Anda di halaman 1dari 30

ANALISA HARGA SATUAN PEKERJAAN

HARGA SAT JUMLAH HARGA


JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
A ANALISA BIAYA KONSTRUKSI PEKERJAAN PERMULAAN
1 M¹ PEKERJAAN PASANGAN BOUWPLANK
Bahan :
Kayu Borneo 5/7 M3 0.0070 3,180,000 22,260.00 22,260.00
paku biasa 2" - 5" kg 0.0200 22,000 440.00 440.00
Kayu Papan Albasia M3 0.0070 1,855,000 12,985.00 12,985.00
Tenaga Kerja : - -
Pekerja org/hr 0.1000 80,000 8,000.00 8,000.00
Tukang Kayu org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Kayu org/hr 0.0100 120,000 1,200.00 1,200.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Alat Bantu ls 1.0000 55,535.00
Jumlah 55,535.00
Keuntungan 10 % 5,553.50
Harga Satuan Pekerja 61,088.50
1 M² PEKERJAAN PEMBERSIHAN LAHAN
Tenaga Kerja :
Pekerja org/hr 0.1000 80,000 8,000 8,000
Mandor org/hr 0.0500 130,000 6,500 6,500
Alat Bantu ls 1.0000
Jumlah 14,500
Keuntungan 10 % 1,450
Harga Satuan Pekerja 15,950
B ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH DAN PONDASI
1 M³ PEKERJAAN GALIAN TANAH BIASA KEDALAMAN 1 M
Tenaga Kerja :
Pekerja org/hr 0.4000 80,000 32,000.00 32,000.0000
Mandor org/hr 0.0400 130,000 5,200.00 5,200.0000
Alat Bantu ls 1.0000
Jumlah 37,200.00
Keuntungan 10 % 3,720.00
Harga Satuan Pekerja 40,920.00
1 M³ PEKERJAAN URUGAN TANAH KEMBALI
Tenaga Kerja :
Pekerja org/hr 0.1920 80,000 15,360.00 15,360.0000
Mandor org/hr 0.0190 130,000 2,470.00 2,470.0000
Alat Bantu ls 1.0000
Jumlah 17,830.00
Keuntungan 10 % 1,783.00
Harga Satuan Pekerja 19,613.00
1 M³ PEKERJAAN URUGAN PASIR
Bahan :
Pasir Urug m3 1.2000 180,200 216,240.00 216,240.0000
Tenaga Kerja : -
Pekerja org/hr 0.3000 80,000 24,000.00 24,000.0000
Mandor org/hr 0.0100 130,000 1,300.00 1,300.0000
Jumlah 241,540.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Keuntungan 10 % 24,154.00
Harga Satuan Pekerja 265,694.00
1 M³ PEKERJAAN AANSTAMPING
Bahan :
Pasir Urug m3 0.1000 180,200 18,020.00 18,020.00
Batu Belah m3 1.2000 212,000 254,400.00 254,400.00
Tenaga Kerja : - -
Pekerja org/hr 0.5000 80,000 40,000.00 40,000.00
Tukang Batu org/hr 0.5630 100,000 56,300.00 56,300.00
Kepala Tukang Batu org/hr 0.0750 120,000 9,000.00 9,000.00
Mandor org/hr 0.0100 130,000 1,300.00 1,300.00
Jumlah 379,020.00
Keuntungan 10 % 37,902.00
Harga Satuan Pekerja 416,922.00
1 M³ PEKERJAAN PASANGAN PONDASI BATU KALI 1 : 5
Bahan :
Batu belah m3 1.1000 212,000 233,200.00 233,200.00
PC kg 136.0000 1,000 136,000.00 136,000.00
Pasir Pasang m3 0.5440 180,200 98,028.80 98,028.80
Tenaga Kerja : - -
Tukang Batu org/hr 0.6000 100,000 60,000.00 60,000.00
Kepala Tukang Batu org/hr 0.0600 120,000 7,200.00 7,200.00
Pekerja org/hr 1.5000 80,000 120,000.00 120,000.00
Mandor org/hr 0.0750 130,000 9,750.00 9,750.00
Jumlah 664,178.80
Keuntungan 10 % 66,417.88
Harga Satuan Pekerja 730,596.68
C ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON
1 M³ ADUKAN BETON TUMBUK CAMP: 1 PC : 2PS : 3 KR
Bahan :
PC kg 232.0000 1,000 232,000.00 232,000.00
Pasir Beton m3 0.5200 265,000 137,800.00 137,800.00
Koral Beton m3 0.7800 250,000 195,000.00 195,000.00
Tenaga Kerja : - -
Tukang Batu org/hr 0.2500 100,000 25,000.00 25,000.00
Kepala Tukang Batu org/hr 0.0250 120,000 3,000.00 3,000.00
Pekerja org/hr 1.6500 80,000 132,000.00 132,000.00
Mandor org/hr 0.0800 130,000 10,400.00 10,400.00
Jumlah 735,200.00
Keuntungan 10 % 73,520.00
Harga Satuan Pekerja 808,720.00
1 M³ ADUKAN BETON K. 175
Bahan :
PC kg 340.0000 1,000 340,000.00 340,000.00
Pasir Beton m3 0.5400 265,000 143,100.00 143,100.00
Koral Beton m3 0.8300 250,000 207,500.00 207,500.00
Tenaga Kerja : - -
Tukang Batu org/hr 0.2500 100,000 25,000.00 25,000.00
Kepala Tukang Batu org/hr 0.0250 120,000 3,000.00 3,000.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Pekerja org/hr 1.6500 80,000 132,000.00 132,000.00
Mandor org/hr 0.0800 130,000 10,400.00 10,400.00
Jumlah 861,000.00
Keuntungan 10 % 86,100.00
Harga Satuan Pekerja
1 M3 ADUKAN BETON K. 225
Bahan :
PC kg 388.0000 1,000 388,000.00 388,000.00
Pasir Beton m3 0.6500 265,000 172,250.00 172,250.00
Koral Beton m3 0.6500 250,000 162,500.00 162,500.00
Tenaga Kerja : - -
Tukang Batu org/hr 1.0000 100,000 100,000.00 100,000.00
Kepala Tukang Batu org/hr 0.1000 120,000 12,000.00 12,000.00
Pekerja org/hr 1.6500 80,000 132,000.00 132,000.00
Mandor org/hr 0.3000 130,000 39,000.00 39,000.00
Jumlah 1,005,750.00
Keuntungan 10 % 100,575.00
Harga Satuan Pekerja 1,106,325.00
1 KG TULANGAN BETON DENGAN BESI POLOS/ULIR
Bahan :
Besi Beton kg 1.0500 6,126 6,432.30 6,432.30
Kawat Beton kg 0.0150 23,000 345.00 345.00
Tenaga Kerja : - -
Tukang Besi org/hr 0.0070 100,000 700.00 700.00
Kepala Tukang Besi org/hr 0.0007 120,000 84.00 84.00
Pekerja org/hr 0.0070 80,000 560.00 560.00
Mandor org/hr 0.0003 130,000 39.00 39.00
Jumlah 8,160.30
Keuntungan 10 % 816.03
Harga Satuan Pekerja 8,976.33
1 M2 PASANG BEKISTING UNTUK SLOOF
Bahan :
Kayu Papan Albasia m3 0.0450 1,855,000 83,475.00 83,475.00
Paku 2 " - 5 " kg 0.3000 22,000 6,600.00 6,600.00
minyak bekisting Lt 0.1000 18,182 1,818.20 1,818.20
Tenaga Kerja : - -
Tukang Kayu org/hr 0.2600 100,000 26,000.00 26,000.00
Kepala Tukang Kayu org/hr 0.0260 120,000 3,120.00 3,120.00
Pekerja org/hr 0.3000 80,000 24,000.00 24,000.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Jumlah 145,663.20
Keuntungan 10 % 14,566.32
Harga Satuan Pekerja 160,229.52
1 M2 PASANG BEKISTING UNTUK KOLOM
Bahan :
Paku 2 " - 5 " kg 0.4000 22,000 8,800.00 8,800.00
minyak bekisting Lt 0.2000 18,182 3,636.40 3,636.40
Kaso 5/7 borneo m3 0.0150 43,000 645.00 645.00
multiplek 9 mm Lbr 0.3500 95,000 33,250.00 33,250.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
dolken dia 8 - 10 /400 cm btg 2.0000 36,000 72,000.00 72,000.00
Tenaga Kerja : - -
Tukang Kayu org/hr 0.3300 100,000 33,000.00 33,000.00
Kepala Tukang Kayu org/hr 0.0330 120,000 3,960.00 3,960.00
Pekerja org/hr 0.3000 80,000 24,000.00 24,000.00
Mandor org/hr 0.0060 130,000 780.00 780.00
Jumlah 180,071.40
Keuntungan 10 % 18,007.14
Harga Satuan Pekerja 198,078.54
1 M3 BETON BERTULANG KOLOM 15X15 ADUKAN BETON K. 175
Bahan :
Adukan beton K. 175 m3 1.0000 750,000 750,000.00 750,000.00
Bekisting u/ dua kali pakai (62,5 %) m2 4.6800 168,353 787,893.07 787,893.07
Besi Beton U - 24 kg 200.0000 10,323 2,064,600.00 2,064,600.00
Jumlah 3,602,493.07
Keuntungan 10 % 360,249.31
Harga Satuan Pekerja 3,962,742.38
1 M3 BETON BERTULANG KOLOM 15X15 ADUKAN BETON K. 225
Bahan :
Adukan beton K. 225 m3 1.0000 870,000 870,000.00 870,000.00
Bekisting u/ dua kali pakai (62,5 %) m2 4.6800 168,353 787,892.04 787,892.04
Besi Beton U - 24 kg
200.0000 10,323 2,064,600.00 2,064,600.00
Jumlah 3,722,492.04
Keuntungan 10 % 372,249.20
Harga Satuan Pekerja 4,094,741.24
1 M3 BETON BERTULANG SLOOF 15/20 ADUKAN BETON K. 175
Bahan :
Adukan beton K. 175 m3 1.0000 750,000 750,000.00 750,000.00
Bekisting u/ dua kali pakai (62,5 %) m2 8.0000 168,353 1,346,824.00 1,346,824.00
Besi Beton U - 24 kg 175.0000 10,323 1,806,525.00 1,806,525.00
Jumlah 3,903,349.00
Keuntungan 10 % 390,334.90
Harga Satuan Pekerja 4,293,683.90
D ANALISA BIAYA KONSTRUKSI PEKERJAAN PASANGAN
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1 : 5
