2. Kelas jalan =A
3. Bentang jembatan
- Panjang Jembatan = 45 m
- Baja = Bj 50
= 2240 + 2,29 . 35
= 2240 + 2,29 . 35
4. Air hujan
1. Beban mati
2. Beban hidup
- Muatan “T” yang bekerja pada plat lantai kendaraan adalah = 225 kN = 22500
𝐿 𝐿𝑦
β = 𝑆𝑛 = 𝐿 (Dipohusodo,Istimawan. 1993 hal 20)
𝑛 𝑥
𝐿 500
Maka β = 𝑆𝑛 = 170 = 2,941 > 2 (pelat satu arah)
𝑛
= 228,289 kg.m
= 156,949 kg.m
MA = ME = -1/24 x Qu1 x L2
= -1/24 x 819,97 x 1,752
= -104,632 kg.m
MB = MD = -1/10 x Qu1 x L2
= -251,118 kg.m
MC = -1/11 x Qu1 x L2
= -228,289 kg.m
Dimana :
MT = Momen tumpuan
ML = Momen lapangan
𝑆+0,6
MT = M L = 0,8 x x Pult
10
1,75+0,6
= 0,8 x x 29250
10
= 5499 kg.m
Mn = Mu/φ
𝑀𝑛 7159 𝑥 104
Rn = = = 2,6137 Mpa
𝑏. 𝑑2 1000 𝑥 165,52
𝑓𝑦
m =
0,85 𝑥 𝑓𝑐
390
= 0,85 𝑥 35
= 13,109
1 2 . 𝑚 . 𝑅𝑛
ρ = 𝑚 {1 − √1 − }
𝑓𝑦
= 0,00702
0,85 𝑥 35 600
= x 0,85 x 600+390
390
= 0,0392
ρmax = 0,75 x ρb
= 0,75 x 0,0392
= 0,0294
1,4
ρmin = 𝑓𝑦
1,4
= 390
= 0,0036
Asperlu = ρ x b x d
Mn = Mu/φ
= 165,5 mm
𝑀𝑛 7187 𝑥 104
Rn = 𝑏. = 1000 𝑥 165,52 = 2,623 Mpa
𝑑2
𝑓𝑦
m = 0,85 𝑥 𝑓𝑐
390
= 0,85 𝑥 35
= 13,109
1 2 . 𝑚 . 𝑅𝑛
ρ = 𝑚 {1 − √1 − }
𝑓𝑦
= 0,0071
0,85 𝑥 35 600
= x 0,85 x 600+390
390
= 0,0392
ρmax = 0,75 x ρb
= 0,75 x 0,0392
= 0,0294
1,4
ρmin = 𝑓𝑦
1,4
= 390
= 0,0036
Asperlu = ρ x b x d
Dipasang tulangan susut dan suhu dengan ketentuan sebagai berikut :(SK SNI
Tulangan pokok ∅ 12 mm :
113,04
Jarak masximum antar tulangan = x 1000 = 379,456 > 300 mm
297,9
gv = 500 kg/m
gh = 500 kg/m
0,20
g1
0,20
g2
1,00
1. Beban mati
2. Beban hidup
3. Perhitungan momen
Mn = 1175,2 kg.m
𝐿 𝐿𝑦
β = 𝑆𝑛 = 𝐿 (Dipohusodo,Istimawan. 1993 hal 20)
𝑛 𝑥
𝐿 500
Maka β = 𝑆𝑛 = 100 = 5 > 2 (pelat satu arah)
𝑛
= 165,5 mm
0,85 𝑥 35 600
= x 0,85 x 600+390
390
= 0,0392
ρmax = 0,75 x ρb
= 0,75 x 0,0392
= 0,0294
1,4
ρmin = 𝑓𝑦
1,4
= 390
= 0,0036
Mu = 1175,2 kg.m
Mn = Mu/φ
𝑀𝑛 1469 𝑥 104
Rn = 𝑏. = 1000 𝑥 165,52 = 0,536 Mpa
𝑑2
𝑓𝑦
m = 0,85 𝑥 𝑓𝑐
390
= 0,85 𝑥 35
= 13,109
1 2 . 𝑚 . 𝑅𝑛
ρ = 𝑚 {1 − √1 − }
𝑓𝑦
= 0,00138
Asperlu = ρmin x b x d
Mu = 1175,2 kg.m
Mn = Mu/φ
𝑀𝑛 1469 𝑥 104
Rn = 𝑏. = 1000 𝑥 165,52 = 0,536 Mpa
𝑑2
𝑓𝑦
m = 0,85 𝑥 𝑓𝑐
390
=
0,85 𝑥 35
