A. DATA TANAH
Kapasitas nominal tiang pancang secara empiris dari nilai N hasil pengujian SPT
menurut Meyerhoff dinyatakan dengan rumus :
2
Pn =E* Nb * Ab + Ns* As E 200 Lempung (kN/m )
dan harus
2
Pn = 380 * Ň * Ab 400 Pasir (kN/m )
Nb = nilai SPT di sekitar dasar tiang, dihitung dari 8.D di atas dasar tiang s.d 4.D di bawah
dasar tiang, (kN)
Ň = nilai SPT rata-rata di sepanjang tiang, Ns 10N Lempung (kN)
2
Ab = luas dasar tiang (m ) 2.N Pasir
2
As = luas selimut tiang (m )
Tahanan lateral tiang (H) kategori tiang panjang, dapat dihitung dengan persamaan :
H = yo * kh * D / [ 2 * β * ( e * β + 1 ) ]
dengan, β = [ kh * D / ( 4 * Ec * Ic ) ]
0.25
3 2
Kuat lentur beton tiang pancang, fb = 0.40 * fc' * 10 = 8300 kN/m
3
Tahanan momen, W = Ic / (D/2) = 0,05027 m
Momen maksimum, My = fb * W = 417,20 kNm
Kohesi tanah rata-rata di sepanjang tiang
No Kedalaman L1 cu cu * L1 L1 cu * L1
z1 (m) z2 (m) 2
(m) (kN/m ) (m)
1 0,00 2,00 2,0 13,50 27,00 0,0 0,00
2 2,00 4,00 2,0 27,00 54,00 2,0 54,00
3 4,00 6,00 2,0 45,00 90,00 4,0 144,00
4 6,00 8,00 2,0 63,00 126,00 6,0 270,00
5 8,00 10,00 2,0 135,00 270,00 8,0 540,00
6 10,00 12,00 2,0 202,50 405,00 10,0 945,00
7 12,00 14,00 2,0 270,00 540,00 12,0 1485,00
8 14,00 16,00 2,0 270,00 540,00 14,0 2025,00
9 16,00 18,00 2,0 270,00 540,00 16,0 2565,00
10 18,00 20,00 2,0 270,00 540,00 18,0 3105,00
11 20,00 22,00 2,0 270,00 540,00 20,0 3645,00
12 22,00 24,00 2,0 270,00 540,00 22,0 4185,00
13 24,00 26,00 2,0 270,00 540,00 24,0 4725,00
14 26,00 28,00 2,0 270,00 540,00 26,0 5265,00
15 28,00 30,00 2,0 270,00 540,00 28,0 5805,00
16 30,00 32,00 2,0 270,00 540,00 30,0 6345,00
17 32,00 34,00 2,0 270,00 540,00 32,0 6885,00
18 34,00 36,00 2,0 270,00 540,00 34,0 7425,00
19 36,00 38,00 2,0 270,00 540,00 36,0 7965,00
20 38,00 40,00 2,0 270,00 540,00 38,0 8505,00
21 40,00 42,00 2,0 270,00 540,00 40,0 9045,00
22 42,00 44,00 2,0 270,00 540,00 42,0 9585,00
23 44,00 46,00 2,0 270,00 540,00 44,0 10125,00
24 46,00 48,00 2,0 270,00 540,00 46,0 10665,00
25 48,00 50,00 2,0 270,00 540,00 48,0 11205,00
Σ L1 = 14,00 Σcu*L1 = 2025,00
2
Kohesi tanah rata-rata, ču = Σ [ cu * L1 ] / Σ L1 = 144,6428571 kN/m
f = Hn / [ 9 * ču * D ] pers.(1)
g = L - ( f + 1.5 * D ) pers.(2)
My = Hn * ( e + 1.5 * D + 0.5 * f ) pers.(3)
2
My = 9 / 4 * D * ču * g pers.(4)