DAFTAR ISI.............................................................................................................................................1
BAB I......................................................................................................................................................3
PENDAHULUAN......................................................................................................................................3
1.1 LATAR BELAKANG...................................................................................................................3
1.2 NAMA DAN LOKASI PEKERJAAN.............................................................................................3
1.3 LINGKUP PEKERJAAN.............................................................................................................3
1.4 WAKTU PELAKSANAAN...........................................................................................................4
1.5 PENGENDALIAN WAKTU PELAKSANAAN.................................................................................4
1.6 HARI KERJA EFEKTIF..............................................................................................................5
-.............................................................................................................................................................5
BAB II.....................................................................................................................................................6
METODE.................................................................................................................................................6
PELAKSANAAN PEKERJAAN...................................................................................................................6
2.1 PEKERJAAN PERSIAPAN.........................................................................................................6
2.1.1. PEKERJAAN PENATAAN DAN PERATAAN LAHAN.............................................................6
2.1.2. MOBILISASI DAN DEMOBILISASI.....................................................................................6
2.2 PEKERJAAN TANAH & PASANGAN...........................................................................................8
2.2.1. Pekerjaan Galian Tanah.....................................................................................................8
2.2.2. Pekerjaan Urugan Tanah Kembali.......................................................................................8
2.2.3. Pekerjaan Urugan Pasir Bawah Pondasi.............................................................................9
2.2.4. Pekerjaan Pasangan Batu Kosong dan Batu Kali..................................................................9
2.2.5. Pekerjaan Pembuatan Tiang Pancang dan Penyambungan...................................................9
2.2.6. Pekerjaan Pembuatan Tiang Pancang dan Penyambungan...................................................9
2.2.7. Pekerjaan Sloof................................................................................................................9
2.2.8. Pekerjaan Balok..............................................................................................................10
2.2.9. Pekerjaan Kolom............................................................................................................10
2.2.10. Pekerjaan Urugan Pasir Bawah Lantai..............................................................................11
2.2.11. Pekerjaan Pasangan Paving & Kansteen...........................................................................11
2.3 PEKERJAAN LANTAI & SANITAIR/PLUMBING.........................................................................11
2.3.1. Pekerjaan Pasangan Keramik..........................................................................................11
2.3.2. Pekerjaan Pasangan Bata................................................................................................12
2.3.3. Pekerjaan Plester & Acian................................................................................................12
2.3.4. Pekerjaan Sanitair...........................................................................................................12
2.3.5. Pekerjaan Plumbing........................................................................................................13
2.4 PEKERJAAN PENGECATAN...................................................................................................13
9
2.4.1. Pekerjaan Pengecatan....................................................................................................13
2.5 PEKERJAAN KAYU & ALUMINIUM..........................................................................................13
2.5.1. Pekerjaan Persipan.........................................................................................................13
2.5.2. Pekerjaan Pengukuran....................................................................................................13
2.5.3. Pemasangan kusen alumunium dan frame........................................................................13
2.5.4. Pemasangan plafon........................................................................................................14
2.5.5. Pemasangan Atap...........................................................................................................14
2.6 PEKERJAAN INSTALASI LISTRIK...........................................................................................14
2.6.1. Pekerjaan instalasi listrik..................................................................................................14
2.7 PEKERJAAN TANAMAN.........................................................................................................15
2.7.1. Pekerjaan Tanaman........................................................................................................15
BAB III..................................................................................................................................................16
PENUTUP.............................................................................................................................................16
9
BAB I
PENDAHULUAN
A. PEKERJAAN PERSIAPAN
1. Penataan dan perataan lahan
2. Mobilisasi dan Demobilisasi
9
12. Pekerjaan Pompa Transfer
13. Pekerjaan Pompa booster
D. PEKERJAAN PENGECATAN
1. Pekerjaan Pengecatan Tembok
2. Pengecatan Garis Parkir
G. PEKERJAAN TANAMAN
9. Pekerjaan Penanaman Bibit
10. Pekerjaan Pemupukan
9
1. Persiapan
2. Pekerjaan jalan setapak
3. Pekerjaan Penanaman
a. Droping bibit di lapangan
b. Penanaman di lokasi tanam
4. Pekerjaan Penataan lahan
5. Pekerjaan toko souvenir
6. Pekerjaan foodcourt
7. Pekerjaan tempat parkir
8. Pekerjaan toilet
9. Pekerjaan signage
10. Pekerjaan green house
11. Pekerjaan gazebo
12. Pekerjaan camping ground
13. Pekerjaan dek
14. Pekerjaan sumber pengairan
15. Pekerjaan sollar cell
16. Pemantauan pelaksanaan
pekerjaan dan pemeliharaan
17 . Pelaporan
BAB II
METODE
PELAKSANAAN PEKERJAAN
9
mana dituangkan dalam Keppres No.80 Tahun 2000.
