No. Item Pekerjaan Spesifikasi Sat.
Upah (Rp) M'tl (Rp) Upah (Rp) M'tl (Rp)
II PEK. TANAH
1 Galian Tanah Pondasi Manual 9.67 m3 56,401.99 0.00 545,520.01 -
2 Urugan Tanah ex. Galian Termasuk perapihan & Perataan tanah sisa galian (disekitar) 4.84 m3 43,048.05 0.00 208,180.36 -
SUBTOTAL 753,700.37 -
D Acian/finishing
1 Acian/finishing Dinding dalam Konvensional; Mortar Acian 155.01 m2 15,000.00 10,812.50 2,325,090.92 1,676,003.03
2 Acian/finishing Dinding luar (depan) Konvensional; Mortar Acian 32.95 m2 15,000.00 10,812.50 494,201.25 356,236.73
3 Acian/finishing Dinding luar (belakang) Konvensional; Mortar Acian 26.93 m2 15,000.00 10,812.50 403,974.00 291,197.93
4 Acian/finishing Dinding luar (samping kiri) Konvensional; 1:4 36.88 m2 15,000.00 10,812.50 553,150.00 398,728.96
5 Acian/finishing Dinding luar (samping kanan) Konvensional; 1:4 - m2 15,000.00 10,812.50 - -
6 Acian/finishing Pagar/batas kavling Konvensional; Mortar Acian 5.79 m2 15,000.00 10,812.50 86,850.00 62,604.38
SUBTOTAL 12,049,728.95 13,990,758.15
V PEKERJAAN ATAP
1 Rangka Baja ringan C75-0,65 + 30-0,45; ex. Union/Metro Truss/ K-Steel 66.91 m2 25,250.00 84,166.67 1,689,601.13 5,632,003.76
2 Pasangan Genteng Badan Metal pasir; Inspiro Charcoal; tb. 0.30 mm 66.91 m2 11,290.91 112,909.09 755,530.01 7,555,300.10
3 Pasangan Nok Atap Metal pasir; Nok Alpha Charcoal Black 914 6.50 m1 6,250.00 31,250.00 40,625.00 203,125.00
4 Pasangan Nok Samping Metal pasir; Nok Samping Charcoal Black 110 16.57 m1 6,954.55 23,181.82 115,236.49 384,121.63
5 Pasangan List plank GRC plank; Polos; 8 mm 30.07 m1 9,600.00 19,200.00 288,671.55 577,343.09
SUBTOTAL 2,889,664.17 14,351,893.59
VI INSTALASI LISTRIK
A Pipa Sparing 0.00
1 Sparing SR Pipa PVC; Dia. 1"; ex. Wavin D - ls 0.00 100,000.00 - -
B Panel
1 Panel box Box 4 grup (Tanam); ex. Presto 1.00 set 50,000.00 150,000.00 50,000.00 150,000.00
2 MCB 1 x20A pole; 1x10A + 1x6A 1.00 set 50,000.00 120,000.00 50,000.00 120,000.00
3 Kabel Toevoer ex. Extrana, NYM 3x4 mm2 5.00 m1 25,000.00 60,000.00 125,000.00 300,000.00
4 Aarde/Grounding BC 6 mm; minimum 0,5 ohm 1.00 ttk 100,000.00 350,000.00 100,000.00 350,000.00
C Lampu
1 Instalasi titik lampu ex. Extrana, NYM 3 x 1,5 mm; saklar Boss; B20; B21(B22)/1/2A 7.00 ttk 27,083.33 108,333.33 189,583.33 758,333.33
E Stop Kontak
1 Instalasi Stop kontak ex. Extrana, NYM 3 x 2,5 mm; Boss; B20; B20426/16S 5.00 ttk 29,708.33 118,833.33 148,541.67 594,166.67
F Sertifikat Laik Operasi (SLO) ex. PPLN 1.00 ls 300,000.00 0.00 300,000.00 -
SUBTOTAL 963,125.00 2,272,500.00
IX PLAFOND
A Plafond dalam
1 Rangka Plafond Hollow; 2x4 + 4x4; 0,30 mm; ex. Shunda 41.99 m2 20,000.00 32,500.00 839,850.00 1,364,756.25
2 Panel Plafond Gypsum Board; 8 mm; ex. Gyproc; finish Cornice + kassa 41.99 m2 15,000.00 21,944.44 629,887.50 921,502.08
0.00
B Plafond luar 0.00
1 Rangka Plafond Hollow; 2x4 + 4x4; 0,30 mm; ex. Shunda 30.07 m1 20,000.00 32,500.00 601,399.05 977,273.46
2 Panel Plafond (incld.) GRC Board; 4 mm; ex. Versa; finish Cornice + kassa 30.07 m1 15,000.00 21,944.44 451,049.29 659,868.41
SUBTOTAL 2,522,185.85 3,923,400.20
B Carport
1 Stepping Site mix conc; B-0; T.8 cm + Wiremesh m-5 (1x); finish roll 1.08 m3 337,500.00 705,970.00 364,500.00 762,447.60
SUBTOTAL 3,529,132.57 5,487,552.98
Total Harga
No. Item Pekerjaan Spesifikasi Sat.
