D PEKERJAAN PENGECORAN
1 M2 Cetakan ( Bekesting ) Beton diperlukan
0.0500 M3 Kayu Meranti 4,400,000.00 220,000.00
0.3000 Kg Paku Biasa 15,000.00 4,500.00
0.3000 OH Pekerja 97,000.00 29,100.00
0.2500 OH Tukang Kayu 115,000.00 28,750.00
1
0.0300 OH Kepala Tukang 139,000.00 4,170.00
0.0300 OH Mandor 145,000.00 4,350.00
Jumlah 66,370.00 224,500.00 290,870.00
Jasa 10 % 29,087.00
Jumlah + Jasa 319,957.00
Tul.Besi Beton 1 Kg Mengerjakan Besi Beton
1.0000 M3 Besi Beton 22,500.00 22,500.00
0.0200 Kg Kawat Minrad 23,000.00 460.00
0.0100 OH Pekerja 97,000.00 970.00
0.0100 OH Tukang Besi 115,000.00 1,150.00
2
0.0007 OH Kepala Tukang 139,000.00 97.30
0.0004 OH Mandor 145,000.00 58.00
Jumlah 2,275.30 22,960.00 25,235.30
Jasa 10 % 2,523.53
Jumlah + Jasa 27,758.83
HARGA SATUAN HARGA JUMLAH HARGA
No. URAIAN PEKERJAAN
( RP. ) UPAH BAHAN ( RP )
1 M3 Adukan Beton Mutu Dengan K-175
6.5200 Zak Semen 95,000.00 619,400.00
0.5400 M3 Pasir beton 455,000.00 245,700.00
0.5700 M3 Koral Beton 475,000.00 270,750.00
215.0000 Ltr Air Bersih 100.00 21,500.00
1.0000 OH Pekerja 97,000.00 97,000.00
3
0.2500 OH Tukang Batu 115,000.00 28,750.00
0.0030 OH Kepala Tukang 139,000.00 417.00
0.0080 OH Mandor 145,000.00 1,160.00
Jumlah 127,327.00 1,157,350.00 1,284,677.00
Jasa 10 % 128,467.70
Jumlah + Jasa 1,413,144.70
1 M3 Adukan Beton Mutu Dengan K-225
7.4200 Zak Semen 95,000.00 704,900.00
0.5000 M3 Pasir Beton 455,000.00 227,500.00
0.5800 M3 Koral Beton 475,000.00 275,500.00
215.0000 Ltr Air Bersih 100.00 21,500.00
1.0000 OH Pekerja 97,000.00 97,000.00
4
0.2600 OH Tukang Batu 115,000.00 29,900.00
0.0030 OH Kepala Tukang 139,000.00 417.00
0.0080 OH Mandor 145,000.00 1,160.00
Jumlah 128,477.00 1,229,400.00 1,357,877.00
Jasa 10 % 122,940.00
Jumlah + Jasa 1,480,817.00
1 M3 Lantai Kerja 1 : 3 : 5
6.5000 Zak Semen 95,000.00 617,500.00
0.5400 M3 Pasir Beton 455,000.00 245,700.00
0.4700 M3 Koral Beton 475,000.00 223,250.00
1.0000 OH Pekerja 97,000.00 97,000.00
7 0.2000 OH Tukang Batu 115,000.00 23,000.00
0.0030 OH Kepala Tukang 139,000.00 417.00
0.0080 OH Mandor 145,000.00 1,160.00
Jumlah 121,577.00 1,086,450.00 1,208,027.00
Jasa 10 % 120,802.70
Jumlah + Jasa 1,328,829.70
E Pekerjaan Pengecatan
1 M2 Pengecatan Besi (delta,sigma dan sejenisnya)
0.2800 Ltr Cat Minyak 145,000.00 40,600.00
1.0000 Lbr Kertas Gosok 5,000.00 5,000.00
0.0800 Ltr Their A Spesial(delta,sigma dan sejenisnya) 76,000.00 6,080.00
0.1000 OH Tukang Cat 115,000.00 11,500.00
1 0.0200 OH Kepala Tukang Cat 139,000.00 2,780.00
0.1000 OH Pekerja Biasa 97,000.00 9,700.00
0.0100 OH Mandor 145,000.00 1,450.00
Jumlah 25,430.00 51,680.00 77,110.00
Jasa 10 % 7,711.00
Jumlah + Jasa 84,821.00
1 M1 Pagar BRC 0.9m t Jadi 1.2m(pondasi batu kali, sloof betosn,1/2 Batako 30 cm,Plester dan Cat )
1.1880 OH Pekerja 97,000.00 115,236.00
0.0720 OH Tukang Besi 115,000.00 8,280.00
0.3410 OH Tukang Batu 115,000.00 39,215.00
0.0725 OH Tukang Cat 115,000.00 8,337.50
0.0590 OH Kepala Tukang 139,000.00 8,201.00
0.0710 OH Mandor 145,000.00 10,295.00
0.2740 M3 Batu Belah 490,000.00 134,260.00
0.0022 M3 Batu Pecah split 2-3 450,000.00 990.00
8.0000 Bj Bata Merah 1,500.00 12,000.00
0.8752 Zak Semen 95,000.00 83,144.00
0.0250 M3 Pasir Urug 137,000.00 3,425.00
0.1200 M3 Pasir Pasang 455,000.00 54,600.00
2
0.0146 M3 Pasir Beton 455,000.00 6,643.00
0.0060 M3 Kayu Balok 4,680,000.00 28,080.00
0.1200 Kg Paku Biasa 15,000.00 1,800.00
1.4400 Kg Besi beton Polos 22,500.00 32,400.00
0.0640 Kg Kawat Minrad 23,000.00 1,472.00
1.0000 M1 Pagar Type E Tinggi t.1.9m 465,000.00 465,000.00
1.0000 Bh Tiang Pagar Type E t.1.9m 229,000.00 229,000.00
0.1150 Kg Plamir Tembok 41,000.00 4,715.00
0.1150 Kg Cat Tembok ( cat dasar) 75,000.00 8,625.00
0.2990 Kg Cat Tembok ( cat penutup ) 79,000.00 23,621.00
Jumlah 189,564.50 1,089,775.00 1,279,339.50
Jasa 10 % 127,933.95
Jumlah + Jasa 1,407,273.45