kaca Buram tebal 3 mm 1 m2 85,243.75
6 M275 Kaca Buram tebal 5 mm 1 m2 140,343.13
7 M276 Kaca Buram tebal 8 mm 1 m2 208,581.25
8 M277 Kaca Buram tebal 12 mm 1 m2 284,481.25
9 M278 Kaca Cermin tebal 5 mm 1 m2 142,168.75
10 M279 Kaca Cermin tebal 6 mm 1 m2 168,791.25
11 M280 Kaca Cermin tebal 8 mm 1 m2 225,055.00
12 M281 Kaca es tebal 5 mm 1 m2 95,000.00
13 M282 Kaca Rayben 20 % tebal 6 mm 1 m2 148,996.88
14 M283 Kaca Rayben 10 % tebal 8 mm 1 m2 197,340.00
15 M284 Kaca Rayben tebal 12 mm 1 m2 266,433.44
XI. PERLENGKAPAN LANTAI
22 M311 Lantai keramik artistik 10 x 10 1 m2 9,271.88
23 M312 Lantai keramik artistik 5 x 20 1 m2 9,271.88
24 M313 Plint keramik artistik 10 x 20 1 m2 18,543.75
25 M314 Plint keramik artistik 10 x 10 1 m2 18,543.75
26 M315 Plint keramik artistik 5 x 20 1 m1 5,500.00
27 M316 Internal cove 5 x 5 x 20 cm 1 m2 24,725.00
28 M317 Keramik Lantai 40 x 40 cm putih 1 m2 57,000.00
29 M318 Keramik Lantai 40 x 40 cm warna/motif 1 m2 62,500.00
30 M319 Keramik Lantai 60 x 60 cm putih 1 m2 156,000.00
31 M320 Keramik Lantai 60 x 60 cm warna/motif 1 m2 245,000.00
32 M321 Keramik Lantai 25 x 40 cm putih 1 m2 45,000.00
33 M322 Keramik Lantai 20 x 20 cm warna/motif 1 m2 47,500.00
34 M323 Keramik Lantai KM 20 x 20 cm 1 m2 45,000.00
35 M324 Plint Keramik Lantai 10 x 20 cm 1 bh 6,000.00
36 M325 Plint Keramik Lantai 10 x 60 cm 1 m2 9,271.88
37 M326 Plint Keramik Lantai 10 x 40 cm 1 m1 7,500.00
38 M327 Keramik Dinding 25 x 40 cm 1 m2 65,000.00
39 M328 Keramik Dinding 20 x 20 cm 1 m2 50,000.00
XII PERPIPAAN
1 M338 Pipa PVC tipe AW Dia 1/2 " ex. Maspion 1 Ljr 20,700.00
2 M339 Pipa PVC tipe AW Dia 3/4 " ex. Maspion 1 Ljr 23,000.00
3 M340 Pipa PVC tipe AW Dia 3 " 1 Ljr 115,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

4 M341 Pipa PVC tipe AW Dia 4 " 1 Ljr 165,000.00


5 M342 Pipa PVC tipe AW Dia 5 " 1 Ljr 281,390.63
6 M343 Pipa PVC tipe AW Dia 6 " 1 Ljr 300,500.00
7 M350 Pipa PVC tipe AW Dia 2 " 1 Ljr 75,000.00
8 M351 Pipa PVC tipe D Dia 4 " 1 Ljr 163,067.13
9 M360 Shock PVC Dia 1/2 " 1 bh 1,545.31
10 M361 Shock PVC Dia 3/4 " 1 bh 2,328.75
11 M362 Shock PVC Dia 1 " 1 bh 3,090.63
12 M363 Shock PVC Dia 1 1/4 " 1 bh 5,031.25
13 M364 Shock PVC Dia 2 " 1 bh 6,892.81
14 M365 Shock PVC Dia 2.5 " 1 bh 12,362.50
15 M366 Shock PVC Dia 3 " 1 bh 13,907.81
16 M367 Tee PVC Dia 1 1/4 " 1 bh 6,000.00
17 M368 Knee PVC Dia 1/2 " 1 bh 2,163.44
18 M369 Knee PVC Dia 3/4 " 1 bh 2,637.81
19 M370 Knee PVC Dia 1 " 1 bh 3,586.56
20 M371 Knee PVC Dia 1 1.4 " 1 bh 8,035.63
21 M372 Knee PVC Dia 2 " 1 bh 12,053.44
22 M373 Knee PVC Dia 2.5 " 1 bh 13,907.81
23 M374 Knee PVC Dia 3 " 1 bh 15,453.13
24 M375 Knee PVC Dia 4 " 1 bh 19,470.94
25 M376 Pipa Galvanis Dia 1/2 " 1 Ljr 103,140.63
26 M377 Pipa Galvanis Dia 3/4 " 1 Ljr 153,165.63
27 M378 Pipa Galvanis Dia 1" 1 Ljr 180,000.00
28 M379 Pipa Galvanis Dia 1.5 " 1 Ljr 280,000.00
29 M380 Pipa Galvanis Dia 2 " 1 Ljr 380,000.00
30 M381 Pipa Galvanis Dia 2.5 " 1 Ljr 602,000.00
31 M382 Pipa Galvanis Dia 3 " 1 Ljr 790,000.00
32 M383 Pipa Galvanis Dia 4 " 1 Ljr 1,147,000.00
33 M384 Shock Galvanis Dia 1/2 " 1 bh 3,399.69
34 M385 Shock Galvanis Dia 3/4 " 1 bh 5,563.13
35 M386 Shock Galvanis Dia 1 " 1 bh 6,984.81
36 M387 Shock Galvanis Dia 1.5 " 1 bh 13,907.81
37 M388 Shock Galvanis Dia 2 " 1 bh 22,994.25
38 M389 Shock Galvanis Dia 2.5 " 1 bh 27,815.63
39 M390 Shock Galvanis Dia 3 " 1 bh 31,524.38
40 M391 Shock Galvanis Dia 4 " 1 bh 38,323.75
41 M392 Knee Galvanis Dia 1/2 " 1 bh 4,945.00
42 M393 Knee Galvanis Dia 3/4 " 1 bh 6,490.31
43 M394 Knee Galvanis Dia 1 " 1 bh 9,271.88
44 M395 Knee Galvanis Dia 1.5 " 1 bh 18,234.69
45 M396 Knee Galvanis Dia 2 " 1 bh 27,197.50
46 M397 Knee Galvanis Dia 2.5 " 1 bh 31,524.38
47 M398 Knee Galvanis Dia 3 " 1 bh 35,851.25
48 M399 Knee Galvanis Dia 4 " 1 bh 44,814.06
49 M400 Pipa Screen PVC tipe AW Dia 6 " 1 ljr 687,843.75
XIII PLITUR & CAT
1 M401 Kertas Gosok 1 Lbr 3,000.00
2 M402 Plamir Kayu 1 kg 25,500.00
3 M403 Plamir Tembok 1 kg 8,925.00
4 M404 Plamir Besi 1 Kg 25,612.50
5 M405 Dempul Jadi 1 kg 29,325.00
6 M406 Minyak Cat 1 Ltr 15,711.88
7 M407 Spiritus 1 Ltr 10,062.50
8 M408 Sirlak 1 kg 140,731.25
9 M409 Cat meni kayu 1 kg 20,340.63
10 M410 Cat Catylac 1 kg 19,000.00
11 M411 Cat Dasar Kayu 1 kg 29,037.50
12 M412 Cat Dasar Tembok 1 kg 18,000.00
13 M413 Cat Dasar Besi 1 kg 33,062.50
14 M414 Cat Kayu sekualitas Avian 1 kg 16,875.00
15 M415 Cat Tembok WaterShieild " DULUX" 1 kg 96,800.00
16 M416 Cat Besi 1 kg 48,875.00
17 M417 Cat Genting 1 kg 36,800.00
18 M418 Waterproofing 1 kg 180,000.00
19 M419 Vernis 1 ltr 29,325.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