Upah (Rp) M'tl (Rp) Upah (Rp) M'tl (Rp)
II PEK. TANAH
1 Galian Tanah Pondasi Manual 10.80 m3 56,401.99 0.00 609,141.45 -
2 Urugan Tanah ex. Galian Termasuk perapihan & Perataan tanah sisa galian (disekitar) 5.40 m3 43,048.05 0.00 232,459.45 -
SUBTOTAL 841,600.91 -
B Kolom (K)
1 Kolom Beton (K1) Site mix; setara k-175; uk. 100x100; 4P8 + P4-200; FL. -0,50 0.67 m3 1,054,857.27 3,516,190.91 701,480.09 2,338,266.95
- -
C Balok (B) - -
1 Ring Balok (RB) Site mix; setara k-175; uk. 120x150; TOC. +3,40 ~ +4,00 0.81 m3 707,216.47 2,357,388.25 572,845.34 1,909,484.48
2 Ring Balok Sopi-sopi (RB) Site mix; setara k-175; uk. 120x150; TOC. +5,90 0.43 m3 707,216.47 2,357,388.25 305,743.74 1,019,145.81
3 BD (Balok Opening) Site mix; setara k-175; uk. 100x150; TOC. +2,50 0.09 m3 1,054,857.27 3,516,190.91 94,937.15 316,457.18
D Plat (S)
1 Kanopi Teras Depan (S1) Site mix; setara k-200; Tb.100; TOC. +2,58 0.45 m3 1,423,194.21 1,778,992.77 640,437.40 800,546.75
2 Plat Meja Dapur Site mix; setara k-200; Tb.100; TOC. +2,80 0.16 m3 889,496.38 1,778,992.77 142,319.42 284,638.84
E Finishing Expose
1 Kanopi Teras Depan (S1) Konvensional; Mortar Acian 4.50 m2 32,000.00 23,022.50 144,000.00 103,601.25
2 Meja Dapur Konvensional; Mortar Acian 1.60 m2 32,000.00 23,022.50 51,200.00 36,836.00
3 Tali air Tanopi & Dak Teras Konvensional; uk. 1 x 1 cm 3.60 m1 32,000.00 0.00 115,200.00 -
SUBTOTAL 4,609,163.11 12,405,321.82
B Pasangan bata
1 Pasangan Dinding Konvensional; Pas. 1/2 bata; 1:4 139.70 m2 20,000.00 45,760.00 2,793,942.00 6,392,539.30
2 Pasangan Dinding (sopi2) Konvensional; Pas. 1/2 bata; 1:4 23.57 m2 17,000.00 45,760.00 400,746.67 1,078,715.73
3 Pasangan Dinding / Batas Kavling Konvensional; Pas. 1/2 bata; 1:4 8.88 m2 20,000.00 45,760.00 177,600.00 406,348.80
C Plesteran
1 Plesteran Dinding dalam Konvensional; 1:4 139.65 m2 17,000.00 12,210.00 2,373,966.70 1,705,066.67
2 Plesteran Dinding luar (depan) Konvensional; 1:4 24.41 m2 17,000.00 12,210.00 414,885.00 297,985.05
3 Plesteran Dinding luar (belakang) Konvensional; 1:4 26.93 m2 17,000.00 12,210.00 457,837.20 328,834.84
4 Plesteran Dinding luar (samping kiri) Konvensional; 1:4 36.88 m2 17,000.00 12,210.00 626,903.33 450,264.10
y 8.39 m2
5 Plesteran Dinding luar (samping kanan) Konvensional; 1:4 41.91 m2 17,000.00 12,210.00 712,441.67 511,700.75
y 10.65
Total Harga
No. Item Pekerjaan Spesifikasi Sat.