Bahan :
Bata Merah kelas 1 bh 70.0000 1,776 124,320.00 124,320.00
PC kg 9.6800 1,000 9,680.00 9,680.00
Pasir Pasang m3 0.0450 180,200 8,109.00 8,109.00
Tenaga Kerja : - -
Tukang Batu org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Batu org/hr 0.0100 120,000 1,200.00 1,200.00
Pekerja org/hr 0.3200 80,000 25,600.00 25,600.00
Mandor org/hr
0.0150 130,000 1,950.00 1,950.00
Jumlah 180,859.00
Keuntungan 10 % 18,085.90
Harga Satuan Pekerja 198,944.90
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1 : 3
Bahan :
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Bata Merah kelas 1 bh 70.0000 1,776 124,320.00 124,320.00
PC kg 14.3700 1,000 14,370.00 14,370.00
Pasir Pasang m3 0.0400 180,200 7,208.00 7,208.00
Tenaga Kerja : - -
Tukang Batu org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Batu org/hr 0.0100 120,000 1,200.00 1,200.00
Pekerja org/hr 0.3200 80,000 25,600.00 25,600.00
Mandor org/hr 0.0150 130,000 1,950.00 1,950.00
Jumlah 184,648.00
Keuntungan 10 % 18,464.80
Harga Satuan Pekerja 203,112.80
1 M2 PLESTERAN DINDING 1 : 3 TEBAL 15 MM
Bahan :
PC kg 6.4800 1,000 6,480.00 6,480.00
Pasir Pasang m3 0.0190 180,200 3,423.80 3,423.80
Tenaga Kerja : - -
Tukang Batu org/hr 0.1500 100,000 15,000.00 15,000.00
Kepala Tukang Batu org/hr 0.0150 120,000 1,800.00 1,800.00
Pekerja org/hr 0.2000 80,000 16,000.00 16,000.00
Mandor org/hr 0.0100 130,000 1,300.00 1,300.00
Jumlah 44,003.80
Keuntungan 10 % 4,400.38
Harga Satuan Pekerja 48,404.18
1 M2 PLESTERAN DINDING 1 : 5 TEBAL 15 MM
Bahan :
PC kg 4.3200 1,000 4,320.00 4,320.00
Pasir Pasang m3 0.0210 180,200 3,784.20 3,784.20
Tenaga Kerja : - -
Tukang Batu org/hr 0.1500 100,000 15,000.00 15,000.00
Kepala Tukang Batu org/hr 0.0150 120,000 1,800.00 1,800.00
Pekerja org/hr 0.1500 80,000 12,000.00 12,000.00
Mandor org/hr 0.0100 130,000 1,300.00 1,300.00
Jumlah 38,204.20
Keuntungan 10 % 3,820.42
Harga Satuan Pekerja 42,024.62
1 M2 PASANGAN LANTAI KERAMIK 20 X 20 CM
Bahan :
Keramik uk. 20 x 20 M2 1.0200 52,250 53,295.00 53,295.00
PC kg 1.3800 1,000 1,380.00 1,380.00
Pasir Pasang m3 0.0420 180,200 7,568.40 7,568.40
Semen Warna kg 1.5000 13,000 19,500.00 19,500.00
Tenaga Kerja : - -
Pekerja org/hr 0.1880 80,000 15,040.00 15,040.00
Tukang Batu org/hr 0.3750 100,000 37,500.00 37,500.00
Kepala Tukang batu org/hr 0.0750 120,000 9,000.00 9,000.00
Mandor org/hr 0.0190 130,000 2,470.00 2,470.00
Jumlah 145,753.40
Keuntungan 10 % 14,575.34
Harga Satuan Pekerja 160,328.74
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
1 M2 PASANGAN KERAMIK 30 X 30 CM
Bahan :
Keramik uk. 30 x 30 M2 1.0200 33,000 33,660.00 33,660.00
PC kg 2.3800 1,000 2,380.00 2,380.00
Pasir Pasang m3 0.0420 180,200 7,568.40 7,568.40
Semen Warna kg 1.5000 13,000 19,500.00 19,500.00
Tenaga Kerja : - -
Pekerja org/hr 0.2660 80,000 21,280.00 21,280.00
Tukang Batu org/hr 0.3750 100,000 37,500.00 37,500.00
Kepala Tukang batu org/hr 0.0750 120,000 9,000.00 9,000.00
Mandor org/hr 0.0190 130,000 2,470.00 2,470.00
Jumlah 133,358.40
Keuntungan 10 % 13,335.84
Harga Satuan Pekerja 146,694.24
1 M2 PASANGAN DINDING KERAMIK 20 X 25 CM
Bahan :
Keramik uk. 25 x 40 M2 1.0200 65,000 66,300.00 66,300.00
PC kg 2.3800 1,000 2,380.00 2,380.00
Pasir Pasang m3 0.0420 180,000 7,560.00 7,560.00
Semen Warna kg 1.5000 13,000 19,500.00 19,500.00
Tenaga Kerja : - -
Pekerja org/hr 0.2660 80,000 21,280.00 21,280.00
Tukang Batu org/hr 0.3750 100,000 37,500.00 37,500.00
Kepala Tukang batu org/hr 0.0750 120,000 9,000.00 9,000.00
Mandor org/hr 0.0190 130,000 2,470.00 2,470.00
Jumlah 165,990.00
Keuntungan 10 % 16,599.00
Harga Satuan Pekerja 182,589.00
E ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU
1 M3 PASANGAN KUSEN PINTU DAN JENDELA, KAYU BORNEO SUPER
Bahan :
Kayu Borneo Super, Balok m3 1.1000 4,770,000 5,247,000.00 5,247,000.00
Paku kg 2.5000 20,000 50,000.00 50,000.00
Lem Kayu Fox kg 1.0000 10,500 10,500.00 10,500.00
Tenaga Kerja : - -
Pekerja org/hr 6.0000 80,000 480,000.00 480,000.00
Tukang Kayu org/hr 18.0000 100,000 1,800,000.00 1,800,000.00
Kepala Tukang Kayu org/hr 2.0000 120,000 240,000.00 240,000.00
Mandor org/hr 0.3000 130,000 39,000.00 39,000.00
Jumlah 7,866,500.00
Keuntungan 10 % 786,650.00
Harga Satuan Pekerja 8,653,150.00
1 M2 PASANGAN PINTU PANIL, KAYU BORNEO
Bahan :
Kayu borneo, Papan m3 0.0400 2,750,000 110,000.00 110,000.00
List Kayu kamper Profil m1 4.0000 29,400 117,600.00 117,600.00
Lem Kayu Fox kg 0.7500 10,500 7,875.00 7,875.00
Tenaga Kerja : - -
Pekerja org/hr 1.0000 80,000 80,000.00 80,000.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Tukang Kayu org/hr 2.5000 100,000 250,000.00 250,000.00
Kepala Tukang Kayu org/hr 0.2500 120,000 30,000.00 30,000.00
Mandor org/hr 0.0500 130,000 6,500.00 6,500.00
Jumlah 601,975.00
Keuntungan 10 % 60,197.50
Harga Satuan Pekerja 662,172.50
1 M2 PASANGAN PINTU & JENDELA KACA , KAYU BORNEO
Bahan :
Kayu Borneo, Papan m3 0.0350 2,750,000 96,250.00 96,250.00
Tenaga Kerja : - -
Pekerja org/hr 0.8000 80,000 64,000.00 64,000.00
Tukang Kayu org/hr 2.0000 100,000 200,000.00 200,000.00
Kepala Tukang Kayu org/hr 0.2000 120,000 24,000.00 24,000.00
Mandor org/hr 0.0400 130,000 5,200.00 5,200.00
Jumlah 389,450.00
Keuntungan 10 % 38,945.00
Harga Satuan Pekerja 428,395.00
1 M2 PASANGAN DAUN DOUBLE TRIPLEK , RANGKA KAYU BONEO
Bahan :
Kayu Boneo, Papan m3 0.0196 2,750,000 53,900.00 53,900.00
paku biasa 1" - 2" kg 0.3000 23,800 7,140.00 7,140.00
Lem Kayu Fox kg 0.3000 10,500 3,150.00 3,150.00
Triplek t: 4 mm Lbr 1.0000 64,400.00 64,400.00 64,400.00
Tenaga Kerja : - -
Pekerja org/hr 0.6000 80,000 48,000.00 48,000.00
Tukang Kayu org/hr 2.0000 100,000 200,000.00 200,000.00
Kepala Tukang Kayu org/hr 0.2000 120,000 24,000.00 24,000.00
Mandor org/hr 0.0300 130,000 3,900.00 3,900.00
Jumlah 404,490.00
Keuntungan 10 % 40,449.00
Harga Satuan Pekerja 444,939.00
1 M3 PASANG KONSTRUKSI KUDA-KUDA , KAYU BORNEO
Bahan :
Kayu Borneo, Balok m3 1.1000 4,770,000 5,247,000.00 5,247,000.00
Besi Strip kg 15.0000 100,000 1,500,000.00 1,500,000.00
paku biasa 2" - 5" kg 0.8000 22,000 17,600.00 17,600.00
Tenaga Kerja : - -
Pekerja org/hr 4.0000 80,000 320,000.00 320,000.00
Tukang Kayu org/hr 12.0000 100,000 1,200,000.00 1,200,000.00
Kepala Tukang Kayu org/hr 1.2000 120,000 144,000.00 144,000.00
Mandor org/hr 0.2000 130,000 26,000.00 26,000.00
Jumlah 8,454,600.00
Keuntungan 10 % 845,460.00
Harga Satuan Pekerja 9,300,060.00
1 M2 PASANG KASO + RENG , GENTENG PALENTONG , KAYU BORNEO
Bahan :
Kayu Borneo, 5/7 & 2/3 m3 0.0120 3,710,000 44,520.00 44,520.00
paku biasa 2" - 5" kg 0.1500 22,000 3,300.00 3,300.00
Tenaga Kerja : - -
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Pekerja org/hr 0.1000 80,000 8,000.00 8,000.00
Tukang Kayu org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Kayu org/hr 0.0100 120,000 1,200.00 1,200.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Jumlah 67,670.00
Keuntungan 10 % 6,767.00
Harga Satuan Pekerja 74,437.00
1 M2 PASANG RANGKA LANGIT-LANGIT 1.00 X 1.00 , KAYU BORNEO
Bahan :
Kayu Borneo, 5/7 m3 0.0175 3,180,000 55,650.00 55,650.00
paku biasa 2" - 5" kg 0.1000 22,000 2,200.00 2,200.00
Tenaga Kerja : - -
Pekerja org/hr 0.1500 80,000 12,000.00 12,000.00
