TIME SCEDULE PEKERJAAN RUMAH TINGGAL

JUMLAH HARGA BOBOT


NO. URAIAN PEKERJAAN (Rp.) (%)

I PEK. PERSIAPAN 7,500,900.00 2.21%

II PEK. GALIAN PONDASI 15,750,600.00 4.64%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.39%

IV PEK. SLOOF DAN KOLOM 45,005,400.00 13.27%

V PEK. DINDING DAN KOLOM 29,950,000.00 8.83%

VI PEK. RING BALK 15,450,700.00 4.55%

VII PEK. KAP & ATAP 75,009,000.00 22.11%

VIII PEK. PLAFON 12,765,100.00 3.76%

IX PEK. PLESTERAN 7,686,713.00 2.27%

X PEK. LANTAI 11,251,350.00 3.32%

XI PEK. PINTU & JENDELA 16,369,850.00 4.83%

XII PEK. PENGECATAN 8,250,000.00 2.43%

XIII PEK. FINISHING DALAM 30,003,600.00 8.84%

XIV PEK. FINISHING LUAR 20,500,000.00 6.04%

XV PEK. TAMAN 8,525,000.00 2.51%

JUMLAH NILAI PEKERJAAN 339,268,963.00 100%


KEMAJUAN MINGGU
RENCANA
KOMULATIF KEMAJUAN
APRIL MINGGU KE- MEI MINGGU KE- JUNI MINGGU KE-
1 2 3 4 1 2 3 4 1

1.11% 1.11%

2.32% 2.32%

3.46% 3.46% 3.46%

4.42% 4.42% 4.42%

4.41% 4.41%

2.28% 2.28%

7.37% 7.37% 7.37%

1.25% 1.25%

1.13% 1.13%

0.83% 0.83%

0.61% 0.61%

2.95%

1.11% 3.43% 5.78% 7.89% 12.30% 11.11% 10.78% 11.19% 13.01%


1.11% 4.53% 10.32% 18.20% 30.50% 41.61% 52.39% 63.59% 76.60%
JUNI MINGGU KE-
PROSENT
2 3 4 ASE (%)

1.25%

0.83% 0.83%

2.41% 2.41%

0.61% 0.61%
30.50%

2.95% 2.95%

2.01% 2.01% 2.01% 18.20%

1.26% 1.26%
10.32%

4.53%
10.07% 10.07% 3.27% 1.11%

86.66% 96.73% 100.00%


100.00%
96.73%

86.66%

76.60%

63.59%

52.39%

41.61%

30.50%

18.20%

10.32%
100.00%
3%
TIME SCEDULE PEK
Nama Proyek : Pembuatan Rumah Tinggal Jumlah Hari Kerja
Anggaran : Rp 339.273.463,00
Lokasi : Ketileng Indah Blok O/69

JUMLAH BOBOT
NO. URAIAN PEKERJAAN
HARGA (Rp.) (%)

I PEK. PERSIAPAN 7,501,100.00 2.24%

II PEK. GALIAN PONDASI 15,750,600.00 4.70%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.51%

IV PEK. SLOOF DAN KOLOM 45,006,600.00 13.42%

V PEK. DINDING DAN KOSEN 25,950,000.00 7.74%

VI PEK. RING BALK 15,450,700.00 4.61%

VII PEK. KAP & ATAP 75,011,000.00 22.37%

VIII PEK. PLAFON 12,765,100.00 3.81%

IX PEK. PLESTERAN 7,686,713.00 2.29%

X PEK. LANTAI 11,251,650.00 3.36%

XI PEK. PINTU & JENDELA 16,369,850.00 4.88%

XII PEK. PENGECATAN 8,250,000.00 2.46%

XIII PEK. FINISHING DALAM 30,004,400.00 8.95%

XIV PEK. FINISHING LUAR 20,500,000.00 6.11%

XV PEK. TAMAN 8,525,000.00 2.54%

JUMLAH NILAI PEKERJAAN 335,273,463.00 100%


KEMAJUAN MINGGU
RENCANA
KOMULATIF KEMAJUAN

150022
TIME SCEDULE PEKERJAAN RUMAH TINGGAL
Jumlah Hari Kerja : 90 Hari Kerja

AGUSTUS MINGGU KE- SEPTEMBER MINGGU KE- OKTOBER MINGGU KE-


1 2 3 4 1 2 3 4 1 2

2.24%

2.35% 2.35%

3.50% 3.50% 3.50%

4.47% 4.47% 4.47%

3.87% 3.87%

2.30% 2.30%

7.46% 7.46% 7.46%

1.27% 1.27% 1.27%

2.29%

1.68%

2.44% 2.44%

2.98%

2.04%

2.24% 2.35% 5.85% 7.98% 11.85% 10.65% 12.05% 11.17% 11.17% 7.97%
2.24% 4.59% 10.44% 18.42% 30.27% 40.92% 52.97% 64.14% 75.31% 83.28%
KTOBER MINGGU KE- PROSENT
3 4 ASE (%)
100%

