Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
0 Master Schedule NWP Design and Build Kompleks Wed 17/10/18 Wed 15/05/19 209,87 days 211 days 0 0 0 25/02/19
Pergudangan dan Open Yard PIER Pasuruan_R1 - Updt 25 Feb
1 Start Mon 25/02/19 Mon 25/02/19 0 days 0 days 0 0 0 25/02
2 PEKERJAAN PERSIAPAN Wed 17/10/18 Tue 14/05/19 208 days 210 days 0 0 0
13 Pembuatan Design Struktur Bangunan Subkontraktor Wed 17/10/18 Sun 21/10/18 5 days 5 days 1 0 1 Subkontraktor
14 Submit Mon 22/10/18 Mon 22/10/18 1 day 1 day 1 0 1
17 Pembuatan Design Struktur Bangunan Subkontraktor Wed 17/10/18 Mon 05/11/18 20 days 20 days 1 0 1 Subkontraktor
18 Submit Tue 06/11/18 Thu 08/11/18 3 days 3 days 1 0 1
21 Pembuatan Design Struktur Bangunan Subkontraktor Wed 17/10/18 Mon 05/11/18 20 days 20 days 1 0 1 Subkontraktor
22 Submit Tue 06/11/18 Thu 08/11/18 3 days 3 days 1 0 1
25 Pembuatan Design Subkontraktor Wed 17/10/18 Mon 05/11/18 20 days 20 days 1 0 1 Subkontraktor
26 Submit Tue 06/11/18 Thu 08/11/18 3 days 3 days 1 0 1
39 Fabrikasi Baja Subkontraktor Fri 21/12/18 Tue 29/01/19 40 days 40 days 1 0 1 Subkontraktor
40 Material On Site Subkontraktor;Crane Wed 30/01/19 Tue 05/02/19 7 days 7 days 1 0 1 Subkontraktor;Crane
41 Kanopi Tue 26/02/19 Thu 14/03/19 17 days 17 days 0 0 0
43 Fabrikasi Kanopi Subkontraktor Fri 01/03/19 Thu 14/03/19 14 days 14 days 1 0 0 Subkontraktor
44 Material On Site Subkontraktor Fri 08/03/19 Thu 14/03/19 7 days 7 days 1 0 0 Subkontraktor
45 Arsitektur Wed 06/02/19 Sat 20/04/19 57 days 74 days 0 0 0
48 Material On Site Subkontraktor;Pekerja Tue 26/02/19 Mon 04/03/19 7 days 7 days 1 0 0 Subkontraktor;Pekerja
49 Cat Interior Tue 05/03/19 Thu 14/03/19 10 days 10 days 0 0 0
51 Material On Site Alat bantu[1];Pekerja Fri 08/03/19 Thu 14/03/19 7 days 7 days 1 0 0 Alat bantu[1];Pekerja
52 Cat Eksterior Tue 05/03/19 Thu 14/03/19 10 days 10 days 0 0 0
54 Material On Site Alat bantu[1];Pekerja Fri 08/03/19 Thu 14/03/19 7 days 7 days 1 0 0 Alat bantu[1];Pekerja
55 Plafond Fri 08/03/19 Sun 17/03/19 10 days 10 days 0 0 0
57 Material On Site Alat bantu[1];Pekerja Mon 11/03/19 Sun 17/03/19 7 days 7 days 1 0 0 Alat bantu[1];Pekerja
58 List gypsum Fri 08/03/19 Sun 17/03/19 10 days 10 days 0 0 0
60 Material On Site Pekerja;Alat bantu[1] Mon 11/03/19 Sun 17/03/19 7 days 7 days 1 0 0 Pekerja;Alat bantu[1]
61 Floorhardener Sat 23/02/19 Sat 02/03/19 10 days 8 days 0 0 0
63 Material On Site Alat bantu[1];Pekerja Sun 24/02/19 Sat 02/03/19 7 days 7 days 1 0 0,5 Alat bantu[1];Pekerja
64 Rak Tue 26/02/19 Wed 06/03/19 9 days 9 days 0 0 0
66 Material On Site Alat bantu[1];Pekerja Thu 28/02/19 Wed 06/03/19 7 days 7 days 1 0 0 Alat bantu[1];Pekerja
67 Kusen, Daun Pintu dan Jendela Tue 26/02/19 Sun 03/03/19 6 days 6 days 0 0 0
69 Material On Site Alat bantu[1];Pekerja Fri 01/03/19 Sun 03/03/19 3 days 3 days 1 0 0 Alat bantu[1];Pekerja
70 Lavatory Gudang Thu 11/04/19 Sat 20/04/19 10 days 10 days 0 0 0
72 Material On Site Alat bantu[1];Pekerja Sun 14/04/19 Sat 20/04/19 7 days 7 days 1 0 0 Alat bantu[1];Pekerja
73 Clading Metal Thu 11/04/19 Sat 20/04/19 10 days 10 days 0 0 0
75 Material On Site Pekerja[2];Alat bantu[1] Sun 14/04/19 Sat 20/04/19 7 days 7 days 1 0 0 Pekerja[2];Alat bantu[1]
76 Construction Sat 10/11/18 Mon 13/05/19 185,2 days 185 days 0 0 0
77 PEKERJAAN STRUKTUR Sat 10/11/18 Sat 27/04/19 184,2 days 169 days 0 0 0
78 II.1. Pekerjaan Struktur Bangunan Gudang Sat 10/11/18 Sun 17/03/19 140,2 days 128 days 0 0 0
Page 1
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
79 Pekerjaan pemancangan pondasi mini pile 25 Sat 10/11/18 Sun 16/12/18 35 days 37 days 0 0 0 25/02/19
x 25 cm, K500
80 - Pengadaan mini pile 25 x 25 cm, K500 Subkontraktor;Crane;Pekerja[2] Sat 10/11/18 Fri 16/11/18 7 days 7 days 2076 0 2076 Subkontraktor;Crane;Pekerja[2]
81 - Pekerjaan pemancangan precast pile Alat Pancang[2];Alat bantu[1] Sat 17/11/18 Sun 16/12/18 28 days 30 days 2076 0 2076 Alat Pancang[2];Alat bantu[1]
82 - Pecah kepala pancang Tukang Batu[2];Jack Hammer[2];Pekerja[2];Alat
Mon 10/12/18 bantu[1]
Sun 16/12/18 7 days 7 days 346 0 346 Tukang Batu[2];Jack Hammer[2];Pekerja[2];Alat bantu[1]
83 Test PDA (Pile Driving Analysis) Test PDA Sun 16/12/18 Mon 17/12/18 2 days 2 days 4 0 4 Test PDA
84 Pilecap Tue 18/12/18 Fri 01/03/19 27 days 74 days 0 0 0
85 Pekerjaan galian tanah pondasi pile cap Alat bantu[1];Pekerja[6] Tue 18/12/18 Fri 21/12/18 4 days 4 days 184,53 0 184,53 Alat bantu[1];Pekerja[6]
86 Pekerjaan urugan pasir bawah pondasi pile Alat bantu[1];Pekerja[2] Sun 23/12/18 Tue 25/12/18 3 days 3 days 11,38 0 11,38 Alat bantu[1];Pekerja[2]
cap
87 Pekerjaan lantai kerja bawah pondasi pile Alat Wed 27/02/19 Fri 01/03/19 3 days 3 days 36,3 0 36,3 Alat bantu[1];Pekerja[2];Tukang Batu
cap bantu[1];Pekerja[2];Tukang
88 Urugan kembali galian tanah pondasi pile Alat Thu 14/02/19 Fri 15/02/19 2 days 2 days 22,75 0 22,75 Alat bantu[1];Pekerja[2];Stamper;Tukang Batu
cap bantu[1];Pekerja[2];Stamper;Tukang
89 Pekerjaan urugan sirtu padat, t = 20 cm Alat bantu[1];Pekerja[10] Mon 11/02/19 Sun 24/02/19 7 days 14 days 3525,28 0 3525,28 Alat bantu[1];Pekerja[10]
90 Pekerjaan lantai kerja, t = 10 cm Alat bantu[1];Tukang Batu[5];Pekerja[10];Mandor
Wed 20/02/19 Sat 02/03/19 7 days 7 days 1762,64 0 1268 Alat bantu[1];Tukang Batu[5];Pekerja[10];Mandor
91 Pekerjaan urugan tanah peninggian lantai Alat Mon 11/02/19 Sun 24/02/19 14 days 14 days 15863,76 0 15863,76 Alat bantu[1];Pekerja[15];Mandor;Stamper[4];Tukang Batu[4]
bantu[1];Pekerja[15];Mandor;Stamper[4];Tukang
92 Pekerjaan pemadatan tanah urugan Alat bantu[1];Pekerja;Tukang Tue 12/02/19 Mon 25/02/19 14 days 14 days 15863,76 0 15863,76 Alat bantu[1];Pekerja;Tukang Batu;Stamper
Batu;Stamper
93 Pekerjaan pilecap type P1 Thu 24/01/19 Sun 10/03/19 15 days 46 days 0 0 0
106 Pekerjaan galian tanah sloof Alat bantu[1];Pekerja[3] Mon 11/02/19 Sun 17/02/19 7 days 7 days 61,51 0 61,51 Alat bantu[1];Pekerja[3]
107 Pekerjaan urugan pasir bawah sloof Alat bantu[1];Pekerja[2] Thu 14/02/19 Wed 20/02/19 7 days 7 days 6,6 0 6,6 Alat bantu[1];Pekerja[2]
108 Pekerjaan lantai kerja bawah sloof Alat Sun 17/02/19 Sat 23/02/19 7 days 7 days 3,3 0 3,3 Alat bantu[1];Pekerja[2];Tukang Batu
bantu[1];Pekerja[2];Tukang
109 Urugan Kembali galian tanah sloof Alat Mon 18/02/19 Sun 24/02/19 7 days 7 days 12,1 0 12,1 Alat bantu[1];Pekerja[2];Stamper;Tukang Batu
bantu[1];Pekerja[2];Stamper;Tukang
110 Pekerjaan kolom tipe K1 Wed 13/02/19 Wed 20/02/19 10 days 8 days 0 0 0
119 Pekerjaan galian pondasi batu belah 1 : 5 Alat Fri 15/02/19 Mon 18/02/19 3 days 4 days 926,18 0 926,18 Alat bantu[1];Pekerja[20];Mandor[2];Tukang Batu[5]
bantu[1];Pekerja[20];Mandor[2];Tukang
120 Pekerjaan urugan sirtu bawah pondasi batu Alat bantu[1];Pekerja[5] Tue 19/02/19 Tue 26/02/19 3 days 3 days 485,88 0 433,69 Alat bantu[1];Pekerja[5]
belah
121 Pekerjaan pondasi batu belah 1 : 5 Pekerja[30];Alat Fri 22/02/19 Wed 27/02/19 3 days 3 days 1898,24 0 1694,7 Pekerja[30];Alat bantu[1];Tukang Batu[15];Mandor[2]
bantu[1];Tukang
122 Urugan kembali galian tanah pondasi batu Alat Mon 25/02/19 Fri 01/03/19 3 days 3 days 308,73 0 276,1 Alat bantu[1];Pekerja[8];Mandor;Stamper[2];Tukang Batu[2]
belah bantu[1];Pekerja[8];Mandor;Stamper[2];Tukang
123 Pekerjaan plat dasar, t = 20 cm Fri 22/02/19 Mon 11/03/19 21 days 18 days 0 0 0
128 - Pembesian Ulir Tukang Besi[3];Pekerja[6] Mon 25/02/19 Tue 26/02/19 2 days 2 days 3470 0 3070,48 Tukang Besi[3];Pekerja[6]
129 - Pembesian Polos Tukang Besi[2];Pekerja[2] Mon 25/02/19 Wed 27/02/19 2 days 2 days 2200 0 1946,01 Tukang Besi[2];Pekerja[2]
130 - Bekisting sloof Tukang Kayu[4];Pekerja[4] Mon 25/02/19 Thu 28/02/19 2 days 2 days 563,2 0 499,2 Tukang Kayu[4];Pekerja[4]
131 - Beton mutu K-225 Tukang Batu[3];Pekerja[3] Mon 25/02/19 Fri 01/03/19 2 days 2 days 42,24 0 37,44 Tukang Batu[3];Pekerja[3]
132 Pekerjaan kolom praktis lantai 01 type Kp Pekerja[6];Tukang Sat 02/03/19 Sat 09/03/19 8 days 8 days 168 0 0 Pekerja[6];Tukang Batu[2];Tukang Besi[2];Tukang Kayu[2];Alat bantu[1]
Batu[2];Tukang Besi[2];Tukang
133 Pekerjaan ringbalk praktis type Rb Tukang Kayu[3];Alat bantu[1];Pekerja[15];Tukang
Sun 10/03/19 Batu[3];Tukang
Sun 17/03/19
Besi[3];Mandor
8 days 8 days 1408 0 0 Tukang Kayu[3];Alat bantu[1];Pekerja[15];Tukang Batu[3];Tukang
134 Pekerjaan tangga rollag bata Thu 28/02/19 Sun 03/03/19 4 days 4 days 0 0 0
135 - Urugan pasir Alat bantu[1];Pekerja[2] Thu 28/02/19 Fri 01/03/19 2 days 2 days 2,84 0 0 Alat bantu[1];Pekerja[2]
136 - Pasangan rollag bata Alat bantu[1];Tukang Batu;Pekerja[2]
Sat 02/03/19 Sun 03/03/19 2 days 2 days 7,09 0 0 Alat bantu[1];Tukang Batu;Pekerja[2]
137 Pekerjaan ramp beton Sat 02/03/19 Wed 06/03/19 5 days 5 days 0 0 0
142 II.2.1. Pekerjaan Kolom H Beam Sun 03/02/19 Sun 10/03/19 13 days 36 days 0 0 0
143 Pekerjaan baja H - beam 300.300.10.15, Alat bantu[2];Crane Sun 03/02/19 Thu 07/03/19 30 days 30 days 122835,02 0 85590,58 Alat bantu[2];Crane
termasuk Asesories mur baut, angkur, base
144 Pekerjaan perakitan rangka baja Crane[2];Alat bantu[2];Tukang Tue 05/02/19 Thu 07/03/19 10 days 30 days 122835,02 0 56631,73 Crane[2];Alat bantu[2];Tukang Besi[10];Pekerja[5]
Besi[10];Pekerja[5]
145 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Mandor[2]
Fri 08/03/19 Sun 10/03/19 3 days 3 days 2283,13 0 0 Tukang Besi[15];Alat bantu[1];Mandor[2]
146 II.2.2. Pekerjaan Kolom IWF Wed 06/02/19 Wed 20/03/19 16 days 43 days 0 0 0
147 Pekerjaan baja IWF 250.125.6.9, termasuk Alat bantu[2];Crane Wed 06/02/19 Wed 20/03/19 30 days 30 days 20829,03 0 13460,93 Alat bantu[2];Crane
Asesories mur baut, angkur, base plate,
148 Pekerjaan perakitan rangka baja Crane[2];Alat bantu[1];Tukang Fri 08/03/19 Sun 17/03/19 10 days 10 days 20829,03 0 0 Crane[2];Alat bantu[1];Tukang Besi[10];Pekerja
Besi[10];Pekerja
149 Pekerjaan cat finishing Tukang Besi[10];Alat bantu[1];Mandor[2]
Mon 18/03/19 Wed 20/03/19 3 days 3 days 642,76 0 0 Tukang Besi[10];Alat bantu[1];Mandor[2]
150 II.2.3. Pekerjaan Kuda - Kuda Baja Sun 10/02/19 Wed 10/04/19 38 days 60 days 0 0 0
151 Pekerjaan baja IWF 400.200.8.13 & IWF Alat bantu[2];Crane Sun 10/02/19 Wed 13/03/19 7 days 30 days 282960,89 0 141934,59 Alat bantu[2];Crane
150.75.5.7, termasuk Asesories mur baut,
152 Pekerjaan perakitan rangka baja Crane[2];Alat bantu[2];Tukang Mon 11/02/19 Fri 05/04/19 30 days 30 days 282960,89 0 71939,21 Crane[2];Alat bantu[2];Tukang Besi[10];Pekerja
Besi[10];Pekerja[5]
153 Pekerjaan grouting bawah plat landas Alat bantu[1];Grouting Sat 06/04/19 Sun 07/04/19 2 days 2 days 154 0 0 Alat bantu[1];Grouting Pump[4];Tukang Batu
Pump[4];Tukang
154 Pekerjaan cat finishing Tukang Besi[10];Alat bantu[1];Mandor[2]
Mon 08/04/19 Wed 10/04/19 3 days 3 days 8969 0 0 Tukang Besi[10];Alat bantu[1];Mandor[2]
155 II.2.4. Pekerjaan Regel Tue 12/02/19 Tue 23/04/19 34 days 71 days 0 0 0
156 Pekerjaan baja Siku L 60.60.6 & Besi D13, Alat bantu[2];Pekerja[2];Crane Tue 12/02/19 Mon 18/03/19 21 days 21 days 13577,81 0 5933,93 Alat bantu[2];Pekerja[2];Crane
termasuk meni besi, pengelasan, dll sesuai
157 Pekerjaan perakitan rangka baja Tukang Besi[15];Alat Thu 14/02/19 Tue 16/04/19 21 days 21 days 13577,81 0 4237,05 Tukang Besi[15];Alat bantu[2];Peker
bantu[2];Pekerja[20]
Page 2
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
158 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Pekerja[5]
Wed 17/04/19 Tue 23/04/19 7 days 7 days 578,75 0 0 25/02/19 Tukang Besi[15];Alat bantu[1
159 II.2.5. Pekerjaan Baja Support Talang Sat 23/02/19 Sat 27/04/19 21 days 64 days 0 0 0
160 Pekerjaan baja Siku L 60.60.6 & L 40.40.4, Alat Sat 23/02/19 Sat 27/04/19 7 days 7 days 14873,78 0 2597,01 Alat bantu[1];Pekerja[2];
termasuk meni besi, pengelasan,plat buhul, bantu[1];Pekerja[2];Crane;Subkontraktor
161 Pekerjaan perakitan rangka baja Tukang Besi[15];Alat Tue 26/02/19 Mon 04/03/19 7 days 7 days 14873,78 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[20]
bantu[1];Pekerja[20]
162 Pekerjaan papan 2/20 Alat bantu[1];Pekerja[10];TukangTue
Besi[8]
05/03/19 Mon 11/03/19 7 days 7 days 4209 0 0 Alat bantu[1];Pekerja[10];Tukang Besi[8]
163 Pekerjaan talang alumunium coated Alat Tue 05/03/19 Mon 11/03/19 7 days 7 days 902,06 0 0 Alat bantu[1];Pekerja[6];Tukang Besi[4]
bantu[1];Pekerja[6];Tukang
164 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Pekerja[5]
Tue 12/03/19 Mon 18/03/19 7 days 7 days 1174,86 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[5]
165 II.2.6. Pekerjaan Gording Wed 20/02/19 Fri 19/04/19 21 days 59 days 0 0 0
166 Pekerjaan rangka baja profil Alat bantu[1];Pekerja[2];Crane Wed 20/02/19 Fri 19/04/19 14 days 14 days 129602 0 58880,82 Alat bantu[1];Pekerja[2];Crane
C.150.50.20.2,3, termasuk mur baut, jarum
167 Pekerjaan perakitan rangka baja Tukang Besi[15];Alat Fri 22/02/19 Thu 07/03/19 14 days 14 days 129602 0 25550,6 Tukang Besi[15];Alat bantu[1];Pekerja[20]
bantu[1];Pekerja[20]
168 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Pekerja[5]
Fri 08/03/19 Thu 14/03/19 7 days 7 days 13809,65 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[5]
169 II.2.7. Pekerjaan Penutup Atap Tue 19/03/19 Mon 15/04/19 28 days 28 days 0 0 0
170 Pekerjaan penutup atap zincalume t = 0,5 Alat Tue 19/03/19 Mon 25/03/19 7 days 7 days 18812,68 0 0 Alat bantu[1];Pekerja[20];Tukang Besi[15]
mm bantu[1];Pekerja[20];Tukang
171 Pekerjaan nok/kerpus sejenis Alat bantu[1];Tukang Besi[8];Pekerja[10]
Tue 26/03/19 Mon 01/04/19 7 days 7 days 681 0 0 Alat bantu[1];Tukang Besi[8];Pekerja[10]
172 Lisplank zincalum t:0,5 mm Tukang Besi[10];Alat bantu[1];Pekerja[15]
Tue 02/04/19 Mon 08/04/19 7 days 7 days 1657,81 0 0 Tukang Besi[10];Alat bantu[1];Pekerja[15]
173 Pekerjaan alumunium foil + roofmesh Tukang Besi[10];Alat Tue 09/04/19 Mon 15/04/19 7 days 7 days 18812,68 0 0 Tukang Besi[10];Alat bantu[1];Pekerj
bantu[1];Pekerja[15]
174 II.3. Pekerjaan Kanopy2 Sun 24/02/19 Mon 01/04/19 30 days 37 days 0 0 0
175 II.3.1. Pekerjaan Kanopy Depan Sun 24/02/19 Sun 24/03/19 30 days 29 days 0 0 0
176 II.3.1.1 Pekerjaan Rangka Baja Sun 24/02/19 Sat 16/03/19 10 days 21 days 0 0 0
177 Pekerjaan baja dobel siku L 60.60.6, L Alat bantu[1];Pekerja[10] Sun 24/02/19 Sat 16/03/19 3 days 3 days 22290 0 4560,6 Alat bantu[1];Pekerja[10]
50.50.5, L 40.40.4 & pipa besi Ø3" tebal
178 Pekerjaan perakitan rangka baja Tukang Besi[15];Alat Tue 26/02/19 Mon 04/03/19 7 days 7 days 22290 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[20]
bantu[1];Pekerja[20]
179 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Pekerja[5]
Tue 05/03/19 Thu 07/03/19 3 days 3 days 1256 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[5]
180 II.3.1.2 Pekerjaan Gording Sun 24/02/19 Sat 16/03/19 10 days 21 days 0 0 0
181 Pekerjaan rangka baja profil Alat bantu[1];Pekerja[10] Sun 24/02/19 Sat 16/03/19 3 days 3 days 14308,84 0 2927,63 Alat bantu[1];Pekerja[10]
C.150.50.20.2,3, termasuk mur baut,
182 Pekerjaan perakitan rangka baja Tukang Besi[10];Alat Tue 26/02/19 Mon 04/03/19 7 days 7 days 14308,84 0 0 Tukang Besi[10];Alat bantu[1];Pekerja[15]
bantu[1];Pekerja[15]
183 Pekerjaan cat finishing Tukang Besi[15];Alat bantu[1];Pekerja[5]
Tue 05/03/19 Thu 07/03/19 3 days 3 days 1560,73 0 0 Tukang Besi[15];Alat bantu[1];Pekerja[5]
184 II.3.1.3 Pekerjaan Penutup Atap Fri 15/03/19 Sun 24/03/19 10 days 10 days 0 0 0
185 Pekerjaan penutup atap zincalume t = Alat Fri 15/03/19 Tue 19/03/19 5 days 5 days 2088,03 0 0 Alat bantu[1];Pekerja[8];Tukang Besi[4]
0,5 mm bantu[1];Pekerja[8];Tukang
186 Pekerjaan alumunium foil + roofmesh Tukang Besi[2];Alat Wed 20/03/19 Sun 24/03/19 5 days 5 days 1810,48 0 0 Tukang Besi[2];Alat bantu[1];Pekerja[4]
bantu[1];Pekerja[4]
187 II.3.2. Pekerjaan Kanopy Belakang Mon 25/02/19 Mon 01/04/19 29 days 36 days 0 0 0
188 II.3.2.1 Pekerjaan Rangka Baja Mon 25/02/19 Sat 16/03/19 10 days 20 days 0 0 0
189 Pekerjaan baja dobel siku L 50.50.5, L Alat bantu[1];Pekerja[4] Mon 25/02/19 Sat 16/03/19 3 days 3 days 3954,53 0 809,11 Alat bantu[1];Pekerja[4]
40.40.4 & pipa besi Ø3" tebal 3,2 mm,
190 Pekerjaan perakitan rangka baja Tukang Besi[3];Alat Tue 26/02/19 Mon 04/03/19 7 days 7 days 3954,53 0 0 Tukang Besi[3];Alat bantu[1];Pekerja[6]