Tukang Kayu org/hr 0.2500 100,000 25,000.00 25,000.00
Kepala Tukang Kayu org/hr 0.0250 120,000 3,000.00 3,000.00
Mandor org/hr 0.0750 130,000 9,750.00 9,750.00
Jumlah 107,600.00
Keuntungan 10 % 10,760.00
Harga Satuan Pekerja 118,360.00
1 M2 PASANG LISTPLANK 3 X 20 , KAYU BORNEO
Bahan :
Kayu Borneo, Papan m3 0.0072 2,750,000 19,800.00 19,800.00
paku biasa 2" - 5" kg 0.0500 22,000 1,100.00 1,100.00
Tenaga Kerja : - -
Pekerja org/hr 0.1000 80,000 8,000.00 8,000.00
Tukang Kayu org/hr 0.2000 100,000 20,000.00 20,000.00
Kepala Tukang Kayu org/hr 0.0250 120,000 3,000.00 3,000.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Jumlah 52,550.00
Keuntungan 10 % 5,255.00
Harga Satuan Pekerja 57,805.00
1 M1 PEKERJAAN PASANG LIST PLAFOND KAYU PROFIL
Bahan :
Kayu Profil m1 1.0500 29,400 30,870.00 30,870.00
Paku 1/2 - 1 " kg 0.0500 23,800 1,190.00 1,190.00
Tenaga Kerja : - -
Pekerja org/hr 0.0210 80,000 1,680.00 1,680.00
Tukang Kayu org/hr 0.0210 100,000 2,100.00 2,100.00
Kepala Tukang Kayu org/hr 0.0020 120,000 240.00 240.00
Mandor org/hr 0.0010 130,000 130.00 130.00
Jumlah 36,210.00
Keuntungan 10 % 3,621.00
Harga Satuan Pekerja 39,831.00
F ANALISA BIAYA KONSTRUKSI PEKERJAAN PENUTUP ATAP
1 M2 PEKERJAAN PASANG ATAP GENTENG PALENTONG
Bahan :
Genteng Palentong bh 25.0000 7,500 187,500.00 187,500.00
Tenaga Kerja : - -
Pekerja org/hr 0.1500 80,000 12,000.00 12,000.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Tukang Kayu org/hr 0.0750 100,000 7,500.00 7,500.00
Kepala Tukang Kayu org/hr 0.0080 120,000 960.00 960.00
Mandor org/hr 0.0080 130,000 1,040.00 1,040.00
Jumlah 209,000.00
Keuntungan 10 % 20,900.00
Harga Satuan Pekerja 229,900.00
1 M1 PEKERJAAN PASANG GENTENG BUBUNG PALENTONG SUPER
Bahan :
Genteng Bubung Palentong Super bh 4.0000 5,000 20,000.00 20,000.00
PC kg 8.0000 1,000 8,000.00 8,000.00
Pasir Pasang m3 0.0320 180,200 5,766.40 5,766.40
Tenaga Kerja : - -
Pekerja org/hr 0.4000 80,000 32,000.00 32,000.00
Tukang Batu org/hr 0.2000 100,000 20,000.00 20,000.00
Kepala Tukang Batu org/hr 0.0200 120,000 2,400.00 2,400.00
Mandor org/hr
0.0020 130,000 260.00 260.00
Jumlah 88,426.40
Keuntungan 10 % 8,842.64
Harga Satuan Pekerja 97,269.04
G ANALISA BIAYA KONSTRUKSI PEKERJAAN LANGIT-LANGIT
1 M2 PEKERJAAN PASANG LANGIT-LANGIT ASBES 1.00 X 1.00 M T=6MM + RANGKA KAYU BORNEO
Bahan :
Kayu Borneo 5/7 m3 0.0120 3,180,000 38,160.00 38,160.00
Asbes lbr 1.1000 30,000 33,000.00 33,000.00
Paku 1/2' - 1" kg 0.0600 23,800 1,428.00 1,428.00
Tenaga Kerja : - -
Pekerja org/hr 0.1800 80,000 14,400.00 14,400.00
Tukang Kayu org/hr
0.3200 100,000 32,000.00 32,000.00
Kepala Tukang Kayu org/hr
0.0320 120,000 3,840.00 3,840.00
Mandor org/hr
0.0090 130,000 1,170.00 1,170.00
Jumlah 123,998.00
Keuntungan 10 % 12,399.80
Harga Satuan Pekerja 136,397.80
H ANALISA BIAYA KONSTRUKSI PEKERJAAN ELEKTRIKAL
1 Ttk. Pas Titik Lampu/Cahaya
Bahan :
Kabel NYM (3 x 2,5) m' 8.2440 17,200 141,796.80 141,796.80
Solatif Kabel roll 0.3330 7,100 2,364.30 2,364.30
Pipa Kabel btg 1.5000 2,000 3,000.00 3,000.00
T.Dus bh 1.0000 4,000 4,000.00 4,000.00
Inbouw - dus bh 1.0000 4,500 4,500.00 4,500.00
Upah Kerja Ls 1.0000 -
Jumlah 155,661.10
Keuntungan 10 % 15,566.11
Harga Satuan Pekerja 171,227.21
1 Ttk. Pas Titik daya/stop kontak
Bahan :
Kabel NYM (3 x 2,5) m' 6.8700 17,200 118,164.00 118,164.00
Solatif Kabel roll 0.3330 7,100 2,364.30 2,364.30
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Pipa Kabel btg 1.5000 2,000 3,000.00 3,000.00
T.Dus bh 1.0000 4,000 4,000.00 4,000.00
Inbouw - dus bh 1.0000 4,500 4,500.00 4,500.00
Upah Kerja Ls 1.0000 -
Jumlah 132,028.30
Keuntungan 10 % 13,202.83
Harga Satuan Pekerja 145,231.13
1 Bh. Pas. Armatur Stop Kontak
Bahan :
Stop Kontak 250 Watt Sek "Broco" bh 1.0000 14,820 14,820.00 14,820.00
Alat Bantu ls 1.0000 -
Upah Kerja Ls 1.0000 -
Jumlah 14,820.00
Keuntungan 10 % 1,482.00
Harga Satuan Pekerja 16,302.00
1 Bh. Pas. Armatur Saklar Tunggal
Bahan :
Saklar Tunggal Sek "Broco" bh 1.0000 12,500 12,500.00 12,500.00
Alat Bantu ls 1.0000 -
Upah Kerja Ls 1.0000 -
Jumlah 12,500.00
Keuntungan 10 % 1,250.00
Harga Satuan Pekerja 13,750.00
1 Bh. Pas. Lampu Pijar 25 Watt
Bahan :
Lampu Pijar Sek."Philip" 25 Watt bh 1.0000 12,000 12,000.00 12,000.00
Pitting Lampu Sek."Broco" bh 1.0000 13,000 13,000.00 13,000.00
Alat Bantu ls 1.0000 -
Upah Kerja Ls 1.0000 -
Jumlah 25,000.00
Keuntungan 10 % 2,500.00
Harga Satuan Pekerja 27,500.00
1 Bh. Pas. TKI + Lampu TL 1 x 36 Watt
Bahan :
Lampu TL Sek."Philip" 36 Watt bh 1.0000 25,500 25,500.00 25,500.00
Trafo Sek."Philip" + TKI 1 x 36 Watt. bh 1.0000 372,000 372,000.00 372,000.00
Alat Bantu ls 1.0000 -
Upah Kerja Ls 1.0000 -
Jumlah 397,500.00
Keuntungan 10 % 39,750.00
Harga Satuan Pekerja 437,250.00
1 Bh. Pas. Armatur Saklar Ganda
Bahan :
Saklar Ganda Sek "Broco" bh 1.0000 17,500 17,500.00 17,500.00
Alat Bantu ls 1.0000 -
Upah Kerja Ls 1.0000 -
Jumlah 17,500.00
Keuntungan 10 % 1,750.00
Harga Satuan Pekerja 19,250.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
I ANALISA BIAYA KONSTRUKSI PEKERJAAN SANITASI
MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN
Bahan :
Kloset Jongkok Standard INA bh 1.0000 270,000 270,000.00 270,000.00
Semen PC kg 6.0000 1,000 6,000.00 6,000.00
Pasir Pasang m3 0.0100 180,200 1,802.00 1,802.00
Tenaga Kerja : - -
Pekerja org/hr 1.0000 80,000 80,000.00 80,000.00 160,000.00
Tukang Batu org/hr 1.2000 100,000 120,000.00 120,000.00 240,000.00
Kepala Tukang Batu org/hr 1.0000 120,000 120,000.00 120,000.00 240,000.00
Mandor org/hr 0.1600 130,000 20,800.00 20,800.00 41,600.00
Jumlah 959,402.00
Keuntungan 10 % 95,940.20
Harga Satuan Pekerja 1,055,342.20
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 1/2"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0360 80,000 2,880.00 2,880.00
Tukang Pipa org/hr 0.0600 100,000 6,000.00 6,000.00
Kepala Tukang Pipa org/hr 0.0060 120,000 720.00 720.00
Mandor org/hr 0.0018 130,000 234.00 234.00
Jumlah 159,034.00
Keuntungan 10 % 15,903.40
Harga Satuan Pekerja 174,937.40
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 3/4"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0360 80,000 2,880.00 2,880.00
Tukang Pipa org/hr 0.0600 100,000 6,000.00 6,000.00
Kepala Tukang Pipa org/hr 0.0060 120,000 720.00 720.00
Mandor org/hr 0.0018 130,000 234.00 234.00
Jumlah 159,034.00
Keuntungan 10 % 15,903.40
Harga Satuan Pekerja 174,937.40
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 1 1/2"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0360 80,000 2,880.00 2,880.00
Tukang Pipa org/hr 0.0600 100,000 6,000.00 6,000.00
Kepala Tukang Pipa org/hr 0.0060 120,000 720.00 720.00
Mandor org/hr 0.0018 130,000 234.00 234.00
Jumlah 159,034.00
Keuntungan 10 % 15,903.40
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Harga Satuan Pekerja 174,937.40
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 2"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0540 80,000 4,320.00 4,320.00
Tukang Pipa org/hr 0.0900 100,000 9,000.00 9,000.00
Kepala Tukang Pipa org/hr 0.0090 120,000 1,080.00 1,080.00
Mandor org/hr 0.0027 130,000 351.00 351.00
Jumlah 163,951.00
Keuntungan 10 % 16,395.10
Harga Satuan Pekerja 180,346.10