75%

50%

1.68%

2.46% 25%

2.98% 2.98%

2.04% 2.04%

2.54%
0%

9.16% 7.56%
92.44% 100.00%
TIME SCEDULE PEKERJAAN RUMAH TINGGAL

JUMLAH HARGA BOBOT APRIL MINGGU KE-


NO. URAIAN PEKERJAAN (Rp.) (%) 1 2 3

I PEK. PERSIAPAN 7,502,700.00 2.21% 1.11% 1.11%

II PEK. GALIAN PONDASI 15,750,600.00 4.64% 2.32% 2.32%

III PEK. PASANGAN PONDASI BATU 35,250,750.00 10.39% 3.46%

IV PEK. SLOOF DAN KOLOM 45,016,200.00 13.27%

V PEK. DINDING DAN KOLOM 29,950,000.00 8.83%

VI PEK. RING BALK 15,450,700.00 4.55%

VII PEK. KAP & ATAP 75,027,000.00 22.11%

VIII PEK. PLAFON 12,765,100.00 3.76%

IX PEK. PLESTERAN 7,686,713.00 2.27%

X PEK. LANTAI 11,254,050.00 3.32%

XI PEK. PINTU & JENDELA 16,369,850.00 4.82%

XII PEK. PENGECATAN 8,250,000.00 2.43%


18.20%
XIII PEK. FINISHING DALAM 30,010,800.00 8.84%

10.32%
XIV PEK. FINISHING LUAR 20,500,000.00 6.04%
4.53%
XV PEK. TAMAN 8,525,000.00 2.51% 1.11%

JUMLAH NILAI PEKERJAAN 339,309,463.00 100% 1.11% 3.43% 5.78%


KEMAJUAN MINGGU 1.11% 4.53% 10.32%
RENCANA
KOMULATIF KEMAJUAN
INGGU KE- MEI MINGGU KE- JUNI MINGGU KE-
PROSENT
4 1 2 3 4 1 2 3 4 ASE (%)
100.00%
96.73%

86.66%
3.46% 3.46%

4.42% 4.42% 4.42% 76.60%

2.21% 2.21% 2.21% 2.21%

2.28% 2.28% 63.59%

7.37% 7.37% 7.37%


52.39%
1.25% 1.25% 1.25%

0.57% 0.57% 0.57% 0.57%


41.61%

0.83% 0.83% 0.83% 0.83%

30.50%
2.41% 2.41%

0.61% 0.61% 0.61% 0.61%


18.20%
2.95% 2.95% 2.95%

10.32%
2.01% 2.01% 2.01%

0.63% 0.63% 0.63% 0.63%

7.89% 10.09% 8.91% 12.42% 12.83% 14.20% 11.26% 9.44% 2.64%


18.20% 28.29% 37.20% 49.62% 62.45% 76.66% 87.92% 97.36% 100.00%
TIME SCEDULE PEKERJAAN KAMAR KOS
NAMA : Muchammad Ichwan Nama Pekerjaan : Pembuatan Kamar Kos
NIM : C.111.15.0026 Lokasi Proyek : JL. Pedurungan Raya No 17
TUGAS : Tugas Besar Majemen Konstruksi Jumlah Hari Kerja : 90 Hari Kerja
JUMLAH BOBOT SEPTEMBER MINGGU KE- OKTOBER MINGGU KE- NOPEMBER MINGGU KE- PROSENTASE
NO. URAIAN PEKERJAAN
HARGA (Rp.) (%) 1 2 3 4 1 2 3 4 1 2 3 4 (%)
100%
I PEK. PERSIAPAN 7,501,300.00 2.24% 2.24%

II PEK. GALIAN PONDASI 15,750,600.00 4.70% 2.35% 2.35%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.51% 3.50% 3.50% 3.50%