bantu[1];Pekerja[6]
191 Pekerjaan cat finishing Tukang Besi[3];Alat bantu[1];Pekerja[2]
Tue 05/03/19 Thu 07/03/19 3 days 3 days 159,77 0 0 Tukang Besi[3];Alat bantu[1];Pekerja[2]
192 II.3.2.2 Pekerjaan Gording Mon 25/02/19 Tue 26/03/19 13 days 30 days 0 0 0
193 Pekerjaan rangka baja profil Alat bantu[1];Pekerja[3] Mon 25/02/19 Sat 16/03/19 3 days 3 days 4046,83 0 827,99 Alat bantu[1];Pekerja[3]
C.150.50.20.2,3, termasuk mur baut,
194 Pekerjaan perakitan rangka baja Tukang Besi[3];Alat Sun 17/03/19 Sat 23/03/19 7 days 7 days 4046,83 0 0 Tukang Besi[3];Alat bantu[1];Pekerja[6]
bantu[1];Pekerja[6]
195 Pekerjaan cat finishing Tukang Besi[5];Alat bantu[1];Pekerja[2]
Sun 24/03/19 Tue 26/03/19 3 days 3 days 456,84 0 0 Tukang Besi[5];Alat bantu[1];Pekerja[2]
196 II.3.2.3 Pekerjaan Penutup Atap Wed 27/03/19 Mon 01/04/19 6 days 6 days 0 0 0
197 Pekerjaan penutup atap zincalume t = Alat Wed 27/03/19 Fri 29/03/19 3 days 3 days 528,26 0 0 Alat bantu[1];Pekerja[4];Tukang Besi[2]
0,5 mm bantu[1];Pekerja[4];Tukang
198 Pekerjaan alumunium foil + roofmesh Tukang Besi;Alat Sat 30/03/19 Mon 01/04/19 3 days 3 days 397,14 0 0 Tukang Besi;Alat bantu[1];Pekerja[2]
bantu[1];Pekerja[2]
199 PEKERJAAN ARSITEKTUR Fri 22/02/19 Mon 13/05/19 84 days 81 days 0 0 0
200 II.1. Pekerjaan Arsitektur Gudang Fri 22/02/19 Mon 13/05/19 84 days 81 days 0 0 0
201 II.1.1 Pekerjaan Pasangan Gudang Fri 22/02/19 Wed 17/04/19 42 days 55 days 0 0 0
213 Pekerjaan rak gudang susun 4 Subkontraktor Thu 18/04/19 Mon 13/05/19 40 days 26 days 2,5 0 0 Subkont
214 Pekerjaan rak gudang susun 5 Subkontraktor Thu 18/04/19 Mon 13/05/19 0 days 26 days 2,5 0 0 Subkont
215 II.1.2 Pekerjaan Kusen Gudang Tue 26/03/19 Sat 20/04/19 26 days 26 days 0 0 0
216 Pekerjaan kosen, daun pintu / jendela Tue 26/03/19 Sat 20/04/19 26 days 26 days 0 0 0
motif kayu dan hardware, assesorisnya
217 Pekerjaan kusen type PB Tukang Kayu[4];Pekerja[8] Tue 26/03/19 Mon 01/04/19 7 days 7 days 10 0 0 Tukang Kayu[4];Pekerja[8]
218 Pekerjaan kusen type P2 Tukang Kayu[4];Pekerja[8] Tue 02/04/19 Mon 08/04/19 7 days 7 days 10 0 0 Tukang Kayu[4];Pekerja[8]
219 Pekerjaan kusen type PG Tukang Kayu[4];Pekerja[8] Tue 09/04/19 Sun 14/04/19 6 days 6 days 10 0 0 Tukang Kayu[4];Pekerja[8]
220 Pekerjaan kusen type BV2 Tukang Kayu[4];Pekerja[8] Mon 15/04/19 Sat 20/04/19 6 days 6 days 10 0 0 Tukang Kayu[4];Pekerja[8]
221 II.1.3 Pek. Lavatory Gudang Tue 09/04/19 Fri 03/05/19 25 days 25 days 0 0 0
Page 3
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
237 Kawat ayam Subkontraktor Thu 11/04/19 Sat 20/04/19 18,67 days 10 days 207,02 0 0 25/02/19 Subkontraktor
238 Clading metal sheet tbl : 0,5 mm termasuk Alat bantu[1];Subkontraktor Sun 21/04/19 Tue 30/04/19 14 days 10 days 11177,7 0 0 Alat bantu[1];Subkon
rangka dan asesories terpasang sesuai
239 Roster terawang Mandor;Tukang Batu[8];Pekerja[16]
Wed 01/05/19 Fri 10/05/19 10 days 10 days 4608 0 0 Mandor;Tuk
240 PEKERJAAN R. SOPIR Tue 26/02/19 Tue 14/05/19 188,7 days 78 days 0 0 0
243 Pembuatan Design Struktur Bangunan Tue 26/02/19 Sun 17/03/19 20 days 20 days 0 0 0
247 Pembuatan Design Struktur Bangunan Tue 26/02/19 Sun 17/03/19 20 days 20 days 0 0 0
264 Dinding Bata Ringan Sun 24/03/19 Tue 02/04/19 10 days 10 days 0 0 0
282 Kusen, Daun Pintu dan Jendela Thu 11/04/19 Sat 20/04/19 10 days 10 days 0 0 0
293 III.1. Pekerjaan Struktur Sun 24/03/19 Thu 25/04/19 19,87 days 33 days 0 0 0
294 Galian tanah pondasi footplat Excavator Sun 24/03/19 Tue 26/03/19 3 days 3 days 100,05 0 0 Excavator
295 Urugan pasir bawah pondasi footplat Tukang Batu[3];Pekerja[6] Wed 27/03/19 Thu 28/03/19 2 days 2 days 5,72 0 0 Tukang Batu[3];Pekerja[6]
296 Lantai kerja bawah pondasi footplat Tukang Batu[3];Pekerja[6] Wed 10/04/19 Thu 11/04/19 2 days 2 days 5,72 0 0 Tukang Batu[3];Pekerja[6]
297 Urugan tanah kembali pondasi footplat Tukang Batu[3];Pekerja[6] Mon 15/04/19 Tue 16/04/19 2 days 2 days 33,35 0 0 Tukang Batu[3];Pekerja[6]
298 Galian tanah pondasi batu belah Tukang Batu[3];Pekerja[6] Sun 24/03/19 Mon 25/03/19 2 days 2 days 4,32 0 0 Tukang Batu[3];Pekerja[6]
299 Urugan sirtu bawah pondasi batu belah Tukang Batu[3];Pekerja[6] Tue 26/03/19 Wed 27/03/19 2 days 2 days 1,08 0 0 Tukang Batu[3];Pekerja[6]
300 Pekerjaan pondasi batu belah Tukang Batu[3];Pekerja[6] Thu 28/03/19 Fri 29/03/19 2 days 2 days 2,38 0 0 Tukang Batu[3];Pekerja[6]
301 Urugan tanah kembali pondasi batu belah Tukang Batu[3];Pekerja[6] Sat 30/03/19 Sun 31/03/19 2 days 2 days 1,44 0 0 Tukang Batu[3];Pekerja[6]
302 Pekerjaan urugan pasir bawah lantai Tukang Batu[3];Pekerja[6] Fri 19/04/19 Sat 20/04/19 2 days 2 days 32,61 0 0 Tukang Batu[3];Pekerja[6]
303 Pekerjaan lantai kerja bawah lantai Tukang Batu[3];Pekerja[6] Sun 21/04/19 Mon 22/04/19 2 days 2 days 16,3 0 0 Tukang Batu[3];Pekerja[6]
304 Pekerjaan urugan tanah peninggian lantai Tukang Batu[3];Pekerja[6] Fri 19/04/19 Sun 21/04/19 3 days 3 days 114,12 0 0 Tukang Batu[3];Pekerja[6]
305 Pekerjaan pemadatan Tukang Batu[5];Pekerja[6];Stamper[3]
Mon 22/04/19 Wed 24/04/19 3 days 3 days 114,12 0 0 Tukang Batu[5];Pekerja[6];S
306 Pekerjaan beton bertulang footplat type FP Fri 12/04/19 Sun 14/04/19 1,87 days 3 days 0 0 0
307 - Pembesian Polos Tukang Besi[3];Pekerja[6] Fri 12/04/19 Fri 12/04/19 0,67 days 1 day 1894,51 0 0 Tukang Besi[3];Pekerja[6]
308 - Bekisting pondasi Tukang Kayu[5];Pekerja[5] Sat 13/04/19 Sat 13/04/19 0,2 days 1 day 24,36 0 0 Tukang Kayu[5];Pekerja[5]
309 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Sun 14/04/19 Sun 14/04/19 1 day 1 day 6,69 0 0 Tukang Batu[4];Pekerja[4]
310 Pekerjaan beton bertulang sloof type S1 Mon 15/04/19 Thu 18/04/19 4 days 4 days 0 0 0
311 - Pembesian Polos Tukang Besi[3];Pekerja[6] Mon 15/04/19 Tue 16/04/19 2 days 2 days 801,36 0 0 Tukang Besi[3];Pekerja[6]
312 - Bekisting sloof Tukang Kayu[5];Pekerja[5] Wed 17/04/19 Wed 17/04/19 1 day 1 day 70,8 0 0 Tukang Kayu[5];Pekerja[5]
313 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Thu 18/04/19 Thu 18/04/19 1 day 1 day 5,31 0 0 Tukang Batu[4];Pekerja[4]
314 Pekerjaan beton bertulang sloof type S2 Mon 15/04/19 Wed 17/04/19 3 days 3 days 0 0 0
315 - Pembesian Polos Tukang Besi[3];Pekerja[6] Mon 15/04/19 Mon 15/04/19 1 day 1 day 26,46 0 0 Tukang Besi[3];Pekerja[6]
Page 4
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
316 - Bekisting sloof Tukang Kayu[5];Pekerja[5] Tue 16/04/19 Tue 16/04/19 1 day 1 day 2,16 0 0 25/02/19 Tukang Kayu[5];Pekerja[5]
317 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Wed 17/04/19 Wed 17/04/19 1 day 1 day 0,16 0 0 Tukang Batu[4];Pekerja[4]
318 Pekerjaan kolom type K1 Fri 19/04/19 Sun 21/04/19 3 days 3 days 0 0 0
319 - Pembesian Polos Tukang Besi[3];Pekerja[6] Fri 19/04/19 Fri 19/04/19 1 day 1 day 1069,79 0 0 Tukang Besi[3];Pekerja[6]
320 - Bekisting kolom Tukang Kayu[5];Pekerja[5] Sat 20/04/19 Sat 20/04/19 1 day 1 day 94,5 0 0 Tukang Kayu[5];Pekerja[5]
321 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Sun 21/04/19 Sun 21/04/19 1 day 1 day 5,91 0 0 Tukang Batu[4];Pekerja[4]
322 Pekerjaan kolom praktis type Kp Tukang Batu[2];Tukang Besi;Tukang
MonKayu;Pekerja[3]
22/04/19 Tue 23/04/19 1,5 days 2 days 112,5 0 0 Tukang Batu[2];Tukang Besi;
323 Pekerjaan balok type RB1 Fri 19/04/19 Sun 21/04/19 3 days 3 days 0 0 0
324 - Pembesian Polos Tukang Besi[3];Pekerja[6] Fri 19/04/19 Fri 19/04/19 1 day 1 day 676 0 0 Tukang Besi[3];Pekerja[6]
325 - Bekisting balok Tukang Kayu[5];Pekerja[5] Sat 20/04/19 Sat 20/04/19 1 day 1 day 94,4 0 0 Tukang Kayu[5];Pekerja[5]
326 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Sun 21/04/19 Sun 21/04/19 1 day 1 day 7,08 0 0 Tukang Batu[4];Pekerja[4]
327 Pekerjaan balok type RB2 Fri 19/04/19 Sun 21/04/19 3 days 3 days 0 0 0
328 - Pembesian Polos Tukang Besi[3];Pekerja[6] Fri 19/04/19 Fri 19/04/19 1 day 1 day 21,2 0 0 Tukang Besi[3];Pekerja[6]
329 - Bekisting balok Tukang Kayu[5];Pekerja[5] Sat 20/04/19 Sat 20/04/19 1 day 1 day 2,97 0 0 Tukang Kayu[5];Pekerja[5]
330 - Beton mutu K-300 Tukang Batu[4];Pekerja[4] Sun 21/04/19 Sun 21/04/19 1 day 1 day 0,16 0 0 Tukang Batu[4];Pekerja[4]
331 Pekerjaan balok praktis latiu Tukang Batu[2];Tukang Besi;Tukang
MonKayu;Pekerja[3]
22/04/19 Mon 22/04/19 1 day 1 day 21,8 0 0 Tukang Batu[2];Tukang Besi;T
332 Pekerjaan urugan pasir bawah rollag bata Tukang Batu[2];Tukang Besi;Tukang
Tue Kayu;Pekerja[3]
23/04/19 Tue 23/04/19 1 day 1 day 0,37 0 0 Tukang Batu[2];Tukang Besi;
333 Pekerjaan rollag bata Tukang Batu[2];Tukang Besi;Tukang
WedKayu;Pekerja[3]
24/04/19 Wed 24/04/19 1 day 1 day 4,47 0 0 Tukang Batu[2];Tukang Besi
334 Pekerjaan tangga rollag bata Wed 24/04/19 Thu 25/04/19 2 days 2 days 0 0 0
338 III.2.1 Pekerjaan Kuda - Kuda Baja Wed 24/04/19 Wed 01/05/19 13 days 8 days 0 0 0
339 Pekerjaan baja IWF 150.75.5.7, termasuk Subkontraktor Wed 24/04/19 Thu 25/04/19 3 days 2 days 1888,17 0 0 Subkontraktor
Asesories mur baut, plat sambung, stifner,
340 Pekerjaan perakitan rangka baja Subkontraktor Fri 26/04/19 Sat 27/04/19 5 days 2 days 1888,17 0 0 Subkontraktor
341 Pekerjaan grouting bawah plat landas Subkontraktor Sun 28/04/19 Mon 29/04/19 2 days 2 days 18 0 0 Subkontraktor
342 Pekerjaan cat finishing Subkontraktor Tue 30/04/19 Wed 01/05/19 3 days 2 days 80,92 0 0 Subkontraktor
343 III.2.2 Pekerjaan Gording Thu 02/05/19 Tue 07/05/19 13 days 6 days 0 0 0
344 Pekerjaan rangka baja profil Subkontraktor Thu 02/05/19 Fri 03/05/19 3 days 2 days 2849 0 0 Subkontraktor
C.150.50.20.2,3, termasuk mur baut, jarum
345 Pekerjaan perakitan rangka baja Subkontraktor Sat 04/05/19 Sun 05/05/19 7 days 2 days 2849 0 0 Subkontraktor
346 Pekerjaan cat finishing Subkontraktor Mon 06/05/19 Tue 07/05/19 3 days 2 days 330,48 0 0 Subkontraktor
347 III.2.3 Pekerjaan Penutup Atap Wed 08/05/19 Tue 14/05/19 9 days 7 days 0 0 0
348 Pekerjaan penutup atap zincalume t = 0,5 mmSubkontraktor Wed 08/05/19 Thu 09/05/19 3 days 2 days 481,74 0 0 Subkontrakt
349 Pekerjaan nok/kerpus sejenis Subkontraktor Fri 10/05/19 Fri 10/05/19 2 days 1 day 37 0 0 Subkontrak
350 Pekerjaan alumunium foil + roofmesh Subkontraktor Sat 11/05/19 Sun 12/05/19 2 days 2 days 481,74 0 0 Subkontra
351 Lisplank zincalum t:0,5 mm Subkontraktor Mon 13/05/19 Tue 14/05/19 2 days 2 days 51,47 0 0 Subkon
352 PEKERJAAN ARSITEKTUR Thu 02/05/19 Tue 14/05/19 32,5 days 13 days 0 0 0
353 III.1.1 Pekerjaan Pasangan R. Sopir Thu 02/05/19 Mon 13/05/19 32,5 days 12 days 0 0 0
354 Pasangan dinding bata ringan Tukang Batu[6];Pekerja[8] Thu 02/05/19 Thu 02/05/19 0,5 days 1 day 402,97 0 0 Tukang Batu[6];Pek
355 Plesteran dinding bata ringan Tukang Batu[6];Pekerja[8] Thu 02/05/19 Thu 02/05/19 3 days 1 day 763,22 0 0 Tukang Batu[6];Pek
356 Acian dinding bata ringan Tukang Batu[6];Pekerja[8] Thu 02/05/19 Thu 02/05/19 3 days 1 day 701,61 0 0 Tukang Batu[6];Pek
357 Sponengan sudut Tukang Batu[6];Pekerja[8] Thu 02/05/19 Thu 02/05/19 3 days 1 day 51,2 0 0 Tukang Batu[6];Pek
358 Plafond gypsumboard 9 mm rangka besi hollow Tukang Kayu[2];Tukang Besi[2] Mon 13/05/19 Mon 13/05/19 1,5 days 1 day 119,09 0 0 Tukang K
40x40x4mm
359 List gypsum Tukang Kayu[2];Tukang Besi[2] Mon 13/05/19 Mon 13/05/19 3 days 1 day 9,9 0 0 Tukang K
360 Pengecatan dinding dengan cat interior Tukang Batu[4] Sun 12/05/19 Sun 12/05/19 0,75 days 1 day 376,4 0 0 Tukang Ba
361 Pengecatan dinding dengan cat eksterior Tukang Batu[4] Sun 12/05/19 Sun 12/05/19 3 days 1 day 325,21 0 0 Tukang Ba
362 Pengecatan plafond dengan cat interior Tukang Batu[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 119,09 0 0 Tukang B
363 Pasangan keramik dinding 30 x 30 cm Polished Tukang Batu[4];Pekerja[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 37,5 0 0 Tukang B
364 Beton expose Tukang Batu[4];Pekerja[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 474,02 0 0 Tukang B
365 Cat beton expose Tukang Batu[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 474,02 0 0 Tukang B
366 Floorhardener Tukang Batu[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 206,7 0 0 Tukang B
367 Lantai keramik 30 x 30 cm polished Tukang Batu[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 35,16 0 0 Tukang B
368 Lantai keramik 30 x 30 cm unpolished Tukang Batu[4] Mon 13/05/19 Mon 13/05/19 3 days 1 day 68,87 0 0 Tukang B
369 Rabat beton tbl 10 cm Tukang Batu[4] Thu 02/05/19 Thu 02/05/19 3 days 1 day 3,43 0 0 Tukang Batu[4]
370 Pekerjaan Saluran Keliling Bangunan U - 20 cm Subkontraktor Thu 02/05/19 Thu 02/05/19 3 days 1 day 59,07 0 0 Subkontraktor
termasuk urugan pasir, pasangan bata, plester
371 Pekerjaan bak kontrol 40 x 40 cm terpasang Tukang Batu[4];Pekerja[4] Thu 02/05/19 Thu 02/05/19 3 days 1 day 10 0 0 Tukang Batu[4];Pek
sesuai gambar
372 III.1.2 Pekerjaan Kusen R. Sopir Sat 04/05/19 Mon 13/05/19 12,5 days 10 days 0 0 0
373 Pekerjaan kosen, daun pintu / jendela motif Sat 04/05/19 Mon 13/05/19 12,5 days 10 days 0 0 0
kayu dan hardware, assesorisnya terpasang
374 Pekerjaan kusen type P1 Tukang Kayu[6];Pekerja[10];Mandor
Sat 04/05/19 Sun 05/05/19 0,5 days 2 days 2 0 0 Tukang Kayu[6];P
375 Pekerjaan kusen type PD Tukang Kayu[6];Pekerja[10] Mon 06/05/19 Tue 07/05/19 3 days 2 days 1 0 0 Tukang Kayu[6
376 Pekerjaan kusen type PB Tukang Kayu[6];Pekerja[10] Wed 08/05/19 Thu 09/05/19 3 days 2 days 2 0 0 Tukang Kayu
377 Pekerjaan kusen type BV Tukang Kayu[6];Pekerja[10] Fri 10/05/19 Sat 11/05/19 3 days 2 days 2 0 0 Tukang Ka
378 Pekerjaan kusen type BV3 Tukang Kayu[6];Pekerja[10] Sun 12/05/19 Mon 13/05/19 3 days 2 days 2 0 0 Tukang K
379 III.1.3 Pek. Lavatory R. Sopir Sun 12/05/19 Tue 14/05/19 12 days 3 days 0 0 0
380 Pasangan closed jongkok Tukang Batu[2];Pekerja[2] Sun 12/05/19 Sun 12/05/19 1 day 1 day 2 0 0 Tukang Ba
381 Tissue holder Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 2 0 0 Tukang B
382 Double rob hook Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 2 0 0 Tukang B
383 Pasangan kran toilet Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 2 0 0 Tukang B
384 Pasangan floor drain Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 2 0 0 Tukang B
385 Pasangan keramik dinding 30 x 60 cm Polished Tukang Batu[2];Pekerja[2] Sun 12/05/19 Tue 14/05/19 3 days 3 days 14,98 0 0 Tukang
386 Pasangan lantai keramik 30 x 30 cm unpolished Tukang Batu[2];Pekerja[2] Sun 12/05/19 Tue 14/05/19 3 days 3 days 4,53 0 0 Tukang
387 III.1.4 Pekerjaan Fasade R. Sopir Fri 03/05/19 Thu 09/05/19 7 days 7 days 0 0 0
388 Roster uk. 10 x 20 cm Tukang Batu[2];Pekerja[2] Fri 03/05/19 Thu 09/05/19 7 days 7 days 380 0 0 Tukang Batu
389 Roster uk. 15 x 25 cm Tukang Batu[2];Pekerja[2] Fri 03/05/19 Thu 09/05/19 7 days 7 days 336 0 0 Tukang Batu
390 PEKERJAAN POWER HOUSE & RUMAH POMPA Tue 26/02/19 Wed 15/05/19 195,7 days 79 days 0 0 0
393 Pembuatan Design Struktur Bangunan Tue 26/02/19 Sun 17/03/19 20 days 20 days 0 0 0
Page 5
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
395 Approval Thu 21/03/19 Sat 23/03/19 3 days 3 days 0 0 0 25/02/19
396 Arsitektur Mon 18/03/19 Fri 12/04/19 26 days 26 days 0 0 0
406 Dinding Bata Ringan Sat 13/04/19 Mon 22/04/19 10 days 10 days 0 0 0
418 Kusen, Daun Pintu dan Jendela Thu 25/04/19 Sat 04/05/19 10 days 10 days 0 0 0
423 Galian tanah pondasi footplat Excavator Sun 24/03/19 Thu 28/03/19 5 days 5 days 34,68 0 0 Excavator
424 Urugan sirtu bawah pondasi footplat Tukang Batu[3];Pekerja[6] Fri 29/03/19 Sun 31/03/19 3 days 3 days 3,47 0 0 Tukang Batu[3];Pekerja[6]
425 Lantai kerja bawah pondasi footplat Tukang Batu[3];Pekerja[6] Wed 03/04/19 Wed 03/04/19 1 day 1 day 0,87 0 0 Tukang Batu[3];Pekerja[6]
426 Urugan tanah kembali pondasi footplat Tukang Batu[3];Pekerja[6] Mon 08/04/19 Fri 12/04/19 5 days 5 days 11,56 0 0 Tukang Batu[3];Pekerja[6]
427 Galian tanah pondasi batu belah Tukang Batu[3];Pekerja[6] Sun 24/03/19 Tue 26/03/19 3 days 3 days 6,48 0 0 Tukang Batu[3];Pekerja[6]
428 Urugan sirtu bawah pondasi batu belah Tukang Batu[3];Pekerja[6] Wed 27/03/19 Wed 27/03/19 1 day 1 day 0,72 0 0 Tukang Batu[3];Pekerja[6]
429 Pekerjaan pondasi batu belah Tukang Batu[3];Pekerja[6] Thu 28/03/19 Sat 30/03/19 3 days 3 days 3,2 0 0 Tukang Batu[3];Pekerja[6]