20 M420 Politur Jadi 1 ltr 65,000.00


21 M421 Kuas 1 bh 11,212.50
22 M422 Lem Kayu 1 Ltr 20,437.50
23 M423 Lem Pipa PVC 1 kg 29,325.00
24 M424 Lem vinyl 1 kg 51,318.75
XIV PERALATAN AIR BERSIH
1 M431 Tandon Air PVC V = 0.5 m3 1 bh 639,687.50
2 M432 Tandon Air PVC V = 1.0 m3 1 bh 1,087,468.75
3 M433 Tandon Air Stainless V = 0.5 m3 1 bh 1,599,218.75
4 M434 Tandon Air Stainless V = 1.0 m3 1 bh 2,558,750.00
5 M435 Sumur Pompa Tangan Lengkap 1 Unit 172,500.00
6 M436 Pompa Air 1 Unit 767,625.00
XV INSTALASI LISTRIK
1 M437 Kabel NYA 2 x 2.5 mm 1 m1 7,500.00
2 M438 Kabel NYA 4.0 mm 1 m1 22,000.00
3 M439 Stop Kontak ex. Brocco 1 bh 27,500.00
4 M440 Saklar tunggal ex. Brocco Type Gracio 1 bh 21,500.00
5 M441 Las doof 1 bh 7,500.00
6 M442 Isolator 1 m1 750.00
7 M443 T dos PVC 1 bh 2,500.00
8 M444 Pipa PVC 5/8" 1 Ljr 7,187.50
9 M445 Fiting Flafond 1 bh 9,271.88
10 M446 Zekering Kast Lokal 1 Group 1 Unit 8,500.00
11 M447 Zekering Kast Lokal 2 Group 1 Unit 12,500.00
12 M448 Zekering Kast Lokal 3 Group 1 Unit 23,500.00
13 M449 Lampu TL Komplit 20 Watt 1 bh 63,250.00
14 M450 Lampu TL Komplit 40 Watt 1 bh 94,300.00
15 M451 Lampu XL 5 Watt 1 bh 28,390.63
16 M452 Lampu XL 8 Watt 1 bh 28,390.63
17 M453 Lampu XL 14 Watt 1 bh 31,481.25
18 M454 Lampu XL 18 Watt 1 bh 34,571.88
19 M455 Lampu XL 23 Watt 1 bh 35,808.13
20 M456 Lampu Pijar 5 - 40 Watt 1 bh 18,543.75
21 M457 Lampu Pijar 50 - 100 Watt 1 bh 30,906.25
22 M460 Pipa Arde 1 m' 107,956.25
XVI LAIN - LAIN
1 M466 Ijuk 1 kg 27,500.00
2 M473 Elektroda 1 kg 20,125.00
3 M474 Minyak bekisting 1 ltr 3,162.50
4 M481 Seal Tape / TBA 1 bh 13,397.50
5 M482 Bensin 1 ltr 5,175.00
6 M483 Solar 1 ltr 4,945.00
7 M484 Minyak Pelumas 1 ltr 36,656.25
8 M485 Grease 1 kg 12,650.00
9 M486 Peralatan Hammer Injection 1 m 5,000.00
10 M487 Sewa Kompresor 1 hr 2,530,000.00
11 M488 Sewa Genset 1 hr 948,750.00
12 M489 Sewa Pompa Tes 1 hr 4,427,500.00
13 M490 Sewa Mesin las 1 hr 158,125.00
14 M502 Jendela Alumunium Putih sekualitas YKK 1 m1 65,656.25
15 M503 Jendela Alumunium Coklat sekualitas YKK 1 m1 65,375.00
16 M512 Splits Dia 1 " 1 bh 75,900.00
17 M513 Timah 1 kg 430,100.00
18 M514 Kawat BC 1 m1 44,275.00
19 M515 Klemp 1 bh 1,897.50
20 M516 Seng plat BJLS 24 (90 x 180) cm 1 lbr 63,250.00
21 M517 Metal furing channel RG3, C Channel RG1,Channel Clamp K26,U clamp K4-TB.C 1 m2 33,000.00
22 M518 Keramik 60 x 60 esenza 1 m2 160,000.00
23 M519 Keramik KM 30 x 30 1 m2 40,000.00
24 M520 Kloset duduk/monoblock sekualitas TOTO Type Avante CW 823 J 1 unit 5,170,000.00
25 M521 Kran Air sekualitas TOTO 1 bh 150,000.00
25 M522 Keramik abu - abu 60 x 60 1 m2 160,000.00
27 M523 Lampu TL 2 x 25 Watt Inbow type RM sekualitas saka + saklar brc 1 unit 240,000.00
28 M524 Lampu TL 50 Watt Inbow type RM sekualitas saka + saklar brc 1 unit 162,500.00
29 M525 Lampu TL 50 Watt Outbow type RM sekualitas saka + saklar brc 1 unit 79,500.00
30 M526 Down light 25 VA Inbow 4" 1 unit 45,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

