DATA PENDUKUN

PAKET : PENINGKATAN JALAN RUAS JALAN JAMPANG TENGAH - KIARADUA (


KM.BDG. 126+500 - KM.BDG.128+000
LOKASI : RUAS JALAN JAMPANG TENGAH - KIARADUA
NOMOR ITEM PEKERJAAN : 7.9
ITEM PEKERJAAN : Pasangan Batu
SATUAN : M3
DIMENSI
NO STA Ki / Ka Panjang w1 w2 w3 w4 w5
(m) (m) (m) (m) (m) (m)
D
1 Dudukan Plat Decker 110.00 0.30 0.50 0.30 0.50 0.50
Lantai 110.00 0.50

Gambar

W1 W2

W4

DUDUKAN PLAT
DECKER

PENGAWAS LAPANGAN KONSULTAN SUPERVIS


PT. KARPA Jo. CV. Hendra
ASEP JUHARA,ST.M.Si SUKAMTO HAMDANI
NIP. 1966 1010 2009 01 1 001 Chief Inspektor
DATA PENDUKUNG

TENGAH - KIARADUA ( 1,50 KM )

DIMENSI Luas
h1 h2 h3 Volume Keterangan
(m) (m) (m) ( m2 ) (m3)

0.50 0.20 0.20 0.800 88.00


0.20 0.100 11.00 0.90

JUMLAH C 99.00

W3

h1

h2

h3

W5

DUDUKAN PLAT
DECKER

ONSULTAN SUPERVISI PENYEDIA JASA


KARPA Jo. CV. Hendra Co
SUKAMTO HAMDANI M. IRZAL FAHLEVI, AM.d
Chief Inspektor Penanggung Jawab Teknik
DATA PENDUKUNG KUANTITA

NAMA PAKET : PENINGKATAN JALAN RUAS JALAN JAMPANG TENGAH - KIARADUA


LOKASI : RUAS JALAN JAMPANG TENGAH - KIARADUA
NOMOR ITEM PEKERJAAN : 7.1.(5)
ITEM PEKERJAAN : Beton K - 250
SATUAN : M3
DIMENSI
NO STA Ki / Ka Panjang w1 w2 w3 h1 h2
(m) (m) (m) (m) (m) (m)
A Lantai Plat Decker
1 110.00 0.90 0.15

110.00

Gambar :

W1

PENGAWAS LAPANGAN KONSULTAN SUPERVIS


PT. KARPA Jo. CV. Hendra
ASEP JUHARA,ST.M.Si SUKAMTO HAMDANI
NIP. 1966 1010 2009 01 1 001 Chief Inspektor
ENDUKUNG KUANTITAS

AMPANG TENGAH - KIARADUA ( 1,50 KM ) KM.BDG. 126+500 - KM.BDG.128+000

DIMENSI Luas
ht Volume Keterangan
(m) (m ) 2
(m3)

0.14 14.85

JUMLAH A 15.00 7.00

h1

KONSULTAN SUPERVISI PENYEDIA JASA


PT. KARPA Jo. CV. Hendra Co
SUKAMTO HAMDANI M. IRZAL FAHLEVI, AM.d
Chief Inspektor Penanggung Jawab Teknik
DATA PENDUKUNG KUANTITAS

NAMA PAKET : PENINGKATAN JALAN RUAS JALAN JAMPANG TENGAH - KIARADUA ( 1,50 K
LOKASI : RUAS JALAN JAMPANG TENGAH - KIARADUA
NOMOR ITEM PEKERJAAN : 7.3.(1)
ITEM PEKERJAAN : BAJA TULANGAN U 24 POLOS
SATUAN : Kg

Ki DIMENSI Jarak Jumlah Panjang


NO STA Cl Panjang lebar 12 10 12
Ka (m) (m) ( cm ) (bh) (bh) (m)

A
1 Lantai Plat Decker 0.50 1.00 20.00 4.00 2.20
20.00 12.00
JUMLA
PJ 110.00

Gambar

0.95

0.10

Ø12 - 20
Ø10 - 20

PENGAWAS LAPANGAN KONSULTAN SUPERVISI


PT. KARPA Jo. CV. Hendra Co

ASEP JUHARA,ST.M.Si SUKAMTO HAMDANI


NIP. 1966 1010 2009 01 1 001 Chief Inspektor
NDUKUNG KUANTITAS

JALAN JAMPANG TENGAH - KIARADUA ( 1,50 KM ) KM.BDG. 126+500 - KM.BDG.128+000

Panjang Berat
10 12 10
(m) (Kg) (Kg)

7.81
0.55 4.06
JUMLAH / buah 7.81 4.06
1,718.20 893.20

JUMLAH A
1,718.20 893.20
TOTAL A 2,611.00

0.10

PENYEDIA JASA

M. IRZAL FAHLEVI, AM.d


Penanggung Jawab Teknik
ITEM PEMBAYARAN NO. : 8.4.(1)

ITEM PEMBAYARAN NO. : 8.4.(3) .(a)


JENIS PEKERJAAN : Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (plat rambu jadi, pipa dan beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.0 KM
5 Jam kerja efektif per-hari Tk 7.00 jam

II. URUTAN KERJA


1 Kesatuan pondasi, pelat & tiang rambu disiapkan dan
dipasang di tempat yang telah ditentukan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Pelat Rambu Jadi (Engineering Grade) (M35a) 1.00 BH
1.b. Pipa Galvanis Dia.1,6" (M24) 1.00 Batang
1.c. Beton K-175 (M60) 0.016 M3
1.d. Cat, dan bahan lainnya - 1.0000 Ls
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 24.0 menit
- Menurunkan = Rata-rata 2.5 menit / buah T3 37.5 menit
- Lain-lain = geser, atur, tunggu, dll. T4 30.0 menit
Ts 121.5 menit

Kap. Prod. / Jam = Cp Q1 7.407 Buah


Ts : 60

Koefisien Alat / Buah = 1 : Q1 (E08) 0.1350 Jam


2.b. ALAT BANTU
- Tang, Obeng, dll = 2 set
- Pacul / Sekop = 4 buah

3. TENAGA
Produksi pemasangan rambu dalam 1 hari = Tk x Q1 Qt 51.85 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 3.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0000 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4050 jam
- Pekerja = (Tk x P) : Qt (L01) 0.6750 jam

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 8.4.(3) .(a)
JENIS PEKERJAAN : Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,016,190.14 / Buah

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 Buah
ITEM PEMBAYARAN NO. : 8.4.(6) .(a)
JENIS PEKERJAAN : Patok Kilometer
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok kilometer beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 3.0 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
7 Tulangan praktis Rc 125.00 Kg/M3

II. URUTAN KERJA


1 Tempat penanaman patok disiapkan / digali
2 Patok Kilometer ditanam ke dalam tanah dengan
elevasi puncak patok sesuai dgn. ketentuan dan dicat

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Beton K-175 = (0.30 x 0.30 x 1.60) x Fh (M60) 0.1512 M3
1.b. Baja Tulangan (M39) 18.9000 Kg
1.c. Cat, dan material lainnya - Ls

2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = muat, atur, ikat, dll T1 20.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 14.40 menit
- Menurunkan = Rata-rata 1.5 menit / buah T3 22.5 menit
- Lain-lain = geser, tunggu, dll T4 10.0 menit
Ts 66.9 menit

Kap. Prod. / Jam = Cp Q1 13.453 Buah


Ts : 60

Koefisien Alat / Buah = 1 : Q1 (E08) 0.0743 Jam

2.b. ALAT BANTU


- Pacul / Sekop = 4 buah
- Kunci Baut = 2 buah

3. TENAGA
Produksi pasang patok kilometer / hari = Tk x Q1 Qt 94.17 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0743 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1487 jam
- Pekerja = (Tk x P) : Qt (L01) 0.3717 jam

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 8.4.(6) .(a)
JENIS PEKERJAAN : Patok Kilometer
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 375,705.51 / Buah

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 7.00 Buah
ITEM PEMBAYARAN NO. : 8.4.(6) .(b)
JENIS PEKERJAAN : Patok Hektometer
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok kilometer beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 3.0 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
7 Tulangan praktis Rc 125.00 Kg/M3

II. URUTAN KERJA


1 Tempat penanaman patok disiapkan / digali
2 Patok Kilometer ditanam ke dalam tanah dengan
elevasi puncak patok sesuai dgn. ketentuan dan dicat
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
1.a. Beton K-175 = (0.20 x 0.20 x 1.50) x Fh (M60) 0.0630 M3
1.b. Baja Tulangan (M39) 7.8750 Kg
1.c. Cat, dan material lainnya - Ls

2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = muat, atur, ikat, dll T1 20.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 14.40 menit
- Menurunkan = Rata-rata 1.5 menit / buah T3 22.5 menit
- Lain-lain = geser, tunggu, dll T4 10.0 menit
Ts 66.9 menit

Kap. Prod. / Jam = Cp Q1 13.453 Buah


Ts : 60

Koefisien Alat / Buah = 1 : Q1 (E08) 0.0743 Jam

2.b. ALAT BANTU


- Pacul / Sekop = 4 buah
- Kunci Baut = 2 buah

3. TENAGA
Produksi pasang patok kilometer / hari = Tk x Q1 Qt 94.17 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0743 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1487 jam
- Pekerja = (Tk x P) : Qt (L01) 0.3717 jam

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 8.4.(6) .(b)
JENIS PEKERJAAN : Patok Hektometer
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN


4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 175,237.34 / Buah

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 63.00 Buah
Analisa EI-841

Analisa LI-843a
Engineering Grade
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Pemeliharaan Berkala/Rehabilitasi Jalan Cirebon - Cikijing
PROP / KAB / KODYA : Jawa Barat / Kab. Cirebon
ITEM PEMBAYARAN NO. : 8.4.(3) .(a)
JENIS PEKERJAAN : Rambu Jalan Tunggal dengan Permuk
div8 SATUAN PEMBAYARAN : BH

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja Biasa (L01) jam 0.6750


2. Tukang (L02) jam 0.4050
3. Mandor (L03) jam 0.0000

JUMLAH HARGA TENAGA

B. BAHAN

1. Pelat Rambu (M35a) BH 1.0000


2. Pipa Galvanis (M24) Batang 1.0000
3. Beton K-175 (M60) M3 0.0160
4. Cat, dan bahan lainnya Ls 1.0000

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck E08 Jam 0.1350


2. Alat Bantu Ls 1.0000
JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pe
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan ope
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tid
Berlanjut ke hal. berikut. yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa LI-843a
gineering Grade
URAIAN ANALISA HARGA SATUAN
Lanjutan

KETERANGAN
Analisa EI-846a

URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Pemeliharaan Berkala/Rehabilitasi Jalan Cirebon - Cikijing
PROP / KAB / KODYA : Jawa Barat / Kab. Cirebon
ITEM PEMBAYARAN NO. : 8.4.(6) .(a)
JENIS PEKERJAAN : Patok Kilometer
SATUAN PEMBAYARAN : BH

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja Biasa (L01) jam 0.3717


2. Tukang (L02) jam 0.1487
3. Mandor (L03) jam 0.0743

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-175 (M60) M3 0.1512


2. Baja Tulangan (M39) Kg 18.9000
3. Cat, dan material lainnya Ls 1.0000

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck E08 Jam 0.0743


2. Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pe
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan ope
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tid
Berlanjut ke hal. berikut. yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-846a

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Analisa EI-846b

URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Pemeliharaan Berkala/Rehabilitasi Jalan Cirebon - Cikijing
PROP / KAB / KODYA : Jawa Barat / Kab. Cirebon
ITEM PEMBAYARAN NO. : 8.4.(6) .(b)
JENIS PEKERJAAN : Patok Hektometer
SATUAN PEMBAYARAN : BH

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA
1. Pekerja Biasa (L01) jam 0.3717
2. Tukang (L02) jam 0.1487
3. Mandor (L03) jam 0.0743

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-175 (M60) M3 0.0630


2. Baja Tulangan (M39) Kg 7.8750
3. Cat, dan material lainnya Ls 1.0000

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck E08 Jam 0.0743


2. Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pe
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan ope
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tid
Berlanjut ke hal. berikut. yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-846b

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Analisa EI-841

Analisa LI-843a

ANDAR UNTUK
NG-MASING HARGA SATUAN

habilitasi Jalan Cirebon - Cikijing

PERKIRAAN VOL. PEK. : 0.00


TOTAL HARGA (Rp.) : 0.00
% THD. BIAYA PROYEK : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

9,342.11 6,305.93
11,677.80 4,729.51
16,348.88 0.00

JUMLAH HARGA TENAGA 11,035.44

540,000.00 540,000.00
329,500.00 329,500.00
691,256.16 11,060.10
5,000.00 5,000.00

JUMLAH HARGA BAHAN 885,560.10

197,879.12 26,713.68
500.00 500.00
UMLAH HARGA PERALATAN 27,213.68

LATAN ( A + B + C ) 923,809.22
92,380.92
1,016,190.14
uk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

en untuk menyelesaikan satu satuan pekerjaan dari nomor

han bakar, bahan habis dipakai dan operator.


seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-846a

ANDAR UNTUK
NG-MASING HARGA SATUAN

habilitasi Jalan Cirebon - Cikijing


PERKIRAAN VOL. PEK. : 7.00
TOTAL HARGA (Rp.) : 2,552,948.18
% THD. BIAYA PROYEK : 0.02

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

9,342.11 3,472.15
11,677.80 1,736.10
16,348.88 1,215.27

JUMLAH HARGA TENAGA 6,423.52

691,256.16 104,517.93
11,000.00 207,900.00
7,500.00 7,500.00

JUMLAH HARGA BAHAN 319,917.93

197,879.12 14,709.01
500.00 500.00

UMLAH HARGA PERALATAN 15,209.01

LATAN ( A + B + C ) 341,550.46
34,155.05
375,705.51
uk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
en untuk menyelesaikan satu satuan pekerjaan dari nomor

han bakar, bahan habis dipakai dan operator.


seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-846b

ANDAR UNTUK
NG-MASING HARGA SATUAN

habilitasi Jalan Cirebon - Cikijing

PERKIRAAN VOL. PEK. : 63.00


TOTAL HARGA (Rp.) : 10,828,416.69
% THD. BIAYA PROYEK : 0.07

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)
9,342.11 3,472.15
11,677.80 1,736.10
16,348.88 1,215.27

JUMLAH HARGA TENAGA 6,423.52

691,256.16 43,549.14
11,000.00 86,625.00
7,500.00 7,500.00

JUMLAH HARGA BAHAN 137,674.14

197,879.12 14,709.01
500.00 500.00

UMLAH HARGA PERALATAN 15,209.01

LATAN ( A + B + C ) 159,306.67
15,930.67
175,237.34
uk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

en untuk menyelesaikan satu satuan pekerjaan dari nomor

han bakar, bahan habis dipakai dan operator.


seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. : 8.1 (1)

ITEM PEMBAYARAN NO. : 8.3.(3)


JENIS PEKERJAAN : Pohon
SATUAN PEMBAYARAN : Buah URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan tenaga pekerja
2 Lokasi pekerjaan : di sepanjang jalan
3 Bahan dasar pohon dan bahan lainnya diterima di lokasi pekerjaan
4 ukuran lubang 0,5 x 0,5 x 0,5 m

5 Jam kerja efektif per-hari Tk 7.00 jam


6 Faktor kehilangan bahan Fh 1.10 -

II. URUTAN KERJA


1 Penggalian lubang
2 Penanaman pohon dan penimbunan dengan tanah humus
3 Pemagaran (sesuai kebutuhan)

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. - pohon (M32) 1.00 bh
1.b. - Tanah humus setebal 20 cm mxx 0.22 m3
1.c. - Pupuk mxx 0.50 kg

2. ALAT
2.a. ALAT BANTU
- Pacul/sekop = 4 buah
- Gerobak Dorong = 1 buah
- Pagar Bambu/kayu = sesuai kebutuhan

3. TENAGA
Produksi penanaman rumput dalam 1 hari Qt 100.00 M2
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 0.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / M2 :
- Mandor = (Tk x M) : Qt (L03) 0.0700 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.0000 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4200 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 33,140.92 / bh

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 bh
Analisa EI-811

Analisa LI-833

URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Pemeliharaan Berkala/Rehabilitasi Jalan Cirebon - Cikijing
PROP / KAB / KODYA : Jawa Barat / Kab. Cirebon
ITEM PEMBAYARAN NO. : 8.3.(3)
JENIS PEKERJAAN : Pohon
SATUAN PEMBAYARAN : Buah

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja Biasa (L01) jam 0.4200


2. Tukang (L02) jam 0.0000
3. Mandor (L03) jam 0.0700

JUMLAH HARGA TEN

B. BAHAN

1. POHON M2 1.0000
JUMLAH HARGA BA

C. PERALATAN

1. Alat Bantu Ls 1.0000

JUMLAH HARGA PERALA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volum
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan o
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-811 Analisa EI-8Analisa EI-811

Analisa LI-833

UNTUK
SING HARGA SATUAN

n Cirebon - Cikijing

PERKIRAAN VOL. PEK. : 0.00


TOTAL HARGA (Rp.) : 0.00
% THD. BIAYA PROYEK : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

9,342.11 3,923.69
11,677.80 0.00
16,348.88 1,144.42

JUMLAH HARGA TENAGA 5,068.11

25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00

60.00 60.00

UMLAH HARGA PERALATAN 60.00

30,128.11
3,012.81
33,140.92
erja dan Peralatan, volume dan/atau ukuran

nyelesaikan satu satuan pekerjaan dari nomor

ahan habis dipakai dan operator.


ak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-841
Analisa EI-1042

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PEMBANGUNAN JALAN LINGKAR SUKABUMI SEGMEN 1 ( STA 0+000 - 6+900 )
LOKASI : JALAN LINGKAR SUKABUMI
PROV / KAB / KODYA : JAWA BARAT /KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 10.4 (2)
JENIS PEKERJAAN : Marka Jalan (Thermoplastic)
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.6000 5,013.75 3,008.25


2. Tukang (L02) Jam 0.1500 6,267.25 940.09
3. Mandor (L03) Jam 0.0750 8,774.13 658.06

JUMLAH HARGA TENAGA 4,606.40

B. BAHAN

1. Cat Marka (M17) Kg 1.9500 50,000.00 97,500.00


2. Thinner (M33) Liter 1.0500 22,000.00 23,100.00
3. Glass Bit (M34) Kg 0.4500 36,400.00 16,380.00

JUMLAH HARGA BAHAN 136,980.00

C. PERALATAN

1. Compressor (E05) Jam 0.0750 137,300.00 10,297.50


2. Dump Truck (E08) Jam 0.0750 170,500.00 12,787.50
3. Alat Bantu Ls 1.0000 250.00 250.00

JUMLAH HARGA PERALATAN 23,335.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 164,921.40


E. OVERHEAD & PROFIT 10.0 % x D 16,492.14
F. HARGA SATUAN PEKERJAAN ( D + E ) 181,413.54
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
H
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : REHABILITASI JALAN RUAS JALAN SUKABUMI ( BAROS ) - SAGARANTEN ( 2,00 KM ) KM.BD
LOKASI : RUAS JALAN SUKABUMI ( BAROS ) - SAGARANTEN
PROV / KAB / KODYA : JAWA BARAT / KABUPATEN SUKABUMI
ITEM PEMBAYARAN NO. : 7.15 (1)
JENIS PEKERJAAN : PEMBONGKARAN PASANGAN BATU
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1. Pekerja (L01) Jam 1.6000 9,342.11


2. Mandor (L03) Jam 0.4000 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

1.
2.

JUMLAH HARGA BAHAN

C. PERALATAN

1. COMPRESSOR (E15) Jam 0.2500 163,441.50


2. JACK HAMMER (E15) Jam 0.2500 31,900.81
3. DUMP TRUCK (E08) Jam 0.3815 197,879.12
4 Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume da
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan peke
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operat
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7151

RMULIR STANDAR UNTUK


LISA MASING-MASING HARGA SATUAN

SUKABUMI ( BAROS ) - SAGARANTEN ( 2,00 KM ) KM.BDG. 127+000 - KM.BDG. 129+000

JUMLAH
HARGA
(Rp.)

14,947.38
6,539.55

21,486.93

0.00

40,860.38
7,975.20
75,490.89
1,000.00

125,326.47
146,813.40
14,681.34
161,494.74
m operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

etiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

termasuk bahan bakar, bahan habis dipakai dan operator.


luaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
JANGAN DIBUANG
* ************************** *******
. 12,044,275,000.00 ******* 1 <=== Bahasa <1> Indonesia,
. ************************** ******* ******* ******* *******
Dua Belas Milyar Empat Puluh Empat Juta Dua Ratus Tujuh Puluh Lima Ribu Rupiah.
******* ************************** ******* ******* ******* *******
******* Satu Dua Tiga Empat Lima Enam Tujuh Delap ***
******* Ribu Juta Milyar ***
******* 012044275000 ***
******* ************************** ******* ******* ******* *******
******* 000 1 ***
******* 0 ***
******* Sepuluh ***
******* 0 ***
******* 0 ***
******* ***
******* ***
******* ***
******* ***
******* 275 2 ***
******* 2 Tujuh Puluh ***
******* Dua Ratus Lima Belas ***
******* 7 Lima ***
******* 5 Tujuh Puluh Lima ***
******* Tujuh Puluh Lima Tujuh Puluh Lima ***
******* Dua Ratus Tujuh Puluh Lima Ribu ***
******* ***
******* ***
******* 044 3 ***
******* 0 Empat Puluh ***
******* Empat Belas ***
******* 4 Empat ***
******* 4 Empat Puluh Empat ***
******* Empat Puluh Empat Empat Puluh Empat ***
******* Empat Puluh Empat Juta ***
******* ***
******* ***
******* 012 4 ***
******* 0 ***
******* Dua Belas ***
******* 1 Dua ***
******* 2 Dua ***
******* Dua Belas Dua Belas ***
******* Dua Belas Milyar ***
******* ***
******* 000 1 ***
******* 0 ***
******* Sepuluh ***
******* 0 ****
******* 0 ***
******* ***
******* ***
******* ***
******* ************************** ******* ******* ******* *******
******* Rupiah 78 00
******* Dua Belas Milyar Empat Puluh EmDua Belas Milyar Empat Puluh Empat Juta Dua Rat
******* Dua Belas Milyar Empat Puluh Empat Juta Dua Ratus Tujuh Puluh Lima Ribu Rupiah
******* Dua Belas Milyar Empat Puluh Empat Juta Dua Ratus Tujuh Puluh Lima Ribu Rupiah
******* ************************** ******* ******* ******* *******
ahasa <1> Indonesia, <2> Inggris

a Ribu Rupiah.
uh Empat Juta Dua Ratus Tujuh Puluh Lima Ribu
uluh Lima Ribu Rupiah
uluh Lima Ribu Rupiah.
PERHITUNGAN KEBUTUHAN VOLUME
MBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUM
Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+

DIVISI 1 - UMUM

DIVISI 2 - D R A I N A S E

DIVISI 3 - PEKERJAAN TANAH

DIVISI 4 - PELEBARAN PERKERASAN DAN BAHU JALAN

DIVISI 5 - PERKERASAN BERBUTIR

DIVISI 6 - PERKERASAN ASPAL

6.1(1) Lapis Resap Pengikat


10,000.00 1.00 1.00 1,000.00

6.1(2) Lapis Perekat


2,000.00 0.35 5.00 3,500.00

6.3(6d) Laston - Lapis Antara (AC-BC) Modifikasi Levelling

2,000.00 0.05 5.00 500.00 2.30

6.3(7a) Laston - Lapis Pondasi (AC-Base)

10,000.00 0.05 1.00 50.00

Err:509 Err:509

500 0.05 5.00 125.00


DIVISI 7 - STRUKTUR

DIVISI 8 - PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1(1) Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor

8.1(5) Campuran Aspal Panas untuk Pekerjaan Minor

8.4(1) Marka Jalan Thermoplastic


1,500.00 0.38 0.12 67.50
500.00 0.12 1.00 60.00
127.50
VOLUME
LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN S
0+949 - Km Bdg.100+894
1,150.00
PEMERINTAH PROVINSI JAWA BARAT
DINAS BINA MARGA
BALAI PENGELOLAAN JALAN WILAYAH PELAYANAN I

PERKIRAAN KUANTITAS
( EE )

PEKERJAAN
PEMBANGUNAN JEMBATAN PAKET ( 40,00 m ) DAN
CIJAMBE
JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR
CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2
LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 -
Km Bdg.100+894

SUMBER DANA APBD PROVINSI JAWA BARAT


TAHUN ANGGARAN 2015

PANITIA PENGADAAN PENYEDIA JASA KONSTRUKSI


KEGIATAN PENINGKATAN JALAN DAN JEMBATAN PROVINSI
DI BALAI PENGELOLAAN JALAN WILAYAH PELAYANAN I
Jalan Raya Ciranjang Km. 52.000 (Bdg) Telp. (0263) 322126 Cianjur 43282
JENIS MATA PEMBAYARAN UTAMA
NAMA PAKET :
PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40
m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1
TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
: Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+894
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI

Nomor
Bobot
Mata Pemb. Jenis Pekerjaan
Utama (%)

3.2(1) Timbunan Biasa Dari Selain Galian Sumber Bahan 5.344


5.6(1) Lapis Pondasi Agregat Dengan Cement Treated Base (CTB) 4.437
6.3(5a) Laston - Lapis Aus (AC-WC) 2.843
6.3(6a) Laston - Lapis Antara (AC-BC) 2.916
6.3(7a) Laston - Lapis Pondasi (AC-Base) 3.137
7.2(8) Unit Pracetak Gelagar Tipe I Bentang 40 Meter 54.147
7.3(1) Baja Tulangan U24 Polos 6.874
7.9 Pasangan Batu 2.598

TOTAL 82.296
JADWAL PELAKSANAAN PEKERJAAN
### ###
PAKET PEKERJAAN : PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
LOKASI : Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+894
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Minggu ( 1 - 4 ) Minggu ( 5 - 8 ) Minggu ( 9 - 12 ) Minggu ( 13 - 16) Minggu ( 17 - 20 ) Minggu ( 21- 24 ) Minggu ( 25- 28 )
No. Divisi Uraian Kuantitas Satuan (%) Ket.
20-26 27-3 4-10 11-17 18-24 25-31 1-7 8-14 15-21 22-28 29-5 6-12 13-19 20-26 27-2 3-9 10-16 17-23 24-30 31 -6 10-16 17-23 24-30 31 -6 10-16 17-23 24-30 31 -6
I Umum
1.2 Mobilisasi

II Drainase
2.1 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air 84.00 M3 Err:509 Err:509 Err:509 Err:509 Err:509

2.2 Pekerjaan Pasangan Batu Dengan Mortar 25.00 M3 Err:509 Err:509 Err:509 Err:509 Err:509

2.3(3) Gorong - gorong Pipa Beton Bertulang diameter dalam - M' Err:509 Err:509 Err:509 Err:509 Err:509
70 cm sampai
100 cm

III Pekerjaan Tanah


3.1(1) Galian Biasa - M3 Err:509 Err:509 Err:509 Err:509 Err:509

3.2(1) Timbunan Biasa Dari Selain Galian Sumber Bahan 5,010.00 M3 Err:509 Err:509 Err:509 Err:509 Err:509

IV Pelebaran Perkerasan dan Bahu Jalan


4.2(2) Lapis Pondasi Agregat kelas B 101.00 M3 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

V Perkerasan Berbutir
5.1(1) Lapis Pondasi Agregat kelas A - M3 Err:509 Err:509 Err:509

5.1(2) Lapis Pondasi Agregat kelas B - M3 Err:509 Err:509 Err:509


5.6(1) Lapis Pondasi Agregat Dengan Cement Treated Base (CTB) 754.00 M3 Err:509 Err:509 Err:509

VI Perkerasan Aspal
6.1(1) Lapis Resap Pengikat 2,138.00 Ltr Err:509 Err:509 Err:509 Err:509 Err:509
6.1(2) Lapis Perekat 851.00 Ltr Err:509 Err:509 Err:509

6.3(5a) Laston - Lapis Aus (AC-WC) 3,113.00 M2 Err:509 Err:509 Err:509

6.3(6c) Laston - Lapis Antara (AC-BC) Levelling - Ton Err:509 Err:509 Err:509

6.3(7c) Laston - Lapis Pondasi (AC-Base) Leveling - M3 Err:509 Err:509 Err:509

VII Struktur
7.1(5) Beton K.250 125.00 M3 Err:509 Err:509 Err:509

7.2(1) Unit Pracetak Gelagar Tipe I Bentang 16 Meter - M3 Err:509 Err:509 Err:509

7.15(6) Pembongkaran Balok Baja (Steel Stringers) - M3 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 M3 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 M3 Err:509 Err:509 Err:509 Err:509 Err:509

VIII Pengembalian Kondisi dan Pekerjaan Minor


8.1(1) Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor - M3 Err:509 Err:509 Err:509 Err:509
8.1 (3) Agregat untuk Perkerasan Tanpa Penutup Aspal untuk - M3 Err:509 Err:509 Err:509 Err:509
8.1(5) Campuran Aspal Panas untuk Pekerjaan Minor - M2 Err:509 Err:509

Jumlah Nilai Pekerjaan Err:509


Kemajuan Pekerjaan Mingguan (%) - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Kemajuan Pekerjaan Kumulatif (%) - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
27.61 Err:509 Err:509 27.61 Err:509 Err:509 27.61 Err:509 Err:509

Mengetahui/Menyetujui Konsultan Supervisi Penyedia Jasa, Penyedia Jasa, Penyedia Jasa,


Pejabat Pembuat Komitment (PPK) PT. PORTAL ENGINEERING PERKASA PT. PRIMA MUKTI USAHA PT. PRIMA MUKTI USAHA PT. PRIMA MUKTI USAHA

YONGGA BHAKTI, ST. MT. Ir. YUSUF SODIKIN NUR MUHAMAD DJUNAEDI NUR MUHAMAD DJUNAEDI NUR MUHAMAD DJUNAED
NIP. 196106141986031008 Site Engineer Direktur Utama Direktur Utama Direktur Utama
PEMERINTAH PROVINSI JAWA BARAT
DINAS BINA MARGA
BALAI PENGELOLAAN JALAN WILAYAH PELAYANAN I

HARGA PERKIRAAN SENDIRI


( HPS )

PEKERJAAN
PEMBANGUNAN JEMBATAN PAKET ( 40,00 m ) DAN
CIJAMBE
JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR
CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2
LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949
- Km Bdg.100+894

SUMBER DANA APBD PROVINSI JAWA BARAT


TAHUN ANGGARAN 2015

PANITIA PENGADAAN PENYEDIA JASA KONSTRUKSI


KEGIATAN PENINGKATAN JALAN DAN JEMBATAN PROVINSI
DI BALAI PENGELOLAAN JALAN WILAYAH PELAYANAN I
Jalan Raya Ciranjang Km. 52.000 (Bdg) Telp. (0263) 322126 Cianjur 43282
REKAPITULASI
DAFTAR KUANTITAS DAN H

No. Paket Kontrak


Nama Paket : P PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG
Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+8
Prov / Kab / Kota : JAWA BARAT / KOTA SUKABUMI
Nama Penawar :

No. DIVISI U r a i a n

1 UMUM

2 DRAINASE

3 PEKERJAAN TANAH

4 PELEBARAN PERKERASAN DAN BAHU JALAN

5 PERKERASAN BERBUTIR

6 PERKERASAN ASPAL

7 STRUKTUR

8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

9 PEKERJAAN HARIAN

10 PEKERJAAN PEMELIHARAAN RUTIN

(A) Jumlah Harga Pekerjaan (termasuk Biaya Umum dan Keuntungan)

(B) Pajak Pertambahan Nilai (PPn) = 10% x (A)

(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)

Terbilang : EMPAT MILYAR ENAM RATUS DUA PULUH JUTA DELAPAN RATU
RUPIAH 61/100
DAFTAR KUANTITAS DAN H

No. Paket Kontrak 0


Nama Paket PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40
Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+894
Prov / Kab / Kota JAWA BARAT / KOTA SUKABUMI
Nama Penawar :
No. Mata
U r a i a n Satuan
Pembayaran

DIVISI 1 - UMUM

1.2 Mobilisasi Ls

Jumlah Harga Pekerjaan Divisi 1 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 2 - D R A I N A S E

2.1 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air M3


2.2 Pekerjaan Pasangan Batu Dengan Mortar M3
2.3(2) Gorong - gorong Pipa Beton Bertulang diameter dalam M'
50 cm sampai 70 cm

Jumlah Harga Pekerjaan Divisi 2 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 3 - PEKERJAAN TANAH

3.1(1) Galian Biasa M3


3.2(1) Timbunan Biasa Dari Selain Galian Sumber Bahan M3

Jumlah Harga Pekerjaan Divisi 3 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 4 - PELEBARAN PERKERASAN DAN


BAHU JALAN

4.2(2) Lapis Pondasi Agregat kelas B M3

Jumlah Harga Pekerjaan Divisi 4 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 5 - PERKERASAN BERBUTIR

5.1(2) Lapis Pondasi Agregat kelas B M3

Jumlah Harga Pekerjaan Divisi 5 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 6 - PERKERASAN ASPAL

6.1(1) Lapis Resap Pengikat Ltr


6.1(2) Lapis Perekat Ltr
6.3(5a) Laston - Lapis Aus (AC-WC) M2
6.3(6a) Laston - Lapis Antara (AC-BC) M3
6.3(6c) Laston - Lapis Antara (AC-BC) Leveling Ton

Jumlah Harga Pekerjaan Divisi 6 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
DIVISI 7 - STRUKTUR

7.1(5) Beton K.250 M3


7.1(8) Beton K.125 M3
7.9 Pasangan Batu M3

Jumlah Harga Pekerjaan Divisi 7 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 8 - PENGEMBALIAN KONDISI DAN


PEKERJAAN MINOR

8.1(1) Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor M3


8.1(5) Campuran Aspal Panas untuk Pekerjaan Minor M3
8.4(1) Marka Jalan Thermoplastic M2

Jumlah Harga Pekerjaan Divisi 8 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
EKAPITULASI
ANTITAS DAN HARGA

0 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEG
m Bdg. 100+949 - Km Bdg.100+894

Jumlah Harga
r a i a n Pekerjaan
(Rp)
-

9,376,090.23

60,137,814.57

9,846,624.01

176,895,997.92

2,613,843,380.04

771,774,251.28

96,811,850.40

3,738,686,008.45

373,868,600.84

4,112,554,609.29

ULUH JUTA DELAPAN RATUS SEMBILAN BELAS RIBU DUA RATUS EMPAT

4,200,758,181.82
5,126,386,000.00 462,072,173.37
4,112,554,609.29 3,738,686,008.45
1,013,831,390.71 4,620,834,000.00

CIANJUR, JANUARI 2011

KEPALA BALAI PENGELOLAAN JALAN


WILAYAH PELAYANAN I

YONGGA BHAKTI, ST. MT.