430 Urugan tanah kembali pondasi batu belah Tukang Batu[3];Pekerja[6] Mon 08/04/19 Tue 09/04/19 2 days 2 days 2,16 0 0 Tukang Batu[3];Pekerja[6]
431 Galian tanah sloof Tukang Batu[3];Pekerja[6] Sun 24/03/19 Tue 26/03/19 3 days 3 days 11,51 0 0 Tukang Batu[3];Pekerja[6]
432 Urugan pasir bawah lantai, t = 10 cm Tukang Batu[3];Pekerja[6] Wed 27/03/19 Fri 29/03/19 3 days 3 days 10,98 0 0 Tukang Batu[3];Pekerja[6]
433 Urugan sirtu bawah sloof Tukang Batu[3];Pekerja[6] Sat 30/03/19 Mon 01/04/19 3 days 3 days 2,54 0 0 Tukang Batu[3];Pekerja[6]
434 Lantai kerja bawah sloof Tukang Batu[5];Pekerja[6];Stamper[3]
Tue 02/04/19 Tue 02/04/19 1 day 1 day 1,27 0 0 Tukang Batu[5];Pekerja[6];Stamper[3]
435 Urugan tanah kembali sloof Tukang Batu[3];Pekerja[6] Mon 15/04/19 Wed 17/04/19 3 days 3 days 3,84 0 0 Tukang Batu[3];Pekerja[6]
436 Lantai kerja bawah lantai teras, t = 5 cm Tukang Batu[3];Pekerja[6] Thu 18/04/19 Sat 20/04/19 3 days 3 days 5,49 0 0 Tukang Batu[3];Pekerja[6]
437 Pekerjaan peninggian tanah Tukang Batu[5];Pekerja[6];Stamper[3]
Sun 21/04/19 Tue 23/04/19 3 days 3 days 38,42 0 0 Tukang Batu[5];Pekerja[6];St
438 Pekerjaan pemadatan tanah Tukang Batu[5];Pekerja[6];Stamper[3]
Wed 24/04/19 Fri 26/04/19 3 days 3 days 38,42 0 0 Tukang Batu[5];Pekerja[6
439 Pekerjaan beton bertulang foot plat K. 300 type FP Thu 04/04/19 Sun 07/04/19 4 days 4 days 0 0 0
445 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Mon 08/04/19 Thu 11/04/19 4 days 4 days 281,8 0 0 Tukang Besi[2];Pekerja[2]
446 - Pembesian Polos Tukang Besi[2];Pekerja[2] Mon 08/04/19 Wed 10/04/19 3 days 3 days 142,52 0 0 Tukang Besi[2];Pekerja[2]
447 - Bekisting sloof Tukang Kayu[3];Pekerja[3] Thu 11/04/19 Fri 12/04/19 2 days 2 days 33,84 0 0 Tukang Kayu[3];Pekerja[3]
448 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Sat 13/04/19 Sun 14/04/19 2 days 2 days 3,38 0 0 Tukang Batu[3];Pekerja[3]
449 Pekerjaan beton bertulang sloof K. 225 type Sp Mon 15/04/19 Thu 18/04/19 4 days 4 days 0 0 0
450 - Pembesian Polos Tukang Besi[2];Pekerja[2] Mon 15/04/19 Tue 16/04/19 2 days 2 days 32,84 0 0 Tukang Besi[2];Pekerja[2]
451 - Bekisting sloof Tukang Kayu[3];Pekerja[3] Wed 17/04/19 Wed 17/04/19 1 day 1 day 3,2 0 0 Tukang Kayu[3];Pekerja[3]
452 - Beton mutu K-225 Tukang Batu[3];Pekerja[3] Thu 18/04/19 Thu 18/04/19 1 day 1 day 0,24 0 0 Tukang Batu[3];Pekerja[3]
453 Pekerjaan beton bertulang kolom pedestal K. 300 type Ks Fri 19/04/19 Tue 23/04/19 5 days 5 days 0 0 0
454 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Fri 19/04/19 Sun 21/04/19 3 days 3 days 220,45 0 0 Tukang Besi[2];Pekerja[2]
455 - Pembesian Polos Tukang Besi[2];Pekerja[2] Fri 19/04/19 Sat 20/04/19 2 days 2 days 49,48 0 0 Tukang Besi[2];Pekerja[2]
456 - Bekisting kolom Tukang Kayu[3];Pekerja[3] Sun 21/04/19 Mon 22/04/19 2 days 2 days 14,04 0 0 Tukang Kayu[3];Pekerja[3]
457 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Tue 23/04/19 Tue 23/04/19 1 day 1 day 1,05 0 0 Tukang Batu[3];Pekerja[3]
458 Pekerjaan beton bertulang kolom K. 300 type Ks Fri 19/04/19 Wed 24/04/19 6 days 6 days 0 0 0
459 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Fri 19/04/19 Sun 21/04/19 3 days 3 days 511,35 0 0 Tukang Besi[2];Pekerja[2]
460 - Pembesian Polos Tukang Besi[2];Pekerja[2] Fri 19/04/19 Sat 20/04/19 2 days 2 days 143,23 0 0 Tukang Besi[2];Pekerja[2]
461 - Bekisting kolom Tukang Kayu[3];Pekerja[3] Sun 21/04/19 Mon 22/04/19 2 days 2 days 48 0 0 Tukang Kayu[3];Pekerja[3]
462 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Tue 23/04/19 Wed 24/04/19 2 days 2 days 3,6 0 0 Tukang Batu[3];Pekerja[3]
463 Pekerjaan beton bertulang kolom praktis type Kp Mon 22/04/19 Sat 27/04/19 6 days 6 days 16 0 0
464 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Mon 22/04/19 Wed 24/04/19 3 days 3 days 511,35 0 0 Tukang Besi[2];Pekerja[2]
465 - Pembesian Polos Tukang Besi[2];Pekerja[2] Mon 22/04/19 Tue 23/04/19 2 days 2 days 143,23 0 0 Tukang Besi[2];Pekerja[2]
466 - Bekisting kolom Tukang Kayu[3];Pekerja[3] Wed 24/04/19 Thu 25/04/19 2 days 2 days 48 0 0 Tukang Kayu[3];Pekerja[3]
467 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Fri 26/04/19 Sat 27/04/19 2 days 2 days 3,6 0 0 Tukang Batu[3];Pekerja[3
468 Pekerjaan beton bertulang plat dasar wiremesh M8-150 Sun 31/03/19 Sun 07/04/19 8 days 8 days 0 0 0
469 - Pembesian Wiremesh Tukang Besi[2];Pekerja[2] Sun 31/03/19 Wed 03/04/19 4 days 4 days 598,07 0 0 Tukang Besi[2];Pekerja[2]
470 - Bekisting plat dasar Tukang Kayu[3];Pekerja[3] Thu 04/04/19 Fri 05/04/19 2 days 2 days 3,6 0 0 Tukang Kayu[3];Pekerja[3]
471 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Sat 06/04/19 Sun 07/04/19 2 days 2 days 10,98 0 0 Tukang Batu[3];Pekerja[3]
472 Pekerjaan beton bertulang plat lantai atap power house K. 300 Wed 08/05/19 Mon 13/05/19 6 days 6 days 0 0 0
473 - Pembesian Polos Tukang Besi[2];Pekerja[2] Wed 08/05/19 Fri 10/05/19 3 days 3 days 1614,54 0 0 Tukang Bes
Page 6
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
474 - Bekisting plat lantai Tukang Kayu[3];Pekerja[3] Sat 11/05/19 Sun 12/05/19 2 days 2 days 153 0 0 25/02/19 Tukang Ka
475 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Mon 13/05/19 Mon 13/05/19 1 day 1 day 20,52 0 0 Tukang B
476 Pekerjaan beton bertulang balok K. 300 type B1 Sun 28/04/19 Sun 05/05/19 8 days 8 days 0 0 0
477 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Sun 28/04/19 Wed 01/05/19 4 days 4 days 550,93 0 0 Tukang Besi[2];Peker
478 - Pembesian Polos Tukang Besi[2];Pekerja[2] Sun 28/04/19 Wed 01/05/19 4 days 4 days 322,8 0 0 Tukang Besi[2];Peker
479 - Bekisting balok Tukang Kayu[3];Pekerja[3] Thu 02/05/19 Fri 03/05/19 2 days 2 days 48,58 0 0 Tukang Kayu[3];Pe
480 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Sat 04/05/19 Sun 05/05/19 2 days 2 days 5,03 0 0 Tukang Batu[3];P
481 Pekerjaan beton bertulang balok K. 300 type B2 Sun 28/04/19 Sat 04/05/19 7 days 7 days 0 0 0
482 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Sun 28/04/19 Wed 01/05/19 4 days 4 days 305,24 0 0 Tukang Besi[2];Peker
483 - Pembesian Polos Tukang Besi[2];Pekerja[2] Sun 28/04/19 Wed 01/05/19 4 days 4 days 176,76 0 0 Tukang Besi[2];Peker
484 - Bekisting balok Tukang Kayu[3];Pekerja[3] Thu 02/05/19 Fri 03/05/19 2 days 2 days 30,2 0 0 Tukang Kayu[3];Pe
485 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Sat 04/05/19 Sat 04/05/19 1 day 1 day 2,42 0 0 Tukang Batu[3];Pe
486 Pekerjaan beton bertulang balok K. 300 type B3 Sun 28/04/19 Thu 02/05/19 5 days 5 days 0 0 0
487 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Sun 28/04/19 Tue 30/04/19 3 days 3 days 152,62 0 0 Tukang Besi[2];Pekerj
488 - Pembesian Polos Tukang Besi[2];Pekerja[2] Sun 28/04/19 Mon 29/04/19 2 days 2 days 45,25 0 0 Tukang Besi[2];Pekerja
489 - Bekisting balok Tukang Kayu[3];Pekerja[3] Tue 30/04/19 Wed 01/05/19 2 days 2 days 12,56 0 0 Tukang Kayu[3];Peke
490 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Thu 02/05/19 Thu 02/05/19 1 day 1 day 0,94 0 0 Tukang Batu[3];Pek
491 Pekerjaan beton bertulang balok K. 300 type Bk Thu 02/05/19 Mon 06/05/19 5 days 5 days 0 0 0
492 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Thu 02/05/19 Sun 05/05/19 4 days 4 days 222,75 0 0 Tukang Besi[2];P
493 - Pembesian Polos Tukang Besi[2];Pekerja[2] Thu 02/05/19 Fri 03/05/19 2 days 2 days 52,32 0 0 Tukang Besi[2];Pek
494 - Bekisting balok Tukang Kayu[3];Pekerja[3] Sat 04/05/19 Sun 05/05/19 2 days 2 days 11,96 0 0 Tukang Kayu[3];P
495 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Mon 06/05/19 Mon 06/05/19 1 day 1 day 0,9 0 0 Tukang Batu[3];
496 Pekerjaan beton bertulang balok K. 300 type BL Thu 02/05/19 Tue 07/05/19 6 days 6 days 0 0 0
497 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Thu 02/05/19 Sat 04/05/19 3 days 3 days 234,42 0 0 Tukang Besi[2];Pe
498 - Pembesian Polos Tukang Besi[2];Pekerja[2] Thu 02/05/19 Sat 04/05/19 3 days 3 days 103,47 0 0 Tukang Besi[2];Pe
499 - Bekisting balok Tukang Kayu[3];Pekerja[3] Sun 05/05/19 Mon 06/05/19 2 days 2 days 30,25 0 0 Tukang Kayu[3]
500 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Tue 07/05/19 Tue 07/05/19 1 day 1 day 1,65 0 0 Tukang Batu[3
501 Pekerjaan balok praktis latiu Tukang Batu;Pekerja[3];Tukang Kayu;Tukang
Wed 08/05/19Besi Mon 13/05/19 6 days 6 days 32 0 0 Tukang B
502 Galian tanah pondasi genset Tukang Batu[3];Pekerja[3] Sun 24/03/19 Mon 25/03/19 2 days 2 days 6,66 0 0 Tukang Batu[3];Pekerja[3]
503 Urugan sirtu bawah pondasi genset Tukang Batu[2];Pekerja[4] Tue 26/03/19 Tue 26/03/19 0,5 days 0,5 days 1 0 0 Tukang Batu[2];Pekerja[4]
504 Lantai kerja bawah pondasi genset Tukang Batu[2];Pekerja[4] Tue 26/03/19 Wed 27/03/19 1 day 1 day 0,33 0 0 Tukang Batu[2];Pekerja[4]
505 Urugan tanah kembali pondasi genset Tukang Batu[2];Pekerja[4] Thu 04/04/19 Fri 05/04/19 1 day 1 day 2,22 0 0 Tukang Batu[2];Pekerja[4]
506 Pekerjaan beton bertulang pondasi genset K. 300 Wed 27/03/19 Thu 04/04/19 8 days 8 days 0 0 0
507 - Pembesian Ulir Tukang Besi[2];Pekerja[2] Wed 27/03/19 Sat 30/03/19 3 days 3 days 212,66 0 0 Tukang Besi[2];Pekerja[2]
508 - Pembesian Polos Tukang Besi[2];Pekerja[2] Sat 30/03/19 Mon 01/04/19 2 days 2 days 15,6 0 0 Tukang Besi[2];Pekerja[2]
509 - Bekisting pondasi Tukang Kayu[3];Pekerja[3] Mon 01/04/19 Wed 03/04/19 2 days 2 days 4,25 0 0 Tukang Kayu[3];Pekerja[3]
510 - Beton mutu K-300 Tukang Batu[3];Pekerja[3] Wed 03/04/19 Thu 04/04/19 1 day 1 day 1,88 0 0 Tukang Batu[3];Pekerja[3]
511 Pekerjaan urugan kerikil dilatasi Tukang Batu[2];Pekerja[4] Thu 04/04/19 Fri 05/04/19 1 day 1 day 0,61 0 0 Tukang Batu[2];Pekerja[4]
512 Pekerjaan urugan sirtu bawah beton B0 Tukang Batu[2];Pekerja[4] Fri 05/04/19 Sun 07/04/19 2 days 2 days 1 0 0 Tukang Batu[2];Pekerja[4]
513 Pekerjaan lantai kerja bawah beton B0 Tukang Batu[2];Pekerja[4] Sun 07/04/19 Wed 10/04/19 3 days 3 days 0,33 0 0 Tukang Batu[2];Pekerja[4]
514 Pekerjaan beton B0, K. 175 Tukang Batu[2];Pekerja[4] Wed 10/04/19 Sat 13/04/19 3 days 3 days 4,66 0 0 Tukang Batu[2];Pekerja[4]
515 Acian beton expose Tukang Batu[2];Pekerja[4] Sat 13/04/19 Sat 20/04/19 7 days 7 days 276,9 0 0 Tukang Batu[2];Pekerja[4]
516 Pekerjaan waterproofing system coating termasuk Tukang Batu[2];Pekerja[4] Sat 20/04/19 Sat 27/04/19 7 days 7 days 171 0 0 Tukang Batu[2];Pekerja[4
beton screed
517 PEKERJAAN ARSITEKTUR Mon 15/04/19 Wed 15/05/19 56 days 31 days 0 0 0
518 Pasangan dinding bata ringan tebal 10 cm Tukang Batu[2];Pekerja[4] Tue 14/05/19 Wed 15/05/19 3,5 days 2 days 218,68 0 0 Tukang
519 Plesteran dinding bata ringan Tukang Batu[2];Pekerja[4] Tue 14/05/19 Wed 15/05/19 7 days 2 days 437,36 0 0 Tukang
520 Acian dinding bata ringan Tukang Batu[2];Pekerja[4] Tue 14/05/19 Wed 15/05/19 7 days 2 days 437,36 0 0 Tukang
521 Sponengan sudut Tukang Batu[2];Pekerja[4] Tue 14/05/19 Wed 15/05/19 5 days 2 days 95,96 0 0 Tukang
522 Pekerjaan cat interior Tukang Batu[2] Tue 14/05/19 Wed 15/05/19 3,5 days 2 days 296 0 0 Tukang
523 Pekerjaan cat exterior Tukang Batu[2] Tue 14/05/19 Wed 15/05/19 7 days 2 days 154,17 0 0 Tukang
524 Floor hardener Tukang Batu[2] Tue 14/05/19 Wed 15/05/19 7 days 2 days 224,95 0 0 Tukang
525 Pasangan roster termasuk finishing cat Tukang Batu[2];Pekerja[4] Tue 14/05/19 Wed 15/05/19 5 days 2 days 31 0 0 Tukang
526 Pekerjaan urugan sirtu bawah got kabel, t = 5 cm Tukang Batu[2];Pekerja[4] Mon 15/04/19 Wed 17/04/19 3 days 3 days 0,75 0 0 Tukang Batu[2];Pekerja[4]
527 Pekerjaan rabat beton got kabel Tukang Batu[2];Pekerja[4] Mon 15/04/19 Wed 17/04/19 7 days 3 days 6,78 0 0 Tukang Batu[2];Pekerja[4]
528 Pekerjaan beton expose got kabel Tukang Batu[2];Pekerja[4] Mon 15/04/19 Wed 17/04/19 5 days 3 days 39,54 0 0 Tukang Batu[2];Pekerja[4]
529 Pekerjaan grill tutup got kabel Tukang Batu[2];Pekerja[4] Mon 15/04/19 Wed 17/04/19 5 days 3 days 11,3 0 0 Tukang Batu[2];Pekerja[4]
530 Pekerjaan cat Beton expose Tukang Batu[2] Mon 15/04/19 Wed 17/04/19 7 days 3 days 276,9 0 0 Tukang Batu[2]
531 Urugan sirtu bawah rabat beton, t = 10 cm Tukang Batu[2];Pekerja[4] Mon 15/04/19 Tue 16/04/19 2 days 2 days 6,76 0 0 Tukang Batu[2];Pekerja[4]
532 Urugan sirtu bawah ramp beton Tukang Batu[2];Pekerja[4] Mon 15/04/19 Tue 16/04/19 2 days 2 days 0,35 0 0 Tukang Batu[2];Pekerja[4]
533 Rabat beton keliling bangunan, t = 10 cm Tukang Batu[2];Pekerja[4] Mon 15/04/19 Tue 16/04/19 2 days 2 days 6,76 0 0 Tukang Batu[2];Pekerja[4]
534 Pekerjaan ramp beton Tukang Batu[2];Pekerja[4] Mon 15/04/19 Tue 16/04/19 2 days 2 days 0,35 0 0 Tukang Batu[2];Pekerja[4]
535 Floor hardener ramp beton Tukang Batu[2] Thu 25/04/19 Fri 26/04/19 2 days 2 days 3,53 0 0 Tukang Batu[2]
536 Pagar besi hollow finishing cat Tukang Besi[5] Mon 15/04/19 Tue 16/04/19 1,4 days 1,4 days 15,9 0 0 Tukang Besi[5]
537 Pekerjaan kosen dan daun pintu / jendela dan Mon 15/04/19 Tue 14/05/19 26,9 days 30 days 0 0 0
hardware dan assesorisnya terpasang sesuai
538 Pekerjaan kusen type PB1 Tukang Kayu[4];Pekerja[6] Tue 14/05/19 Tue 14/05/19 1,75 days 1 day 2 0 0 Tukang
539 Pekerjaan kusen type PB2 Tukang Kayu[4];Pekerja[6] Tue 14/05/19 Tue 14/05/19 7 days 1 day 3 0 0 Tukang
540 Pekerjaan kusen type KS Tukang Kayu[4];Pekerja[6] Tue 14/05/19 Tue 14/05/19 7 days 1 day 6 0 0 Tukang
541 Pekerjaan railing besi hollow + pintu fin cat t = Tukang Besi[5];Pekerja[2] Tue 14/05/19 Tue 14/05/19 1,4 days 1 day 1 0 0 Tukang
1,8 m dan p = 15 m termasuk asesories dll
542 Pekerjaan Saluran Keliling Bangunan U - 20 cm Tukang Batu[2];Pekerja[4] Mon 15/04/19 Fri 19/04/19 13 days 5 days 50,37 0 0 Tukang Batu[2];Pekerja[4]
termasuk urugan pasir, pasangan bata, plester
543 Pekerjaan Bak Kontrol 40 x 40 cm terpasang Tukang Batu[2];Pekerja[4] Mon 15/04/19 Fri 19/04/19 13 days 5 days 8 0 0 Tukang Batu[2];Pekerja[4]
sesuai gambar
544 PEKERJAAN GROUNDTANK Tue 26/02/19 Tue 14/05/19 152,95 days 78 days 0 0 0
547 Pembuatan Design Struktur Bangunan Tue 26/02/19 Wed 27/03/19 30 days 30 days 0 0 0
Page 7
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
553 PO Wed 03/04/19 Fri 05/04/19 3 days 3 days 0 0 0 25/02/19
554 Material On Site Sat 06/04/19 Fri 12/04/19 7 days 7 days 0 0 0
556 Galian tanah groundtank Excavator[2] Sun 24/03/19 Mon 25/03/19 2,5 days 2 days 309,1 0 0 Excavator[2]
557 Urugan tanah kembali groundtank Excavator[2] Fri 10/05/19 Fri 10/05/19 1,5 days 1 day 103,03 0 0 Excavator[2
558 Urugan pasir bawah groundtank Tukang Batu[2];Pekerja[4] Tue 26/03/19 Wed 27/03/19 3 days 2 days 5,83 0 0 Tukang Batu[2];Pekerja[4]
559 Lantai kerja bawah groundtank Tukang Batu[2];Pekerja[4] Sat 13/04/19 Sun 14/04/19 2 days 2 days 5,83 0 0 Tukang Batu[2];Pekerja[4]
560 Pekerjaan beton bertulang plat dasar groundtank t = Mon 15/04/19 Wed 17/04/19 3,25 days 3 days 0 0 0
20 cm
561 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Mon 15/04/19 Mon 15/04/19 1,75 days 1 day 3410,46 0 0 Tukang Besi[4];Pekerja[4]
562 - Bekisting plat dasar Tukang Kayu[4];Pekerja[4] Tue 16/04/19 Tue 16/04/19 0,5 days 1 day 14,99 0 0 Tukang Kayu[4];Pekerja[4]
563 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Wed 17/04/19 Wed 17/04/19 1 day 1 day 31,3 0 0 Tukang Batu[2];Pekerja[4]
564 Pekerjaan beton bertulang balok bagian bawah Thu 18/04/19 Sat 20/04/19 3 days 3 days 0 0 0
groundtank 20 x 30 cm
565 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Thu 18/04/19 Fri 19/04/19 2 days 2 days 249,03 0 0 Tukang Besi[4];Pekerja[4]
566 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Sat 20/04/19 Sat 20/04/19 1 day 1 day 1,06 0 0 Tukang Batu[2];Pekerja[4]
567 Pekerjaan beton bertulang balok bagian bawah Thu 18/04/19 Sat 20/04/19 3 days 3 days 0 0 0
groundtank 20 x 40 cm
568 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Thu 18/04/19 Fri 19/04/19 2 days 2 days 83,48 0 0 Tukang Besi[4];Pekerja[4]
569 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Sat 20/04/19 Sat 20/04/19 1 day 1 day 0,28 0 0 Tukang Batu[2];Pekerja[4]
570 Pekerjaan beton bertulang balok bagian atas Sun 21/04/19 Tue 23/04/19 3 days 3 days 0 0 0
groundtank 20 x 30 cm
571 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Sun 21/04/19 Mon 22/04/19 2 days 2 days 249,35 0 0 Tukang Besi[4];Pekerja[4]
572 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Tue 23/04/19 Tue 23/04/19 1 day 1 day 1,8 0 0 Tukang Batu[2];Pekerja[4]
