DAFTAR HARGA SATUAN UPAH KERJA DAN MATERIAL

DAFTAR HARGA SATUAN MATERIAL


NO Uraian Satuan
1 Bata merah bh
2 Rangka baja ringan m2
3 Cat dasar kg
4 Cat ICI Weathershield l
5 Cat penutup tembok Catylac kg
6 Cat tembok luar Mowilex Weathercoat l
7 Cross Tee bh
8 Genteng metal lbr
9 Gypsum board lbr
10 Kapur pasang zak
11 Kayu bengkirai m3
12 Keramik 40/40 m2
13 main Runner bh
14 Metal Furing m
15 Paku anti karat kg
16 Paku reng kg
17 Paku usuk kg
18 Pasir pasang kg
19 PC kg
20 Plamir tembok kg
21 Reng kayu bengkirai 2/3 btg
22 Semen putih kg
23 Semen warna kg
24 Soda api bj
25 Suspension Bracket bh
26 Suspension Clip bh
27 Suspension Rod bh
28 Usuk kayu bengkirai 5/7 btg
29 Wall Angle bh
DAFTAR HARGA SATUAN UPAH KERJA
NO Uraian Satuan
1 Kepala tukang batu OH
2 Kepala tukang cat OH
3 Kepala tukang kayu OH
4 Mandor OH
5 Pekerja OH
6 Tukang OH
7 Tukang batu OH
8 Tukang cat OH
9 Tukang kayu OH
AH KERJA DAN MATERIAL

Harga Satuan Harga pasaran


Angka satuan
Rp Rp
Rp 910 1 Rp 910
Rp 168,000 1 Rp 168,000
Rp 30,736 1 Rp 30,736
Rp 226,571 2.5 Rp 566,427
Rp 31,462 1 Rp 31,462
Rp 159,244 2.5 Rp 398,109
Rp 11,200 1 Rp 11,200
Rp 140,000 1 Rp 140,000
Rp 91,000 1 Rp 91,000
Rp 16,787 1 Rp 16,787
Rp 13,904,545 1 Rp 13,904,545
Rp 70,255 1 Rp 70,255
Rp 14,000 1 Rp 14,000
Rp 56,000 1 Rp 56,000
Rp 35,000 1 Rp 35,000
Rp 27,364 1 Rp 27,364
Rp 27,364 1 Rp 27,364
Rp 144,900 1 Rp 144,900
Rp 1,830 40 Rp 73,182
Rp 21,076 1 Rp 21,076
Rp 5,269 2.5 Rp 13,173
Rp 109,773 1 Rp 109,773
Rp 16,902 1 Rp 16,902
Rp 28,000 1 Rp 28,000
Rp 2,800 1 Rp 2,800
Rp 5,600 1 Rp 5,600
Rp 2,100 1 Rp 2,100
Rp 37,030 4 Rp 148,120
Rp 19,600 1 Rp 19,600
Harga Satuan
( Rp )
Rp 150,000
Rp 150,000
Rp 150,000
Rp 150,000
Rp 100,000
Rp 100,000
Rp 100,000
Rp 100,000
Rp 100,000
ANALISA SATUAN PEKERJ

No. Macam Pekerjaan


(1) (2)

I.8 10.0000 m2
0.5000 org
1.0000 org

10.0000 m2
2.0000 org
0.1000 org

L.12 1.0000 m3
6.0000 org
0.6000 org
4.0000 org
0.2000 org

L.14 1.0000 m3
12.0000 org
1.2000 org
4.0000 org
0.2000 org
Analisa ZAZ 1.0000 m2
3.5000 kg
0.0330 org
0.0033 org
0.0700 org
0.0035 org

1.0000 m2
70.0000 bh
4.5000 kg
0.0150 m3
0.0500 m3
0.1000 org
0.0100 org
0.3200 org
0.0150 org

1.0000 m2
1.8400 kg
0.0060 m3
0.0140 m3
0.1500 org
0.0150 org
0.2000 org
0.0100 org
AK 1.0000 m2
1.0000 m2
0.1500 kg
0.1000 kg
0.1000 org
0.0100 org
0.1000 org
0.0025 org

1.0000 m2
0.3472 lbr
0.7200 unit
0.3600 unit
0.7200 unit
1.7000 m'
0.1400 unit
0.2400 unit
1.4400 unit
0.3000 Oh
0.2500 Oh
0.0800 Oh

