Kurva - S

No Item Pekerjaan RAB BOBOT NOVEMBER DESEMBER


3 4 1 2 3
I PEKERJAAN PERSIAPAN DAN BONGKARAN
1 Bongkar dan pembersihan Rp 2,500,000 2.849 1.425 1.425
II PEKERJAAN TANAH 120.000
1 Galian Tanah Pondasi Rp 65,394 0.075 0.075
2 Urug Tanah Bekas Galian Rp 10,344 0.012 0.012
3 Urugan Pasir Rp 96,296 0.110 0.110
III PEKERJAAN BETON
1 Sloof beton bertulang (10 x 15) cm Rp 756,824 0.863 0.288 0.288 0.288
2 Plat Meja Dapur Rp 1,148,833 1.309
3 Ring Balok beton bertulang (10 x 15) cm Rp 3,324,618 3.789 0.758

IV PEKERJAAN LANTAI 100.000


1 Pasang lantai keramik 25x25 cm Rp 1,005,512 1.146 0.573
2 Pasang lantai keramik 30 x 30 cm Rp 1,394,834 1.590 0.530
3 Pasang dinding keramik 25x40 cm, Motif Rp 4,236,337 4.829 0.966 0.966 0.966
4 List Keramik Dinding 5 / 25 Rp 222,474 0.254 0.254

V PEKERJAAN DINDING
1 Pasangan Bata Merah Tebal 1 Bata 1 Pc : 6 Ps Rp 925,432 1.055 0.527 0.527
2 Pasangan Bata Merah Tebal 1/2 Bata 1 Pc : 6 Ps Rp 3,810,560 4.343 1.448 1.448
3 Plesteran 1 Pc : 6 Ps tebal 15 mm Rp 2,431,266 2.771 80.000 1.386
4 Pasang engsel pintu Rp 383,854 0.438
5 Pasang kunci tanam Rp 422,650 0.482

VII PEKERJAAN LISTRIK


1 Memasang lampu pijar SL 18 watt Rp 1,493,960 1.703
2 Memasang Saklar tunggal Rp 393,550 0.449
3 Memasang Saklar ganda Rp 400,050 0.456
4 Memasang Stop Kontak Rp 751,100 0.856
5 Konekting Kabel Rp 15,315,000 17.456 60.000
6 Memasang Box MCB Rp 518,200 0.591
7 Memasang sekring 2 group Rp 234,168 0.267
60.000

VIII PEKERJAAN CAT


1 Cat tembok Rp 8,528,514 9.721
2 Cat kayu Rp 869,069 0.991
3 Cat Plafon Rp 5,026,269 5.729
4 Cat Genteng Rp 8,092,280 9.224
40.000
IX PEKERJAAN SANITASI
1 Memasang 1 buah bak mandi Fibreglass volume 0.3 M³ Rp 1,331,608 1.518
2 Memasang pipa air kotor PVC diameter 3'' Rp 1,429,004 1.629
3 Memasang 1 m' pipa PVC diameter 1/2'' Maspion Rp 293,640 0.335
4 Memasang 1 buah Kran Air Rp 288,389 0.329
5 Memasang 1 buah Avour stainles Rp 58,125 0.066
6 Pasang pintu KM PVC KW 1 Rp 1,650,000 1.881
7 Memasang Kitchen Zink 1 lubang 1 sayap Rp 427,086 0.487
8 Pasang kran kitchenzink Rp 144,194 0.164
20.000

X PEKERJAAN LANGIT - LANGIT


1 Pasang rangka plafond Rp 1,875,088 2.137
2 Pasang plafond eternit Rp 476,328 0.543
3 Pasang gording 8/12, kayu meranti Rp 2,268,336 2.585
4 Pasang reng 3/5, usuk 5/7, kayu meranti Rp 7,906,285 9.012
5 Pasang Genteng tilup Rp 2,933,813 3.344
6 Pasang Genteng LAMA Rp 784,493 0.894
7 List langit - langit Gypsum T = 7,5cm Rp 1,511,038 1.722
-
0 2 4 6
Rp 87,734,811 100.000
Progress Rencana 1.425 1.621 2.034 3.228 5.947
Progress Kumulatif 1.425 3.046 5.080 8.308 14.256
Progress Aktual
Progress Kumulatif
EMBER JANUARI FEBRUARI MARET
4 1 2 3 4 1 2 3 4 1 2

0.436 0.436 0.436


0.758 0.758 0.758 0.758

0.573
0.530 0.530
0.966 0.966

1.448
1.386
0.438
0.482

0.851 0.851
0.449
0.456
0.856 Row 76
4.364 4.364 4.364 4.364 Linear (Row 76)
0.591
0.267
Row 76
Linear (Row 76)

2.430 2.430 2.430 2.430


0.991
5.729
1.845 1.845 1.845 1.845 1.845

0.759 0.759
0.814 0.814
0.335
0.329
0.066
0.940 0.940
0.487
0.164

2.137
0.543
1.293 1.293
2.253 2.253 2.253 2.253
1.672 1.672
0.894
0.861 0.861
4 6 8 10 12 14 16 18

10.024 7.910 10.865 10.241 8.537 10.387 6.127 7.574 5.363 4.358 4.358
24.280 32.190 43.054 53.296 61.833 72.220 78.347 85.921 91.283 95.642 100.000