IV PEK. SLOOF DAN KOLOM 45,007,800.00 13.42% 4.47% 4.47% 4.47% 75%

V PEK. RING BALK 15,450,700.00 4.61% 2.30% 2.30%

VI PEK. DINDING DAN KOSEN 25,950,000.00 7.74% 3.87% 3.87%

VII PEK. KAP & ATAP 75,013,000.00 22.37% 7.46% 7.46% 7.46%

VIII PEK. PLAFON 12,765,100.00 3.81% 1.27% 1.27% 1.27% 50%

IX PEK. PLESTERAN 7,686,713.00 2.29% 2.29%

X PEK. LANTAI 11,251,950.00 3.36% 1.68% 1.68%

XI PEK. PINTU & JENDELA 16,369,850.00 4.88% 2.44% 2.44%

XII PEK. PENGECATAN 8,250,000.00 2.46% 2.46% 25%

XIII PEK. FINISHING DALAM 30,005,200.00 8.95% 2.98% 2.98% 2.98%

XIV PEK. FINISHING LUAR 20,500,000.00 6.11% 3.06% 3.06%

XV PEK. TAMAN 8,525,000.00 2.54% 2.54%


0%
JUMLAH NILAI PEKERJAAN (Rp.) 335,277,963.00 100%
KEMAJUAN MINGGU 2.24% 2.35% 5.85% 7.98% 10.28% 10.65% 11.33% 9.90% 11.17% 11.28% 11.45% 5.53%
RENCANA
KOMULATIF KEMAJUAN 2.24% 4.59% 10.44% 18.42% 28.70% 39.35% 50.68% 60.58% 71.75% 83.03% 94.47% 100.00%

NIM 150026
TIME SCEDULE PEK
NAMA : Vernando Nirvan Maulana Nama Pekerjaan
NIM : C.111.15.0024 Lokasi Proyek
TUGAS : Tugas Besar Majemen Konstruksi Jumlah Hari Kerja
JUMLAH BOBOT
NO. URAIAN PEKERJAAN
HARGA (Rp.) (%)

I PEK. PERSIAPAN 7,501,200.00 2.21%

II PEK. GALIAN PONDASI 15,750,600.00 4.64%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.39%

IV PEK. SLOOF DAN KOLOM 45,007,200.00 13.27%

V PEK. RING BALK 15,450,700.00 4.55%

VI PEK. DINDING DAN KOSEN 29,950,000.00 8.83%

VII PEK. KAP & ATAP 75,012,000.00 22.11%

VIII PEK. PLAFON 12,765,100.00 3.76%

IX PEK. PLESTERAN 7,686,713.00 2.27%

X PEK. LANTAI 11,251,800.00 3.32%

XI PEK. PINTU & JENDELA 16,369,850.00 4.82%

XII PEK. PENGECATAN 8,250,000.00 2.43%

XIII PEK. FINISHING DALAM 30,004,800.00 8.84%

XIV PEK. FINISHING LUAR 20,500,000.00 6.04%

XV PEK. TAMAN 8,525,000.00 2.51%

JUMLAH NILAI PEKERJAAN (Rp.) 339,275,713.00 100%


KEMAJUAN MINGGU
RENCANA
KOMULATIF KEMAJUAN
NIM 150024
TIME SCEDULE PEKERJAAN RUMAH TINGGAL
: Pembuatan Rumah Tinggal
: Jl. Sriwijaya Raya No 05 Semarang
: 90 Hari Kerja
APRIL MINGGU KE- MEI MINGGU KE- JUNI MINGGU KE-
1 2 3 4 1 2 3 4 1 2

1.11% 1.11%

2.32% 2.32%

3.46% 3.46% 3.46%

4.42% 4.42% 4.42%

2.28% 2.28%

4.41% 4.41%

7.37% 7.37% 7.37%

1.88% 1.88%

1.13%

1.66%

2.41% 2.41%

2.95%

3.02%

1.11% 3.43% 5.78% 7.89% 10.16% 11.11% 11.78% 9.78% 11.66% 10.64%
1.11% 4.53% 10.32% 18.20% 28.36% 39.48% 51.26% 61.04% 72.71% 83.35%
PROSE
JUNI MINGGU KE- NTASE
3 4 (%)
100%

75%

50%

1.13%

1.66%

2.43% 25%

2.95% 2.95%

3.02%

1.26% 1.26%
0%

12.45% 4.20%
95.80% 100.00%
TIME SCEDULE PEKERJAAN RUMAH TINGGAL
NAMA : Ramadhendy Putra Nama Pekerjaan : Pembuatan Rumah Tinggal
NIM : C.111.15.0051 Lokasi Proyek : JL. Kalilangse No 69
TUGAS : Tugas Besar Majemen Konstruksi Jumlah Hari Kerja : 90 Hari Kerja
JUMLAH JANUARI MINGGU KE-
NO. URAIAN PEKERJAAN BOBOT (%)
HARGA (Rp.) 1 2 3 4

I PEK. PERSIAPAN 7,502,550.00 2.21% 1.11% 1.11%

II PEK. GALIAN PONDASI 15,750,600.00 4.64% 2.32% 2.32%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.39% 3.46% 3.46%