NIP. 19610614 198603 1 008
ANTITAS DAN HARGA

) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN
dg. 100+949 - Km Bdg.100+894

Perkiraan Harga Satuan Jumlah Harga-Harga


Satuan
Kuantitas (Rp) (Rp)

- - -

ulasi Perkiraan Harga Pekerjaan) -

11.02 - -
5.51 585,859.79 3,228,087.45
5.00 1,229,600.56 6,148,002.78

ulasi Perkiraan Harga Pekerjaan) 9,376,090.23

1,075.50 55,101.65 59,261,825.28


7.50 116,798.57 875,989.29

ulasi Perkiraan Harga Pekerjaan) 60,137,814.57


30.00 328,220.80 9,846,624.01

ulasi Perkiraan Harga Pekerjaan) 9,846,624.01

537.75 328,955.83 176,895,997.92

ulasi Perkiraan Harga Pekerjaan) 176,895,997.92

2,688.75 13,932.91 37,462,123.07


4,693.38 13,437.53 63,067,456.64
11,000.00 99,988.00 1,099,867,970.15
134.44 2,533,603.61 340,617,669.33
Ton 955.79 1,122,451.75 1,072,828,160.84

ulasi Perkiraan Harga Pekerjaan) 2,613,843,380.04


673.39 996,136.87 670,788,606.89
134.44 737,801.15 99,189,986.61
3.00 598,552.60 1,795,657.79

ulasi Perkiraan Harga Pekerjaan) 771,774,251.28

62.33 371,623.29 23,163,279.64


24.92 2,547,468.49 63,482,914.69
90.00 112,951.73 10,165,656.07

ulasi Perkiraan Harga Pekerjaan) 96,811,850.40


DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
(Rp)
SBB 2015
1 Pasir Pasang M3 124,295.22 226,514.00
2 Pasir Beton M3 146,812.47 238,436.00
3 Batu Kali / Batu Belah M3 126,096.60 177,635.00
4 Agregat Kasar M3 166,627.65 215,000.00
5 Agregat Halus M3 175,634.55 235,000.00
6 Agregat Pengisi (Filler) Kg 1,260.97 1,400.00
7 Batu Pecah 7 : 10 M3 146,812.47 208,632.00
8 Batu Pecah 5 : 7 M3 146,812.47 247,199.00
9 Batu Pecah 3 : 5 M3 146,812.47 184,788.00
10 Batu Pecah 2 : 3 M3 146,812.47 250,358.00
11 Batu Pecah 1 : 2 M3 155,819.37 220,553.00
12 Abu Batu M3 155,819.37 202,671.00
13 Batu Belah M3 126,096.60 177,635.00
14 Gravel M1 34,316.29 42,000.00
15 Material Timbunan Biasa M3 58,544.85 71,531.00
16 Material Timbunan Pilihan M3 87,366.93 119,636.00
17 Asphalt Cement (Curah) Kg 10,357.94 11,500.00
18 Asphalt Cement (Drum) Kg 11,438.76 13,977.42
19 Minyak Tanah Ltr 12,609.66 15,500.00
20 Semen Kg 1,260.97 1,621.36
21 Baja Tulangan U.24 Polos Kg 8,556.56 11,000.00
22 Baja Tulangan U.32 Ulir Kg 9,817.52 12,000.00
23 Kawat Beton Kg 28,641.94 35,000.00
24 Kawat Bronjong 4 MM Kg 29,272.43 35,765.00
25 Sirtu M3 108,983.49 141,869.00
26 Cat Marka Jalan Kg 48,727.33 59,609.00
27 Paku Kg 16,302.49 20,000.00
28 Kayu Perancah M3 1,418,586.75 1,732,500.00
29 Bensin Ltr 6,845.24 7,550.00
30 Solar Ltr 8,196.28 9,100.00
31 Minyak Pelumas (Olie) Ltr 26,029.94 31,800.00
32 Kerosine Ltr 12,609.66 15,500.00
33 Plastik Filter kg 40,891.33 50,000.00
34 Pipa Galvanize 3" Btg 550,231.52 672,000.00
35 Pipa Porous M' 106,371.49 130,000.00
36 Agregat Base Kls A M3 259,578.86 317,120.00
37 Agregat Base Kls B M3 248,860.65 304,006.00
38 Asphalt Emulsi ltr 9,006.90 12,000.00
39 Gebalan Rumput M2 4,953.80 7,500.00
40 Thinner A Ltr 21,346.35 26,168.00
41 Cat Marka Jalan Kg 48,727.33 59,609.00
42 Glass Bead Kg 37,648.84 0.00
43 Pelat Rambu Bh 842,145.15 540,000.00
44 Beton Kelas K-350 M3 740,367.18 1,254,769.00
45 Beton Kelas K-125 M3 621,476.10 900,000.00
46 Beton Kelas K-250 M3 680,921.64 1,157,011.00
47 Beton Kelas K-175 M3 653,000.25 1,043,158.00
48 Cat Besi Kg 37,648.84 46,000.00
49 Pemantul Cahaya (reflector) Bh 122,764.05 150,000.00
50 Pasir Urug M3 107,362.25 131,140.00
51 Baja Struktur Kg 24,570.00 33,000.00
52 Kawat Las Kg 36,855.00 49,500.00
53 Pipa Baja (Tiang Pancang) Kg 4,323.31 5,364.81
54 Plat Baja Kg 19,184.70 23,500.00
55 Multiplek M3 3,739,845.02 4,567,500.00
56 Joint Sealant Kg 32,695.05 40,000.00
57 Kerb Pracetak Bh 49,087.61 60,000.00
58 Gorong-Gorong Beton M 763,064.57 596,090.00
Bertulang Dia. 50-70 Cm -
59 Gorong-Gorong Beton M 1,139,192.71 834,526.00
Bertulang Dia. 70-100 Cm -
60 Gorong-Gorong Beton M 2,453,479.56 1,311,398.00
Bertulang Dia. 100-130 Cm -
61 Gorong-Gorong Beton M - 596,090.00
Bertulang Dia. 140-150 Cm -
62 POHON - 25,000.00
63 Pipa Galvanize 1.5" BTG - 329,500.00
64 Plat Besi Tipis 2 mm s/d 5 mm KG 13,060.01 16,000
65 BESI SIKU 30.30.3 9,006.90 11,000
Gorong-Gorong Beton M 552,303.11
Bertulang Dia. 50 Cm -
DAFTAR
HARGA DASAR SATUAN UPAH
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
(Rp)

1 Pekerja Jam 9,342.11


2 Tukang Jam 11,677.80
3 Mandor Jam 16,348.88
4 Operator Jam 16,348.88
5 Pembantu Operator Jam 9,342.15
6 Sopir / Driver Jam 14,013.22
7 Pembantu Sopir / Driver Jam 9,342.15
8 Mekanik Jam 16,348.88
9 Pembantu Mekanik Jam 9,342.15
HARGA & JARAK RATA-RATA
DARI SUMBER BAHAN (QUARRY)

HARGA JARAK
No. URAIAN SATUAN ROYALTY QUARRY
(Rp) ( Km )

1. M01 - P a s i r M3 19,100.00 13.89

2. M02 - Batu Kali M3 10,000.00 5.00

3. M06 - Batu Belah M3 11,000.00 5.00

4. M07 - G r a v e l M3 12,500.00 13.89

5. M10 - Aspal Cement (Pelabuhan) KG 4,000.00 800.00

6. M16 - S i r t u M3 48,000.00 5.00

7. M44 - Pasir Urug M3 9,000.00 5.00


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M01 - Pasir


Lokasi : Quarry
Tujuan: Base Camp

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 13.89 Km
4 Harga satuan pasir di Quarry RpM01 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam

II. URUTAN KERJA


1 Pasir digali dengan Excavator
2 Excavator sekaligus memuat pasir hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir ke lokasi
Base Camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 36.45 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 4,931.68 Rupiah

DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 20.84 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 16.67 menit
- Muat = (V/Q1) x 60 T3 6.58 menit
- Lain-lain T4 1.00 menit
Ts2 45.10 menit

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M01 - Pasir


Lokasi : Quarry
Tujuan: Base Camp

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 3.99 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 49,577.69 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI BASE CAMP

Harga Satuan Dasar Pasir =

( RpM01 + Rp1 + Rp2 ) M01 73,609.38 Rupiah

Dibulatkan : M01 73,600.00 Rupiah


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M02 - Batu Kali


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke Lokasi Pekerjaan L 5.00 Km
4 Harga satuan batu kali di Quarry RpM02 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam

II. URUTAN KERJA


1 Batu kali digali dengan Excavator
2 Excavator sekaligus memuat batu kali
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut batu kali ke
lokasi pekerjaan

III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 24.3 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 7,397.53 Rupiah

DUMP TRUCK (E08)


Kapasitas bak V 3.33 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 6.00 menit
- Muat = (V/Q1) x 60 T3 8.23 menit
- Lain-lain T4 1.00 menit
Ts2 22.73 menit

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M02 - Batu Kali


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 6.60 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 29,985.88 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN
Harga Satuan Dasar Batu kali =

( RpM02 + Rp1 + Rp2 ) M02 47,383.41 Rupiah

Dibulatkan : M02 47,400.00 Rupiah

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M06 - Batu Belah


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke Lokasi Pekerjaan L 5.00 Km
4 Harga satuan batu kali di Quarry RpM06 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam
7 Harga Satuan Dasar Wheel Loader RpE15 1.00 Jam
8 Harga Satuan Upah Pekerja RpL01 1.00 Jam
II. URUTAN KERJA
1 Batu kali digali dengan Excavator
2 Batu kali dibelah oleh Pekerja
3 Dengan Wheel Loader batu belah dimuat
ke Dump Truck yang mengangkut batu
belah ke lokasi pekerjaan
III. PERHITUNGAN

3.a EXCAVATOR (E10)


Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 24.3 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 7,397.53 Rupiah

3.b WHEEL LOADER (E15)


Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi Alat Fa 0.75 -
Waktu sklus Ts1
- Muat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kapasitas Produksi / Jam =
V x Fb x Fa x 60 Q2 40.5 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q2) x RpE15 Rp2 5,609.69 Rupiah

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M06 - Batu Belah


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

3.c DUMP TRUCK (E08)


Kapasitas bak V 3.33 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 6.00 menit
- Muat = (V/Q2) x 60 T3 4.94 menit
- Lain-lain T4 1.00 menit
Ts2 19.44 menit

Kapasitas Produksi / Jam =


V x Fa x 60 Q3 7.72 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q3) x RpE08 Rp3 25,642.85 Rupiah

3.d PEKERJA

Produksi menentukan : Excavator Q1 24.3 M3 / Jam


Hasil galian batu / hari = Q1 x 7 Jam Qt 170.1 M3 / 7 jam
Kebutuhan Pekerja P 15.00 Orang

Biaya Pekerja / M3 =
{ (7 Jam x P) : Qt } x RpL01 Rp4 5,766.74 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar Batu belah =

( RpM06 + Rp1 + Rp2 + Rp3 + Rp4 ) M06 55,416.81 Rupiah

Dibulatkan : M06 55,400.00 Rupiah


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M07 - Gravel


Lokasi : Quarry
Tujuan: Base Camp

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke Lokasi Pekerjaan L 13.89 Km
4 Harga satuan Gravel di Quarry RpM07 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam

II. URUTAN KERJA


1 Gravel digali dengan Excavator
2 Excavator sekaligus memuat gravel
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut gravel ke
lokasi pekerjaan

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 24.3 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 7,397.53 Rupiah

DUMP TRUCK (E08)


Kapasitas bak V 3.33 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 20.84 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 16.67 menit
- Muat = (V/Q1) x 60 T3 8.23 menit
- Lain-lain T4 1.00 menit
Ts2 46.74 menit

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M07 - Gravel


Lokasi : Quarry
Tujuan: Base Camp

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 3.21 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 61,664.74 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI BASE CAMP

Harga Satuan Dasar Gravel =

( RpM07 + Rp1 + Rp2 ) M07 81,562.27 Rupiah

Dibulatkan : M07 81,600.00 Rupiah


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M16 - Sirtu


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 5.00 Km
4 Harga satuan Sirtu di Quarry RpM16 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam

II. URUTAN KERJA


1 Sirtu digali dengan Excavator
2 Excavator sekaligus memuat sirtu hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut sirtu ke lokasi
Base Camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 36.45 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 4,931.68 Rupiah

DUMP TRUCK (E08)


Kapasitas bak V 3.75 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 6.00 menit
- Muat = (V/Q1) x 60 T3 6.17 menit
- Lain-lain T4 1.00 menit
Ts2 20.67 menit

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M16 - Sirtu


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 8.16 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 24,241.32 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar Sirtu =

( RpM16 + Rp1 + Rp2 ) M16 77,173.01 Rupiah


Dibulatkan : M16 77,200.00 Rupiah

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M44 - Pasir Urug


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam
6 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam

II. URUTAN KERJA


1 pasir urug digali dengan Excavator
2 Excavator sekaligus memuat pasir urug
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir urug
ke lokasi pekerjaan

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 36.45 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 4,931.68 Rupiah

DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 50.00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 6.00 menit
- Muat = (V/Q1) x 60 T3 6.58 menit
- Lain-lain T4 1.00 menit
Ts2 21.08 menit

ANALISA HARGA DASAR SATUAN BAHAN

Jenis : M44 - Pasir Urug


Lokasi : Quarry
Tujuan: Lokasi Pekerjaan
No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 8.54 M3 / Jam
Ts2

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 23,178.64 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar pasir urug =

( RpM44 + Rp1 + Rp2 ) M44 37,110.32 Rupiah

Dibulatkan : M44 37,100.00 Rupiah


KET.

Ke Base Camp

Ke Lokasi Pek.

Ke Lokasi Pek.

Ke Base Camp

Ke Base Camp

Ke Lokasi Pek.

Ke Lokasi Pek.
N

HARGA
SATUAN
(Rp.)

19,100.00
179,759.91
197,879.12
Bersambung

Lanjutan
HARGA
SATUAN
(Rp.)
N

HARGA
SATUAN
(Rp.)

10,000.00
179,759.91
197,879.12
Bersambung

Lanjutan
HARGA
SATUAN
(Rp.)
N

HARGA
SATUAN
(Rp.)
11,000.00
179,759.91
197,879.12
227,192.50
9,342.11

Bersambung

N
Lanjutan
HARGA
SATUAN
(Rp.)
N

HARGA
SATUAN
(Rp.)

12,500.00
179,759.91
197,879.12
Bersambung

Lanjutan
HARGA
SATUAN
(Rp.)
N

HARGA
SATUAN
(Rp.)

48,000.00
179,759.91
197,879.12
Bersambung

Lanjutan
HARGA
SATUAN
(Rp.)
N

HARGA
SATUAN
(Rp.)

9,000.00
179,759.91
197,879.12

Bersambung

Lanjutan
HARGA
SATUAN
(Rp.)
PEMERINTAH PROVINSI JAWA BARAT
DINAS BINA MARGA
BALAI PENGELOLAAN JALAN
WILAYAH PELAYANAN II

HARGA PERKIRAAN SENDIRI ( HPS )


PAKET :

PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m)


RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2
LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )

TAHUN ANGGARAN 2016

KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN PROVINSI


DI BALAI PENGELOLAAN JALAN WILAYAH PELAYANAN II
Jalan Bhayangkara No.209 Tlp (0266) 239928-6323591 Sukabumi 43114.
ITEM PEMBAYARAN : ASPAL
JENIS PEKERJAAN : PENGADAAN ASPAL
SATUAN PEMBAYARAN : KG URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN

I ASUMSI
1 Bahan dasar diambil dari terminal (Cilacap)
2 Jarak rata-rata Terminal (Pelabuhan) ke Base Camp L 800.00 Km
3 Jam kerja efektif per-hari Tk 8.00 jam

II METHODE PELAKSANAAN

1 Truck tangki mengangkut aspal dari terminal (pelabuhan)


2 Setelah sampai Base Camp aspal dimasukan kedalam
tangki aspal di AMP

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Aspal 1.00 Kg

2. ALAT
2.a. TRUK TANGKI (E09)
Kapasitas bak V 8,000.0 Kg
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 Km / Jam
Kecepatan rata-rata kosong v2 40.00 Km / Jam
Waktu Siklus Ts2
- Mengisi Bak T1 300.00 menit
- Angkut = (L : v1) x 60 menit T2 1,600.00 menit
- Tunggu, tuang, dll T3 360.00 menit
- Kembali = (L : v2) x 60 menit T4 1,200.00 menit
Ts1 3,460.00 menit

Kap.Prod. / jam = V x Fa x 60 Q1 115.14 Kg


Ts1

Koefisien Alat / M3 = 1 : Q1 (E09) 0.0087 Jam

2.b. ALAT BANTU 1.00 Ls

3. TENAGA
Produksi Aspal = Tk x Q1 Qt 921.16 Kg

Kebutuhan tenaga : - Mandor M 1.00 orang


- Pekerja P 2.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.0087 jam
- Pekerja = (Tk x P) : Qt (L01) 0.0174 jam
ITEM PEMBAYARAN : AGREGAT KASAR & HALUS
JENIS PEKERJAAN : PENGADAAN AGREGAT KASAR & HALUS
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN

I ASUMSI
1 Bahan dasar (Batu dan Pasir) diterima di lokasi Alat
Pemecah Batu (di Base Camp)
2 Kegiatan dilakukan di dalam lokasi Base Camp
3 Hasil produksi Alat Pemecah Batu : - Agregat Halus H 30.00 %
- Agregat Kasar K 70.00 %
4 Berat Isi Bahan : - Batu / Gravel D1 1.20 Ton/M3
- Pasir D2 1.40 Ton/M3
- Batu Pecah D3 1.35 Ton/M3
5 Harga Satuan Bahan Dasar : - Batu Kali Rp1 10,000.00 Rp./M3
- Pasir Rp2 19,100.00 Rp./M3
6 Biaya Operasi Alat : - Pemecah Batu (Stone Crusher) Rp3 491,665.38 Rp./Jam
- Wheel Loader Rp4 227,192.50 Rp./Jam
7 Kapasitas Alat : - Pemecah Batu (Stone Crusher) Cp1 50.00 Ton/Jam
- Wheel Loader Cp2 1.50 M3
8 Faktor Efisiensi Alat : - Pemecah Batu (Stone Crusher) Fa1 0.70 -
- Wheel Loader Fa2 0.83 -
9 Faktor Kehilangan Material Fh 1.10 -
10 Agregat Halus masih perlu dicampur dengan pasir

II METHODE PELAKSANAAN

1 Wheel Loader mengangkut batu/gravel dari tumpukan


dan menuangkannya ke Alat Pemecah Batu.

2 Batu/gravel dipecah dengan Alat Pemecah Batu


(Stone Crusher) sehingga menghasilkan Agregat Batu
Pecah Kasar dan Halus.

3 Agregat Halus dicampur dengan pasir menggunakan Loader

III PERHITUNGAN
III.1. HARGA SATUAN AGREGAT PRODUKSI ST. CRUSHER

1.a. Kerja Stone Crusher memecah gravel :


- Waktu kerja Stone Crusher Tst 1.00 Jam
- Produksi Stone Crusher 1 jam = (Fa1 x Cp1) : D3 Qb 25.93 M3/Jam
- Kebutuhan batu/gravel 1 jam = (Fa1 x Cp1) : D1 Qg 29.17 M3/Jam

1.b. Kerja Wheel Loader melayani Stone Crusher :


- Kap. Angkut / rit = (Fa2 x Cp2) Ka 1.25 M3
- Waktu Siklus (Muat, Tuang, Tunggu, dll) Ts 5.00 menit
- Waktu kerja W.Loader memasok gravel
= {(Qg : Ka) x Ts} : 60 menit Tw 1.95 Jam

1.c. Biaya Produksi Batu Pecah / M3


= {(Tst x Rp3) + (Tw x Rp4)} : Qb Bp 36,072.11 Rp./M3

1.d. Harga Satuan Batu Pecah Produksi St.Crusher / M3


= {(Qg : Qb) x Fh x Rp1} + Bp HSb 48,447.11 Rp./M3

ITEM PEMBAYARAN : AGREGAT KASAR & HALUS


JENIS PEKERJAAN : PENGADAAN AGREGAT KASAR & HALUS
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN

III.2. HARGA SATUAN AGREGAT KASAR

Agregat Kasar Produksi Stone Crusher = 70% K 70.00 %


(Tertahan saringan # 4 = 4,75mm)
Harga Satuan Agregat Kasar / M3 = (K x HSb) / K HSAk 48,447.11 Rupiah

III.3. HARGA SATUAN AGREGAT HALUS

Dianggap Agregat produksi Stone Crusher yang lolos


saringan # 4 (4,75 mm) belum memenuhi Spesifikasi
sehingga perlu dicampur lagi dengan pasir sebanyak = Pst 10.00 %

3.a. Agregat Halus Produksi Stone Crusher = 30% H 30.00 %


Harga Agregat Halus Prod. Stone Crsh.= (H x HSb) / H Hs1 48,447.11 Rupiah
3.b. Pasir tambahan = Pst x Rp2 Hs2 1,910.00 Rupiah
3.c. Waktu pencampuran (blending) dengan Wheel Loader Tc 0.033 Jam/M3
3.d. Biaya Pencampuran = ( 1 + Pst) M3 x Tc x Rp4 Hs3 8,330.39 Rupiah

Harga Satuan Agregat Halus / M3


= Hs1 + Hs2 + Hs3 HSAh 58,687.50 Rupiah
ITEM PEMBAYARAN : AGREGAT KELAS A
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN

I ASUMSI
1 Bahan Agregat Halus & Kasar diterima di lokasi
Base Camp
2 Kegiatan dilakukan di dalam lokasi Base Camp
3 Proporsi campuran : - Agregat Kasar Ak 60.00 %
- Sirtu Srt 40.00 %
- Tanah Tn 5.00 %
4 Harga Satuan : - Agregat Kasar HSAk 166,627.65 Rp./M3
- Sirtu HSSrt 108,983.49 Rp./M3
- Tanah HSTn 58,544.85 Rp./M3
5 Biaya Operasi Alat : - Wheel Loader Rp1 227,192.50 Rp./Jam
6 Faktor Efisiensi Alat : - Wheel Loader Fa1 0.83 -
7 Kapasitas Alat : - Wheel Loader Cp2 1.50 M3

II METHODE PELAKSANAAN
1 Wheel Loader melakukan pencampuran (blending)
Agregat Kasar, Sirtu dan tanah
menjadi Agregat Kelas A.

III.1 PROSES PENCAMPURAN AGREGAT KELAS A

Untuk setiap 1 M3 Agregat Kelas A, diperlukan :

- Agregat Kasar = Ak x 1 M3 Vk 0.600 M3


1.a. - Sirtu = Srt x 1 M3 Vs 0.400 M3
- Tanah = Tn x 1 M3 Vt 0.050 M3
- Total volume agregat = Vk + Vh Va 1.050 M3

1.b. Waktu pencampuran (blending) oleh Wheel Loader Tc 0.025 Jam/M3

III.2 HARGA SATUAN BAHAN AGREGAT KELAS A

Agregat Kasar = Vk x HSAk Hs1 99,976.59 Rupiah

2.a. Sirtu = Vs x HSSt Hs2 43,593.40 Rupiah

2.b. Tanah = Vs x HSTn Hs3 23,417.94 Rupiah

2.c. Biaya Pencampuran = Tc x Rp1 Hs4 5,679.81 Rupiah

2.d. Harga Satuan Agregat Kelas A / M3


= Hs1 + Hs2 + Hs3 + Hs4 HSAA 172,667.74 Rupiah

ITEM PEMBAYARAN : AGREGAT KELAS B


JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS B
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN

I ASUMSI
1 Bahan Agregat Halus & Kasar diterima di lokasi
Base Camp
2 Kegiatan dilakukan di dalam lokasi Base Camp
3 Proporsi campuran : - Agregat Kasar Ak 59.00 %
- Sirtu Srt 15.00 %
- Tanah Tn 26.00 %
4 Harga Satuan : - Agregat Kasar HSAk 166,627.65 Rp./M3
- Sirtu HSSrt 108,983.49 Rp./M3
- Tanah HSTn 58,544.85 Rp./M3
5 Biaya Operasi Alat : - Wheel Loader Rp1 227,192.50 Rp./Jam
6 Faktor Efisiensi Alat : - Wheel Loader Fa1 0.83 -
7 Kapasitas Alat : - Wheel Loader Cp2 1.50 M3

II METHODE PELAKSANAAN

1 Wheel Loader melakukan pencampuran (blending)


Agregat Kasar, Sirtu dan tanah
menjadi Agregat Kelas B.

III.1 PROSES PENCAMPURAN AGREGAT KELAS B

Untuk setiap 1 M3 Agregat Kelas B, diperlukan :

1.a. - Agregat Kasar = Ak x 1 M3 Vk 0.590 M3


- Sirtu = Srt x 1 M3 Vs 0.150 M3
- Tanah = Tn x 1 M3 Vt 0.260 M3
- Total volume agregat = Vk + Vh + Vs Va 1.000 M3

1.b. Waktu pencampuran (blending) oleh Wheel Loader Tc 0.025 Jam/M3

III.2 HARGA SATUAN BAHAN AGREGAT KELAS B

2.a. Agregat Kasar = Vk x HSAk Hs1 98,310.31 Rupiah

2.b. Sirtu = Vs x HSSt Hs2 16,347.52 Rupiah

2.c. Tanah = Vs x HSTn Hs3 15,221.66 Rupiah

2.d. Biaya Pencampuran = Tc x Rp1 Hs4 5,679.81 Rupiah

2.e. Harga Satuan Agregat Kelas B / M3


= Hs1 + Hs2 + Hs3 + Hs4 HSAB 120,337.65 Rupiah

ITEM PEMBAYARAN : AGREGAT KELAS C


JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEFISIEN SATUAN


I ASUMSI
1 Bahan Agregat Kasar, Pasir dan Tanah diterima di lokasi
Base Camp
2 Kegiatan dilakukan di dalam lokasi Base Camp
3 Proporsi campuran : - Agregat Kasar Ak 38.00 %
- Sirtu Srt 47.00 %
- Tanah Tn 15.00 %
4 Harga Satuan : - Agregat Kasar HSAk 166,627.65 Rp./M3
- Sirtu HSSrt 108,983.49 Rp./M3
- Tanah HSTn 58,544.85 Rp./M3
5 Biaya Operasi Alat : - Wheel Loader Rp1 227,192.50 Rp./Jam
6 Faktor Efisiensi Alat : - Wheel Loader Fa1 0.83 -
7 Kapasitas Alat : - Wheel Loader Cp2 1.50 M3

II METHODE PELAKSANAAN

1 Wheel Loader melakukan pencampuran (blending)


Agregat Kasar, Sirtu & Tanah menjadi Agregat Kelas C.

