ANALISA HARGA SATUAN PEKERJAAN

HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)

Resiko 10.00%

1 Bowplank/m' Pasang 1/2

Kayu balok bekisting 0.0014 m3 1,632,000.00 2,350.08


Kayu papan bekisting 0.0024 m3 1,683,000.00 4,039.20
Paku 0.0200 kg 12,240.00 244.80
Upah tukang kayu 0.0460 Hr 84,150.00 3,870.90
Upah pekerja 0.0230 Hr 71,400.00 1,642.20
Upah Mandor 0.0023 Hr 102,000.00 234.60
Alat bantu 1.0000 ls 500.00 500.00
Jumlah Harga 12,881.78
Resiko 10.00% 1,288.18
Total 14,169.96
Dibulatkan 14,170.00

2 Galian Tanah

Upah Pekerja 0.8000 Hr 71,400.00 57,120.00


Upah Mandor 0.0400 Hr 102,000.00 4,080.00
Alat bantu 1.0000 ls 500.00 500.00
Jumlah Harga 61,700.00
Resiko 10.00% 6,170.00
Total 67,870.00
Dibulatkan 67,870.00

3 Urug pasir

Pasir pasang 1.2000 m3 56,100.00 67,320.00


Upah Pekerja 0.3833 Hr 71,400.00 27,370.00
Upah Mandor 0.0192 Hr 102,000.00 1,955.00
Alat bantu 1.0000 ls 515.00 515.00
Jumlah Harga 97,160.00
Resiko 10.00% 9,716.00
Total 106,876.00
Dibulatkan 106,880.00

4 Urug tanah

Tanah urug 1.2000 m3 20,400.00 24,480.00


Upah Pekerja 0.3833 Hr 71,400.00 27,370.00
Upah Mandor 0.0192 Hr 102,000.00 1,955.00
Alat bantu 1.0000 ls 772.50 772.50
Jumlah Harga 54,577.50
Resiko 10.00% 5,457.75
Total 60,035.25
Dibulatkan 60,040.00

5 Pemadatan tanah (m2)

Upah Pekerja 0.0575 Hr 71,400.00 4,105.50


Upah Mandor 0.0029 Hr 102,000.00 293.25
Alat bantu 1.0000 ls 20,600.00 20,600.00
Jumlah Harga 24,998.75
Resiko 10.00% 2,499.88
Total 27,498.63
Dibulatkan 27,500.00

6 Buang tanah sisa galian (keluar lokasi)

Upah Pekerja 0.3833 Hr 71,400.00 27,370.00


Upah Mandor 0.0192 Hr 102,000.00 1,955.00
Alat bantu Termasuk Truk 1.0000 ls 20,600.00 20,600.00
Jumlah Harga 49,925.00
Resiko 10.00% 4,992.50
Total 54,917.50
Dibulatkan 54,920.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)

7 Urugan tanah kembali

Upah Pekerja 0.2875 Hr 71,400.00 20,527.50


Upah Mandor 0.0144 Hr 102,000.00 1,466.25
Alat bantu 1.0000 ls 2,000.00 2,000.00
Jumlah Harga 23,993.75
Resiko 10.00% 2,399.38
Total 26,393.13
Dibulatkan 26,390.00

8 Urugan Pasir t = 10 cm /m3

Pasir Urug 1.2000 m3 56,100.00 67,320.00


Upah Pekerja 0.3833 Hr 71,400.00 27,370.00
Upah Mandor 0.0153 Hr 102,000.00 1,564.00
Alat bantu 1.0000 ls 515.00 515.00
Jumlah Harga 96,769.00
Resiko 10.00% 9,676.90
Total 106,445.90
Dibulatkan 106,450.00

9 Upah untuk lantai kerja beton


Upah Tukang Batu 0.4600 Hr 66,300.00 30,498.00
Upah Pekerja 2.7600 Hr 71,400.00 197,064.00
Upah Kepala Tukang Batu 0.0460 Hr - -
Upah Mandor 0.0230 Hr 102,000.00 2,346.00
Jumlah Harga 229,908.00
Dibulatkan 229,908.00

10 Upah pengecoran manual molen


Upah Tukang Batu 0.3830 Hr 66,300.00 25,392.90
Upah Pekerja 2.2980 Hr 71,400.00 164,077.20
Upah Kepala Tukang Batu 0.0383 Hr - -
Upah Mandor 0.0192 Hr 102,000.00 1,953.30
Jumlah Harga 191,423.40
Dibulatkan 191,423.00

11 Lantai Kerja Beton


Semen PC @ 50 kg 4.6000 zak 64,260.00 295,596.00
Pasir beton 0.4500 m3 56,100.00 25,245.00
Batu kerikil 0.7500 m3 255,000.00 191,250.00
Upah lantai kerja beton 1.0000 Hr 191,423.00 191,423.00
Alat bantu molen 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 704,514.00
Resiko 10.00% 70,451.40
Total 774,965.40
Dibulatkan 774,970.00

12 Cor beton adukan 1 : 2 : 3 / M 3


Semen PC @ 50 kg 6.5200 Zak 64,260.00 418,975.20
Pasir beton 0.4500 m3 56,100.00 25,245.00
Batu kerikil 0.8400 m3 255,000.00 214,200.00
Upah pengecoran manual molen 1.0000 Hr 191,423.00 191,423.00
Alat bantu molen 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 850,843.20
Resiko 10.00% 85,084.32
Total 935,927.52
Dibulatkan 935,930.00

13 Cor beton adukan 1 : 3 : 5 / M 3


Semen PC @ 50 kg 4.6000 zak 64,260.00 295,596.00
Pasir beton 0.4500 m3 56,100.00 25,245.00
Batu kerikil 0.7500 m3 255,000.00 191,250.00
Upah pengecoran manual molen 1.0000 Hr 191,423.00 191,423.00
Alat bantu molen 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 704,514.00
Resiko 10.00% 70,451.40
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
Total 774,965.40
Dibulatkan 774,970.00

14 Upah Fabrikasi Besi U 24


Upah Tukang besi 0.0125 Hr 66,300.00 828.75
Upah Kepala Tukang besi 0.0013 Hr - -
Upah Pekerja 0.0063 Hr 71,400.00 446.25
Upah Mandor 0.0006 Hr 102,000.00 63.75
Jumlah Harga 1,338.75
Dibulatkan 1,339.00

15 Upah Fabrikasi Besi U 39


Upah Tukang besi 0.0120 Hr 66,300.00 795.60
Upah Kepala Tukang besi 0.0012 Hr - -
Upah Pekerja 0.0060 Hr 71,400.00 428.40
Upah Mandor 0.0006 Hr 102,000.00 61.20
Jumlah Harga 1,285.20
Dibulatkan 1,285.00

16 Besi beton U 24 / kg
Besi beton u24 1.0300 Kg 8,466.00 8,719.98
Kawat ikat 0.0100 kg 15,300.00 153.00
Loading & un loading 1.0000 kg 40.00 40.00
Upah Fabrikasi Besi U 24 1.0000 ls 1,339.00 1,339.00
Jumlah Harga 10,251.98

17 Besi beton U 39 / kg
Besi beton u39 1.0300 Kg 8,466.00 8,719.98
Kawat ikat 0.0100 kg 15,300.00 153.00
Loading & un loading 1.0000 kg 40.00 40.00
Upah Fabrikasi Besi U 39 1.0000 ls 1,285.00 1,285.00
Jumlah Harga 10,197.98

18 Upah pasang wire mesh


Upah Tukang besi 0.0254 Hr 66,300.00 1,680.89
Upah Kepala Tukang besi 0.0051 Hr - -
Upah Pekerja 0.0127 Hr 71,400.00 905.09
Upah Mandor 0.0025 Hr 102,000.00 258.60
Jumlah Harga 2,844.58
Dibulatkan 2,845.00

19 Wire Mesh M8
Wire mesh M8 1.1000 m2 43,445.00 47,789.50
Kawat ikat 0.0025 kg 15,300.00 38.25
Upah Pasang Wire Mesh 1.0000 m2 2,845.00 2,845.00
Jumlah Harga 50,672.75
Resiko 10.00% 5,067.28
Total 55,740.03
Dibulatkan 55,740.00

20 Wire Mesh M7
Wire mesh M7 1.1000 m2 33,262.00 36,588.20
Kawat ikat 0.0025 kg 15,300.00 38.25
Upah Pasang Wire Mesh 1.0000 m2 2,845.00 2,845.00
Jumlah Harga 39,471.45
Resiko 10.00% 3,947.15
Total 43,418.60
Dibulatkan 43,420.00