573 Pekerjaan beton bertulang dinding groundtank t = 20 Wed 24/04/19 Sat 04/05/19 11 days 11 days 0 0 0
cm
574 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Wed 24/04/19 Sun 28/04/19 5 days 5 days 4030,72 0 0 Tukang Besi[4];Pekerja[
575 - Bekisting dinding Tukang Kayu[4];Pekerja[4] Mon 29/04/19 Fri 03/05/19 5 days 5 days 304,29 0 0 Tukang Kayu[4];Pe
576 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Sat 04/05/19 Sat 04/05/19 1 day 1 day 30,98 0 0 Tukang Batu[2];Pe
577 Pekerjaan beton bertulang plat atap groundtank t = Sun 05/05/19 Thu 09/05/19 5 days 5 days 0 0 0
15 cm
578 - Pembesian Ulir Tukang Besi[4];Pekerja[4] Sun 05/05/19 Mon 06/05/19 2 days 2 days 2648,05 0 0 Tukang Besi[4];
579 - Bekisting plat lantai Tukang Kayu[4];Pekerja[4] Tue 07/05/19 Wed 08/05/19 2 days 2 days 123,18 0 0 Tukang Kayu[
580 - Beton mutu K-300 Tukang Batu[2];Pekerja[4] Thu 09/05/19 Thu 09/05/19 1 day 1 day 17,21 0 0 Tukang Batu
581 Waterprofing integral beton groundtank Tukang Batu[2];Pekerja[4] Fri 10/05/19 Fri 10/05/19 2 days 1 day 79,49 0 0 Tukang Batu
582 Waterprofing system coating Tukang Batu[2];Pekerja[4] Sat 11/05/19 Sat 11/05/19 2 days 1 day 300,65 0 0 Tukang Ba
583 Waterstop PVC Tukang Kayu;Pekerja[4] Sun 12/05/19 Sun 12/05/19 1 day 1 day 60 0 0 Tukang Ka
584 Pekerjaan tutup groundtank dari besi ( lengkap Tukang Besi[4];Pekerja[4] Mon 13/05/19 Mon 13/05/19 1 day 1 day 3 0 0 Tukang B
terpasang termasuk asesories engsel, handle, dll dan
585 Pekerjaan keramik 30 x 30 polished Tukang Batu[2];Pekerja[4] Tue 14/05/19 Tue 14/05/19 2 days 1 day 300,65 0 0 Tukang
586 Pekerjaan tangga servis stainless steel ( lengkap Tukang Besi[4];Pekerja[4] Fri 10/05/19 Sun 12/05/19 5 days 3 days 3 0 0 Tukang Be
terpasang termasuk asesories dll sesuai gambar )
587 PEKERJAAN POS JAGA 3 UNIT Thu 21/02/19 Mon 13/05/19 197,7 days 82 days 0 0 0
590 Pembuatan Design Struktur Bangunan Tue 26/02/19 Wed 27/03/19 30 days 30 days 0 0 0
603 Dinding Bata Ringan Fri 03/05/19 Sat 04/05/19 10 days 2 days 0 0 0
612 Kusen, Daun Pintu dan Jendela Mon 06/05/19 Tue 07/05/19 10 days 2 days 0 0 0
617 Galian tanah pondasi batu belah Excavator Thu 21/02/19 Sun 24/03/19 5 days 5 days 34,22 0 22,82 Excavator
618 Urugan sirtu bawah pondasi batu belah Tukang Batu[3];Pekerja[6] Mon 25/02/19 Mon 25/03/19 2 days 2 days 7,9 0 7,61 Tukang Batu[3];Pekerja[6]
619 Pekerjaan pondasi batu belah Tukang Batu[3];Pekerja[6] Mon 25/02/19 Fri 29/03/19 5 days 5 days 20,48 0 5,27 Tukang Batu[3];Pekerja[6]
620 Urugan tanah kembali pondasi batu belah Tukang Batu[3];Pekerja[6] Mon 25/02/19 Sat 06/04/19 3 days 3 days 11,41 0 13,65 Tukang Batu[3];Pekerja[6]
621 Pekerjaan urugan pasir bawah lantai Tukang Batu[3];Pekerja[6] Sun 07/04/19 Sun 07/04/19 5 days 1 day 3,8 0 0 Tukang Batu[3];Pekerja[6]
622 Pekerjaan lantai kerja bawah lantai Tukang Batu[3];Pekerja[6] Sat 13/04/19 Sat 13/04/19 5 days 1 day 1,9 0 0 Tukang Batu[3];Pekerja[6]
623 Pekerjaan urugan tanah peninggian lantai Tukang Batu[3];Pekerja[6] Sun 14/04/19 Sun 14/04/19 5 days 1 day 22,8 0 0 Tukang Batu[3];Pekerja[6]
624 Pekerjaan pemadatan Tukang Batu[3];Pekerja[6] Sun 21/04/19 Sun 21/04/19 5 days 1 day 22,8 0 0 Tukang Batu[3];Pekerja[6]
625 Pekerjaan beton bertulang sloof type S1 Mon 25/02/19 Thu 04/04/19 2,5 days 39 days 0 0 0
Page 8
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
632 - Beton mutu K-225 Tukang Batu[2];Pekerja[2] Mon 25/02/19 Thu 04/04/19 3 days 3 days 0,5 0 38,76 25/02/19 Tukang Batu[2];Pekerja[2]
633 Pekerjaan kolom type Kp Mon 25/02/19 Sat 20/04/19 9 days 55 days 0 0 0
665 Pasangan dinding bata ringan tebal 10 cm Tukang Batu[2];Pekerja[2] Sat 04/05/19 Sun 05/05/19 2,5 days 2 days 142,24 0 0 Tukang Batu[2];P
666 Plesteran dinding bata ringan Tukang Batu[2];Pekerja[2] Sat 04/05/19 Sun 05/05/19 5 days 2 days 284,49 0 0 Tukang Batu[2];P
667 Acian dinding bata ringan Tukang Batu[2];Pekerja[2] Sat 04/05/19 Sun 05/05/19 5 days 2 days 172,41 0 0 Tukang Batu[2];P
668 Sponengan sudut Tukang Batu[2];Pekerja[2] Sat 04/05/19 Sun 05/05/19 5 days 2 days 104,82 0 0 Tukang Batu[2];P
669 Pekerjaan plafond gypsumboard + rangka hollow 4/4Tukang Kayu[2];Tukang Besi[2] Sat 04/05/19 Sun 05/05/19 2,5 days 2 days 18,75 0 0 Tukang Kayu[2];T
670 Pekerjaan cat plafond Tukang Kayu[2] Sat 04/05/19 Sat 04/05/19 1 day 1 day 18,75 0 0 Tukang Kayu[2]
671 Pekerjaan list gypsum Tukang Kayu[2] Sat 04/05/19 Sat 04/05/19 2 days 1 day 30 0 0 Tukang Kayu[2]
672 Pekerjaan cat interior Tukang Kayu[2] Sun 05/05/19 Sun 05/05/19 2 days 1 day 10,53 0 0 Tukang Kayu[2]
673 Pekerjaan cat exterior Tukang Kayu[2] Mon 06/05/19 Mon 06/05/19 5 days 1 day 190,54 0 0 Tukang Kayu[2]
674 Pasangan penutup lantai keramik 30 x 30 cm polished
Tukang Batu[2];Pekerja[2] Sun 12/05/19 Sun 12/05/19 2 days 1 day 16,97 0 0 Tukang Ba
675 Pasangan penutup lantai keramik 30 x 30 cm unpolished
Tukang Batu[2];Pekerja[2] Sun 12/05/19 Sun 12/05/19 2 days 1 day 15,91 0 0 Tukang Ba
676 Pasangan penutup dinding keramik 30 x 30 cm polished
Tukang Batu[2];Pekerja[2] Sun 12/05/19 Sun 12/05/19 2 days 1 day 95,94 0 0 Tukang Ba
677 Pasangan penutup dinding keramik 10 x 30 cm motifTukang Batu[2];Pekerja[2] Sun 12/05/19 Sun 12/05/19 2 days 1 day 1,62 0 0 Tukang Ba
678 Pasangan keramik meja beton 30 x 30 cm polished Tukang Batu[2];Pekerja[2] Fri 03/05/19 Fri 03/05/19 2 days 1 day 4,94 0 0 Tukang Batu[2];Pe
679 Pekerjaan closet jongkok Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 3 0 0 Tukang B
680 Pekerjaan floor drain Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 3 0 0 Tukang B
681 Pekerjaan keran toilet Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 3 0 0 Tukang B
682 Pekerjaan gantungan (rob hook) Tukang Batu[2];Pekerja[2] Sun 12/05/19 Mon 13/05/19 2 days 2 days 3 0 0 Tukang B
683 Urugan sirtu bawah rabat beton, t = 10 cm Tukang Batu[2];Pekerja[2] Thu 28/02/19 Thu 28/02/19 1 day 1 day 1,9 0 0 Tukang Batu[2];Pekerja[2]
684 Rabat beton keliling bangunan, t = 10 cm Tukang Batu[2];Pekerja[2] Fri 01/03/19 Fri 01/03/19 1 day 1 day 3,8 0 0 Tukang Batu[2];Pekerja[2]
685 Pekerjaan plesteran rabat beton Tukang Batu[2];Pekerja[2] Sat 02/03/19 Sun 03/03/19 4 days 2 days 38,03 0 0 Tukang Batu[2];Pekerja[2]
686 Pekerjaan acian rabat beton Tukang Batu[2];Pekerja[2] Mon 04/03/19 Tue 05/03/19 4 days 2 days 38,03 0 0 Tukang Batu[2];Pekerja[2]
687 Pekerjaan cat Beton expose Tukang Batu[2] Wed 06/03/19 Fri 08/03/19 7 days 3 days 44,18 0 0 Tukang Batu[2]
688 Pekerjaan portal dari pipa besi fin cat termasuk Tukang Batu[2];Pekerja[2] Sat 09/03/19 Mon 11/03/19 7 days 3 days 3 0 0 Tukang Batu[2];Pekerja[2]
pondasi portal dll terpasang sesuai dengan gambar
689 Pekerjaan kosen dan daun pintu / jendela dan Tue 07/05/19 Sat 11/05/19 4,5 days 5 days 0 0 0
hardware dan assesorisnya terpasang sesuai
690 Pekerjaan kusen type P1 Tukang Kayu[2];Pekerja[2] Tue 07/05/19 Tue 07/05/19 0,5 days 1 day 3 0 0 Tukang Kayu[2
691 Pekerjaan kusen type P2 Tukang Kayu[2];Pekerja[2] Wed 08/05/19 Wed 08/05/19 1 day 1 day 3 0 0 Tukang Kayu[
692 Pekerjaan kusen type J1 Tukang Kayu[2];Pekerja[2] Thu 09/05/19 Thu 09/05/19 1 day 1 day 6 0 0 Tukang Kayu
693 Pekerjaan kusen type J2 Tukang Kayu[2];Pekerja[2] Fri 10/05/19 Fri 10/05/19 1 day 1 day 3 0 0 Tukang Kay
694 Pekerjaan kusen type BV Tukang Kayu[2];Pekerja[2] Sat 11/05/19 Sat 11/05/19 1 day 1 day 3 0 0 Tukang Ka
695 Pekerjaan rangka atap + penutup atap Wed 08/05/19 Wed 08/05/19 4,5 days 1 day 0 0 0
696 Rangka atap baja ringan Tukang Besi[4];Pekerja[2] Wed 08/05/19 Wed 08/05/19 0,5 days 1 day 33,36 0 0 Tukang Besi[4
697 Penutup atap zincalume t = 0,5 mm Tukang Besi[4];Pekerja[2] Wed 08/05/19 Wed 08/05/19 2 days 1 day 33,36 0 0 Tukang Besi[4
698 Lapisan alumunium foil + roofmesh Tukang Besi[4];Pekerja[2] Wed 08/05/19 Wed 08/05/19 2 days 1 day 33,36 0 0 Tukang Besi[4
699 PEKERJAAN INFRASTRUKTUR Tue 18/12/18 Tue 14/05/19 209,87 days 148 days 0 0 0
701 Perkerasan & Saluran Areal Bangunan Tue 26/02/19 Tue 02/04/19 36 days 36 days 0 0 0
702 Pembuatan Perkerasan & Saluran Bangunan Tue 26/02/19 Wed 27/03/19 30 days 30 days 0 0 0
705 Pagar Precast 5x40x240 cm kolom 170x180x3200 Tue 26/02/19 Tue 02/04/19 36 days 36 days 0 0 0
706 Pembuatan Perkerasan & Saluran Bangunan Tue 26/02/19 Wed 27/03/19 30 days 30 days 0 0 0
710 Perkerasan & Saluran Areal Bangunan Wed 03/04/19 Fri 12/04/19 10 days 10 days 0 0 0
Page 9
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
711 U Ditch-40 Wed 03/04/19 Fri 12/04/19 10 days 10 days 0 0 0 25/02/19
712 PO Wed 03/04/19 Fri 05/04/19 3 days 3 days 0 0 0
717 Box Culvert 40.40.100 Wed 03/04/19 Fri 12/04/19 10 days 10 days 0 0 0
720 Box Culvert 50.50.100 Wed 03/04/19 Fri 12/04/19 10 days 10 days 0 0 0
724 Pagar Precast 5x40x240 cm kolom 170x180x3200 Wed 03/04/19 Fri 12/04/19 10 days 10 days 0 0 0
727 Construction Tue 18/12/18 Tue 14/05/19 151,67 days 148 days 0 0 0
728 VII.1. Pekerjaan Perkerasan & Saluran Areal Tue 18/12/18 Fri 19/04/19 68,5 days 122,5 days 0 0 0
Bangunan
729 Pekerjaan cut/galian tanah (mekanis) Buldozer[2];Excavator[3] Tue 18/12/18 Tue 01/01/19 15 days 15 days 40629,79 0 40629,79 Buldozer[2];Excavator[3]
730 Pekerjaan buang tanah keluar area pekerjaan Dump Truck[4] Tue 18/12/18 Wed 13/03/19 80 days 80 days 40629,79 0 36371,61 Dump Truck[4]
(mekanis)
731 Pekerjaan pasir urug, t = 5 cm Buldozer[2] Tue 26/02/19 Mon 04/03/19 7 days 7 days 1419,31 0 0 Buldozer[2]
732 Pekerjaan sub base course KI.B CBR 60 % Buldozer[2] Sun 03/02/19 Sat 16/02/19 14 days 14 days 8515,88 0 8515,88 Buldozer[2]
733 Pekerjaan pemadatan tanah dasar Vibro Roller[2] Fri 01/02/19 Thu 07/02/19 7 days 7 days 28386,28 0 28386,28 Vibro Roller[2]
734 Geotextille non woven Subkontraktor Sat 02/02/19 Fri 15/02/19 14 days 14 days 28386,28 0 28386,28 Subkontraktor
735 Pekerjaan paving Tukang Batu[25];Pekerja[20] Tue 26/02/19 Tue 26/02/19 0,48 days 0,48 days 9951,83 0 0 Tukang Batu[25];Pekerja[20]
736 Pekerjaan kansteen beton Tukang Batu[5];Pekerja[5] Tue 26/02/19 Mon 01/04/19 35 days 35 days 806,77 0 0 Tukang Batu[5];Pekerja[5]
737 Pekerjaan cat kansteen Tukang Batu[5];Pekerja[5] Tue 02/04/19 Thu 04/04/19 3 days 3 days 477,93 0 0 Tukang Batu[5];Pekerja[5]
738 Pekerjaan urugan tanah Buldozer[2];Excavator[3] Mon 18/02/19 Wed 20/02/19 2 days 3 days 1372,28 0 1372,28 Buldozer[2];Excavator[3]
739 Pekerjaan plat beton bertulang area "OPEN YARD" Fri 08/02/19 Tue 02/04/19 24,3 days 54 days 0 0 0
744 - Pembesian ulir tiebar Tukang Besi[5];Pekerja[5] Thu 14/02/19 Sat 02/03/19 14 days 14 days 5252,7 0 1418,08 Tukang Besi[5];Pekerja[5]
745 - Pembesian polos cross bar Tukang Besi[5];Pekerja[5] Tue 26/02/19 Mon 04/03/19 7 days 7 days 5252,22 0 1417,95 Tukang Besi[5];Pekerja[5]
746 - Pembesian polos chair Tukang Besi[5];Pekerja[5] Wed 20/02/19 Wed 27/02/19 7 days 7 days 1359,05 0 366,91 Tukang Besi[5];Pekerja[5]
747 - Pekerjaan cat anti karat Tukang Besi[5];Pekerja[5] Mon 25/02/19 Fri 08/03/19 5 days 5 days 27,88 0 4,74 Tukang Besi[5];Pekerja[5]
748 - Pembesian polos dowel : Mon 18/02/19 Wed 20/03/19 15 days 30,4 days 0 0 0
749 - Pembesian polos dowel Tukang Besi[5];Pekerja[5] Mon 18/02/19 Tue 26/02/19 7 days 7 days 34104,87 0 9207,35 Tukang Besi[5];Pekerja[5]
750 - Pembesian polos chair Tukang Besi[5];Pekerja[5] Thu 21/02/19 Sun 24/02/19 3 days 4 days 4605,1 0 1243,25 Tukang Besi[5];Pekerja[5]
751 - Pembesian polos cross bar Tukang Besi[5];Pekerja[5] Sat 23/02/19 Fri 01/03/19 7 days 7 days 17796,48 0 4804,54 Tukang Besi[5];Pekerja[5]
752 - Pekerjaan cat anti karat Tukang Besi[5];Pekerja[5] Sun 24/02/19 Wed 20/03/19 5 days 5 days 188,94 0 32,11 Tukang Besi[5];Pekerja[5]
753 - Pekerjaan pipa 1,5" Tukang Besi[5];Pekerja[5] Sun 24/02/19 Thu 28/02/19 5 days 5 days 5638,2 0 958,33 Tukang Besi[5];Pekerja[5]
754 Pekerjaan urugan pasir bawah U Ditch Tukang Batu[5];Pekerja[5] Thu 14/03/19 Thu 14/03/19 0,4 days 0,4 days 18,82 0 0 Tukang Batu[5];Pekerja[5]
755 Pekerjaan saluran U Ditch-40 Excavator[2] Sat 13/04/19 Sun 14/04/19 1,5 days 1,5 days 627,46 0 0 Excavator[2]
756 Pekerjaan bak kontrol 60 x 60 cm terpasang sesuai Tukang Batu[10];Pekerja[10] Wed 20/03/19 Thu 21/03/19 2 days 2 days 7 0 0 Tukang Batu[10];Pekerja[10]
gambar
757 - Joint sealer Tukang Batu[10];Pekerja[10] Sun 14/04/19 Fri 19/04/19 5 days 5 days 8965,97 0 0 Tukang Batu[10];Pekerja[10]
758 Pekerjaan tutup beton bertulang saluran U Ditch-40 Thu 14/03/19 Tue 19/03/19 5 days 5 days 0 0 0
759 - Pembesian Polos Tukang Besi[5];Pekerja[5] Thu 14/03/19 Sun 17/03/19 3 days 3 days 3663,15 0 0 Tukang Besi[5];Pekerja[5]
760 - Bekisting plat Pekerja[5];Tukang Kayu[5] Fri 15/03/19 Sun 17/03/19 2 days 2 days 470,7 0 0 Pekerja[5];Tukang Kayu[5]
761 - Beton mutu K-225 Tukang Batu[5];Pekerja[5] Sun 17/03/19 Tue 19/03/19 2 days 2 days 34,51 0 0 Tukang Batu[5];Pekerja[5]
762 Pekerjaan tutup beton bertulang bak kontrol 60 x 60 cm Sun 17/03/19 Tue 19/03/19 3 days 3 days 0 0 0
763 - Pembesian Polos Tukang Besi[5];Pekerja[5] Sun 17/03/19 Mon 18/03/19 2 days 2 days 45,05 0 0 Tukang Besi[5];Pekerja[5]
764 - Bekisting plat Pekerja[5];Tukang Kayu[5] Mon 18/03/19 Mon 18/03/19 1 day 1 day 6,04 0 0 Pekerja[5];Tukang Kayu[5]
765 - Beton mutu K-225 Tukang Batu[5];Pekerja[5] Tue 19/03/19 Tue 19/03/19 1 day 1 day 0,39 0 0 Tukang Batu[5];Pekerja[5]
766 Pekerjaan urugan pasir bawah U Ditch Tukang Batu[5];Pekerja[5] Thu 14/03/19 Fri 15/03/19 2 days 2 days 24,51 0 0 Tukang Batu[5];Pekerja[5]
767 Pekerjaan koral untuk isian bak kontrol 60 x 60 cm Tukang Batu[5];Pekerja[5] Sat 16/03/19 Sat 16/03/19 1 day 1 day 0,38 0 0 Tukang Batu[5];Pekerja[5]
768 Pekerjaan saluran U Ditch-50 Excavator[2] Sat 16/03/19 Wed 20/03/19 5 days 5 days 700,25 0 0 Excavator[2]
769 Pekerjaan bak kontrol 70 x 70 cm terpasang sesuai Tukang Batu[10];Pekerja[10] Wed 20/03/19 Wed 20/03/19 1 day 1 day 4 0 0 Tukang Batu[10];Pekerja[10]
gambar
770 Pekerjaan tutup beton bertulang saluran U Ditch-50 Thu 14/03/19 Mon 18/03/19 4 days 4 days 0 0 0
771 - Pembesian Polos Tukang Besi[5];Pekerja[5] Thu 14/03/19 Sun 17/03/19 3 days 3 days 4807,53 0 0 Tukang Besi[5];Pekerja[5]
772 - Bekisting plat Pekerja[5];Tukang Kayu[5] Fri 15/03/19 Sun 17/03/19 2 days 2 days 595,34 0 0 Pekerja[5];Tukang Kayu[5]
773 - Beton mutu K-225 Tukang Batu[5];Pekerja[5] Sun 17/03/19 Mon 18/03/19 1 day 1 day 45,52 0 0 Tukang Batu[5];Pekerja[5]
774 Pekerjaan tutup beton bertulang bak kontrol 70 x 70 cm Mon 18/03/19 Thu 21/03/19 3 days 3 days 0 0 0
775 - Pembesian Polos Tukang Besi[5];Pekerja[5] Mon 18/03/19 Wed 20/03/19 2 days 2 days 33,49 0 0 Tukang Besi[5];Pekerja[5]
776 - Bekisting plat Pekerja[5];Tukang Kayu[5] Tue 19/03/19 Wed 20/03/19 1 day 1 day 4,25 0 0 Pekerja[5];Tukang Kayu[5]
777 - Beton mutu K-225 Tukang Batu[5];Pekerja[5] Wed 20/03/19 Thu 21/03/19 1 day 1 day 0,29 0 0 Tukang Batu[5];Pekerja[5]
778 Pekerjaan koral untuk isian bak kontrol 70 x 70 cm Tukang Batu[5];Pekerja[5] Thu 21/03/19 Fri 22/03/19 1 day 1 day 0,29 0 0 Tukang Batu[5];Pekerja[5]
779 Pekerjaan buis beton Ø20 cm Excavator[2] Fri 22/03/19 Sun 24/03/19 2 days 2 days 31,43 0 0 Excavator[2]
780 Pekerjaan box culvert 40.40.100 Excavator[2] Sat 13/04/19 Sat 13/04/19 1 day 1 day 9,28 0 0 Excavator[2]
781 Pekerjaan box culvert 50.50.100 Excavator[2] Sun 14/04/19 Mon 15/04/19 2 days 2 days 19,94 0 0 Excavator[2]
782 Pekerjaan peresapan Ø 100 cm Tue 26/02/19 Wed 06/03/19 9 days 9 days 0 0 0
783 - Pekerjaan galian tanah Tukang Batu[5];Pekerja[5] Tue 26/02/19 Thu 28/02/19 3 days 3 days 9,42 0 0 Tukang Batu[5];Pekerja[5]
784 - Pekerjaan buang tanah Alat bantu[1];Excavator Tue 26/02/19 Thu 28/02/19 3 days 3 days 9,42 0 0 Alat bantu[1];Excavator
785 - Lapisan batu pecah Tukang Batu[5];Pekerja[5] Fri 01/03/19 Sat 02/03/19 2 days 2 days 4,71 0 0 Tukang Batu[5];Pekerja[5]
786 - Pasang buis beton Ø 100 cm Excavator[2] Sun 03/03/19 Mon 04/03/19 2 days 2 days 6 0 0 Excavator[2]
787 - Tutup beton peresapan Ø 100 cm, t = 12 cm Excavator[2] Tue 05/03/19 Wed 06/03/19 2 days 2 days 2 0 0 Excavator[2]
788 Pekerjaan pintu keamanan area "Open Yard" dari Tukang Thu 07/03/19 Fri 08/03/19 2 days 2 days 1 0 0 Tukang Besi[5];Pekerja[5];Crane
plat besi panjang 16 m dan tinggi 3 m, lengkap Besi[5];Pekerja[5];Crane