31 M527 Lampu Taman 1 Unit 50,000.00


32 M528 Lampu Spot Light 1 unit 700,000.00
33 M529 SL 25 VA 1 unit 29,000.00
34 M530 Down light 25 VA inbow 6" 1 unit 45,000.00
35 M531 Pipa GI 21/2" 1 ljr 274,000.00
36 M532 Pipa GI 1" 1 ljr 79,500.00
37 M533 Down light 20 W 1 unit 45,000.00
39 M534 Pipa GI 11/2 " 1 ljr 120,000.00
40 M535 Alumunium 1 lbr 80,000.00
41 M536 Pipa GI 1 1/4 " 1 ljr 225,500.00
42 M537 Pipa GI 1/2 " 1 ljr 70,000.00
43 M538 Plat besi 1 cm 1 m2 225,000.00
44 M539 Kawat las 1 kg 10,000.00
45 M540 Pengelasan 1 cm 1,150.00
46 M541 Besi Polos 12 1 kg 9,775.00
47 M542 Besi polos 14 1 kg 9,775.00
48 M543 Besi Ulir 16 1 kg 10,350.00
49 M544 Besi Ulir 19 1 kg 10,350.00
50 M545 Besi Ulir 22 1 kg 10,350.00
51 M546 Besi Polos 10 1 kg 9,775.00
52 M547 Besi Polos 16 1 kg 9,775.00
53 M548 Besi Polos 19 1 kg 9,775.00
54 M549 Keramik 50 x 50 sekualitas Roman 1 m2 84,960.00
55 M550 Cat Tembok Catylax 1 kg 18,000.00
56 M551 Keramik 33. x 33.1 Toilet Sekualitas Ezensa 1 m2 240,000.00
57 M552 Rel Jendela 1 bh 10,000.00
58 M553 Keramik 30 x 30 sekualitas Roman 1 m2 54,960.00
59 M554 Besi polos 8 1 kg 9,775.00
60 M555 Besi Ulir 25 1 kg 10,350.00
61 M556 Sealent 1 bh 40,000.00
62 M557 Reiling steinless tangga 1 m2 550,000.00
63 M558 Reiling void 1 m2 465,000.00
64 M559 List keramik 1 m' 45,000.00
65 M560 Seng Gelombang 240 x 80 x 0.20 cm sekualitas elephant 1 lbr 46,500.00
66 M561 Keramik 25 x 46 sekualitas Ezensa 1 m2 250,000.00
67 M562 Keramik 40 x 40 sekualitas Ezensa 1 m2 270,000.00
68 M563 Keramik 60 x 60 sekualitas Esenza 1 m2 300,000.00
69 M564 Granite Tile 60 x 60 cm 1 m2 190,000.00
70 M565 Gerbil beton 1 bh 18,000.00
71 M566 Batu andesit hitam susun sirih kasar 3 x 30 cm ( rata alam ) 1 m2 95,450.00
72 M567 Coating batu alam ex. Propan 1 ltr 51,750.00
73 M568 Batu beton sisir 1 m2 35,000.00
74 M569 Kabel NYM 3 x 2.5 1 m1 7,500.00
75 M570 Pipa PVC tipe AW Dia 5 " 1 ljr 275,000.00
76 M571 Pipa GI 4 " 1 ljr 350,000.00
77 M572 Saklar Tunggal MK 1 bh 15,000.00
78 M573 Saklar Ganda MK 1 bh 17,500.00
79 M574 Stepnosing sekualitas roman 10 x 33 1 bh 6,500.00
80 M575 Keramik 40 x 40 Sekualitas Roman 1 m2 64,000.00
81 M576 Shower komplit sekualitas TOTO seri TX433SJ 1 Unit 1,100,000.00
82 M577 Akrilik bening t = 4 mm 1 m2 45,000.00
83 M578 Gate valves 2 " sekualitas TOYO 1 bh 439,000.00
84 M579 Gate vaves 1 1/4 " sekualitas TOYO 1 bh 308,000.00
85 M580 Pompa Groundfos CH8-50 1 unit 5,000,000.00
86 M581 Isolator pipa air panas 1 m' 20,000.00
87 M582 Bata klinker 1 m2 65,000.00
88 M583 Stop Kran sekualitas TOTO 1 bh 150,000.00
89 M584 Bedet Shower sekualitas TOTO 1 bh 150,000.00
90 M585 Box Lemari Panel 1 unit 6,000,000.00
91 M586 Lampu indikator 3 warna + Fuse Hitam 1 set 19,000.00
92 M587 Volt meter + volt selector 1 set 120,000.00
93 M588 Ampere meter 400A + CT 400/5 1 unit 130,000.00
94 M589 Bus bar 1 lot 1,500,000.00
95 M590 Arester 3 fasa STH 3 + N 65kA 1 unit 1,940,000.00
96 M591 MCCB 4 x 125 A 1 unit 1,050,000.00
97 M592 MCCB 3 x 6 A 1 unit 95,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