21 Wire Mesh M5
Wire mesh M5 1.1000 m2 24,437.00 26,880.70
Kawat ikat 0.0025 kg 15,300.00 38.25
Upah Pasang Wire Mesh 1.0000 m2 2,845.00 2,845.00
Jumlah Harga 29,763.95
Resiko 10.00% 2,976.40
Total 32,740.35
Dibulatkan 32,740.00

22 Upah Bekisting balok praktis (m2)


Upah Tukang Kayu 0.0767 Hr 84,150.00 6,451.50
Upah Kepala Tukang Kayu 0.0077 Hr - -
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
Upah Pekerja 0.1150 Hr 71,400.00 8,211.00
Upah Mandor 0.0015 Hr 102,000.00 156.40
14,818.90
14,810.00

23 Upah Bekisting Kolom Praktis (m2)


Upah Tukang Kayu 0.0767 Hr 84,150.00 6,451.50
Upah Kepala Tukang Kayu 0.0077 Hr - -
Upah Pekerja 0.1150 Hr 71,400.00 8,211.00
Upah Mandor 0.0015 Hr 102,000.00 156.40
Total 14,818.90
Dibulatkan 14,810.00

24 Upah Bekisting Kolom Struktur (m2)


Upah Tukang Kayu 0.1917 Hr 84,150.00 16,128.75
Upah Kepala Tukang Kayu 0.0192 Hr - -
Upah Pekerja 0.1917 Hr 71,400.00 13,685.00
Upah Mandor 0.0038 Hr 102,000.00 391.00
Jumlah Harga 30,204.75
Dibulatkan 30,200.00

25 Upah Bekisting Balok Struktur (m2)


Upah Tukang Kayu 0.1643 Hr 84,150.00 13,824.64
Upah Kepala Tukang Kayu 0.0164 Hr - -
Upah Pekerja 0.1643 Hr 71,400.00 11,730.00
Upah Mandor 0.0033 Hr 102,000.00 335.14
Jumlah Harga 25,889.79
Dibulatkan 25,880.00

26 Upah Bekisting Plat Struktur (m2)


Upah Tukang Kayu 0.1278 Hr 84,150.00 10,752.50
Upah Kepala Tukang Kayu 0.0128 Hr - -
Upah Pekerja 0.1278 Hr 71,400.00 9,123.33
Upah Mandor 0.0026 Hr 102,000.00 260.67
Jumlah Harga 20,136.50
Dibulatkan 20,130.00

27 Upah bongkar bekisting dan pembersihan (m2)


Upah Tukang Kayu 0.0460 Hr 84,150.00 3,870.90
Upah Kepala Tukang Kayu 0.0046 Hr - -
Upah Pekerja 0.0460 Hr 71,400.00 3,284.40
Upah Mandor 0.0009 Hr 102,000.00 93.84
Jumlah Harga 7,249.14
Dibulatkan 7,240.00

28 Bekisting Kolom 0.0267


dipakai 3x
Multipleks 12mm 0.0965 lbr 127,500.00 12,297.45
kayu balok bekisting 5/7 0.0075 m3 1,632,000.00 12,185.60
kayu balok bekisting 5/10 0.0083 m3 1,632,000.00 13,600.00
Paku 0.3000 kg 12,240.00 3,672.00
Upah Bekisting Kolom Struktur 1.0000 m2 30,200.00 30,200.00
Upah bongkar bekisting dan pembersihan 1.0000 m2 7,240.00 7,240.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 80,195.05
Resiko 10.00% 8,019.51
Total 88,214.56
Dibulatkan 88,210.00

29 Bekisting kayu balok struktur 0.0267


dipakai 3x
Multipleks 12mm 0.0965 lbr 127,500.00 12,297.45
kayu balok bekisting 5/7 0.0093 m3 1,632,000.00 15,232.00
kayu balok bekisting 5/10 0.0056 m3 1,632,000.00 9,066.67
Paku 0.3000 kg 12,240.00 3,672.00
Upah Bekisting Balok Struktur 1.0000 m2 25,880.00 25,880.00
Upah bongkar bekisting dan pembersihan 1.0000 m2 7,240.00 7,240.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 74,388.12
Dibulatkan 74,390.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)

30 Bekisting plat struktur


dipakai 3x
Multipleks 12mm 0.0965 lbr 127,500.00 12,297.45
kayu balok bekisting 5/7 0.0058 m3 1,632,000.00 9,520.00
kayu balok bekisting 5/10 0.0056 m3 1,632,000.00 9,066.67
Paku 0.3000 kg 12,240.00 3,672.00
Upah Bekisting Plat Struktur 1.0000 m2 20,130.00 20,130.00
Upah bongkar bekisting dan pembersihan 1.0000 m2 7,240.00 7,240.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 62,926.12
Dibulatkan 62,930.00

31 Bekisting Sloof (Balok 200)


kayu papan bekisting 0.0048 m3 1,683,000.00 8,078.40
Paku 0.0010 kg 12,240.00 12.24
kayu balok bekisting 5/7 0.0020 m3 1,632,000.00 3,264.00
Upah Bekisting Sloof 0.5000 m2 25,880.00 12,940.00
Alat dan material bantu 1.0000 ls 500.00 500.00
Jumlah Harga 24,794.64
Dibulatkan 24,790.00

32 Bekisting kolom praktis(m')


Multipleks 12mm 0.0326 lbr 127,500.00 4,150.39
kayu balok bekisting 5/7 0.0045 m3 1,632,000.00 7,344.00
Paku 0.0200 kg 12,240.00 244.80
Upah Bekisting kolom praktis 0.3000 m2 14,810.00 4,443.00
Alat dan material bantu 1.0000 ls 500.00 500.00
Jumlah Harga 16,682.19
Dibulatkan 16,680.00

33 Bekisting kolom praktis(m')


kayu papan bekisting 0.0032 m3 1,683,000.00 5,385.60
kayu balok bekisting 5/7 0.0010 m3 1,632,000.00 1,632.00
Paku 0.0200 kg 12,240.00 244.80
Upah Bekisting kolom praktis 0.3000 m2 14,810.00 4,443.00
Alat dan material bantu 1.0000 ls 200.00 200.00
Jumlah Harga 11,905.40
Dibulatkan 11,910.00

34 Bekisting kolom Struktur


Multipleks 12mm 0.0651 lbr 127,500.00 8,300.78
kayu balok bekisting 5/7 0.0045 m3 1,632,000.00 7,344.00
Paku 0.0500 kg 12,240.00 612.00
Upah Bekisting balok praktis 0.6000 m2 14,810.00 8,886.00
Alat dan material bantu 1.0000 ls 500.00 500.00
Jumlah Harga 25,642.78
Dibulatkan 25,640.00

35 Sloop
Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Besi (4ø10, ø8-200) 151.3300 kg 10,251.98 1,551,432.13
Bekisting 3.3333 m2 25,640.00 85,466.67
Jumlah Harga 2,513,267.30
Resiko 10.00% 251,326.73
Total 2,764,594.03
Dibulatkan 2,764,000.00

36 Kolom Praktis (m3)


Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Besi (4ø10, ø8-200) 325.8000 kg 10,251.98 3,340,095.08
Bekisting 3.3333 m2 11,905.40 39,684.67
Jumlah Harga 4,256,148.25
Resiko 10.00% 425,614.82
Total 4,681,763.07
Dibulatkan 4,681,000.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
37 Kolom 100 x 200 k1
Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Besi (4ø12, ø8-200) 236.8500 kg 10,251.98 2,428,181.46
Bekisting 2.0000 m2 25,640.00 51,280.00
Jumlah Harga 3,355,829.96
Resiko 10.00% 335,583.00
Total 3,691,412.95
Dibulatkan 3,691,000.00

38 Balok 100 x 200


Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Besi (4ø12, ø8-200) 182.6500 kg 10,251.98 1,872,524.15
Bekisting 2.0000 m2 24,790.00 49,580.00
Jumlah Harga 2,798,472.64
Resiko 10.00% 279,847.26
Total 3,078,319.91
Dibulatkan 3,078,000.00

39 Slab (Dak/Kanopy)
Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Wire Mesh M5 100.0000 m2 32,740.00 3,274,000.00
Bekisting 11.4000 m2 62,930.00 717,402.00
Jumlah Harga 4,867,770.50
Resiko 10.00% 486,777.05
Total 5,354,547.55
Dibulatkan 5,354,000.00