789 VII.2. Pekerjaan Pagar Keliling Thu 31/01/19 Tue 14/05/19 144,67 days 104 days 0 0 0
Page 10
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
790 VII.2.1 Pekerjaan Pagar Type A Tue 14/05/19 Tue 14/05/19 12 days 1 day 0 0 0 25/02/19
791 Pekerjaan talud batu belah Tue 14/05/19 Tue 14/05/19 9 days 1 day 0 0 0
792 - Galian tanah talud batu belah Excavator Tue 14/05/19 Tue 14/05/19 2 days 1 day 75,6 0 0 Excavat
793 - Urugan sirtu Tukang Batu[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 1 day 1 day 16,8 0 0 Tukang
794 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 2 days 1 day 156,8 0 0 Tukang
795 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 1 day 1 day 25,2 0 0 Tukang
796 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Tue 14/05/19 Tue 14/05/19 3 days 1 day 70 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
797 Pekerjaan plesteran siar Tukang Batu[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 2 days 1 day 54,1 0 0 Tukang
798 Pekerjaan pipa PVC Ø1" Tukang Batu[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 2 days 1 day 98,94 0 0 Tukang
799 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Besi[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 3 days 1 day 63,36 0 0 Tukang
terpasang termasuk asesories, mur baut, cat
800 Pekerjaan kawat duri terpasang Tukang Besi[5];Pekerja[5] Tue 14/05/19 Tue 14/05/19 2 days 1 day 210 0 0 Tukang
801 VII.2.2 Pekerjaan Pagar Type B Tue 26/02/19 Tue 02/04/19 36 days 36 days 0 0 0
802 Pekerjaan talud batu belah Tue 26/02/19 Sat 23/03/19 26 days 26 days 0 0 0
803 - Galian tanah talud batu belah Excavator Tue 26/02/19 Fri 01/03/19 4 days 4 days 24,6 0 0 Excavator
804 - Urugan sirtu Tukang Batu[5];Pekerja[5] Sat 02/03/19 Tue 05/03/19 4 days 4 days 5,68 0 0 Tukang Batu[5];Pekerja[5]
805 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Wed 06/03/19 Sat 09/03/19 4 days 4 days 33,12 0 0 Tukang Batu[5];Pekerja[5]
806 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Wed 20/03/19 Sat 23/03/19 4 days 4 days 8,2 0 0 Tukang Batu[5];Pekerja[5]
807 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Sun 10/03/19 Tue 19/03/19 10 days 10 days 47,31 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
808 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Sun 10/03/19 Tue 19/03/19 10 days 10 days 43,69 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
809 Pekerjaan pipa PVC Ø1" Tukang Batu[5];Pekerja[5] Wed 06/03/19 Tue 12/03/19 7 days 7 days 23,25 0 0 Tukang Batu[5];Pekerja[5]
810 Pekerjaan plesteran siar Tukang Besi[5];Pekerja[5] Wed 20/03/19 Tue 26/03/19 7 days 7 days 13,28 0 0 Tukang Besi[5];Pekerja[5]
811 Pekerjaan kawat duri terpasang Tukang Besi[5];Pekerja[5] Wed 27/03/19 Tue 02/04/19 7 days 7 days 141,93 0 0 Tukang Besi[5];Pekerja[5]
812 VII.2.3 Pekerjaan Pagar Type C Tue 26/02/19 Sat 30/03/19 33 days 33 days 0 0 0
813 Pekerjaan pondasi batu belah Tue 26/02/19 Wed 20/03/19 23 days 23 days 0 0 0
814 - Galian tanah pondasi batu belah Excavator Tue 26/02/19 Fri 01/03/19 4 days 4 days 31,2 0 0 Excavator
815 - Urugan sirtu Tukang Batu[5];Pekerja[5] Sat 02/03/19 Tue 05/03/19 4 days 4 days 7,2 0 0 Tukang Batu[5];Pekerja[5]
816 - Pasangan pondasi batu belah Tukang Batu[5];Pekerja[5] Wed 06/03/19 Sat 09/03/19 4 days 4 days 42 0 0 Tukang Batu[5];Pekerja[5]
817 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Sun 17/03/19 Wed 20/03/19 4 days 4 days 10,4 0 0 Tukang Batu[5];Pekerja[5]
818 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Sun 10/03/19 Sat 16/03/19 7 days 7 days 60 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
819 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Sun 10/03/19 Sat 16/03/19 7 days 7 days 54,62 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
820 Pekerjaan pipa PVC Ø1" Tukang Batu[5];Pekerja[5] Wed 06/03/19 Sun 10/03/19 5 days 5 days 28,55 0 0 Tukang Batu[5];Pekerja[5]
821 Pekerjaan plesteran siar Tukang Besi[5];Pekerja[5] Sun 17/03/19 Sat 23/03/19 7 days 7 days 16,85 0 0 Tukang Besi[5];Pekerja[5]
822 Pekerjaan kawat duri terpasang Tukang Besi[5];Pekerja[5] Sun 24/03/19 Sat 30/03/19 7 days 7 days 180 0 0 Tukang Besi[5];Pekerja[5]
823 VII.2.4 Pekerjaan Pagar Type D Thu 31/01/19 Fri 26/04/19 36 days 86 days 0 0 0
824 Pekerjaan talud batu belah Thu 31/01/19 Sat 13/04/19 23 days 73 days 0 0 0
825 - Galian tanah talud batu belah Excavator Thu 31/01/19 Mon 11/03/19 21 days 21 days 207,07 0 51,77 Excavator
826 - Urugan sirtu Tukang Batu[5];Pekerja[5] Mon 18/02/19 Mon 25/03/19 21 days 21 days 46,02 0 11,5 Tukang Batu[5];Pekerja[5]
827 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Mon 18/02/19 Tue 02/04/19 14 days 14 days 353,48 0 88,37 Tukang Batu[5];Pekerja[5]
828 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Wed 10/04/19 Sat 13/04/19 4 days 4 days 69,02 0 0 Tukang Batu[5];Pekerja[5]
829 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Wed 03/04/19 Tue 09/04/19 7 days 7 days 209,16 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
830 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Wed 10/04/19 Sun 14/04/19 5 days 5 days 185,7 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
831 Pekerjaan kawat duri terpasang Tukang Batu[5];Pekerja[5] Sat 20/04/19 Fri 26/04/19 7 days 7 days 627,48 0 0 Tukang Batu[5];Pekerja[5
832 Pekerjaan plesteran siar Tukang Besi[5];Pekerja[5] Wed 10/04/19 Fri 19/04/19 10 days 10 days 123,39 0 0 Tukang Besi[5];Pekerja[5]
833 Pekerjaan pipa PVC Ø1" Tukang Besi[5];Pekerja[5] Mon 18/02/19 Tue 26/03/19 7 days 7 days 286,85 0 71,71 Tukang Besi[5];Pekerja[5]
834 VII.2.5 Pekerjaan Pagar Type E Thu 31/01/19 Thu 09/05/19 36 days 99 days 0 0 0
835 Pekerjaan talud batu belah Thu 31/01/19 Fri 26/04/19 23 days 86 days 0 0 0
836 - Galian tanah talud batu belah Excavator Thu 31/01/19 Sat 02/02/19 3 days 3 days 33,3 0 33,3 Excavator
837 - Urugan sirtu Tukang Batu[5];Pekerja[5] Sat 02/02/19 Sun 03/02/19 2 days 2 days 18 0 18 Tukang Batu[5];Pekerja[5]
838 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Sun 03/02/19 Wed 06/02/19 4 days 4 days 99 0 99 Tukang Batu[5];Pekerja[5]
839 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Tue 23/04/19 Fri 26/04/19 4 days 4 days 11,1 0 0 Tukang Batu[5];Pekerja[5
840 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Sat 13/04/19 Mon 22/04/19 10 days 10 days 100 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
841 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Tue 23/04/19 Thu 02/05/19 10 days 10 days 89,57 0 0 Tukang Batu[5];Pek
terpasang termasuk asesories, mur baut, cat
842 Pekerjaan kawat duri terpasang Tukang Batu[5];Pekerja[5] Fri 03/05/19 Thu 09/05/19 7 days 7 days 300 0 0 Tukang Batu
843 Pekerjaan plesteran siar Tukang Besi[5];Pekerja[5] Tue 23/04/19 Sat 27/04/19 5 days 5 days 34,22 0 0 Tukang Besi[5];Pekerja[5
844 Pekerjaan pipa PVC Ø1" Tukang Besi[5];Pekerja[5] Mon 04/02/19 Fri 08/02/19 5 days 5 days 57,97 0 57,97 Tukang Besi[5];Pekerja[5]
845 VII.2.6 Pekerjaan Pagar Type F Fri 01/02/19 Wed 27/03/19 41 days 55 days 0 0 0
846 Pekerjaan talud batu belah Fri 01/02/19 Sun 10/03/19 24 days 38 days 0 0 0
847 - Galian tanah talud batu belah Excavator Fri 01/02/19 Sun 03/02/19 3 days 3 days 87,55 0 87,55 Excavator
848 - Urugan sirtu Tukang Batu[5];Pekerja[5] Sun 03/02/19 Tue 05/02/19 3 days 3 days 15,45 0 15,45 Tukang Batu[5];Pekerja[5]
849 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Mon 04/02/19 Fri 08/02/19 5 days 5 days 51,5 0 51,5 Tukang Batu[5];Pekerja[5]
850 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Fri 08/03/19 Sun 10/03/19 3 days 3 days 29,18 0 0 Tukang Batu[5];Pekerja[5]
851 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Tue 26/02/19 Thu 07/03/19 10 days 10 days 114,44 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
852 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Fri 08/03/19 Sun 17/03/19 10 days 10 days 102,68 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
853 Pekerjaan kawat duri terpasang Tukang Batu[5];Pekerja[5] Mon 18/03/19 Wed 27/03/19 10 days 10 days 343,32 0 0 Tukang Batu[5];Pekerja[5]
854 VII.2.7 Pekerjaan Pagar Type G Fri 01/02/19 Thu 21/03/19 35 days 49 days 0 0 0
855 Pekerjaan talud batu belah Fri 01/02/19 Wed 20/02/19 24 days 20 days 0 0 0
856 - Galian tanah talud batu belah Excavator Fri 01/02/19 Sun 03/02/19 3 days 3 days 67,95 0 67,95 Excavator
857 - Urugan sirtu Tukang Batu[5];Pekerja[5] Tue 05/02/19 Thu 07/02/19 3 days 3 days 29,12 0 29,12 Tukang Batu[5];Pekerja[5]
858 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Fri 08/02/19 Tue 12/02/19 5 days 5 days 97,07 0 97,07 Tukang Batu[5];Pekerja[5]
859 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Mon 18/02/19 Wed 20/02/19 3 days 3 days 22,65 0 22,65 Tukang Batu[5];Pekerja[5]
860 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Tue 26/02/19 Thu 07/03/19 10 days 10 days 215,71 0 0 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
861 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Fri 08/03/19 Thu 14/03/19 7 days 7 days 192,25 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
862 Pekerjaan kawat duri terpasang Tukang Batu[5];Pekerja[5] Fri 15/03/19 Thu 21/03/19 7 days 7 days 647,13 0 0 Tukang Batu[5];Pekerja[5]
863 VII.2.8 Pekerjaan Pagar Type H Sat 02/02/19 Sat 23/03/19 37 days 50 days 0 0 0
864 Pekerjaan talud batu belah Sat 02/02/19 Sun 17/02/19 16 days 16 days 0 0 0
865 - Galian tanah talud batu belah Excavator Sat 02/02/19 Mon 04/02/19 3 days 3 days 59,4 0 59,4 Excavator
866 - Urugan sirtu Tukang Batu[5];Pekerja[5] Tue 05/02/19 Thu 07/02/19 3 days 3 days 13,2 0 13,2 Tukang Batu[5];Pekerja[5]
867 - Pasangan talud batu belah Tukang Batu[5];Pekerja[5] Fri 08/02/19 Tue 12/02/19 5 days 5 days 113,1 0 113,1 Tukang Batu[5];Pekerja[5]
868 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Fri 15/02/19 Sun 17/02/19 3 days 3 days 19,8 0 19,8 Tukang Batu[5];Pekerja[5]
Page 11
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
869 Pekerjaan pagar precast 5 x 40 x 240 cm Crane Tue 26/02/19 Mon 04/03/19 7 days 7 days 60 0 0 25/02/19 Crane
dengan kolom ukuran 170 x 180 x 3200 mm
870 Pekerjaan baja siku L 50.50.5 atas pagar precast Tukang Batu[5];Pekerja[5] Tue 05/03/19 Mon 11/03/19 7 days 7 days 54,62 0 0 Tukang Batu[5];Pekerja[5]
terpasang termasuk asesories, mur baut, cat
871 Pekerjaan kawat duri terpasang Tukang Batu[5];Pekerja[5] Tue 19/03/19 Sat 23/03/19 5 days 5 days 180 0 0 Tukang Batu[5];Pekerja[5]
872 Pekerjaan plesteran siar Tukang Besi[5];Pekerja[5] Tue 12/03/19 Mon 18/03/19 7 days 7 days 40,73 0 0 Tukang Besi[5];Pekerja[5]
873 Pekerjaan pipa PVC Ø1" Tukang Besi[5];Pekerja[5] Fri 08/02/19 Thu 14/02/19 7 days 7 days 83,23 0 83,23 Tukang Besi[5];Pekerja[5]
874 VII.3. Pekerjaan Tower Air 5 unit Mon 25/02/19 Tue 14/05/19 31,4 days 79 days 0 0 0
875 Pekerjaan pondasi footplat Mon 25/02/19 Thu 02/05/19 5,4 days 67 days 0 0 0
876 - Galian tanah pondasi footplat Excavator Thu 11/04/19 Thu 11/04/19 1 day 1 day 39,93 0 0 Excavator
877 - Urugan sirtu Excavator Fri 12/04/19 Fri 12/04/19 1 day 1 day 2,42 0 0 Excavator
878 - Lantai kerja Tukang Batu[5];Pekerja[5] Sat 13/04/19 Sat 13/04/19 1 day 1 day 1,21 0 0 Tukang Batu[5];Pekerja[5]
879 - Pembesian polos Tukang Besi[5];Pekerja[5] Mon 25/02/19 Fri 19/04/19 7 days 7 days 543,88 0 435,1 Tukang Besi[5];Pekerja[5]
880 - Bekisting pondasi Tukang Kayu[5];Pekerja[5] Mon 25/02/19 Thu 25/04/19 7 days 7 days 12,8 0 10,24 Tukang Kayu[5];Pekerja[5]
881 - Pekerjaan beton K-225 Tukang Batu[5];Pekerja[5] Mon 25/02/19 Wed 01/05/19 7 days 7 days 4,48 0 3,58 Tukang Batu[5];Peke
882 - Urugan tanah kembali bekas galian Tukang Batu[5];Pekerja[5] Thu 02/05/19 Thu 02/05/19 1 day 1 day 13,31 0 0 Tukang Batu[5];Pek
883 Pekerjaan sloof 15 x 25 cm Fri 03/05/19 Sun 05/05/19 3 days 3 days 0 0 0
884 - Pembesian polos Tukang Besi[5];Pekerja[5] Fri 03/05/19 Fri 03/05/19 1 day 1 day 267,23 0 0 Tukang Besi[5];Pek
885 - Bekisting sloof Tukang Kayu[5];Pekerja[5] Sat 04/05/19 Sat 04/05/19 1 day 1 day 25,5 0 0 Tukang Kayu[5];P
886 - Pekerjaan beton K-225 Tukang Batu[5];Pekerja[5] Sun 05/05/19 Sun 05/05/19 1 day 1 day 1,91 0 0 Tukang Batu[5];P
887 Pekerjaan kolom 20 x 20 cm Mon 06/05/19 Wed 08/05/19 3 days 3 days 0 0 0
888 - Pembesian polos Tukang Besi[5];Pekerja[5] Mon 06/05/19 Mon 06/05/19 1 day 1 day 410,59 0 0 Tukang Besi[5];
889 - Bekisting kolom Tukang Kayu[5];Pekerja[5] Tue 07/05/19 Tue 07/05/19 1 day 1 day 11,6 0 0 Tukang Kayu[5
890 - Pekerjaan beton K-225 Tukang Batu[5];Pekerja[5] Wed 08/05/19 Wed 08/05/19 1 day 1 day 1,16 0 0 Tukang Batu[5
891 Perakitan Rangka Baja Tukang Besi[5];Pekerja[5];CraneThu 09/05/19 Fri 10/05/19 7 days 2 days 3794,49 0 0 Tukang Bes
892 Pekerjaan plat bordes 3 mm Tukang Batu[5];Pekerja[5];Tukang
SatBesi[2];Tukang
11/05/19 Kayu[2]
Sun 12/05/19 3 days 2 days 27,75 0 0 Tukang Ba
893 Pekerjaan baja siku L 70.70.6, L 60.60.5, L 40.40.4, Tukang Mon 13/05/19 Mon 13/05/19 7 days 1 day 3794,49 0 0 Tukang B
termasuk Asesories angkur, mur baut, plat landas, Besi[5];Pekerja[5];Crane
894 Pekerjaan finishing cat Tukang Besi[5];Pekerja[5];CraneTue 14/05/19 Tue 14/05/19 3 days 1 day 195,74 0 0 Tukang
895 VII.4. Pekerjaan Sum pit Mon 15/04/19 Mon 13/05/19 29 days 29 days 0 0 0
896 VII.4.1 Pekerjaan Sum pit 2 m3 (6 unit) Mon 15/04/19 Mon 13/05/19 29 days 29 days 0 0 0
897 Galian tanah sum pit Excavator Mon 15/04/19 Tue 16/04/19 2 days 2 days 37,94 0 0 Excavator
898 Urugan tanah kembali sum pit Excavator Wed 17/04/19 Thu 18/04/19 2 days 2 days 12,65 0 0 Excavator
899 Pasir urug bawah sum pit Tukang Batu[5];Pekerja[5];Tukang
FriBesi[2];Tukang
19/04/19 Kayu[2]
Sat 20/04/19 2 days 2 days 1,22 0 0 Tukang Batu[5];Pekerja[5];Tuka
900 Lantai kerja bawah sum pit Tukang Batu[5];Pekerja[5];Tukang
Sun
Besi[2];Tukang
21/04/19 Kayu[2]
Mon 22/04/19 2 days 2 days 0,61 0 0 Tukang Batu[5];Pekerja[5];Tuk
901 Pekerjaan balok bagian bawah sum pit Tue 23/04/19 Wed 24/04/19 2 days 2 days 0 0 0
902 - Pembesian ulir Tukang Besi[5];Pekerja[5];CraneTue 23/04/19 Wed 24/04/19 2 days 2 days 219,65 0 0 Tukang Besi[5];Pekerja[5];C
903 Pekerjaan balok bagian atas sum pit Fri 03/05/19 Sat 04/05/19 2 days 2 days 0 0 0
904 - Pembesian ulir Tukang Besi[5];Pekerja[5];CraneFri 03/05/19 Sat 04/05/19 2 days 2 days 219,65 0 0 Tukang Besi[5];Pe
905 Pekerjaan plat dasar sum pit t = 15 cm Thu 25/04/19 Thu 02/05/19 8 days 8 days 0 0 0
906 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneThu 25/04/19 Fri 26/04/19 2 days 2 days 298,29 0 0 Tukang Besi[5];Pekerja[5]
907 - Bekisting plat Tukang Kayu[2];Pekerja[5];Tukang
SatBatu[5];Tukang
27/04/19 Besi[2]
Wed 01/05/19 5 days 5 days 5,22 0 0 Tukang Kayu[2];Peke
908 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
Thu
Besi[2];Tukang
02/05/19 Kayu[2]
Thu 02/05/19 1 day 1 day 2,74 0 0 Tukang Batu[5];Pek
909 Pekerjaan dinding sum pit Sat 27/04/19 Wed 01/05/19 5 days 5 days 0 0 0
910 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneSat 27/04/19 Sun 28/04/19 2 days 2 days 2399,25 0 0 Tukang Besi[5];Pekerja[
911 - Bekisting dinding Tukang Kayu[2];Pekerja[5];Tukang
MonBatu[5];Tukang
29/04/19 Besi[2]
Tue 30/04/19 2 days 2 days 126,72 0 0 Tukang Kayu[2];Peker
912 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
Wed
Besi[2];Tukang
01/05/19 Kayu[2]
Wed 01/05/19 1 day 1 day 9,5 0 0 Tukang Batu[5];Peke
913 Pekerjaan plat atap sum pit Sun 05/05/19 Thu 09/05/19 5 days 5 days 0 0 0
914 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneSun 05/05/19 Mon 06/05/19 2 days 2 days 155,36 0 0 Tukang Besi[5];
915 - Bekisting plat Tukang Kayu[2];Pekerja[5];Tukang
TueBatu[5];Tukang
07/05/19 Besi[2]
Wed 08/05/19 2 days 2 days 13,74 0 0 Tukang Kayu[
916 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
Thu
Besi[2];Tukang
09/05/19 Kayu[2]
Thu 09/05/19 1 day 1 day 1,06 0 0 Tukang Batu
917 Waterprofing integral beton sum pit Tukang Batu[5];Pekerja[5];Tukang
FriBesi[2];Tukang
10/05/19 Kayu[2]
Sat 11/05/19 2 days 2 days 13,3 0 0 Tukang Ba
918 Waterstop PVC Tukang Batu[5];Pekerja[5];Tukang
Tue
Besi[2];Tukang
07/05/19 Kayu[2]
Wed 08/05/19 2 days 2 days 26,4 0 0 Tukang Batu[5
919 Pekerjaan tutup sum pit dari besi ( lengkap Tukang Sun 12/05/19 Mon 13/05/19 2 days 2 days 6 0 0 Tukang B