98 M593 MCCB 3 x 10 A 1 unit 95,000.00


99 M594 MCCB 3 x 25 A 1 unit 265,000.00
100 M595 MCCB 3 x 40 A 1 unit 369,000.00
101 M596 MCCB 3 x 50 A 1 unit 369,000.00
102 M597 Grounding panel dengan BC 50 mm2 1 set 600,000.00
103 M598 Grounding arester dengan BC 50 mm2 1 set 600,000.00
104 M599 Asesories dan wiring panel 1 lot 900,000.00
105 M600 Panel Box 30x40x15 1 unit 123,000.00
106 M601 Lampu indikator 3 warna + fuse hitam 1 unit 15,000.00
107 M602 Volt meter + volt selector 1 set 120,000.00
108 M603 Ampere meter + CT 1 unit 130,000.00
109 M604 Bus bar Sisir 1 lot 100,000.00
110 M605 Arester 3 fasa STD 3+N 1 unit 895,000.00
111 M606 MCB 1 x 4 A 1 unit 38,000.00
112 M607 MCB 1 x 6 A 2 unit 38,000.00
113 M608 MCB 3 x 6 A 1 unit 95,000.00
114 M609 Grounding panel dengan BC 10 mm2 1 mtr 12,000.00
115 M610 Grounding arester dengan BC 10 mm2 1 mtr 12,000.00
116 M611 Asesories dan wiring panel 1 set 450,000.00
117 M612 Kabel Power NYY 4 x 2,5 mm2 1 mtr 14,000.00
118 M613 Panel Box 1 unit 300,000.00
119 M614 Lampu indikator 3 warna+fuse hitam 1 set 19,000.00
120 M615 Volt meter + volt selector 1 set 120,000.00
121 M616 Ampere meter + CT 1 unit 130,000.00
122 M617 Bus bar sisir 1 lot 100,000.00
123 M618 Arester 3 fasa STD 3+N 1 unit 895,000.00
124 M619 MCB 1 x 6 A 1 unit 38,000.00
125 M620 MCB 1 x 10 A 1 unit 38,000.00
126 M621 MCB 1 x 16 A 1 unit 58,000.00
127 M622 MCCB 3 x 50 A 1 unit 369,000.00
128 M623 busbar 3x20 1 lot 200,000.00
129 M624 Grounding panel dengan BC 16 mm2 1 mtr 17,000.00
130 M625 Grounding arester dengan BC 16 mm2 1 mtr 17,000.00
131 M626 Asesories dan wiring panel 1 set 450,000.00
132 M627 Kabel Power NYY 4 x 10 mm2 1 mtr 48,000.00
133 M628 Indoor Hydrant Box Type A2 c/w Glass 1 unit 3,851,400.00
134 M638 Terminal Box for 2 Module 1 unit 752,300.00
135 M639 Back Up Power / UPS ( 24 V DC, 10 AH) 1 unit 1,500,000.00
136 M640 MCB 3 x 10 A 1 unit 95,000.00
137 M641 NYFgBy 4 x 50 mm2 1 m 400,000.00
138 M642 Granit black pearl Meja Wastafel/meja TPT/dinding TPT 1 m2 650,000.00
139 M646 Kran air panas + air dingin diameter 1/2" sekualitas TOTO 1 bh 400,000.00
140 M653 Saklar Hotel 1 bh 40,000.00
141 M654 Kabel NYA 3 x 2.5 1 m1 5,200.00
142 M655 Tiang Pancang 25x25 cm 1 m1 120,000.00
143 M656 Kalsiboard t = 9 mm sekualitas Jayaboard 1 m2 110,000.00
144 M657 Kabel NYY 4 x 6 sekualitas supreme 1 m1 34,500.00
145 M658 Rangka Hollow 4/4 1 ljr 115,000.00
146 M659 Partikel t = 12 mm 1 m2 65,000.00
147 M660 Megateak t = 3 mm 1 m2 89,250.00
148 M661 Wallpaper 1 m2 60,000.00
149 M662 Engsel Pivot 1 bh 110,000.00
150 M663 Rangka Baja siku 1 m2 350,000.00
151 M664 Akustik board t = 9 mm sekualitas Jayaboard 1 m2 95,000.00
152 M665 GRC board t = 9 mm sekualitas Jayaboard 1 m2 150,000.00
153 M666 List kayu jati 2/10 profil 1 m' 24,150.00
154 M667 List kayu jati 2/20 profil 1 m' 55,000.00
155 M668 List kayu kamper 2/5 1 m' 5,000.00
156 M669 Karet ramp 1 m2 45,000.00
157 M670 Papan (1,5x15) cm 1 m3 8,525,000.00
158 M671 Pintu DBS pvc PVC door + kusen AKBS komplit ( kusen + slimar aluminium ) 1 unit 825,000.00
159 M672 Border 4 x 46 cm sekualitas Ezensa 1 bh 17,500.00
160 M673 Border 6.5 x 25 cm sekualitas Ezensa 1 bh 19,000.00
161 M674 Penyekat sekualitas TOTO 1 m2 65,000.00
162 M675 Slimar aluminium 1 m1 95,000.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