40 Beton Carport
Beton site mix 1 : 2 : 3 1.0300 m3 850,843.20 876,368.50
Wire Mesh M5 100.0000 m2 32,740.00 3,274,000.00
Bekisting 11.4000 m2 62,930.00 717,402.00
Jumlah Harga 4,867,770.50
Resiko 10.00% 486,777.05
Total 5,354,547.55
Dibulatkan 5,354,000.00

41 Upah pasangan 1/2 bata (m2)

Upah Tukang Batu 0.1278 hr 66,300.00 8,471.67


Upah Kepala Tukang Batu 0.0128 hr - -
Upah Pekerja 0.1278 hr 71,400.00 9,123.33
Upah Mandor 0.0064 hr 102,000.00 651.67
Jumlah Harga 18,246.67
Dibulatkan 18,250.00

42 1 M2 Pasangan dinding bata adukan 1 : 2

Semen PC @ 50 kg 0.4000 zak 76,500.00 30,600.00


Pasir pasang 0.0300 m3 37,740.00 1,132.20
Bata merah uk. 8 x 8 x 16 69.0000 bh 459.00 31,671.00
Upah Pasangan 1/2 bata 1.0000 m2 18,250.00 18,250.00
Alat bantu pasangan bata 1.0000 ls 500.00 500.00
Jumlah Harga 82,153.20
Resiko 10.00% 8,215.32
Total 90,368.52
Dibulatkan 90,370.00

43 1 M3 Pasangan Pondasi Rollag

Semen PC @ 50 kg 4.9600 zak 64,260.00 318,729.60


Pasir pasang 0.3720 m3 56,100.00 20,869.20
Bata merah uk. 8 x 8 x 16 690.0000 bh 459.00 316,710.00
Upah Pasangan 1/2 bata 1.0000 m2 18,250.00 18,250.00
Alat bantu pasangan bata 1.0000 ls 500.00 500.00
Jumlah Harga 675,058.80
Resiko 10.00% 67,505.88
Total 742,564.68
Dibulatkan 742,560.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
44 1 M2 Pasangan dinding bata adukan 1 : 5

Semen PC @ 50 Kg 0.1710 zak 64,260.00 10,988.46


Pasir pasang 0.0320 m3 56,100.00 1,795.20
Bata merah uk. 8 x 8 x 16 69.0000 bh 459.00 31,671.00
Upah Pasangan 1/2 bata 1.0000 m2 18,250.00 18,250.00
Alat bantu pasangan bata 1.0000 ls 500.00 500.00
Jumlah Harga 63,204.66
Resiko 10.00% 6,320.47
Total 69,525.13
Dibulatkan 69,530.00

45 Upah Plester
Upah Tukang Batu 0.1045 hr 66,300.00 6,931.36
Upah Kepala Tukang Batu 0.0209 hr - -
Upah Pekerja 0.0697 hr 71,400.00 4,976.36
Upah Mandor 0.0105 hr 102,000.00 1,066.36
Jumlah Harga 12,974.09
Dibulatkan 12,974.00

46 Upah Aci
Upah Tukang Batu 0.0575 hr 66,300.00 3,812.25
Upah Kepala Tukang Batu 0.0115 hr - -
Upah Pekerja 0.0288 hr 71,400.00 2,052.75
Upah Mandor 0.0058 hr 102,000.00 586.50
Jumlah Harga 6,451.50
Dibulatkan 6,452.00

47 Upah Plester Aci


Upah Tukang Batu 0.1620 hr 66,300.00 10,743.61
Upah Kepala Tukang Batu 0.0324 hr - -
Upah Pekerja 0.0984 hr 71,400.00 7,029.11
Upah Mandor 0.0162 hr 102,000.00 1,652.86
Jumlah Harga 19,425.59
Dibulatkan 19,426.00

48 1 M2 Plesteran adukan 1 : 2 tebal 15 mm

Semen PC @ 50 Kg 0.1634 zak 64,260.00 10,500.00


Pasir pasang 0.0184 m3 56,100.00 1,031.25
Upah Plester 1.0000 m2 12,974.00 12,974.00
Alat bantu Plester 1.0000 ls 500.00 500.00
Jumlah Harga 25,005.25
Resiko 10.00% 2,500.53
Total 27,505.78
Dibulatkan 27,510.00

49 1 M2 Plesteran adukan 1 : 2 tebal 20 mm

Semen PC @ 50 Kg 0.2179 zak 64,260.00 14,000.00


Pasir pasang 0.0245 m3 56,100.00 1,375.00
Upah Plester 1.0000 m2 12,974.00 12,974.00
Alat bantu Plester 1.0000 ls 500.00 500.00
Jumlah Harga 28,849.00
Resiko 10.00% 2,884.90
Total 31,733.90
Dibulatkan 31,730.00

50 1 M2 Plesteran adukan 1 : 5 tebal 15 mm

Semen PC @ 50 Kg 0.0907 zak 64,260.00 5,826.24


Pasir pasang 0.0170 m3 56,100.00 953.70
Upah Plester 1.0000 m2 12,974.00 12,974.00
Alat bantu Plester 1.0000 ls 500.00 500.00
Jumlah Harga 20,253.94
Resiko 10.00% 2,025.39
Total 22,279.33
Dibulatkan 22,280.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
51 1 M2 Plesteran adukan 1 : 5 tebal 20 mm

Semen PC @ 50 Kg 0.1413 zak 64,260.00 9,082.08


Pasir pasang 0.0265 m3 56,100.00 1,486.65
Upah Plester 1.0000 m2 12,974.00 12,974.00
Alat bantu Plester 1.0000 ls 500.00 500.00
Jumlah Harga 24,042.73
Resiko 10.00% 2,404.27
Total 26,447.00
Dibulatkan 26,450.00

52 1 M2 acian
Semen PC @ 50 Kg 0.0750 zak 64,260.00 4,819.50
Upah Aci 1.0000 m2 6,452.00 6,452.00
Alat bantu Aci 1.0000 ls 150.00 150.00
Jumlah Harga 11,421.50
Resiko 10.00% 1,142.15
Total 12,563.65
Dibulatkan 12,560.00

53 1 m2 dinding 1:2
Pasangan bata 1 : 2 1.0000 m2 742,560.00 742,560.00
Plester 1 : 2 t=20mm 1.0000 m2 31,730.00 31,730.00
Acian 2.0000 m2 12,560.00 25,120.00
799,410.00

54 1 m2 dinding 1:5
Pasangan bata 1 : 5 1.0000 m2 69,530.00 69,530.00
Plester 1 : 5 t=20mm 1.0000 m2 22,280.00 22,280.00
Acian 2.0000 m2 12,560.00 25,120.00
116,930.00

55 Upah Pasang Keramik dinding


Upah Tukang batu 0.2000 Hr 66,300.00 13,260.00
Upah Kepala Tukang Batu 0.0200 Hr - -
Upah Pekerja 0.3000 Hr 71,400.00 21,420.00
Upah Mandor 0.0040 Hr 102,000.00 408.00
35,088.00
35,080.00

56 Upah Pasang Keramik lantai


Upah Tukang batu 0.1600 Hr 66,300.00 10,608.00
Upah Kepala Tukang Batu 0.0160 Hr - -
Upah Pekerja 0.2400 Hr 71,400.00 17,136.00
Upah Mandor 0.0032 Hr 102,000.00 326.40
28,070.40
28,070.00

57 1 M2 Lapisan dinding Keramik (1 : 5) 20x20


Keramik 20x20 Ikad 1.0500 m2 - -
Semen PC @ 50 Kg 0.1817 zak 64,260.00 11,673.90
Pasir pasang - t = 15mm 0.0200 m3 56,100.00 1,122.00
Semen WARNA 0.0400 zak 12,240.00 489.60
Upah pasang keramik dinding 1.0000 hk 35,080.00 35,080.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 49,365.50
Resiko 10.00% 4,936.55
Total 54,302.05
Dibulatkan 54,300.00

58 1 M2 Lapisan dinding Keramik (1 : 5) 20x25


Keramik 20x25 Ikad 1.0500 m2 - -
Semen PC @ 50 Kg 0.1817 zak 64,260.00 11,673.90
Pasir pasang - t = 15mm 0.0200 m3 56,100.00 1,122.00
Semen WARNA 0.0400 zak 12,240.00 489.60
Upah pasang keramik dinding 1.0000 hk 35,080.00 35,080.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 49,365.50
Resiko 10.00% 4,936.55
Total 54,302.05
Dibulatkan 54,300.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)