terpasang termasuk asesories engsel, handle, Besi[5];Pekerja[5];Crane
920 VII.4.2 Pekerjaan Sum pit 10 m3 (1 unit) Mon 15/04/19 Fri 10/05/19 26 days 26 days 0 0 0
921 Galian tanah sum pit Excavator Mon 15/04/19 Tue 16/04/19 2 days 2 days 37,24 0 0 Excavator
922 Pasir urug bawah sum pit Excavator Wed 17/04/19 Thu 18/04/19 2 days 2 days 1,06 0 0 Excavator
923 Lantai kerja bawah sum pit Tukang Batu[5];Pekerja[5];Tukang
Sun
Besi[2];Tukang
21/04/19 Kayu[2]
Sun 21/04/19 1 day 1 day 0,53 0 0 Tukang Batu[5];Pekerja[5];Tuk
924 Urugan tanah kembali sum pit Tukang Batu[5];Pekerja[5];Tukang
Mon
Besi[2];Tukang
22/04/19 Kayu[2]
Tue 23/04/19 2 days 2 days 12,41 0 0 Tukang Batu[5];Pekerja[5];Tu
925 Pekerjaan balok bagian bawah sum pit Fri 19/04/19 Sat 20/04/19 2 days 2 days 0 0 0
926 - Pembesian ulir Tukang Besi[5];Pekerja[5];CraneFri 19/04/19 Sat 20/04/19 2 days 2 days 125,19 0 0 Tukang Besi[5];Pekerja[5];Crane
927 Pekerjaan balok bagian atas sum pit Sun 21/04/19 Mon 22/04/19 2 days 2 days 0 0 0
928 - Pembesian ulir Tukang Besi[5];Pekerja[5];CraneSun 21/04/19 Mon 22/04/19 2 days 2 days 125,19 0 0 Tukang Besi[5];Pekerja[5];Cra
929 Pekerjaan plat dasar sum pit t = 15 cm Mon 22/04/19 Fri 26/04/19 5 days 5 days 0 0 0
930 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneMon 22/04/19 Tue 23/04/19 2 days 2 days 258,3 0 0 Tukang Besi[5];Pekerja[5];Cr
931 - Bekisting plat Tukang Kayu[2];Pekerja[5];Tukang
WedBatu[5];Tukang
24/04/19 Besi[2]
Thu 25/04/19 2 days 2 days 2,32 0 0 Tukang Kayu[2];Pekerja[5]
932 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
FriBesi[2];Tukang
26/04/19 Kayu[2]
Fri 26/04/19 1 day 1 day 3,78 0 0 Tukang Batu[5];Pekerja[5
933 Pekerjaan dinding sum pit Sat 27/04/19 Wed 01/05/19 5 days 5 days 0 0 0
934 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneSat 27/04/19 Sun 28/04/19 2 days 2 days 1018,13 0 0 Tukang Besi[5];Pekerja[
935 - Bekisting dinding Tukang Kayu[2];Pekerja[5];Tukang
MonBatu[5];Tukang
29/04/19 Besi[2]
Tue 30/04/19 2 days 2 days 59,16 0 0 Tukang Kayu[2];Peker
936 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
Wed
Besi[2];Tukang
01/05/19 Kayu[2]
Wed 01/05/19 1 day 1 day 6,73 0 0 Tukang Batu[5];Peke
937 Pekerjaan plat atap sum pit Thu 02/05/19 Mon 06/05/19 5 days 5 days 0 0 0
938 - Pembesian polos Tukang Besi[5];Pekerja[5];CraneThu 02/05/19 Fri 03/05/19 2 days 2 days 140,86 0 0 Tukang Besi[5];Pek
939 - Bekisting plat Tukang Kayu[2];Pekerja[5];Tukang
SatBatu[5];Tukang
04/05/19 Besi[2]
Sun 05/05/19 2 days 2 days 6,61 0 0 Tukang Kayu[2];P
940 - Beton mutu K-300 Tukang Batu[5];Pekerja[5];Tukang
Mon
Besi[2];Tukang
06/05/19 Kayu[2]
Mon 06/05/19 1 day 1 day 0,64 0 0 Tukang Batu[5];
941 Waterstop PVC Tukang Batu[5];Pekerja[5];Tukang
SatBesi[2];Tukang
04/05/19 Kayu[2]
Sun 05/05/19 2 days 2 days 11,6 0 0 Tukang Batu[5];P
942 Waterprofing integral beton sum pit Tukang Batu[5];Pekerja[5];Tukang
Tue
Besi[2];Tukang
07/05/19 Kayu[2]
Wed 08/05/19 2 days 2 days 11,14 0 0 Tukang Batu[5
943 Pekerjaan tutup sum pit dari besi ( lengkap Tukang Thu 09/05/19 Fri 10/05/19 2 days 2 days 1 0 0 Tukang Bes
terpasang termasuk asesories engsel, handle, Besi[5];Pekerja[5];Crane
944 PEKERJAAN MEKANIKAL ELEKTRIKAL Tue 26/02/19 Wed 15/05/19 198,2 days 79 days 0 0 0
946 Instalasi Air Bersih Tue 26/02/19 Wed 06/03/19 36 days 9 days 0 0 0
947 Pembuatan Instalasi Air Bersih Tue 26/02/19 Thu 28/02/19 30 days 3 days 0 0 0
Page 12
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
948 Submit Fri 01/03/19 Sun 03/03/19 3 days 3 days 0 0 0 25/02/19
949 Approval Mon 04/03/19 Wed 06/03/19 3 days 3 days 0 0 0
950 Instalasi Air Kotor dan Air Bekas Fri 01/03/19 Sat 09/03/19 36 days 9 days 0 0 0
951 Pembuatan Instalasi Air Kotor dan Air Bekas Fri 01/03/19 Sun 03/03/19 30 days 3 days 0 0 0
954 Instalasi Pipa Pembuangan Air Hujan Mon 04/03/19 Tue 12/03/19 36 days 9 days 0 0 0
955 Instalasi Pipa Pembuangan Air Hujan Mon 04/03/19 Wed 06/03/19 30 days 3 days 0 0 0
962 Instalasi Distribusi Listrik Mon 18/03/19 Tue 26/03/19 36 days 9 days 0 0 0
967 Instalasi Air Bersih Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
968 Pipa PP-R PN 10 dia. 1/2" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
971 Pipa PP-R PN 10.dia. 3/4" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
974 Pipa PP-R PN 10 dia. 1" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
977 Pipa PP-R PN 10 dia. 2" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
980 Gate Valve PN 10 dia. 3/4" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
983 Gate Valve PN 10 dia. 1" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
986 Gate Valve PN 10 dia. 1,5" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
989 Gate Valve PN 10 dia. 2" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
995 Flexible Joint dia.1,5" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
998 Foot Valve dia.1,5" Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
1001 Header dia. 3", c/w ac accessories Thu 07/03/19 Tue 12/03/19 10 days 6 days 0 0 0
1016 Instalasi Air Kotor dan Air Bekas Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1017 Pipa PVC kls AW dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1020 Pipa PVC kls AW dia. 1,5" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1023 Pipa PVC kls AW dia. 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1026 Pipa PVC kls AW dia. 3" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
Page 13
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1027 PO Wed 27/03/19 Fri 29/03/19 3 days 3 days 0 0 0 25/02/19
1028 Material On Site Sat 30/03/19 Mon 01/04/19 7 days 3 days 0 0 0
1029 Pompa Submersible kapasitas 2 m3 Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1032 Instalasi Pipa Pembuangan Air Hujan Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1033 Pipa PVC dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1036 Pipa PVC dia. 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1039 Roof Drain. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1044 Pipa BS SCH 40 dia 1" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1047 Pipa BS SCH 40 dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1050 Pipa BS SCH 40 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1053 Header dia. 8", c/w accessoriesnya Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1056 Gate Valve PN 16 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1059 Gate Valve PN 16 dia 3" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1062 Gate Valve PN 16 dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1065 Gate Valve PN 16 dia 1" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1068 Stainer PN 16 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1071 Stainer PN 16 dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1074 Fleksible Joint PN 16 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1077 Fleksible Joint PN 16 dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1080 Check Valve PN 16 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1083 Check Valve PN 16 dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1086 Foot Valve dia 2" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1095 Safety Valve PN 16 dia. 3'' Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1098 Electric Hydrant Pump standar NFPA-20 kap. Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1000 GPM, head 85 m, daya 90 kW, c/w
1099 PO Wed 27/03/19 Fri 29/03/19 3 days 3 days 0 0 0
1101 Diesel Hydrant Pump standar NFPA-20 kap. 1000 GPM, Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1104 Pompa Jockey Standard Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
Page 14
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1106 Material On Site Sat 30/03/19 Mon 01/04/19 7 days 3 days 0 0 0 25/02/19
1107 Primming Tank Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1110 Pompa Primming Tank Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1113 Fire Extinguisher kapasitas 3 Kg type dry powder Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1116 Fire Extinguisher kapasitas 5 Kg type CO2 Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1120 Pipa BS SCH 40 dia 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1123 Pipa BS SCH 40 dia 6" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1126 Outdoor Hydrant Box lengkap dengan Hose, Hose rack, Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1129 Gate Valve PN 16 dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1132 Check Valve PN 16 dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1135 Hydrant PN 16 dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1138 Seamesse Connection dia. 4" Wed 27/03/19 Mon 01/04/19 10 days 6 days 0 0 0
1143 Instalasi Air Bersih Sun 24/03/19 Mon 13/05/19 63 days 51 days 0 0 0
1144 Pipa PP-R PN 10 dia. 1/2" Subkontraktor Fri 05/04/19 Sun 07/04/19 5 days 3 days 106 0 0 Subkontraktor
1145 Gate Valve PN 10 dia. 1,5" Subkontraktor Mon 08/04/19 Wed 10/04/19 5 days 3 days 4 0 0 Subkontraktor
1146 Check Valve PN 10 dia. 1,5" Subkontraktor Thu 11/04/19 Sat 13/04/19 5 days 3 days 2 0 0 Subkontraktor
1147 Strainer PN 10 dia. 1,5'' Subkontraktor Mon 08/04/19 Fri 12/04/19 5 days 5 days 2 0 0 Subkontraktor
1148 Flexible joint dia. 1,5'' Subkontraktor Mon 08/04/19 Wed 10/04/19 5 days 3 days 4 0 0 Subkontraktor
1149 Foot Valve dia. 1,5'' Subkontraktor Mon 08/04/19 Wed 10/04/19 5 days 3 days 2 0 0 Subkontraktor
1150 Pipa PP-R PN 10 dia. 1,5" Subkontraktor Sun 14/04/19 Thu 18/04/19 5 days 5 days 138 0 0 Subkontraktor
1151 Pipa PP-R PN 10 dia. 3/4" Subkontraktor Fri 19/04/19 Sun 21/04/19 6 days 3 days 81 0 0 Subkontraktor
1152 Gate Valve PN 10 dia. 3/4" Subkontraktor Mon 22/04/19 Fri 26/04/19 5 days 5 days 4 0 0 Subkontraktor
1153 Pipa PP-R PN 10 dia. 1" Subkontraktor Mon 22/04/19 Wed 24/04/19 6 days 3 days 368 0 0 Subkontraktor
1154 Gate Valve PN 10 dia. 1" Subkontraktor Thu 25/04/19 Mon 29/04/19 5 days 5 days 22 0 0 Subkontraktor
1155 Pipa PP-R PN 10 dia. 2" Subkontraktor Thu 25/04/19 Tue 30/04/19 6 days 6 days 11 0 0 Subkontraktor
1156 Pipa PP-R PN 10 dia. 2" Subkontraktor Thu 25/04/19 Mon 29/04/19 5 days 5 days 154 0 0 Subkontraktor
1157 Pipa PP-R PN 10 dia. 2" (dari PDAM ke Subkontraktor Thu 25/04/19 Mon 29/04/19 5 days 5 days 270 0 0 Subkontraktor
Groundtank)
1158 Gate Valve PN 10 dia. 2" Subkontraktor Wed 01/05/19 Sun 05/05/19 5 days 5 days 1 0 0 Subkontraktor
1159 Pressure Gauge Subkontraktor Mon 06/05/19 Thu 09/05/19 4 days 4 days 2 0 0 Subkontrakt
1160 Pressure Switch Subkontraktor Fri 10/05/19 Mon 13/05/19 4 days 4 days 2 0 0 Subkont
1161 Sambungan PDAM Subkontraktor Tue 30/04/19 Fri 03/05/19 4 days 4 days 1 0 0 Subkontraktor
1162 Rooftank Stainless Steel kapasitas 2 m3, c/w Subkontraktor Mon 06/05/19 Sat 11/05/19 6 days 6 days 10 0 0 Subkontra
dudukan, valve penguras, floating valve dan
1163 Pompa submersible untuk kuras groundtank, Subkontraktor Sun 24/03/19 Fri 29/03/19 6 days 6 days 2 0 0 Subkontraktor
kap. 8 m3/jam, head 20 m, daya 2,2 kW, c/w
1164 Pompa transfer (dari groundtank ke rooftank) Subkontraktor Sat 30/03/19 Thu 04/04/19 6 days 6 days 1 0 0 Subkontraktor
di ruang pompa,kap. 12 m3/jam, head 30 m,
1165 Header dia. 3", c/w accessoriesnya Subkontraktor Fri 05/04/19 Mon 08/04/19 4 days 4 days 1 0 0 Subkontraktor
1166 Instalasi Air Kotor dan Air Bekas Subkontraktor Mon 18/03/19 Tue 30/04/19 29 days 44 days 0 0 0
1167 Pompa submersible untuk bak penampung Subkontraktor Tue 02/04/19 Sat 06/04/19 5 days 5 days 6 0 0 Subkontraktor
kapasitas 2 m3 di area siteplan, kap. 2 m3/jam,
1168 Pompa submersible untuk bak penampung Subkontraktor Mon 18/03/19 Thu 21/03/19 4 days 4 days 1 0 0 Subkontraktor
kapasitas 10 m3, di area siteplan, kap. 8
1169 Pipa PVC klas AW dia. 1,5" Subkontraktor Thu 25/04/19 Tue 30/04/19 6 days 6 days 34 0 0 Subkontraktor
1170 Pipa PVC klas AW dia. 2" Subkontraktor Thu 25/04/19 Tue 30/04/19 6 days 6 days 46 0 0 Subkontraktor
1171 Pipa PVC klas AW dia. 4" Subkontraktor Thu 25/04/19 Tue 30/04/19 6 days 6 days 114 0 0 Subkontraktor
1172 Pipa PVC klas AW dia. 3" Subkontraktor Sun 07/04/19 Fri 12/04/19 6 days 6 days 244 0 0 Subkontraktor
1173 Bak Penampung dan Tutup Beton, kapasitas 2 Subkontraktor Sat 13/04/19 Thu 18/04/19 6 days 6 days 6 0 0 Subkontraktor
m3
1174 Bak Penampung dan Tutup Beton, kapasitas 10 Subkontraktor Fri 19/04/19 Wed 24/04/19 6 days 6 days 1 0 0 Subkontraktor
m3
1175 Instalasi Pipa Pembuangan Air Hujan Tue 02/04/19 Fri 05/04/19 4 days 4 days 0 0 0
1176 Roof drain dia. 4'' Subkontraktor Tue 02/04/19 Wed 03/04/19 2 days 2 days 236 0 0 Subkontraktor
1177 Pipa PVC dia. 4" Subkontraktor Thu 04/04/19 Fri 05/04/19 2 days 2 days 2357 0 0 Subkontraktor
1178 Pipa PVC dia. 6" Subkontraktor Thu 04/04/19 Fri 05/04/19 2 days 2 days 1260 0 0 Subkontraktor
1179 Instalasi Hidran Tue 02/04/19 Mon 15/04/19 14 days 14 days 0 0 0
1181 Pipa BS SCH 40 dia. 1" Subkontraktor Sat 06/04/19 Mon 08/04/19 3 days 3 days 20 0 0 Subkontraktor
1182 Pipa BS SCH 40 dia. 2" Subkontraktor Sat 06/04/19 Mon 08/04/19 3 days 3 days 10 0 0 Subkontraktor
1183 Pipa BS SCH 40 dia. 2,5" Subkontraktor Sat 06/04/19 Mon 08/04/19 3 days 3 days 50 0 0 Subkontraktor
1184 Pipa BS SCH 40 dia. 3" Subkontraktor Sat 06/04/19 Mon 08/04/19 3 days 3 days 220 0 0 Subkontraktor
Page 15
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1185 Pipa BS SCH 40 dia. 6" Subkontraktor Sat 06/04/19 Mon 08/04/19 3 days 3 days 20 0 0 25/02/19 Subkontraktor
1186 Header dia. 8", c/w accessoriesnya Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 1 0 0 Subkontraktor
1187 Gate Valve PN 16 dia. 6'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 5 0 0 Subkontraktor
1188 Gate Valve PN 16 dia. 3'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 1 0 0 Subkontraktor
1189 Gate Valve PN 16 dia. 2'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 3 0 0 Subkontraktor
1190 Gate Valve PN 16 dia. 1'' Subkontraktor Tue 09/04/19 Fri 12/04/19 4 days 4 days 4 0 0 Subkontraktor
1191 Check Valve PN 16 dia. 6'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 2 0 0 Subkontraktor
1192 Check Valve PN 16 dia. 2'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 1 0 0 Subkontraktor
1193 Strainer PN 16 dia. 6'' Subkontraktor Tue 09/04/19 Wed 10/04/19 2 days 2 days 2 0 0 Subkontraktor
1194 Strainer PN 16 dia. 2'' Subkontraktor Tue 09/04/19 Wed 10/04/19 2 days 2 days 1 0 0 Subkontraktor
1195 Fleksibel Joint PN 16 dia. 6'' Subkontraktor Sat 13/04/19 Mon 15/04/19 3 days 3 days 4 0 0 Subkontraktor
1196 Fleksibel Joint PN 16 dia. 2'' Subkontraktor Sat 13/04/19 Mon 15/04/19 3 days 3 days 2 0 0 Subkontraktor
1197 Foot Valve dia. 2'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 1 0 0 Subkontraktor
1198 Pressure gauge Subkontraktor Sat 13/04/19 Mon 15/04/19 3 days 3 days 3 0 0 Subkontraktor
1199 Pressure Switch Subkontraktor Sat 13/04/19 Mon 15/04/19 3 days 3 days 2 0 0 Subkontraktor
1200 Safety Valve PN 16 dia. 3'' Subkontraktor Tue 09/04/19 Thu 11/04/19 3 days 3 days 1 0 0 Subkontraktor
1201 Electric Hydrant Pump standar NFPA-20 Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 1 0 0 Subkontraktor
kap. 1000 GPM, head 85 m, daya 90 kW,
1202 Diesel Hydrant Pump standar NFPA-20 kap. Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 1 0 0 Subkontraktor
1000 GPM,
1203 Pompa Jockey standar NFPA-20 kap. 50 Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 1 0 0 Subkontraktor
GPM, head 90 m,
1204 Priming Tank kapasitas 500 liter, c/w Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 1 0 0 Subkontraktor
pondasi,
1205 Pompa Priming Tank kapasitas 25 lpm, Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 1 0 0 Subkontraktor
head 15 m, 125 W,
1206 Fire Extinguisher kapasitas 5 Kg type CO2 Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 10 0 0 Subkontraktor
1207 Indoor Hydrant Box lengkap dengan Hose, Subkontraktor Tue 02/04/19 Thu 04/04/19 3 days 3 days 10 0 0 Subkontraktor
Hose rack,
1208 Fire Extinguisher kapasitas 3 Kg type dry Subkontraktor Tue 02/04/19 Fri 05/04/19 4 days 4 days 40 0 0 Subkontraktor
powder
