LANTAI 1
IV PEKERJAAN BETON
1 Pek. Beton Rabat tbl. 5 cm
2 Pek. Sloof 15/20
3 Pek. Kolom K1 25/25
4 Pek. Kolom KP 15/15
5 Pek. Balok B1 25/35
6 Pek. Balok B2 20/20
7 Pek. Balok B3 15/20
8 Pek. Tangga
V PEKERJAAN DINDING
1 Pek. Pasangan 1/2 Bata 1 Pc : 4 Pp
2 Pek. Pasangan 1/2 Bata 1 Pc : 2 Pp
3 Pek. Plesteran Dinding 1 Pc : 4 Ps
4 Pek. Plesteran Dinding 1 Pc : 2 Ps
5 Pek. Acian Dinding dan Beton
6 Pek. Pasang Batu Tempel Marmo
VI PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant
2 Pek. Profil List Palfond Kayu
3 Pek. Plafond Gypsum Board tbl. 9 mm
VII PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30
2 Pek. Lantai Keramik 20 x 20
3 Pek. Keramik Dinding Kamar Mandi 20 x 20
4 Pek. List Keramik Dinding Kamar Mandi
5 Pek. Paving Stone
VIII PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/15
2 Pek. Pasang Pintu PVC
3 Pek. Pasang Daun Pintu Panil
4 Pek. Pasang Daun Jendela Kayu
5 Pek. Pasang Kaca 5 mm
LANTAI 2
I PEKERJAAN BETON
1 Pek. Plat Lantai tbl. 12 cm
2 Pek. Kolom K2 20/20
3 Pek. Kolom KP 15/15
4 Pek. Balok B1 25/35
5 Pek. Balok B3 15/20
6 Pek. Ring Gewel 15/15
II PEKERJAAN DINDING
1 Pek. Pasangan 1/2 bata 1 Pc : 4 Pp
2 Pek. Pasangan 1/2 bata 1 Pc : 2 Pp
3 Pek. Plesteran Dinding 1 Pc : 4 Ps
4 Pek. Plesteran Dinding 1 Pc : 2 Ps
5 Pek. Acian Dinding dan Beton
III PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant
2 Pek. Profil List Palfond Gypsum
3 Pek. Plafond Gypsum Board tbl. 9 mm
IV PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30
2 Pek. Lantai Keramik 20 x 20
3 Pek. Keramik Dinding Kamar Mandi 20 x 20
4 Pek. List Keramik Dinding Kamar Mandi
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/15
2 Pek. Pasang Pintu PVC
3 Pek. Pasang Daun Pintu Panil
4 Pek. Pasang Daun Jendela Kayu
5 Pek. Pasang Kaca 5 mm
VI PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pemasangan Kunci Tanam Pintu
2 Pek. Pemasangan Engsel Pintu
3 Pek. Pemasangan Engsel Jendela
4 Pasangan Grendel Pintu
5 Pasangan Hak Angin
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam
2 Pek. Pengecatan Dinding Luar
3 Pek. Pengecatan Plafond
4 Pek. Pengecatan List Plafond Kayu
5 Pek. Pengecatan Kusen Pintu & Jendela
6 Pek. Pengecatan Daun Pintu
VIII PEKERJAAN INSTALASI LISTRIK
1 Pek. Pemasangan Titk Lampu
2 Pek. Pemasangan Stop Kontak
3 Pek. Pemasangan Saklar Tunggal
4 Pek. Pemasangan Saklar Ganda
IX PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 "
2 Pek. Instalasi Air Bekas Pipa PVC 2,5 "
3 Pek. Instalasi Air Kotor Pipa PVC 3 "
4 Pek. Kloset Duduk Porselen
5 Pek. Kran Air
6 Pek. Floor Drain
X PEKERJAAN ATAP
1 Pek. Pasangan Kuda-kuda (8/12)
2 Pek. Pasangan Balok Tembok + Nok + Gording + Jurai (8/12)
3 Pek. Pasangan Usuk dan Reng
4 Pek. Pasangan Lisplank (2/20)
5 Pek. Penutup Atap Genteng
6 Pek. Pasangan Bubungan
DAFTAR HARGA SATUAN UPAH
Bahan Semen
1 PC (Portland Cement) Kg Rp 1,476.00