SNI 1.0000 m2
03-3436-2002 1.5873 m2
6.32 0.2000 kg
0.1000 org
0.0100 org
0.2000 org
0.0010 org

SNI 1.0000 m1
6.24 0.2300 m2
1.2000 kg
0.0030 m3
0.1000 kg
0.0300 org
0.0030 org
0.0600 org
0.0030 org

AK 1.0000 m2
1.0000 m2
4.0800 kg
0.0090 m3
0.6000 kg
0.5000 org
0.0500 org
0.2500 org
0.0125 org

SNI 1.0000 m2
6.1 0.0500 kg
0.1500 org
0.0025 org

SNI 1.0000 m2
6.14 0.1000 kg
0.3600 kg
0.0630 org
0.0063 org
0.0200 org
0.0025 org
ANALISA SATUAN PEKERJAAN

Macam Pekerjaan
(2)

Membongkar atap seng


Tukang
Pekerja
JUMLAH ( BELUM PPN )

TIAP 1M2 ( BELUM PPN )


JASA 10 %
JUMLAH
DIBULATKAN

Membongkar usuk / reng tidak dipakai lagi


Pekerja
Mandor
JUMLAH ( BELUM PPN )

TIAP 1M2 ( BELUM PPN )


JASA 10 %
JUMLAH
DIBULATKAN

Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
Tukang kayu
Kepala tukang kayu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Mengerjakan kembali bangunan kayu yang telah dibongkar


Tukang kayu
Kepala tukang kayu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Acian dinding bata


PC
Tukang batu
Kepala tukang batu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps


Bata merah
PC
Kapur pasang
Pasir pasang
Tukang batu
Kepala tukang batu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Plesteran 1 PC : 3 Kp : 10 Ps, tebal 15 mm


PC
Kapur pasang
Pasir pasang
Tukang batu
Kepala tukang batu
Pekerja
Mandor
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Rangka atap baja ringan
Rangka baja ringan
Paku usuk
Paku reng
Tukang kayu
Kepala tukang kayu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Pasangan Plafond gypsum board


Gypsum board
Suspension Bracket
Suspension Rod
Suspension Clip
Metal Furing
Wall Angle
Main Runner
Cross Tee
Tukang Kayu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Pasang atap genteng metal roof
Genteng metal
Paku anti karat
Tukang kayu
Kepala tukang kayu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Pasang plint keramik ukuran 10 x 40 cm


Keramik 40/40
PC
Pasir pasang
Semen warna
Tukang batu
Kepala tukang batu
Pekerja
Mandor
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Pasang tegel keramik 40/40


Keramik 40/40
PC
Pasir pasang
Semen putih
Tukang batu
Kepala tukang Batu
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Mengikis / mengerok permukaan cat tembok lama


Soda api
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN

Pengecatan tembok tidak terlindung dari panas dan hujan


Cat tembok luar Mowilex Weathercoat
Cat ICI Weathershield
Tukang cat
Kepala tukang cat
Pekerja
Mandor
JUMLAH ( BELUM PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Upah Bahan Jumlah
(3) (4) (5)

@ Rp. 100,000.00 50,000.00


@ Rp. 100,000.00 100,000.00
150,000.00 0.00 150,000.00

15,000.00 0.00 15,000.00


1,500.00 0.00 1,500.00
16,500.00 0.00 16,500.00
16,500.00 0.00 16,500.00

@ Rp. 100,000.00 200,000.00


@ Rp. 150,000.00 15,000.00
215,000.00 0.00 215,000.00

21,500.00 0.00 21,500.00


2,150.00 0.00 2,150.00
23,650.00 0.00 23,650.00
23,650.00 0.00 23,650.00

@ Rp. 100,000.00 600,000.00


@ Rp. 150,000.00 90,000.00
@ Rp. 100,000.00 400,000.00
@ Rp. 150,000.00 30,000.00
1,120,000.00 0.00 1,120,000.00
112,000.00 0.00 112,000.00
1,232,000.00 0.00 1,232,000.00
1,232,000.00 0.00 1,232,000.00

@ Rp. 100,000.00 1,200,000.00


@ Rp. 150,000.00 180,000.00
@ Rp. 100,000.00 400,000.00
@ Rp. 150,000.00 30,000.00
1,810,000.00 0.00 1,810,000.00
181,000.00 0.00 181,000.00
1,991,000.00 0.00 1,991,000.00
1,991,000.00 0.00 1,991,000.00