= 13,109
1 2 . 𝑚 . 𝑅𝑛
ρ = 𝑚 {1 − √1 − }
𝑓𝑦
= 0,00138
Asperlu = ρmin x b x d
Dipasang tulangan susut dan suhu dengan ketentuan sebagai berikut :(SK SNI
Tulangan pokok ∅ 12 mm :
Vuc = u . d . fcv
1 2
fcv = 6 x (1+β ) x √fc′
h
dimana :
𝛽h = Perbandingan antara dimensi terpanjang dari luas efektif yang dibebani n”y”
1. Muatan “T” dengan P = 25 kN dan luas bidang kontak roda 150 mm x 250
P = 25 kN
165,5
d/2 = = 82,75 mm
2
= 1462 mm
2
fcv = 1/6 x {1 + (250 )} 𝑥 √35
⁄150
= 2,169 Mpa
Karena fcv = 2,169 Mpa > 0,34 x √35 = 2,011 Mpa, maka :
Vuc = u x d x fcv
= 524868,9 N → 524,868 kN
86,5
200 173
86,5
150
86,5
2. Muatan “T” P = 112,5 kN dan luas bidang kontak roda 250 mm x 750
P = 112,5 kN
165,5
d/2 = = 82,75 mm
2
= 2662 mm
2
fcv = 1/6 x {1 + (750 )} 𝑥 √35
⁄250
= 1,643 Mpa
Vuc = u x d x fcv
= 723998,3 N → 723,998 kN
P = 292,5 kN
86,5
200 173
86,6
750
86,6
1. Beban Mati
Berat sendiri plat beton = 0,20 x 1,75 x 2320,15 x 1,3 = 1055,6 kg/m
qd = 1434,963 kg/m
MD = 1/8 x qd x l2
= 1/8 x 1434,963 x 52
2. Beban Hidup
1,75
= = 0,5147
3,4
ML = ¼ x (Ft x P) x L
= ¼ x (0,5147 x 26325) x 5
G = 66,00 Kg/m
1,3 cm
A = 84,12 cm2
Ix = 23700 cm4
40 cm
0,8 cm
Iy = 1740 cm4
Zx = 1190 cm3
20 cm Zy = 174 cm3
Mu2 = 1/8 x q x l2
∅b . Mn = ∅b . Zx . Fy
d. Kontrol tegangan
𝑀𝑡𝑜𝑡𝑎𝑙 2142356,9
σ = = = 1800,299 < 2900 kg/cm2
𝑍𝑥 1190
MD = 1/8 x qd1 x l2
= 1/8 x 1128,3 x 52
a. Beban mati
MD = 1/8 x qd2 x l2
= 1/8 x 1507,56 x 52
b. Beban hidup
ML = 1693704,04 kg.cm
Menurut RSNI T-03-2005, nilai Beff diambil nilai yang terkecil dari :
- 12 x tebal plat
b. Beff = 175 cm
c. Beff = 12 x 20 = 240 cm
Ec = 4700 . √𝑓𝑐 ′
= 4700 . √35
= 27805,574 Mpa
200000
= 27805,574
= 7,192
𝐵𝑒𝑓𝑓 100
= = 14,2 cm
𝑛 7
∑ 369,83 6221,94
∑𝐴 . 𝑦 6221,94
ya = ∑𝐴
= = 16,82 cm (diukur dari bagian atas pelat)
369,83
yb =t+d–y
= 20 + 40 – 16,82
= 43,18 cm
Gambar 4.8. Penampang Komposit Gelagar Memanjang
sumbu sejajar :
𝑏 . ℎ3
I = 12
14,2 𝑥 203
= 12
= 9523,81 cm4
Itr 91697,76
91697,76
= = 5450,54 cm3
16,82
𝐼
𝑡𝑟
Ssb = 𝑦𝑏
91697,76
= = 2123,79 cm3
43,17
𝑡𝑟 𝐼
Ssa = 𝑦−20
91697,76
= 16,82−20 = 28868,42 cm3
profil baja.