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 3"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0810 80,000 6,480.00 6,480.00
Tukang Pipa org/hr 0.1350 100,000 13,500.00 13,500.00
Kepala Tukang Pipa org/hr 0.0135 120,000 1,620.00 1,620.00
Mandor org/hr 0.0041 130,000 533.00 533.00
Jumlah 171,333.00
Keuntungan 10 % 17,133.30
Harga Satuan Pekerja 188,466.30
MEMASANG 1 M1 PIPA PVC TYPE AW DIA 4"
Bahan :
Pipa PVC m1 1.2000 31,000 37,200.00 37,200.00
Perlengkapan (35% harga Pipa) ls 1.0000 112,000 112,000.00 112,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0810 80,000 6,480.00 6,480.00
Tukang Pipa org/hr 0.1350 100,000 13,500.00 13,500.00
Kepala Tukang Pipa org/hr 0.0135 120,000 1,620.00 1,620.00
Mandor org/hr 0.0041 130,000 533.00 533.00
Jumlah 171,333.00
Keuntungan 10 % 17,133.30
Harga Satuan Pekerja 188,466.30
MEMASANG 1 BUAH Kitchenzink
Bahan :
Kitchenzink m1 1.0000 950,000 950,000.00 950,000.00
Water Drain + Acesories (12% harga set 1.0000 75,000 75,000.00 75,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0300 80,000 2,400.00 2,400.00
Tukang Batu org/hr 0.3000 100,000 30,000.00 30,000.00
Kepala Tukang Batu org/hr 0.0300 120,000 3,600.00 3,600.00
Mandor org/hr 0.0015 130,000 195.00 195.00
Jumlah 1,061,195.00
Keuntungan 10 % 106,119.50
Harga Satuan Pekerja 1,167,314.50
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
MEMASANG 1 BUAH Kran AIR DIA 1/2" ATAU 3/4"
Bahan :
Kran Air m1 1.0000 25,000 25,000.00 25,000.00
Seal tape set 0.0250 4,500 112.50 112.50
Tenaga Kerja : - -
Pekerja org/hr 0.0100 80,000 800.00 800.00
Tukang Pipa org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Pipa org/hr 0.0100 120,000 1,200.00 1,200.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Jumlah 37,762.50
Keuntungan 10 % 3,776.25
Harga Satuan Pekerja 41,538.75
MEMASANG 1 BUAH FLOOR DRAIN
Bahan :
Floor drain m1 1.0000 150,000 150,000.00 150,000.00
Tenaga Kerja : - -
Pekerja org/hr 0.0100 80,000 800.00 800.00
Tukang Pipa org/hr 0.1000 100,000 10,000.00 10,000.00
Kepala Tukang Pipa org/hr 0.0100 120,000 1,200.00 1,200.00
Mandor org/hr 0.0050 130,000 650.00 650.00
Jumlah 162,650.00
Keuntungan 10 % 16,265.00
Harga Satuan Pekerja 178,915.00
J ANALISA BIAYA KONSTRUKSI PEKERJAAN PENGECATAN
2 1 M2 PENGECATAN BIDANG TEMBOK BARU DENGAN ICI interior 2 X LAPIS CAT PENUTUP
Bahan :
Plamir kg 0.1000 15,000 1,500.00 1,500.00
Ampelas lbr 0.1500 3,000 450.00 450.00
Cat Dasar kg 0.1000 35,000 3,500.00 3,500.00
Cat Penutup, 2 X kg 0.2600 30,000 7,800.00 7,800.00
Rol cat bh 0.0100 30,000 300.00 300.00
Tenaga Kerja : - -
Pekerja org/hr 0.0280 80,000 2,240.00 2,240.00
Tukang Cat org/hr 0.0630 100,000 6,300.00 6,300.00
Kepala Tukang Cat org/hr 0.0063 120,000 756.00 756.00
Mandor org/hr 0.0025 130,000 325.00 325.00
Jumlah 23,171.00
Keuntungan 10 % 2,317.10
Harga Satuan Pekerja 25,488.10
3 1 M2 PENGECATAN BIDANG TEMBOK BARU DENGAN ICI Exterior 2 X LAPIS CAT PENUTUP
Bahan :
Plamir kg 0.1000 15,000 1,500.00 1,500.00
Ampelas lbr 0.1500 3,000 450.00 450.00
Cat Dasar kg 0.1000 35,000 3,500.00 3,500.00
Cat Penutup, 2 X kg 0.2600 30,000 7,800.00 7,800.00
Rol cat bh 0.0100 30,000 300.00 300.00
Tenaga Kerja : - -
Pekerja org/hr 0.0280 80,000 2,240.00 2,240.00
Tukang Cat org/hr 0.0630 100,000 6,300.00 6,300.00
Kepala Tukang Cat org/hr 0.0063 120,000 756.00 756.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
Mandor org/hr 0.0025 130,000 325.00 325.00
Jumlah 23,171.00
Keuntungan 10 % 2,317.10
Harga Satuan Pekerja 25,488.10
7 1 M2 PENGECATAN BIDANG PLAFOND BARU DENGAN SANLEX 2 X LAPIS CAT PENUTUP
Bahan :
Plamir kg 0.1000 15,000 1,500.00 1,500.00
Ampelas lbr 0.1500 3,000 450.00 450.00
Cat Dasar kg 0.1000 35,000 3,500.00 3,500.00
Cat Penutup, 2 X kg 0.2800 30,000 8,400.00 8,400.00
Rol cat bh 0.0100 30,000 300.00 300.00
Tenaga Kerja : - -
Pekerja org/hr 0.0300 80,000 2,400.00 2,400.00
Tukang Cat org/hr 0.0750 100,000 7,500.00 7,500.00
Kepala Tukang Cat org/hr 0.0075 120,000 900.00 900.00
Mandor org/hr 0.0030 130,000 390.00 390.00
Jumlah 25,340.00
Keuntungan 10 % 2,534.00
Harga Satuan Pekerja 27,874.00
8 1 M2 PENGECATAN BIDANG PLAFOND BARU DENGAN VINILEX 2 X LAPIS CAT PENUTUP
Bahan :
Plamir kg 0.1000 25,000 2,500.00 2,500.00
Ampelas lbr 0.1500 5,000 750.00 750.00
Cat Dasar kg 0.1000 30,000 3,000.00 3,000.00
Cat Penutup, 2 X kg 0.2800 25,000 7,000.00 7,000.00
Rol cat bh 0.0100 32,500 325.00 325.00
Tenaga Kerja : - -
Pekerja org/hr 0.0300 42,000 1,260.00 1,260.00
Tukang Cat org/hr 0.0750 65,000 4,875.00 4,875.00
Kepala Tukang Cat org/hr 0.0075 75,000 562.50 562.50
Mandor org/hr 0.0030 80,000 240.00 240.00
Jumlah 20,512.50
Keuntungan 10 % 2,051.25
Harga Satuan Pekerja 22,563.75
13 1 M2 PENGECATAN BIDANG KAYU BARU 3 X LAPIS CAT PENUTUP
Bahan :
Cat meni kayu kg 0.2000 Rp 43,000.00 8600 8600
Plamir kg 0.1500 25,000 3,750.00 3750
Ampelas lbr 0.1500 3,000 450.00 450
Cat Dasar kg 0.1700 30,000 5,100.00 5100
Cat Penutup, 3 X kg 0.3500 41,700 14,595.00 14595
minyak cat terpentin ltr 0.1500 91,000 13,650.00 13650
kwas bh 0.1000 5,500 550.00 550
Tenaga Kerja :
Pekerja org/hr 0.0700 42,000 2,940.00 2940
Tukang Cat org/hr 0.1050 65,000 6,825.00 6825
Kepala Tukang Cat org/hr 0.0040 75,000 300.00 300
Mandor org/hr 0.0025 80,000 200.00 200
Jumlah 56,960.00
Keuntungan 10 % 5,696.00
Harga Satuan Pekerja 62,656.00
HARGA SAT JUMLAH HARGA
JUMLAH HARGA
NO URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH BAHAN UPAH
Rp Rp Rp Rp
a b c d e f= d x e g=dxe h = f+g
14 1 M2 PENGECATAN BIDANG KAYU LAMA 2 X LAPIS CAT PENUTUP
Bahan :
Ampelas lbr 0.1500 3,000 450.00 450.00
Cat Penutup, 2 X kg 0.3500 41,700 14,595.00 14,595.00
minyak cat terpentin ltr 0.1500 91,000 13,650.00 13,650.00
kwas bh 0.1000 5,500 550.00 550.00
Tenaga Kerja : - -
Pekerja org/hr 0.0700 42,000 2,940.00 2,940.00
Tukang Cat org/hr 0.1050 65,000 6,825.00 6,825.00
Kepala Tukang Cat org/hr 0.0040 75,000 300.00 300.00
Mandor org/hr 0.0025 80,000 200.00 200.00
Jumlah 39,510.00
Keuntungan 10 % 3,951.00
Harga Satuan Pekerja 43,461.00
15 1 M2 LABURAN BIDANG KAYU DENGAN RESIDU DAN TER
Bahan :
Residu atau ter kg 0.3500 8,100 2,835.00 2,835.00
kuas bh 0.0500 5,500 275.00 275.00
Tenaga Kerja : - -
Pekerja org/hr 0.1000 42,000 4,200.00 4,200.00
Mandor org/hr 0.0060 80,000 480.00 480.00
Jumlah 7,790.00
Keuntungan 10 % 779.00
Harga Satuan Pekerja 8,569.00
KELAS :
KELOMPOK :
NAMA :
NIS :
DAFTAR HARGA SATUAN BAHAN DAN UPAH
NO NAMA BAHAN SAT HARGA
A BAHAN AGREGAT KASAR & BAHAN PEREKAT
1 Tanah Urug M3 130,000
2 Pasir urug M3 130,000
3 Pasir pasang M3 180,200
4 Pasir beton M3 230,000
5 Kerikil (Split) 1/2 M3 160,000
6 Kerikil (Split) 2/3 M3 150,000
7 Sirtu M3 120,000
8 Batu kali/belah M3 180,000
9 Batu bata/bata merah kelas I Bh 1,200
10 Batu bata/bata merah kelas II Bh 900
11 Batako Kecil uk. 10 X 20 X 8 Bh 3,219
12 Batako Besar uk. 20 X 30 X 8 Bh 4,44
13 Beton Rooster uk. 20 X 20 Bh 14,500
14 Batu Templek Hitam M2 225,000
15 Batu Templek Palimanan M2 75,000
16 Batu Candi M2 120,000
17 Semen Tiga Roda Zak 73,000
18 Semen putih Kg 3,000
19 Semen merah/warna LEMKRA Kg 5,000
20 Lem Kuning ( Aibon) Kg 78,000
21 Lem Putih Fox Kg 46,500
22 Lem Vinil M2 90,000