163 M676 Palimanan 40 x 40 cm 1 m2 85,000.00


164 M677 Batu sebar hijau dan putih 1 m2 25,875.00

165 M678 Batu ampyang 1 m2 27,500.00


166 M679 Granite Tile 40 x 40 cm 1 m2 308,000.00
167 M680 Kawat Ayam 1 m2 46,000.00
168 M681 Batu paras Jogja 15 x 30 cm rata alam 1 m2 66,125.00
169 M682 Batu paras Jogja 15 x 30 cm pecah 1 m2 67,275.00
170 M682 Batu palimanan 20 x 40 cm 1 m2 68,400.00
171 M683 Batu palimanan 15 x 30 cm 1 m2 65,550.00
172 M684 Batu palimanan pola acak rata mesin 1 m2 65,550.00
173 M685 Batu andesit hitam susun sirih kasar 20 x 20 ( rata mesin ) 1 m2 110,400.00
174 M686 Bubungan genteng samping sekualitas Abadi 1 bh 3,250.00
175 M687 List aluminium 1 m1 15,500.00
176 M688 List kaca 1 m1 5,000.00
177 M689 Pintu Kaca tampered sliding komplit ( sliding door otomatis/sensor ) 1 Unit 31,900,000.00
178 M690 Engsel pintu utama sekualitas DEKSON ( 1 psng 2 bh ) 1 psng 526,500.00
179 M691 Kunci Tanam sekualitas Dekson 1 bh 515,200.00
180 M692 Handel Pintu Dekson stanless l = 60 cm 1 psng 517,500.00
181 M693 Kaca Rayben 20 % tebal 10 mm 1 m2 258,600.00
182 M694 List kayu kamper 5/5 profil 1 m' 29,750.00
183 M695 Engsel kaca sekualitas SOLID ( 1 psng 2 bh ) 1 psng 105,500.00
184 M696 Handel pintu lemari Dekson stanless l = 20 cm 1 psng 126,500.00
185 M697 Sewa Excavator 1 hr 959,298.61
186 M698 Sewa Whell Loader 1 hr 1,215,817.10
187 M699 Sewa Motor Grader 1 hr 1,429,558.09
188 M700 Sewa Vibro Roller 1 hr 991,751.04
189 M701 Sewa Water Tanker 1 hr 637,783.46
190 M702 Paving K 400, t = 8 cm 1 m2 48,300.00
191 M703 Kansteen uk. 15 x 40 x 50 cm 1 bh 48,301.00
192 M704 Saklar ganda ex. Brocco Type Gracio 1 bh 17,500.00
193 M705 Saklar tunggal ex. Clipsal 1 bh 10,800.00
194 M706 Saklar ganda ex. Clipsal 1 bh 15,600.00
195 M707 Stop kontak ex. Clipsal 1 bh 18,000.00
196 M708 Aluminium plat t = 3 mm 1 m1 45,000.00
197 M709 Aluminium 5/7 cm 1 m1 65,000.00
198 M710 AC 2 split PK SHARP AH-A18KCY-Sayonara 3 series Anti Bacterial, 1540 W 1 unit 8,131,650.00
199 M711 AC 1 split PK SHARP AH-A12KHL-Sayonara 3 series Anti Bacterial, 970 W 1 unit 5,923,650.00
200 M712 AC split ceiling 2 PK 1 unit 16,263,300.00
201 M713 AC split ceiling 3 PK TOSHOBA VitaPlasma RS27MKPX 1 unit 18,227,500.00
202 M714 AC cassette ceiling 2 PK LG/PANASONIC 1 unit 3,500,000.00
203 M715 AHU 380-415 V/3PH/50HZ sekualitas ACSON ( VEDC)/ AC Central 10 PK McQuay 1 unit 28,750,000.00
204 M716 Exhoust Fan ex. PANASONIC FV20EGU1, 18 Watt 1 unit 235,750.00
205 M717 Rumput gajah mini 1 m2 20,500.00
206 M718 Flamboyan ( t = 2 m ) 1 pohon 208,450.00
207 M719 Palem merah ( t = 2 m) 1 batang 357,600.00
208 M720 Palem putri ( t = 1.5 m ) 1 batang 199,410.00
209 M721 Lili paris ( t = 0.3 m ) 1 batang 4,800.00
210 M722 Irish ( 0.5 m2 = 20 polybag ) 1 olybag 5,750.00
211 M723 Soka Ixora Javanice ( t = 0.25 m ) 1 pohon 10,626.00
212 M724 Lidah mertua ( t= 0.3 m - 0.5 m ) 1 pot 26,400.00
213 M725 Bougenville ( t = 1.5 m ) 1 pohon 165,000.00
214 M726 MDP/LVMDP/panel box 1 unit 15,000,000.00
215 M727 Lampu HPI-T 250 watt tunggal ( tiang + armatur RL ARTO A2 HPL-N + lampu sekualita1 unit 6,020,024.60
216 M728 Lampu HPI-T 250 watt ganda( tiang + armatur RL ARTO A2 HPL-N + lampu sekualitas 1 unit 8,877,549.20
217 M729 Lampu sport par AMAR E40 HPI-T 400 watt ex. Phillips ( armatur artolite + lampu phi 1 unit 2,239,270.00
218 M730 Lampu tanam lengkap SL 11 watt sekualitas phillips 1 unit 45,000.00
219 M731 Saklar CAM ex. Clipsal 1 bh 15,600.00
220 M732 Kabel feeder 1 m1 850,000.00
221 M733 Partikel t = 9 mm 1 m2 48,300.00
222 M734 Border chrome 2/6 cm ( stainless steel ) 1 m1 45,000.00
223 M735 Border chrome 2 cm ( stainless steel ) 1 m1 25,000.00
224 M736 Metal furring channel RG3, C channel RG1, channel clamp K 26, 1 m1 23,100.00
U clamp K4-TB.C, rod M5, wall angle LG 2222
225 M737 Boder chrome 2 cm ( list tempel )
226 M738 Kaca oneway tebal 8 mm ex. Asahi mas 1 m2 310,500.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

227 M739 Aluminium komposit JLS-8129 Silver brushed 1 m2 660,000.00


228 M740 Baja siku 60x60x4 1 m1 27,500.00
229 M741 Akrilik bening t = 2 mm 1 lbr 207,000.00
230 M742 Akrilik bening t = 5 mm 1 lbr 701,500.00