3,525 𝑥 107
= 1190 𝑥 103
= 29,628 Mpa
fsb = fsa
Tahap II : Beton sudah mengeras, beban hidup dipikul oleh penampang
komposit.
Mmaks = MD + ML
= 4711,13 + 1693704,04
16,984 𝑥 107
= 7 𝑥 5450,54 𝑥 103 = 4,451 Mpa < 35 Mpa (tekan)
16,984 𝑥 107
= 2123,79 𝑥 103 = 5,883 Mpa < 174 Mpa (tarik)
(bagian atas baja terletak di bawah sumbu netral, sehingga fsa adalah
tegangan tarik)
16,984 𝑥 106
= 783,01 𝑥 103 = 79,97 Mpa < 174 Mpa (tarik)
4.3.4 Lendutan Gelagar Memanjang
Panjang masing – masing gelagar rangka baja adalah 5 m, maka besar defleksi
PL = 26325 kg
Is = 23700 cm4
It = 91697,76 cm4
5 . 𝑞𝑑1 . 𝐿4
∆D = 384 . 𝐸 . 𝐼𝑠
5 𝑥 11,2826 𝑥 5004
= 384 𝑥 2000000 𝑥 23700
= 0,051 cm
5 . 𝑞𝑑2 . 𝐿4
∆d = 384 . 𝐸 . 𝐼𝑡
5 𝑥 15,0756 𝑥 5004
= 384 𝑥 200000 𝑥 91697,76
= 0,668
𝑃 . 𝐿3
∆L = 48 . 𝐸 . 𝐼𝑡
26325 𝑥 5003
= 48 𝑥 2000000 𝑥 91697,76
= 0,374 cm
∆ = ∆D + ∆d + ∆L
1. Beban mati
qd =1507,56 kg/m
2. Beban hidup
Beban “T”
𝑆 1,75
Faktor beban “T” → FT = 3,4 = = 0,514
3,4
Kondisi pembebanan :
a. Pada x = 0 m
Beban mati :
Beban hidup :
b. Pada x = 1,0 m
Beban mati :
= 2261,34 kg
Beban hidup :
Beban mati :
= 753,78 kg
Beban hidup :
Asc = π x 9,52
Ec = 4700 . √𝑓𝑐
= 4700 x √35 = 27805,57 Mpa
= 1397,80 kg
𝑡𝑠 𝑥 𝐵𝑒𝑓𝑓 20 𝑥 100
At = = = 278,055 cm2
𝑛 7,193
ST = At x dc
= 278,055 x 6,82
= 1897,34 kg/cm
𝑆𝑇
τ = x Dmaks
𝐼𝑡
1897,34
= 91711,76 x 17318,54= 358,153 kg/cm
2795,61
= 358,153
= 9,610 cm
4.4.1 Pembebanan
1. Beban Mati
= 10833,44 kg
= 9573,83 kg.m
P = 66 x 5 x 1,1 = 363 kg
5 𝑥 363
RA = = 907,5 kg
2
MD = Md1 + Md2
= 9573,83 + 2178
= 11751,8 kg.m
2. Beban hidup
∑MB = 0
= 221130 kg.m
Mtotal = MD + M L
= 11751,8 + 221130
1,6 cm
G = 243 Kg/m
A = 309,8 cm2
Ix = 41100 cm4
90 cm
2,3 cm
Iy = 12600 cm4
Zx = 9140 cm3
Zy = 843 cm3
30 cm
Mu2 = 1/8 x q x l2
∅b . Mn = ∅b . Zx . Fy
∅b . Mn = ∅b . Zx . Fy ≥ Mu1 + Mu2
= 33111,73 kg.m
5 𝑥 363
RA = = 907,5 kg
2
= 2178 kg.m
= 33111,73 + 2178
= 42034,25 kg.m
ML = 196560 kg.m
Menurut RSNI T-03-2005, nilai Beff diambil nilai yang terkecil dari :
- 12 x tebal plat
f. Beff = 12 x 20 = 240 cm
Ec = 4700 . √𝑓𝑐 ′
= 7,193
𝐵𝑒𝑓𝑓 175
= = 25 cm
𝑛 7
∑ 809,8 25137
∑𝐴 . 𝑦 25137
ya = ∑𝐴
= = 31,04 cm (diukur dari bagian atas pelat)
809,8
yb =t+d–y
= 90 + 20 – 31,04 = 79 cm
sumbu sejajar :
𝑏 . ℎ3
I = 12
25 𝑥 203
= = 2083,33 cm4
12
Itr 621810,772
621810,772
= 31,04
= 20031,92 cm3
𝐼
𝑡𝑟
Ssb = 𝑦𝑏
621810,772
= = 7875,11 cm3
79
𝑡𝑟 𝐼
Ssa = 𝑦−20
621810,772
= = 56318,35 cm3
31,04−20
profil baja.
