ARRIVAL MEETING REPORT

TK. PULAU TIGA 330


ARRIVAL MEETING 21 AGUSTUS 2019
ESTIMASI PEKERJAAN BAWAH AIR SELESAI 21 HARI
PEKERJAAN SELESAI 05 september 2019

Free gas tank


Scrabbing, pengetokan
Buka manhole
Sandblasting & Painting
Blasting bottom
Blasting Top side
Blasting maindeck outside
Painting bottom area
Painting topside area
Painting maindeck outside

Perawatan & painting plimsolmark, ship name, port register, waterline mark

Hull outfitting
Bongkar pasang zink anode ( pasang sesuai yang lama )
Bongkar pasang kupingan ban dapra ( material sudah digudang )
Ganti rantai jangkar
Ruang rantai dibersihkan
Ganti stoper jangkar (difungsikan kembali rantai stopper jangkar)
Ganti kampas rem jangkar
Pasang pelindung kopling transmisi untuk safety
Tambah ventilasi di rumah jangkar (buat baru pintu samping )
Repair railling rumah jangkar
Replating dinding rumah jangkar yang keropos
Tambah bolder disebelah kiri ( belakang push pad haluan )

MENYETUJUI MENGETAHUI

--------------------- ----------------- ------------------ ---------------------


( OWNER KAPAL ) ( KAPRO ) ( DIR OPS ) ( DIR KOMERSIAL)

ARRIVAL MEETING REPORT

LANJUTAN
Ganti baru ban dapra
Ganti wire towing
Ganti safety lubang wire towing ( di bulwark )
Pasang tangga darurat pada bagian belakang ruang muat
Penambahan drainase kanan kiri belakang
Pemasangan safety pada drainase
Ganti plat nomor pada draft dan plimsolmark, port register san garis air
Ganti gipsi pada windlass jangkar
Ganti tiang penyangga lama diganti h beam 150
Ganti lantai keropos rumah jangkar
Ganti hause penutup rumah jangkar
Reposisi dudukan mesin jangkar
HULL STEEL WORK
Replating side shell lajur 1 Area rantai breider (S)
Replating plat bottom deformasi di tanki 2 (S)
Replating top side lajur I (fr 39/40-43/44) ( S )
Replating top side lajur I yang bocor di tanki 6 (S)
Replating vender retak tanki 8 (S)
Replating side shell lajur I Fr 54-55 (P)
Replating top side lajur G Fr 48/49-50/51 (P)
Replating top side lajur I Fr 38-39
Replating deck deformasi tanki 4 (P)
Replating lajur G Fr 32/33-34/35 (P)
Replating lajur H Fr 31/32-34/35 (P)
Replating lajur I Fr 33/34-36/37 (P)

MENYETUJUI MENGETAHUI
--------------------- ----------------- ------------------ ---------------------
( OWNER KAPAL ) ( KAPRO ) ( DIR OPS ) ( DIR KOMERSIAL)

ARRIVAL MEETING REPORT

LANJUTAN
Replating lajur bottom lajur E Fr 33/34-36/37 (P)
Replating deck deformasi tanki 5 (P)
Replating vender pecar tanki 6 (P)
Replating top side corner belakang (S)
Reweld skeg
Ganti baru bolder haluan belakang,
bongkar pasang sliding pintu depan
bracket bulwark kanan
reweld main deck haluan
Test requirment
Air pressure test

MENYETUJUI MENGETAHUI

--------------------- ----------------- ------------------ ---------------------


( OWNER KAPAL ) ( KAPRO ) ( DIR OPS ) ( DIR KOMERSIAL)
TB. BOMAS LESTARI
ARRIVAL MEETING 21 AGUSTUS 2019

1 Pemasangan pompa PC8000 untuk pendingn AE kiri


2 pemasangan pompa fresh water
3 penggantian kran overboard sea chash kanan
4 penggantian crane ( vent kotak sea chast ) kondisional
5 ganti kran isap dan oralel pompa GS
6 modif pipa flowmeter
7 perbaiki pondasi OWS
8 ganti seal manibar bar shaft propeller
9 repair kran isap tanki 7P