III.1 PROSES PENCAMPURAN AGREGAT KELAS C

Untuk setiap 1 M3 Agregat Kelas C, diperlukan :

1.a. - Agregat Kasar = Ak x 1 M3 Vk 0.380 M3


- Sirtu = Srt x 1 M3 Vs 0.470 M3
- Tanah = Tn x 1 M3 Vt 0.150 M3
- Total volume agregat = Vk + Vp + Vt Va 1.000 M3

1.b. Waktu pencampuran (blending) oleh Wheel Loader Tc 0.025 Jam/M3

III.2 HARGA SATUAN BAHAN AGREGAT KELAS C

2.a. Agregat Kasar = Vk x HSAk Hs1 41,413.73 Rupiah

2.b. Sirtu = Vs x HSSt Hs2 78,315.00 Rupiah

2.c. Tanah = Vs x HSTn Hs3 8,781.73 Rupiah

2.d. Biaya Pencampuran = Tc x Rp1 Hs4 5,679.81 Rupiah

2.e. Harga Satuan Agregat Kelas C / M3


= Hs1 + Hs2 + Hs3 + Hs4 HSAB 125,408.53 Rupiah
AIAN ANALISA HARGA SATUAN

KETERANGAN
Berlanjut
AIAN ANALISA HARGA SATUAN

KETERANGAN

Berongga
Berongga
Berongga

Kap. Bucket
Batu pecah

Berlanjut

RAIAN ANALISA HARGA SATUAN


Lanjutan 1

KETERANGAN

Di Luar PPN

per 1 M3
per (Pst) M3

Di luar PPN
AIAN ANALISA HARGA SATUAN

KETERANGAN

Kap. Bucket
Di luar PPN

AIAN ANALISA HARGA SATUAN

KETERANGAN
Kap. Bucket

Di luar PPN

AIAN ANALISA HARGA SATUAN

KETERANGAN
Kap. Bucket

Di luar PPN
No. Paket :

PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40


NAMA PAKET : ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
LOKASI : Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+894
PANJANG : 1.44 Km
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
Jarak Quarry ke Lokasi : 18.89 Km
Jarak Quarry ke Base Camp : 13.89 Km
Jarak Base Camp ke Lokasi : 5.00 Km 61100
Pelabuhan (Aspal) ke Base Camp : 800.00 Km

Jam Kerja Efektif : 8.00 Jam

Kecepatan rata-rata Dump Truck


- Muatan : 30.00 Km/Jam
- Kosong : 40.00 Km/Jam

Efisiensi Alat :
- Alat Baru : 0.83
- Alat Habis Umur : 0.75

Harga Satuan Dasar Upah KOTA SUKABUMI Cianjur


Pekerja : 74,736.90 /Hari 9,342.11 /Jam 68,500.00
Tukang : 93,422.42 /Hari 11,677.80 /Jam 80,000.00
Mandor : 130,791.01 /Hari 16,348.88 /Jam 91,400.00
Operator : 130,791.01 /Hari 16,348.88 /Jam 91,400.00
Pembantu Operator : 74,737.18 /Hari 9,342.15 /Jam 68,500.00
Sopir / Driver : 112,105.78 /Hari 14,013.22 /Jam 80,000.00
Pembantu Sopir / Driver : 74,737.18 /Hari 9,342.15 /Jam 68,500.00
Mekanik : 130,791.01 /Hari 16,348.88 /Jam 91,400.00
Pembantu Mekanik : 74,737.18 /Hari 9,342.15 /Jam 68,500.00

Harga Satuan Dasar Alat


Jenis Alat Tenaga Harga Sewa Alat (Rp)
ASPHALT MIXING PLANT (AMP) : 150 HP 3,870,485.39 1
ASPHALT FINISHER : 47 HP 138,940.57 2
ASPHALT SPRAYER : 15 HP 55,496.85 3
BULLDOZER 100 - 150 HP : 140 HP 252,475.76 4
COMPRESSOR 4000 - 6500 L/M : 80 HP 163,441.50 5
CONCRETE MIXER 0.30 - 0.60 M3 : 15 HP 54,939.82 6
CRANE 10 - 15 TON : 150 HP 291,112.47 7
DUMP TRUCK 3 - 4 M3 : 100 HP 197,879.12 8
DUMP TRUCK : 125 HP 246,739.58 9
EXCAVATOR 80 - 140 HP : 80 HP 179,759.91 10
FLAT BAD TRUCK 3 - 4 M3 : 100 HP 214,809.47 11
GENERATOR SET : 175 HP 326,510.25 12
MOTOR GRADER > 100 HP : 125 HP 265,505.74 13
TRACK LOADER 75 - 100 HP : 90 HP 210,033.44 14
WHEEL LOADER 1,0 - 1,60 M3 : 105 HP 227,192.50 15
THREE WHEEL ROLLER 6 - 8 T : 55 HP 126,207.91 16
TANDEM ROLLER 6 - 8 T : 50 HP 123,819.90 17
TIRE ROLLER 8 - 10 T : 60 HP 147,815.38 18
VIBRATORY ROLLER 6 - 8 T : 75 HP 173,735.15 19
CONCRETE VIBRAETOR : 10 HP 42,925.02 20
STONE CRUSHER : 220 HP 491,665.38 21
WATER PUMP 70 - 100 mm : 6 HP 36,411.61 22
WATER TANKER 3000 - 4500 L : 100 HP 195,023.40 23
PEDESTRIAN ROLLER : 11 HP 47,672.69 24
TAMPER : 5 HP 35,140.60 25
JACK HAMMER : 3 HP 31,900.81 26
FULVI MIXER : 75 HP 156,565.93 27
PILE DRIVER (ALAT PANCANG) : 125 HP 279,172.41 28
CRANE ON TRACK : 150 HP 329,868.68 29
TRAILLER : 150 HP 309,470.68 30
GROUTING MACHINE : 10 HP 45,969.54 31
STRESSING MACHINE : 50 HP 112,804.97 32
BATCHING PLANT : 150 HP 574,644.74 33
TRUCK MIXER : 125 HP 252,308.23 34
CONCRETE PUMP : 125 HP 275,736.28 35
BAR CUTTER : - HP 25,000.00 36
WELDING SET : - HP 75,000.00 37
VIBRATORY ROLLER 4 T : - HP 100,000.00
N JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN )

+949 - Km Bdg.100+894

JAWA BARAT / SUKABUMI


quarry 82000
baseecamp 95894
lokasi 100894 112000 165070

amp 80000 112000 165070


baseecamp 95894
lokasi 100894

AMP-LOKASI 20.89

Juknis 2015
Kab Sukabumi Kab. Bogor Kota Depok Kota Sukabumi Kab. Bekasi Kota Bekasi
71,178.00 68,500.00 68,500.00 61,364.00 74,250.00 74,250.00
88,973.73 80,000.00 80,000.00 76,705.31 91,400.00 91,400.00
124,562.87 91,400.00 91,400.00 107,387.13 100,000.00 100,000.00
124,562.87 91,400.00 91,400.00 107,387.13 100,000.00 100,000.00
71,178.27 68,500.00 68,500.00 61,363.64 74,250.00 74,250.00
106,767.41 80,000.00 80,000.00 92,046.98 100,000.00 100,000.00
71,178.27 68,500.00 68,500.00 61,363.64 74,250.00 74,250.00
124,562.87 91,400.00 91,400.00 107,387.13 100,000.00 100,000.00
71,178.27 68,500.00 68,500.00 61,363.64 74,250.00 74,250.00

Harga Alat (Rp)


3,391,400.00 575,540,910.00 639,000,000.00
128,200.00 175,634,550.00 195,000,000.00
51,500.00 24,318,630.00 27,000,000.00
258,000.00 -
108,300.00 36,027,600.00 40,000,000.00
49,600.00 19,815,180.00 22,000,000.00
300,600.00 99,075,900.00 110,000,000.00
146,000.00 45,034,500.00 50,000,000.00
193,000.00 81,962,790.00 91,000,000.00
272,000.00 108,082,800.00 120,000,000.00
250,000.00 119,791,770.00 133,000,000.00
218,100.00 76,558,650.00 85,000,000.00
275,300.00 164,826,270.00 183,000,000.00
197,400.00 170,230,410.00 189,000,000.00
240,800.00 138,706,260.00 154,000,000.00
105,100.00 50,438,640.00 56,000,000.00
191,600.00 75,657,960.00 84,000,000.00
141,000.00 99,075,900.00 110,000,000.00
203,000.00 106,281,420.00 118,000,000.00
29,900.00 2,071,587.00 2,300,000.00
431,000.00 442,689,135.00 491,500,000.00
27,400.00 2,702,070.00 3,000,000.00
137,800.00 32,424,840.00 36,000,000.00
39,000.00 16,662,765.00 18,500,000.00
30,300.00 2,702,070.00 3,000,000.00
28,000.00 2,702,070.00 3,000,000.00
83,200.00 41,431,740.00 46,000,000.00
47,700.00 225,172,500.00 250,000,000.00
350,000.00 270,207,000.00 300,000,000.00
208,000.00 180,138,000.00 200,000,000.00
34,264.18 18,013,800.00 20,000,000.00
102,403.89 27,020,700.00 30,000,000.00
363,500.00 1,351,035,000.00 1,500,000,000.00
190,300.00 106,551,627.00 118,300,000.00
116,000.00 106,551,627.00 118,300,000.00
25,000.00 -
75,000.00 -
-
-
TAHAP 2 LANJUTAN )

2016
KAB Sukabumi
74,736.90
93,422.42
130,791.01
130,791.01
74,737.18
112,105.78
74,737.18
130,791.01
74,737.18

SBB 2015
6,052,859.00
168,713.00
64,435.00
378,909.00
177,322.00
62,535.00
334,244.00
232,310.00
300,817.00
340,945.00

340,945.00
365,858.00
331,285.00
152,545.00
180,023.00
192,687.00
267,662.00
38,483.00
620,689.00
32,578.00
224,110.00
48,471.00
34,566.00
29,589.00

492,881.00
298,084.00
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA SEWA
No. U R A I A N KODE HP KAPASITAS ALAT / JAM
(Rp)
1 ASPHALT MIXING PLANT (AMP) E01 150 50.00 Ton/Jam 3,870,485.39
2 ASPHALT FINISHER E02 47 40.00 Ton/Jam 138,940.57
3 ASPHALT SPRAYER E03 15 800.00 Ltr 55,496.85
4 BULLDOZER 100 - 150 HP E04 140 - - 252,475.76
5 COMPRESSOR 4000 - 6500 L/M E05 80 - - 163,441.50
6 CONCRETE MIXER 0.30 - 0.60 M3 E06 15 500.00 Ltr 54,939.82
7 CRANE 10 - 15 TON E07 150 10.00 Ton 291,112.47
8 DUMP TRUCK 3 - 4 M3 E08 100 4.00 M3 197,879.12
9 DUMP TRUCK E09 125 8.00 Ton 246,739.58
10 EXCAVATOR 80 - 140 HP E10 80 0.50 M3 179,759.91
11 FLAT BAD TRUCK 3 - 4 M3 E11 100 4.00 M3 214,809.47
12 GENERATOR SET E12 175 125.00 KVA 326,510.25
13 MOTOR GRADER > 100 HP E13 125 - - 265,505.74
14 TRACK LOADER 75 - 100 HP E14 90 1.60 M3 210,033.44
15 WHEEL LOADER 1,0 - 1,60 M3 E15 105 1.50 M3 227,192.50
16 THREE WHEEL ROLLER 6 - 8 T E16 55 8.00 Ton 126,207.91
17 TANDEM ROLLER 6 - 8 T E17 50 8.00 Ton 123,819.90
18 TIRE ROLLER 8 - 10 T E18 60 10.00 Ton 147,815.38
19 VIBRATORY ROLLER 6 - 8 T E19 75 7.00 Ton 173,735.15
20 CONCRETE VIBRAETOR E20 10 - - 42,925.02
21 STONE CRUSHER E21 220 50.00 Ton/Jam 491,665.38
22 WATER PUMP 70 - 100 mm E22 6 - - 36,411.61
23 WATER TANKER 3000 - 4500 L E23 100 4,000.00 Ltr 195,023.40
24 PEDESTRIAN ROLLER E24 11 0.98 Ton 47,672.69
25 TAMPER E25 5 0.17 Ton 35,140.60
26 JACK HAMMER E26 3 - - 31,900.81
27 FULVI MIXER E27 75 - - 156,565.93
28 PILE DRIVER (ALAT PANCANG) E28 125 2.50 Ton 279,172.41
29 CRANE ON TRACK E29 150 25.00 Ton 329,868.68
30 CRANE ON TRACK E29 150 100.00 Ton 833,333.33
31 TRAILLER E30 150 40.00 Ton 309,470.68
32 GROUTING MACHINE E31 10 - - 45,969.54
33 STRESSING MACHINE E32 50 - - 112,804.97
34 BATCHING PLANT E33 150 40.00 M3/Jam 574,644.74
35 TRUCK MIXER E34 125 6.00 M3 252,308.23
36 CONCRETE PUMP E35 125 10.00 M3 275,736.28
37 BAR CUTTER E37 75 - - 25,000.00
38 WELDING SET E37 75 50.00 Kg 75,000.00
HARGA
No. U R A I A N KODE HP KAPASITAS ALAT
(Rp)
1 ASPHALT MIXING PLANT (AMP) E01 150 50.00 Ton/Jam 575,540,910.00
2 ASPHALT FINISHER E02 47 40.00 Ton/Jam 175,634,550.00
3 ASPHALT SPRAYER E03 15 800.00 Ltr 24,318,630.00
4 BULLDOZER 100 - 150 HP E04 140 - - -
5 COMPRESSOR 4000 - 6500 L/M E05 80 - - 36,027,600.00
6 CONCRETE MIXER 0.30 - 0.60 M3 E06 15 500.00 Ltr 19,815,180.00
7 CRANE 10 - 15 TON E07 150 15.00 Ton 99,075,900.00
8 DUMP TRUCK 3 - 4 M3 E08 100 4.00 M3 45,034,500.00
9 DUMP TRUCK E09 125 8.00 Ton 81,962,790.00
10 EXCAVATOR 80 - 140 HP E10 80 0.50 M3 108,082,800.00
11 FLAT BAD TRUCK 3 - 4 M3 E11 100 4.00 M3 119,791,770.00
12 GENERATOR SET E12 175 125.00 KVA 76,558,650.00
13 MOTOR GRADER > 100 HP E13 125 - - 164,826,270.00
14 TRACK LOADER 75 - 100 HP E14 90 1.60 M3 170,230,410.00
15 WHEEL LOADER 1,0 - 1,60 M3 E15 105 1.50 M3 138,706,260.00
16 THREE WHEEL ROLLER 6 - 8 T E16 55 8.00 Ton 50,438,640.00
17 TANDEM ROLLER 6 - 8 T E17 50 8.00 Ton 75,657,960.00
18 TIRE ROLLER 8 - 10 T E18 60 10.00 Ton 99,075,900.00
19 VIBRATORY ROLLER 6 - 8 T E19 75 7.00 Ton 106,281,420.00
20 CONCRETE VIBRAETOR E20 10 - - 2,071,587.00
21 STONE CRUSHER E21 220 50.00 Ton/Jam 442,689,135.00
22 WATER PUMP 70 - 100 mm E22 6 - - 2,702,070.00
23 WATER TANKER 3000 - 4500 L E23 100 4,000.00 Ltr 32,424,840.00
24 PEDESTRIAN ROLLER E24 11 0.98 Ton 16,662,765.00
25 TAMPER E25 5 0.17 Ton 2,702,070.00
26 JACK HAMMER E26 3 - - 2,702,070.00
27 FULVI MIXER E27 75 - - 41,431,740.00
28 PILE DRIVER (ALAT PANCANG) E28 125 2.50 Ton 225,172,500.00
29 CRANE ON TRACK E29 150 25.00 Ton 270,207,000.00
30 TRAILLER E30 150 40.00 Ton 180,138,000.00
31 GROUTING MACHINE E31 10 - - 18,013,800.00
32 STRESSING MACHINE E32 50 - - 27,020,700.00
33 BATCHING PLANT E33 150 8,000 Ltr/Jam 1,351,035,000.00
34 TRUCK MIXER E34 125 6.00 M3 106,551,627.00
35 CONCRETE PUMP E35 125 10.00 M3 210,000,000.00
### E37 75 - - 46,000,000.00
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan ASPHALT MIXING PLA
2 Tenaga Pw 1
3 Kapasitas Cp 50.
4 Alat Baru : a. Umur Ekonomis A 10.
b. Jam Kerja Dalam 1 Tahun W 1,500.
c. Harga Alat B 575,540,910.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 10.
b. Jam Kerja Dalam 1 Tahun W' 1,500.
c. Harga Alat (*) B' 575,540,910.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 57,554,091.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.238


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 82,367.
W'

b. Asuransi, dll = 0.002 x B' F 767.


W'

Biaya Pasti per Jam = (E+F) G 83,135.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H1 184,416.


Bahan Bakar Pemanasan Material = 12 x 0.70 Cp x Ms H2 3,442,437.
2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 58,567.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 57,554.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 28,026.

Biaya Operasi Per Jam = (H+I+K+L+M) P 3,787,350.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 3,870,485.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan ASPHALT FINIS
2 Tenaga Pw
3 Kapasitas Cp 40.
4 Alat Baru : a. Umur Ekonomis A 6.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 175,634,550.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 6.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 175,634,550.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 17,563,455.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.300


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 23,766.
W'

b. Asuransi, dll = 0.002 x B' F 175.


W'

Biaya Pasti per Jam = (E+F) G 23,942.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 57,783.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 18,351.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 13,172.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 114,998.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 138,940.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan ASPHALT SPRA
2 Tenaga Pw
3 Kapasitas Cp 800.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 24,318,630.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 24,318,630.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 2,431,863.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 3,659.
W'

b. Asuransi, dll = 0.002 x B' F 24.


W'

Biaya Pasti per Jam = (E+F) G 3,683.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 18,441.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 5,856.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 1,823.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 51,813.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 55,496.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan BULLDOZER 100 -
2 Tenaga Pw 1
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B'

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E
W'

b. Asuransi, dll = 0.002 x B' F


W'

Biaya Pasti per Jam = (E+F) G

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 172,121.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 54,662.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 252,475.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 252,475.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan COMPRESSOR 4000 -
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 36,027,600.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 36,027,600.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 3,602,760.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 5,421.
W'

b. Asuransi, dll = 0.002 x B' F 36.


W'

Biaya Pasti per Jam = (E+F) G 5,457.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 98,355.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 31,235.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 2,702.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 157,984.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 163,441.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan CONCRETE MIXER 0.30
2 Tenaga Pw
3 Kapasitas Cp 500.
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 19,815,180.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 19,815,180.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 1,981,518.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 3,444.
W'

b. Asuransi, dll = 0.002 x B' F 19.


W'

Biaya Pasti per Jam = (E+F) G 3,464.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 18,441.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 5,856.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 1,486.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 51,475.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 54,939.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan CRANE 10 - 15 T
2 Tenaga Pw 1
3 Kapasitas Cp 15.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 99,075,900.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 99,075,900.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 9,907,590.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 14,908.
W'

b. Asuransi, dll = 0.002 x B' F 99.


W'

Biaya Pasti per Jam = (E+F) G 15,007.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 184,416.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 58,567.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 7,430.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 276,105.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 291,112.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK 3 -
2 Tenaga Pw 1
3 Kapasitas Cp 4.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 45,034,500.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 45,034,500.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 4,503,450.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 6,776.
W'

b. Asuransi, dll = 0.002 x B' F 45.


W'

Biaya Pasti per Jam = (E+F) G 6,821.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 122,944.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 39,044.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 3,377.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 191,057.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 197,879.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUC
2 Tenaga Pw 1
3 Kapasitas Cp 8.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 81,962,790.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 81,962,790.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 8,196,279.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 12,333.
W'

b. Asuransi, dll = 0.002 x B' F 81.


W'

Biaya Pasti per Jam = (E+F) G 12,414.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 153,680.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 48,806.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 6,147.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 234,324.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 246,739.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan EXCAVATOR 80 - 1
2 Tenaga Pw
3 Kapasitas Cp 0.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 108,082,800.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 108,082,800.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 10,808,280.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,263.
W'

b. Asuransi, dll = 0.002 x B' F 108.


W'

Biaya Pasti per Jam = (E+F) G 16,371.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 98,355.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 31,235.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 8,106.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 163,388.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 179,759.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan FLAT BAD TRUCK 3
2 Tenaga Pw 1
3 Kapasitas Cp 4.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 119,791,770.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 119,791,770.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 11,979,177.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 18,025.
W'

b. Asuransi, dll = 0.002 x B' F 119.


W'

Biaya Pasti per Jam = (E+F) G 18,144.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 122,944.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 39,044.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 8,984.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 196,664.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 214,809.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan GENERATOR S
2 Tenaga Pw 1
3 Kapasitas Cp 125.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 76,558,650.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 76,558,650.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 7,655,865.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 11,519.
W'

b. Asuransi, dll = 0.002 x B' F 76.


W'

Biaya Pasti per Jam = (E+F) G 11,596.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 215,152.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 68,328.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 5,741.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 314,913.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 326,510.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan MOTOR GRADER >
2 Tenaga Pw 1
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 164,826,270.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 164,826,270.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 16,482,627.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 24,801.
W'

b. Asuransi, dll = 0.002 x B' F 164.


W'

Biaya Pasti per Jam = (E+F) G 24,966.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 153,680.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 48,806.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 12,361.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 240,539.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 265,505.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TRACK LOADER 75
2 Tenaga Pw
3 Kapasitas Cp 1.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 170,230,410.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 170,230,410.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 17,023,041.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 25,614.
W'

b. Asuransi, dll = 0.002 x B' F 170.


W'

Biaya Pasti per Jam = (E+F) G 25,784.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 110,649.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 35,140.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 12,767.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 184,248.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 210,033.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan WHEEL LOADER 1,0 -
2 Tenaga Pw 1
3 Kapasitas Cp 1.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 138,706,260.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 138,706,260.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 13,870,626.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 20,871.
W'

b. Asuransi, dll = 0.002 x B' F 138.


W'

Biaya Pasti per Jam = (E+F) G 21,009.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 129,091.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 40,997.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 10,402.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 206,182.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 227,192.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan THREE WHEEL ROLLE
2 Tenaga Pw
3 Kapasitas Cp 8.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 50,438,640.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 50,438,640.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 5,043,864.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 7,589.
W'

b. Asuransi, dll = 0.002 x B' F 50.


W'

Biaya Pasti per Jam = (E+F) G 7,639.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 67,619.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 21,474.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 3,782.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 118,567.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 126,207.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TANDEM ROLLER
2 Tenaga Pw
3 Kapasitas Cp 8.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 75,657,960.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 75,657,960.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 7,565,796.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 11,384.
W'

b. Asuransi, dll = 0.002 x B' F 75.


W'

Biaya Pasti per Jam = (E+F) G 11,459.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 61,472.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 19,522.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 5,674.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 112,359.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 123,819.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TIRE ROLLER 8 -
2 Tenaga Pw
3 Kapasitas Cp 10.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 1,800.
c. Harga Alat B 99,075,900.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 1,800.
c. Harga Alat (*) B' 99,075,900.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 9,907,590.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,564.
W'

b. Asuransi, dll = 0.002 x B' F 110.


W'

Biaya Pasti per Jam = (E+F) G 16,674.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 73,766.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 23,426.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 8,256.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.


5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 131,140.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 147,815.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan VIBRATORY ROLLER
2 Tenaga Pw
3 Kapasitas Cp 7.
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 106,281,420.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 106,281,420.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 10,628,142.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 18,474.
W'

b. Asuransi, dll = 0.002 x B' F 106.


W'

Biaya Pasti per Jam = (E+F) G 18,581.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 92,208.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 29,283.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 7,971.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 155,153.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 173,735.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT


No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan CONCRETE VIBRA
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 1,000.
c. Harga Alat B 2,071,587.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 1,000.
c. Harga Alat (*) B' 2,071,587.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 207,158.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 720.
W'

b. Asuransi, dll = 0.002 x B' F 4.


W'

Biaya Pasti per Jam = (E+F) G 724.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 12,294.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 3,904.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 310.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.


Biaya Operasi Per Jam = (H+I+K+L+M) P 42,200.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 42,925.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan STONE CRUSH
2 Tenaga Pw 2
3 Kapasitas Cp 50.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 442,689,135.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 442,689,135.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 44,268,913.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 66,611.
W'

b. Asuransi, dll = 0.002 x B' F 442.


W'

Biaya Pasti per Jam = (E+F) G 67,054.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 270,477.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 85,898.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 33,201.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 2 Orang / Jam ) x U2 M 18,684.

Biaya Operasi Per Jam = (H+I+K+L+M) P 424,610.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 491,665.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.


No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan WATER PUMP 70 - 1
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 2.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 2,702,070.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 2.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 2,702,070.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 270,207.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.654


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 795.
W'

b. Asuransi, dll = 0.002 x B' F 2.


W'

Biaya Pasti per Jam = (E+F) G 798.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 7,376.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 2,342.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 202.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 35,613.


D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 36,411.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan WATER TANKER 300
2 Tenaga Pw 1
3 Kapasitas Cp 4,000.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 32,424,840.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 32,424,840.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 3,242,484.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 4,878.
W'
b. Asuransi, dll = 0.002 x B' F 32.
W'

Biaya Pasti per Jam = (E+F) G 4,911.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 122,944.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 39,044.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 2,431.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 190,111.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 195,023.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.


A URAIAN PERALATAN
1 Jenis Peralatan PEDESTRIAN RO
2 Tenaga Pw
3 Kapasitas Cp 0.
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 16,662,765.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 16,662,765.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 1,666,276.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2,896.
W'

b. Asuransi, dll = 0.002 x B' F 16.


W'

Biaya Pasti per Jam = (E+F) G 2,913.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 13,523.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 4,294.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 1,249.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 44,759.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 47,672.


E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TAMPER
2 Tenaga Pw
3 Kapasitas Cp 0.
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 1,000.
c. Harga Alat B 2,702,070.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 1,000.
c. Harga Alat (*) B' 2,702,070.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 270,207.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 939.
W'

b. Asuransi, dll = 0.002 x B' F 5.


W'
Biaya Pasti per Jam = (E+F) G 944.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 6,147.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 1,952.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 405.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 34,195.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 35,140.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan JACK HAMME
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 4.
b. Jam Kerja Dalam 1 Tahun W 1,000.
c. Harga Alat B 2,702,070.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.
b. Jam Kerja Dalam 1 Tahun W' 1,000.
c. Harga Alat (*) B' 2,702,070.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 270,207.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.386


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 939.
W'

b. Asuransi, dll = 0.002 x B' F 5.


W'

Biaya Pasti per Jam = (E+F) G 944.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 3,688.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 1,171.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 405.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 30,956.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 31,900.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan FULVI MIXER
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 41,431,740.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 41,431,740.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 4,143,174.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 6,234.
W'

b. Asuransi, dll = 0.002 x B' F 41.


W'

Biaya Pasti per Jam = (E+F) G 6,275.


C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 92,208.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 29,283.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 3,107.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 150,290.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 156,565.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan PILE DRIVER (ALAT P
2 Tenaga Pw 1
3 Kapasitas Cp 2.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 225,172,500.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 225,172,500.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 22,517,250.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 33,881.
W'

b. Asuransi, dll = 0.002 x B' F 225.


W'

Biaya Pasti per Jam = (E+F) G 34,107.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 153,680.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 48,806.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 16,887.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 245,065.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 279,172.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan CRANE ON TRA
2 Tenaga Pw 1
3 Kapasitas Cp 25.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 270,207,000.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 270,207,000.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 27,020,700.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 40,658.
W'

b. Asuransi, dll = 0.002 x B' F 270.


W'

Biaya Pasti per Jam = (E+F) G 40,928.

C BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 184,416.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 58,567.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 20,265.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 288,940.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 329,868.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TRAILLER
2 Tenaga Pw 1
3 Kapasitas Cp 40.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 180,138,000.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 180,138,000.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 18,013,800.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 27,105.
W'

b. Asuransi, dll = 0.002 x B' F 180.


W'

Biaya Pasti per Jam = (E+F) G 27,285.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 184,416.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 58,567.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 13,510.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 282,185.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 309,470.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan GROUTING MAC
2 Tenaga Pw
3 Kapasitas Cp 10.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 18,013,800.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 18,013,800.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 1,801,380.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2,710.
W'

b. Asuransi, dll = 0.002 x B' F 18.


W'

Biaya Pasti per Jam = (E+F) G 2,728.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 12,294.


2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 3,904.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 1,351.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 43,240.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 45,969.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan STRESSING MAC
2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 27,020,700.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 27,020,700.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 2,702,070.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 4,065.
W'

b. Asuransi, dll = 0.002 x B' F 27.


W'

Biaya Pasti per Jam = (E+F) G 4,092.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 61,472.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 19,522.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 2,026.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 108,712.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 112,804.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan BATCHING PLA
2 Tenaga Pw 1
3 Kapasitas Cp 8,000.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 1,351,035,000.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 1,351,035,000.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 135,103,500.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 203,291.
W'

b. Asuransi, dll = 0.002 x B' F 1,351.


W'

Biaya Pasti per Jam = (E+F) G 204,642.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 184,416.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 58,567.


3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 101,327.
W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 370,002.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 574,644.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan TRUCK MIXE
2 Tenaga Pw 1
3 Kapasitas Cp 6.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 106,551,627.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 106,551,627.
B BIAYA PASTI PER JAM KERJA
1 Nilai Sisa Alat = 10% x B C 10,655,162.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,032.
W'

b. Asuransi, dll = 0.002 x B' F 106.


W'

Biaya Pasti per Jam = (E+F) G 16,139.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 153,680.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 48,806.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 7,991.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 236,168.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 252,308.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF.

A URAIAN PERALATAN
1 Jenis Peralatan CONCRETE PU
2 Tenaga Pw 1
3 Kapasitas Cp 10.
4 Alat Baru : a. Umur Ekonomis A 5.
b. Jam Kerja Dalam 1 Tahun W 2,000.
c. Harga Alat B 210,000,000.
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.
b. Jam Kerja Dalam 1 Tahun W' 2,000.
c. Harga Alat (*) B' 210,000,000.

B BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = 10% x B C 21,000,000.

2 Faktor Angsuran Modal = i x ( 1 + i ) ^ A' D 0.334


( 1 + i )^A'-1
3 Biaya Pasti Perjam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 31,598.
W'

b. Asuransi, dll = 0.002 x B' F 210.


W'

Biaya Pasti per Jam = (E+F) G 31,808.

C BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = (0.125 - 0.175 Ltr/HP/Jam) x Pw x Ms H 153,680.

2 Pelumas = (0.010 - 0.020 Ltr/HP/Jam) x Pw x Mp I 48,806.

3 Perawatan dan Perbaikan = (12.5% - 17.5%) x B' K 15,750.


W'

4 Operator = ( 1 Orang / Jam ) x U1 L 16,348.

5 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,342.

Biaya Operasi Per Jam = (H+I+K+L+M) P 243,927.

D TOTAL BIAYA SEWA ALAT / J= ( G + P ) S 275,736.