2 Semen Portland 40 Kg Zak Rp 59,040.00
3 Semen Portland 50 Kg Zak Rp 73,800.00
4 Semen Warna Kg Rp 15,300.00
Bahan Sanitasi
1 Kloset Jongkok Buah Rp 247,000.00
2 Kloset Duduk Buah Rp 368,000.00
3 Floor Drain Unit Rp 20,000.00
4 Wastafel Buah Rp 358,500.00
5 Kitchen Zink Buah Rp 575,000.00
6 Kran Air Buah Rp 56,000.00
7 Rol TBA Roll Rp 9,000.00
8 Septctank Unit Rp 6,000,000.00
9 Pipa PVC 3/4" panjang 4 m Batang Rp 28,900.00
10 Pipa PVC 4" panjang 4 m Batang Rp 163,000.00
11 Pipa PVC 3" panjang 4 m Batang Rp 97,500.00
Sewa Alat
1 Sewa Alat Bantu Strouss Pile Jam Rp 11,000.00
2 Sewa Stemper Jam Rp 113,700.00
ANALISA HARGA SATUAN PEKERJAAN
I PEKERJAAN PERSIAPAN
Jenis Pekerjaan : Pembersihan Lapangan dan Pemerataan Tanah Per 1 m2 (HSPK 2018)
Satuan : m2
Harga Satuan : Rp 20,533.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0504 O.H Rp 150,000.00 Rp 7,561.23
2 Pekerja 0.1010 O.H Rp 110,000.00 Rp 11,105.90
Sub Total Upah Rp 18,667.13
B. Bahan
1-
2-
Sub Total Bahan
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 18,667.13
E. Overhead + Profit (10% + D) Rp 1,866.71
F. Harga Satuan Pekerjaan (D + E) Rp 20,533.85
Dibulatkan Rp 20,533.00
Jenis Pekerjaan : Pengukuran dan Pemasangan 1 m' Bouwplank (UITZET) (HSPK 2018)
Satuan : m'
Harga Satuan : Rp 126,226.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0101 O.H Rp 150,000.00 Rp 1,512.25
2 Kepala Tukang Kayu 0.0050 O.H Rp 140,000.00 Rp 705.71
3 Tukang Kayu 0.1009 O.H Rp 120,000.00 Rp 12,107.38
4 Pekerja 0.1010 O.H Rp 110,000.00 Rp 11,105.90
Sub Total Upah Rp 25,431.25
B. Bahan
1 Paku Biasa 2 - inchi 0.0200 Doz Rp 16,000.00 Rp 320.00
2 Kayu Merant Papan 2/20, 4/10 0.0070 m3 Rp 5,000,000.00 Rp 35,000.00
3 Kayu Merant Usuk 4/6, 5/7 0.0120 m3 Rp 4,500,000.00 Rp 54,000.00
Sub Total Bahan Rp 89,320.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 114,751.25
E. Overhead + Profit (10% + D) Rp 11,475.12
F. Harga Satuan Pekerjaan (D + E) Rp 126,226.37
Dibulatkan Rp 126,226.00
II PEKERJAAN TANAH
Jenis Pekerjaan : Pembuatan Lubang Strous Pile diameter 30 cm kedalaman 3 m (HSPK 2018)
Satuan : Titk
Harga Satuan : Rp 202,420.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0726 O.H Rp 150,000.00 Rp 10,890.00
2 Pekerja 1.4539 O.H Rp 110,000.00 Rp 159,929.00
Sub Total Upah Rp 170,819.00
B. Bahan
1-
2-
Sub Total Bahan
C. Peralatan
1 Sewa Alat Bantu Strouss Pile 1.2000 Jam Rp 11,000.00 Rp 13,200.00
2-
Sub Total Peralatan Rp 13,200.00
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 184,019.00
E. Overhead + Profit (10% + D) Rp 18,401.90
F. Harga Satuan Pekerjaan (D + E) Rp 202,420.90
Dibulatkan Rp 202,420.00
Jenis Pekerjaan : Pemasangan 1 m3 Batu Kali Belah Kosongan (aanstamping) (HSPK 2018)
Satuan : m3
Harga Satuan : Rp 363,679.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0393 O.H Rp 150,000.00 Rp 5,895.00
2 Kepala Tukang Batu 0.0393 O.H Rp 140,000.00 Rp 5,502.00