IV PEK. SLOOF DAN KOLOM 45,015,300.00 13.27% 4.42%

V PEK. RING BALK 15,450,700.00 4.55%

VI PEK. DINDING DAN KOSEN 29,950,000.00 8.83%

VII PEK. KAP & ATAP 75,025,500.00 22.11%

VIII PEK. PLAFON 12,765,100.00 3.76%

IX PEK. PLESTERAN 7,686,713.00 2.27%

X PEK. LANTAI 11,253,825.00 3.32%

XI PEK. PINTU & JENDELA 16,369,850.00 4.82%

XII PEK. PENGECATAN 8,250,000.00 2.43%


XIII PEK. FINISHING DALAM 30,010,200.00 8.84%

XIV PEK. FINISHING LUAR 20,500,000.00 6.04%

XV PEK. TAMAN 8,525,000.00 2.51%

JUMLAH NILAI PEKERJAAN (Rp.) 339,306,088.00 100%


KEMAJUAN MINGGU 1.11% 3.43% 5.78% 7.89%
RENCANA
KOMULATIF KEMAJUAN 1.11% 4.53% 10.32% 18.20%

NIM 150051
LE PEKERJAAN RUMAH TINGGAL

FEBRUARI MINGGU KE- MARET MINGGU KE- PROSENTASE


1 2 3 4 1 2 3 4 (%)
100%

3.46%

4.42% 4.42%
75%
2.28% 2.28%

4.41% 4.41%

7.37% 7.37% 7.37%

1.88% 1.88%
50%
2.27%

1.66% 1.66%

2.41% 2.41%

1.22% 1.22%
25%
2.95% 2.95% 2.95%

3.02% 3.02%

2.51%
0%

7.89% 6.70% 6.69% 14.20% 12.05% 15.07% 10.72% 8.48%


26.09% 32.79% 39.48% 53.67% 65.72% 80.79% 91.52% 100.00%
TIME SCEDULE PEKE
NAMA : Nunuk Sarah Z Nama Pekerjaan
NIM : C.111.15.0013 Lokasi Proyek
TUGAS : Tugas Besar Majemen Konstruksi Jumlah Hari Kerja
JUMLAH BOBOT
NO. URAIAN PEKERJAAN
HARGA (Rp.) (%)

I PEK. PERSIAPAN 7,500,650.00 2.24%

II PEK. GALIAN PONDASI 15,750,600.00 4.70%

III PEK. PASANGAN PONDASI BATU KALI 35,250,750.00 10.51%

IV PEK. SLOOF DAN KOLOM 45,003,900.00 13.42%

V PEK. RING BALK 15,450,700.00 4.61%

VI PEK. DINDING DAN KOSEN 25,950,000.00 7.74%

VII PEK. KAP & ATAP 75,006,500.00 22.37%

VIII PEK. PLAFON 12,765,100.00 3.81%

IX PEK. PLESTERAN 7,686,713.00 2.29%

X PEK. LANTAI 11,250,975.00 3.36%

XI PEK. PINTU & JENDELA 16,369,850.00 4.88%

XII PEK. PENGECATAN 8,250,000.00 2.46%

XIII PEK. FINISHING DALAM 30,002,600.00 8.95%

XIV PEK. FINISHING LUAR 20,500,000.00 6.11%

XV PEK. TAMAN 8,525,000.00 2.54%

JUMLAH NILAI PEKERJAAN (Rp.) 335,263,338.00 100%


KEMAJUAN MINGGU
RENCANA
KOMULATIF KEMAJUAN
NIM 150013
TIME SCEDULE PEKERJAAN RUMAH TINGGAL
: Pembuatan Rumah Tinggal
: Jl. Seruni IV No 70 Tlogosai, Semarang
: 90 Hari Kerja
JUNI MINGGU KE- JULI MINGGU KE- AGUSTUS MINGGU KE-
1 2 3 4 1 2 3 4 1 2

2.24%

2.35% 2.35%

3.50% 3.50% 3.50%

4.47% 4.47% 4.47%

2.30% 2.30%

3.87% 3.87%

7.46% 7.46% 7.46%

1.27% 1.27% 1.27%

2.29%

1.68%

2.44% 2.44%

2.98%

2.04%

2.24% 2.35% 5.85% 7.98% 10.28% 10.65% 11.33% 13.46% 11.17% 7.97%
2.24% 4.59% 10.44% 18.42% 28.70% 39.35% 50.68% 64.14% 75.31% 83.28%
PROSE
GUSTUS MINGGU KE- NTASE
3 4 (%)
100%

75%

50%

1.68%

2.46% 25%

2.98% 2.98%

2.04% 2.04%

2.54%
0%

9.16% 7.56%
92.44% 100.00%