E LAIN - LAIN
1 Tingkat Suku Bunga i 20.
2 Upah Operator / Sopir U1 16,348.
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.
4 Bahan Bakar Bensin Mb 6,845.
5 Bahan Bakar Solar Ms 8,196.
6 Minyak Pelumas Mp 26,029.
7 PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
ER JAM KERJA

KETERANGAN
HARGA BIAYA SEWA
ALAT ALAT / JAM
(Rp) (Rp)
575,540,910.00 3,870,485.39
175,634,550.00 138,940.57
24,318,630.00 55,496.85
- 252,475.76
36,027,600.00 163,441.50
19,815,180.00 54,939.82
99,075,900.00 291,112.47
45,034,500.00 197,879.12
81,962,790.00 246,739.58
108,082,800.00 179,759.91
119,791,770.00 214,809.47
76,558,650.00 326,510.25
164,826,270.00 265,505.74
170,230,410.00 210,033.44
138,706,260.00 227,192.50
50,438,640.00 126,207.91
75,657,960.00 123,819.90
99,075,900.00 147,815.38
106,281,420.00 173,735.15
2,071,587.00 42,925.02
442,689,135.00 491,665.38
2,702,070.00 36,411.61
32,424,840.00 195,023.40
16,662,765.00 47,672.69
2,702,070.00 35,140.60
2,702,070.00 31,900.81
41,431,740.00 156,565.93
225,172,500.00 279,172.41
270,207,000.00 329,868.68
180,138,000.00 309,470.68
18,013,800.00 45,969.54
27,020,700.00 112,804.97
1,351,035,000.00 574,644.74
106,551,627.00 252,308.23
210,000,000.00 275,736.28
46,000,000.00 KOEF.
T

KOEF. SATUAN KETERANGAN

PHALT MIXING PLANT (AMP) E01


150 HP
50.00 Ton/Jam
10.00 Tahun
1,500.00 Jam
575,540,910.00 Rupiah
10.00 Tahun Alat Baru
1,500.00 Jam Alat Baru
575,540,910.00 Rupiah Alat Baru

57,554,091.00 Rupiah

0.23852 - 1.2383472845
5.19

82,367.76 Rupiah

767.39 Rupiah

83,135.15 Rupiah

184,416.28 Rupiah
3,442,437.18
58,567.37 Rupiah

57,554.09 Rupiah

16,348.88 Rupiah
28,026.44 Rupiah

3,787,350.24 Rupiah

3,870,485.39 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

ASPHALT FINISHER E02


47 HP
40.00 Ton
6.00 Tahun
2,000.00 Jam
175,634,550.00 Rupiah
6.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
175,634,550.00 Rupiah Alat Baru

17,563,455.00 Rupiah

0.30071 - 0.5971968
1.99

23,766.44 Rupiah

175.63 Rupiah

23,942.08 Rupiah

57,783.77 Rupiah

18,351.11 Rupiah

13,172.59 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

114,998.49 Rupiah

138,940.57 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

ASPHALT SPRAYER E03


15 HP
800.00 Ltr
5.00 Tahun
2,000.00 Jam
24,318,630.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
24,318,630.00 Rupiah Alat Baru

2,431,863.00 Rupiah

0.33438 - 0.497664
1.49

3,659.25 Rupiah

24.32 Rupiah

3,683.56 Rupiah

18,441.63 Rupiah

5,856.74 Rupiah

1,823.90 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

51,813.29 Rupiah

55,496.85 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

BULLDOZER 100 - 150 HP E04


140 HP
- -
5.00 Tahun
2,000.00 Jam
- Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
- Rupiah Alat Baru

- Rupiah

0.33438 - 0.497664
1.49

- Rupiah

- Rupiah

- Rupiah

172,121.86 Rupiah

54,662.88 Rupiah

- Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

252,475.76 Rupiah

252,475.76 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

MPRESSOR 4000 - 6500 L/M E05


80 HP
- -
5.00 Tahun
2,000.00 Jam
36,027,600.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
36,027,600.00 Rupiah Alat Baru

3,602,760.00 Rupiah

0.33438 - 0.497664
1.49

5,421.10 Rupiah

36.03 Rupiah

5,457.13 Rupiah

98,355.35 Rupiah

31,235.93 Rupiah

2,702.07 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

157,984.37 Rupiah

163,441.50 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

NCRETE MIXER 0.30 - 0.60 M3 E06


15 HP
500.00 Ltr
4.00 Tahun
2,000.00 Jam
19,815,180.00 Rupiah
4.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
19,815,180.00 Rupiah Alat Baru

1,981,518.00 Rupiah

0.38629 - 0.41472
1.07

3,444.47 Rupiah

19.82 Rupiah

3,464.29 Rupiah

18,441.63 Rupiah

5,856.74 Rupiah

1,486.14 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

51,475.53 Rupiah

54,939.82 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

CRANE 10 - 15 TON E07


150 HP
15.00 Ton
5.00 Tahun
2,000.00 Jam
99,075,900.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
99,075,900.00 Rupiah Alat Baru

9,907,590.00 Rupiah

0.33438 - 0.497664
1.49

14,908.04 Rupiah

99.08 Rupiah

15,007.11 Rupiah

184,416.28 Rupiah

58,567.37 Rupiah

7,430.69 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

276,105.36 Rupiah

291,112.47 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

DUMP TRUCK 3 - 4 M3 E08


100 HP
4.00 Ton
5.00 Tahun
2,000.00 Jam
45,034,500.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
45,034,500.00 Rupiah Alat Baru

4,503,450.00 Rupiah

0.33438 - 0.497664
1.49

6,776.38 Rupiah

45.03 Rupiah

6,821.41 Rupiah

122,944.19 Rupiah

39,044.91 Rupiah

3,377.59 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

191,057.71 Rupiah

197,879.12 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

DUMP TRUCK E09


125 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
81,962,790.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
81,962,790.00 Rupiah Alat Baru

8,196,279.00 Rupiah

0.33438 - 0.497664
1.49

12,333.01 Rupiah

81.96 Rupiah

12,414.97 Rupiah

153,680.23 Rupiah

48,806.14 Rupiah

6,147.21 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

234,324.60 Rupiah

246,739.58 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

EXCAVATOR 80 - 140 HP E10


80 HP
0.50 M3
5.00 Tahun
2,000.00 Jam
108,082,800.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
108,082,800.00 Rupiah Alat Baru

10,808,280.00 Rupiah

0.33438 - 0.497664
1.49

16,263.31 Rupiah

108.08 Rupiah

16,371.40 Rupiah

98,355.35 Rupiah

31,235.93 Rupiah

8,106.21 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

163,388.51 Rupiah

179,759.91 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

FLAT BAD TRUCK 3 - 4 M3 E11


100 HP
4.00 M3
5.00 Tahun
2,000.00 Jam
119,791,770.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
119,791,770.00 Rupiah Alat Baru

11,979,177.00 Rupiah

0.33438 - 0.497664
1.49

18,025.17 Rupiah

119.79 Rupiah

18,144.96 Rupiah

122,944.19 Rupiah

39,044.91 Rupiah

8,984.38 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

196,664.50 Rupiah

214,809.47 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

GENERATOR SET E12


175 HP
125.00 KVA
5.00 Tahun
2,000.00 Jam
76,558,650.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
76,558,650.00 Rupiah Alat Baru

7,655,865.00 Rupiah

0.33438 - 0.497664
1.49

11,519.85 Rupiah

76.56 Rupiah

11,596.41 Rupiah

215,152.32 Rupiah

68,328.60 Rupiah

5,741.90 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

314,913.84 Rupiah

326,510.25 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

MOTOR GRADER > 100 HP E13


125 HP
- -
5.00 Tahun
2,000.00 Jam
164,826,270.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
164,826,270.00 Rupiah Alat Baru

16,482,627.00 Rupiah

0.33438 - 0.497664
1.49

24,801.55 Rupiah

164.83 Rupiah

24,966.38 Rupiah

153,680.23 Rupiah

48,806.14 Rupiah

12,361.97 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

240,539.37 Rupiah

265,505.74 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

TRACK LOADER 75 - 100 HP E14


90 HP
1.60 M3
5.00 Tahun
2,000.00 Jam
170,230,410.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
170,230,410.00 Rupiah Alat Baru

17,023,041.00 Rupiah

0.33438 - 0.497664
1.49

25,614.72 Rupiah

170.23 Rupiah

25,784.95 Rupiah

110,649.77 Rupiah

35,140.42 Rupiah

12,767.28 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

184,248.49 Rupiah

210,033.44 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

WHEEL LOADER 1,0 - 1,60 M3 E15


105 HP
1.50 M3
5.00 Tahun
2,000.00 Jam
138,706,260.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
138,706,260.00 Rupiah Alat Baru

13,870,626.00 Rupiah

0.33438 - 0.497664
1.49

20,871.25 Rupiah

138.71 Rupiah

21,009.96 Rupiah

129,091.39 Rupiah

40,997.16 Rupiah

10,402.97 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

206,182.55 Rupiah

227,192.50 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

HREE WHEEL ROLLER 6 - 8 T E16


55 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
50,438,640.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
50,438,640.00 Rupiah Alat Baru

5,043,864.00 Rupiah

0.33438 - 0.497664
1.49

7,589.55 Rupiah

50.44 Rupiah

7,639.98 Rupiah

67,619.30 Rupiah

21,474.70 Rupiah

3,782.90 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

118,567.93 Rupiah

126,207.91 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

TANDEM ROLLER 6 - 8 T E17


50 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
75,657,960.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
75,657,960.00 Rupiah Alat Baru

7,565,796.00 Rupiah

0.33438 - 0.497664
1.49

11,384.32 Rupiah

75.66 Rupiah

11,459.98 Rupiah

61,472.09 Rupiah

19,522.46 Rupiah

5,674.35 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

112,359.92 Rupiah

123,819.90 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

TIRE ROLLER 8 - 10 T E18


60 HP
10.00 Ton
5.00 Tahun
1,800.00 Jam
99,075,900.00 Rupiah
5.00 Tahun Alat Baru
1,800.00 Jam Alat Baru
99,075,900.00 Rupiah Alat Baru

9,907,590.00 Rupiah

0.33438 - 0.497664
1.49

16,564.49 Rupiah

110.08 Rupiah

16,674.57 Rupiah

73,766.51 Rupiah

23,426.95 Rupiah

8,256.33 Rupiah

16,348.88 Rupiah
9,342.15 Rupiah

131,140.81 Rupiah

147,815.38 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

VIBRATORY ROLLER 6 - 8 T E19


75 HP
7.00 Ton
4.00 Tahun
2,000.00 Jam
106,281,420.00 Rupiah
4.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
106,281,420.00 Rupiah Alat Baru

10,628,142.00 Rupiah

0.38629 - 0.41472
1.07
18,474.91 Rupiah

106.28 Rupiah

18,581.19 Rupiah

92,208.14 Rupiah

29,283.68 Rupiah

7,971.11 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

155,153.95 Rupiah

173,735.15 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

T
KOEF. SATUAN KETERANGAN

CONCRETE VIBRAETOR E20


10 HP
- -
4.00 Tahun
1,000.00 Jam
2,071,587.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
2,071,587.00 Rupiah Alat Baru

207,158.70 Rupiah

0.38629 - 0.41472
1.07

720.21 Rupiah

4.14 Rupiah

724.35 Rupiah

12,294.42 Rupiah

3,904.49 Rupiah

310.74 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah
42,200.67 Rupiah

42,925.02 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

STONE CRUSHER E21


220 HP
50.00 Ton/Jam
5.00 Tahun
2,000.00 Jam
442,689,135.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
442,689,135.00 Rupiah Alat Baru

44,268,913.50 Rupiah

0.33438 - 0.497664
1.49

66,611.82 Rupiah
442.69 Rupiah

67,054.51 Rupiah

270,477.21 Rupiah

85,898.81 Rupiah

33,201.69 Rupiah

16,348.88 Rupiah

18,684.30 Rupiah

424,610.87 Rupiah

491,665.38 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN


KOEF. SATUAN KETERANGAN

WATER PUMP 70 - 100 mm E22


6 HP
- -
2.00 Tahun
2,000.00 Jam
2,702,070.00 Rupiah
2.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
2,702,070.00 Rupiah Alat Baru

270,207.00 Rupiah

0.65455 - 0.288
0.44

795.88 Rupiah

2.70 Rupiah

798.58 Rupiah

7,376.65 Rupiah

2,342.69 Rupiah

202.66 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

35,613.03 Rupiah
36,411.61 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

WATER TANKER 3000 - 4500 L E23


100 HP
4,000.00 Ltr
5.00 Tahun
2,000.00 Jam
32,424,840.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
32,424,840.00 Rupiah Alat Baru

3,242,484.00 Rupiah

0.33438 - 0.497664
1.49

4,878.99 Rupiah
32.42 Rupiah

4,911.42 Rupiah

122,944.19 Rupiah

39,044.91 Rupiah

2,431.86 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

190,111.98 Rupiah

195,023.40 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN


PEDESTRIAN ROLLER E24
11 HP
0.17 Ton
4.00 Tahun
2,000.00 Jam
16,662,765.00 Rupiah
4.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
16,662,765.00 Rupiah Alat Baru

1,666,276.50 Rupiah

0.38629 - 0.41472
1.07

2,896.49 Rupiah

16.66 Rupiah

2,913.15 Rupiah

13,523.86 Rupiah

4,294.94 Rupiah

1,249.71 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

44,759.53 Rupiah

47,672.69 Rupiah
20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

TAMPER E25
5 HP
0.17 Ton
4.00 Tahun
1,000.00 Jam
2,702,070.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
2,702,070.00 Rupiah Alat Baru

270,207.00 Rupiah

0.38629 - 0.41472
1.07

939.40 Rupiah

5.40 Rupiah
944.81 Rupiah

6,147.21 Rupiah

1,952.25 Rupiah

405.31 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

34,195.79 Rupiah

35,140.60 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

JACK HAMMER E26


3 HP
- -
4.00 Tahun
1,000.00 Jam
2,702,070.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
2,702,070.00 Rupiah Alat Baru

270,207.00 Rupiah

0.38629 - 0.41472
1.07

939.40 Rupiah

5.40 Rupiah

944.81 Rupiah

3,688.33 Rupiah

1,171.35 Rupiah

405.31 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

30,956.01 Rupiah

31,900.81 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

FULVI MIXER E27


75 HP
- -
5.00 Tahun
2,000.00 Jam
41,431,740.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
41,431,740.00 Rupiah Alat Baru

4,143,174.00 Rupiah

0.33438 - 0.497664
1.49

6,234.27 Rupiah

41.43 Rupiah

6,275.70 Rupiah
92,208.14 Rupiah

29,283.68 Rupiah

3,107.38 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

150,290.23 Rupiah

156,565.93 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

LE DRIVER (ALAT PANCANG) E28


125 HP
2.50 Ton
5.00 Tahun
2,000.00 Jam
225,172,500.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
225,172,500.00 Rupiah Alat Baru

22,517,250.00 Rupiah

0.33438 - 0.497664
1.49

33,881.90 Rupiah

225.17 Rupiah

34,107.07 Rupiah

153,680.23 Rupiah

48,806.14 Rupiah

16,887.94 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

245,065.33 Rupiah

279,172.41 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

CRANE ON TRACK E29


150 HP
25.00 Ton
5.00 Tahun
2,000.00 Jam
270,207,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
270,207,000.00 Rupiah Alat Baru

27,020,700.00 Rupiah

0.33438 - 0.497664
1.49

40,658.28 Rupiah

270.21 Rupiah

40,928.49 Rupiah
184,416.28 Rupiah

58,567.37 Rupiah

20,265.53 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

288,940.19 Rupiah

329,868.68 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

TRAILLER E30
150 HP
40.00 Ton
5.00 Tahun
2,000.00 Jam
180,138,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
180,138,000.00 Rupiah Alat Baru

18,013,800.00 Rupiah

0.33438 - 0.497664
1.49

27,105.52 Rupiah

180.14 Rupiah

27,285.66 Rupiah

184,416.28 Rupiah

58,567.37 Rupiah

13,510.35 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

282,185.02 Rupiah

309,470.68 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

GROUTING MACHINE E31


10 HP
10.00 0
5.00 Tahun
2,000.00 Jam
18,013,800.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
18,013,800.00 Rupiah Alat Baru

1,801,380.00 Rupiah

0.33438 - 0.497664
1.49

2,710.55 Rupiah

18.01 Rupiah

2,728.57 Rupiah

12,294.42 Rupiah
3,904.49 Rupiah

1,351.04 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

43,240.97 Rupiah

45,969.54 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

STRESSING MACHINE E32


50 HP
- -
5.00 Tahun
2,000.00 Jam
27,020,700.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
27,020,700.00 Rupiah Alat Baru

2,702,070.00 Rupiah

0.33438 - 0.497664
1.49

4,065.83 Rupiah

27.02 Rupiah

4,092.85 Rupiah

61,472.09 Rupiah

19,522.46 Rupiah

2,026.55 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

108,712.13 Rupiah

112,804.97 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

BATCHING PLANT E33


150 HP
8,000.00 Ltr/Jam
5.00 Tahun
2,000.00 Jam
1,351,035,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
1,351,035,000.00 Rupiah Alat Baru

135,103,500.00 Rupiah

0.33438 - 0.497664
1.49

203,291.41 Rupiah

1,351.04 Rupiah

204,642.44 Rupiah

184,416.28 Rupiah

58,567.37 Rupiah
101,327.63 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

370,002.29 Rupiah

574,644.74 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter

KOEF. SATUAN KETERANGAN

TRUCK MIXER E34


125 HP
6.00 M3
5.00 Tahun
2,000.00 Jam
106,551,627.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
106,551,627.00 Rupiah Alat Baru
10,655,162.70 Rupiah

0.33438 - 0.497664
1.49

16,032.92 Rupiah

106.55 Rupiah

16,139.47 Rupiah

153,680.23 Rupiah

48,806.14 Rupiah

7,991.37 Rupiah

16,348.88 Rupiah

9,342.15 Rupiah

236,168.77 Rupiah

252,308.23 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
T

KOEF. SATUAN KETERANGAN

CONCRETE PUMP E35


125 HP
10.00 M3
5.00 Tahun
2,000.00 Jam
210,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
210,000,000.00 Rupiah Alat Baru

21,000,000.00 Rupiah

0.33438 - 0.497664
1.49

31,598.88 Rupiah

210.00 Rupiah

31,808.88 Rupiah

153,680.23 Rupiah

48,806.14 Rupiah

15,750.00 Rupiah
16,348.88 Rupiah

9,342.15 Rupiah

243,927.40 Rupiah

275,736.28 Rupiah

20.00 % / Tahun
16,348.88 Rp. / Jam
9,342.15 Rp. / Jam
6,845.24 Liter
8,196.28 Liter
26,029.94 Liter
ALAT BARU ALAT YANG DIPAKAI
UMUR EKONOMIS JAM KERJA HARGA ALAT UMUR EKONOMIS JAM KERJA
(TAHUN) (JAM) (Rp) (TAHUN) (JAM)
10.00 1,500.00 575,540,910.00 10.00 1,500.00
6.00 2,000.00 175,634,550.00 6.00 2,000.00
5.00 2,000.00 24,318,630.00 5.00 2,000.00
5.00 2,000.00 - 5.00 2,000.00
5.00 2,000.00 36,027,600.00 5.00 2,000.00
4.00 2,000.00 19,815,180.00 4.00 2,000.00
5.00 2,000.00 99,075,900.00 5.00 2,000.00
5.00 2,000.00 45,034,500.00 5.00 2,000.00
5.00 2,000.00 81,962,790.00 5.00 2,000.00
5.00 2,000.00 108,082,800.00 5.00 2,000.00
5.00 2,000.00 119,791,770.00 5.00 2,000.00
5.00 2,000.00 76,558,650.00 5.00 2,000.00
5.00 2,000.00 164,826,270.00 5.00 2,000.00
5.00 2,000.00 170,230,410.00 5.00 2,000.00
5.00 2,000.00 138,706,260.00 5.00 2,000.00
5.00 2,000.00 50,438,640.00 5.00 2,000.00
5.00 2,000.00 75,657,960.00 5.00 2,000.00
5.00 1,800.00 99,075,900.00 5.00 1,800.00
4.00 2,000.00 106,281,420.00 4.00 2,000.00
4.00 1,000.00 2,071,587.00 4.00 1,000.00
5.00 2,000.00 442,689,135.00 5.00 2,000.00
2.00 2,000.00 2,702,070.00 2.00 2,000.00
5.00 2,000.00 32,424,840.00 5.00 2,000.00
4.00 2,000.00 16,662,765.00 4.00 2,000.00
4.00 1,000.00 2,702,070.00 4.00 1,000.00
4.00 1,000.00 2,702,070.00 4.00 1,000.00
5.00 2,000.00 41,431,740.00 5.00 2,000.00
5.00 2,000.00 225,172,500.00 5.00 2,000.00
5.00 2,000.00 270,207,000.00 5.00 2,000.00
5.00 2,000.00 180,138,000.00 5.00 2,000.00
5.00 2,000.00 18,013,800.00 5.00 2,000.00
5.00 2,000.00 27,020,700.00 5.00 2,000.00
5.00 2,000.00 1,351,035,000.00 5.00 2,000.00
5.00 2,000.00 106,551,627.00 5.00 2,000.00
5.00 2,000.00 210,000,000.00 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 #REF! 5.00 2,000.00
5.00 2,000.00 46,000,000.00 5.00 2,000.00

1 Tingkat Suku Bunga i 20.00 % / Tahun


2 Upah Operator / Sopir U1 16,348.88 Rp. / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 9,342.15 Rp. / Jam
4 Bahan Bakar Bensin Mb 6,845.24 Liter
5 Bahan Bakar Solar Ms 8,196.28 Liter
6 Minyak Pelumas Mp 26,029.94 Liter
YANG DIPAKAI
AM KERJA HARGA ALAT
(JAM) (Rp)
1,500.00 575,540,910.00
2,000.00 175,634,550.00
2,000.00 24,318,630.00
2,000.00 -
2,000.00 36,027,600.00
2,000.00 19,815,180.00
2,000.00 99,075,900.00
2,000.00 45,034,500.00
2,000.00 81,962,790.00
2,000.00 108,082,800.00
2,000.00 119,791,770.00
2,000.00 76,558,650.00
2,000.00 164,826,270.00
2,000.00 170,230,410.00
2,000.00 138,706,260.00
2,000.00 50,438,640.00
2,000.00 75,657,960.00
1,800.00 99,075,900.00
2,000.00 106,281,420.00
1,000.00 2,071,587.00
2,000.00 442,689,135.00
2,000.00 2,702,070.00
2,000.00 32,424,840.00
2,000.00 16,662,765.00
1,000.00 2,702,070.00
1,000.00 2,702,070.00
2,000.00 41,431,740.00
2,000.00 225,172,500.00
2,000.00 270,207,000.00
2,000.00 180,138,000.00
2,000.00 18,013,800.00
2,000.00 27,020,700.00
2,000.00 1,351,035,000.00
2,000.00 106,551,627.00
2,000.00 210,000,000.00
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 #REF!
2,000.00 46,000,000.00
REKAPITULASI
DAFTAR KUANTITAS DAN

No. Paket Kontrak


NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (
: SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATA
LOKASI : Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+89
Prov / Kab / Kota : JAWA BARAT / KOTA SUKABUMI
Nama Penawar :

No. DIVISI U r a i a n

1 UMUM

2 DRAINASE

3 PEKERJAAN TANAH

4 PELEBARAN PERKERASAN DAN BAHU JALAN

5 PERKERASAN BERBUTIR

6 PERKERASAN ASPAL

7 STRUKTUR

8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

9 PEKERJAAN HARIAN

10 PEKERJAAN PEMELIHARAAN RUTIN

(A) Jumlah Harga Pekerjaan (termasuk Biaya Umum dan Keuntungan)

(B) Pajak Pertambahan Nilai (PPn) = 10% x (A)

(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)

Terbilang :
Dua Belas Milyar Empat Puluh Empat Juta Dua Ratus Tujuh Puluh Lim
DAFTAR KUANTITAS DAN
No. Paket Kontrak 0

Nama Paket : PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (


SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATA
: Km Bdg. 100+049 - Km Bdg.100+624 & Km Bdg. 100+949 - Km Bdg.100+89
Prov / Kab / Kota : JAWA BARAT / KOTA SUKABUMI
Nama Penawar :
No. Mata
U r a i a n
Pembayaran

DIVISI 1 - UMUM

Jumlah Harga Pekerjaan Divisi 1 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 2 - D R A I N A S E

2.1 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air


2.2 Pekerjaan Pasangan Batu Dengan Mortar

Jumlah Harga Pekerjaan Divisi 2 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 3 - PEKERJAAN TANAH

3.2(1) Timbunan Biasa Dari Selain Galian Sumber Bahan


3.2(2) Timbunan Pilihan

Jumlah Harga Pekerjaan Divisi 3 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 4 - PELEBARAN PERKERASAN DAN


BAHU JALAN

4.2(2) Lapis Pondasi Agregat kelas B


No. Mata
U r a i a n
Pembayaran

Jumlah Harga Pekerjaan Divisi 4 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 5 - PERKERASAN BERBUTIR

5.6(1) Lapis Pondasi Agregat Dengan Cement Treated Base (CTB)

Jumlah Harga Pekerjaan Divisi 5 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 6 - PERKERASAN ASPAL

6.1(1) Lapis Resap Pengikat


6.1(2) Lapis Perekat
6.3(5a) Laston - Lapis Aus (AC-WC)
6.3(6a) Laston - Lapis Antara (AC-BC)
6.3(7a) Laston - Lapis Pondasi (AC-Base)

Jumlah Harga Pekerjaan Divisi 6 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
No. Mata
U r a i a n
Pembayaran

DIVISI 7 - STRUKTUR

7.1(4) Beton K.300


7.1(5) Beton K.250
7.1(6) Beton K.175
7.2(8) Unit Pracetak Gelagar Tipe I Bentang 40 Meter
7.2(11) Beton Diafragma K.350 Termasuk Pekerjaan Pra Penegangan
setelah Pengecoran ( Post-tension )
7.3(1) Baja Tulangan U24 Polos
7.3(3) Baja Tulangan U32 Ulir
7.4(1) Baja Struktur Ttk. Leleh 2500 Kg/cm2, Penyediaan dan Pemasangan
7.9 Pasangan Batu
7.11(6) Expantion Joint Type Baja Bersudut
7.12(4) Perletakan Elastomerik Jenis 3 (300 x 450 x 45)
7.13 Sandaran Jembatan Baja
7.14 Papan Nama Jembatan
7.15(1) Pembongkaran Pasangan Batu
7.15(2) Pembongkaran Pasangan Beton
7.17 (3) Pipa Cucuran

Jumlah Harga Pekerjaan Divisi 7 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 8 - PENGEMBALIAN KONDISI DAN


PEKERJAAN MINOR

8.4(1) Marka Jalan Thermoplastik


8.4(3)(a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
8.4(5) Patok Pengarah
8.4(10) Kerb Pracetak
8.7(1) Unit LampuPenerangan Jalan Lengan Tunggal, Type Sodium 250 watt
8.7(2) Unit LampuPenerangan Jalan Lengan Ganda, Type Sodium 250 watt

Jumlah Harga Pekerjaan Divisi 8 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
No. Mata
U r a i a n
Pembayaran
Jumlah Harga Pekerjaan Divisi 8 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 9 - PEKERJAAN HARIAN

Jumlah Harga Pekerjaan Divisi 9 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 10 - PEKERJAAN PEMELIHARAAN RUTIN

Jumlah Harga Pekerjaan Divisi 10 (Masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
KAPITULASI
ANTITAS DAN HARGA

N JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR


UNAN ATAS DAN PENATAAN SIMPANG )
0+949 - Km Bdg.100+894

Jumlah Harga
a i a n Pekerjaan
(Rp)
-

19,275,033.35

741,044,470.70

33,150,300.80

485,875,353.08

1,015,214,004.74

8,139,742,147.95

515,040,178.55

10,949,341,489.17

1,094,934,148.92

12,044,275,000.00

atus Tujuh Puluh Lima Ribu Rupiah.

#REF!
Sukabumi, Januari 2016

Dibuat Oeh :
Pejabat Pembuat Komitmen ( PPK )
Balai Pengelolaan Jalan Wilayah Pelayanan II

ERYANTO,ST,MT
Pembina
NIP. 19591105 198903 1 006
ANTITAS DAN HARGA

N JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR


UNAN ATAS DAN PENATAAN SIMPANG )
0+949 - Km Bdg.100+894

Perkiraan Harga Satuan Jumlah Harga-Harga


Satuan
Kuantitas (Rp) (Rp)

raan Harga Pekerjaan) -

M3 84.00 55,101.65 4,628,538.60


M3 25.00 585,859.79 14,646,494.75

raan Harga Pekerjaan) 19,275,033.35

M3 5,010.00 116,798.57 585,160,835.70


M3 1,055.00 147,757.00 155,883,635.00

raan Harga Pekerjaan) 741,044,470.70

M3 101.00 328,220.80 33,150,300.80


Perkiraan Harga Satuan Jumlah Harga-Harga
Satuan
Kuantitas (Rp) (Rp)

raan Harga Pekerjaan) 33,150,300.80

M3 754.00 644,397.02 485,875,353.08

raan Harga Pekerjaan) 485,875,353.08

Liter 2,138.00 13,932.91 29,788,561.58


Liter 851.00 13,437.53 11,435,338.03
M2 3,113.00 99,988.00 311,262,644.00
M3 126.00 2,533,603.61 319,234,054.86
M3 151.00 2,274,790.77 343,493,406.27

raan Harga Pekerjaan) 1,015,214,004.74


Perkiraan Harga Satuan Jumlah Harga-Harga
Satuan
Kuantitas (Rp) (Rp)

M3 189.00 1,222,948.03 231,137,177.67


M3 125.00 996,136.87 124,517,108.75
M3 101.00 760,381.77 76,798,558.77
Buah 14.00 423,483,552.39 5,928,769,733.46
M3 72.00 2,974,983.46 214,198,809.12

Kg 62,800.00 11,985.14 752,666,792.00


Kg 11,726.00 12,708.48 149,019,636.48
Kg 3,200.00 54,755.57 175,217,824.00
M3 514.00 553,331.13 284,412,200.82
M' 40.00 405,600.00 16,224,000.00
Buah 28.00 2,450,000.00 68,600,000.00
M' 320.00 275,000.00 88,000,000.00
Buah 4.00 1,170,284.50 4,681,138.00
M3 10.00 161,494.74 1,614,947.40
M3 3.00 261,407.16 784,221.48
M1 84.00 275,000.00 23,100,000.00

raan Harga Pekerjaan) 8,139,742,147.95

M2 149.00 112,951.73 16,829,807.77


Buah 8.00 1,016,190.14 8,129,521.12
Buah 50.00 149,694.15 7,484,707.50
M' 678.00 200,693.72 136,070,342.16
Buah 5.00 14,341,960.00 71,709,800.00
Buah 10.00 27,481,600.00 274,816,000.00

raan Harga Pekerjaan) 515,040,178.55


Perkiraan Harga Satuan Jumlah Harga-Harga
Satuan
Kuantitas (Rp) (Rp)
raan Harga Pekerjaan) 515,040,178.55

raan Harga Pekerjaan) -

kiraan Harga Pekerjaan) -


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / KOTA SUKABUMI
JENIS PEKERJAAN : ASPAL
SATUAN PEMBAYARAN : KG

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0087 9,342.11


2. Mandor (L03) jam 0.0174 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

Aspal Kg 1.0000 4,620.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Truck Tangki jam 0.0087 257,000.00


2. Alat Bantu Ls 1.0000 223.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. PPN 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-21

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 1.2 PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Mobilisasi TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Ls % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

I Sewa Tanah M2 - -

II Mobilisasi dan Demobilisasi Ls - -


Peralatan

III Fasilitas Penyedia Jasa


1 Sewa Kantor Lapangan Unit 1.00 10,000,000.00

IV Lain - lain
1 Papan Nama Proyek Buah 2.00 500,000.00
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( I s.d IV )
TUAN

ATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN AT

JUMLAH
HARGA
(Rp.)