1209 Fire Extinguisher kapasitas 5 Kg type CO2 Subkontraktor Tue 02/04/19 Fri 05/04/19 4 days 4 days 40 0 0 Subkontraktor
1210 Hydrant Site Tue 02/04/19 Sun 07/04/19 6 days 6 days 0 0 0
1211 Pipa BS SCH 40 dia. 4" Subkontraktor Thu 04/04/19 Fri 05/04/19 2 days 2 days 30 0 0 Subkontraktor
1212 Pipa BS SCH 40 dia. 6" Subkontraktor Thu 04/04/19 Fri 05/04/19 2 days 2 days 1220 0 0 Subkontraktor
1213 Gate Valve PN 16 dia. 4" Subkontraktor Sat 06/04/19 Sun 07/04/19 2 days 2 days 20 0 0 Subkontraktor
1214 Check Valve PN 16 dia. 4'' Subkontraktor Sat 06/04/19 Sun 07/04/19 2 days 2 days 1 0 0 Subkontraktor
1215 Seamesse Connection dia. 4" Subkontraktor Sat 06/04/19 Sun 07/04/19 2 days 2 days 1 0 0 Subkontraktor
1216 Outdoor Hydrant Box lengkap dengan Hose, Subkontraktor Tue 02/04/19 Wed 03/04/19 2 days 2 days 20 0 0 Subkontraktor
Hose rack,
1217 Hydrant Pillar dia. 4" Subkontraktor Tue 02/04/19 Wed 03/04/19 2 days 2 days 20 0 0 Subkontraktor
1218 PEKERJAAN ELEKTRIKAL Sat 09/03/19 Wed 15/05/19 75 days 68 days 0 0 0
1219 Pekerjaan Distribusi Listrik Sat 09/03/19 Wed 15/05/19 55 days 68 days 0 0 0
1220 Sambung Daya PLN 197 KVA Sat 09/03/19 Fri 05/04/19 28 days 28 days 0 0 0
1229 Pemasangan Tiang Listrik + Pondasi Subkontraktor Sat 09/03/19 Fri 15/03/19 7 days 7 days 18 0 0 Subkontraktor
1230 tiang listrik C11 / 350 dn Subkontraktor Sat 09/03/19 Fri 15/03/19 7 days 7 days 18 0 0 Subkontraktor
1231 Material Bantu Subkontraktor Sat 09/03/19 Wed 13/03/19 5 days 5 days 18 0 0 Subkontraktor
1232 Material kabel Power dan Pemasangan Sat 16/03/19 Thu 21/03/19 9 days 6 days 0 0 0
1233 Kabel Power AAAC /240 mm voksel Subkontraktor Sat 16/03/19 Sun 17/03/19 3 days 2 days 2250 0 0 Subkontraktor
1234 Kabel Netral AAAC 150mm Subkontraktor Sat 16/03/19 Sun 17/03/19 3 days 2 days 850 0 0 Subkontraktor
1235 Accessories / Perlengkapan Subkontraktor Mon 18/03/19 Tue 19/03/19 3 days 2 days 17 0 0 Subkontraktor
1236 Jasa Penarikan AAAC 240 mm² Subkontraktor Wed 20/03/19 Thu 21/03/19 3 days 2 days 2250 0 0 Subkontraktor
1237 Jasa Penarikan AAAC 150 mm2 Subkontraktor Wed 20/03/19 Thu 21/03/19 3 days 2 days 2250 0 0 Subkontraktor
1238 Panel LVMDP & Capasitor Bank Subkontraktor Fri 22/03/19 Sun 24/03/19 3 days 3 days 1 0 0 Subkontraktor
1239 PANEL AMF - ATS 250kVA Subkontraktor Fri 22/03/19 Sun 24/03/19 3 days 3 days 1 0 0 Subkontraktor
1240 PP penerangan power House & Supir Tue 14/05/19 Tue 14/05/19 6 days 1 day 0 0 0
1241 Box Uk. 40 x60 x 25 cm (tebal 2,5 mm) Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1242 - MCCB 40A/3P/18kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 2 0 0 Subkon
1243 - MCCB 10A/3P/7,5kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 2 0 0 Subkon
1244 - MCB 6A/1P/7,5kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 10 0 0 Subkon
1245 - Sekering 3 A Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 3 0 0 Subkon
1246 - Lampu tanda Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 3 0 0 Subkon
1247 - Volt metering & Amper meter digital c/w Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
CT & asesories
1248 - Selektor Switch Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1249 - Busbar RSTN G Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1250 - Instalasi Grounding tembaga Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1251 Wiring + Material Bantu Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 1 0 0 Subkon
1252 SUB DISTRIBUTION PANEL POMPA (PP Tue 14/05/19 Tue 14/05/19 3 days 1 day 0 0 0
POMPA) RUMAH POMPA
1253 Box Uk. 50 x70 x 15 cm (tebal 2,5 mm) Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1254 - MCCB 100A/3P/18kA Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1255 - MCCB 50A/3P/10kA Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 2 0 0 Subkon
1256 - MCB 16A/1P/7,5kA Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 2 0 0 Subkon
1257 - Sekering 3 A Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1258 - Lampu tanda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1259 - Volt metering & Amper meter digital c/w Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
CT & asesories
1260 - Selektor Switch Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1261 - Busbar RSTN G Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1262 - Instalasi Grounding Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1263 -Wiring + Material Bantu Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
Page 16
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1264 POWER PANEL HYDRANT (PP HYDRANT) RUMAH POMPA Tue 14/05/19 Tue 14/05/19 5 days 1 day 0 0 0 25/02/19
1265 Box Uk. 50 x70 x 15 cm (tebal 2,5 mm) Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkont
1266 - MCCB 400A/3P/36kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1267 - MCCB 300A/3P/36kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1268 - MCB 25A/1P/10kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1269 - MCB 16A/1P/7,5kA Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 2 0 0 Subkon
1270 - Sekering 3 A Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 3 0 0 Subkon
1271 - Lampu tanda Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 3 0 0 Subkon
1272 - Volt metering & Amper meter digital c/w Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
CT & asesories
1273 - Selektor Switch Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1274 - Busbar RSTN G Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1275 - Instalasi Grounding Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 1 0 0 Subkon
1276 -Wiring + Material Bantu Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1277 P.P CHAMBER Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 10 0 0 Subkon
1278 P.P penerangan halaman Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 4 0 0 Subkon
1279 Kabel Power Mon 25/03/19 Tue 14/05/19 36 days 51 days 0 0 0
1290 Pelat Tembaga 20x3mm / keliling bangunan Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 45 0 0 Subkon
1291 BC 50 mm Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 45 0 0 Subkon
1292 Konektor grounding dan material bantu lainnya Subkontraktor Tue 14/05/19 Wed 15/05/19 2 days 2 days 1 0 0 Subkon
1293 Pekerjaan Instalasi Penerangan dan Kotak Kontak Sat 09/03/19 Tue 14/05/19 62,5 days 67 days 0 0 0
1295 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 7 days 1 day 38 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1296 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1297 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1298 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 13 0 0 Subkon
penggantung galvanis 1", support dan
1299 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 14 0 0 Subkon
penggantung galvanis 1", support dan
1300 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 7 0 0 Subkon
penggantung galvanis 1", support dan
1301 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1302 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 8 0 0 Subkon
1303 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1304 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 7 days 1 day 77 0 0 Subkon
1305 Chamber 2 Tue 14/05/19 Tue 14/05/19 7 days 1 day 0 0 0
1306 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 7 days 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1307 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 4 days 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1308 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1309 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 5 days 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1310 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1311 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 7 0 0 Subkon
1312 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1313 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 4 days 1 day 8 0 0 Subkon
1314 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1315 Chamber 3 Tue 14/05/19 Tue 14/05/19 7 days 1 day 0 0 0
1316 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 7 days 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1317 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1318 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1319 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 5 days 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1320 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1321 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 7 0 0 Subkon
1322 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1323 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 8 0 0 Subkon
1324 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1325 Chamber 4 Tue 14/05/19 Tue 14/05/19 6 days 1 day 0 0 0
1326 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1327 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1328 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1329 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1330 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1331 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1332 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1333 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1334 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1335 Chamber 5 Tue 14/05/19 Tue 14/05/19 6 days 1 day 0 0 0
1336 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1337 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1338 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1339 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1340 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1341 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1342 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
Page 17
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1343 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 25/02/19 Subkon
1344 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1345 Chamber 6 Tue 14/05/19 Tue 14/05/19 6 days 1 day 0 0 0
1346 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1347 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1348 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1349 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1350 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1351 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1352 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1353 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1354 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1355 Chamber 7 Tue 14/05/19 Tue 14/05/19 5 days 1 day 0 0 0
1356 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1357 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1358 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1359 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1360 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1361 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1362 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1363 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1364 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1365 Chamber 8 Tue 14/05/19 Tue 14/05/19 5 days 1 day 0 0 0
1366 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1367 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1368 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1369 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1370 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1371 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1372 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1373 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1374 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1375 Chamber 9 Tue 14/05/19 Tue 14/05/19 4 days 1 day 0 0 0
1376 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1377 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1378 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1379 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1380 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1381 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1382 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1383 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1384 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1385 Chamber 10 Tue 14/05/19 Tue 14/05/19 4 days 1 day 0 0 0
1386 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 77 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1387 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1388 LED DownLight 7 W Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1389 Lampu Industrial led 80 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 45 0 0 Subkon
penggantung galvanis 1", support dan
1390 Lampu LED TKO 2x18 Watt, berikut tiang Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 21 0 0 Subkon
penggantung galvanis 1", support dan
1391 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1392 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1393 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 8 0 0 Subkon
1394 Kotak Kontak Dinding 2 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1395 Power House Tue 14/05/19 Tue 14/05/19 3 days 1 day 0 0 0
1396 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 14 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1397 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 12 0 0 Subkon
mm dlm Pipa Conduit dia. 20 mm
1398 Lampu Armature Bambu LED 18 watt Subkontraktor Tue 14/05/19 Tue 14/05/19 3 days 1 day 14 0 0 Subkon
1399 Barret Led 2 x 7 watt Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 6 0 0 Subkon
1400 Saklar Tunggal Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 6 0 0 Subkon
1401 Saklar Ganda Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1402 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Tue 14/05/19 Tue 14/05/19 2 days 1 day 12 0 0 Subkon
1403 Supir & pluging charge Fri 03/05/19 Mon 06/05/19 4 days 4 days 0 0 0
1404 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Fri 03/05/19 Mon 06/05/19 4 days 4 days 51 0 0 Subkontraktor
mm dlm Pipa Conduit dia. 20 mm
1405 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Fri 03/05/19 Sun 05/05/19 3 days 3 days 27 0 0 Subkontraktor
mm dlm Pipa Conduit dia. 20 mm
1406 Lampu Armature Bambu LED 18 watt Subkontraktor Fri 03/05/19 Sat 04/05/19 2 days 2 days 20 0 0 Subkontraktor
1407 Barret Led 2 x 7 watt Subkontraktor Fri 03/05/19 Sat 04/05/19 2 days 2 days 21 0 0 Subkontraktor
1408 Saklar Tunggal Subkontraktor Fri 03/05/19 Fri 03/05/19 1 day 1 day 3 0 0 Subkontraktor
1409 Saklar Ganda Subkontraktor Fri 03/05/19 Sat 04/05/19 2 days 2 days 7 0 0 Subkontraktor
1410 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Fri 03/05/19 Sat 04/05/19 2 days 2 days 27 0 0 Subkontraktor
1411 Pos Satpam Mon 06/05/19 Mon 06/05/19 1 day 1 day 0 0 0
1412 Instalasi Penerangan dg Kabel NYM 3 X 2.5 Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 6 0 0 Subkontraktor
mm dlm Pipa Conduit dia. 20 mm
1413 Instalasi Kotak-Kontak dg Kabel NYM 3 X 2.5 Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 3 0 0 Subkontraktor
mm dlm Pipa Conduit dia. 20 mm
1414 Barret Led 2 x 7 watt Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 4 0 0 Subkontraktor
1415 Saklar Tunggal Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 1 0 0 Subkontraktor
1416 Saklar Ganda Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 1 0 0 Subkontraktor
1417 Kotak Kontak Dinding 1 X 16 Amp Subkontraktor Mon 06/05/19 Mon 06/05/19 1 day 1 day 3 0 0 Subkontraktor
1418 Penerangan Site plan Sat 09/03/19 Mon 11/03/19 3 days 3 days 0 0 0
1419 Lampu PJU Street light LED 100 W Satu Subkontraktor Sat 09/03/19 Sat 09/03/19 1 day 1 day 111 0 0 Subkontraktor
Lengan (Lampu) '-plus pondasi & tiang
1420 Instalasi Penerangan dg Kabel NYY 3 X 6 Subkontraktor Sun 10/03/19 Sun 10/03/19 1 day 1 day 63 0 0 Subkontraktor
mm dlm Pipa Conduit dia. 20 mm
1421 Lampu halogen 1000 w support dan Subkontraktor Mon 11/03/19 Mon 11/03/19 1 day 1 day 48 0 0 Subkontraktor
acessories '-plus pondasi & tiang tinggi 15
Page 18