231 M743 Akrilik bening t = 10 mm 1 x 2 cm 1 lbr 943,000.00


232 M744 Kuda-kuda baja WF.100.100 1 kg 11,500.00
233 M745 Gording canal C 125.50.20 1 kg 10,600.00
234 M746 Trekstang 12 cm 1 kg 9,775.00
235 M747 Polycarbonate 2.1 x 11 ( twinlite ) 1 lbr 1,840,000.00
236 M748 Kait tarik 1 bh 5,500.00
237 M749 Drat pengunci trekstang 1 bh 15,500.00
238 M750 Pompa hydrant 1 unit 47,150,000.00
239 M751 Pompa kap 40 lpm head 30 m ( groundfos 1 pk ) 1 unit 4,025,000.00
240 M752 Tandon air stainless steel 1000 ltr ex. Maspion 1 unit 2,817,500.00
241 M753 Head Sprinkle 1 bh 402,500.00
242 M754 Panel induk 1 unit 15,000,000.00
243 M755 Sub Panel lantai 1 (PHB-1) 1 unit 10,000,000.00
244 M756 Sub Panel genset lantai 1 1 unit 13,700,000.00
245 M757 Pas Kabel Feeder NYY 4 x (1x150) mm2 (kWh ke LV-MDP) 1 m' 650,000.00
246 M758 Pas Kabel Feeder NYY 4 x (1x150) mm2 (Genset ke LV-MDP) 1 m' 650,000.00
247 M759 Pas Kabel Feeder NYY 4 x 50 mm2 (LV-MDP ke PP-1) 1 m' 300,000.00
248 M760 Pas Kabel Feeder NYY 4 x 25 mm2 (LV-MDP ke PP-2) 1 m' 250,000.00
249 M761 Panel AC 1 unit 10,000,000.00
250 M762 Kabel power ( NYY 3 x 2.5 mm ) 1 m1 40,250.00
251 M763 Swicth HUB 1 unit 1,200,000.00
252 M764 DVR 16 ch + DVD-RW 1 unit 12,075,000.00
253 M765 Camera dome rotated CCD 1 unit 1,725,000.00
254 M766 Camera square CCD 1 unit 1,150,000.00
255 M767 Camera rotated CCD outdoor 1 unit 2,875,000.00
256 M768 Komputer pantau ( pos satpam ) 1 set 8,625,000.00
257 M769 Monitor 15 " luar ( pos satpam ) 1 unit 1,265,000.00
258 M770 Kabel jaringan CCTV ( NYY 3 x 2.5 mm ) 1 m1 40,250.00
259 M771 Mine control fire alarm ( box panel alarm ) 1 unit 750,000.00
260 M772 Rate or rise head detector 1 unit 350,000.00
261 M773 Smoke detector 1 unit 400,000.00
262 M774 Manual break glass 1 unit 350,000.00
263 M775 Alarm bell 1 unit 350,000.00
264 M776 Fire extingusher 3 kg 1 bh 850,000.00
265 M777 Alarm lampu 1 unit 750,000.00
266 M778 Kabel jaringan fire alarm ( NYY 3 x 2.5 mm ) 1 m1 40,250.00
267 M779 Box kontrol 1 unit 500,000.00
268 M780 Ceilling speaker ( spiker plafound ) 1 unit 450,000.00
269 M781 Wall speaker / spiker dinding 1 unit 500,000.00
270 M782 Volume control 1 unit 400,000.00
271 M783 PABX / Box kontrol 1 unit 400,000.00
272 M784 Outlet telepon 1 unit 250,000.00
273 M785 Kabel jaringan telepon 1 m1 14,400.00
274 M786 Swicth HUB 1 unit 1,500,000.00
275 M787 Komputer server 1 unit 8,625,000.00
276 M788 Komputer reuter 1 unit 8,625,000.00
277 M789 Lan port 1 unit 350,000.00
278 M790 Modem 1 unit 780,000.00
279 M791 Kiosk mesin APl type L, 17 " LCD, core duo 1,8 GHz, 16 BSODIMM, 120 GB HDD s 1 unit 28,750,000.00
280 M792 Runing teks LCD 0.17 x 7.2 m 1 unit 9,600,000.00
281 M793 LED Samsung 40" ( ruang lobby dan TPT ) 1 unit 34,500,000.00
282 M794 Lampu sorot utk. Logo dan tulisan di TPT 1 unit 350,000.00
283 M795 Emergency 40 watt 1 unit 550,000.00
284 M796 Ducting exhaust 1 m1 237,000.00
285 M797 Besi siku 30.30.3 1 kg 9,775.00
286 M798 Ducting AC 1 m1 402,500.00
287 M799 Electric remote control Apollo ERS-200 ( ruang rapat ) 1 unit 13,800,000.00
288 M800 LED Samsung 40" ( ruang rapat ) 1 unit 34,500,000.00
289 M801 Lampu tempel/dinding bulat ( ruang rapat ) 1 set 150,000.00
290 M802 Lampu tempel/dinding bulat panjang ( ruang rapat ) 1 set 250,000.00
291 M803 Lampu tempel/dinding kerucut ( ruang rapat ) 1 set 300,000.00
292 M804 Lampu gantung ( ruang rapat ) 1 set 12,500,000.00
293 M805 LV-MDP + capasitor bank 100 Kvar + Grounding 1 unit 154,770,000.00
294 M806 Down light 25 Watt Inbow komplit 4" ( armatur ) ex. Phillips ( armatur artolite + lampu 1 unit 270,000.00
295 M807 Lampu RM 300 GLOSS 2 x 18 Watt ALML (M1) sekualitas ( armatur artolite + lampu p 1 unit 519,960.00
296 M808 Lampu RM 300 GLOSS 2 x 36 Watt ALML (M1) sekualitas Phillips ( armatur artolite + 1 unit 882,735.00
NO. KODE BAHAN BANGUNAN SATUAN HARGA