3 Tukang Batu 0.3935 O.H Rp 120,000.00 Rp 47,220.00
4 Pekerja 0.7875 O.H Rp 110,000.00 Rp 86,625.00
Sub Total Upah Rp 145,242.00
B. Bahan
1 Pasir Urug 0.4320 m3 Rp 68,000.00 Rp 29,376.00
2 Batu Kali Belah 15/20 cm 1.2000 m3 Rp 130,000.00 Rp 156,000.00
Sub Total Bahan Rp 185,376.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 330,618.00
E. Overhead + Profit (10% + D) Rp 33,061.80
F. Harga Satuan Pekerjaan (D + E) Rp 363,679.80
Dibulatkan Rp 363,679.00
Jenis Pekerjaan : Pekerjaan Pasangan 1 m3 Batu Kali Belah 15/20 cm (1 Pc : 5 Ps) (HSPK 2018)
Satuan : m3
Harga Satuan : Rp 626,523.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0756 O.H Rp 150,000.00 Rp 11,340.00
2 Kepala Tukang Batu 0.0756 O.H Rp 140,000.00 Rp 10,584.00
3 Tukang Batu 0.7567 O.H Rp 120,000.00 Rp 90,804.00
4 Pekerja 1.5144 O.H Rp 110,000.00 Rp 166,584.00
Sub Total Upah Rp 279,312.00
B. Bahan
1 Semen PC 50 kg 0.4320 m3 Rp 396,700.00 Rp 171,374.40
2 Pasir Pasang 0.5440 m3 Rp 170,000.00 Rp 92,480.00
3 Batu Kali Belah 15/20 cm 1.2000 m3 Rp 22,000.00 Rp 26,400.00
Sub Total Bahan Rp 290,254.40
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 569,566.40
E. Overhead + Profit (10% + D) Rp 56,956.64
F. Harga Satuan Pekerjaan (D + E) Rp 626,523.04
Dibulatkan Rp 626,523.00
Jenis Pekerjaan : Pemasangan 1 m2 Pondasi Rollag Bata (Permen PUPR 2016) ( Modifikasi)
Satuan : m2
Harga Satuan : Rp 259,270.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.6000 O.H Rp 150,000.00 Rp 90,000.00
2 Kepala Tukang Batu 0.2000 O.H Rp 140,000.00 Rp 28,000.00
3 Tukang Batu 0.0200 O.H Rp 120,000.00 Rp 2,400.00
4 Pekerja 0.0300 O.H Rp 110,000.00 Rp 3,300.00
Sub Total Upah Rp 123,700.00
B. Bahan
1 Bata Merah 140.000 m3 Rp 800.00 Rp 112,000.00
Sub Total Bahan Rp 112,000.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 235,700.00
E. Overhead + Profit (10% + D) Rp 23,570.00
F. Harga Satuan Pekerjaan (D + E) Rp 259,270.00
Dibulatkan Rp 259,270.00
IV PEKERJAAN BETON
V PEKERJAAN DINDING
Jenis Pekerjaan : Pemasangan 1 m2 Dinding Batu Merah 1 Pc : 4 Pp Tebal 1/2 Bata (HSPK 2018)
Satuan : m2
Harga Satuan : Rp 99,515.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0101 O.H Rp 150,000.00 Rp 1,512.00
2 Tukang Batu 0.1009 O.H Rp 120,000.00 Rp 12,106.80
3 Pekerja 0.3029 O.H Rp 110,000.00 Rp 33,317.90
Sub Total Upah Rp 46,936.70
B. Bahan
1 Semen PC 40 Kg 0.2300 Zak Rp 59,040.00 Rp 13,579.20
2 Pasir Pasang 0.0430 m3 Rp 170,000.00 Rp 7,310.00
Batu Bata Merah Kelas 1
3 70.000 Press Rp 800.00 Rp 56,000.00
(Uk. 22 x 11 x 4.5 cm)
Sub Total Bahan Rp 76,889.20
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 90,468.40
E. Overhead + Profit (10% + D) Rp 9,046.84
F. Harga Satuan Pekerjaan (D + E) Rp 99,515.24
Dibulatkan Rp 99,515.00
Jenis Pekerjaan : Pemasangan 1 m2 Dinding Batu Merah 1 Pc : 2 Pp Tebal 1/2 Bata (HSPK 2018)
Satuan : m2