Upah (Rp) M'tl (Rp) Upah (Rp) M'tl (Rp)
6 Plesteran Pagar / Batas Kavling Konvensional; 1:4 8.88 m2 17,000.00 12,210.00 150,960.00 108,424.80
Total Harga
No. Item Pekerjaan Spesifikasi Sat.
Upah (Rp) M'tl (Rp) Upah (Rp) M'tl (Rp)
7 Relief Façade & Penebalan Konvensional (termasuk tali air) 5.40 m2 37,000.00 57,970.00 199,800.00 313,038.00
D Acian/finishing
1 Acian/finishing Dinding dalam Konvensional; Mortar Acian 139.65 m2 15,000.00 10,812.50 2,094,676.50 1,509,912.64
2 Acian/finishing Dinding luar (depan) Konvensional; Mortar Acian 24.41 m2 15,000.00 10,812.50 366,075.00 263,879.06
3 Acian/finishing Dinding luar (belakang) Konvensional; Mortar Acian 26.93 m2 15,000.00 10,812.50 403,974.00 291,197.93
4 Acian/finishing Dinding luar (samping kiri) Konvensional; 1:4 36.88 m2 15,000.00 10,812.50 553,150.00 398,728.96
5 Acian/finishing Dinding luar (samping kanan) Konvensional; 1:4 41.91 m2 15,000.00 10,812.50 628,625.00 453,133.85
6 Acian/finishing Pagar/batas kavling Konvensional; Mortar Acian 8.88 m2 15,000.00 10,812.50 133,200.00 96,015.00
SUBTOTAL 13,460,783.07 16,082,325.48
V PEKERJAAN ATAP
1 Rangka Baja ringan C75-0,65 + 30-0,45; ex. Union/Metro Truss/ K-Steel 66.91 m2 25,250.00 84,166.67 1,689,601.13 5,632,003.76
2 Pasangan Genteng Badan Metal pasir; Inspiro Charcoal; tb. 0.30 mm 66.91 m2 11,290.91 112,909.09 755,530.01 7,555,300.10
3 Pasangan Nok Atap Metal pasir; Nok Alpha Charcoal Black 914 6.50 m1 6,250.00 31,250.00 40,625.00 203,125.00
4 Pasangan Nok Samping Metal pasir; Nok Samping Charcoal Black 110 16.57 m1 6,954.55 23,181.82 115,236.49 384,121.63
5 Pasangan List plank GRC plank; Polos; 8 mm 30.07 m1 9,600.00 19,200.00 288,671.55 577,343.09
SUBTOTAL 2,889,664.17 14,351,893.59
VI INSTALASI LISTRIK
A Pipa Sparing
1 Sparing SR Pipa PVC; Dia. 1"; ex. Wavin D - ls 0.00 100,000.00 - -
B Panel
1 Panel box Box 4 grup (Tanam); ex. Presto 1.00 set 50,000.00 150,000.00 50,000.00 150,000.00
2 MCB 1 x20A pole; 1x10A + 1x6A 1.00 set 50,000.00 120,000.00 50,000.00 120,000.00
3 Kabel Toevoer ex. Extrana, NYM 3x4 mm2 5.00 m1 25,000.00 60,000.00 125,000.00 300,000.00
4 Aarde/Grounding BC 6 mm; minimum 0,5 ohm 1.00 ttk 100,000.00 350,000.00 100,000.00 350,000.00
C Lampu