59 1 M2 Lapisan Lantai Keramik (1 : 5) 20x20


Keramik 20x20 Ikad 1.0500 m2 - -
Semen PC @ 50 Kg 0.2083 zak 64,260.00 13,387.50
Pasir pasang t = 20mm 0.0250 m3 56,100.00 1,402.50
Semen WARNA 0.0400 zak 12,240.00 489.60
Upah pasang keramik lantai 1.0000 hk 28,070.00 28,070.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 44,349.60
Resiko 10.00% 4,434.96
Total 48,784.56
Dibulatkan 48,780.00

60 1 M2 Lapisan Lantai Keramik (1 : 5) 30x30


Keramik 30x30 Ikad 1.0500 m2 - -
Semen PC @ 50 Kg 0.2083 zak 64,260.00 13,387.50
Pasir pasang t = 20mm 0.0250 m3 56,100.00 1,402.50
Semen WARNA 0.0400 zak 12,240.00 489.60
Upah pasang keramik lantai 1.0000 hk 28,070.00 28,070.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 44,349.60
Resiko 10.00% 4,434.96
Total 48,784.56
Dibulatkan 48,780.00

100 1 M2 Lapisan Lantai Keramik (1 : 5) 40x40


Keramik 40x40 1.0500 m2 - -
Semen PC @ 50 Kg 0.2083 zak 64,260.00 13,387.50
Pasir pasang t = 20mm 0.0250 m3 56,100.00 1,402.50
Semen WARNA 0.0400 zak 12,240.00 489.60
Upah pasang keramik lantai 1.0000 hk 28,070.00 28,070.00
Alat bantu 1.0000 ls 1,000.00 1,000.00
Jumlah Harga 44,349.60
Resiko 10.00% 4,434.96
Total 48,784.56
Dibulatkan 48,780.00

101 Upah pengecatan interior


Upah Tukang cat 0.0625 Hr 66,300.00 4,143.75
Upah Kepala Tukang cat 0.0031 Hr - -
Upah Pekerja 0.0156 Hr 71,400.00 1,115.63
Upah Mandor 0.0013 Hr 102,000.00 127.50
5,386.88
5,380.00

102 Upah pengecatan Exterior


Upah Tukang cat 0.0833 Hr 66,300.00 5,525.00
Upah Kepala Tukang cat 0.0042 Hr - -
Upah Pekerja 0.0208 Hr 71,400.00 1,487.50
Upah Mandor 0.0017 Hr 102,000.00 170.00
7,182.50
7,180.00

103 Upah pengecatan cat minyak


Upah Tukang cat 0.1042 Hr 66,300.00 6,906.25
Upah Kepala Tukang cat 0.0052 Hr - -
Upah Pekerja 0.0260 Hr 71,400.00 1,859.38
Upah Mandor 0.0021 Hr 102,000.00 212.50
8,978.13
8,970.00

104 1 M2 Cat tembok interior

Alkali Resistant Primer ICI 0.0031 peil 561,000.00 1,753.13


Cat interior 0.0125 peil 663,000.00 8,287.50
Kwas Roll 0.0250 bh 24,480.00 612.00
Upah Pengecatan interior 1.0000 m2 5,380.00 5,380.00
Transport 1.0000 ls 50.00 50.00
Alat bantu 1.0000 ls 100.00 100.00
Jumlah Harga 16,182.63
Resiko 10.00% 1,618.26
Total 17,800.89
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
Dibulatkan 17,800.00

105 1 M2 Cat tembok Exterior weather shield

Alkali Resistant Primer ICI 0.0031 peil 561,000.00 1,753.13


Cat weathershield 0.0094 peil 1,428,000.00 13,387.50
Kwas Roll 0.0250 bh 24,480.00 612.00
Upah Pengecatan exterior 1.0000 m2 7,180.00 7,180.00
Transport 1.0000 ls 50.00 50.00
Alat bantu 1.0000 ls 100.00 100.00
Jumlah Harga 23,082.63
Resiko 10.00% 2,308.26
Total 25,390.89
Dibulatkan 25,390.00

106 1 M2 Cat Konstruksi Kayu dan besi 0.0833

1 Meni kayu 0.1000 Kg 15,000.00 1,500.00


2 Cat dasar Besi ex ICI 0.1111 Kg 35,000.00 3,888.89
3 Cat Besi ex ICI 0.2222 Kg 65,000.00 14,444.44
4 Minyak cat 0.0667 ltr 11,220.00 748.00
5 Amplas 0.1500 lbr 3,060.00 459.00
6 Kwas 2" 0.0200 bh 8,160.00 163.20
7 Upah Pengecatan cat minyak 1.0000 m2 8,970.00 8,970.00
8 transport 1.0000 ls 50.00 50.00
9 Alat bantu 1.0000 ls 1,500.00 1,500.00
Jumlah Harga 26,334.64
Profit & over head 10.00% 2,633.46
Total 28,968.11
Dibulatkan 28,970.00

106 Plafon Gypsum Board 9mm

Gypsum 9mm Elephant 0.3819 m2 56,100.00 21,427.08


Rangka Hollow 1.0000 m2 23,750.00 23,750.00
Jointing 1.0000 m' 2,400.00 2,400.00
Pengantung, skrup dll 1.0000 ls 5,000.00 5,000.00
Material bantu 1.0000 ls 2,500.00 2,500.00
Alumunium U 1.0000 ls 6,120.00 6,120.00
Upah pasang plafon 1.0000 m2 30,600.00 30,600.00
Jumlah Harga 91,797.08
Resiko 10.00% 9,179.71
Total 100,976.79
Dibulatkan 100,980.00

107 Plafon Kalsiboard 6 mm

Kalsiboard 6 mm 0.3819 m2 56,100.00 21,427.08


Rangka Hollow 1.0000 m2 23,750.00 23,750.00
Jointing 1.0000 m' 2,400.00 2,400.00
Pengantung, skrup dll 1.0000 ls 5,000.00 5,000.00
Material bantu 1.0000 ls 2,500.00 2,500.00
Alumunium U 1.0000 ls 6,120.00 6,120.00
Upah pasang plafon 1.0000 m2 30,600.00 30,600.00
Jumlah Harga 91,797.08
Resiko 10.00% 9,179.71
Total 100,976.79
Dibulatkan 100,980.00

108 Rangka atap baja ringan


Rangka atap baja ringan 1.0000 m2 86,700.00 86,700.00
Alumunium Foil 1.1000 m2 12,240.00 13,464.00
Talang Umpet 0.5000 m 23,970.00 11,985.00
Dudukan lisplank 1.0000 ls 2,500.00 2,500.00
114,649.00
Resiko 10.00% 11,464.90
Total 126,113.90
Dibulatkan 126,110.00

109 Pasang Penutup ATAP - Genteng Badan


Genteng Lokal ex Sarko 1.0000 m2 - -
Alat bantu 1.0000 m2 250.00 250.00
Upah 1.0000 ls 9,000.00 9,000.00
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH
No. JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
Rp (Rp)
9,250.00
Resiko 10.00% 925.00
Total 10,175.00
Dibulatkan 10,180.00

110 Pasang Penutup ATAP - Genteng Tepi


Genteng Lokal ex Sarko 1.0000 m2 - -
Baut 1.0000 ls 500.00 500.00
Alat bantu 1.0000 m2 250.00 250.00
Upah 1.0000 ls 9,000.00 9,000.00
9,750.00
Resiko 10.00% 975.00
Total 10,725.00
Dibulatkan 10,730.00

111 Pasang NOK - Genteng


Nok Lokal ex Sarko 1.0000 m - -
Mortar 1.0000 m 5,000.00 5,000.00
Alat bantu 1.0000 ls 250.00 250.00
Upah 1.0000 ls 20,000.00 20,000.00
25,250.00
Resiko 10.00% 2,525.00
Total 27,775.00
Dibulatkan 27,780.00

112 Septik Tank/Resapan


Galian tanah 9.1900 m3 61,700.00 567,023.00
Urug pasir 0.1838 m3 97,160.00 17,853.15
Beton 1 : 2 : 3 1.1025 m3 4,867,770.50 5,366,716.97
Pas 1/2 bata Trasram 12.7500 m2 82,153.20 1,047,453.30
Plester + Aci 13.2000 13.2 40,270.50 531,570.60
7,530,617.02
Resiko 10.00% 753,061.70
Total 8,283,678.72
Dibulatkan 8,283,680.00
RENCANA ANGGARAN BIAYA
Citra Bukit Raya
Type Tanjung (36/90)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )

A. Pekerjaan Persiapan
1 Pembersihan lapangan 1.000 ls 100,000.00 100,000.00 Sebelum proyek
2 Direksi keet/gudang 1.000 ls 1,100,000.00 1,100,000.00 ukuran 4 x 6 m
3 Air kerja 1.000 ls 450,000.00 450,000.00 Jet Pump
` 4 Listrik kerja 1.000 ls 85,000.00 85,000.00 1300 watt
5 Keamanan 1.000 ls 100,000.00 100,000.00 Selama proyek berlangsung
6 Bouwplank 42.000 m' 33,190.80 1,394,013.60 Keliling lahan
TOTAL 3,229,013.60

B. Pekerjaan Tanah Dan Pondasi


1 Galian pondasi 11.827 m³ 42,789.00 506,054.81 Manual
2 Pemadatan tanah lantai & pondasi 36.000 m² 40,800.00 1,468,800.00 Dengan stamper
3 Urugan Pasir dibawah pondasi 0.605 m³ 89,760.00 54,327.24 Pasir pasang; Tebal = 5 cm
4 Lantai Kerja dibawah pondasi 0.763 m³ 678,159.50 517,520.47 Ad. 1pc:3ps:5krl ; T.5 cm
5 Pondasi 1 Bata 1 : 3 16.140 m² 193,611.85 3,124,895.26 Pas. Rollage 1Pc : 3Ps
TOTAL 5,671,597.77

C. Pekerjaan Beton
1 Pek. Sloof 15 x 20 cm 1.211 m³ 2,067,029.50 2,502,139.21 site mix 1:2:3; SL
2 Pek. Kolom 10 x 20 0.868 m³ 2,600,400.25 2,257,147.42 site mix 1:2:3; K1
3 Pek. Kolom Praktis 10 x 10 cm 24.900 m' 56,063.50 1,395,981.15 site mix 1:2:3; KP
4 Pek. Ring Balok 10 x 20 cm 1.920 m³ 2,216,196.85 4,255,097.95 site mix 1:2:3; RB
5 Pek. Slab (Dak/Canopy) T. 10 cm 0.200 m³ 2,104,769.50 420,953.90 site mix 1:2:3; RB
TOTAL 10,831,319.63

D. Pekerjaan Dinding
1 Pek. Pasangan 1/2 bata 1 : 2 10.610 m² 84,112.55 892,434.16 konvensional
2 Pek. Plesteran 1 : 2 Trasraam 21.220 m² 42,126.24 893,918.81 konvensional
3 Pek. Pasangan 1/2 bata 1 : 5 135.655 m² 74,378.30 10,089,788.29 konvensional
4 Pek. Plesteran 1 : 5 217.048 m² 34,707.90 7,533,280.28 konvensional
5 Pek. Acian 238.268 m² 27,891.25 6,645,592.36 konvensional
TOTAL 26,055,013.89

E. Pekerjaan Lantai keramik


1 Urugan Pasir bawah lantai 1.800 m³ 89,760.00 161,568.00 T.5 cm
2 Floor bawah keramik 1.800 m³ 678,159.50 1,220,687.10 Rabat/B-0; T.5 cm
3 Keramik lantai 40 x 40 31.827 m² 60,724.25 1,932,670.70 ex. Ikad
4 Keramik lantai 30 x 30 4.890 m² 64,564.00 315,717.96 ex. Ikad SBO Keramik
5 Keramik lantai KM 20 x 20 2.250 m² 67,783.55 152,512.99 ex. Ikad SBO Keramik
6 Keramik Dinding KM 20 x 25 7.800 m² 133,509.00 1,041,370.20 ex. Ikad SBO Keramik
7 Cor Carport (Fin Rabat) Bertulang 0.216 m³ 82,144.01 17,743.11 Ad. 1pc:2ps:3krl T.10 cm; fin. Aci
TOTAL 4,842,270.06
RENCANA ANGGARAN BIAYA
Citra Bukit Raya
Type Tanjung (36/90)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )
F. Pekerjaan Kusen, Pintu & Jendela

1 Pintu P3 (PVC) 1.000 unit 350,000.00 350,000.00 PVC


TOTAL 350,000.00

G. Pekerjaan Plafond
1 Plafond dalam + Rangka 34.077 m² 69,495.50 2,368,198.15 Gypsum A Plus, T.9 mm hollow meni 2/4 + 4/4
2 Plafond luar + Rangka 11.800 m² 69,495.50 820,046.90 GRC, ex. Royal Board; T.4 mm; meni 2/4 + 4/4
3 List plafond 53.050 m' 14,000.00 742,700.00 Perapihan Sudut
TOTAL 3,930,945.05

H. Pekerjaan Atap
1 Rangka atap baja ringan 81.000 m² 89,200.00 7,225,200.00 Full system Truss; ex. Union truss
2 Genteng Badan 81.000 m' 10,180.00 824,580.00 Lokal; ex. Sarko SBO Genteng
3 Nok 7.000 m' 24,111.20 168,778.40 Lokal; ex. Sarko SBO Nok
4 Ujung Nok 1.000 m' 24,111.20 24,111.20 Lokal; ex. Sarko SBO Ujung nok
5 Genteng Tepi 22.400 m' 12,055.60 270,045.44 Lokal; ex. Sarko SBO Genteng tepi
6 Lisplank 38.400 m' 25,000.00 960,000.00 GRC; ex. Royal plank T. 9 mm
TOTAL 9,472,715.04

I. Pekerjaan Sanitair & Instalasi Air


1 Instalasi air bersih, pipa 3/4 20.100 m' 15,312.75 307,786.28 ex.Vinilon 3/4"
2 Instalasi air bersih, pipa 1/2 3.000 m' 13,719.00 41,157.00 ex.Vinilon 1/2"
3 Kran carport/taman 1.000 unit 39,766.50 39,766.50 ex. Onda
4 Kran bak/taman 1.000 unit 39,766.50 39,766.50 ex. Onda
5 Bak Mandi fiber 1.000 bh 300,000.00 300,000.00 Plastik
6 Instalasi air kotor, pipa 3' 8.000 m' 44,369.45 354,955.60 ex. Vinilon 3"
7 Instalasi air kotor, pipa 4' 4.000 m' 58,604.10 234,416.40 ex. Vinilon 4"
8 Kloset jongkok 1.000 bh 230,271.00 230,271.00 Toho
9 Bak kontrol 2.000 bh 264,934.70 529,869.40 Konvesional
10 Floor drain 1.000 bh 86,139.00 86,139.00 ex. Onda
11 Septik tank + rembesan 1.000 unit 4,000,000.00 4,000,000.00 Konvesional
TOTAL 6,164,127.68

J. Pekerjaan Pengecatan
1 Cat dinding dalam 108.524 m² 17,637.08 1,914,045.93 Aplikator
2 Cat dinding luar 43.410 m² 25,169.38 1,092,592.64 Aplikator
3 Cat plafond 34.077 m² 17,637.08 601,018.60 Aplikator
4 Cat lisplank 11.520 m² 25,169.38 289,951.24 Aplikator
5 Cat pintu dan kusen 6.32 m² 37,539.75 237,176.14 Aplikator
TOTAL 4,134,784.55

K. Pekerjaan Listrik
1 Panel Box / sekering 4 grup 1.000 unit 300,000.00 300,000.00 ex. Boss 5 group
2 Kabel tuvur + BC 10 mm 7.000 m' 100,000.00 700,000.00 NYY 3 x 10 mm2; ex extrana
3 Sparing SR/PLN 1.000 ls 200,000.00 200,000.00 ex. Vinilon AW dia. 1 1/2"
4 Instalasi titik lampu 12.000 ttk 125,000.00 1,500,000.00 NYM 3x2.5 mm2; ex. Extrana
Fitting lampu gantung 8.000 ttk 25,000.00 200,000.00 Lokal SBO Asesories
5 Saklar single 2.000 ttk 8,000.00 16,000.00 Boss B10 SBO Asesories
6 Saklar seri 3.000 ttk 8,000.00 24,000.00 Boss B10 SBO Asesories
7 Instalasi stop kontak 4.000 ttk 125,000.00 500,000.00 SBO Asesories
8 Stop kontak 4.000 ttk 8,000.00 32,000.00 Boss B10 SBO Asesories
RENCANA ANGGARAN BIAYA
Citra Bukit Raya
Type Tanjung (36/90)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )
TOTAL 3,472,000.00
RENCANA ANGGARAN BIAYA
Citra Bukit Raya
Type Tanjung (36/90)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )

L. Pekerjaan lain-lain
1 Pembersihan akhir 1.000 ls 300,000.00 300,000.00
2 Ban banan (dinding Teras) 4.650 m² 33,200.00 154,380.00
TOTAL 454,380.00

Jumlah (A+B+C+D+E+F+G+H+I+J+K+L) 78,608,167.26


Fee 10% 7,860,816.73
TOTAL 86,468,983.99

DIBULATKAN 86,400,000.00
PPn 10 % 8,640,000.00
GRAND TOTAL 95,040,000.00

Harga per m2 Exclude Ppn10% 2,400,000.00


Harga per m2 Include Ppn10% 2,640,000.00

Jambi, 13 Januari 2013


CV. INDORAYA KONTRINDO

IRWAN SAPUTRA
Direktur
RENCANA ANGGARAN BIAYA

Citra Bukit Raya


Type Flamboyan (36/120)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )

A. Pekerjaan Persiapan

1 Pembersihan lapangan 1.000 ls 100,000.00 100,000.00 Sebelum proyek

2 Direksi keet/gudang 1.000 ls 1,100,000.00 1,100,000.00 ukuran 4 x 6 m

3 Air kerja 1.000 ls 450,000.00 450,000.00 Jet Pump

` 4 Listrik kerja 1.000 ls 85,000.00 85,000.00 1300 watt

5 Keamanan 1.000 ls 100,000.00 100,000.00 Selama proyek berlangsung

6 Bouwplank 46.000 m' 33,190.80 1,526,776.80 Keliling lahan

TOTAL 3,361,776.80

B. Pekerjaan Tanah Dan Pondasi

1 Galian pondasi 14.216 m³ 42,789.00 608,267.03 Manual

2 Pemadatan tanah lantai & pondasi 36.000 m² 40,800.00 1,468,800.00 Dengan stamper

3 Urugan Pasir dibawah pondasi 0.656 m³ 89,760.00 58,837.68 Pasir pasang; Tebal = 5 cm

4 Lantai Kerja dibawah pondasi 0.656 m³ 678,159.50 444,533.55 Ad. 1pc:3ps:5krl ; T.5 cm

5 Pondasi 1 Bata 1 : 3 17.480 m² 193,611.85 3,384,335.14 Pas. Rollage 1Pc : 3Ps

TOTAL 5,964,773.40

C. Pekerjaan Beton

1 Pek. Sloof 15 x 20 cm 1.211 m³ 2,067,029.50 2,502,139.21 site mix 1:2:3; SL

2 Pek. Kolom 10 x 20 0.992 m³ 2,600,400.25 2,579,597.05 site mix 1:2:3; K1

3 Pek. Kolom Praktis 10 x 10 cm 33.000 m' 56,063.50 1,850,095.50 site mix 1:2:3; KP

4 Pek. Ring Balok 10 x 20 cm 1.817 m³ 2,216,196.85 4,026,829.68 site mix 1:2:3; RB

5 Pek. Slab (Dak/Canopy) T. 10 cm 0.220 m³ 2,104,769.50 463,049.29 site mix 1:2:3; RB

TOTAL 11,421,710.72

D. Pekerjaan Dinding

1 Pek. Pasangan 1/2 bata 1 : 2 8.970 m² 84,112.55 754,489.57 konvensional

2 Pek. Plesteran 1 : 2 Trasraam 17.940 m² 42,126.24 755,744.75 konvensional

3 Pek. Pasangan 1/2 bata 1 : 5 135.685 m² 74,378.30 10,092,019.64 konvensional

4 Pek. Plesteran 1 : 5 217.096 m² 34,707.90 7,534,946.26 konvensional

5 Pek. Acian 235.036 m² 27,891.25 6,555,447.84 konvensional

TOTAL 25,692,648.05

E. Pekerjaan Lantai keramik

1 Urugan Pasir bawah lantai 1.800 m³ 89,760.00 161,568.00 T.5 cm

2 Floor bawah keramik 1.800 m³ 678,159.50 1,220,687.10 Rabat/B-0; T.5 cm

3 Keramik lantai 40 x 40 34.763 m² 60,724.25 2,110,926.74 ex. Ikad


4 Keramik lantai 30 x 30 4.450 m² 64,564.00 287,283.97 ex. Ikad SBO Keramik
5 Keramik lantai KM 20 x 20 3.000 m² 67,783.55 203,350.65 ex. Ikad SBO Keramik
6 Keramik Dinding KM 20 x 25 8.550 m² 133,509.00 1,141,501.95 ex. Ikad SBO Keramik
7 Cor Carport (Fin Rabat) Bertulang 0.432 m³ 82,144.01 35,486.21 Ad. 1pc:2ps:3krl T.10 cm; fin. Aci

TOTAL 5,160,804.63
RENCANA ANGGARAN BIAYA

Citra Bukit Raya


Type Flamboyan (36/120)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )
F. Pekerjaan Kusen, Pintu & Jendela

1 Pintu P3 (PVC) 1.000 unit 350,000.00 350,000.00 PVC

TOTAL 350,000.00

G. Pekerjaan Plafond

1 Plafond dalam + Rangka 37.763 m² 69,495.50 2,624,323.82 Gypsum A Plus, T.9 mm hollow meni 2/4 + 4/4

2 Plafond luar + Rangka 11.800 m² 69,495.50 820,046.90 GRC, ex. Royal Board; T.4 mm; meni 2/4 + 4/4

3 List plafond 62.100 m' 14,000.00 869,400.00 Perapihan Sudut

TOTAL 4,313,770.72

H. Pekerjaan Atap

1 Rangka atap baja ringan 81.000 m² 89,200.00 7,225,200.00 Full system Truss; ex. Union truss
2 Genteng Badan 81.000 m' 10,180.00 824,580.00 Lokal; ex. Sarko SBO Genteng
3 Nok 8.000 m' 24,111.20 192,889.60 Lokal; ex. Sarko SBO Nok
4 Ujung Nok 2.000 m' 24,111.20 48,222.40 Lokal; ex. Sarko SBO Ujung nok
5 Genteng Tepi 23.200 m' 12,055.60 279,689.92 Lokal; ex. Sarko SBO Genteng tepi
6 Lisplank 41.200 m' 25,000.00 1,030,000.00 GRC; ex. Royal plank T. 9 mm

TOTAL 9,600,581.92

I. Pekerjaan Sanitair & Instalasi Air

1 Instalasi air bersih, pipa 3/4 20.100 m' 15,312.75 307,786.28 ex.Vinilon 3/4"

2 Instalasi air bersih, pipa 1/2 3.000 m' 13,719.00 41,157.00 ex.Vinilon 1/2"

3 Kran carport/taman 1.000 unit 39,766.50 39,766.50 ex. Onda

4 Kran bak/taman 1.000 unit 39,766.50 39,766.50 ex. Onda


5 Bak Mandi fiber 1.000 bh 300,000.00 300,000.00 Plastik
6 Instalasi air kotor, pipa 3' 8.000 m' 44,369.45 354,955.60 ex. Vinilon 3"

7 Instalasi air kotor, pipa 4' 4.000 m' 58,604.10 234,416.40 ex. Vinilon 4"

8 Kloset jongkok 1.000 bh 230,271.00 230,271.00 Toho

9 Bak kontrol 2.000 bh 264,934.70 529,869.40 Konvesional

10 Floor drain 1.000 bh 86,139.00 86,139.00 ex. Onda

11 Septik tank + rembesan 1.000 unit 4,000,000.00 4,000,000.00 Konvesional

TOTAL 6,164,127.68

J. Pekerjaan Pengecatan

1 Cat dinding dalam 108.548 m² 17,637.08 1,914,469.22 Aplikator

2 Cat dinding luar 43.419 m² 25,169.38 1,092,834.26 Aplikator

3 Cat plafond 37.763 m² 17,637.08 666,020.04 Aplikator

4 Cat lisplank 12.360 m² 25,169.38 311,093.51 Aplikator

5 Cat pintu dan kusen 6.32 m² 37,539.75 237,176.14 Aplikator

TOTAL 4,221,593.18
RENCANA ANGGARAN BIAYA

Citra Bukit Raya


Type Flamboyan (36/120)

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi Ket
( Rp. ) ( Rp. )