Harga Satuan : Rp 117,933.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0101 O.H Rp 150,000.00 Rp 1,512.00
2 Tukang Batu 0.1009 O.H Rp 120,000.00 Rp 12,106.80
3 Pekerja 0.3029 O.H Rp 110,000.00 Rp 33,317.90
Sub Total Upah Rp 46,936.70
B. Bahan
1 Semen PC 40 Kg 0.3790 Zak Rp 59,040.00 Rp 22,376.16
2 Pasir Pasang 0.0380 m3 Rp 170,000.00 Rp 6,460.00
Batu Bata Merah Kelas 1
3 70.000 Press Rp 800.00 Rp 56,000.00
(Uk. 22 x 11 x 4.5 cm)
Sub Total Bahan Rp 84,836.16
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 107,212.32
E. Overhead + Profit (10% + D) Rp 10,721.23
F. Harga Satuan Pekerjaan (D + E) Rp 117,933.55
Dibulatkan Rp 117,933.00
VI PEKERJAAN LANGIT-LANGIT
Jenis Pekerjaan : Pemasangan 1 m' List Langit-langit Kayu Profil (Permen PUPR 2016)
Satuan : m'
Harga Satuan : Rp 23,947.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0030 O.H Rp 150,000.00 Rp 450.00
2 Kepala Tukang 0.0050 O.H Rp 140,000.00 Rp 700.00
3 Tukang Kayu 0.0500 O.H Rp 120,000.00 Rp 6,000.00
4 Pekerja 0.0500 O.H Rp 110,000.00 Rp 5,500.00
Sub Total Upah Rp 12,650.00
B. Bahan
1 List kayu Profil 1.0500 m' Rp 8,500.00 Rp 8,925.00
2 Paku 0.0100 Kg Rp 19,500.00 Rp 195.00
Sub Total Bahan Rp 9,120.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 21,770.00
E. Overhead + Profit (10% + D) Rp 2,177.00
F. Harga Satuan Pekerjaan (D + E) Rp 23,947.00
Dibulatkan Rp 23,947.00
Jenis Pekerjaan : Pemasangan 1 m2 Langit-langit Gypsum Board Tebal 9 mm (Permen PUPR 2016)
Satuan : m2
Harga Satuan : Rp 46,972.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0050 O.H Rp 150,000.00 Rp 750.00
2 Kepala Tukang 0.0050 O.H Rp 140,000.00 Rp 700.00
3 Tukang Kayu 0.0500 O.H Rp 120,000.00 Rp 6,000.00
4 Pekerja 0.1000 O.H Rp 110,000.00 Rp 11,000.00
Sub Total Upah Rp 18,450.00
B. Bahan
1 Gypsum Board 0.3640 Lembar Rp 63,000.00 Rp 22,932.00
2 Paku Skrup 0.1100 Kg Rp 12,000.00 Rp 1,320.00
Sub Total Bahan Rp 24,252.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 42,702.00
E. Overhead + Profit (10% + D) Rp 4,270.20
F. Harga Satuan Pekerjaan (D + E) Rp 46,972.20
Dibulatkan Rp 46,972.00
Jenis Pekerjaan : Pemasangan 1 m2 Paving Block Natural Tebal 6 cm (Permen PUPR 2016)
Satuan : m2
Harga Satuan : Rp 736,322.40
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0013 O.H Rp 150,000.00 Rp 195.00
2 Kepala Tukang 0.0500 O.H Rp 140,000.00 Rp 7,000.00
3 Tukang Batu 0.5000 O.H Rp 120,000.00 Rp 60,000.00
4 Pekerja 0.5000 O.H Rp 110,000.00 Rp 55,000.00
Sub Total Upah Rp 122,195.00
B. Bahan
1 Paving Block 8 cm 1.0100 m2 Rp 8,900.00 Rp 8,989.00
2 Pasir Beton 2.0700 m3 Rp 260,000.00 Rp 538,200.00
Sub Total Bahan Rp 547,189.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 669,384.00
E. Overhead + Profit (10% + D) Rp 66,938.40
F. Harga Satuan Pekerjaan (D + E) Rp 736,322.40
Dibulatkan Rp 736,322.00
Jenis Pekerjaan : Pemasangan Kunci Tanam Besar 2x Putar Kuningan (HSPK 2018)
Satuan : Buah