1 Instalasi titik lampu ex. Extrana, NYM 3 x 1,5 mm; saklar Boss; B20; B21(B22)/1/2A 7.00 ttk 27,083.33 108,333.33 189,583.33 758,333.33
E Stop Kontak
1 Instalasi Stop kontak ex. Extrana, NYM 3 x 2,5 mm; Boss; B20; B20426/16S 5.00 ttk 29,708.33 118,833.33 148,541.67 594,166.67
F Sertifikat Laik Operasi (SLO) ex. PPLN 1.00 ls 300,000.00 0.00 300,000.00 -
SUBTOTAL 963,125.00 2,272,500.00
IX PLAFOND
A Plafond dalam
1 Rangka Plafond Hollow; 2x4 + 4x4; 0,30 mm; ex. Shunda 41.99 m2 20,000.00 32,500.00 839,850.00 1,364,756.25
2 Panel Plafond Gypsum Board; 8 mm; ex. Gyproc; finish Cornice + kassa 41.99 m2 15,000.00 21,944.44 629,887.50 921,502.08
B Plafond luar
1 Rangka Plafond Hollow; 2x4 + 4x4; 0,30 mm; ex. Shunda 30.07 m1 20,000.00 32,500.00 601,399.05 977,273.46
2 Panel Plafond (incld.) GRC Board; 4 mm; ex. Versa; finish Cornice + kassa 30.07 m1 15,000.00 21,944.44 451,049.29 659,868.41
SUBTOTAL 2,522,185.85 3,923,400.20
B Carport
1 Stepping Site mix conc; B-0; T.8 cm + Wiremesh m-5 (1x); finish roll 1.08 m3 337,500.00 705,970.00 364,500.00 762,447.60
SUBTOTAL 3,529,132.57 5,487,552.98
BLOK SH-10 N0. 03 (STD) BLOK SH-10 N0. 05 (STD) BLOK SH-10 N0. 06 (STD) BLOK SH-10 N0. 07 (STD) BLOK SH-10 N0. 02 (KHUSUS)
BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
NO. URAIAN PEKERJAAN
PEK. RENC.
MG. LALU MG. INI MG. LALU MG. INI MG. LALU MG. INI MG. LALU MG. INI MG. LALU MG. INI
I PENDAHULUAN & PERSIAPAN 4.65 1.51 0.77 0.77 0.77 0.77 4.04 4.04 4.08 4.08 0.73 0.73
II PEK. TANAH 0.83 0.85 - - - - 0.83 0.83 0.83 0.83 - -
III PEKERJAAN PONDASI & BETON 17.24 10.49 - - - - 12.67 14.98 14.60 14.98 - -
IV PASANGAN & FINISHING DINDING 28.60 - - - - - 8.70 11.45 13.95 15.43 - -
V PEKERJAAN ATAP 18.93 - - - - - - - - - - -
VI INSTALASI LISTRIK 3.55 - - - - - - - - - - -
VII JARINGAN AIR BERSIH 1.28 - - - - - - 0.24 - 0.24 - -
VIII JARINGAN AIR KOTOR 4.99 - - - - - 1.63 1.63 1.63 1.63 - -
IX PLAFOND 7.08 - - - - - - - - - - -
X WATERPROOFING (Incld. Screeding) 0.34 - - - - - - - - - - -
XI LANTAI & KERAMIK 9.90 - - - - - - - - - - -
XII LAIN-LAIN & TAMBAHAN 2.60 - - - - - - - - - - -
100.00 12.85 0.77 0.77 0.77 0.77 27.86 33.17 35.09 37.19 0.73 0.73
BLOK SH-10 N0. 08 (KHUSUS) BLOK SH-10 N0. 26 (KHUSUS) BLOK SH-11 N0. 17 (KHUSUS)
BOBOT BOBOT
NO. URAIAN PEKERJAAN
PEK. RENC.