B BAHAN LOGAM
1 Besi Beton U-24 Polos Kg 13,000
2 Besi Beton U-32 Polos Kg 75,000
3 Besi Beton U-32 Ulir Kg 15,000
4 Besi Beton U-39 Ulir Kg 90,000
5 Seng BJLS 30 lebar 60 cm (1 Rol 50 M) m1 45,000
6 Seng BJLS 30 lebar 90 cm (1 Rol 50 M) m1 55,000
7 Seng Gelombang BJLS 25 uk. 90 X 180 Lbr 60,000
8 Seng Gelombang BJLS 30 uk. 90 X 180 Lbr 100,000
9 Kawat Beton Kg 15,000
10 Kawat Ram m2 40,000
11 Kawat Nyamuk Hijau m2 20,000
12 Plat Besi tipis 1 mm kg 20,000
13 Plat Besi tipis 2 - 5 mm kg 16,000
14 Pintu Aluminium + Kusen Berikut Kunci Unit 2,000,000
15 Rolling Door Biasa Type Selat Aluminium m2 625,000
16 Railing Tangga Besi Stainles m1 400,000
17 Paku Kaca Kg 17,500
18 Paku Eternit Kg 17,500
19 Paku Triplek Kg 17,500
20 Paku 1 s/d 3 cm Kg 12,000
21 Paku 4 s/d 7 cm Kg 16,000
22 Paku 8 s/d 12 cm Kg 20,000
23 Paku Gypsum anti karat Kg 47,000
24 Angker Mur Baut dia 19 60 cm bh 15,000
44,000
C BAHAN SALURAN AIR BERSIH & KOTOR
1 Grafel U 20 x 100 cm m1 35,000
2 Grafel U 30 x 100 cm m1 80,000
3 Pipa PVC Rucika AW dia 1/2" btg 31,500
4 Pipa PVC Rucika AW dia 3/4" btg 42,700
5 Pipa PVC Rucika AW dia 1 1/4" btg 87,200
6 Pipa PVC Rucika AW dia 1 1/2" btg 100,200
7 Pipa PVC Rucika AW dia 2" btg 128,100
8 Pipa PVC Rucika AW dia 3" btg 262,900
9 Pipa PVC Rucika AW dia 4" btg 435,600
10 Pipa PVC Rucika AW dia 6" btg 967,600
11 Pipa PVC Maspion AW dia 1/2" btg 31,588
12 Pipa PVC Maspion AW dia 3/4" btg 42,700
13 Pipa PVC Maspion AW dia 1 1/4" btg 87,200
14 Pipa PVC Maspion AW dia 1 1/2" btg 100,200
15 Pipa PVC Maspion AW dia 2" btg 128,100
16 Pipa PVC Maspion AW dia 3" btg 262,900
17 Pipa PVC Maspion AW dia 4" btg 435,600
18 Sambungan Paralon dia 1/2" bh 7,000
19 Sambungan Paralon dia 3/4" bh 9,000
20 Sambungan Paralon dia 1" bh 14,700
21 Sambungan Paralon dia 1 1/2" bh 35,200
22 Sambungan Paralon dia 1 1/4" bh 22,700
23 Sambungan Paralon dia 2" bh 55,650
24 Sambungan Paralon dia 2 1/2" bh 77,700
25 Sambungan Paralon dia 3" bh 112,650