35,289 x 107
=
9140 𝑥 103
= 38,610 Mpa
fsb = fsa
Tahap II : Beton sudah mengeras, beban hidup dipikul oleh penampang
komposit.
Mmaks = MD + ML
= 42034,25 + 196560
2385,9425 x 107
= 7 𝑥 20031,92 𝑥 103 = 17,015 Mpa < 35 Mpa
2385,9425 x 107
= = 42,365 Mpa < 174 Mpa
56318,35 𝑥 103
2385,9425 x 107
= = 4,236 Mpa < 174 Mpa
7875,11 𝑥 103
Panjang masing – masing gelagar rangka baja adalah 8 m, maka besar defleksi
PL = 36855 kg
Is = 411000 cm4
It = 621810,72 cm4
5 .𝑞𝑑𝑡𝑜𝑡𝑎𝑙 . 𝐿4
∆D = 384 . 𝐸 . 𝐼𝑠
5 𝑥 62,9969 𝑥 9004
= 384 𝑥 2000000 𝑥 411000
= 0,655 cm
5 .𝑞3 . 𝐿4
∆d = 384 . 𝐸 . 𝐼𝑡
5 𝑥 436719,5 𝑥 9004
= 384 𝑥 2000000 𝑥 621810,72
= 0,301 cm
𝑃 . 𝐿3
∆L = 48 . 𝐸 . 𝐼𝑡
36855 𝑥 9003
= 48 𝑥 2000000 𝑥 621810,72
= 0,451 cm
∆ = ∆D + ∆L
1. Beban mati
qd = 4367,195 kg/m
2. Beban hidup
= 36855 kg
Kondisi pembebanan :
a. Pada x = 1,75 m
Beban mati :
= 12539,30 kg
Beban hidup :
b. Pada x = 3,5 m
Beban mati :
= 4345,35 kg
Beban hidup :
c. Pada x = 4,5 m
Beban mati :
= 545,89 kg
Beban hidup :
Asc = π x 9,52
Ec = 4700 . √𝑓𝑐
= 1397,80 kg
𝑡𝑠 𝑥 𝐵𝑒𝑓𝑓 20 𝑥 175
At = = = 486,597 cm2
𝑛 7,192
ST = At x dc
= 486,597 x 21,04
= 10238,49 kg/cm
𝑆𝑇
τ = x Dmaks
𝐼𝑡
10238,49
= 621810,77 x 90303,35 = 1486,91 kg/cm
2795,61
= 1486,91
= 1,880 cm
= 190020,28 kg
= 108583,02 kg
G7 = (n x a) x L x a = (8 x 9) x 45 x 9 x 1,1 = 32076 kg
Gtotal = 509314,54 kg
𝐺 254657,27
P1 = 8 = = 28295,25 kg
9
𝑃1 28295,25
P2 = = = 14147,62 kg
2 2
4.5.2 Beban Hidup
L = 45 m > 30 m
15
q = 9,0 x (0,5 + ) = 7,5 kpa = 750 kg/m
45
1350
Beban 50% →q = x 50% = 245,45 kg/m
2,75
15003,41
RA = = 1667,045 kg/m
9
Q = RA x 45 = 1667,045 x 45 = 75017,05 kg
𝑄 75017,05
Qt = ∑ = = 10716,72 kg
𝑡𝑖𝑡𝑖𝑘 𝑏𝑢ℎ𝑢𝑙 7
- 5% dari berat truk rencana ditambah beban lajur terbagi rata BTR
= 56,25 kN
= 132,167 kN
1321,67
= x 1,8 = 1189,505 kg
2
1189,505
= = 169,92 kg
7
169,92
= = 84,96 kg
2
diasumsikan sebagai tekanan menerus sebesar 1,46 N/mm, tegak lurus dan
= 2628 N = 262,8 Kg
200
TEW1 TEW2
180
400
Gelagar Memanjang
Gelagar Memanjang
900
𝑉 𝑍
VDZ = 2,5 x V0 x ( 𝑉10 )ln(𝑍 ) (SNI 1725-2016 pasal 9.6.1 hal 55)
𝐵 0
126 10400
VDZ = 2,5 x 13,2 x (126)ln( ) = 165,035 km/jam
70
𝑉 2
PD = PB( 𝑉𝐷𝑍 ) (SNI 1725-2016 pasal 9.6.1 hal 56)
𝐵
165,035 2