K. Pekerjaan Listrik

1 Panel Box / sekering 5 grup 1.000 unit 300,000.00 300,000.00 ex. Boss 5 group

2 Kabel tuvur + BC 10 mm 7.000 m' 100,000.00 700,000.00 NYY 3 x 10 mm2; ex extrana

3 Sparing SR/PLN 1.000 ls 200,000.00 200,000.00 ex. Vinilon AW dia. 1 1/2"

4 Instalasi titik lampu 14.000 ttk 125,000.00 1,750,000.00 NYM 3x2.5 mm2; ex. Extrana
5 Fitting lampu gantung 6.000 ttk 25,000.00 150,000.00 Lokal SBO Asesories
6 Saklar single 1.000 ttk 8,000.00 8,000.00 Boss B10 SBO Asesories
7 Saklar seri 4.000 ttk 8,000.00 32,000.00 Boss B10 SBO Asesories
8 Instalasi stop kontak 5.000 ttk 125,000.00 625,000.00 - SBO Asesories
9 Stop kontak 5.000 ttk 8,000.00 40,000.00 Boss B10 SBO Asesories
TOTAL 3,805,000.00

L. Pekerjaan lain-lain

1 Pembersihan akhir 1.000 ls 100,000.00 100,000.00

2 Ban banan (dinding Teras) 4.619 m² 33,200.00 153,350.80

TOTAL 253,350.80

Jumlah (A+B+C+D+E+F+G+H+I+J+K+L) 80,310,137.89


Fee 10% 8,031,013.79
TOTAL 88,341,151.68

DIBULATKAN 88,300,000.00
PPn 10 % 8,830,000.00
GRAND TOTAL 97,130,000.00

Harga per m2 Exclude Ppn10% 2,452,777.78


Harga per m2 Include Ppn10% 2,698,055.56

Jambi, 13 Januari 2014


CV. INDORAYA KONTRINDO

IRWAN SAPUTRA
Direktur
RENCANA ANGGARAN BIAYA

GUDANG LIMBAH B3

Harga Satuan Total Harga


No. Item Pekerjaan Vol. Sat. Spesifikasi % Ket
( Rp. ) ( Rp. )

A. Pekerjaan Persiapan
1 Pembersihan lapangan 1.000 ls 100,000.00 100,000.00 Sebelum proyek 0.38
2 Gudang 1.000 ls - Ukuran 2,4 x 3,6 m -
3 Air kerja 1.000 ls 100,000.00 100,000.00 0.38
4 Listrik kerja 1.000 ls 150,000.00 150,000.00 0.57
5 Keamanan 1.000 ls 400,000.00 Selama proyek berlangsung -
6 Bouwplank 13.000 m' 22,000.00 286,000.00 Keliling Lahan Material 2 x Pakai 1.08
7 Peralatan K3 1.000 Ls 300,000.00 -
TOTAL 636,000.00 2.40
B. Pekerjaan Tanah Dan Pondasi
1 Galian pondasi 3.314 m³ 72,000.00 238,636.80 Manual 0.90
2 Pemadatan tanah lantai & pondasi 2.661 m³ 45,000.00 119,754.00 Manual 0.45
3 Pondasi 1 Bata 1 : 4 Tinggi 50 cm 6.000 m2 130,000.00 780,000.00 Pas. Rollage 2.95
4 Dinding Batas Rabat 1 : 4 7.200 m2 65,000.00 468,000.00 Pas. Rollage 1.77
TOTAL 1,138,390.80 4.30
C. Pekerjaan Beton
1 Pek. Sloof 15 x 20 cm 0.360 m³ 3,100,000.00 1,116,000.00 site mix 1:2:3 uk. Besi 10 dan 6 4.22
2 Pek. Kolom 13 x 13 cm (Struktural) 0.311 m³ 2,600,400.25 807,424.28 site mix 1:2:3 uk. Besi 10 dan 6 3.05
3 Pek. Kolom Praktis 10 x 10 cm 0.104 m³ 4,400,000.00 455,400.00 site mix 1:2:3 uk. Besi 8 dan 6 1.72
4 Pek. Balok Gantung 10 x 20 cm 0.057 m³ 4,200,000.00 239,400.00 site mix 1:2:3 uk. Besi 8 dan 6 0.90
5 Pek. Rink Balok 10 x 15 cm 0.180 m³ 3,900,000.00 702,000.00 site mix 1:2:3 uk. Besi 8 dan 6 2.65
5 Pek. Balok Sopi Sopi 10 x 15 cm 0.108 m³ 3,900,000.00 421,200.00 site mix 1:2:3 T. 10 cm ; S1 (wireme 1.59
TOTAL 3,741,424.28 14.14
D. Pekerjaan Dinding
1 Pek. Pasangan Dinding Bata 1 : 4 18.500 m² 65,000.00 1,202,500.00 konvensional 4.55
2 Pek. Plesteran + Aci 1 : 4 36.600 m² 55,000.00 2,013,000.00 konvensional 7.61
TOTAL 3,215,500.00 12.15
E. Pekerjaan Lantai keramik
1 Pek. Urugan Pasir bawah lantai T. 5 cm 0.810 m³ 65,000.00 52,650.00 0.20
2 Pek. Cor Bawah Lantai 1pc : 3ps : 5krl T. 5 cm 0.867 m³ 678,000.00 587,826.00 2.22
3 Pek. Cor Lantai Raam 1pc : 3ps : 5krl T. 8 cm + Ac 2.000 m² 130,000.00 260,000.00 0.98
4 Pek. Keramik Lantai Dalam 30 x 30 9.000 m² - -
5 Pek. Keramik lantai Luar 30 x 30 7.900 m² - -
6 Pek. Acian Tepi Rabat 3.528 m² 22,000.00 77,616.00 0.29
TOTAL 978,092.00 0.49
F. Pekerjaan Kusen, Pintu & Jendela
1 Pek. Pas. Pintu Plat Besi T. 4 mm uk. 2 x 2,5 m + 1.000 unit 7,500,000.00 7,500,000.00 SBO
Rangka Besi UNP + Finish Cat Duco - - SBO
2 Pek. Pas. Kawat Harmonika + Rangka Besi Siku 6.000 unit 600,000.00 3,600,000.00 SBO
uk. 1.38 x 2.85 m L 40.40.4 mm + Finish Cat - - SBO
Rangka Besi - - SBO
3 Pek. Pas. Kawat Harmonika + Rangka Besi Siku 1.000 unit 250,000.00 250,000.00 SBO
uk. 0.65 x 2.00 m L 40.40.4 mm + Finish Cat - - SBO
Rangka Besi - - SBO
TOTAL 11,350,000.00
Instalasi AIR Kotor
VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
22.6 m1 1.10 Pipa AW dia. 3 6.22 Btg 38,000 236,170
1.00 Bh 1.00 Closed Duty 1.00 bh 115,000 115,000
1.00 Bh 1.00 Sambungan L 3" 1.00 bh 35,000 35,000
1.00 Bh 1.00 Floor Drain Onda 1.00 bh 15,000 15,000
4.00 1.00 Gorong Gorong dia. 100 cm 4.00 bh 120,000 480,000
2.00 2.00 Ijuk 4.00 bh 25,000 100,000
981,170

Urugan Pasir Bawah Lantai


VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
1.79 m3 1.10 Pasir 0.49 M3 60,000 29,576
29,576

Keramik Lantai 40 x 40
VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
30.90 m2 0.023 Pasir 0.71 M3 60,000 42,642
30.90 m2 8.16 Semen Portland 5.04 Zak 67,000 337,873
30.90 m2 1.50 Nut Am 35 46.35 Kg 15,000 695,250
1,075,765

Keramik Lantai Teras 33 x 33


VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
2.70 m2 0.042 Pasir 0.11 M3 60,000 6,804
2.70 m2 11.38 Semen Portland 0.61 Zak 67,000 41,173
2.70 m2 1.50 Nut Am 35 4.05 Kg 15,000 60,750
108,727

Keramik Lantai KM 20 x 20
VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
2.25 m2 0.042 Pasir 0.09 M3 60,000 5,670
2.25 m2 11.38 Semen Portland 0.51 Zak 67,000 34,311
2.25 m2 1.50 Nut Am 35 3.38 Kg 15,000 50,625
90,606

Keramik Dinding KM 20 x 40
VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
6.36 m2 0.018 Pasir 0.11 M3 60,000 6,869
6.36 m2 9.30 Semen Portland 1.18 Zak 67,000 79,258
6.36 m2 1.50 Nut Am 35 9.54 Kg 15,000 143,100
229,227