Rincian pekerjaan yang harus dilakukan dalam tahapan pekerjaan persiapan adalah sebagai
berikut :
9
Scaffolding Mesin Aduk Manual
Genset
9
e) Sebelum dimulainya penggalian, Pelaksana Pekerjaan harus membuat bouwplank sebagai
patok dasar pengukuran bangunan. Pelaksana Pekerjaan harus menjaga dan memelihara
keutuhan serta ketetapan letak dan tinggi patok-patok pengukuran.
f) Galian dilakukan sesuai dengan batas-batas peil dan kemiringan pada gambar-gambar
perencanaan. Galian tersebut harus mempunyai ukuran yang cukup agar pelaksanaan
penempatan konstruksi dapat dilakukan dengan dimensi yang sesuai dengan gambar
perencanaan.
g) Semua material lepas, batu-batuan lapuk dan lapisan-lapisan tipis harus dibuang. Jika material
dasar galian sesuai dengan gambar-gambar perencanaan ternyata terdiri dari material lunak
atau tidak cukup kokoh menurut pendapat Konsultan Manajemen Konstruksi, maka Pelaksana
Pekerjaan harus mengganti material dasar tersebut dengan material yang tepat sesuai dengan
petunjuk Konsultan Manajemen Konstruksi.
h) Pekerjaan galian harus sepenuhnya dilaksanakan dalam pengawasan Konsultan Manajemen
Konstruksi.
9
b) Pemakaian ukuran batu kali harus variatif.
c) Susunan batu kali dibuat berdiri, dengan ketebalan sekitar 20 cm dan dikunci dengan batu
yang ukurannya lebih kecil.
d) Batu kali jangan blondos, tetapi batu pecah dengan tujuan agar bidang sentuh antar
permukaan batu belah lebih luas
9
e) Untuk pelaksanaan pengecoran balok, digunakan concrete pump yang menyalurkan beton
readymix dari truck mixer ke lokasi pengecoran, dengan menggunakan pipa pengecoran yang
di sambung-sambung
f) Alirkan beton readymix sampai ke lokasi pengecoran, lalu padatkan dengan menggunakan
vibrator
g) Setelah beton dipadatkan, maka dilakukan petrataan permukaan coran dengan menggunakan
alat-alat manual
h) Setelah proses pengecoran selesai ampai batas pengecoran, maka dilakukan finishing
i) Pembongkaran bekisting balok dilakukan 7 hari setelah pengecoran
9
d) Lakukan pemasangan paving block dengan cara maju kedepan, sementara pekerja pemasang
paving berada diatas paving yang telah terpasang.
e) Untuk tepian lahan/ sudut-sudut yang belum terpasang paving block (las-lasan), potong paving
block dengan menggunakan alat pemotong paving block / paving block cutter.
f) Setelah lahan 100% sudah terpasang paving block, selanjutnya kita lakukan pengisian antar
naat paving block tersebut (pengisian joint filler) dengan menggunakan abu batu.
g) Padatkan paving block yang telah terpasang dengan menggunakan baby roller atau stamper
kodok 1 sampai 2 kali putaran agar timbul gaya saling mengunci antar paving block satu sama
lainnya.
h) Bersihkan area lahan yang telah terpasang paving block dari sisa-sisa abu batu
9
memperhatikan lot lokasi paling atas dan bawah dengan menyesuaikan plesteran antar
kepalaan
d) Basahi permukaan plesteran dan aci permukaan plesteran hingga rata dan menutup seluruh
pori-pori plesteran
e) Finishing dengan kertas ex. Semen
f) Kondisi acian setelah kering di gosok dengan spons
9
e) Pengecatan dilakukan lapis demi lapis hingga didapatkan permukaan cat dengan warna yang
merata
9
2.5.5. Pemasangan Atap
Langkah dan tahapan pelaksanaan pekerjaan atap sebgai berikut :
a) Kontrol ulang apakah rangka atap telah terpasang sesuai dengan spesifikasi yang
ditentukan, misalnya jarak antar-usuk, jarak antar-reng, ukuran kayu untuk kuda-kuda,
gording, usuk dan reng, sambungan antarkayu, dan aplikasi obat antirayap
b) Pasang dahulu lisplank dan talang genteng dinaikkan
c) Bila menggunakan insulasi (aluminium foil), pasanglah di atas usuk, lalu pasangan reng
d) Pasang satu jalur genteng terlebih dahulu dari bawah ke atas. Pemasangan harus lurus dan
rapi agar polanya menjadi rapi agar polanya menjadi rapi dan tidak berbelok-belok
BAB III
PENUTUP
9
Paparan tentang metode pelaksanaan pekerjaan Pemulihan Keruskan Lahan Akses Terbuka Bekas
Pertambangan Pasir dan Batu ini diharapkan dapat memberikan gambaran tentang tahapan teknis
pekerjaan dilapangan.