BOBOT BOBOT BOBOT CITRA MENDALO PRIMA KSO
MG. LALU MG. INI MG. LALU MG. INI MG. LALU MG. INI
MENGETAHUI
I PENDAHULUAN & PERSIAPAN 4.41 1.51 3.87 3.87 0.73 0.73 4.03 4.03
II PEK. TANAH 0.88 0.85 0.88 0.88 - - 0.88 0.88
III PEKERJAAN PONDASI & BETON 17.73 10.49 13.75 13.91 - - 15.54 15.54
IV PASANGAN & FINISHING DINDING 30.78 - 12.43 14.68 - - 14.38 16.51 EDDY PURWANTO
V PEKERJAAN ATAP 17.97 - - - - - 16.63 16.63 KASIE BANGUNAN
VI INSTALASI LISTRIK 3.37 - - - - - - - DIPERIKSA
VII JARINGAN AIR BERSIH 1.22 - - 0.23 - - - 0.23
VIII JARINGAN AIR KOTOR 4.74 - 1.73 1.73 - - 1.73 1.73
IX PLAFOND 6.72 - - - - - - -
X WATERPROOFING (Incld. Screeding) 0.33 - - - - - - - GORDON
XI LANTAI & KERAMIK 9.40 - - - - - - - PENGAWAS LAPANGAN
XII LAIN-LAIN & TAMBAHAN 2.47 - - - - - - - DIBUAT CV. BANGUN JAYA ABADI
100.00 12.85 32.66 35.30 0.73 0.73 53.19 55.55
RATA-RATA PRESTASI S/D MINGGU INI 20.53
RENCANA S/D MINGGU INI 12.85
SELISIH RENCANA DAN REALISASI 7.67 DANI NOPRIADY
RATA-RATA PRESTASI S/D MINGGU LALU 18.98 PELAKSANA LAPANGAN
CITRA MENDALO PRIMA KSO
BLOK SH-10 N0. 03 (STD) BLOK SH-10 N0. 05 (STD) BLOK SH-10 N0. 06 (STD) BLOK SH-10 N0. 07 (STD)
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
II PEK. TANAH
1 Galian Tanah Pondasi 0.60 - - - - - - - - 100.00 0.60 100.00 0.60 100.00 0.60 100.00 0.60
2 Urugan Tanah ex. Galian 0.23 - - - - - - - - 100.00 0.23 100.00 0.23 100.00 0.23 100.00 0.23
TOTAL 0.83 - - - - 0.83 0.83 0.83 0.83
V PEKERJAAN ATAP
1 Rangka Baja ringan 8.04 - - - - - - - - - - - - - - - -
2 Pasangan Genteng Badan 9.13 - - - - - - - - - - - - - - - -
3 Pasangan Nok Atap 0.27 - - - - - - - - - - - - - - - -
4 Pasangan Nok Samping 0.55 - - - - - - - - - - - - - - - -
5 Pasangan List plank 0.95 - - - - - - - - - - - - - - - -
TOTAL 18.93 - - - - - - - -
BLOK SH-10 N0. 03 (STD) BLOK SH-10 N0. 05 (STD) BLOK SH-10 N0. 06 (STD) BLOK SH-10 N0. 07 (STD)
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
VI INSTALASI LISTRIK
A Pipa Sparing
1 Sparing SR
B Panel
1 Panel box 0.22 - - - - - - - - - - - - - - - -
2 MCB 0.19 - - - - - - - - - - - - - - - -
3 Kabel Toevoer 0.47 - - - - - - - - - - - - - - - -
4 Aarde/Grounding 0.49 - - - - - - - - - - - - - - - -
C Lampu
1 Instalasi titik lampu 1.04 - - - - - - - - - - - - - - - -
E Stop Kontak
1 Instalasi Stop kontak 0.82 - - - - - - - - - - - - - - - -
F Sertifikat Laik Operasi (SLO) 0.33 - - - - - - - - - - - - - - - -
TOTAL 3.55 - - - - - - - -
IX PLAFOND
A Plafond dalam
1 Rangka Plafond 2.42 - - - - - - - - - - - - - - - -
2 Panel Plafond 1.70 - - - - - - - - - - - - - - - -
B Plafond luar
1 Rangka Plafond 1.73 - - - - - - - - - - - - - - - -
2 Panel Plafond (incld.) 1.22 - - - - - - - - - - - - - - - -
TOTAL 7.08 - - - - - - - -
JUMLAH 100.00 0.77 0.77 0.77 0.77 27.86 33.17 35.09 37.19
LAPORAN PROGGRES MINGGUAN KONTRAKTOR