D BAHAN SANITAIR
1 Stop Kran 3/4 " Onda bh 22,800
2 Stop Kran 1 " Onda bh 28,500
3 Stop Kran 1 1/2 " Onda bh 17,500
4 Stop Kran 2 " Onda bh 90,000
5 Stop Kran 2 1/2 " Onda bh 105,800
6 Kran biasa bh 43,500
7 Lem pipa Wavin klg 60,000
8 Kitchen Zink Stainles 1 lubang tanpa sayap bh 150,000
9 Closet duduk TOTO warna Standard Lengkap bh 1,260,000
10 Closet Duduk TOTO Standar Lengkap Warna Tua bh 850,000
11 Closet duduk Standard INA bh 1,112,000
12 Closet jongkok INA bh 280,000
13 Floor Drain Lokal bh 150,000
14 Bak Mandi Fiber uk. Kecil bh 385,000
15 Shower bh 100,000
16 Wastapel INA bh 475,000
17 Tempat sabun bh 10,000
18 Kran Angsa Onda 1/2 " bh 150,000

E BAHAN ELEKTRIKAL
1 Stop kontak ex. Broco Lux cream bh 15,000
2 Saklar Double ex. Broco Lux Cream bh 20,000
3 Saklar Engkel ex. Broco Lux cream bh 22,000
4 Saklar Tripelex. Broco Lux cream bh 10,000
5 Box Panel ex. Merlin bh 95,000
6 Fiting Lampu ex. Broco bh 15,000
7 Lampu Pijar 25 watt s/d 100 watt bh 12,000
8 Lampu Down Light + SL 25 W bh 85,750
9 Lampu Neon TL 40 W bh 117,000
10 Lampu Neon TL 20 W bh 27,300
11 Lampu Gantung bh 200,000
12 Lampu taman PLS-28 watt bh 425,000
13 Lampu Spotlight 500 watt + dudukan tiang GIP bh 905,000
14 Jack Antena / Telephone ex. Broco Lux bh 7,000
15 Kabel NYA 1 x 1.5 Prima (1 rol 50 m) roll 150,000
16 Kabel NYA 1 x 2.5 Prima (1 rol 50 m) roll 400,200
17 Kabel NYM 2 x 1.5. Prima (1 rol 50 m) roll 571,000
18 Kabel NYM 3 x 1.5 Prima (1 rol 50 m) roll 935,000
19 In bow dus stern bh 4,500
20 Lampu Dinding bh 60,000
21 T Dus bh 4,000

F BAHAN ALAT PENGGANTUNG , KUNCI & KACA


1 Kunci Pintu Union/Royal Type kecil Bh 50,000
2 Kunci Pintu Union/Royal Type Besar Bh 80,000
3 Kunci Pintu SES Type kecil Bh 60,000
4 Kunci Pintu SES Type Besar Bh 87,500
5 Kunci Pintu Kamar Mandi, Alpha Bh 55,100
6 Kunci Pintu Aluminium , Alpha uk. Pintu Standar Bh 70,000
7 Handle Pintu Aluminium Bh 61,800
8 Engsel pintu Nylon 4 " Psg 20,000
9 Engsel pintu Nylon 3 " Psg 20,000
10 Engsel pintu Aluminium (floor Hinge) ex. AKN uk. Standar bh 40,000
11 Engsel jendela Biasa Bh 16,500
12 Kait angin jendela biasa Bh 6,427
13 Grendle jendela biasa bh 7,000
14 Grendle Pintu biasa Bh 3,500
15 Kaca polos 3 mm m2 90,000
16 Kaca polos 5 mm m2 97,500
17 Kaca Es 3 mm m2 100,000
18 Kaca Es 5 mm m2 150,000
19 Kaca Patri Ex. Lokal terpasang m2 2,500,000
20 Glass Block 20 X 20 Ex. DN bh 35,000

G BAHAN FINISHING
1 Cat Dasar Tembok, Indo 9000 Sealer Water Base kg 60,000
2 Cat Dasar Kayu Ltr 45,000
3 Cat Tembok, ICI Interior warna standard Gln 191,000
4 Cat Tembok, ICI Interior warna tua Gln 160,000
5 Cat Tembok, ICI Exterior warna standard Gln 350,000
6 Cat Tembok, Catylac Exterior warna standard Gln 120,000
7 Cat Tembok, Catylac Interior warna standard Gln 150,000
8 Cat Tembok, Sanlek kg 50,000
9 Cat Tembok, Sanlek Wonder kg 40,000
10 Cat Tembok, Wiratek kg 68,000
11 Cat Kayu Dulux, warna Standard Ltr 60,000
12 Cat Kayu Dulux, warna Putih Ltr 65,000
13 Cat Kayu Dulux, warna Spesial Ltr 70,000
14 Cat Kayu / besi SEIV kg 67,500
15 Cat Kayu / besi AVIAN kg 60,000
16 Cat Brom kg 65,000
17 Meni Kayu/besi Bola Mas kg 50,000
18 Plamir kg 15,000
19 Dempul Kayu kg 25,000
20 Dempul Plitur kg 70,000
21 Dempul halus (Imfra/Wood Filer) kg 70,000
22 Solignem Ltr 20,000
23 Terpentin Ltr 70,000
24 Thiner A Ltr 22,500
25 Thiner B Ltr 15,000
26 Kompon kg 5,000
27 Oker putih kg 15,000
28 Oker warna kg 12,000
29 Melamik kg 87,000
30 Spirtus ltr 20,000
31 Plitur Jadi ltr 72,000
32 Kuas 3 " bh 8,000
33 Kape Tembok bh 5,500
34 Kape Kayu bh 5,000
35 Ampelas lbr 3,000
36 Water Profing kg 62,000

H BAHAN KAYU/KAYU LAPIS DAN PLAFOND


1 Kayu Balok Alba m3 1,000,000
2 Kayu Papan Alba m3 1,200,000
3 Kayu Terentang m3 48,000
4 Kayu Kamper singkil m3 265,000
5 Kayu Kamper Medan m3 4,350,000
6 Kayu Kamper Medan uk. 3/20 cm - 3/30 cm m3 2,475,000
7 Kayu Kamper Banjar m3 2,475,000
8 Kayu Kamper Banjar uk. 3/20 cm - 3/30 cm m3 85,000
9 Kayu Kamper Samarinda m3 8,600,000
10 Kayu Kamper Samarinda uk. 3/20 cm - 3/30 cm m3 12,500,000
11 Kayu Kamper Samarinda uk. 3/20 cm m1 11,500
12 Kayu Kamper Samarinda uk. 3/30 cm m1 11,500
13 Kayu Balok Borneo Super m3 4,000,000
14 Kayu Papan Borneo Super (Meranti) uk. 3/20 cm - 3/30 cm m3 4,200,000
15 Kayu Kaso Borneo uk. 5/7 - 4,00 m m3 133,000
16 Dolken dia 5 - 7 cm btg 25,000
17 Dolken dia 7 - 10 cm btg 35,000
18 Bambu dia 5 - 7 cm btg 12,000
19 Bambu dia 7 - 10 cm btg 15,000
20 Bambu gombong btg 15,000
21 Triplek 3 mm lbr 50,000
22 Triplek 4 mm lbr 55,000
23 Triplek 4 mm uk. Pintu lbr 66,000
24 Triplek 6 mm lbr 85,000
25 Multiplek 9 mm lbr 100,000
26 Multiplek 12 mm lbr 152,000
27 Multiplek 18 mm lbr 226,000
28 Teakwood 3 mm lbr 130,000
29 Teakwood 4 mm lbr 136,000
30 Teakwood 3 mm uk. Pintu lbr 137,000
31 Teakwood 4 mm uk. Pintu lbr 165,000
32 Melamin 4 mm lbr 10,000
33 Formika Putih lbr 115,000
34 Formika motif uk. Pintu lbr 147,500
35 Reng 2/3 Borneo Super m1 25,000
36 Reng 3/4 Borneo Super m1 28,000
37 Reng 3/4 Kamper Banjar m1 39,000
38 Gyfsum ex. DN lbr 75,000
39 Gyfsum ex. LN lbr 75,000
40 Eternit Asbes 1 X 1 M X 4 mm bh 20,000
41 Eternit Asbes 1 X 1 M X 6 mm bh 65,000
42 Eternit Asbes 1 X 1 M X 5 mm bh 52,000
43 List Profil 1 cm kayu kamper m1 5,000
44 List Profil 2 cm kayu kamper m1 12,500
45 List Profil 4 cm kayu kamper m1 19,000
46 List Profil 5 cm kayu kamper m1 24,500
47 List Profil 10 cm kayu kamper m1 30,000
48 List Profil 7 cm Gyfsum m1 14,000
49 List Profil 10 cm Gyfsum m1 17,200
50 List Profil 14 cm Gyfsum m1 20,000