@ Rp. 1,829.55 6,403.41


@ Rp. 100,000.00 3,300.00
@ Rp. 150,000.00 495.00
@ Rp. 100,000.00 7,000.00
@ Rp. 150,000.00 525.00
11,320.00 6,403.41 17,723.41
1,132.00 640.34 1,772.34
12,452.00 7,043.75 19,495.75
12,452.00 7,043.00 19,495.00

@ Rp. 910.00 63,700.00


@ Rp. 1,829.55 8,232.95
@ Rp. 16,787.27 251.81
@ Rp. 144,900.00 7,245.00
@ Rp. 100,000.00 10,000.00
@ Rp. 150,000.00 1,500.00
@ Rp. 100,000.00 32,000.00
@ Rp. 150,000.00 2,250.00
45,750.00 79,429.76 125,179.76
4,575.00 7,942.98 12,517.98
50,325.00 87,372.74 137,697.74
50,325.00 87,372.00 137,697.00

@ Rp. 1,829.55 3,366.36


@ Rp. 16,787.27 100.72
@ Rp. 144,900.00 2,028.60
@ Rp. 100,000.00 15,000.00
@ Rp. 150,000.00 2,250.00
@ Rp. 100,000.00 20,000.00
@ Rp. 150,000.00 1,500.00
38,750.00 5,495.69 44,245.69
3,875.00 549.57 4,424.57
42,625.00 6,045.26 48,670.26
42,625.00 6,045.00 48,670.00
@ Rp. 168,000.00 168,000.00
@ Rp. 27,363.64 4,104.55
@ Rp. 27,363.64 2,736.36
@ Rp. 100,000.00 10,000.00
@ Rp. 150,000.00 1,500.00
@ Rp. 100,000.00 10,000.00
@ Rp. 150,000.00 375.00
21,875.00 174,840.91 196,715.91
2,187.50 17,484.09 19,671.59
24,062.50 192,325.00 216,387.50
24,062.00 192,325.00 216,387.00

@ Rp. 91,000.00 31,597.22


@ Rp. 2,800.00 2,016.00
@ Rp. 2,100.00 756.00
@ Rp. 5,600.00 4,032.00
@ Rp. 56,000.00 95,200.00
@ Rp. 19,600.00 2,744.00
@ Rp. 14,000.00 3,360.00
@ Rp. 11,200.00 16,128.00
@ Rp. 100,000.00 30,000.00
@ Rp. 100,000.00 25,000.00
@ Rp. 150,000.00 12,000.00
67,000.00 155,833.22 222,833.22
6,700.00 15,583.32 22,283.32
73,700.00 171,416.54 245,116.54
73,700.00 171,416.00 245,116.00

@ Rp. 140,000.00 222,222.22


@ Rp. 35,000.00 7,000.00
@ Rp. 100,000.00 10,000.00
@ Rp. 150,000.00 1,500.00
@ Rp. 100,000.00 20,000.00
@ Rp. 150,000.00 150.00
31,650.00 229,222.22 260,872.22
3,165.00 22,922.22 26,087.22
34,815.00 252,144.44 286,959.44
34,815.00 252,144.00 286,959.00
@ Rp. 70,254.55 16,158.55
@ Rp. 1,829.55 2,195.45
@ Rp. 144,900.00 434.70
@ Rp. 16,901.82 1,690.18
@ Rp. 100,000.00 3,000.00
@ Rp. 150,000.00 450.00
@ Rp. 100,000.00 6,000.00
@ Rp. 150,000.00 450.00
9,900.00 20,478.88 30,378.88
990.00 2,047.89 3,037.89
10,890.00 22,526.77 33,416.77
10,890.00 22,526.00 33,416.00

@ Rp. 70,254.55 70,254.55


@ Rp. 1,829.55 7,464.55
@ Rp. 144,900.00 1,304.10
@ Rp. 109,772.73 1,646.59
@ Rp. 100,000.00 50,000.00
@ Rp. 150,000.00 7,500.00
@ Rp. 100,000.00 25,000.00
@ Rp. 150,000.00 1,875.00
84,375.00 80,669.78 165,044.78
8,437.50 8,066.98 16,504.48
92,812.50 88,736.76 181,549.26
92,812.00 88,736.00 181,549.00