81.13
283.97

365.11

4,620.00

4,620.00

2,231.98
223.00

2,454.98

7,440.08
744.01
8,184.09
olume dan/atau ukuran

uan pekerjaan dari nomor

api tidak termasuk PPN


Analisa EI-21

TUAN

ATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN AT

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

10,000,000.00

1,000,000.00
11,000,000.00
AP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
AP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN SIMPANG )
ITEM PEMBAYARAN NO. : 2.1
JENIS PEKERJAAN : Pek. Galian Untuk Saluran Air (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 jam
5 Faktor pengembangan bahan Fk 1.20 -

II. URUTAN KERJA


1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 3.00 Km
4 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -

Waktu siklus Ts1 menit


- Menggali / memuat T1 0.500 menit
- Lain-lain T2 0.500 menit
Ts1 1.000 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3 / jam


Ts1 x Fh

Koefisien Alat / M3 = 1 : Q1 - 0.0535 Jam

2.b. DUMP TRUCK (E08)


Kaasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 Km/Jam
Kecepatan rata-rata kosong v2 40.00 Km/Jam
Waktu siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 6.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 4.50 menit
- Muat = (V : Q1) x 60 T3 12.85 menit
- Lain-lain T4 6.00 menit
Ts2 29.35 menit
Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.1
JENIS PEKERJAAN : Pek. Galian Untuk Saluran Air (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 5.66 M3 / Jam


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 - 0.1768 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 18.68 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 149.40 M3
Kebutuhan tenaga :
- Pekerja P 5.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.2677 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0535 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 57,189.56 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : - Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : - M3
ITEM PEMBAYARAN NO. : 2.1
JENIS PEKERJAAN : Pek. Galian Untuk Saluran (Manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 jam
5 Faktor pengembangan bahan Fk 1.20 -

II. URUTAN KERJA


1 Penggalian dilakukan dengan manual (Tenaga kerja)
2 Tenaga kerja menuangkan hasil galian kedalam
Dump Truck
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 3.00 Km
4 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.b. DUMP TRUCK (E08)
Kaasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 Km/Jam
Kecepatan rata-rata kosong v2 40.00 Km/Jam
Waktu siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 6.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 4.50 menit
- Muat T3 10.00 menit
- Lain-lain T4 2.00 menit
Ts2 22.50 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 7.38 M3 / Jam


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 - 0.1355 Jam

2.a. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu
- Cangkul

3. TENAGA
Asumsi Produksi pekerjaan : Q1 4.00 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 32.00 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.0000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.2500 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 55,101.65 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 17 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 84.00 M3

ITEM PEMBAYARAN NO. : 2.2


JENIS PEKERJAAN : Pasangan Batu Dengan Mortar
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan buruh (cara manual)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 18.9 KM
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 25 %
: - Volume Pasir Ps 75 %
7 Perbandingan Batu & Mortar :
- Batu Bt 60 %
- Mortar (campuran semen & pasir) Mr 40 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.67 ton/M3
- Semen Portland D5 1.44 ton/M3
9 Faktor kehilangan bahan : - Batu Fh1 1.20 -
- Pasir / Semen Fh2 1.05 -

II. URUTAN KERJA


1 Semen, pasir dan air dicampur dan diaduk menjadi
mortar dengan menggunakan alat bantu
2 Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
3 Penyelesaian dan perapihan setelah pemasangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x Fh1 (M02) 1.1 M3
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x Fh2 (M12) 0.1400 M3
x {D5 x (1000)} (M12) 202 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x Fh2 (M01) 0.4527 M3

2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Sekop = 2 buah
- Pacul = 2 buah
- Sendok Semen = 2 buah
- Ember Cor = 4 buah
- Gerobak Dorong = 1 buah

3. TENAGA
Produksi Pasangan Batu dengan Mortar dalam 1 hari Qt 6.00 M3
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Batu Tb 4.00 orang
- Pekerja P 14.00 orang

Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.2
JENIS PEKERJAAN : Pasangan Batu Dengan Mortar
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.3333 jam
- Tukang = (Tk x Tb) : Qt (L02) 5.3333 jam
- Pekerja = (Tk x P) : Qt (L01) 18.6667 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 872,093.01 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : - Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 2.2
JENIS PEKERJAAN : Pasangan Batu Dengan Mortar
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.0 KM
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 25 %
: - Volume Pasir Ps 75 %
7 Perbandingan Batu & Mortar :
- Batu Bt 60 %
- Mortar (campuran semen & pasir) Mr 40 %
8 Berat Isi Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.67 ton/M3
- Semen Portland D5 1.40 ton/M3

II. URUTAN KERJA


1 Semen, pasir dan air dicampur dan diaduk menjadi
mortar dengan menggunakan alat bantu
2 Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
3 Penyelesaian dan perapihan setelah pemasangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.20 (M02) 1.1 M3
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.05 (M12) 0.1400 M3
x {D5 x (1000)} (M12) 196 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01) 0.4527 M3

2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 Liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4)
- Memuat T1 1.00 menit
- Mengaduk T2 1.00 menit
- Menuang T3 1.00 menit
- Tunggu, dll. T4 0.50 menit
Ts1 3.50 menit
Kap. Prod. / jam = V x Fa x 60 Q1 7.114 M3
1000 x Ts1

Koefisien Alat / M3 = 1 : Q1 (E06) 0.1406 jam

Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.2
JENIS PEKERJAAN : Pasangan Batu Dengan Mortar
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

2.b. WATER TANK TRUCK (E23)


Volume Tanki Air V 4.00 M3
Kebutuhan air / M3 pasangan batu Wc 0.088 M3
Faktor Efiesiensi Alat Fa 0.83 -
Pengisian Tanki / jam n 1.00 kali

Kap. Prod. / jam = V x Fa x n Q2 37.64 M3


Wc
Koefisien Alat / M3 = 1 : Q2 (E23) 0.0266 jam
2.c.
Diperlukan :
- Sekop = 4 buah
- Pacul = 4 buah
- Sendok Semen = 4 buah
- Ember Cor = 8 buah
- Gerobak Dorong = 3 buah
3. TENAGA
Produksi Pas. Batu yang menentukan (Asumsi) Q1 1.00 M3/Jam
Produksi Pasangan Batu dalam 1 hari = Tk x Q1 Qt 8.00 M3

Kebutuhan tenaga : - Mandor M 1.00 orang


- Tukang Batu Tb 2.00 orang
- Pekerja P 4.00 orang

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.0000 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.0000 jam
- Pekerja = (Tk x P) : Qt (L01) 4.0000 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 585,859.79 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0.57 bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 25.00 M3
ITEM PEMBAYARAN NO. : 2.3 (1)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 0.40 m
4 Jarak rata-rata Unit Produksi ke lokasi pekerjaan L 18.89 Km
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Tebal gorong-gorong tg 6.50 Cm

II. URUTAN KERJA


1 Gorong-gorong dicetak di Base Camp
2 Dump Truck mengangkut gorong-gorong jadi
ke lapangan
3 Dasar gorong-gorong digali lalu dipadatkan dengan
Tamper
4 Lapis dasar gorong-gorong dibayar terpisah
5 Material pasir untuk penimbunan kembali (backfill)
6 Sekelompok pekerja akan melaksanakan pekerjaan
dengan cara manual dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Untuk mendapatkan 1 M' gorong-gorong diperlukan
- Beton K-300 (EI-714) 0.0950 M3
- Baja Tulangan (asumsi 100kg/m3) (M39) 10.4450 Kg
- Timbunan Pilihan = ((2*tg/100+d+0.5)*(0.5+2*tg/100+d+0.5) (M01) 0.7531 M3
-(22/7*(0.5*(2*tg/100+d))^2)*1)*1.05

2. ALAT
2.a. TAMPER (E25)
Kecepatan v 0.50 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 10 lintasan
Tebal lapis hamparan tp 0.20 M

Kap. Prod. / Jam = v x 1000 x Fa x Lb x 60 Q1 3.32 M3 / Jam


n x tp

Koefisien Alat / m' = 1 : Q1 x Vp (E25) 0.2268 jam

2.b. DUMP TRUCK (E08)


Kapasitas bak sekali muat V 15.00 Buah/M'
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 30.00 Km/Jam
Kecepatan rata-rata kosong v2 40.00 Km/Jam
Waktu siklus : Ts1
- Waktu tempuh in si = (L : v1 ) x 60 T1 37.79 menit
- Waktutempuh kosong = (L : v2) x 60 T2 28.34 menit
- Lain-lain T3 10.00 menit
Ts1 76.13 menit
Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.3 (1)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 9.812 M' / Jam


Ts1

Koefisien Alat / m3 = 1 : Q2 (E08) 0.1019 jam

2.c. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop = 3 buah
- Alat-alat kecil lain

3. TENAGA
Produksi Gorong-gorong / hari Qt 10.00 M'
Kebutuhan tenaga :
- Pekerja P 5.00 orang
- Tukang T 2.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 4.0000 Jam
- Tukang = (Tk x T) : Qt (L02) 1.6000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.8000 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,063,825.59 / M'

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
ITEM PEMBAYARAN NO. : 2.3 (2)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 - 70 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 0.60 m
4 Jarak rata-rata Unit produksi ke lokasi pekerjaan L 60.0 Km
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Tebal gorong-gorong tg 7.47 Cm

II. URUTAN KERJA


1 Gorong-gorong dicetak di Base Camp
2 Dump Truck mengangkut gorong-gorong jadi
ke lapangan
3 Dasar gorong-gorong digali lalu dipadatkan dengan
Tamper
4 Lapis dasar gorong-gorong dibayar terpisah
5 Material pasir untuk penimbunan kembali (backfill)
6 Sekelompok pekerja akan melaksanakan pekerjaan
dengan cara manual dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Untuk mendapatkan 1 M' gorong-gorong diperlukan

- Gorong-gorong Beton Bertulang Dia. Dalam 45-75 Cm 1.0000 M


- Timbunan Pilihan = (Tinggi x Lebar) - ( Luas Gorong gorong ) (EI-322) 1.6576 M3
= (1,8 x 1,2 ) - ( 3,14) x ( 0,4 x 0,4 )

2. ALAT
2.a. TAMPER (E25)
Kecepatan v 0.50 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 10 lintasan
Tebal lapis hamparan tp 0.20 M

Kap. Prod. / Jam = v x 1000 x Fa x Lb x 60 Q1 3.32 M3 / Jam


n x tp

Koefisien Alat / m' = 1 : Q1 x Vp (E25) 0.4993 jam

2.b. DUMP TRUCK (E08)


Kapasitas bak sekali muat V 10.00 Buah/M'
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 30.00 Km/Jam
Kecepatan rata-rata kosong v2 40.00 Km/Jam
Waktu siklus : Ts
- Waktu tempuh in si = (L : v1 ) x 60 T1 120.00 menit
- Waktutempuh kosong = (L : v2) x 60 T2 90.00 menit
- Lain-lain T3 50.00 menit
Ts 260.00 menit
Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.3 (2)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 - 70 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 1.9154 M' / Jam


Ts

Koefisien Alat / m3 = 1 : Q2 (E08) 0.5221 jam

2.c. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop = 3 buah
- Alat-alat kecil lain

3. TENAGA
Produksi Gorong-gorong / hari Qt 10.00 M'
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Tukang T 2.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M' :


- Pekerja = (Tk x P) : Qt (L01) 5.6000 jam
- Tukang = (Tk x T) : Qt (L02) 1.6000 jam
- Mandor = (Tk x M) : Qt (L03) 0.8000 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,229,600.56 / M'

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
ITEM PEMBAYARAN NO. : 2.3 (3)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 70 - 100 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 1.00 m
4 Jarak rata-rata Dari Unit Produksi ke lokasi pekerjaan L 18.9 Km
5 Jam kerja efektif per-hari Tk 8.00 Jam
6 Tebal gorong-gorong tg 9.15 Cm

II. URUTAN KERJA


1 Gorong-gorong dicetak di Unit Produksi
2 Dump Truck mengangkut gorong-gorong jadi
ke lapangan
3 Dasar gorong-gorong digali lalu dipadatkan dengan
Tamper
4 Tebal lapis porus pada dasar gorong-gorong tp 0.15 M
5 Material pilihan untuk penimbunan kembali
6 Sekelompok pekerja akan melaksanakan pekerjaan
dengan cara manual dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Untuk mendapatkan 1 M' gorong-gorong diperlukan
- Beton K-300 (EI-714) 0.3140 M3
- Baja Tulangan (asumsi 100kg/m3) (M39) 34.5354 Kg
Timb. Pilihan = ((2*tg/100+d+0.5)*(0.5+2*tg/100+d+0.5) (EI-322) 1.6174 M3
-(22/7*(0.5*(2*tg/100+d))^2)*1)*1.05

2. ALAT
2.a. TAMPER (E25)
Kecepatan V 0.50 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 10 lintasan
Tebal lapis hamparan tp 0.20 M

Kap. Prod. / Jam = v x 1000 x Fa x Lb x 60 Q1 3.3200 M3 / Jam


n x tp

Koefisien Alat / m' = 1 : Q1 x Vp (E25) 0.4872 jam

2.b. DUMP TRUCK (E08)


Kapasitas bak sekali muat V 4.00 Buah/M'
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 30.00
Kecepatan rata-rata kosong v2 40.00
Waktu siklus : Ts
- Waktu tempuh in si = (L : v1 ) x 60 T1 37.79 menit
- Waktutempuh kosong = (L : v2) x 60 T2 28.34 menit
- Lain-lain T3 50.00 menit
Ts 116.13 menit
Berlanjut ke halam
ITEM PEMBAYARAN NO. : 2.3 (3)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 70 - 100 cm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARG

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 1.7153 M' / Jam


Ts

Koefisien Alat / m' = 1 : Q2 (E08) 0.5830 jam

2.c. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop = 3 buah
- Alat-alat kecil lain

3. TENAGA
Produksi Gorong-gorong / hari Qt 6.00 M'
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Tukang T 1.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M' :


- Pekerja = (Tk x P) : Qt (L01) 10.6667 jam
- Tukang = (Tk x T) : Qt (L02) 1.3333 jam
- Mandor = (Tk x M) : Qt (L03) 1.3333 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,841,584.04 / M'

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M'
Analisa EI-21

URAIAN ANALISA HARGA SATUAN

KETERANGAN
Berlanjut ke halaman berikut
Analisa EI-21

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

Lump Sump
Analisa EI-21

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Lump Sump
Analisa LI-22

URAIAN ANALISA HARGA SATUAN

KETERANGAN
Berlanjut ke halaman berikut
Analisa LI-22

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Analisa EI-22

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Kuat Tekan min.


50 kg/cm2
Berlanjut ke halaman berikut
Analisa EI-22

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Analisa EI-231

URAIAN ANALISA HARGA SATUAN

KETERANGAN

= Vp
Berlanjut ke halaman berikut
Analisa EI-231

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

Lump Sump
Analisa EI-232

URAIAN ANALISA HARGA SATUAN

KETERANGAN

= Vp
Berlanjut ke halaman berikut
Analisa EI-232

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

Lump Sump
Analisa EI-233

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Min 10% dia.


atau 5cm.

= Vp
Berlanjut ke halaman berikut
Analisa EI-233

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

Lump Sump
Analisa EI-21

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. : 0.00
ITEM PEMBAYARAN NO. : 2.1 TOTAL HARGA (Rp.) : 0.00
JENIS PEKERJAAN : Pek. Galian Untuk Saluran Air (Mekanik) % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.2677 9,342.11 2,501.23


2. Mandor (L03) jam 0.0535 16,348.88 875.44

JUMLAH HARGA TENAGA 3,376.68

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Excavator (E10) jam 0.0535 179,759.91 9,625.70


2. Dump Truck (E08) jam 0.1768 197,879.12 34,988.14
3. Alat Bantu Ls 1.0000 4,000.00 4,000.00

JUMLAH HARGA PERALATAN 48,613.83

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 51,990.51


E. OVERHEAD & PROFIT 10.0 % x D 5,199.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,189.56
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa LI-22

FORMULIR STANDAR UNTUK


Analisa EI-21

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. : 84.00
ITEM PEMBAYARAN NO. : 2.1 TOTAL HARGA (Rp.) : 4,628,538.60
JENIS PEKERJAAN : Pek. Galian Untuk Saluran (Manual) % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 2.0000 9,342.11 18,684.23


2. Mandor (L03) jam 0.2500 16,348.88 4,087.22

JUMLAH HARGA TENAGA 22,771.44

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Excavator (E10) jam #REF! 0.00 0.00


1 Dump Truck (E08) jam 0.1355 197,879.12 26,820.97
2 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 27,320.97

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 50,092.41


E. OVERHEAD & PROFIT 10.0 % x D 5,009.24
F. HARGA SATUAN PEKERJAAN ( D ) 55,101.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa LI-22
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 2.2 PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Pasangan Batu Dengan Mortar TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 18.6667 9,342.11 174,386.10


2. Tukang (L02) jam 5.3333 11,677.80 62,281.61
3. Mandor (L03) jam 1.3333 16,348.88 21,798.50

JUMLAH HARGA TENAGA 258,466.21

B. BAHAN
1. Batu (M02) M3 1.100 126,096.60 138,706.26
2. Semen (PC) (M12) Kg 202.000 1,260.97 254,715.13
3. Pasir (M01) M3 0.4527 124,295.22 56,267.78
4. Bahan bantu Ls 1.000 12,582.64 12,582.64

JUMLAH HARGA BAHAN 462,271.81

C. PERALATAN

1. Alat Bantu Ls 1.0000 72,073.80 72,073.80

JUMLAH HARGA PERALATAN 72,073.80

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 792,811.82


E. OVERHEAD & PROFIT 10.0 % x D 79,281.18
E. HARGA SATUAN PEKERJAAN ( D ) 872,093.01
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-22

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. : 25.00
ITEM PEMBAYARAN NO. : 2.2 TOTAL HARGA (Rp.) : 14,646,494.75
JENIS PEKERJAAN : Pasangan Batu Dengan Mortar % THD. BIAYA PROYEK : 0.13
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 4.0000 9,342.11 37,368.45


2. Tukang Batu (L02) jam 2.0000 11,677.80 23,355.60
3. Mandor (L03) jam 1.0000 16,348.88 16,348.88

JUMLAH HARGA TENAGA 77,072.93

B. BAHAN

1. Batu (M02) M3 1.1000 126,096.60 138,706.26


2. Semen (PC) (M12) zak 196.0000 1,260.97 247,149.34
3. Pasir (M01) M3 0.4527 124,295.22 56,267.78
4. Bahan bantu Ls 1.000 0.00 0.00

JUMLAH HARGA BAHAN 442,123.37

C. PERALATAN

1. Conc. Mixer (E06) jam 0.1406 54,939.82 7,722.46


2. Wtr Tank Truck (E22) jam 0.0266 195,023.40 5,181.04
3. Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 13,403.51

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 532,599.81


E. OVERHEAD & PROFIT 10.0 % x D 53,259.98
F. HARGA SATUAN PEKERJAAN ( D + E ) 585,859.79
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-231

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 2.3 (1)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 cm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 4.0000 9,342.11 37,368.45


2. Tukang (L02) jam 1.6000 11,677.80 18,684.48
3. Mandor (L03) jam 0.8000 16,348.88 13,079.10

JUMLAH HARGA TENAGA 69,132.03

B. BAHAN

1. Gorong2 Beton Bertulang M1 1.0000 763,064.57 763,064.57


Dia. Dlm 50 Cm
2 Timb. Pilihan (M01) M3 0.7531 134,324.52 101,153.42

JUMLAH HARGA BAHAN 864,217.99

C. PERALATAN

1. Tamper (E25) jam 0.2268 35,140.60 7,970.70


2. Dump Truck (E08) jam 0.1019 197,879.12 20,166.45
3. Alat Bantu Ls 1.0000 5,627.00 5,627.00

JUMLAH HARGA PERALATAN 33,764.15

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 967,114.17


E. OVERHEAD & PROFIT 10.0 % x D 96,711.42
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,063,825.59
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-232

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 2.3 (2)
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 50 - 70 cm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.6000 9,342.11 52,315.83


2. Tukang (L02) jam 1.6000 11,677.80 18,684.48
3. Mandor (L03) jam 0.8000 16,348.88 13,079.10

JUMLAH HARGA TENAGA 84,079.41

B. BAHAN

1. Gorong2 Beton Bertulang


Dia. Dlm 50-70 Cm M 1.0000 763,064.57 763,064.57
2. Timb. Pilihan (M01) M3 1.6576 87,366.93 144,819.42

JUMLAH HARGA BAHAN 907,883.99

C. PERALATAN

1. Tamper (E25) Jam 0.4993 35,140.60 17,544.90


2. Dump Truck (E08) Jam 0.5221 197,879.12 103,310.39
3. Alat Bantu Ls 1.0000 5,000.00 5,000.00

JUMLAH HARGA PERALATAN 125,855.28

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,117,818.69


E. OVERHEAD & PROFIT 10.0 % x D 111,781.87
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,229,600.56
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-233

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 2.3 (3) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Gorong 2x Pipa Btn Bertl. Dia Dlm 70 - 100 cmTOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M' % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 10.6667 9,342.11 99,649.20


2. Tukang (L02) Jam 1.3333 11,677.80 15,570.40
3. Mandor (L03) Jam 1.3333 16,348.88 21,798.50

JUMLAH HARGA TENAGA 137,018.11

B. BAHAN

1. Gorong2 Beton Bertulang


Dia. Dlm 75-120 Cm m1 1.0000 1,139,192.71 1,139,192.71
2. Timb. Pilihan (M01) M3 1.6174 147,756.97 238,982.13

JUMLAH HARGA BAHAN 1,378,174.84

C. PERALATAN

1. Tamper (E25) Jam 0.4872 35,140.60 17,119.40


2. Dump Truck (E08) Jam 0.5830 197,879.12 115,358.96
3. Alat Bantu Ls 1.0000 26,496.00 26,496.00

JUMLAH HARGA PERALATAN 158,974.36

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,674,167.31


E. OVERHEAD & PROFIT 10.0 % x D 167,416.73
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,841,584.04
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
MULIR STANDAR UNTUK
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
ISA MASING-MASING HARGA SATUAN

BATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1

JUMLAH
HARGA
(Rp.)
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
ap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

aran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
MULIR STANDAR UNTUK
ISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)
ap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

aran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. : 3.1 (1)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Cara Manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -

II. URUTAN KERJA


1 Tanah yang dipotong umumnya berada disisi jalan
2 Penggalian dilakukan dengan menggunakan Excavator
3 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
4 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 3.00 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -

Waktu siklus Ts1 menit


- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3/Jam


Ts1 x Fh

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0535 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2 menit
- Waktu tempuh isi = (L : v1) x 60 T1 6.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 4.50 menit
- Muat = (V : Q1) x 60 T3 10.00 menit
- Lain-lain T4 2.00 menit
Ts2 22.50 menit
Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (1)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 7.38 M3/Jam


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 (E08) 0.1355 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang

3. TENAGA
Produksi menentukan : Asumsi Q1 4.00 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 32.00 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.0000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.2500 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 55,101.65 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 14 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 3.1 (2)
JENIS PEKERJAAN : Galian Batu
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -

II. URUTAN KERJA


1 Cadas yg dipotong umumnya berada disisi jalan
2 Penggalian dilakukan dengan menggunakan Compresor
dan Jack Hammer, dimuat ke dlm Truk dengan Loader.
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh : L 3.00 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. COMPRESSOR, JACK HAMMER dan LOADER
Produksi per jam Q1 5.00 M3 / Jam

Koefisien Alat / m3 = 1 : Q1 (E05/26) 0.2000 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts1 menit
- Waktu tempuh isi = (L : v1) x 60 T1 6.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 4.50 menit
- Muat = (V : Q1) x 60 T3 10.00 menit
- Lain-lain T4 2.00 menit
Ts1 22.50 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 7.38 M3 / Jam


Fk x Ts1

Koefisien Alat / m3 = 1 : Q2 (E08) 0.1355 Jam

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (2)
JENIS PEKERJAAN : Galian Batu
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Pahat / Tatah = 2 buah
- Palu Besar = 2 buah

3. TENAGA
Produksi menentukan : JACK HAMMER Q1 5.00 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 40.00 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.8000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.2000 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 134,278.53 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : - M3
ITEM PEMBAYARAN NO. : 3.1 (3)
JENIS PEKERJAAN : Galian Struktur Kedalaman 0-2 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fh 1.20 -
6 Pengurugan kembali (backfill) untuk struktur Uk 50.00 %/M3

II. METHODE PELAKSANAAN


1 Tanah yang dipotong berada disekitar lokasi
2 Penggalian dilakukan dengan menggunakan alat
Excavator
3 Bulldozer mengangkut/mengusur hasil galian ke tempat
pembuangan di sekitar lokasi pekerjaan L 0.0750 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Urugan Pilihan (untuk backfill) = Uk x 1M3 (EI-322) 0.50 M3

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Faktor kedalaman Fd 0.80 -
Berat isi material Bim 0.85 -

Waktu siklus
- Menggali / memuat Te1 0.50 menit
- Lain-lain Te2 0.25 menit
Te 0.75 menit

Kap. Prod. / jam = V x Fb x Fa x Fd x Bim x 60 Q1 16.93 M3/Jam


Te x Fh

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0591 Jam

2.a. BULLDOZER (E04)


Faktor blade Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Kecepatan maju F 3.00 Km/Jam
Kecepatan mundur R 4.00 Km/Jam
Lebar Blade B 3.00 M
` Tinggi blade H 1.20 M
Jarak Gusur L 75.00 M

Volume 1 kali gusur = H^2 x B x Fb V 3.89 M3

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (3)
JENIS PEKERJAAN : Galian Struktur Kedalaman 0-2 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Waktu Siklus
- Maju = (L x 60) / (F x 1000) Tb1 1.50 menit
- Mundur = (L x 60) / (R x 1000) Tb2 1.13 menit
- Lain-lain Tb3 0.15 menit
Tb 2.78 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 58.14 M3 / Jam


Tb x Fh

Koefisien Alat / M3 = 1 : Q2 (E04) 0.0172 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Pacul = 2 buah
- Sekop = 2 buah

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 16.93 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 135.46 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.2362 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0591 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 93,822.91 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : Hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 3.1 (4)
JENIS PEKERJAAN : Galian Struktur Kedalaman 2-4 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fh 1.20 -
6 Pengurugan kembali (backfill) untuk struktur Uk 50.00 %/M3

II. METHODE PELAKSANAAN


1 Tanah yang dipotong berada disekitar jembatan
2 Penggalian dilakukan dengan menggunakan alat
Excavator
3 Bulldozer mengangkut/mengusur hasil galian ke tempat
pembuangan di sekitar lokasi pekerjaan L 0.0750 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Urugan Pilihan (untuk backfill) = Uk x 1M3 (EI-322) 0.50 M3

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Faktor kedalaman Fd 0.65 -
Berat isi material Bim 0.85 -

Waktu siklus
- Menggali / memuat Te1 0.55 menit
- Lain-lain Te2 0.25 menit
Te 0.80 menit

Kap. Prod. / jam = V x Fb x Fa x Fd x Bim x 60 Q1 12.90 M3/Jam


Te x Fh

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0775 Jam

2.a. BULLDOZER (E04)


Faktor blade Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Kecepatan maju F 3.00 Km/Jam
Kecepatan mundur R 4.00 Km/Jam
Lebar Blade B 3.00 M
` Tinggi blade H 1.20 M
Jarak Gusur L 75.00 M

Volume 1 kali gusur = H^2 x B x Fb V 3.89 M3

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (4)
JENIS PEKERJAAN : Galian Struktur Kedalaman 2-4 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Waktu Siklus
- Maju = (L x 60) / (F x 1000) Tb1 1.50 menit
- Mundur = (L x 60) / (R x 1000) Tb2 1.13 menit
- Lain-lain Tb3 0.15 menit
Tb 2.78 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 58.14 M3 / Jam


Tb x Fh

Koefisien Alat / M3 = 1 : Q2 (E04) 0.0172 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Pacul = 2 buah
- Sekop = 2 buah

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 12.90 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 103.18 M3
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.7753 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0775 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 103,348.42 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 1,267.61 M3

ITEM PEMBAYARAN NO. : 3.1 (5)


JENIS PEKERJAAN : Galian Struktur Kedalaman 4-6 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fh 1.20 -

II. METHODE PELAKSANAAN


1 Tanah / batu yang dipotong berada disekitar jembatan
2 Penggalian dilakukan dengan mgenggunakan alat
Excavator
3 Bulldozer mengankut/mengusur hasil galian ke tempat
pembuangan dilokasi sekitar jembatan L 0.0750 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Faktor kedalaman Fd 0.65 -
Berat isi material Bim 0.85 -

Waktu siklus
- Menggali / memuat Te1 0.65 menit
- Lain-lain Te2 0.25 menit
Te 0.90 menit

Kap. Prod. / jam = V x Fb x Fa x Fd x Bim x 60 Q1 11.46 M3/Jam


Te x Fh
Koefisien Alat / M3 = 1 : Q1 (E10) 0.0872 Jam

2.a. BULLDOZER (E04)


Faktor blade Fb 0.90 -
Faktor efisiensi alat Fa 0.75 -
Kecepatan maju F 3.00 Km/Jam
Kecepatan mundur R 4.00 Km/Jam
Lebar Blade B 3.00 M
` Tinggi blade H 1.20 M
Jarak Gusur L 75.00 M

Volume 1 kali gusur = H^2 x B x Fb V 3.89 M3

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (5)
JENIS PEKERJAAN : Galian Struktur Kedalaman 4-6 M
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Waktu Siklus
- Maju = (L x 60) / (F x 1000) Tb1 1.50 menit
- Mundur = (L x 60) / (R x 1000) Tb2 1.13 menit
- Lain-lain Tb3 0.15 menit
Tb 2.78 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 52.54 M3 / Jam


Tb x Fh

Koefisien Alat / M3 = 1 : Q2 (E04) 0.0190 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Pacul = 2 buah
- Sekop = 2 buah

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 11.46 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 91.72 M3
Kebutuhan tenaga :
- Pekerja P 12.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 1.0467 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0872 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 46,125.72 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 1,426.06 M3
ITEM PEMBAYARAN NO. : 3.2 (1)
JENIS PEKERJAAN : Timbunan Biasa dari selain Galian Sumber Bahan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Tebal hamparan padat t 0.20 M

