NAMA PAKET : PROYEK PEMBANGUNAN JALAN TOL PEKANBARU - DUMAI BUKU HARIAN STANDARD
SEKSI :2 TANGGAL : 9-Apr-18
HARI KE :
A. PEKERJAAN C. MATERIAL
NO URAIAN LOKASI VOL SAT JUM MP NO JENIS SAT. CACAH/VOLUME KETERANGAN CUACA
Pekdum 12.00 AM
1 Bobok Pancang STA 27+200 5,00 bh 1 1 Playwood Finolite 12 mm lbr 18 1.00 AM
2 Barak Pekerja STA 27+200 1,00 bh 8 2 Kayu kaso m3 1 2.00 AM
3 Seng 7 kaki lbr 60 3.00 AM
4 Paku kg 10 4.00 AM
5 Playwood 3mm lbr 35 5.00 AM
6.00 AM
7.00 AM
8.00 AM
9.00 AM
10.00 AM
11.00 AM
12.00 PM
1.00 PM
2.00 PM
3.00 PM
D. PEMAKAIAN PERALATAN 4.00 PM
5.00 PM
NO. JENIS SAT CACAH/VOLUME KETERANGAN
6.00 PM
7.00 PM
1 Genset unit 1 Baik 8.00 PM
2 Gerinda unit 2 Baik 9.00 PM
3 Pahat Beton bh 2 Baik 10.00 PM
B. RENCANA PEKERJAAN TANGGAL : 10 April 2018 4 Bodem bh 4 Baik 11.00 PM
5 Gergaji bh 2 Baik
NO URAIAN LOKASI VOL SAT JUM MP
6 Palu bh 4 Baik
7 Meteran bh 2 Baik CLEAR
1 Melanjutkan Bobok Pancang+Potong besi pancang STA 27+200 8,0 tiang 1
2 Melanjutkan Pembuatan barak Pekerja STA 27+200 1,0 unit 4 RAIN
3 Pabrikasi pembesian untuk P2 Kantor HKI 50 btg 4
1 STA 27+200 Tanah Longsor di pekerjaan P1 ( pier 1 ) HKI Belum ada perbaikan
F. PERSONIL CGAA
1 Untuk pekerjaan Dinding P2 ( Pier 2 ) Belum bisa dikerjakan karena masih menunggu batu mangga dan tanah yang longsor pun belum ada perbaikan dari pihak HKI
2 Rencana besok kita mulai Pabrikasi Pembesian Untuk Pekerjaan P2 di kantor HKI
…………………… …………………………………………
Pelaksana Lapangan