BLOK / NO. : SH-10 No. 02, 03, 05, 06, 07, 08, 26 & SH-11 No. 17 ( 8 UNIT )
PROGRES PEKERJAAN PERIODE : 26 AGUSTUS 2019 S/D 01 SEPTEMBER 2019
BLOK SH-10 N0. 02 (KHUSUS) BLOK SH-10 N0. 08 (KHUSUS) BLOK SH-10 N0. 26 (KHUSUS) BLOK SH-11 N0. 17 (KHUSUS)
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
II PEK. TANAH
1 Galian Tanah Pondasi 0.63 - - - - 100.00 0.63 100.00 0.63 - - - - 100.00 0.63 100.00 0.63
2 Urugan Tanah ex. Galian 0.24 - - - - 100.00 0.24 100.00 0.24 - - - - 100.00 0.24 100.00 0.24
TOTAL 0.88 - - 0.88 0.88 - - 0.88 0.88
V PEKERJAAN ATAP
1 Rangka Baja ringan 7.63 - - - - - - - - - - - - 95.00 7.25 95.00 7.25
2 Pasangan Genteng Badan 8.66 - - - - - - - - - - - - 90.00 7.79 90.00 7.79
3 Pasangan Nok Atap 0.25 - - - - - - - - - - - - 95.00 0.24 95.00 0.24
4 Pasangan Nok Samping 0.52 - - - - - - - - - - - - 95.00 0.49 95.00 0.49
5 Pasangan List plank 0.90 - - - - - - - - - - - - 95.00 0.86 95.00 0.86
TOTAL 17.97 - - - - - - 16.63 16.63
BLOK SH-10 N0. 02 (KHUSUS) BLOK SH-10 N0. 08 (KHUSUS) BLOK SH-10 N0. 26 (KHUSUS) BLOK SH-11 N0. 17 (KHUSUS)
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
VI INSTALASI LISTRIK
A Pipa Sparing
1 Sparing SR
B Panel
1 Panel box 0.21 - - - - - - - - - - - - - - - -
2 MCB 0.18 - - - - - - - - - - - - - - - -
3 Kabel Toevoer 0.44 - - - - - - - - - - - - - - - -
4 Aarde/Grounding 0.47 - - - - - - - - - - - - - - - -
C Lampu
1 Instalasi titik lampu 0.99 - - - - - - - - - - - - - - - -
E Stop Kontak
1 Instalasi Stop kontak 0.77 - - - - - - - - - - - - - - - -
F Sertifikat Laik Operasi (SLO) 0.31 - - - - - - - - - - - - - - - -
TOTAL 3.37 - - - - - - - -
IX PLAFOND
A Plafond dalam
1 Rangka Plafond 2.30 - - - - - - - - - - - - - - - -
2 Panel Plafond 1.62 - - - - - - - - - - - - - - - -
B Plafond luar
1 Rangka Plafond 1.64 - - - - - - - - - - - - - - - -
2 Panel Plafond (incld.) 1.16 - - - - - - - - - - - - - - - -
TOTAL 6.72 - - - - - - - -
JUMLAH 100.00 0.73 0.73 32.66 35.30 0.73 0.73 53.19 55.55
24,750,000
BLO
MINGGU LALU
PROGRES
STANDART KHUSUS
0.14 130,000.00 91,064,501.02 100,000.00 15.00
0.63 576,000.00 91,064,501.02 249,230.77 100.00
0.47 425,000.00 91,064,501.02 180,000.00
0.33 300,000.00 91,064,501.02 180,000.00
0.44 400,000.00 91,064,501.02 100,000.00
0.53 483,452.38 91,064,501.02 184,615.38 100.00
1.32 1,200,000.00 91,064,501.02 2,541,071.43
91,064,501.02
3.86 3,514,452.38
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
6.35 5,780,887.00 91,064,501.02
BLO
MINGGU LALU
PROGRES
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
#REF! #REF! 91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
#DIV/0! 210,000.00 -
#DIV/0!
0.02 19,800.00 91,064,501.02
0.04 39,000.00 91,064,501.02
91,064,501.02
91,064,501.02
#REF! #REF!
91,064,501.02
#REF! #REF!
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
91,064,501.02
#REF! #REF!
BLO
MINGGU LALU
PROGRES
#REF!