I BAHAN PENUTUP ATAP


1 Genteng Keramik warna standar, KIA bh 65,000
2 Genteng Keramik warna khusus, KIA bh 70,000
3 Genteng Pelentong pres Molen Oven KW I ex. Jatiwangi bh 4,000
4 Genteng Pelentong Super/ besar natural ex. Jatiwangi bh 2,750
5 Genteng Pelentong Super/ besar Galzuur ex. Jatiwangi bh 6,600
6 Genteng beton natural rengganis bh 7,881
7 Genteng beton natural 14,4/m2 m2 8,800
8 Genteng beton warna 14,4/m3 m2 8,800
9 Genteng Morando natural ex. Jatiwangi bh 5,000
10 Genteng Morando glazuur ex. Jatiwangi bh 4,100
11 Bubung natural morando bh 6,100
12 Bubung glazuur morando bh 13,000
13 Bubung beton natural rengganis bh 4,300
14 Bubung beton warna rengganis bh 5,400
15 Bubung palentong besar natural bh 1,800
16 Bubung palentong besar glazuur bh 2,000
17 Bubung keramik warna standar KIA bh 13,500
18 Bubung keramik warna khusus KIA bh 19,500
19 Atap Asbes uk. 0,85 X 1,15 lbr 25,000
20 Nok Genteng asbes uk. 1.15 m bh 19,000
21 Atap Asbes gelombang uk. 1.05 X 1.80 4mm lbr 25,000
22 Atap Asbes gelombang uk. 1.05 X 2.10 5mm lbr 30,000
23 Atap Asbes gelombang uk. 1.05 X 2.40 4mm lbr 54,000
24 Atap Asbes gelombang uk. 1.05 X 2.70 4mm lbr 60,000
25 Atap Asbes gelombang uk. 1.10 X 1.80 5mm lbr 26,500
26 Atap Asbes gelombang uk. 1.10 X 2.00 5mm lbr 30,600
27 Atap Asbes gelombang uk. 1.10 X 2.50 5mm lbr 35,500
28 Atap Asbes gelombang uk. 1.10 X 3.00 5mm lbr 50,500
29 Atap Asbes gelombang uk. 1.10 X 1.80 6mm lbr 35,000
30 Atap Asbes gelombang uk. 1.10 X 2.00 6mm lbr 34,000
31 Atap Asbes gelombang uk. 1.10 X 2.50 6mm lbr 41,500
32 Atap Asbes gelombang uk. 1.10 X 3.00 6mm lbr 60,000

J BAHAN PENUTUP LANTAI


1 Keramik dinding 10/20, 20/20, KW I putih/polos m2 60,000
2 Keramik dinding 10/20, corak warna anti slip m2 74,000
3 Keramik dinding 20/20, corak warna anti slip m2 65,000
4 Keramik dinding 20/25 corak warna m2 55,000
5 Keramik 20/20 KM warna tua corak warna anti slip m2 65,000
6 Keramik 20/20 KM KW I DN putih polos m2 60,000
7 Keramik Lantai 30/30 DN putih polos m2 53,000
8 Keramik Lantai 30/30 DN corak/warna anti slip m2 61,000
9 Keramik Mozaik lantai 30/30 DN corak/warna anti slip m2 123,000
10 Granit alam uk. Besar DN m2 165,000
11 Granit alam uk. Kecil DN m2 285,000
12 Granito tile Esenza 40 X 40 polis m2 135,000
13 Granito tile Esenza 40 X 40 unpolis m2 137,000
14 Lantai Marmer Citatah uk. 15/30 m2 240,000
15 Lantai Marmer Citatah uk. 20/30 m2 450,000
16 Lantai Marmer Citatah uk. 30/30 m2 490,000
17 Lantai Marmer Citatah uk. 60/60 m2 953,800
18 Lantai Parkuet motif jati uk. 1.2 X 5.0 X 25 cm m2 240,000
19 Lantai Parkuet motif jati uk. 1.2 X 5.0 X 30 cm m2 390,000
20 Flooring jati uk 1.50 X 9.0 X 60/90 - 105.00 cm m2 350,000
21 Flooring Dedan uk 1.50 X 9.0 X 60/75 - 90.00 cm m2 80,000
22 Paving Block segi enam t:6 cm natural m2 30,000
23 Paving Block segi enam t:8 cm natural m2 36,000
24 Paving Block segi enam t:6 cm warna m2 57,500
25 Paving Block segi enam t:8 cm warna m2 58,000
26 Cansteen paving m1 12,500

DAFTAR HARGA SATUAN BAHAN DAN UPAH


ANALISA HARGA SATUAN UPAH
NO NAMA SATUAN UPAH SAT HARGA
1 Mandor Org / hr 85
2 Kepala Tukang Org / hr 80
3 Tukang gali tanah Org / hr 75
4 Tukang batu Org / hr 75
5 Tukang Kayu Org / hr 75
6 Tukang besi Org / hr 75
7 Tukang cat Org / hr 75
8 Pekerja/laden Org / hr 70
MENGHITUNG VOLUME PEKERJAAN

NO URAIAN PEKERJAAN VOL SAT


1 2 3 4

A PEKERJAAN PERMULAAN
1 Pekerjaaan Pembersihan lahan 130.00 m2
2 Pekerjaaan Pasangan Bouwplank 40.00 m1

B PEKERJAAN TANAH & PONDASI


3 Pek. Galian Tanah Pondasi 69,62 m3
4 Pek. Urugan pasir bawah pondasi 34,88 m3
5 Pek. Aanstamping 38,6 m3
6 Pek. Pondasi batu kali 1 : 5 119,34 m3
7 Pek Urugan Tanah kembali 29,62 m3

C PEKERJAAN BETON
1 sloof 1,2 m3
2 kolom (15\15) 0,897 m3
3 balok 0,897 m3

D PEKERJAAN PASANGAN DINDING


1 D1 1:5 = 5,8575 1:3 = 0.9 m2
2 D2 1:5 = 3,775 1:3 = 0.645 m2
3 D3 1:5 = 3,395 1:3 = 3,25 m2
4 D4 1:5 = 8,1 1:3 = 0,9 m2
5 D5 1:5 = 3 1:3 = 3 m2
6 D6 1:5 = 6,475 1:3 = 0,945 m2
7 D7 1:5 = 9,45 1:3 = 1,05 m2
8 D8 1:5 = 1,89 1:3 = 2,25 m2
9 D9 1:5 = 9,45 1:3 = 1,05 m2
10 D10 1:5 = 1,305 1:3 = 1,2 m2
11 D11 1:5 = 12,15 1:3 = 1,35 m2

E PEKERJAAN KUSEN
1 Jendala 1 0.08865 m3
2 Pintu 1 0.135 m3
3 Pintu jendela 0.13455 m3
4 Pintu 2 0.0675 m3
5 Boven light 0.0504 m3

F KUDA-KUDA ATAP
1 KTP1 0.414504 m3
2 KTP2 0.009696 m3

G GORDING DAN NOK


1 KTP1 0.39168 m3
2 KTP2 0.475136 m3
H KASO-KASO DAN RENG
1 KR 0.5712 m3
2 Reng 0.19584 m3

I LISPLANK KAYU 25.44 m3

J PEKERJAAN PLAFOND
Kedap air
1 Kamar mandi 3 m2
2 Teras 7.5 m2
3 Selasar 19 m2
Biasa
1 Ruang tidur 10.5 m2
2 Ruang teras 9 m2
3 Dapur + R.Makan 6 m2

K PEKERJAAN LANTAI
1 Kamar Mandi 3 m2
2 Dapur 7.5 m2
3 Ruang Tamu 9 m2
4 Ruang Tidur 10.5 m2
5 Dinding Kamar Mandi 9.45 m2
6 Dinding Dapur 1.5 m2