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1422 Pekerjaan Instalasi Fire Alaram Tue 19/03/19 Tue 14/05/19 58,5 days 57 days 0 0 0 25/02/19
1423 Peralatan Utama Thu 04/04/19 Mon 08/04/19 5 days 5 days 0 0 0
1430 Kabel NYA 2x1x1.5 mm² dalam High Thu 04/04/19 Tue 09/04/19 6 days 6 days 0 0 0
Impact conduit dia. 20 mm
1431 Instalasi Detector Fire Alarm & ROR Subkontraktor Thu 04/04/19 Sat 06/04/19 3 days 3 days 9 0 0 Subkontraktor
1432 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Thu 04/04/19 Sat 06/04/19 3 days 3 days 5 0 0 Subkontraktor
1433 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Sun 07/04/19 Mon 08/04/19 2 days 2 days 3 0 0 Subkontraktor
1434 End of Line Resistor Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1435 Kabel FRC 2x1.5 mm² dalam High Impact Thu 04/04/19 Fri 05/04/19 2 days 2 days 0 0 0
conduit dia. 20 mm
1436 Instalasi Indicator Lamp Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1437 Indicator Lamp Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1438 Instalasi Alarm Bell Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1439 Alarm Bell Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1440 Manual call point with backbox Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1441 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1442 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1443 CHAMBER 2 Thu 04/04/19 Sat 06/04/19 3 days 3 days 0 0 0
1444 Kabel NYA 2x1x1.5 mm² dalam High Thu 04/04/19 Sat 06/04/19 3 days 3 days 0 0 0
Impact conduit dia. 20 mm
1445 Instalasi Detector Fire Alarm & ROR Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 11 0 0 Subkontraktor
1446 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 7 0 0 Subkontraktor
1447 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 3 0 0 Subkontraktor
1448 End of Line Resistor Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1449 Kabel FRC 2x1.5 mm² dalam High Impact Thu 04/04/19 Fri 05/04/19 2 days 2 days 0 0 0
conduit dia. 20 mm
1450 Instalasi Indicator Lamp Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1451 Indicator Lamp Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1452 Instalasi Alarm Bell Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1453 Alarm Bell Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1454 Manual call point with backbox Subkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1455 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Thu 04/04/19 Thu 04/04/19 1 day 1 day 1 0 0 Subkontraktor
1456 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1457 CHAMBER 3 Fri 05/04/19 Sun 14/04/19 10 days 10 days 0 0 0
1458 Kabel NYA 2x1x1.5 mm² dalam High Sun 07/04/19 Sun 14/04/19 8 days 8 days 0 0 0
Impact conduit dia. 20 mm
1459 Instalasi Detector Fire Alarm & ROR Subkontraktor Sun 07/04/19 Thu 11/04/19 5 days 5 days 11 0 0 Subkontraktor
1460 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Sun 07/04/19 Thu 11/04/19 5 days 5 days 7 0 0 Subkontraktor
1461 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Fri 12/04/19 Sat 13/04/19 2 days 2 days 3 0 0 Subkontraktor
1462 End of Line Resistor Subkontraktor Sun 14/04/19 Sun 14/04/19 1 day 1 day 1 0 0 Subkontraktor
1463 Kabel FRC 2x1.5 mm² dalam High Impact Fri 05/04/19 Sat 06/04/19 2 days 2 days 0 0 0
conduit dia. 20 mm
1464 Instalasi Indicator Lamp Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1465 Indicator Lamp Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1466 Instalasi Alarm Bell Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1467 Alarm Bell Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1468 Manual call point with backbox Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1469 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1470 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1471 CHAMBER 4 Fri 05/04/19 Sun 14/04/19 10 days 10 days 0 0 0
1472 Kabel NYA 2x1x1.5 mm² dalam High Fri 05/04/19 Sun 14/04/19 10 days 10 days 0 0 0
Impact conduit dia. 20 mm
1473 Instalasi Detector Fire Alarm & ROR Subkontraktor Fri 05/04/19 Tue 09/04/19 5 days 5 days 11 0 0 Subkontraktor
1474 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Wed 10/04/19 Fri 12/04/19 3 days 3 days 7 0 0 Subkontraktor
1475 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Sat 13/04/19 Sat 13/04/19 1 day 1 day 3 0 0 Subkontraktor
1476 End of Line Resistor Subkontraktor Sun 14/04/19 Sun 14/04/19 1 day 1 day 1 0 0 Subkontraktor
1477 Kabel FRC 2x1.5 mm² dalam High Impact Fri 05/04/19 Sun 07/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1478 Instalasi Indicator Lamp Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1479 Indicator Lamp Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1480 Instalasi Alarm Bell Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1481 Alarm Bell Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1482 Manual call point with backbox Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1483 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1484 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1485 CHAMBER 5 Sat 06/04/19 Tue 16/04/19 11 days 11 days 0 0 0
1486 Kabel NYA 2x1x1.5 mm² dalam High Wed 10/04/19 Tue 16/04/19 7 days 7 days 0 0 0
Impact conduit dia. 20 mm
1487 Instalasi Detector Fire Alarm & ROR Subkontraktor Wed 10/04/19 Sun 14/04/19 5 days 5 days 11 0 0 Subkontraktor
1488 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Sat 13/04/19 Sat 13/04/19 1 day 1 day 7 0 0 Subkontraktor
1489 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Mon 15/04/19 Mon 15/04/19 1 day 1 day 3 0 0 Subkontraktor
1490 End of Line Resistor Subkontraktor Tue 16/04/19 Tue 16/04/19 1 day 1 day 1 0 0 Subkontraktor
1491 Kabel FRC 2x1.5 mm² dalam High Impact Sat 06/04/19 Mon 08/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1492 Instalasi Indicator Lamp Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1493 Indicator Lamp Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1494 Instalasi Alarm Bell Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1495 Alarm Bell Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1496 Manual call point with backbox Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1497 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1498 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1499 CHAMBER 6 Sat 06/04/19 Thu 18/04/19 13 days 13 days 0 0 0
1500 Kabel NYA 2x1x1.5 mm² dalam High Wed 10/04/19 Thu 18/04/19 9 days 9 days 0 0 0
Impact conduit dia. 20 mm
Page 19
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1501 Instalasi Detector Fire Alarm & ROR Subkontraktor Wed 10/04/19 Sun 14/04/19 5 days 5 days 11 0 0 25/02/19 Subkontraktor
1502 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Wed 10/04/19 Sun 14/04/19 5 days 5 days 7 0 0 Subkontraktor
1503 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Mon 15/04/19 Wed 17/04/19 3 days 3 days 3 0 0 Subkontraktor
1504 End of Line Resistor Subkontraktor Thu 18/04/19 Thu 18/04/19 1 day 1 day 1 0 0 Subkontraktor
1505 Kabel FRC 2x1.5 mm² dalam High Impact Sat 06/04/19 Mon 08/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1506 Instalasi Indicator Lamp Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1507 Indicator Lamp Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1508 Instalasi Alarm Bell Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1509 Alarm Bell Subkontraktor Sat 06/04/19 Sat 06/04/19 1 day 1 day 1 0 0 Subkontraktor
1510 Manual call point with backbox Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1511 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1512 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1513 CHAMBER 7 Sun 07/04/19 Sun 21/04/19 15 days 15 days 0 0 0
1514 Kabel NYA 2x1x1.5 mm² dalam High Mon 15/04/19 Sun 21/04/19 7 days 7 days 0 0 0
Impact conduit dia. 20 mm
1515 Instalasi Detector Fire Alarm & ROR Subkontraktor Mon 15/04/19 Fri 19/04/19 5 days 5 days 11 0 0 Subkontraktor
1516 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Mon 15/04/19 Fri 19/04/19 5 days 5 days 7 0 0 Subkontraktor
1517 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Sat 20/04/19 Sat 20/04/19 1 day 1 day 3 0 0 Subkontraktor
1518 End of Line Resistor Subkontraktor Sun 21/04/19 Sun 21/04/19 1 day 1 day 1 0 0 Subkontraktor
1519 Kabel FRC 2x1.5 mm² dalam High Impact Sun 07/04/19 Tue 09/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1520 Instalasi Indicator Lamp Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1521 Indicator Lamp Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1522 Instalasi Alarm Bell Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1523 Alarm Bell Subkontraktor Sun 07/04/19 Sun 07/04/19 1 day 1 day 1 0 0 Subkontraktor
1524 Manual call point with backbox Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1525 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1526 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1527 CHAMBER 8 Mon 08/04/19 Tue 16/04/19 9 days 9 days 0 0 0
1528 Kabel NYA 2x1x1.5 mm² dalam High Mon 08/04/19 Tue 16/04/19 9 days 9 days 0 0 0
Impact conduit dia. 20 mm
1529 Instalasi Detector Fire Alarm & ROR Subkontraktor Mon 08/04/19 Fri 12/04/19 5 days 5 days 11 0 0 Subkontraktor
1530 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Mon 08/04/19 Fri 12/04/19 5 days 5 days 7 0 0 Subkontraktor
1531 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Sat 13/04/19 Mon 15/04/19 3 days 3 days 3 0 0 Subkontraktor
1532 End of Line Resistor Subkontraktor Tue 16/04/19 Tue 16/04/19 1 day 1 day 1 0 0 Subkontraktor
1533 Kabel FRC 2x1.5 mm² dalam High Impact Mon 08/04/19 Wed 10/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1534 Instalasi Indicator Lamp Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1535 Indicator Lamp Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1536 Instalasi Alarm Bell Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1537 Alarm Bell Subkontraktor Mon 08/04/19 Mon 08/04/19 1 day 1 day 1 0 0 Subkontraktor
1538 Manual call point with backbox Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1539 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1540 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1541 CHAMBER 9 Tue 09/04/19 Mon 15/04/19 7 days 7 days 0 0 0
1542 Kabel NYA 2x1x1.5 mm² dalam High Sat 13/04/19 Mon 15/04/19 3 days 3 days 0 0 0
Impact conduit dia. 20 mm
1543 Instalasi Detector Fire Alarm & ROR Subkontraktor Sat 13/04/19 Sat 13/04/19 1 day 1 day 11 0 0 Subkontraktor
1544 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Sat 13/04/19 Sat 13/04/19 1 day 1 day 7 0 0 Subkontraktor
1545 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Sun 14/04/19 Sun 14/04/19 1 day 1 day 3 0 0 Subkontraktor
1546 End of Line Resistor Subkontraktor Mon 15/04/19 Mon 15/04/19 1 day 1 day 1 0 0 Subkontraktor
1547 Kabel FRC 2x1.5 mm² dalam High Impact Tue 09/04/19 Thu 11/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1548 Instalasi Indicator Lamp Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1549 Indicator Lamp Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1550 Instalasi Alarm Bell Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1551 Alarm Bell Subkontraktor Tue 09/04/19 Tue 09/04/19 1 day 1 day 1 0 0 Subkontraktor
1552 Manual call point with backbox Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1553 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1554 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1555 CHAMBER 10 Wed 10/04/19 Tue 16/04/19 7 days 7 days 0 0 0
1556 Kabel NYA 2x1x1.5 mm² dalam High Sun 14/04/19 Tue 16/04/19 3 days 3 days 0 0 0
Impact conduit dia. 20 mm
1557 Instalasi Detector Fire Alarm & ROR Subkontraktor Sun 14/04/19 Sun 14/04/19 1 day 1 day 11 0 0 Subkontraktor
1558 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Sun 14/04/19 Sun 14/04/19 1 day 1 day 7 0 0 Subkontraktor
1559 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Mon 15/04/19 Mon 15/04/19 1 day 1 day 3 0 0 Subkontraktor
1560 End of Line Resistor Subkontraktor Tue 16/04/19 Tue 16/04/19 1 day 1 day 1 0 0 Subkontraktor
1561 Kabel FRC 2x1.5 mm² dalam High Impact Wed 10/04/19 Fri 12/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1562 Instalasi Indicator Lamp Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1563 Indicator Lamp Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1564 Instalasi Alarm Bell Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1565 Alarm Bell Subkontraktor Wed 10/04/19 Wed 10/04/19 1 day 1 day 1 0 0 Subkontraktor
1566 Manual call point with backbox Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
1567 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
1568 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Fri 12/04/19 Fri 12/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1569 Power House & pluging charger Thu 11/04/19 Tue 14/05/19 19 days 34 days 0 0 0
1570 Kabel NYA 2x1x1.5 mm² dalam High Tue 14/05/19 Tue 14/05/19 4 days 1 day 0 0 0
Impact conduit dia. 20 mm
1571 Instalasi Detector Fire Alarm & ROR Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 11 0 0 Subkon
1572 Heat Detector ROR c/w Alarm Response Lamp
Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 7 0 0 Subkon
1573 Smoke Detector c/w Alarm Response Lamp
Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 3 0 0 Subkon
1574 End of Line Resistor Subkontraktor Tue 14/05/19 Tue 14/05/19 1 day 1 day 1 0 0 Subkon
1575 Kabel FRC 2x1.5 mm² dalam High Impact Thu 11/04/19 Sat 13/04/19 3 days 3 days 0 0 0
conduit dia. 20 mm
1576 Instalasi Indicator Lamp Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
1577 Indicator Lamp Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
1578 Instalasi Alarm Bell Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
1579 Alarm Bell Subkontraktor Thu 11/04/19 Thu 11/04/19 1 day 1 day 1 0 0 Subkontraktor
Page 20
ID Task Task Name Resource Names Start Finish Baseline Duration Volume Kontrak Volume Realisasi Volume Realisasi
Mode Duration S/D Periode Lalu Periode Ini November December January February March April May
15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12 07/01 14/01 21/01 28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05
1580 Manual call point with backbox Subkontraktor Fri 12/04/19 Fri 12/04/19 1 day 1 day 1 0 0 25/02/19 Subkontraktor
1581 Terminal Box 24 pair size 30X25X8 cm TB Subkontraktor
24 Fri 12/04/19 Fri 12/04/19 1 day 1 day 1 0 0 Subkontraktor
1582 Kabel NYA 2x1,5 mm Instalasi Dari Subkontraktor Sat 13/04/19 Sat 13/04/19 1 day 1 day 1 0 0 Subkontraktor
terminal box Ke MCP-FA
1583 Pekerjaan Penyalur Petir Tue 19/03/19 Fri 05/04/19 18 days 18 days 0 0 0
1584 Perijinan Subkontraktor Tue 19/03/19 Mon 01/04/19 14 days 14 days 1 0 0 Subkontraktor
1585 Tiang penyangga penangkal petir 2 meter Subkontraktor Tue 02/04/19 Tue 02/04/19 1 day 1 day 2 0 0 Subkontraktor
1586 Head terminal Radius Proteksi 90 Meter Subkontraktor Wed 03/04/19 Wed 03/04/19 1 day 1 day 2 0 0 Subkontraktor
1587 Down conductor Coaxial Kabel NYY 1X70 mmSubkontraktor Thu 04/04/19 Thu 04/04/19 1 day 1 day 178 0 0 Subkontraktor
1588 BC 50 mm ring grounding Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 37 0 0 Subkontraktor
1589 Sumuran grounding tahanan max 3 ohm Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 3 0 0 Subkontraktor
1590 Material Bantu Subkontraktor Fri 05/04/19 Fri 05/04/19 1 day 1 day 1 0 0 Subkontraktor
1591 Pekerjaan Pengadan dan Pemasangan Generator Set Sun 14/04/19 Mon 13/05/19 31 days 30 days 0 0 0
1592 - Pengadaan Generator Set, Kapasitas 250 Subkontraktor;Crane Sun 14/04/19 Mon 13/05/19 2 days 2 days 1 0 0 Subkont
KVA (Silent)
1593 pemasangan Generator Set, Kapasitas 250 Subkontraktor;Crane Sat 20/04/19 Sun 21/04/19 1 day 1 day 0 0 0 Subkontraktor;Crane
KVA (Silent)
1594 Tangki bahan bakar 5000 l, beserta Subkontraktor;Crane Sat 20/04/19 Sun 21/04/19 1 day 1 day 1 0 0 Subkontraktor;Crane
kelengkapannya RANGKA ;
1595 Pemipaan bahan bakar dari Tangki ke Subkontraktor;Crane Sat 20/04/19 Sun 21/04/19 1 day 1 day 1 0 0 Subkontraktor;Crane
Genset beserta aksesorisnya
1596 Finish Wed 15/05/19 Wed 15/05/19 0 days 0 days 0 0 0 15/05