9,204,589.62
LAPORAN PROGGRES MINGGUAN KONTRAKTOR
BLOK / NO. : A-8/02 s/d 11 : SH-10 No. 02, 03, 05, 06, 07, 08, 26 & SH-11 No. 17 ( 8 UNIT )
LAPORAN PROGRES PEKERJAAN PERIOD : : 26 AGUSTUS 2019 S/D 01 SEPTEMBER 2019
A. Pekerjaan Persiapan
0.02 15.00 0.02 1 Pembersiha 1.000 ls ### ### - 0.11 15.00 0.02 15.00 0.02 15.00 0.02 15.00 0.02
0.27 100.00 0.27 2 Direksi kee 1.000 ls ### ### Ukuran 2,4 0.27 100.00 0.27 100.00 0.27 100.00 0.27 100.00 0.27
- 20.00 0.04 3 Air kerja 1.000 ls ### ### 0.20 20.00 20.00 0.04 - 20.00 0.04
- - ` 4 Listrik kerja 1.000 ls ### ### 0.20 - - - -
- - 5 Photo proy 1.000 ls ### ### - 0.11 - - - -
0.20 100.00 0.20 6 Keamanan 46.000 m' 0.00 - Keliling La 0.20 100.00 0.20 100.00 0.20 100.00 0.20 100.00 0.20
Peralatan dan Perlengkapan K3
B. PEK. TANAH
0.60 100.00 0.60 1 Galian Tan 13.420 m³ 0.00 - - 0.60 100.00 0.60 100.00 0.60 100.00 0.60 100.00 0.60
0.03 15.00 0.03 2 Urugan Tan 45.250 m² 0.00 - - 0.23 15.00 0.03 15.00 0.03 15.00 0.03 15.00 0.03
0.63 0.63 TOTAL - 0.83 0.63 0.63 0.63 0.63
C. Pekerjaan Beton
- 1 Pondasi & S 1.370 m³ 0.00 - site mix 1: - 100.00 - 100.00 - 100.00 - 100.00 -
0.48 15.00 0.48 2 Pondasi Ro 1.370 m³ 0.00 - site mix 1: 3.17 15.00 0.48 15.00 0.48 15.00 0.48 15.00 0.48
0.12 15.00 0.12 3 Pondasi Rol 1.370 m³ 0.00 - site mix 1: 0.83 15.00 0.12 15.00 0.12 15.00 0.12 15.00 0.12
- - 4 Sloof (S) 1.370 m³ 0.00 - site mix 1: 3.01 - - - -
D. Pekerjaan Dinding
TOTAL -
H. Pekerjaan Atap
- - 1 Instalasi Pi 1.370 m³ 0.00 - site mix 1: 0.81 - - - -
- - 2 Pasang Bak 1.370 m³ 0.00 - site mix 1: 0.22 - - - -
- - 3 Kran Dindi 1.370 m³ 0.00 - site mix 1: 0.07 - - - -
- - 4 Kran Kitche 1.370 m³ 0.00 - site mix 1: 0.12 - - - -
- - 5 Kran Taman 1.370 m³ 0.00 - site mix 1: 0.06 - - - -
- - TOTAL - 1.28 - - - -
- - TOTAL - 4.12 - - - -
- - TOTAL - 4.12 - - - -
- - TOTAL - - - - - -
BLOK A8 N0. 05 Harga Satuan
Total Harga BLOK A8 N0. 06 BLOK A8 N0. 07
BOBOT
MINGGU LALU MINGGU INI NO.
