Anda di halaman 1dari 2

ENGINEER'S ESTIMATE (EE)

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL


LOKASI : JAKARTA
TAHUN : 2017

PEKERJAAN STRUKTUR
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN LANTAI I
A PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi Foot Plat 123.48 M3 25,000.00 3,087,000.00
2 Pek. Galian Tanah Sloof 7.46 M3 25,000.00 186,600.00
3 Pek. Urugan Pasir Bawah Foot Plat T.5cm 1.27 M3 150,000.00 190,500.00
4 Pek. Lantai Kerja Foot Plat T.5cm Adk. 1:3:5 1.27 M3 800,000.00 1,016,000.00

JUMLAH 4,480,100.00

B PEKERJAAN PONDASI
1 Pek. Beton Pondasi Foot Plat K-250 7.62 M3 3,500,000.00 26,670,000.00
2 Pek. Pedestal Kolom 40x40 K-250 3.66 M3 3,500,000.00 12,796,875.00

JUMLAH 39,466,875.00

C PEKERJAAN BETON BERTULANG


1 Pek. Sloof 15x40 K-250 7.76 M3 3,500,000.00 27,174,000.00
2 Pek. Kolom Struktur K-250 7.82 M3 3,500,000.00 27,385,312.50
3 Pek. Kolom Praktis K-175 1.68 M3 2,500,000.00 4,207,775.00
4 Pek. Plat Lantai Ram t.10cm 4.29 M3 3,000,000.00 12,870,750.00
5 Pek. Plat Beton Meja Wastafel 0.27 M3 3,000,000.00 812,250.00

JUMLAH 72,450,087.50

D PEKERJAAN KANOPI ENTRANCE


1 Pek. Balok Baja IWF 200.150.6.9 596.70 Kg 22,000.00 13,127,400.00
2 Pek. Base Plat t.15mm 25.25 M2 22,000.00 555,390.00
3 Pek. Angkur D-19 L-60 cm 88.00 Bh 50,000.00 4,400,000.00
4 Pek. Perakitan 596.70 Kg 750.00 447,525.00
5 Pek. Zincromate 20.09 M2 22,500.00 452,047.50
6 Pek. Pengecatan 20.09 M2 23,000.00 462,093.00
7 Pek. Bekisting Boundeck 8.69 M2 3,500,000.00 30,397,500.00
8 Pek. Plat Beton t.10cm 0.87 M3 3,000,000.00 2,605,500.00

JUMLAH 52,447,455.50
TOTAL PEKERJAAN LANTAI I 168,844,518.00

II PEKERJAAN LANTAI II
A PEKERJAAN BETON BERTULANG
1 Pek. Kolom Struktur K-250 5.63 M3 3,500,000.00 19,707,187.50
2 Pek. Kolom Praktis K-175 1.16 M3 2,500,000.00 2,911,562.50
3 Pek. Balok K-250 10.29 M3 3,500,000.00 36,003,450.00
4 Pek. Plat Beton Lantai K-250 14.67 M3 3,000,000.00 44,010,000.00
5 Pek. Dak Beton t.10cm K-175 1.84 M3 2,500,000.00 4,606,100.00

JUMLAH 107,238,300.00
PEKERJAAN STRUKTUR
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6

B SUNSCREEN
1 Pek. Finishing Plat 4.40 M1 150,000.00 660,000.00
2 Pek. Balok 20/30 K-250 0.25 M3 3,500,000.00 873,600.00
3 Pek. Balok 11/15 K-175 0.04 M3 2,500,000.00 90,750.00
4 Pek. Plat Beton t.10cm K-175 0.22 M3 2,500,000.00 550,000.00

JUMLAH 2,174,350.00
TOTAL PEKERJAAN LANTAI II 109,412,650.00

III PEKERJAAN LANTAI III


A PEKERJAAN BETON BERTULANG
1 Pek. Kolom Struktur K-250 4.39 M3 3,500,000.00 15,356,250.00
2 Pek. Kolom Praktis K-175 0.51 M3 2,500,000.00 1,278,062.50
3 Pek. Balok K-250 9.55 M3 3,500,000.00 33,438,300.00
4 Pek. Plat Beton Lantai K-250 14.09 M3 3,000,000.00 42,256,368.00

JUMLAH 92,328,980.50

B SUNSCREEN
1 Pek. Finishing Plat 10.13 M1 150,000.00 1,519,500.00
2 Pek. Balok 20/30 K-250 0.61 M3 3,500,000.00 2,127,300.00
3 Pek. Balok 11/15 K-175 0.08 M3 2,500,000.00 210,375.00
4 Pek. Plat Beton t.10cm K-175 0.79 M3 2,500,000.00 1,970,000.00

JUMLAH 5,827,175.00
TOTAL PEKERJAAN LANTAI III 98,156,155.50

IV PEKERJAAN TOP FLOOR


1 Pek. Kolom Struktur K-250 1.90 M3 3,500,000.00 6,654,375.00
2 Pek. Kolom Praktis K-175 0.20 M3 2,500,000.00 511,225.00
3 Pek. Balok K-250 5.83 M3 3,500,000.00 20,405,700.00
4 Pek. Plat Beton T.12cm K-250 1.24 M3 3,000,000.00 3,726,000.00
5 Pek. Dak Beton t.10cm K-175 1.30 M3 2,500,000.00 3,241,575.00

TOTAL PEKERJAAN TOP FLOOR 34,538,875.00

V PEKERJAAN TANGGA
1 Pek. Galian Tanah Pondasi Tangga 4.78 M3 25,000.00 119,531.25
2 Pek. Urugan Tanah Kembali 1.59 M3 50,000.00 79,687.50
3 Pek. Urugan Pasir Bawah Pondasi Tangga 0.09 M3 150,000.00 12,937.50
4 Pek. Beton Foot Plat Tangga K-250 0.47 M3 3,500,000.00 1,651,125.00
5 Pek. Pedestal Tangga K-250 2.40 M3 3,500,000.00 8,402,187.50
6 Pek. Balok 15/30 K-250 1.50 M3 3,500,000.00 5,240,340.00
7 Pek. Beton Tangga K-250 3.09 M3 3,500,000.00 10,824,953.13

TOTAL PEKERJAAN TANGGA 26,330,761.88

VI PEKERJAAN ATAP
1 Pas. Rangka Atap Baja Ringan dan Penutup Atap 73.43 M2 160,000.00 11,748,640.00
2 Pas. Bubungan Metal Pasir 7.70 M1 30,000.00 231,000.00
3 Pas. Lisplank Wood Plank 7.70 M1 45,000.00 346,500.00

JUMLAH 12,326,140.00
TOTAL PEKERJAAN ATAP 148,069,551.88
TOTAL PEKERJAAN STRUKTUR 585,352,512.25