297 M809 Lampu BL TG 1 x 36 Watt TL-D sekualitas Phillips ( armatur artolite + lampu phillips 1 unit 284,550.00
298 M810 Lampu plafound SCCB 20 ACR E27, 25 watt sekualitas Phillips ( armatur artolite + la 1 unit 215,250.00
299 M811 DO Halogen AMAC SON E27 50 watt sekulitas Phillips ( armatur artolite + lampu phil 1 unit 1,655,280.00
300 M812 Lampu sport AMAC MHN-TD E27 70 watt sekualitas Phillips ( armatur artolite + lampu 1 unit 1,715,780.00
301 M813 kamprotan ( semprot, racikan pabrik ) 1 m2 78,750.00
302 M814 Lampu kristal ( gantung ) 1 unit 25,000,000.00
303 M815 Logo KPP stainless 1 unit 750,000.00

304 M816 Tulisan stainless 1 bh 195,000.00


305 M817 Lampu BL TG 1 x 18 Watt TL-D sekualitas Phillips ( armatur artolite + lampu phillips 1 unit 243,705.00
306 M818 Lampu taman lengkap PL BD 833 E27 23 watt ( armatur artolite + lampu phillips ) 1 unit 1,121,820.00
307 M819 Lampu sorot halogen AMAR E40 HPI-T 300 watt ex. Phillips ( armatur artolite + lampu 1 unit 2,228,270.00
308 M820 Pasang titik instalasi telephone dan soket 1 bh 225,000.00
309 M821 Kuda-kuda baja ringan komplit sekualitas smatrass 1 m2 230,000.00
310 M822 Tulisan stainless kecil 1 bh 75,000.00
311 M823 Tulisan stainless besar 1 bh 115,000.00
312 M824 Sewa Mesin Stamper 1 hr 350,000.00
313 M825 Sewa Alat Pondasi Strouss 1 hr 175,000.00
314 M826 Batu Candi 1 m2 126,500.00
315 M829 Lampu TL 2 x 40 Watt Inbow type RM sekualitas saka + saklar brc 1 unit 345,000.00
316 M830 Saklar Ganda 1 bh 23,500.00
317 M831 Vernis Batu Alam 1 ltr 48,500.00
319 M832 Usuk dan reng baja ringan 1 m2 110,000.00
320 M833 Genteng Keramik Ex. Kamuri 1 bh 5,900.00
321 M834 Bubungan genteng keramik Ex. Kamuri 1 bh 12,500.00
322 M835 Woodplank 2/30 1 Ljr 32,000.00
323 M836 Grendel pintu tanam 1 unit 83,500.00
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMASANGAN WASTAFEL RS BHAYANGKARA LUMAJANG 2017
LOKASI : JL. KYAI ILYAS NO 7 LUMAJANG