Harga Satuan : Rp 207,696.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0050 O.H Rp 150,000.00 Rp 756.12
2 Kepala Tukang 0.0101 O.H Rp 140,000.00 Rp 1,411.42
3 Tukang Kayu 0.5045 O.H Rp 120,000.00 Rp 60,536.93
4 Pekerja 0.0101 O.H Rp 110,000.00 Rp 1,110.59
Sub Total Upah Rp 63,815.07
B. Bahan
1 Kunci Tanam Besar (Kuningan) 1.0000 Buah Rp 125,000.00 Rp 125,000.00
Sub Total Bahan Rp 125,000.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 188,815.07
E. Overhead + Profit (10% + D) Rp 18,881.51
F. Harga Satuan Pekerjaan (D + E) Rp 207,696.57
Dibulatkan Rp 207,696.00
X PEKERJAAN PENGECATAN
Jenis Pekerjaan : Pengecatan Kayu (1 Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Penutup)
(HSPK 2018)
Satuan : m2
Harga Satuan : Rp 76,550.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0040 O.H Rp 150,000.00 Rp 604.50
2 Tukang Cat 0.1059 O.H Rp 120,000.00 Rp 12,712.80
3 Pekerja 0.0707 O.H Rp 110,000.00 Rp 7,773.70
Sub Total Upah Rp 21,091.00
B. Bahan
1 Cat Kayu 0.1700 Kg Rp 55,000.00 Rp 9,350.00
2 Cat Meni Kayu 0.2000 Kg Rp 20,000.00 Rp 4,000.00
3 Clear Gloss 0.3500 Kg Rp 80,000.00 Rp 28,000.00
4 Plamir Tembok 5 Kg 0.1500 Kaleng Rp 47,000.00 Rp 7,050.00
5 Kuas 4 inchi 0.0100 Buah Rp 10,000.00 Rp 100.00
Sub Total Bahan Rp 48,500.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 69,591.00
E. Overhead + Profit (10% + D) Rp 6,959.10
F. Harga Satuan Pekerjaan (D + E) Rp 76,550.10
Dibulatkan Rp 76,550.00
Jenis Pekerjaan : Pemasangan Pipa Air Bersih diameter 3/4" (HSPK 2018)
Satuan : m'
Harga Satuan : Rp 26,494.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0018 O.H Rp 150,000.00 Rp 272.21
2 Kepala Tukang 0.0060 O.H Rp 140,000.00 Rp 846.86
3 Tukang Pipa 0.0605 O.H Rp 120,000.00 Rp 7,264.43
4 Pekerja 0.0363 O.H Rp 110,000.00 Rp 3,998.13
Sub Total Upah Rp 12,381.62
B. Bahan
Pipa Plastk PVC Tipe AW
1 0.3000 Batang Rp 28,900.00 Rp 8,670.00
Uk. 3/4 Pj. 4 mtr
Pipa Plastk PVC Tipe AW
2 0.1050 Batang Rp 28,900.00 Rp 3,034.50
Uk. 3/4 Pj. 4 mtr
Sub Total Bahan Rp 11,704.50
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 24,086.12
E. Overhead + Profit (10% + D) Rp 2,408.61
F. Harga Satuan Pekerjaan (D + E) Rp 26,494.73
Dibulatkan Rp 26,494.00
Jenis Pekerjaan : Pemasangan Pipa Air Bekas diameter 3" (HSPK 2018)
Satuan : m'
Harga Satuan : Rp 74,089.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0041 O.H Rp 150,000.00 Rp 620.03
2 Kepala Tukang 0.0136 O.H Rp 140,000.00 Rp 1,905.43
3 Tukang Pipa 0.1362 O.H Rp 120,000.00 Rp 16,344.97
4 Pekerja 0.0818 O.H Rp 110,000.00 Rp 8,995.78
Sub Total Upah Rp 27,866.20
B. Bahan
Pipa Plastk PVC Tipe AW
1 0.3000 Batang Rp 97,500.00 Rp 29,250.00
Uk. 3 inchi Pj. 4 mtr
Pipa Plastk PVC Tipe AW
2 0.1050 Batang Rp 97,500.00 Rp 10,237.50
Uk. 3 inchi Pj. 4 mtr
Sub Total Bahan Rp 39,487.50
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 67,353.70
E. Overhead + Profit (10% + D) Rp 6,735.37