= 0,0024 x ( )
126
Ab = ½ x (45 + 40) x 7 x 30 %
= 89,25 m2
TEW2 = PD x Ab
= 365,925 kN = 36592,5 kg
∑V = 0
RA x b – TEW1 x a1 + TEW2 x a2
= 12250,06 kg
12250,06
= 7
= 1750,01 kg
1750,01
Pu = 2
= 675,004 kg
= 1080000 cm2
= 38880 kg
38880
= 7
= 5554,28 kg
= 2777,14 kg
= 1215000 cm2
P = 0,0019 MPa x Ab
= 23085 kg
23085
= 7
= 3297,85 kg
3297,85
= 2
= 1648,92 kg
4.6 Statika Gelagar Induk
1. Data struktur
2. Skema pembebanan
Pm1 = 28295,25 kg
Pm2 = 14147,62 kg
Beban hidup yang bekerja pada titik simpul akibat beban terbagi rata :
Ph1 = 7631,14 kg
Ph2 = 3815,37 kg
Pg1 = 36561,70 kg
d. Pembebanan Akibat Beban Rem
Pr1 = 1139,75 kg
Pr2 = 569,88 kg
Pa1 = 1385,78 kg
Pa2 = 692,89 kg
f. Pembebanan Ikatan Angin Atas
Pat1 = 4320 kg
Pat2 = 2160 kg
Pab1 = 2280 kg
Pab2 = 1140 kg
Tabel 4.8. Hasil resume dari aplikasi SAP 2000 untuk batang bawah, atas dan ikatan angin
Beban Jumlah Jumlah Jumlah
Live Live Live Live Live Live Live Live Live Live Live Live Live Live Beban Beban Beban
No. batang Dead Load
(BTR) (BGT 1) (BGT 2) (BGT 3) (BGT 4) (BGT 5) (BGT 6) (BGT 7) (BGT 8) (BGT 9) (REM) (Angin) (Angin (Angin Gelagar Ikatan Ikatan
(Kgm)
(Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) (Kgm) Atas) Bawah) Induk Atas Bawah
12 -173537,73
12 -50874,27
0,00
9 -26659,57
10 -45702,13
11 -57127,66
12 -60936,17
13 -57127,66 -561163,75 -15861,44 -10862,56
14 -45702,13
15 -26659,57
16 0,00
12 -7598,33
12 -9238,53
12 -15861,44
12, 13 -10862,56
4, 5 168114,68
4, 5 49284,45
0,00
2 24755,32
3 41893,61
4 51414,89
4, 5 53319,15
5 51414,89 523156,64 16538,56 11224,94
6 41893,61
7 24755,32
0,00
4, 5 7360,89
4, 5 8949,83
4 16538,56
4, 5 11224,94
Jumlah batang terbanyak untuk batang tekan Batang 12 -302185,03 -15861,44 -10862,56
Jumlah batang terbanyak untuk batang tarik Batang 4, 5 389858,78 16538,56 11224,94
23, 24 98699,59
23, 24 28934,74
0,00
24 34657,44
24, 25 29706,38
24, 25, 26 24755,32
24 s/d 27, 20 s/d 23 19804,25
21, 22, 23 24755,32 335252,83 0,00 0,00
22, 23 29706,38
23 34657,44
0,00
23, 24 4321,55
23, 24 5254,42
Jumlah batang terbanyak untuk batang tekan Batang 16 atau 31 -246133,69 0,00 0,00
Jumlah batang terbanyak untuk batang tarik Batang 4, 5 246133,69 0,00 0,00