L PEKERJAAN FINISHING/PENGECATAN
1 Cat Plafond 55 m2
2 Cat Kusen 82.2125 m2
J1 3.04 m2
P1(2 buah) 15,942,912 m2
P2 1.018 m2
3 Cat Daun Pintu (3 buah) 2.22 m2
4 Cat Daun Jendela (3 buah) 9.9 m2
5 Bidang Cat Kayu 28.067 m2
AAN

SKETSA GAMBAR
5
RENCANA ANGGARAN BIAYA
NO URAIAN PEKERJAAN SATUAN VOLUME HSP (RP) JUMLAH HARGA
A Pek, Permulaan
1 Pembersihan lahan m2 130 15,950 2073500
2 Pek, Bouplank m2 40 61,088.00 2,443,520.00
Jumlah 4,517,020.00
B Pek,Tanah dan Pondasi
1 Galian Tanah Pondasi m3 69.62 40,920 2848850.4
2 Lapisan Pasir m3 34.88 265,694 9267406.72
3 Anstamping m3 38.6 416,922 16093189.2
4 Pas,Batu Kali m3 119.34 730,596.00 87189326.64
5 Urugan Tanah Kembali m3 29.62 19.613 580.93706
Jumlah 115399353.89706
C Pek, Beton
1 Sloof m3 1.2 160,229.00 192274.8
2 Kolom ( 15/15 ) m3 0.897 3,962,742.00 3554579.574
3 Balok m3 0.897 198,078 177675.966
Jumlah 3924530.34
D Pek,Dinding
1 D1 1:5 m2 58,575 240.968 14114700.6
D1 1:3 0.9 251.516 226.3644
2 D2 1:5 m2 3.775 240.968 909.6542
D2 1:3 0.645 251.516 162.22782
3 D3 1:5 m2 3.395 240.968 818.08636
D3 1:3 3.225 251.516 811.1391
4 D4 1:5 m2 8.1 240.968 1951.8408
D4 1:3 0.9 251.516 226.3644
5 D5 1:5 m2 3 240.968 722.904
D5 1:3 3 251.516 754.548
6 D6 1:5 m2 6,475 240.968 1560267.8
D6 1:3 0.945 251.516 237.68262
7 D7 1:5 m2 9.45 240.968 2277.1476
D7 1:3 1.05 251.516 264.0918
8 D8 1:5 m2 1.89 240.968 455.42952
D8 1:3 2.25 251.516 565.911
9 D9 1:5 m2 9.45 240.968 2277.1476
D9 1:3 1.05 251.516 264.0918
10 D10 1:5 m2 1,305 240.968 314463.24
D10 1:3 1.2 251.516 301.8192
11 D11 1:5 m2 12.15 240.968 2927.7612
D11 1:3 1.35 251.516 339.5466
Jumlah 16005925.39802
E Pek, Kusen, pintu , jendela
1 Jendela 1 m3 0.08865 8,653.15 767.1017475
2 Pintu 1 m3 0.135 8,653.15 1168.17525
3 Pintu jendela m3 0.13455 8,653.15 1164.2813325
4 Pintu 2 m3 0.0675 8,653.15 584.087625
5 Bovenlight m3 0.0504 8,653.15 436.11876
Jumlah 4119.764715
F Kuda - Kuda Atap
1 KTP 1 m3 0.414504 9,300.06 3854.91207024
2 KTP 2 m3 0.009696 9,300.06 90.17338176
Jumlah 3945.085452
G Gording dan Nok
1 KTP 1 m3 0.39168 74,437 29155.48416
2 KTP 2 m3 4,475,136 74,437 333,115.70
Jumlah 362271.18216
H Kaso - kaso dan Reng
1 KR m3 0.5712 74,437 42518.4144
2 Reng m3 0.19584 74,437 14577.74208
Jumlah 57096.15648
I Lipslank kayu m3 25.44 57,805 1470559.2
Jumlah 1470559.2
J Pek, Plafond
- Kedap Air
1 K,mandi m2 3 39,831 119493
2 Teras m2 7.5 39,831 298732.5
3 Selasar m2 19 39,831 756789
- Biasa
1 R,Tidur m2 10.5 39,831 418225.5
2 R, Tamu m2 9 39,831 358479
3 Dapur + R,Makan m2 6 39,831 238986
Jumlah 2190705
K Pek, Lantai
1 K,mandi m2 3 160,328 480984
2 Dapur m2 7.5 146,694 1100205
3 R,Tamu m2 9 146,694 1320246
4 R,Tidur m2 10.5 146,694 1540287
5 Dinding K,Mandi m2 9.45 182,589 1725466.05
6 Dinding Dapur m2 1.5 182,589 273883.5
Jumlah 6441071.55
L Finishing ( Cat Kayu )
1 Cat Plafond m2 55 22,563 1240965
2 Cat Kusen m2 822,125 43,461 35730374625
D1 m2 2.04 43,461 88660.44
P1 (2) m2 15,945,912 43,461 693,025,281,432
P2 m2 1,018 43,461 44243298
3 Cat Daun Pintu (3) m2 2.22 43,461 96483.42
4 Cat Daun Jendela (3) m2 9.4 43,461 408533.4
5 Bidang Cat Kayu m2 28,067 43,461 1219819887
Jumlah 730,021,553,884
CATATAN
CEK PENJUMLAHAN HSP JUMLAH HARGA
Rp 2,073,500.00 ok ok
Rp 2,443,520.00 ok ok
Rp 4,517,020.00 ok ok

Rp 2,848,850.40 ok ok
Rp 9,267,406.72 ok ok
Rp 16,093,189.20 ok ok
Rp 87,189,326.64 ok ok
Rp 580.94 ok ok
Rp 115,399,353.90

Rp 192,274.80 OK ok
Rp 3,554,579.57 OK ok
Rp 177,675.97 ini ngambil hspnya dari balok? ok
Rp 3,924,530.34 ok ok

Rp 14,114,700.60 HSP Ok tapi acuannya darimana? ok


Rp 226.36 HSP Ok tapi acuannya darimana? ok
Rp 909.65 HSP Ok tapi acuannya darimana? ok
Rp 162.23 HSP Ok tapi acuannya darimana? ok
Rp 818.09 HSP Ok tapi acuannya darimana? ok
Rp 811.14 HSP Ok tapi acuannya darimana? ok
Rp 1,951.84 HSP Ok tapi acuannya darimana? ok
Rp 226.36 HSP Ok tapi acuannya darimana? ok
Rp 722.90 HSP Ok tapi acuannya darimana? ok
Rp 754.55 HSP Ok tapi acuannya darimana? ok
Rp 1,560,267.80 HSP Ok tapi acuannya darimana? ok
Rp 237.68 HSP Ok tapi acuannya darimana? ok
Rp 2,277.15 HSP Ok tapi acuannya darimana? ok
Rp 264.09 HSP Ok tapi acuannya darimana? ok
Rp 455.43 HSP Ok tapi acuannya darimana? ok
Rp 565.91 HSP Ok tapi acuannya darimana? ok
Rp 2,277.15 HSP Ok tapi acuannya darimana? ok
Rp 264.09 HSP Ok tapi acuannya darimana? ok
Rp 314,463.24 HSP Ok tapi acuannya darimana? ok
Rp 301.82 HSP Ok tapi acuannya darimana? ok
Rp 2,927.76 HSP Ok tapi acuannya darimana? ok
Rp 339.55 HSP Ok tapi acuannya darimana? ok
Rp 16,005,925.40 HSP Ok tapi acuannya darimana? ok

Rp 767.10 OK ok
Rp 1,168.18 OK ok
Rp 1,164.28 OK ok
Rp 584.09 OK ok
Rp 436.12 OK ok
Rp 4,119.76 OK ok

Rp 3,854.91 OK ok
Rp 90.17 OK ok
Rp 3,945.09 OK ok

Rp 29,155.48 OK ok
Rp 333,115,698,432.00 OK ok
Rp 333,115,727,587.49 OK ok

Rp 42,518.41 OK OK
Rp 14,577.74 OK OK
Rp 57,096.16 OK OK
Rp 1,470,559.20
Rp -

Rp 119,493.00 OK OK
Rp 298,732.50 OK OK
Rp 756,789.00 OK OK
Rp - OK OK
Rp 418,225.50 OK OK
Rp 358,479.00 OK OK
Rp 238,986.00 OK OK
Rp 2,190,705.00 OK OK

Rp 480,984.00 OK OK
Rp 1,100,205.00 OK OK
Rp 1,320,246.00 OK OK
Rp 1,540,287.00 OK OK
Rp 1,725,466.05 OK OK
Rp 273,883.50 OK OK
Rp 6,441,071.55 OK OK

Rp 1,240,965.00 OK OK
Rp 35,730,374,625.00 OK OK
Rp 88,660.44 OK OK
Rp 693,025,281,432.00 OK OK
Rp 44,243,298.00 OK OK
Rp 96,483.42 OK OK
Rp 408,533.40 OK OK
Rp 1,219,819,887.00 OK OK
Rp 730,021,553,884.26 OK OK