REKAPITULASI RAB

REKAPITULASI RENCANA ANGGARAN BIAYA PEMBANGUNAN RUMAH TINGGAL TIPE 55/100


NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp.) PEMBULATAN

I. PEKERJAAN PERSIAPAN 16,993,093.20 16,994,000


II. PEKERJAAN TANAH 9,047,949.24 9,050,000
III. PEKERJAAN PONDASI DAN BETON BERTULANG 39,205,488.45 39,206,000
IV PEKERJAAN DINDING DAN PLESTERAN 21,493,368.53 21,490,000
V PEKERJAAN LANTAI 10,447,985.42 10,448,000
VI. PEKERJAAN ATAP 9,614,962.45 9,615,000
VII. PEKERJAAN LANGIT-LANGIT 9,078,799.02 9,079,000
VIII PEKERJAAN PLUMBING 4,955,848.54 4,956,000
IX PEKERJAAN PENGECATAN 10,509,089.16 10,510,000
X PEKERJAAN LISTRIK 9,154,396.79 9,155,000
XI PEKERJAAN SANITAIR 5,836,232.45 5,837,000
Jumlah 146,337,213.25
Dibulatkan 146,340,000.00
BAB 2

TABEL RENCANA ANGGARAN BIAYA RUMAH TIPE 55/100

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

I PEKERJAAN PERSIAPAN
1 Pekerjaan persiapan lahan (lokasi pekerjaan) 100 m2 Rp 157,742.00 Rp 15,774,200.00
2 Pekerjaan pengukuran dan pemasangan bouw plank 34 m1 Rp 46,969.80 Rp 1,596,973.20
JUMLAH Rp 16,993,093.20

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

II PEKERJAAN TANAH
1 Pekerjaan galian tanah untuk pondasi 52.5 m3 Rp 101,287.50 Rp 5,317,593.75
2 Pekerjaan urugan tanah kembali sisi pondasi 33.27125 m3 Rp 72,175.00 Rp 2,401,352.47
3 Pekerjaan urugan pasir di bawah pondasi 2.14375 m3 Rp 292,435.00 Rp 626,907.53
4 Pekerjaan urugan pasir dibawah lantai 2.40086 m3 Rp 292,435.00 Rp 702,095.49
JUMLAH Rp 9,047,949.24

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

III PEKERJAAN PONDASI DAN BETON


1 Pasangan pondasi batu kali 16.835 m3 Rp 1,447,667.30 Rp 24,371,479.00
2 Pekerjaan sloof beton 15/20 1.605 m3 Rp 2,587,987.85 Rp 4,153,720.50
3 Pekerjaan kolom beton 15/15 1.46025 m3 Rp 4,371,633.71 Rp 6,383,678.13
4 Pekerjaan beton ring balk 1.605 m3 Rp 120,261.69 Rp 193,020.01
5 Pekerjaan beton lantai kerja 2.40086 m3 Rp 1,709,217.04 Rp 4,103,590.82
JUMLAH Rp 39,205,488.45

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN


1 Pasangan dinding bata merah 1:5 136.01 m2 Rp 127,386.02 Rp 17,325,772.58
2 Pekerjaan plesteran 52.5 m3 Rp 79,382.78 Rp 4,167,595.95
3 Pekerjaan acian 52.5 m3 Rp 48,903.52 Rp 2,567,434.80
JUMLAH Rp 21,493,368.53

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

V PEKERJAAN LANTAI
1 Pasangan keramik 40 cm x 40 cm 46.8778 m2 Rp 163,830.52 Rp 7,680,014.35
2 Pasangan lantai keramik 20 cm x 20 cm 1.8225 m2 Rp 155,395.28 Rp 283,207.90
3 Pasangan dinding keramik 20 cm x 20 cm 7.99 m2 Rp 287,154.34 Rp 2,294,363.18
4 Pasangan plin keramik 10 cm x 40 cm 19.04 m1 Rp 10,000.00 Rp 190,400.00
JUMLAH Rp 10,447,985.42

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

VI PEKERJAAN ATAP
1 Pasangan rangka atap 81.3953 m2 Rp 63,063.52 Rp 5,133,074.13
2 Pasangan listplang kayu 29.92 m2 Rp 99,346.00 Rp 2,972,432.32
3 Pasangan nok/bubungan keramik 6 m2 Rp 251,576.00 Rp 1,509,456.00
JUMLAH Rp 9,614,962.45

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

VII PEKERJAAN LANGIT-LANGIT


1 Pasangan rangka langit-langit 60x60 cm 45.3952 m2 Rp 108,670.56 Rp 4,933,121.81
2 Pasangan langit-langit gypsum board 45.3952 m2 Rp 46,427.26 Rp 2,107,574.75
3 Pasangan list gypsum profil 56.5 m2 Rp 36,072.61 Rp 2,038,102.47
JUMLAH Rp 9,078,799.02

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

VIII PEKERJAAN PLUMBING


1 Pekerjaan bak kontrol 60 cm x 60 cm x 65 cm 1 bh Rp 285,306.49 Rp 285,306.49
2 Pemasangan pipa PVC 4 " 25.3 m' Rp 166,177.04 Rp 4,204,279.11
3 Pemasangan pipa PVC ¾ " 8.72 m' Rp 53,470.52 Rp 466,262.93
JUMLAH Rp 4,955,848.54

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

IX PEKERJAAN PENGECATAN
1 Pasangan lapis planir 264.03 m2 Rp 10,959.06 Rp 2,893,520.61
2 Pasangan pengecatan tembok dengan roll 264.03 m2 Rp 23,482.50 Rp 6,200,084.48
3 Pasangan pengecatan plafon dengan roll 45.3952 m2 Rp 31,181.36 Rp 1,415,484.07
JUMLAH Rp 10,509,089.16
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

X PEKERJAAN LISTRIK
1 Pekerjaan instalasi lampu dan kotak kontak 39.28 m' Rp 177,820.40 Rp 6,984,785.31
2 Pekerjaan stop kontak 6 bh Rp 38,575.64 Rp 231,453.84
3 Pekerjaan lampu 18 watt 5 bh Rp 56,775.64 Rp 283,878.20
4 Pekerjaan lampu bohlam 24 bh Rp 30,575.64 Rp 733,815.36
5 Pekerjaan sekring kast 1 bh Rp 68,575.64 Rp 68,575.64
6 Pekerjaan MCB box 1 bh Rp 97,375.64 Rp 97,375.64
7 Pekerjaan saklar tunggal 5 bh Rp 73,851.28 Rp 369,256.40
8 Pekerjaan saklar ganda 5 bh Rp 77,051.28 Rp 385,256.40
JUMLAH Rp 9,154,396.79

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

XI PEKERJAAN SANITAIR
1 Pekerjaan kloset duduk 1 bh Rp 3,697,947.05 Rp 3,697,947.05
2 Pekerjaan bak fiberglass volume 1 m³ 1 bh Rp 1,252,017.80 Rp 1,252,017.80
3 Pekerjaan kran air Ø ¾ " atau ½ " 2 bh Rp 69,713.52 Rp 139,427.04
4 Pekerjaan bak cuci piring stainless steel 1 bh Rp 746,840.56 Rp 746,840.56
5 Pekerjaan floor drain 2 bh 118840.56 Rp 237,681.12
JUMLAH Rp 5,836,232.45