II. URUTAN KERJA


1 Whell Loader memuat ke dalam Dump Truck
2 Dump Truck mengangkut ke lapangan dengan jarak
quari ke lapangan L 5.00 Km
3 Material dihampar dengan menggunakan Motor Grader
4 Hamparan material disiram air dengan Watertank Truck
(sebelum pelaksanaan pemadatan) dan dipadatkan
dengan menggunakan Vibro Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Material timbunan = 1 x Fk (M08) 1.20 M3

2. ALAT
2.a. WHELL LOADER (E15)
Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1 menit
- Muat T1 1.00 menit
- Lain-lain T2 1.00 menit
Ts1 2.00 menit

Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1

Koefisienalat / M3 = 1 : Q1 (E15) 0.0357 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktusiklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 10.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 7.50 menit
- Lain-lain T3 1.00 menit
Ts2 18.50 menit

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.2 (1)
JENIS PEKERJAAN : Timbunan Biasa dari selain Galian Sumber Bahan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 8.97 M3


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 (E08) 0.1114 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar Efektif kerja Blade b 2.40 M
Faktor Efisiensi Alat Fa 0.83 -
Kecepatan rata-rata alat v 5.00 Km / Jam
Jumlah lintasan n 5 lintasan
Waktu siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.60 menit
- Lain-lain T2 0.50 menit
Ts3 1.10 menit

Kapasitas Produksi / Jam = Lh x b x t x Fa x 60 Q3 217.31 M3


n x Ts3

Koefisien Alat / M3 = 1 : Q3 (E13) 0.0046 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 4.00 Km / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam (v x 1000) x b x t x Fa Q4 132.80 M3


n

Koefisien Alat / M3 = 1 : Q4 (E19) 0.0075 Jam

2.e. WATER TANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 material padat Wc 0.07 M3
Pengisian Tangki / jam n 3.00 kali
Faktor efisiensi alat Fa 0.83 -

Kapasitas Produksi / Jam = V x n x Fa Q5 142.29 M3


Wc

Koefisien Alat / M3 = 1 : Q5 (E23) 0.0070 Jam


2.f. ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop = 3 buah

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.2 (1)
JENIS PEKERJAAN : Timbunan Biasa dari selain Galian Sumber Bahan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

3. TENAGA
Produksi menentukan : WHELL LOADER Q1 28.01 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 224.10 M3
Kebutuhan tenaga :
- Pekerja P 6.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.2142 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0357 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 116,798.57 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 3.2 (2)
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Tebal hamparan padat t 0.20 M

II. URUTAN KERJA


1 Whell Loader memuat ke dalam Dump Truck
2 Dump Truck mengangkut ke lapangan dengan jarak
basecamp/pool ke lapangan L 1.44 Km
3 Material dihampar secara manual
4 Hamparan material disiram air dengan Watertank Truck
(sebelum pelaksanaan pemadatan) dan dipadatkan
dengan menggunakan Vibro Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Material pilihan = 1 x Fk (M09) 1.20 M3

2. ALAT
2.a. WHELL LOADER (E15)
Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1 menit
- Muat T1 1.00 menit
- Lain-lain T2 1.00 menit
Ts1 2.00 menit

Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1

Koefisienalat / M3 = = 1 : Q1 (E15) 0.0357 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 Km / Jam
Kecepatan rata-rata kosong v2 40.00 Km / Jam
Waktusiklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 2.88 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 2.16 menit
- Lain-lain T3 1.00 menit
Ts2 6.04 menit

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.2 (2)
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 27.48 M3


Fk x Ts2

Koefisien Alat / m3 = 1 : Q2 (E08) 0.0364 Jam

2.c. VIBRO ROLLER (E19)


Kecepatan rata-rata alat v 1.00 Km / jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam (v x 1000) x b x t x Fa Q4 24.90 M3


n

Koefisien Alat / m3 = 1 : Q4 (E19) 0.0402 Jam

2.d. WATER TANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 material padat Wc 0.07 M3
Pengisian Tangki / jam n 1.00 kali
Faktor efisiensi alat Fa 0.83 -

Kapasitas Produksi / Jam = V x n x Fa Q5 47.43 M3


Wc

Koefisien Alat / m3 = 1 : Q5 (E23) 0.0211 Jam

2.e. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop = 3 buah

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.2 (2)
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

3. TENAGA
Produksi menentukan : Penghamparan Manual Q1 28.01 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 224.10 M3
Kebutuhan tenaga :
- Pekerja P 6.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.2142 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0357 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 147,756.97 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 4.71 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 1,055.00 M3
ITEM PEMBAYARAN NO. : 3.1 (8)
JENIS PEKERJAAN : Galian Beraspal Tanpa Cold Milling Machine
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan dengan alat
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : rusak
4 Jam kerja efektif per-hari Tk 8.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -

II. URUTAN KERJA


1 permukaan aspal yg dipotong umumnya berada disepanjang jalan
2 Penggalian dilakukan dengan menggunakan Compresor
dan Jack Hammer, dimuat ke dlm Truk secara manual
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh : L 3.00 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. COMPRESSOR, JACK HAMMER
Produksi per jam Q1 3.32 M3 / Jam
v 4.00 M3 / Jam
fa 0.83
Koefisien Alat / m3 = 1 : Q1 (E05/26) 0.3012 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts1 menit
- Waktu tempuh isi = (L : v1) x 60 T1 6.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 4.50 menit
- Muat = (V : 2Q1) x 60 T3 36.14 menit
- Lain-lain T4 1.00 menit
Ts1 47.64 menit
Kapasitas Produksi / Jam = V x Fa x 60 Q2 3.48 M3 / Jam
Fk x Ts1

Koefisien Alat / m3 = 1 : Q2 (E08) 0.2870 Jam

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.1 (8)
JENIS PEKERJAAN : Galian Beraspal Tanpa Cold Milling Machine
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Pahat / Tatah = 2 buah
- Palu Besar = 2 buah

3. TENAGA
Produksi menentukan : JACK HAMMER Q1 3.32 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 26.56 M3
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 3.0120 Jam
- Mandor = (Tk x M) : Qt (L03) 0.3012 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 131,144.49 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 3.3
JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilaksanakan pada tanah galian yang disiapkan
untuk penghamparan lapis pondasi
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan Tk 8.00 Jam
4 Kondisi jalan : jelek/ belum padat
5 Jam kerja efektif per- hari

II. URUTAN KERJA


1 Pekerja meratakan permukaan galian
2 Vibro Roller memadatkan permukaan yang telah dipotong atau
diratakan oleh Pekerja
3 Sekelompok pekerja akan membantu meratakan badan jalan
dengan alat bantu.

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Tidak diperlukan bahan/ material

2. ALAT
2.a. MOTOR GRADER (E13)
Panjang hamparan Lh 50.00 M
Lebar Efektif kerja Blade b 2.40 M
Faktor Efisiensi Alat Fa 0.83 -
Kecepatan rata-rata alat v 5.00 Km / Jam
Jumlah lintasan n 4 lintasan
Waktu siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.60 menit
- Lain-lain T2 0.50 menit
Ts3 1.10 menit

Kapasitas Produksi / Jam = Lh x b x Fa x 60 Q3 1,358.18 M2


n x Ts3

Koefisien Alat / M2 = 1 : Q3 (E13) 0.0007 Jam

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 3.3
JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.b. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 4.00 Km / Jam
Lebar efektif pemadatan b 0.80 M
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam (v x 1000) x b x Fa Q4 442.67 M2


n

Koefisien Alat / M2 = 1 : Q4 (E19) 0.0023 Jam

2.f. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Cangkul = 3 buah
- Sekop = 3 buah
3. TENAGA
Produksi menentukan : Asumsi Q 50.00 M2/Jam
Produksi Galian / hari = Tk x Q Qt 400.00 M2
Kebutuhan tenaga :
- Pekerja P 6.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M2 :
- Pekerja = (Tk x P) : Qt (L01) 0.1200 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0200 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,951.33 / M2

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0 hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-311

KETERANGAN
Berlanjut ke halaman berikut
Analisa EI-311

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-312

KETERANGAN

(E05/26/15)
Berlanjut ke halaman berikut
Analisa EI-312

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-314

KETERANGAN
Loose

Berlanjut ke halaman berikut


Analisa EI-314

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-315

KETERANGAN
Loose

Berlanjut ke halaman berikut


Analisa EI-315

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-316

KETERANGAN
Loose

Berlanjut ke halaman berikut


Analisa EI-316

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-321

KETERANGAN

Borrow Pit
Berlanjut ke halaman berikut
Analisa EI-321

Lanjutan

KETERANGAN

Baik
Lump Sump

Berlanjut ke halaman berikut


Analisa EI-321

Lanjutan

KETERANGAN
Analisa EI-322

KETERANGAN
Berlanjut ke halaman berikut
Analisa EI-322
Lanjutan

KETERANGAN

Lump Sump
Berlanjut ke halaman berikut
Analisa EI-322

Lanjutan

KETERANGAN

( dari Dump
Truck )
Analisa EI-312

KETERANGAN

(E05/26/15)
Berlanjut ke halaman berikut
Analisa EI-312

Lanjutan

KETERANGAN

Lump Sump
Analisa EI-3.3

KETERANGAN

Berlanjut ke halaman berikut


Analisa EI-321

Lanjutan

KETERANGAN
Analisa EI-311

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI PERKIRAAN VOL. PEK. :
ITEM PEMBAYARAN NO. : 3.1 (1) TOTAL HARGA (Rp.) :
JENIS PEKERJAAN : Galian Biasa % THD. BIAYA PROYEK :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 2.0000 9,342.11


2. Mandor (L03) Jam 0.2500 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Excavator (E10) Jam 0.0000 179,759.91


2. Dump Truck (E08) Jam 0.1355 197,879.12
3. Alat Bantu Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.1 (2) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Galian Batu TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.8000 9,342.11


2. Mandor (L03) Jam 0.2000 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Compressor (E05) Jam 0.2000 163,441.50
2. Jack Hammer (E26) Jam 0.2000 31,900.81
3. Wheel Loader (E15) Jam 0.2000 227,192.50
4. Dump Truck (E08) Jam 0.1355 197,879.12
5 Alat bantu Ls 1.0000 1,113.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.1 (3) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Galian Struktur Kedalaman 0-2 M TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2362 9,342.11


2. Mandor (L03) Jam 0.0591 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

1. Urugan Pilihan (EI-322) M3 0.5000 134,324.52

JUMLAH HARGA BAHAN

C. PERALATAN
1. Excavator (E10) Jam 0.0591 179,759.91
2. Bulldozer (E04) Jam 0.0172 252,475.76
3. Alat bantu Ls 1.0000 150.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.1 (4) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Galian Struktur Kedalaman 2-4 M TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.7753 9,342.11


2. Mandor (L03) Jam 0.0775 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

1. Urugan Pilihan (EI-322) M3 0.5000 134,324.52

JUMLAH HARGA BAHAN

C. PERALATAN
1. Excavator (E10) Jam 0.0775 179,759.91
2. Bulldozer (E04) Jam 0.0172 252,475.76
3. Alat bantu Ls 1.0000 183.00
4.

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.1 (5) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Galian Struktur Kedalaman 4-6 M TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 1.0467 9,342.11


2. Mandor (L03) Jam 0.0872 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Excavator (E10) Jam 0.0872 179,759.91
2. Bulldozer (E04) Jam 0.0190 252,475.76
3. Alat bantu Ls 1.0000 10,242.61
4.
JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-32
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.2 (1)
JENIS PEKERJAAN : Timbunan Biasa dari selain Galian Sumber Bahan
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2142 9,342.11


2. Mandor (L02) Jam 0.0357 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

1. Material timbunan (M08) M3 1.2000 58,544.85

JUMLAH HARGA BAHAN

C. PERALATAN
1. Whell Loader (E15) Jam 0.0357 227,192.50
2. Dump Truck (E08) Jam 0.1114 197,879.12
3. Motor Grader (E13) Jam 0.0046 265,505.74
3. Vibro Roller (E19) Jam 0.0075 173,735.15
4. Water Tanker (E23) Jam 0.0070 195,023.40
5. Alat Bantu ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-32
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 3.2 (2) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Timbunan Pilihan TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2142 9,342.11


2. Mandor (L03) Jam 0.0357 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

1. Material pilihan (M09) M3 1.2000 87,366.93

JUMLAH HARGA BAHAN

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0357 227,192.50
2. Dump Truck (E08) Jam 0.0364 197,879.12
3 Motor Grader (E13) Jam - 265,505.74
4. Vibro Roller (E25) Jam 0.0402 173,735.15
5. Water Tanker (E23) Jam 0.0211 195,023.40
6. Alat Bantu ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI PERKIRAAN VOL. PEK. :
ITEM PEMBAYARAN NO. : 3.1 (8) TOTAL HARGA (Rp.) :
JENIS PEKERJAAN : Galian Beraspal Tanpa Cold Milling Machine % THD. BIAYA PROYEK :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 3.0120 9,342.11


2. Mandor (L03) Jam 0.3012 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Compressor (E05) Jam 0.3012 163,441.50
2. Jack Hammer (E26) Jam 0.3012 31,900.81
3. Dump Truck (E08) Jam 0.1355 197,879.12
4. Alat bantu Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-32
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. :
ITEM PEMBAYARAN NO. : 3.3 TOTAL HARGA (Rp.) :
JENIS PEKERJAAN : Penyiapan Badan Jalan % THD. BIAYA PROYEK :
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1200 9,342.11


2. Mandor (L02) Jam 0.0200 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Motor Grader (E13) Jam - 265,505.74
2. Vibro Roller (E19) Jam 0.0023 100,000.00
3. Alat Bantu ls 1.0000 100.00
3.
4.
5.

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau uk
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-311

FORMULIR STANDAR UNTUK


AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

18,684.23
4,087.22

22,771.44

0.00

0.00
26,820.97
500.00

27,320.97

50,092.41
5,009.24
55,101.65
as jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

tas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-312
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

7,473.69
3,269.78

10,743.47

0.00

32,688.30
6,380.16
45,438.50
26,820.97
0.00

111,327.93

122,071.40
12,207.14
134,278.53
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-314
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

2,206.97
965.56

3,172.53

67,162.26

67,162.26

10,616.58
4,342.18
0.00

14,958.76

85,293.56
8,529.36
93,822.91
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-315
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

7,243.40
1,267.61

8,511.00

67,162.26

67,162.26

13,937.66
4,342.18
0.00

18,279.85

93,953.11
9,395.31
103,348.42
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-316
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

9,778.58
1,426.06

11,204.64

0.00

15,679.87
4,805.35
10,242.61
30,727.83

41,932.47
4,193.25
46,125.72
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-321
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA
(Rp.)

2,000.99
583.63

2,584.62

70,253.82

70,253.82

8,110.40
22,052.79
0.00
1,308.25
1,370.65
500.00

33,342.08

106,180.52
10,618.05
116,798.57
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-322
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

1,055.00
155,883,608.45
1.42

JUMLAH
HARGA
(Rp.)

2,000.99
583.63

2,584.62

104,840.32

104,840.32

8,110.40
7,199.94
0.00
6,977.32
4,111.94
500.00

26,899.59

134,324.52
13,432.45
147,756.97
as jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

tas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-318
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

28,138.89
4,924.36

33,063.25

0.00

49,229.37
9,608.68
26,820.97
500.00

86,159.01

119,222.27
11,922.23
131,144.49
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-321
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

0.00
0.00
0.00

JUMLAH
HARGA
(Rp.)

1,121.05
326.98

1,448.03

0.00

-
225.90
100.00

325.90

1,773.93
177.39
1,951.33
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

n sudah termasuk bahan bakar, bahan habis dipakai dan operator.


uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. : 4.2 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Kasar Ak 60.00 %
- Agregat Halus Ah 40.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaandan dihampar dengan Motor Grader
3 Hamparaan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7200 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.4800 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Mencampur T1 2.00 menit
- Memuat dan lain-lain T2 1.00 menit
Ts1 3.00 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3
Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0535 Jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-lain termasuk menurunkan Agregat T3 3.00 menit
Ts2 69.13 menit
Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 4.2 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

Kap. Prod./jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1= 1 : Q2 (E08) 0.2776 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 Jam

2.d. TANDEM ROLLER (E17)


Kecepatan rata-rata v 3.00 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 56.03 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0178 Jam

2.e. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x n x Fa Q5 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q5 (E23) 0.0211 Jam

2.g. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 4.2 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 18.68 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 149.40 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.4284 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0535 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 330,278.28 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Waktu pelaksanaan : . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls.B (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis Agregat padat t 0.20 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Kasar Ak 65.00 %
- Agregat Halus Ah 35.00 %
- Sirtu St 0.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan pekerja manual
3 Hamparaan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7800 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.4200 M3
- Sirtu = St x 1 M3 x Fk M16 0.0000 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Mencampur T1 2.00 menit
- Memuat dan lain-lain T2 1.00 menit
Ts1 3.00 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3
Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0535 Jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-Lain termasuk memuat dan menurunkan material T3 3.00 menit
Ts2 69.13 menit
Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls.B (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / Jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.2776 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 113.83 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0088 Jam

2.c. TANDEM ROLLER (E17)


Kecepatan rata-rata v 3.00 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q4 74.70 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0134 Jam

2.d. WATER TANKER (E23)


Volume Tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / Jam n 1.00 kali
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = V x n Fa Q5 47.43 M3


Wc

Koefisien Alat / M3 = 1 : Q5 (E23) 0.0211 Jam

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

Berlanjut ke halaman
ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls.B (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

3. TENAGA
Produksi menentukan : Penghamparan Manual Q1 18.68 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 149.40 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.4284 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0535 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 328,220.80 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Waktu pelaksanaan 0.676037483 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 101.00 M3
ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls B (Manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Kasar Ak 85.00 %
- Agregat Halus Ah 15.00 %
- Sirtu St 0.00 %
II. URUTAN KERJA
1 Dump Truck mengangkut Agregat ke lokasi dari Quarry
dalam Dump Truck di Base Camp
2 Agregat dihampar secara manual dengan Tenaga Kerja
3 Agregat yang telah dihampar dipadatkan dengan
Tamper
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agregat Kasar M3
- Agregat Halus = Ak x 1 M3 x Fk M03 1.0200 M3
- Sirtu = Ah x 1 M3 x Fk M04 0.1800 M3
2. ALAT = St x 1 M3 x Fk M16 0.0000
2.a. DUMP TRUCK (E09)
Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-Lain termasuk memuat dan menurunkan material T3 3.00 menit
Ts2 69.13 menit
Kap. Prod. / Jam = V x Fa x 60 Q2 3.60 M3
Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.2776 Jam

TAMPER (E17)
Kecepatan rata-rata v 1.00 KM / Jam
Lebar efektif pemadatan b 0.50 M
Jumlah lintasan n 25.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q4 2.49 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.4016 Jam
ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls B (Manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : TAMPER Q1 2.49 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 19.92 M3
Kebutuhan tenaga :
- Pekerja P 5.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.0080 Jam
- Mandor = (Tk x M) : Qt (L03) 0.4016 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 340,465.00 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Waktu pelaksanaan : . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-421

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus -
memenuhi Spec.

Pemuatan ringan
Berlanjut ke halaman berikut
Analisa EI-421

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

3 x pp

Lump Sum
Berlanjut ke halaman berikut
Analisa EI-421

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Analisa EI-422

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi

Pemuatan ringan
Berlanjut ke halaman berikut
Analisa EI-422

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

3 x pp
Berlanjut ke halaman berikut
Analisa EI-422

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

( dari DT )
Analisa EI-422

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi
URAIAN ANALISA HARGA SATUAN
Lanjutan

KETERANGAN
Analisa EI-421

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LIN
LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 4.2 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.4284 9,342.11 4,001.98


2. Mandor (L03) Jam 0.0535 16,348.88 875.44

JUMLAH HARGA TENAGA 4,877.42

B. BAHAN

1. Agregat Kasar (M03) M3 0.7200 166,627.65 119,971.91


2. Agregat Halus (M04) M3 0.4800 175,634.55 84,304.58

JUMLAH HARGA BAHAN 204,276.49

C. PERALATAN

1 Wheel Loader (E15) Jam 0.0535 227,192.50 12,165.60


2 Dump Truck (E09) Jam 0.2776 246,739.58 68,501.45
3 Motor Grader (E13) Jam 0.0117 265,505.74 3,110.01
4 Tandem Roller (E17) Jam 0.0178 123,819.90 2,210.08
5 Water Tanker (E23) Jam 0.0211 195,023.40 4,111.94
6. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 91,099.07

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 300,252.98


E. OVERHEAD & PROFIT 10.0 % x D 30,025.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 330,278.28
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-422

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : KM.BDG. 93+183-KM.BDG.94+623


LOKASI : JAWA BARAT / KOTA SUKABUMI
PROP / KAB / KOTA JAWA BARAT / SUKABUMI PERKIRAAN VOL. PEK. : 101.00
ITEM PEMBAYARAN NO. : 4.2 (2) TOTAL HARGA (Rp.) : 33,150,300.80
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls.B (Mekanik) % THD. BIAYA PROYEK : 0.30
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.4284 9,342.11 4,001.98


2. Mandor (L03) Jam 0.0535 16,348.88 875.44

JUMLAH HARGA TENAGA 4,877.42

B. BAHAN

1. Agregat Kasar (M03) M3 0.7800 166,627.65 129,969.57


2. Agregat Halus (M04) M3 0.4200 175,634.55 73,766.51
3. Sirtu (M16) M3 0.0000 108,983.49 0.00

JUMLAH HARGA BAHAN 203,736.08

C. PERALATAN

1 Wheel Loader (E15) Jam 0.0535 227,192.50 12,165.60


2 Dump Truck (E09) Jam 0.2776 246,739.58 68,501.45
3 Motor Grader (E13) Jam 0.0088 265,505.74 2,332.51
4 Tandem Roller (E17) Jam 0.0134 123,819.90 1,657.56
5 Water Tanker (E23) Jam 0.0211 195,023.40 4,111.94
6. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 89,769.05

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 298,382.55


E. OVERHEAD & PROFIT 10.0 % x D 29,838.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 328,220.80
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-422

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LIN
LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 4.2 (2) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls B (Manual) TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 2.0080 9,342.11 18,759.26


2. Mandor (L03) Jam 0.4016 16,348.88 6,565.81

JUMLAH HARGA TENAGA 25,325.08

B. BAHAN

1. Agregat Kasar (M03) M3 1.0200 166,627.65 169,960.20


2. Agregat Halus (M04) M3 0.1800 175,634.55 31,614.22
3. Sirtu (M16) M3 0.0000 108,983.49 0.00

JUMLAH HARGA BAHAN 201,574.42

C. PERALATAN

1 Wheel Loader (E15) Jam #REF! 426,928.50 #REF!


1 Dump Truck (E09) Jam 0.2776 246,739.58 68,501.45
2 Tamper (E13) Jam 0.4016 35,140.60 14,112.69

6 Alat Bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN 82,614.14

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 309,513.63


E. OVERHEAD & PROFIT 10.0 % x D 30,951.36
F. HARGA SATUAN PEKERJAAN ( D + E ) 340,465.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 56.00 %
- Agregat Halus Ah 44.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur dan memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.6720 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.5280 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 2.00 menit
- Memuat dan lain-lain T2 1.00 menit
Ts1 3.00 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3
Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0535 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/jam
Kecepatan rata-rata kosong v2 40.00 KM/jam
Waktu Siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-Lain termasuk memuat dan menurunkan material T3 3.00 menit
Ts2 69.13 menit

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E09) 0.2776 jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap. Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata alat v 3.00 KM/jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q4 56.03 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0178 jam

2.e. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -
Kap. Prod. / jam = V x n x Fa Q6 47.43 M3
Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 jam

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (Mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.f. ALAT BANTU


Diperlukan :
- Kereta dorong = 2 buah.
- Sekop = 3 buah.
- Garpu = 2 buah.

3. TENAGA
Produksi menentukan : Asumsi Q 18.68 M3/jam
Produksi agregat / hari = Tk x Q Qt 149.40 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.4284 jam
- Mandor = (Tk x M) : Qt (L03) 0.0535 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 331,733.89 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0 hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Kasar Ak 60.00 %
- Agregat Halus Ah 40.00 %

II. URUTAN KERJA


1 Dump Truck mengangkut Agregat ke lokasi dari Quarry
dalam Dump Truck di Base Camp
2 Agregat dihampar secara manual dengan Tenaga Kerja
3 Agregat yang telah dihampar dipadatkan dengan
Tamper
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7200 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.4800 M3

2. ALAT
2.a. DUMP TRUCK (E09)
Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-Lain termasuk memuat dan menurunkan material T3 3.00 menit
Ts2 69.13 menit
Kap. Prod. / Jam = V x Fa x 60 Q2 3.60 M3
Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.2776 Jam

TAMPER (E17)
Kecepatan rata-rata v 1.00 KM / Jam
Lebar efektif pemadatan b 0.50 M
Jumlah lintasan n 25.00 lintasan
Faktor Efisiensi alat Fa 0.75 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q4 2.25 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.4444 Jam
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : TAMPER Q1 2.25 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 18.00 M3
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 4.4444 Jam
- Mandor = (Tk x M) : Qt (L03) 0.4444 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 377,410.42 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Waktu pelaksanaan : . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 5.1 (2)
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis agregat padat t 0.20 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 65.00 %
- Agregat Halus Ah 35.00 %
- Sirtu St 0.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur dan memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7800 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.4200 M3
- Sirtu = St x 1 M3 x Fk M16 0.0000 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 2.00 menit
- Memuat dan lain-lain T2 1.00 menit
Ts1 3.00 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 18.68 M3
Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0535 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/jam
Kecepatan rata-rata kosong v2 40.00 KM/jam
Waktu Siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-Lain termasuk memuat dan menurunkan material T3 3.00 menit
Ts2 69.13 menit

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.1 (2)
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 - 0.2776 jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap. Prod. / jam = Lh x b x t x Fa x 60 Q3 113.83 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0088 jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata alat v 3.00 KM/jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q4 74.70 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0134 jam

2.e. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -
Kap. Prod. / jam = V x n x Fa Q6 47.43 M3
Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 jam

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.1 (2)
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (mekanik)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.f. ALAT BANTU


Diperlukan :
- Kereta dorong = 2 buah.
- Sekop = 3 buah.
- Garpu = 2 buah.

3. TENAGA
Produksi menentukan : Asumsi Q 18.68 M3/jam
Produksi agregat / hari = Tk x Q Qt 149.40 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.4284 jam
- Mandor = (Tk x M) : Qt - 0.0535 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 328,955.83 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 5.1 (2)
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis Agregat padat t 0.20 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam

9 Proporsi Campuran : - Agregat Kasar Ak 65.00 %


- Agregat Halus Ah 35.00 %
- Sirtu St 0.00 %
II. URUTAN KERJA
1 Dump Truck mengangkut Agregat ke lokasi dari Quarry
dalam Dump Truck di Base Camp
2 Agregat dihampar secara manual dengan Tenaga Kerja
3 Agregat yang telah dihampar dipadatkan dengan
Tamper
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7800 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.4200 M3
- Sirtu = St x 1 M3 x Fk M16 0.0000 M3
2. ALAT
2.a. DUMP TRUCK (E09)
Kapasitas bak V 4.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-lain termasuk menurunkan material T3 3.00 menit
Ts2 69.13 menit
Kap. Prod. / Jam = V x Fa x 60 Q2 2.40 M3
Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.4164 Jam

TAMPER (E17)
Kecepatan rata-rata v 1.00 KM / Jam
Lebar efektif pemadatan b 0.50 M
Jumlah lintasan n 25.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q4 3.32 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.3012 Jam

ITEM PEMBAYARAN NO. : 5.1 (2)


JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (manual)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA S

No. URAIAN KODE KOEF. SATUAN

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : TAMPER Q1 3.32 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 26.56 M3
Kebutuhan tenaga :
- Pekerja P 20.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 6.0241 Jam
- Mandor = (Tk x M) : Qt (L03) 0.3012 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 416,102.40 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Waktu pelaksanaan : . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

ITEM PEMBAYARAN NO. : 5.2 (1)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 40.0 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam

II. URUTAN KERJA


1 Wheel Loader memuat Agregat ke dalam Dump
Tuck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaandan dihampar dengan Motor Grader
3 Hamparaan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Material Agregat Kelas C hasil produksi di Base Camp
Setiap 1 M3 Agregat padat diperlukan : 1 x Fk (M28) 1.20 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Muat T1 0.25 menit
- Lain-lain T2 0.25 menit
Ts1 0.50 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 112.05 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0089 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 53.33 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 40.00 menit
- Lain-lain T3 5.00 menit
Ts2 98.33 menit

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.2 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod./jam = V x Fa x 60 Q2 1.69 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.5924 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 Jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata v 2.50 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 Jam

2.f. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 Jam

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.2 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.g. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 112.05 M3 / Jam
Produksi Agregat / hari = Tk x Q1 Qt 896.40 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0625 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0089 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 288,564.39 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

ITEM PEMBAYARAN NO. : 5.2 (2)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 40.00 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 Jam

II. URUTAN KERJA


1 Wheel Loader memuat Agregat ke dalam Dump
Tuck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaandan dihampar dengan Motor Grader
3 Hamparaan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Material Agregat Kelas C2 hasil produksi di Base Camp
Setiap 1 M3 Agregat padat diperlukan : 1 x Fk (M29) 1.20 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Muat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 56.03 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0178 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 53.33 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 40.00 menit
- Lain-lain T3 5.00 menit
Ts2 98.33 menit

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod./jam = V x Fa x 60 Q2 1.69 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.5924 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 Jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata v 2.50 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 Jam

2.f. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 Jam

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.2 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.g. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 56.03 M3 / Jam
Produksi Agregat / hari = Tk x Q1 Qt 448.20 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1249 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0178 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. #VALUE! / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

ITEM PEMBAYARAN NO. : 5.4(1)


JENIS PEKERJAAN : Semen Untuk Pond. Tnh. Semen
SATUAN PEMBAYARAN : TON URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 40.00 Km
5 Jam kerja efektif per-hari Tk 8.00 Jam
6 Semen diangkut dari Base Camp ke lapangan
dengan menggunakan Dump Truck
7 Satu hari dapat diselesaikan hamparan Soil Cement
sepanjang Ls 400.00 M
8 Faktor hilang Material Fh 1.05 -
9 Tebal hamparan t 0.15 M

II. URUTAN KERJA


1 Dump Truck mengangkut semen dari Base Camp
ke lokasi Pekerjaan
2 Semen diatur/disusun di tempat hamparan
soil/tanah oleh tenaga manusia

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Bahan yang diperlukan / ton = (1 x Fh x 1000) (M12) 1,050.00 Kg

2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas bak V 6.00 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 Km / Jam
Kecepatan rata-rata kosong v2 60.00 Km / Jam
Waktu siklus Ts1
- Waktu tempuh isi = (L : v1) x 60 T1 53.33 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 40.00 menit
- Waktu mengisi T3 40.00 menit
- Waktu bongkar T4 30.00 menit
- Lain-lain T5 10.00 menit
Ts1 173.33 menit

Kapasitas Prod. / jam = V x Fa x 60 Q1 1.64 Ton/Jam


Fh x Ts1

Koefisien Alat / M3 = 1 / Q1 (E08) 0.6091 Jam

3. TENAGA
Lebar Soil Cement b 6.00 M
Kadar semen : Spesifikasi 5.4.3 (1) = ( 3 - 12 ) % s 7.50 %
Berat jenis tanah Bj 1.60 ton / M3
Setiap hari dengan produksi = {(s : 100) x t x b x Ls} x Bj Qt 43.20 Ton