@ Rp. 28,000.00 1,400.00


@ Rp. 100,000.00 15,000.00
@ Rp. 150,000.00 375.00
15,375.00 1,400.00 16,775.00
1,537.50 140.00 1,677.50
16,912.50 1,540.00 18,452.50
16,912.00 1,540.00 18,452.00

@ Rp. 159,243.64 15,924.36


@ Rp. 226,570.91 81,565.53
@ Rp. 100,000.00 6,300.00
@ Rp. 150,000.00 945.00
@ Rp. 100,000.00 2,000.00
@ Rp. 150,000.00 375.00
9,620.00 97,489.89 107,109.89
962.00 9,748.99 10,710.99
10,582.00 107,238.88 117,820.88
10,582.00 107,238.00 117,820.00
INSTANSI : YAYASAN PENDIDIKAN ISLAM YLPI RIAU
KEGIATAN : REHABILITASI RINGAN GEDUNG SEKOLAH
PEKERJAAN : REHABILITASI AULA GEDUNG SEKOLAH SMP ISLAM YLPI RIAU
LOKASI : PEKANBARU, RIAU
TAHUN ANGGARAN : 2014

DAFTAR KUANTITAS DAN HARGA

No. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA KETERANGAN
(Rp.) (Rp)
1 2 3 4 5 6 7

I PEKERJAAN BONGKARAN
1 Membongkar atap seng 658.95 m2 16,500.00 10,872,656.95
2 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi 5.14 m3 1,232,000.00 6,328,143.36
3 Membongkar usuk / reng tidak dipakai lagi 461.26 m2 23,650.00 10,908,899.14
4 Mengerjakan kembali bangunan kayu yang telah dibongkar 5.14 m3 1,991,000.00 10,226,731.68
38,336,431.14
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 101.00 m2 137,697.00 13,907,397.00
2 Plesteran 1 PC : 3 Kp : 10 Ps, tebal 15 mm 417.00 m2 48,670.00 20,295,390.00
3 Acian dinding bata 202.00 m2 19,495.00 3,937,990.00
38,140,777.00
III PEKERJAAN PENUTUP ATAP, PLAFOND, DAN TALANG
1 Pasang atap genteng metal roof 658.95 m2 286,959.00 189,091,319.20
2 Rangka atap baja ringan 461.26 m2 216,387.00 99,811,583.89
3 Pasangan Plafond gypsum board 420.00 m2 245,116.00 102,948,720.00
391,851,623.09
IV PEKERJAAN LANTAI
1 Pasang plint keramik ukuran 10 x 40 cm 101.00 m 33,416.00 3,375,016.00
2 Pasang tegel keramik 40/40 430.00 m2 181,549.00 78,066,070.00
81,441,086.00
V PEKERJAAN CAT-CATAN
1 Mengikis / mengerok permukaan cat tembok lama 707.00 m2 18,452.00 13,045,564.00
2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 707.00 m2 117,820.00 83,298,740.00
3 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 202.00 m2 117,820.00 23,799,640.00
120,143,944.00

Pekanbaru, 6 April 2014


Dibuat oleh
SMP Islam YLPI
KEPALA SEKOLAH

DWI ARTATY S.Pd


NIP :
INSTANSI : YAYASAN PENDIDIKAN ISLAM YLPI RIAU
KEGIATAN : REHABILITASI RINGAN GEDUNG SEKOLAH
PEKERJAAN : REHABILITASI AULA GEDUNG SEKOLAH SMP ISLAM YLPI RIAU
LOKASI : PEKANBARU, RIAU
TAHUN ANGGARAN : 2014

DAFTAR REKAPITULASI BIAYA

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
II PEKERJAAN BONGKARAN Rp. 38,336,431.14
IV PEK. PASANGAN DAN PLESTERAN Rp. 38,140,777.00
VI PEKERJAAN PENUTUP ATAP, PLAFOND, DAN TALANG Rp. 391,851,623.09
VIII PEK. LANTAI Rp. 81,441,086.00
IX PEK. CAT-CATAN Rp. 120,143,944.00

JUMLAH BIAYA : Rp. 669,913,861.23


PPN 10 % Rp. 66,991,386.12

JUMLAH TOTAL : Rp. 736,905,247.35


DIBULATKAN : Rp. 736,905,247.00

Pekanbaru, 6 April 2014


Dibuat oleh
SMP Islam YLPI
KEPALA SEKOLAH

DWI ARTATY S.Pd


NIP :