Stapping T. 7 cm
VOLUME KOEFISIEN BAHAN JUMLAH SATUAN HARGA JUMLAH
0.18 m3 218.000 Semen Portland 0.78 Zak 67,000 52,582
0.18 m3 0.52 Pasir 0.09 M3 60,000 5,616
0.18 m3 0.87 Kerikil 0.16 Kg 300,000 46,980
105,178

BAHAN 20,670,983
UPAH 15,000,000
TOTAL 1 RMH 35,670,983
Semen = 32.83 zak 1.00 32.8 67,000
Pasir = 5.06 m3 1.00 5.1 60,000
Kerikil = 1.16 m3 1.00 1.2 300,000
Besi 10 = 32.40 btg 1.00 32.4 50,000
Besi 8 = 34.89 btg 1.00 34.9 31,500
Besi 6 = 35.54 btg 1.00 35.5 29,000
Batu Bata = 1,281.50 bh 1.00 1,281.5 550
Kawat Ikat = 23.33 kg 1.00 23.3 15,000
Kayu dolken = 4.00 bh 1.00 4.0 5,000
Papan 2 x 10 = 12.50 btg 1.00 12.5 20,000
Papan 2 x 20 = 0.50 m3 1.00 0.5 1,600,000
I
2,199,497
303,561
347,220 II
1,619,750
1,098,972
1,030,672 III
704,825
350,010
20,000 IV
250,000
800,000 0.016 31.25 btg
8,724,508 V
15,000,000
23,724,508
11,246,836
34,971,344
3,497,134
38,468,478
1,068,569
Item Pekerjaan Untuk Point :
B, C, D, E, G, I, L Rp. 20,670,983

Item Pekerjaan Untuk Point :


A Rp. 436,000

Item Pekerjaan Untuk Point :


F Rp. 2,173,874

Item Pekerjaan Untuk Point :


H Rp. 5,135,962

Item Pekerjaan Untuk Point :


UPAH Rp. 15,000,000

43,416,819 13,025,046

4,341,682

47,758,500

4,775,850

52,534,351

1,459,288
1,326,625
HARGA SATUAN BAHAN DAN UPAH
HARGA X HARGA
NO. JENIS MATERIAL Vol Satuan SATUAN PPh 2% SATUAN
+ PPH 2%
A Harga Bahan

1 Profil Alumunium ex. HP 3"x1.5" Coating 1 m' 60,000 1.02 61,200


2 Bata merah 1 bh 450 1.02 459
3 Batu Kerikil 1 m3 250,000 1.02 255,000
4 Bendrat 1 kg 15,000 1.02 15,300
5 Besi beton U24 1 kg 8,300 1.02 8,466
6 Closed Jongkok ex. TOHO 1 bh 100,000 1.02 102,000
7 Cat dasar Besi ex ICI 1 kg 35,000 1.02 35,700
8 Cat Kayu ex Glotex 1 kg 40,000 1.02 40,800
9 Gypsum 9mm Gyproc 1 lbr 55,000 1.02 56,100
10 Genteng Badan ex. Sarko 1 Bh 4,900 1.02 4,998
11 Floor Drain Onda 1 Bh 75,000 1.02 76,500
12 Dolken 1 Btg 5,000 1.02 5,100
13 Engsel Pintu 1 Bh 25,000 1.02 25,500
14 Hollow Meni 20 x 40 1 m' 14,500 1.02 14,790
15 GRC 4 mm Royal 1 lbr 55,000 1.02 56,100
16 Kayu balok bekisting 1 m3 1,600,000 1.02 1,632,000
17 Kayu Papan bekisting 1 m3 1,650,000 1.02 1,683,000
18 Keramik Ikad 20 x 20 Lantai 1 dus 1.02 -
19 Keramik Ikad 20 x 25 Dinding 1 dus 1.02 -
20 Keramik Ikad 30 x 30 1 dus 1.02 -
21 Keramik Ikad 40 x 40 1 dus 1.02 -
22 Kran Bak Mandi Merk Onda A801T 1 bh 30,000 1.02 30,600
23 Kaca Asahimas T. 5mm 1 m2 88,500 1.02 90,270
24 Kaca Es T. 3 mm 1 m2 86,000 1.02 87,720
25 Kunci Pintu 1 bh 130,000 1.02 132,600
26 Lem Kayu Fox 1 kg 28,000 1.02 28,560
27 Minyak cat 1 ltr 11,000 1.02 11,220
28 Minyak Bekisting 1 ltr 3,500 1.02 3,570
29 Nok Genteng' 1 Bh 9,100 1.02 9,282
30 Paku 1 kg 12,000 1.02 12,240
31 Paku skrup 1 kg 17,000 1.02 17,340
32 Pasir urug 1 m3 55,000 1.02 56,100
33 Pasir pasang 1 m3 55,000 1.02 56,100
34 Pasir beton 1 m3 55,000 1.02 56,100
35 Papan Kls. II 1 m3 2,600,000 1.02 2,652,000
36 Semen PC @ 50 kg 1 zak 63,000 1.02 64,260
37 Semen PC @ 50 kg 1 kg 1,260 1.02 1,285
38 Semen WARNA Lemkra 1 kg 12,000 1.02 12,240
39 Skrup Fixer 1 bh 400 1.02 408
40 Sealant 1 kg 65,000 1.02 66,300
41 Seal Tape 1 bh 5,000 1.02 5,100
42 Teakwood 3 mm 1 lbr 92,000 1.02 93,840
43 Upah Kepala Tukang Batu 1 Hari 1.02 -
44 Upah Mandor 1 Hari 100,000 1.02 102,000
45 Upah Pekerja 1 Hari 70,000 1.02 71,400
46 Upah Tukang 1 Hari 82,500 1.02 84,150
47 Pipa PVC 1/2" Vinilon Type AW 1 m' 4,000 1.02 4,080
48 Pipa PVC 3/4" AW 1 m' 4,750 1.02 4,845
HARGA SATUAN BAHAN DAN UPAH
HARGA X HARGA
NO. JENIS MATERIAL Vol Satuan SATUAN PPh 2% SATUAN
+ PPH 2%

49 Pipa PVC 3" ex Vinilon type D 1 m' 18,125 1.02 18,488


50 Pipa PVC 4" ex Vinilon type D 1 m' 27,750 1.02 28,305
51 Wiremesh M5 1 m2 23,000 1.02 23,460
52 Rangka Atap Baja Ringan 1 m2 85,000 1.02 86,700
53 Alumunium Foil 1 m2 12,000 1.02 12,240

Jambi, 26 Mei 2014


CV. INDORAYA KONTRINDO

-
Direktur
TIME SCHEDULLE
CITRA BUKIT RAYA TYPE MAHONI (42/120)

BULAN KE I BULAN KE II BULAN KE III BULAN KE IV BULAN KE V


NO. URAIAN PEKERJAAN BOBOT KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A. Pekerjaan Persiapan 2.40 0.54 0.54 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07

B. Pekerjaan Tanah Dan Pondasi 4.30 0.45 0.45 0.68 0.68 0.68 0.68 0.68

C. Pekerjaan Beton 14.14 1.41 1.41 1.41 1.41 1.41 2.83 1.41 2.83

D. Pekerjaan Dinding 12.15 1.35 1.35 1.35 0.68 2.03 2.70 1.35 1.35

E. Pekerjaan Lantai keramik 3.70 0.74 0.74 0.74 0.74 0.74

F. Pekerjaan Kusen, Pintu & Jendela 42.90 21.45 10.73 10.73

G. Pekerjaan Plafond - - - - -

H. Pekerjaan Atap 14.84 2.97 2.97 2.97 2.97 2.97

I. Pekerjaan Sanitair & Instalasi Air - - - - - -

J. Pekerjaan Pengecatan 5.18 1.04 1.04 1.04 1.04 1.04

K. Pekerjaan Listrik - - - - - - -

L. Pekerjaan lain-lain 0.38 0.19 0.19

100.00

RENCANA PROGRESS MINGGUAN 0.54 0.99 1.94 2.17 3.52 3.52 3.52 4.26 2.10 2.96 5.81 4.39 27.32 3.04 14.51 12.57 1.85 1.85 1.85 1.30

AKUMULASI RENCANA PROGRESS MINGGUAN - 0.54 1.53 3.47 5.64 9.16 12.68 16.19 20.45 22.55 25.51 31.32 35.71 63.03 66.07 80.58 93.15 95.00 96.85 98.70 100.0

AKUMULASI REALISASI PROGRESS MINGGUAN

DEVIASI