Kebutuhan tenaga :
- Pekerja P 15.00 orang
- Mandor M 1.00 orang

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.4(1)
JENIS PEKERJAAN : Semen Untuk Pond. Tnh. Semen
SATUAN PEMBAYARAN : TON URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Koefisien tenaga / Ton :


- Pekerja = (Tk x P) : Qt (L01) 2.7778 Jam
- Mandor = (Tk x M) : Qt (L03) 0.1852 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,620,873.06 / Ton


6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 Ton

ITEM PEMBAYARAN NO. : 5.4(2)


JENIS PEKERJAAN : Lapis Pondasi Tanah Semen
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jarak rata-rata sumber material ke lokasi pekerjaan L 40.00 Km
5 Jam kerja efektif per-hari Tk 8.00 Jam
6 Harga pembayaran tidak termasuk semen ( semen
dibayar dalam item tersendiri)
7 Satu hari dapat diselesaikan hamparan Soil Cement
sepanjang Ls 400.00 M
8 Faktor kembang material (padat - lepas) Fk 1.20 -
9 Tebal hamparan padat t 0.15 M

II. URUTAN KERJA


1 Whell Loader memuat tanah/material ke dalam
Dump Truck di lokasi sumber bahan
2 Dump Truck mengangkut material ke lokasi pekerjaan
3 Motor Grader menghampar material di lokasi pekerjaan
4 Semen dan material tanah diaduk ditempat dengan
menggunakan Vulvi Mixer
5 Sebelum pemadatan material dibasahi dengan
menggunakan Water Tank Truck
6 Pemadatan dilakukan dengan menggunakan
Vibrator Roller dan Pneumatic Tire Roller
7 Selama pelaksanaan pekerjaan sekelompok pekerja
akan merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Setiap M3 Soil Cement padat diperlukan = 1 x Fk (M08) 1.20 M3

2. ALAT
2.a. WHELL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus : Ts1
- Muat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit

Kap. Prod. / Jam = V x Fb x Fa x 60 Q1 56.03 M3


Fk x Ts1

Koefisien Alat / M3 = 1 / Q1 (E15) 0.0178 Jam

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.4(2)
JENIS PEKERJAAN : Lapis Pondasi Tanah Semen
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 Km / Jam
Kecepatan rata-rata kosong v2 60.00 Km / Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 53.33 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 40.00 menit
- Lain-lain T3 3.00 menit
Ts2 96.33 menit

Kapasitas Prod. / jam = V x Fa x 60 Q2 1.72


Fk x Ts2

Koefisien Alat / M3 = 1 / Q2 (E08) 0.5803 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 100.00 M
Lebar efektif kerja blade b 2.40 M
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 6.00 lintasan
Waktu siklus Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 1.50 menit
- Lain-lain T2 1.00 menit
Ts3 2.50 menit

Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3 119.52 M3


n x Ts3

Koefisien Alat / M3 = 1 / Q3 (E13) 0.0084 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 2.50 Km / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n

Koefisien Alat / M3 = 1 / Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 Km / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.4(2)
JENIS PEKERJAAN : Lapis Pondasi Tanah Semen
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q5 116.72 M3


n

Koefisien Alat / M3 = 1 / Q5 (E18) 0.0086 Jam

2.e. WATER TANK TRUCK (E23)


Volume Tangki air V 4.00 M3
Kebutuhan air / M3 material padat Wc 0.07 M3
Pengisian tanhgki / jam n 3.00 kali
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = V x n x Fa Q6 142.29 M3


Wc

Koefisien Alat / M3 = 1 / Q6 (E23) 0.0070 Jam

2.f. FULVI MIXER (E27)


Kecepatan rata-rata alat v 2.50 Km / Jam
Lebar efektif pemadatan b 1.00 M
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q7 51.88 M3


n

Koefisien Alat / M3 = 1 / Q7 (E27) 0.0193 Jam

2.g. ALAT BANTU


Diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah

3. TENAGA
Produksi menetukan : VIBRATOR ROLLER Q4 46.69 M3/Jam
Produksi Soil Cement / hari = Tk x Q4 Qt 373.50 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1499 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0214 Jam
Berlanjut ke ha
ITEM PEMBAYARAN NO. : 5.4(2)
JENIS PEKERJAAN : Lapis Pondasi Tanah Semen
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 222,740.35 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 5.6 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat dengan CTB
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima di lok. Pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.0 KM
5 Tebal lapis agregat padat t 0.30 M
6 Faktor kembang material (Padat-Lepas) Fk 1.10 -
7 Jam kerja efektif per-hari Tk 8.00 jam
8 Kadar Semen (Spesifikasi) : Ks1 250 Kg/M3
9 Perbandingan Air/Semen Maksimum (Spesifikasi) Wcr 0.00 -
10 Perbandingan Camp. 1.00 : Semen Sm 10.0 %
3.80 : Pasir Ps 38.0 %
5.20 : Kerikil Pecah Kr 52.0 %
11 Berat Jenis Material : 10
- Beton 9.0000 D1 2.40 T/M3
- Semen D2 1.40 T/M3
- Pasir D3 2.00 T/M3
- Kerikil Pecah (Agregat Kasar) D4 2.15 T/M3

II. URUTAN KERJA


1 Agregat, Semen, Air yang sudah melalui proses laboratorium
grading dicampur di plant CTB,
2 Setelah dicampur Kemudian diangkut kedalam dump truck
untuk siap digelar dilapangan dengan alat penghampar
Finisher dan Alat pemadat yang digunakan adalah
Tandem Roller dengan berat 6 – 8 ton dan Tire Roller dengan
berat 10 -12 ton

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Semen (PC) = {Sm x D1 x 1000} x 1.05 (M12) 252.00 Kg
1.b. Pasir Beton = {(Ps x D1) : D3} x 1.05 (M01) 0.4788 M3
1.c. Kerikil Pecah = {(Kr x D1) : D4} x Fk (M03) 0.6385 M3
1.e. Kayu Perancah (M19) 0.0000 M3
1.f Paku (M18) 0.0000 Kg

2. ALAT
2.a. BATCHING PLANT / CONCRETE MIXER (E33)
Kapasitas Alat V 500 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 3.00 menit
- Mengaduk T2 2.00 menit
- Menuang T3 2.00 menit
- Tunggu, dll. T4 3.00 menit
Ts 10.00 menit

Kap. Prod. / jam = V x Fa x 60 Q1 2.490 M3/jam


1000 x Ts

Koefisien Alat / M3 = 1 : Q1 (E06) 0.4016 jam


Berlanjut ke hal.
ITEM PEMBAYARAN NO. : 5.6 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat dengan CTB
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/jam
Kecepatan rata-rata kosong v2 40.00 KM/jam
Waktu Siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 10.00 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 7.50 menit
- Memuat dan lain-lain T3 5.00 menit
Ts2 22.50 menit

Kap. Prod. / jam = V x Fa x 60 Q2 12.07 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E09) 0.0828 jam

2.c. FINISHER (E02)


Kapasitas produksi V 40.00 ton / Jam
Faktor efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x Fa Q5 13.83 M3


D1
Koefisien Alat / M3 = 1 : Q5 (E02) 0.0723 Jam

2.d. TANDEM ROLLER (E17)


Kecepatan rata-rata alat v 3.50 Km / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 6.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod./jam = (v x 1000) x b x t x Fa Q6 174.30 M3


n
Koefisien Alat / M3 = 1 : Q6 (E17) 0.0057 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata v 6.00 KM / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q7 280.13 M3


n
Koefisien Alat / M3 = 1 : Q7 (E18) 0.0036 Jam

Berlanjut ke hal.
ITEM PEMBAYARAN NO. : 5.6 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat dengan CTB
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

2.h. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3. TENAGA
Produksi menentukan : Batching Plant/Concrete Mixer Q1 2.49 M3/Jam
Produksi CTB / hari = Tk x Q1 Qt 19.92 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien Tenaga / M3 :
- Pekerja = (Tk x P) / Qt (L01) 3.2129 Jam
- Mandor = (Tk x M) / Qt (L03) 0.4016 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 644,397.02 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M3
Analisa EI-511

KETERANGAN

Gradasi harus
memenuhi Spec.
Berlanjut ke hal. berikut
Analisa EI-511

Lanjutan

KETERANGAN

3 x pp
Berlanjut ke hal. berikut
Analisa EI-511

Lanjutan

KETERANGAN

Lump Sum
Analisa EI-422

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi
URAIAN ANALISA HARGA SATUAN
Lanjutan

KETERANGAN
Analisa EI-512

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi
Berlanjut ke hal. berikut
Analisa EI-512

Lanjutan

KETERANGAN

3 x pp
Berlanjut ke hal. berikut
Analisa EI-512

Lanjutan

KETERANGAN

Lump Sum
Analisa EI-422

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi
URAIAN ANALISA HARGA SATUAN
Lanjutan

KETERANGAN
Analisa EI-521

KETERANGAN
Agregat lepas

Pemuatan ringan

Berlanjut ke hal. berikut


Analisa EI-521

Lanjutan

KETERANGAN

3 x pp
Berlanjut ke hal. berikut
Analisa EI-521

Lanjutan

KETERANGAN

Lump Sum
Analisa EI-522
KETERANGAN

Agregat lepas

Pemuatan ringan
Berlanjut ke hal. berikut
Analisa EI-522

Lanjutan

KETERANGAN

3 x pp

4 x pp

2 x pp
Berlanjut ke hal. berikut
Analisa EI-522

Lanjutan

KETERANGAN

Lump Sum
Analisa EI-541

KETERANGAN
Berlanjut ke hal. berikut
Analisa EI-541

Lanjutan

KETERANGAN
Analisa EI-542

KETERANGAN
Pemuatan ringan

Berlanjut ke hal. berikut


Analisa EI-542

Lanjutan

KETERANGAN
3 x pp

3 x pp

4 x pp

Berlanjut ke hal. berikut


Analisa EI-542
Lanjutan

KETERANGAN

3 x pp

Lump Sump
Berlanjut ke hal. berikut
Analisa EI-542

Lanjutan

KETERANGAN
Analisa EI-561

KETERANGAN

Berdasarkan
JMF & sesuai
dgn Spesifikasi

Agregat Kasar
Berlanjut ke hal. berikut.
Analisa EI-561

Lanjutan

KETERANGAN

Berlanjut ke hal. berikut.


Analisa EI-561

Lanjutan

KETERANGAN

Lump Sum
Analisa EI-511

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 5.1 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (Mekanik) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.4284 9,342.11 4,001.98


2. Mandor (L03) jam 0.0535 16,348.88 875.44

JUMLAH HARGA TENAGA 4,877.42

B. BAHAN

1. Agregat Kasar (M03) M3 0.6720 166,627.65 111,973.78


2. Agregat Halus (M04) M3 0.5280 175,634.55 92,735.04

JUMLAH HARGA BAHAN 204,708.82

C. PERALATAN
1. Wheel Loader (E15) jam 0.0535 227,192.50 12,165.60
2. Dump Truck (E09) jam 0.2776 246,739.58 68,501.45
3. Motor Grader (E13) jam 0.0117 265,505.74 3,110.01
4. Vibratory Roller (E19) jam 0.0178 173,735.15 3,101.03

5. Water Tanker (E23) jam 0.0211 195,023.40 4,111.94


6. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 91,990.02

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 301,576.26


E. OVERHEAD & PROFIT 10.0 % x D 30,157.63
F. HARGA SATUAN PEKERJAAN ( D + E ) 331,733.89
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-422

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LIN
LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 5.1 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kls. A (manual) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 4.4444 9,342.11 41,520.50


2. Mandor (L03) Jam 0.4444 16,348.88 7,266.17

JUMLAH HARGA TENAGA 48,786.67

B. BAHAN

1. Agregat Kasar (M03) M3 0.7200 166,627.65 119,971.91


2. Agregat Halus (M04) M3 0.4800 175,634.55 84,304.58

JUMLAH HARGA BAHAN 204,276.49

C. PERALATAN

1 Wheel Loader (E15) Jam #REF! 426,928.50 #REF!


1 Dump Truck (E09) Jam 0.2776 246,739.58 68,501.45
2 Tamper (E13) Jam 0.4444 48,455.50 21,535.78

6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 90,037.23

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 343,100.38


E. OVERHEAD & PROFIT 10.0 % x D 34,310.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 377,410.42
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-512
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 5.1 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (mekanik) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.4284 9,342.11 4,001.98


2. Mandor (L03) jam 0.0535 16,348.88 875.44

JUMLAH HARGA TENAGA 4,877.42

B. BAHAN

1. Agregat Kasar (M03) M3 0.7800 166,627.65 129,969.57


2. Agregat Halus (M04) M3 0.4200 175,634.55 73,766.51
3. Sirtu (M16) M3 0.0000 108,983.49 0.00

JUMLAH HARGA BAHAN 203,736.08

C. PERALATAN
1. Wheel Loader (E15) jam 0.0535 227,192.50 12,165.60
2. Dump Truck (E09) jam 0.2776 246,739.58 68,501.45
3. Motor Grader (E13) jam 0.0088 265,505.74 2,332.51
4. Vibratory Roller (E19) jam 0.0134 173,735.15 2,325.77

5. Water Tanker (E23) jam 0.0211 195,023.40 4,111.94


6. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 90,437.26

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 299,050.76


E. OVERHEAD & PROFIT 10.0 % x D 29,905.08
F. HARGA SATUAN PEKERJAAN ( D + E ) 328,955.83
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-521

Analisa EI-422

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LIN
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 5.1 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, (manual) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 6.0241 9,342.11 56,277.79


2. Mandor (L03) Jam 0.3012 16,348.88 4,924.36

JUMLAH HARGA TENAGA 61,202.15

B. BAHAN

1. Agregat Kasar (M03) M3 0.7800 166,627.65 129,969.57


2. Agregat Halus (M04) M3 0.4200 175,634.55 73,766.51
3. Sirtu (M16) M3 0.0000 108,983.49 0.00

JUMLAH HARGA BAHAN 203,736.08

C. PERALATAN

1 Wheel Loader (E15) Jam #REF! 426,928.50 #REF!


1 Dump Truck (E09) Jam 0.4164 246,739.58 102,752.17
2 Tamper (E13) Jam 0.3012 35,140.60 10,584.52
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 113,336.69

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 378,274.91


E. OVERHEAD & PROFIT 10.0 % x D 37,827.49
F. HARGA SATUAN PEKERJAAN ( D + E ) 416,102.40
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.2 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0625 9,342.11 583.62


2. Mandor (L03) Jam 0.0089 16,348.88 145.91

JUMLAH HARGA TENAGA 729.53

B. BAHAN
1. Agregat Kelas C1 (M28) M3 1.2000 108,983.49 130,780.19

JUMLAH HARGA BAHAN 130,780.19

C. PERALATAN

1. Wheel Loader (E15) Jam 0.0089 227,192.50 2,027.60


2. Dump Truck (E08) Jam 0.5924 197,879.12 117,217.55
3. Motor Grader (E13) Jam 0.0117 265,505.74 3,110.01
4. Vibratory Roller (E19) Jam 0.0214 173,735.15 3,721.23
5. P. Tyre Roller (E18) Jam 0.0043 147,815.38 633.21
6. Water Tanker (E23) Jam 0.0211 195,023.40 4,111.94
7. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 130,821.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 262,331.26


E. OVERHEAD & PROFIT 10.0 % x D 26,233.13
F. HARGA SATUAN PEKERJAAN ( D + E ) 288,564.39
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-522

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.2 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2 TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1249 Jam #VALUE!


2. Mandor (L03) Jam 0.0178 Jam #VALUE!

JUMLAH HARGA TENAGA #VALUE!

B. BAHAN

1. Agregat Kelas C2 (M29) M3 1.2000 0.00 0.00

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1 Wheel Loader (E15) Jam 0.0178 223,000.00 3,980.37


2 Dump Truck (E08) Jam 0.5924 81,000.00 47,981.93
3 Motor Grader (E13) Jam 0.0117 208,000.00 2,436.41
4 Vibratory Roller (E19) Jam 0.0214 192,000.00 4,112.45
5 P. Tyre Roller (E18) Jam 0.0043 81,000.00 346.99
6 Water Tanker (E23) Jam 0.0211 81,000.00 1,707.83
7 Alat Bantu Ls 1.0000 800.00 800.00

JUMLAH HARGA PERALATAN 61,365.98

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #VALUE!


E. OVERHEAD & PROFIT 10.0 % x D #VALUE!
F. HARGA SATUAN PEKERJAAN ( D + E ) #VALUE!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-541

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.4(1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Semen Untuk Pond. Tnh. Semen TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : TON % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 2.7778 9,342.11 25,950.31


2. Mandor (L03) Jam 0.1852 16,348.88 3,027.57

JUMLAH HARGA TENAGA 28,977.88

B. BAHAN
1. Semen (M12) Kg 1,050.0000 1,260.97 1,324,014.30
JUMLAH HARGA BAHAN 1,324,014.30

C. PERALATAN
1. Dump Truck (E08) Jam 0.6091 197,879.12 120,528.78

JUMLAH HARGA PERALATAN 120,528.78

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,473,520.97


E. OVERHEAD & PROFIT 10.0 % x D 147,352.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,620,873.06
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-542

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.4(2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Tanah Semen TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja (L01) Jam 0.1499 9,342.11 1,400.69


2. Mandor (L03) Jam 0.0214 16,348.88 350.18

JUMLAH HARGA TENAGA 1,750.87

B. BAHAN

1. Tanah Timbunan (M08) M3 1.2000 58,544.85 70,253.82

JUMLAH HARGA BAHAN 70,253.82

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0178 227,192.50 4,055.20
2. Dump Truck (E08) Jam 0.5803 197,879.12 114,833.47
3. Motor Grader (E13) Jam 0.0084 265,505.74 2,221.43
4. Vibrator Roller (E19) Jam 0.0214 173,735.15 3,721.23
5. P. Tyre Roller (E18) Jam 0.0086 147,815.38 1,266.42
6. Water Tanker (E23) Jam 0.0070 195,023.40 1,370.65
7. Fulvi Mixer (E27) Jam 0.0193 156,565.93 3,018.14
8. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 130,486.54

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 202,491.23


E. OVERHEAD & PROFIT 10.0 % x D 20,249.12
F. HARGA SATUAN PEKERJAAN ( D + E ) 222,740.35
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-561

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI PERKIRAAN VOL. PEK. : 754.00
ITEM PEMBAYARAN NO. : 5.6 (1) TOTAL HARGA (Rp.) : 485,875,353.08
JENIS PEKERJAAN : Lapis Pondasi Agregat dengan CTB % THD. BIAYA PROYEK : 4.44
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 3.2129 9,342.11 30,014.82


2. Mandor (L03) jam 0.4016 16,348.88 6,565.81

JUMLAH HARGA TENAGA 36,580.63

B. BAHAN

1. Semen (M12) Kg 252.0000 1,260.97 317,763.43


2. Pasir (M01) M3 0.4788 146,812.47 70,293.81
3. Agregat Kasar (M03) M3 0.6385 166,627.65 106,393.69

JUMLAH HARGA BAHAN 494,450.93

C. PERALATAN

1. Concrete Mixer (E33) jam 0.4016 54,939.82 22,064.18


2. Dump Truck (E09) jam 0.0828 246,739.58 20,437.77
3. Finisher (E02) jam 0.0723 138,940.57 10,043.90
4. Tandem Roller (E17) jam 0.0057 123,819.90 710.38
5. P. Tire Roller (E18) jam 0.0036 147,815.38 527.68
6. Alat Bantu (E20) jam 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 54,783.91

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 585,815.47


E. OVERHEAD & PROFIT 10.0 % x D 58,581.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 644,397.02
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK Analisa EI-637a
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA JAWA BARAT / SUKABUMI
ITEM PEMBAYARAN NO. : 6.3 (7a) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : LASTON - LAPIS PONDASI (AC-Base) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.4395 9,342.11 4,106.03


2. Mandor (L03) Jam 0.0549 16,348.88 898.20

JUMLAH HARGA TENAGA 5,004.23

B. BAHAN

1. Agregat Kasar (M03) M3 0.7844 166,627.65 130,710.50


2. Agregat Halus (M04) M3 0.5225 175,634.55 91,769.05
3 Filler (M05) Kg 17.5560 1,260.97 22,137.52
4 Aspal (M10) Kg 131.6700 10,357.94 1,363,829.30

JUMLAH HARGA BAHAN 1,608,446.38

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0565 227,192.50 12,841.46
2. AMP (E01) Jam 0.0549 3,870,485.39 212,643.53
3. Genset (E12) Jam 0.1099 326,510.25 35,876.79
4. Dump Truck (E09) Jam 0.6589 246,739.58 162,569.50
5. Asphalt Finisher (E02) Jam 0.0687 138,940.57 9,541.70
6. Tandem Roller (E17) Jam 0.0382 123,819.90 4,735.89
7 P. Tyre Roller (E18) Jam 0.0428 147,815.38 6,332.12
8 Alat Bantu Ls 1.0000 10,000.00 10,000.00

JUMLAH HARGA PERALATAN 454,541.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,067,991.61


E. OVERHEAD & PROFIT 10.0 % x D 206,799.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,274,790.77
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
METODE PELAKSANAAN DAN METODE ANALISA
ITEM PEMBAYARAN NO. : 7.1 (4)
JENIS PEKERJAAN : Beton K300
SATUAN PEMBAYARAN : M3

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 18.9 KM
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Kadar Semen (Spesifikasi) : - Minimum Ks1 300 Kg/M3
: - Maksimum Ks2 350 Kg/M3
7 Perbandingan Air/Semen Maksimum (Spesifikasi) Wcr 0.42 -
8 Perbandingan Camp. 1 : Semen Sm 15.4 %
2.5 : Pasir Ps 38.5 %
3 : Agregat Kasar Kr 46.2 %
9 Berat Jenis Material :
- Beton D1 2.40 T/M3
- Semen D2 1.44 T/M3
- Pasir D3 2.00 T/M3
- Agregat Kasar D4 2.15 T/M3

II. TAHAP PELAKSANAAN PEKERJAAN


1 Semen, pasir, batu kerikil dan air dicampur dan diaduk
menjadi beton dengan menggunakan Concrete Mixer
2 Beton di-cor ke dalam perancah yang telah disiapkan
3 Penyelesaian dan perapihan setelah pemasangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Semen (PC) = {Sm x D1 x 1000} x 1.05 387.0000 Kg
1.b. Pasir Beton = {(Ps x D1) : D3} x 1.05 0.4846 M3
1.c. Agregat Kasar = {(Kr x D1) : D4} x 1.35 0.6955 M3
1.d. Kayu Perancah 0.2000 M3
1.e. Paku 1.6000 Kg

2. ALAT
2.a. BATCHING PLANT / CONCRETE MIXER
Kapasitas Alat V 8,000.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : Ts
- Memuat T1 8.00 menit
- Mengaduk T2 5.00 menit
- Menuang T3 5.00 menit
- Tunggu, dll. T4 5.00 menit
Ts 23.00 menit

Kap. Prod. / jam = V x Fa x 60 Q1 17.322 M3/jam

File : 433096126.xlsx
1000 x Ts

Koefisien Alat / M3 = 1 : Q1 0.0577 jam

File : 433096126.xlsx
ITEM PEMBAYARAN NO. : 7.1 (4)
JENIS PEKERJAAN : Beton K300
SATUAN PEMBAYARAN : M3

No. URAIAN KODE KOEF. SATUAN

2.b. CONCRETE TRUCK (TRUCK MIXER) (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Waktu Siklus Ts2
- Mengisi Bak T1 20.00 menit
- Angkut = (L : v1) x 60 menit T2 37.79 menit
- Tunggu + dump + Putar T3 10.00 menit
- Kembali = (L : v2) x 60 menit T4 28.34 menit
Ts2 96.13 menit

Kap.Prod. / jam = V x Fa x 60 Q4 3.11 M3


Ts2

Koefisien Alat/M3 = 1 : Q4 (E09) 0.3217 Jam

2.c. CONCRETE VIBRATOR


Disesuaikan dgn kapasitas produksi Alat Pencampur
(Concrete Mixer)

Kap. Prod. / jam = Kap. Prod./jam Concrete Mixer Q3 17.322 M3

Koefisien Alat / M3 = 1 : Q3 0.0577 jam

2.d. CONCRETTE PUMP


Kapasitas Alat V 8.00 M3
Faktor Efisiensi Alat Fa 0.83 -

Kap. Prod. / jam = Kap. Prod./jam Concrete Mixer Q2 17.322 M3

Koefisien Alat / M3 = 1 : Q3 0.0577 jam

2.e. ALAT BANTU


Diperlukan :
- Sekop
- Pacul
- Sendok Semen
- Ember Cor

3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 138.57 M3

Kebutuhan tenaga : - Mandor M 1.00 orang


- Tukang Tb 4.00 orang
- Pekerja P 12.00 orang

File : 433096126.xlsx
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt 0.0577 jam
- Tukang = (Tk x Tb) : Qt 0.2309 jam
- Pekerja = (Tk x P) : Qt 0.6928 jam

4 VOLUME PEKERJAAN YANG DIPERLUKAN 0.00 M3

5 WAKTU PELAKSANAAN YANG DIPERLUKAN 0.00 Hari

File : 433096126.xlsx
ITEM PEMBAYARAN NO. : 7.1 (4)
JENIS PEKERJAAN : Beton K300
SATUAN PEMBAYARAN : M3

No. URAIAN KODE KOEF. SATUAN

4 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,222,948.03 / M3

5. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0.00 hari

6. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

File : 433096126.xlsx
File : 433096126.xlsx
Analisa EI-714

KETERANGAN

Berdasarkan
JMF & sesuai
dgn Spesifikasi

967
1,493

File : 433096126.xlsx
File : 433096126.xlsx
KETERANGAN

File : 433096126.xlsx
Lanjutan

File : 433096126.xlsx
KETERANGAN

File : 433096126.xlsx
File : 433096126.xlsx
Analisa

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 7.2(8a) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Unit Pracetak Gelagar Tipe I Bentang 40 m TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUML


NO. KOMPONEN SATUAN KUANTITAS SATUAN HAR
(Rp.) (Rp

A. TENAGA

1. Pekerja jam 84.00 9,342.11


3. Mandor jam 14.00 16,348.88

JUMLAH HARGA TENAGA

B. BAHAN
Pracetak Gelagar Tipe I Bentang 40 m bh 1.0000 362,821,200.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Trailer jam 0.00000 309,470.68
1. Crane 160 ton jam 4.744 3,125,000.00
2. Crane 75 ton jam 3.373 1,875,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomo
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa 728a

ORMULIR STANDAR UNTUK


NALISA MASING-MASING HARGA SATUAN

5.00
2,117,417,761.95

JUMLAH
HARGA
(Rp.)

784,737.45
228,884.27

1,013,621.72

362,821,200.00

362,821,200.00

0.00
14,824,924.70
6,325,301.20

21,150,225.90

384,985,047.63
38,498,504.76
423,483,552.39
perasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
p komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

an untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN


ITEM PEMBAYARAN NO. : 8.1 (1)
JENIS PEKERJAAN : Pondasi Agregat Kls. A Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : setempat2 di sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata quarry ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 56.00 %
- Agregat Halus Ah 44.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar secara manual
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Pedestrian Roller
4 Sekelompok pekerja membuat galian lubang/patching,
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.6720 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.5280 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 1.50 menit
- Memuat dan lain-lain T2 0.50 menit
Ts1 2.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0357 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/jam
Kecepatan rata-rata kosong v2 40.00 KM/jam
Waktu Siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-lain (termasuk dumping setempat-setempat) T3 3.00 menit
Ts2 69.13 menit

Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (1)
JENIS PEKERJAAN : Pondasi Agregat Kls. A Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E09) 0.2776 jam

2.c. PEDESTRIAN ROLLER (E24)


Kecepatan rata-rata alat v 2.50 KM/jam
Lebar efektif pemadatan b 0.65 M
Jumlah lintasan n 12.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q3 16.86 M3


n
Koefisien Alat / M3 = 1 : Q3 (E24) 0.0593 jam

2.d. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = V x n x Fa Q4 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q4 (E23) 0.0211 jam

2.g. ALAT BANTU


Diperlukan :
- Kereta dorong = 5 buah
- Sekop = 10 buah
- Garpu = 10 buah

TENAGA
Produksi menentukan : galian untuk patching ( Asumsi )
Produksi agregat / hari Qt 15.00 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

3. Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 4.2667 jam
- Mandor = (Tk x M) : Qt (L03) 0.5333 jam
Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (1)
JENIS PEKERJAAN : Pondasi Agregat Kls. A Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 371,623.29 / M3.

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M3
ITEM PEMBAYARAN NO. : 8.1 (2)
JENIS PEKERJAAN : Pondasi Agregat Kls. B Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : setempat2 di sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 18.89 KM
5 Tebal lapis agregat padat t 0.20 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 8.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 59.00 %
- Agregat Halus Ah 15.00 %
- Sirtu St 26.00 %
II. URUTAN KERJA
1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan pekerja
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Pedestrian Roller
4 Sekelompok pekerja membuat galian lubang/patching,
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.7080 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.1800 M3
- Sirtu = St x 1 M3 x Fk M16 0.3120 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 1.50 menit
- Memuat dan lain-lain T2 0.50 menit
Ts1 2.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0357 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/jam
Kecepatan rata-rata kosong v2 40.00 KM/jam
Waktu Siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 37.79 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 28.34 menit
- Lain-lain (termasuk dumping setempat-setempat) T3 3.00 menit
Ts2 69.13 menit

Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (2)
JENIS PEKERJAAN : Pondasi Agregat Kls. B Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = V x Fa x 60 Q2 3.60 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E09) 0.2776 jam

2.c. PEDESTRIAN ROLLER (E24)


Kecepatan rata-rata alat v 2.50 KM/jam
Lebar efektif pemadatan b 0.65 M
Jumlah lintasan n 12.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q3 22.48 M3


n
Koefisien Alat / M3 = 1 : Q3 (E24) 0.0445 jam

2.d. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = V x n x Fa Q4 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q4 (E23) 0.0211 jam

2.e. ALAT BANTU


Diperlukan :
- Kereta dorong = 5 buah
- Sekop = 10 buah
- Garpu = 10 buah

3. TENAGA
Produksi menentukan : galian untuk patching ( Asumsi )
Produksi agregat / hari Q1 15.00 M3/jam
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 4.2667 jam
- Mandor = (Tk x M) : Qt (L03) 0.5333 jam

Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (2)
JENIS PEKERJAAN : Pondasi Agregat Kls. B Untuk Pek. Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 347,614.36 / M3.

