Volume Urugan Pasir = Tinggi Urugan Pasir x Lebar Bawah x Panjang Pondasi = 0.05 x 0.5 x 125 = 3.125 = 0.781 = 1 Truk
Kebutuhan Pasir = 0.54 x Volume Pondasi = 0.54 x 32.5 = 17.55 m3 = 4.388 Truk = 5 Truk
Kebutuhan Batu = 1.2 x Volume Pondasi = 1.2 x 32.5 = 39 m3 = 9.75 Truk = 10 Truk
Kebutuhan Semen = 2.68 x Volume Pondasi = 2.68 x 32.5 = 87.1 sak = 88 sak