URAIAN PEKERJAAN
Vol. Sat. Spesifikasi MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
BOBOT PROGRES BOBOT ( Rp. ) ( Rp. ) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
A. Pekerjaan Persiapan
15.00 0.02 15.00 0.02 1 Pembersiha 1.000 ls ### ### - 0.11 15.00 0.02 15.00 0.02 15.00 0.02 15.00 0.02
100.00 0.27 100.00 0.27 2 Direksi kee 1.000 ls ### ### - 0.27 100.00 0.27 100.00 0.27 100.00 0.27 100.00 0.27
- 20.00 0.04 3 Air kerja 1.000 ls ### ### - 0.20 - 20.00 0.04 - 20.00 0.04
- - 4 Listrik kerja 1.000 ls ### ### - 0.20 - - - -
- - 5 Photo proy 1.000 ls ### ### - 0.11 - - - -
100.00 0.20 100.00 0.20 6 Keamanan 1.000 ls ### ### - 0.20 100.00 0.20 100.00 0.20 100.00 0.20 100.00 0.20
Peralatan dan Perlengkapan K3
C. Pekerjaan Beton
100.00 - 100.00 - 1 Pondasi & S 1.000 ls ### ### - - 100.00 - 100.00 - 100.00 - 100.00 -
15.00 0.48 15.00 0.48 2 Pondasi Ro 1.000 ls ### ### - 3.17 15.00 0.48 15.00 0.48 15.00 0.48 15.00 0.48
15.00 0.12 15.00 0.12 3 Pondasi Rol 1.000 ls ### ### - 0.83 15.00 0.12 15.00 0.12 15.00 0.12 15.00 0.12
- - 4 Sloof (S) 1.000 ls ### ### - 3.01 - - - -
D. Pekerjaan Dinding
TOTAL ###
H. Pekerjaan Atap
- - 1 Instalasi Pi 1.000 ls ### ### - 0.81 - - - -
- - 2 Pasang Bak 1.000 ls ### ### - 0.22 - - - -
- - 3 Kran Dindi 1.000 ls ### ### - 0.07 - - - -
- - 4 Kran Kitche 1.000 ls ### ### - 0.12 - - - -
- - 5 Kran Taman 1.000 ls ### ### - 0.06 - - - -
- - TOTAL ### 1.28 - - - -
- - TOTAL - - - - - -
BLOK A8 N0. 08 Harga Satuan
Total Harga BLOK A8 N0. 09 BLOK A8 N0. 10
BOBOT
MINGGU LALU MINGGU INI NO.
URAIAN PEKERJAAN
Vol. Sat. Spesifikasi MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI
PEK.
PROGRES BOBOT PROGRES BOBOT ( Rp. ) ( Rp. ) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
100.00 0.60 100.00 0.60 0.60 ### 0.60 ### ### 0.5990479
15.00 0.03 15.00 0.03 0.23 0.23 ###
0.63 0.63 0.83
- - 3.34 #DIV/0! -
11.76
- - #REF! #REF! #REF!
- - #DIV/0!
- - #REF! #REF! ###
- - #REF! #REF! 60,750.00
- - #REF! #REF!
#REF! #REF! 14700000 #REF! ###
BLOK A8 N0. 11
MINGGU LALU MINGGU INI Ket
PROGRES BOBOT PROGRES BOBOT
###
SBO ###
SBO ###
SBO ###
SBO
SBO
SBO
SBO
- - #REF! #REF!
- - #REF! #REF!
- - #REF! #REF!
- - #REF! #REF!
- - #REF! #REF!
- - #REF!
- - #REF! #REF!
- - #DIV/0!
- - #DIV/0! -
- - #REF! #REF!
- - #REF! #REF!
- - #REF! #REF!
- - #REF! #REF!
- - #REF!
BLOK A8 N0. 11
MINGGU LALU MINGGU INI Ket
PROGRES BOBOT PROGRES BOBOT
- - #DIV/0! -
- - #DIV/0!
- - #DIV/0! -
- - #REF! #REF!
- - #REF!
- - #REF!
- - #REF!
BLOK A8 N0. 11
MINGGU LALU MINGGU INI Ket
PROGRES BOBOT PROGRES BOBOT
- - #DIV/0! -
Pj Pond 65.65
Rollag 8.65
1.477 4.5790875
###
TIME SCHEDULLE
TYPE CANOLA SPRINGHILL TAHAP- III
BLN JULI '19 BULAN AGUSTUS 2019 BULAN SEPTEMBER 2019 BULAN OKTOBER 2019 BULAN NOPEMBER 2019 BULAN DESEMBER 2019
NO. URAIAN PEKERJAAN BOBOT KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I PENDAHULUAN & PERSIAPAN 4.53 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38
III PEKERJAAN PONDASI & BETON 17.48 1.75 1.75 3.50 3.50 3.50 3.50
IV PASANGAN & FINISHING DINDING 29.69 3.71 3.71 3.71 3.71 3.71 3.71 7.42
DANI NOPRIADY
PELAKSANA LAPANGAN