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 8.1 (5)
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Unit Produksi ke lokasi pekerjaan L 18.89 KM
5 Tebal Lapis Hotmix padat t 0.06 M
6 Jam kerja efektif per-hari Tk 8.00 Jam
7 Faktor kehilanganmaterial : - Agregat Fh1 1.10 -
- Aspal Fh2 1.05 -
8 Komposisi campuran AC :
- Coarse Agregat CA 62.15 %
- Fine Agregat FA 27.20 %
- Fraksi Filler FF 4.85 %
- Asphalt As 5.80 %
9 Berat jenis bahan :
- AC D1 2.27 ton / M3
- Coarse Agregat & Fine Agregat D2 1.80 ton / M3
- Fraksi Filler D3 1.40 ton / M3
- Asphalt D4 1.03 ton / M3
II. URUTAN KERJA
1 Wheel Loader memuat Agregat dan Aspal ke dalam
Cold Bin AMP
2 Agregat dan aspal dicampur dan dipanaskn
dengan AMP untuk dimuat langsung kedalam
Dump Truck dan diangkut ke lokasi pekerjaan
3 Lapis Resap Pengikat/ Perekat dihampar manual
4 Campuran aspal panas dihampar secara manual
dan dipadatkan dengan Tandem
5 Sekelompok pekerja membuat galian lubang/patching,
merapikan tepi hamparaan dengan menggunakan
Alat Bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Agregat Kasar = (CA x (D1 x tM3) x Fh1) : D2 (M03) 0.8622 M3
1.b. Agregat Halus = (FA x (D1 x tM3) x Fh1) : D2 (M04) 0.3773 M3
1.c. Filler = (FF x (D1 x 1 M3) x Fh1) (M05) 121.105 M3
1.d. Aspal = (AS x (D1 x tM3) x Fh2) x 1000 (M10) 138.243 Kg
1.e. Emulsi = 1 M3 / t x 0,4 x 1,1 7.33 liter
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus Ts1
- Muat T1 2.00 menit
- Lain lain T2 1.00 menit
Ts1 3.00 menit

Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (5)
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = D2 x V x Fb x Fa x 60 Q1 17.77 M3


D1 x t x Ts1

Koefisien Alat/M3 = 1 : Q1 (E15) 0.0563 Jam

2.b. ASPHALT MIXING PLANT (AMP) (E01)


Kapasitas produksi V 50.0 ton / Jam
Faktor Efisiensi alat Fa 0.80 -

Kap.Prod. / jam = V x Fa Q2 17.62 M3


D1
Koefisien Alat/M3 = 1 : Q2 (E01) 0.0568 Jam

2.c. GENERATORSET ( GENSET ) (E12)


Kap.Prod. / Jam = SAMA DENGAN AMP Q3 17.62 M3
Koefisien Alat/M3 = 1 : Q3 (E12) 0.0568 Jam

2.d. DUMP TRUCK (DT) (E09)


Kapasitas bak V 8.00 ton
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM / Jam
Kecepatan rata-rata kosong v2 40.00 KM / Jam
Kapasitas AMP / batch Q2b 1.00 ton
Waktu menyiapkan 1 batch AC Tb 1.50 menit
Waktu Siklus Ts2
- Mengisi Bak = (V : Q2b) x Tb T1 12.00 menit
- Angkut = (L : v1) x 60 menit T2 37.79 menit
- Tunggu + dump + Putar T3 10.00 menit
- Kembali = (L : v2) x 60 menit T4 28.34 menit
Ts2 88.13 menit

Kap.Prod. / jam = V x Fa x 60 Q4 1.99 M3


D1 x Ts2

Koefisien Alat/M3 = 1 : Q4 (E09) 0.5021 Jam

2.e. ASPHALT FINISHER (E02)


Kapasitas produksi V 40.00 ton / jam
Faktor efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x Fa Q5 14.63 M3


D1
Koefisien Alat/M3 = 1 : Q5 (E02) 0.0684 Jam
2.f. TANDEM ROLLER (E17)
Kecepatan rata-rata alat v 3.50 Km / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Berlanjut ke hala
ITEM PEMBAYARAN NO. : 8.1 (5)
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q6 26.15 M3


n
Koefisien Alat/M3 = 1 : Q6 (E17) 0.0382 Jam

2.g. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata v 5.00 KM / jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 16.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q7 23.34 M3


n
Koefisien Alat/M3 = 1 : Q7 (E18) 0.0428 Jam

2.h. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3. TENAGA
Produksi menentukan : galian Patching ( Asumsi ) Q5 1.50 M3 / Jam
Produksi AC / hari = Tk x Q5 Qt 12.00 M3
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien Tenaga / M3 :
- Pekerja = (Tk x P) / Qt (L01) 6.6667 Jam
- Mandor = (Tk x M) / Qt (L03) 0.6667 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 2,547,468.49 / M3.


6. MASA PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 8.4(5)
JENIS PEKERJAAN : Patok Pengarah
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok beton cetak, dll) diangkut dengan
Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 18.9 KM
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
7 Tulangan praktis Rc 125.00 Kg/M3

II. URUTAN KERJA


1 Patok ditanam di tepi luar bahu jalan sesuai dengan
gambar rencana dan di-cat

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Beton K-225 = (0.15 x 0.15 x 1.50) x Fh (M38) 0.0354 M3
1.b. Baja Tulangan (M39) 4.6512 Kg
1.c. Cat, dan material lainnya - Ls

2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 19.0 Buah
Faktor Efisiensi Alat Fa 0.83 -
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 90.7 menit
- Menurunkan = Rata-rata 1 menit / buah T3 10.0 menit
- Lain-lain = geser, atur, tunggu, dll. T4 30.0 menit
Ts 160.7 menit

Kap. Prod. / Jam = Cp x Fa Q1 6 Buah


Ts : 60

Koefisien Alat / Buah = 1 : Q1 (E08) 0.1698 Jam

2.b. ALAT BANTU


- Pacul / Sekop = 4 buah

3. TENAGA
Produksi pasang patok pengarah / hari = Tk x Q1 Qt 47.11 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.1698 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.6793 jam
- Pekerja = (Tk x P) : Qt (L01) 1.3586 jam

Berlanjut ke
ITEM PEMBAYARAN NO. : 8.4(5)
JENIS PEKERJAAN : Patok Pengarah
SATUAN PEMBAYARAN : BH URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 149,694.15 / Buah

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 30 Hari

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 20.00 Buah
ITEM PEMBAYARAN NO. : 8.4 (1)
JENIS PEKERJAAN : Marka Jalan (Thermoplastic)
SATUAN PEMBAYARAN : M2 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.0 KM
5 Jam kerja efektif per-hari Tk 8.00 jam
6 Faktor Kehilangan Material Fh 1.05 -
7 Tebal lapisan cat secara mekanik t 0.0015 M
8 Berat Isi Bahan Cat BJ.Cat 1.05 Kg/Liter
9 Perbandingan pemakaian bahan : - Cat C 80 %
- Thinner T 20 %
II. URUTAN KERJA
1 Permukaan jalan dibersihkan dari debu/kotoran
2 Cat disemprotkan dengan Compressor di atas maal
tripleks yang dipasang di permukaan jalan
3 Glass Bead diberikan segera setelah cat marka selesai
disemprotkan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Cat Marka Thermoplastic = C x R x (BJ.Cat) (M17) 1.2600 Kg
1.b. Thinner = TxR (M33) 0.3000 Liter
1.c. Glass Bead (M34) 0.4500 Kg

2. ALAT
2.a. COMPRESSOR (E05)
Kapasitas penyemprotan V 40.00 Ltr/Jam
Jumlah cat cair = (1 M x 1 M) x t x 1000 R 1.50 Ltr/M2

Kap. Prod. / Jam = V:R Q1 26.667 M2/Jam

Koef. Alat / M2 = 1 : Q1 (E05) 0.0375 Jam

2.b. DUMP TRUCK (E08)


Pada dasarnya alat ini digunakan bersama-sama
dengan Compressor Q3 26.667 M2/Jam
Koef. Alat / M2 = 1 : Q3 (E08) 0.0375 Jam

2.c. ALAT BANTU Ls


Diperlukan :
- Sapu Lidi = 3 buah
Analisa EI-811

KETERANGAN

Gradasi harus
memenuhi Spec.
Berlanjut ke halaman berikut
Analisa EI-811

Lanjutan

KETERANGAN

Lump Sum
Berlanjut ke halaman berikut
Analisa EI-811

Lanjutan

KETERANGAN
Analisa EI-812

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi
Berlanjut ke halaman berikut
Analisa EI-812

Lanjutan

KETERANGAN

Lump Sum
Berlanjut ke halaman berikut
Analisa EI-812

Lanjutan

KETERANGAN
Analisa EI-815

URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus -
memenuhi -
Spesifikasi
Berlanjut ke halaman berikut
Analisa EI-815

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
Berlanjut ke halaman berikut
Analisa EI-815

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN

Lump Sum
Analisa EI-845

KETERANGAN
Berlanjut ke hal. berikut.
Analisa EI-845

Lanjutan

KETERANGAN
Analisa EI-841

KETERANGAN
Analisa EI-811

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. : 0.00
ITEM PEMBAYARAN NO. : 8.1 (1) TOTAL HARGA (Rp.) : 0.00
JENIS PEKERJAAN : Pondasi Agregat Kls. A Untuk Pek. Minor % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 4.2667 9,342.11 39,859.68


2. Mandor (L03) jam 0.5333 16,348.88 8,719.40

JUMLAH HARGA TENAGA 48,579.08

B. BAHAN

1. Agregat Kasar (M03) M3 0.6720 166,627.65 111,973.78


2. Agregat Halus (M04) M3 0.5280 175,634.55 92,735.04

JUMLAH HARGA BAHAN 204,708.82

C. PERALATAN

1. Wheel Loader (E15) jam 0.0357 227,192.50 8,110.40


2. Dump Truck (E09) jam 0.2776 246,739.58 68,501.45
3. Pedestrian Roller (E24) jam 0.0593 47,672.69 2,827.67
4. Water Tanker (E23) jam 0.0211 195,023.40 4,111.94
5. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 84,551.45

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 337,839.35


E. OVERHEAD & PROFIT 10.0 % x D 33,783.94
F. HARGA SATUAN PEKERJAAN ( D + E ) 371,623.29
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-812

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA : JAWA BARAT / KOTA SUKABUMI
MATA PEMBAYARAN NO. : 8.1 (2)
JENIS PEKERJAAN : Pondasi Agregat Kls. B Untuk - PERKIRAAN VOL. PEK. : 0.00
SATUAN PEMBAYARAN : M3 TOTAL HARGA (Rp.) : 0.00
Pek Pek. Minor % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 4.2667 9,342.11 39,859.68


2. Mandor (L03) jam 0.5333 16,348.88 8,719.40

JUMLAH HARGA TENAGA 48,579.08

B. BAHAN

1. Agregat Kasar (M03) M3 0.7080 166,627.65 117,972.38


2. Agregat Halus (M04) M3 0.1800 175,634.55 31,614.22
3. Sirtu (M16) M3 0.3120 108,983.49 34,002.85

JUMLAH HARGA BAHAN 183,589.44

C. PERALATAN

1. Wheel Loader (E15) jam 0.0357 227,192.50 8,110.40


2. Dump Truck (E09) jam 0.2776 246,739.58 68,501.45
3. Pedestrian Roller (E24) jam 0.0445 47,672.69 2,120.75
4. Water Tanker (E23) jam 0.0211 195,023.40 4,111.94
5. Alat Bantu ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 83,844.53

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 316,013.06


E. OVERHEAD & PROFIT 10.0 % x D 31,601.31
F. HARGA SATUAN PEKERJAAN ( D + E ) 347,614.36
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-815

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI PERKIRAAN VOL. PEK. : 0.00
ITEM PEMBAYARAN NO. : 8.1 (5) TOTAL HARGA (Rp.) : 0.00
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 6.6667 9,342.11 62,280.75


2. Mandor (L03) Jam 0.6667 16,348.88 10,899.25

JUMLAH HARGA TENAGA 73,180.00

B. BAHAN
1. Agregat Kasar (M03) M3 0.8622 166,627.65 143,659.46
2. Agregat Halus (M04) M3 0.3773 175,634.55 66,271.21
3 Filler (M05) M3 121.1045 1,260.97 152,708.66
4 Aspal (M10) Kg 138.2430 10,357.94 1,431,912.01
Emulsi liter 7.3333 9,006.90 66,050.60

JUMLAH HARGA BAHAN 1,860,601.94

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0563 227,192.50 12,785.14
2. AMP (E01) Jam 0.0568 3,870,485.39 219,650.05
3. Genset (E12) Jam 0.0568 326,510.25 18,529.46
4. Dump Truck (E09) Jam 0.5021 246,739.58 123,897.97
5. Asp. Finisher (E02) Jam 0.0684 238,868.50 0.00
6. Tandem Roller (E17) Jam 0.0382 123,819.90 4,735.89
7 Alat Bantu Ls 1.0000 2,500.00 2,500.00
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 382,098.50

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,315,880.44


E. OVERHEAD & PROFIT 10.0 % x D 231,588.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,547,468.49
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-845
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KABUPATEN SUKABUMI
ITEM PEMBAYARAN NO. : 8.4(5) PERKIRAAN VOL. PEK. : 20.00
JENIS PEKERJAAN : Patok Pengarah TOTAL HARGA (Rp.) : 2,993,883.03
SATUAN PEMBAYARAN : BH % THD. BIAYA PROYEK : 1.65

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 1.3586 9,342.11 12,692.41


2. Tukang (L02) jam 0.6793 11,677.80 7,932.87
3. Mandor (L03) jam 0.1698 16,348.88 2,776.50

JUMLAH HARGA TENAGA 23,401.78

B. BAHAN

1. Beton K-250 (M38) M3 0.0354 905,578.97 32,091.45


2. Baja Tulangan (M39) Kg 4.6512 8,556.56 39,798.01
3. Cat, dan material lainnya Ls 1.0000 7,188.95 7,188.95

JUMLAH HARGA BAHAN 79,078.41

C. PERALATAN

1. Dump Truck (E08) Jam 0.1698 197,879.12 33,605.40


2. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 33,605.40

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 136,085.59


E. OVERHEAD & PROFIT 10.0 % x D 13,608.56
F. HARGA SATUAN PEKERJAAN ( D + E ) 149,694.15
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-841

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : PENINGKATAN JALAN SARASA ( SUKABUMI ) ( 1,44 KM )


LOKASI : KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KOTA : JAWA BARAT / KOTA SUKABUMI
ITEM PEMBAYARAN NO. : 8.4 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Marka Jalan (Thermoplastic) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.3000 9,342.11 2,802.63


2. Tukang (L02) jam 0.0750 11,677.80 875.84
3. Mandor (L03) jam 0.0375 16,348.88 613.08

JUMLAH HARGA TENAGA 4,291.55

B. BAHAN

1. Cat Marka (M17) Kg 1.2600 48,727.33 61,396.43


2. Thinner (M33) Liter 0.3000 21,346.35 6,403.91
3. Glass Bead (M34) Kg 0.4500 37,648.84 16,941.98

JUMLAH HARGA BAHAN 84,742.32

C. PERALATAN

1. Compressor (E05) Jam 0.0375 163,441.50 6,129.06


2. Dump Truck (E08) Jam 0.0375 197,879.12 7,420.47
3. Alat Bantu Ls 1.0000 100.00 100.00

JUMLAH HARGA PERALATAN 13,649.52

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 102,683.39


E. OVERHEAD & PROFIT 10.0 % x D 10,268.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 112,951.73
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
Analisa EI-1011

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / KOTA SUKABUMI
MATA PEMBAYARAN NO. : Pemeliharaan Rutin Perkerasan PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : 10.1(1) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 Pek. Minor % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa (L01) jam 0.0000 9,342.11 0.00


2 Tukang (L02) jam 0.0000 11,677.80 0.00
3 Mandor (L03) jam 0.0000 16,348.88 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Agregat Kasar (M03) M3 #REF! 166,627.65 #REF!


2. Agregat Halus (M04) M3 #REF! 175,634.55 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Wheel Loader (E15) jam #REF! 227,192.50 #REF!


2. Dump Truck (E09) jam #REF! 197,879.12 #REF!
3. Pedestrian Roller (E24) jam #REF! 47,672.69 #REF!
4. Water Tanker (E23) jam #REF! 195,023.40 #REF!
5. Alat Bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Analisa EI-1012

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / KOTA SUKABUMI
MATA PEMBAYARAN NO. : Pemeliharaan Rutin Bahu Jalan PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : 10.1(2) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 Pek. Minor % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa (L01) jam 270.0000 9,342.11 2,522,370.38


2 Tukang (L02) jam 135.0000 11,677.80 1,576,503.28
3 Mandor (L03) jam 13.5000 16,348.88 220,709.84

JUMLAH HARGA TENAGA 4,319,583.49

B. BAHAN

1. Agregat Kelas B M3 180.0000 248,860.65 44,794,916.46


2.

JUMLAH HARGA BAHAN 44,794,916.46

C. PERALATAN

1 Dump Truck jam 67.5000 197,879.12 13,356,840.83


2 Pedestrian Roller jam 67.5000 47,672.69 3,217,906.28
3 Water Tanker jam 33.7500 195,023.40 6,582,039.84
4 Alat Bantu Ls 1.0000 1,157,839.35 1,157,839.35
JUMLAH HARGA PERALATAN 24,314,626.29

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 73,429,126.24


E. OVERHEAD & PROFIT 10.0 % x D 7,342,912.62
F. HARGA SATUAN PEKERJAAN ( D + E ) 80,772,038.86

Analisa EI-1013
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN L
: KM.BDG. 93+183-KM.BDG.94+623
PROP / KAB / KODYA JAWA BARAT / KOTA SUKABUMI
MATA PEMBAYARAN NO. : Pemeliharaan Rutin Selokan, Sal. Air, Galian PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : 10.1(2) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 Pek. Minor % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa (L01) jam 2,200.0000 9,342.11 20,552,647.50


2 Tukang (L02) jam 1,100.0000 11,677.80 12,845,582.27
3 Mandor (L03) jam 550.0000 16,348.88 8,991,882.18

JUMLAH HARGA TENAGA 42,390,111.95

B. BAHAN

JUMLAH HARGA BAHAN 0.00


C. PERALATAN

1 Alat Bantu Ls 1.0000 4,239,011.19 4,239,011.19

JUMLAH HARGA PERALATAN 4,239,011.19

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 46,629,123.14


E. OVERHEAD & PROFIT 10.0 % x D 4,662,912.31
F. HARGA SATUAN PEKERJAAN ( D + E ) 51,292,035.46
Analisa EI-813

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 0.00
#REF! % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN #REF!
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam #REF! 3,375.00 #REF!


2. Mandor (L03) Jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Agregat Kelas C (M28) M3 #REF! 98,500.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1 Wheel Loader (E15) Jam #REF! 391,100.50 #REF!


2 Dump Truck (E09) Jam #REF! 228,051.00 #REF!
3 Pedestrian Roller (E24) Jam #REF! 61,145.50 #REF!
4 Water Tanker (E23) Jam #REF! 198,301.00 #REF!
5 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-814

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Waterbound Macadam Utk. Pek. - TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN #REF! Minor % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam #REF! 3,375.00 #REF!


2. Mandor (L03) Jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Agregat Kasar (M03) M3 #REF! 120,000.00 #REF!


2. Agregat Halus (M04) M3 #REF! 136,350.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Wheel Loader (E15) Jam #REF! 391,100.50 #REF!


2. Dump Truck (E09) Jam #REF! 228,051.00 #REF!
3. 3-Wheel Roller (E16) Jam #REF! 141,725.50 #REF!
4. Alat BAntu Ls 1.0000 0.00 0.00
JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-815

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja Biasa (L01) Jam #REF! 3,375.00 #REF!
2. Mandor (L03) Jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Agregat Kasar (M03) M3 #REF! 120,000.00 #REF!


2. Agregat Halus (M04) M3 #REF! 136,350.00 #REF!
3 Filler (M05) M3 #REF! 1,500.00 #REF!
4 Aspal (M10) Kg #REF! 6,364.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN
1. Wheel Loader (E15) Jam #REF! 391,100.50 #REF!
2. AMP (E01) Jam #REF! 3,299,000.00 #REF!
3. Genset (E12) Jam #REF! 174,625.50 #REF!
4. Dump Truck (E09) Jam #REF! 228,051.00 #REF!
5. Asp. Finisher (E02) Jam #REF! 238,868.50 0.00
6. Tandem Roller (E17) Jam #REF! 177,688.00 #REF!
7 P. Tyre Roller (E18) Jam #REF! 176,952.11 0.00
8 Alat Bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-817

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN #REF! TOTAL HARGA : 0.00
SATUAN PEMBAYARAN #REF! #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam #REF! 3,375.00 #REF!


2. Mandor (L03) Jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. #REF! (M03) M3 #REF! 120,000.00 #REF!


2. Agregat Halus (M04) M3 #REF! 136,350.00 #REF!
3 #REF! (M10) Kg #REF! 6,364.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Wheel Loader (E15) Jam #REF! 391,100.50 #REF!


2. Dump Truck (E09) Jam #REF! 228,051.00 #REF!
3. 3-Wheel Roller (E16) Jam #REF! 141,725.50 #REF!
4. Asp. Sprayer (E03) Jam #REF! 80,800.50 #REF!
5. Alat bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN #REF!


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!
E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-818

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN #REF! TOTAL HARGA : 0.00
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 3,375.00 #REF!


2. Mandor (L03) jam #REF! 5,313.00 #REF!
JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Agregat Halus (M04) M3 #REF! 136,350.00 #REF!


2. #REF! (M31) Kg #REF! 6,000.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Conc. Mixer (E06) jam #REF! 77,675.50 #REF!


2. Pedestrian Roller (E24) jam #REF! 61,145.50 #REF!
3. Dump Truck (E09) jam #REF! 228,051.00 #REF!
4. Alat Bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-819

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN #REF! TOTAL HARGA : 0.00
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam #REF! 3,375.00 #REF!


2. Mandor (L03) Jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Aspal (M10) Kg #REF! 6,364.00 #REF!


2. Kerosene (M11) Liter #REF! 2,500.00 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Asphalt Sprayer (E03) Jam #REF! 80,800.50 #REF!


2. Compresor (E05) Jam #REF! 139,163.00 #REF!
3. Dump Truck (E08) Jam #REF! 198,301.00 #REF!

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-845
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : REHABILITASI JEMBATAN BOJONGTUGU, RUAS JALAN JAMPANGTENGAH - KIARADUA


KM.BDG 162 +917
PROP / KAB / KODYA : JAWA BARAT / KABUPATEN SUKABUMI
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 20.00
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 9,342.11 #REF!


2. Tukang (L02) jam #REF! 11,677.80 #REF!
3. Mandor (L03) jam #REF! 16,348.88 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Beton K-250 (M38) M3 #REF! 905,578.97 #REF!


2. Baja Tulangan (M39) Kg #REF! 8,556.56 #REF!
3. Cat, dan material lainnya Ls 1.0000 #REF! #REF!
JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Dump Truck (E08) Jam #REF! 197,879.12 #REF!


2. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-8.4(6).(c)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 0
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 3,375.00 #REF!


2. Tukang (L02) jam #REF! 4,563.00 #REF!
3. Mandor (L03) jam #REF! 5,313.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Beton K-250 (M38) M3 #REF! 657,625.24 #REF!


2. Baja Tulangan (M39) Kg #REF! 8,775.77 #REF!
3. Cat, dan material lainnya Ls 1.0000 10,000.00 10,000.00
4 Beton 125 M3 #REF! 463,193.77 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Dump Truck (E08) Jam #REF! 198,301.00 #REF!


2. Alat Bantu dan Ls 1.0000 10,000.00 10,000.00
Pengukuran

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa LI-8.4(4).(c)
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 0
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 0.00 #REF!


2. Tukang (L02) jam #REF! 0.00 #REF!
3. Mandor (L03) jam #REF! 0.00 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Pelat (M35) BH #REF! 300,000.00 #REF!


2. Pipa Galvanis (M24) Batang #REF! 0.00 #REF!
3. Beton K-250 (M38) M3 #REF! 657,625.24 #REF!
4. Cat, dan bahan lainnya Ls 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Dump Truck (E08) Jam #REF! 198,301.00 #REF!


2. Alat Bantu Ls 1.0000 5,000.00 5,000.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa LI-1032

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 0
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 0
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 9,342.11 #REF!


2. Tukang (L02) jam #REF! 11,677.80 #REF!
3. Mandor (L03) jam #REF! 16,348.88 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Pelat Rambu (M35) BH #REF! 842,145.15 #REF!


2. Pipa Galvanis (M24) Batang #REF! 550,231.52 #REF!
3. Beton K-225 (M38) M3 #REF! 680,921.64 #REF!
4. Cat, dan bahan lainnya Ls 1.0000 #REF! #REF!
JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Dump Truck (E08) Jam #REF! 198,301.00 #REF!


2. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-1041

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 135.00
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 23,893,208.55
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 1.52

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 9,342.11 #REF!


2. Tukang (L02) jam #REF! 11,677.80 #REF!
3. Mandor (L03) jam #REF! 16,348.88 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Cat Marka (M17) Kg #REF! 37,648.84 #REF!


2. Thinner (M33) Liter #REF! 21,346.35 #REF!
3. Blass Bit (M34) Kg #REF! 37,648.84 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Compressor (E05) Jam #REF! 163,441.50 #REF!


2. Dump Truck (E08) Jam #REF! 197,879.12 #REF!
3. Alat Bantu Ls 1.0000 #REF! #REF!

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-1042

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET 0
0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. #REF! PERKIRAAN VOL. PEK. : 135.00
JENIS PEKERJAAN #REF! TOTAL HARGA (Rp.) : 23,893,208.55
SATUAN PEMBAYARAN #REF! % THD. BIAYA PROYEK : 1.52

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam #REF! 9,342.11 #REF!


2. Tukang (L02) jam #REF! 11,677.80 #REF!
3. Mandor (L03) jam #REF! 16,348.88 #REF!

JUMLAH HARGA TENAGA #REF!

B. BAHAN

1. Cat Marka (M17) Kg #REF! 37,648.84 #REF!


2. Thinner (M33) Liter #REF! 21,346.35 #REF!
3. Blass Bit (M34) Kg #REF! 37,648.84 #REF!

JUMLAH HARGA BAHAN #REF!

C. PERALATAN

1. Compressor (E05) Jam #REF! 163,441.50 #REF!


2. Dump Truck (E08) Jam #REF! 197,879.12 #REF!
3. Alat Bantu Ls 1.0000 #REF! 0.00

JUMLAH HARGA PERALATAN #REF!

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 10.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIRFORMULIR STANDAR UNTUK

m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


MLAH JUMLAH JUMLAH JUMLAH JUMLAH JUMLAH JUMLAH JUMLAH JUMLAH
RGA HARGA HARGA HARGA HARGA HARGA HARGA HARGA HARGA
p.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
TENAGA TENAGA TENAGA TENAGA TENAGA
TENAGA TENAGA TENAGA TENAGA TENAGA
0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
BAHAN BAHAN BAHAN BAHAN BAHAN
BAHAN BAHAN BAHAN BAHAN BAHAN
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN ATAS DAN PENATAAN
: KM.BDG. : KM.BDG. : KM.BDG. : KM.BDG. : KM.BDG. : KM.BDG. : KM.BDG. : KM.BDG. 93+183-KM.BDG.9
JAWA BARA JAWA BARA JAWA BARA JAWA BARA JAWA BARA JAWA BARA JAWA BARAT / KOTA SUKAB
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
0.00
0.00
0.00
MLAH JUMLAH
RGA HARGA
p.) (Rp.)
(Rp.)
(Rp.)
TENAGA
TENAGA
2,522,370.38
1,576,503.28
220,709.84
220,709.84
220,709.84
4,319,583.49

2. 2. 2. 2. 2. 2. 2. 2.
44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.46
44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.44,794,916.46
PERALATAN
PERALATAN
13,356,840.83
3,217,906.28
6,582,039.84
1,157,839.35
### ###
###
24,314,626.29
24,314,626.29
73,429,126.24
7,342,912.62
80,772,038.86
80,772,038.86
80,772,038.86
80,772,038.86

sa EI-1013

m) RUAS JALAN LINGKAR CIBOLANGPEMBANGUN


PEMBANGUN
PEMBANGUN
PEMBANGUN
PEMBANGUNAN JEMBATAN CIJAMBE ( 40,00 m )
: KM.BDG. 93+183-KM.BDG.94+623
JAWA BARA
JAWA BARAT / KOTA SUKABUMIJAWA BARAT / KOTA SUKABUMI
0.00
0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
MLAH JUMLAH JUMLAH JUMLAH JUMLAH
RGA HARGA HARGA HARGA HARGA
p.) (Rp.) (Rp.) (Rp.) (Rp.)
(Rp.) (Rp.) (Rp.) (Rp.)
(Rp.) (Rp.) (Rp.) (Rp.)
TENAGA TENAGA TENAGA TENAGA
TENAGA TENAGA TENAGA TENAGA
20,552,647.20,552,647.20,552,647.20,552,647.50
12,845,582.12,845,582.12,845,582.12,845,582.27
8,991,882.18,991,882.18,991,882.18,991,882.18
8,991,882.18,991,882.18,991,882.18,991,882.18
8,991,882.18,991,882.18,991,882.18,991,882.18
42,390,111.42,390,111.42,390,111.42,390,111.95
42,390,111.42,390,111.42,390,111.42,390,111.95
BAHAN BAHAN BAHAN BAHAN
BAHAN BAHAN BAHAN BAHAN
BAHAN BAHAN BAHAN BAHAN
4,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.19
4,239,011.14,239,011.14,239,011.14,239,011.19
46,629,123.46,629,123.46,629,123.46,629,123.14
4,662,912.34,662,912.34,662,912.34,662,912.31
51,292,035.51,292,035.51,292,035.51,292,035.46
51,292,035.51,292,035.51,292,035.51,292,035.46
51,292,035.51,292,035.51,292,035.51,292,035.46
51,292,035.51,292,035.51,292,035.51,292,035.46
MLAH
RGA
p.)

#REF!

atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)

#REF!
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)
#REF!

atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)

#REF!
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)
#REF!

atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)

atau ukuran
an dari nomor

rmasuk PPN

- KIARADUA

MLAH
RGA
p.)
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)
atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)

#REF!

atau ukuran

an dari nomor

rmasuk PPN
MLAH
RGA
p.)

#REF!
TAS DAN PENATAAN SIMPANG )
TAS DAN PENATAAN SIMPANG )
GUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGK
GUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGK
GUNAN JEMBATAN CIJAMBE ( 40,00 m ) DAN JEMBATAN CIPELANG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGK
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
NG (40 m) RUAS JALAN LINGKAR CIBOLANG - BAROS ( LINGKAR SUKABUMI SEGMEN 1 TAHAP 2 LANJUTAN ) ( BANGUNAN A
PERKERASAN JALAN BETON
PERHITUNGAN PERANCAH BESI
Plat Besi Tipis 2 mm s/d 5 mm 0.81 M2 1.36 KG 1.1016 KG 13,060 Rp.
BESI SIKU 30.30.3 12 M 1.36 KG 16.32 KG 9,007 Rp.
TULANGAN BAJA POLOS BESI DIA 12 MM 1.8 M 0.89 KG 1.602 KG 8,556.56 Rp.
14,386.90
146,992.61
13,707.60
175,087.11