HARGA
NO URAIAN PEKERJAAN VOLUME JUMLAH
SATUAN
LANTAI 1
I PEKERJAAN PERSIAPAN DAN PENDAHULUAN
1 Pagar Sementara Dari Seng Gelombang Tinggi 2 m - m1 218,937.00 -
2 Pembuatan Direksi Kit, gudang semen dan alat-alat - m2 1,381,050.00 -
3 Pembersihan Lokasi dan Perataan - m2 11,250.00 -
4 Pengukuran - m1 83,915.00 -
5 Bongkar pas. Dinding - m3 250,000.00 -
6 Bongkar plafon - m2 19,930.00 -
7 Bongkar tanah/taman - m3 81,250.00 -
8 Bongkar Atap - m2 50,000.00 -
9 Bongkar Kusen - m2 24,850.00 -
10 Bongkar beton - m3 494,995.00 -
11 Bongkar Pondasi Depan - m3 494,995.00 -
12 Buang bongkaran - m3 94,475.00 -
Sub Total -
II PEKERJAAN TANAH DAN GALIAN
1 Galian Tanah Pondasi Batu Kali - m3 58,200.00 -
2 Galian Tanah Pondasi Foot Plate - m3 55,240.00 -
3 Galian Tanah Pondasi Struoss - m1 57,655.00 -
4 Urugan Kembali Tanah Galian Pondasi - m3 15,055.00 -
5 Pemadatan Tanah - m2 23,000.00 -
6 Urugan Pasir Dibawah Pondasi - m3 90,850.00 -
7 Urugan Tanah Peninggian Peil Lantai - m3 92,875.00 -
Sub total -
III PEKERJAAN PONDASI DAN PASANGAN
1 Aanstamping - m3 236,985.00 -
2 Pasangan Pondasi batu kali - m3 475,489.00 -
3 Pasangan Bata merah - m2 93,873.00 -
4 Patelahan Lantai - m2 64,323.00 -
5 Plesteran - m2 52,414.50 -
6 Benangan - m1 19,822.00 -
7 Lantai Kerja Pondasi Foot Plate t=5 cm - m3 564,442.50 -
Sub total -
IV PEKERJAAN BETON
1 Pondasi foot plate 100x100 - m3 3,812,840.00 -
2 Kolom Struktur 30/30 - m3 3,634,700.00 -
3 Kolom Praktis 15/20 - m3 3,634,700.00 -
4 Sloof 15/25 - m3 3,477,077.50 -
5 Balok struktur 20/35 - m3 4,698,356.40 -
6 Balok latei 15/20 - m3 4,558,351.40 -
7 Plat lantai t = 12 cm - m3 4,551,005.20 -
8 Ring Balk 15/20 - m3 2,774,770.00 -
9 Tangga Beton t=11 cm - m3 4,258,460.00 -
10 Rhepel Beton t=8 cm - m3 4,131,005.20 -
Sub total -
V PEKERJAAN KUSEN, PINTU DAN JENDELA
1 Pasang Kusen Aluminium sekualitas - m1 156,692.00 -
2 Pasang Jendela Kaca Rangka Aluminium - bh 546,716.88 -
3 Pasang Pintu Lapis HPL - bh 1,746,253.51 -
4 Pasang Kaca Polos 5 mm - m2 151,063.75 -
5 Pasang Engsel Pintu - set 99,813.75 -
6 Grendel Tanam Pintu - set 92,542.50 -
7 Pasang Kunci Tanam Pintu - set 164,425.00 -
8 Pasang Pegangan Pintu - set 170,212.50 -
9 Pasang Door closer - set 192,556.25 -
10 Pasang Engsel Jendela - set 66,542.50 -
11 Pasang Grendel Jendela - set 30,542.50 -
12 Pasang Hak Angin Jendela - set 47,600.00 -
13 Pasang Pintu KM/WC - set 546,716.88 -
Sub total -
VI PEKERJAAN ATAP
1 Kuda-kuda Baja IWF 20 - kg 38,546.50 -
2 Gording Chanal C-125 - kg 38,546.50 -
3 Pasang Baut Angker Baja - kg 44,739.50 -
4 Usuk dan reng baja ringan. - m2 178,870.00 -
5 Trackstang 14 mm - kg 14,921.50 -
6 Pasang Genteng Beton - m2 94,445.00 -
7 Pasang Bubungan Genteng Beton - m1 142,344.00 -
8 Plendes - kg 28,916.04 -
9 Rangka Besi Double Siku 6 x 6 - m1 99,270.00 -
10 Pasang Rangka Dan Lisplank - m1 117,870.00 -
Sub total -
VII PEKERJAAN PLAFON
1 Pasang Rangka Metal furing Jarak 60x80 - m2 76,282.00 -
2 Pasang Plafon Gypsum board ( dalam ) - m2 35,273.00 -
3 Pasang List Gypsum - m1 28,726.88 -
Sub total -
VIII PEKERJAAN KERAMIK
1 Pasang Keramik Lantai 60x60 (warna terang) - m2 236,433.00 -
2 Pasang Keramik Teras 40x40 (Kasar) - m2 175,933.00 -
3 Pasang Plain Lantai 10x60 cm - m1 21,422.90 -
4 Pasang Keramik Dinding KM/WC 25/40 - m2 166,876.00 -
5 Pasang Keramik Lantai KM/WC 25/25 - m2 157,146.00 -
6 Pasang Keramik Dinding Dapur 25/40 - m2 157,146.00 -
7 Pasang Keramik carport 40x40 - m2 175,933.00 -
8 Pasang Keramik Tangga - m2 157,146.00 -
Sub total -
IX PEKERJAAN PLUMBING
1 Pasang Monoblok sek. Toto - bh 1,983,120.00 -
2 Pasang Urinoir Ex. Toto - bh 1,969,220.00 -
3 Pasang Wastafel 15.00 bh 605,976.60 9,089,649.00
4 Pasang Tempat sabun - bh 84,425.00 -
5 Pasang Pipa Air bersih dia 3/4 - m1 28,778.00 -
6 Pasang Pipa Air Kotor dia 2,5" - m1 65,811.00 -
7 Pasang Pipa Air Closed dia 4" - m1 86,936.00 -
8 Pasang Pipa Air Hujan dia 4" - m1 86,936.00 -
9 Pasang Pipa Air Kotor dia 1" 30.00 m1 50,178.50 1,505,355.00
10 Pasang Kran Air 3/4" - bh 67,221.19 -
11 Pasang Kran Wastafel 15.00 bh 174,759.94 2,621,399.06
12 Pasang Syphon Wastafel 15.00 bh 111,425.00 1,671,375.00
13 Pasang Kaca cermin - bh 169,949.38 -
Sub Total 14,887,778.06
X PEKERJAAN LISTRIK
1 Pasang Stop Kontak - bh 227,921.88 -
2 Pasang Instalasi AC - bh 227,921.88 -
3 Pasang Lampu SL 23wt + Saklar - bh 267,517.51 -
4 Pasang Box MCB - bh 750,000.00 -
5 Pasang Saklar Hotel - bh 227,921.88 -
Sub total -
XI PEKERJAAN PENGECATAN
1 Cat Dinding Eksterior Dulux Weathershield - m2 34,702.00 -
2 Cat Dinding Interior Sekualitas Catylac - m2 28,059.00 -
3 Cat Plafond sekualitas Catylac - m2 28,059.00 -
4 Cat Partisi - m2 34,702.00 -
5 Cat Kusen - m2 34,702.00 -
6 Waterproofing - m2 71,641.50 -
Sub total -

XII PEKERJAAN LAIN-LAIN


1 Partisi Rangka Kayu - m2 108,985.00 -
2 Penutup Partisi - bh 60,067.50 -
3 Pasang Lapisan Timbal - m2 75,000.00 -
4 Pembuatan Saluran Air - m1 358,062.50 -
Sub total -

TOTAL 14,887,778.06
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMASANGAN WASTAFEL RS BHAYANGKARA LUMAJANG 2017
LOKASI : JL. KYAI ILYAS NO 7 LUMAJANG

TOTAL BIAYA
NO URAIAN PEKERJAAN
(Rp.)
LANTAI 1
I PEKERJAAN PERSIAPAN DAN PENDAHULUAN -
II PEKERJAAN TANAH DAN GALIAN -
III PEKERJAAN PONDASI DAN PASANGAN -
IV PEKERJAAN BETON -
V PEKERJAAN KUSEN, PINTU DAN JENDELA -
VI PEKERJAAN ATAP -
VII PEKERJAAN PLAFON -
VIII PEKERJAAN KERAMIK -
IX PEKERJAAN PLUMBING 14,887,778.06
X PEKERJAAN LISTRIK -
XI PEKERJAAN PENGECATAN -
XII PEKERJAAN LAIN-LAIN -
JUMLAH 14,887,778.06
PPN 10 % 1,488,777.81

JUMLAH TOTAL 16,376,555.87

Malang, 8 Oktober 2017

M.AFIF ASYHARI,ST