F. Harga Satuan Pekerjaan (D + E) Rp 74,089.07
Dibulatkan Rp 74,089.00
Jenis Pekerjaan : Pemasangan Pipa Air Kotor diameter 3" (HSPK 2018)
Satuan : M
Harga Satuan : Rp 74,089.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 0.0041 O.H Rp 150,000.00 Rp 620.03
2 Kepala Tukang 0.0136 O.H Rp 140,000.00 Rp 1,905.43
3 Tukang Pipa 0.1362 O.H Rp 120,000.00 Rp 16,344.97
4 Pekerja 0.0818 O.H Rp 110,000.00 Rp 8,995.78
Sub Total Upah Rp 27,866.20
B. Bahan
Pipa Plastk PVC Tipe AW
1 0.3000 Batang Rp 97,500.00 Rp 29,250.00
Uk. 3 inchi Pj. 4 mtr
Pipa Plastk PVC Tipe AW
2 0.1050 Batang Rp 97,500.00 Rp 10,237.50
Uk. 3 inchi Pj. 4 mtr
Sub Total Bahan Rp 39,487.50
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 67,353.70
E. Overhead + Profit (10% + D) Rp 6,735.37
F. Harga Satuan Pekerjaan (D + E) Rp 74,089.07
Dibulatkan Rp 74,089.00
Jenis Pekerjaan : Pemasangan Bak Kontrol Pasangan Bata 30x30 Tinggi 35 cm (Permen PUPR 2016)
Satuan : Buah
Harga Satuan : Rp 1,114,095.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 2.1600 O.H Rp 150,000.00 Rp 324,000.00
2 Kepala Tukang 0.7200 O.H Rp 140,000.00 Rp 100,800.00
3 Tukang Batu 0.0720 O.H Rp 120,000.00 Rp 8,640.00
4 Pekerja 0.0110 O.H Rp 110,000.00 Rp 1,210.00
Sub Total Upah Rp 434,650.00
B. Bahan
1 Bata Merah 40.000 Buah Rp 800.00 Rp 32,000.00
2 Semen Portland 44.000 Kg Rp 1,476.00 Rp 64,944.00
3 Pasir Pasang 0.0700 m3 Rp 170,000.00 Rp 11,900.00
4 Pasir Beton 0.0600 m3 Rp 260,000.00 Rp 15,600.00
5 Kerikil 0.0700 m3 Rp 260,000.00 Rp 18,200.00
6 Batu Tulangan 1.6000 Kg Rp 272,200.00 Rp 435,520.00
Sub Total Bahan Rp 578,164.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 1,012,814.00
E. Overhead + Profit (10% + D) Rp 101,281.40
F. Harga Satuan Pekerjaan (D + E) Rp 1,114,095.40
Dibulatkan Rp 1,114,095.00
Jenis Pekerjaan : Pemasangan Kuda-kuda Kayu Kamper (Bentang Max 7 m) (HSPK 2018)
Satuan : m3
Harga Satuan : Rp 19,780,217.00
Harga Jumlah
No Uraian Koefisien Satuan
Satuan (Rp) Harga (Rp)
(1) (2) (3) (4) (5) (6) = (3) x (5)
A. Tenaga Kerja
1 Mandor 1.2098 O.H Rp 150,000.00 Rp 181,464.74
2 Kepala Tukang 0.2016 O.H Rp 140,000.00 Rp 28,228.59
3 Tukang Kayu 12.107 O.H Rp 120,000.00 Rp 1,452,886.15
4 Pekerja 4.0385 O.H Rp 110,000.00 Rp 444,236.14
Sub Total Upah Rp 2,106,815.62
B. Bahan
Plat Besi/Baja 244 x 122, tebal
1 15 Lonjor Rp 514,800.00 Rp 7,722,000.00
1,8 mm
3 Paku Klem (No. 4)/Beton 5.6000 Doz Rp 22,000.00 Rp 123,200.00
4 Kayu Kamper Balok 6/12, 6/15 1.1000 m3 Rp 7,300,000.00 Rp 8,030,000.00
Sub Total Bahan Rp 15,875,200.00
C. Peralatan
1-
2-
Sub Total Peralatan
D. Jumlah Harga Tenaga Kerja, Bahan, Peralatan (A + B + C) Rp 17,982,015.62
E. Overhead + Profit (10% + D) Rp 1,798,201.56
F. Harga Satuan Pekerjaan (D + E) Rp 19,780,217.18
Dibulatkan Rp 19,780,217.00
2 Pembuatan Bouwplank/Uitzet
p = 18.00 m
l = 12.00 m
K = 2 (p + l)
= 60.00 m'
II PEKERJAAN TANAH
1 Pek. Galian Tanah
- Pile Cape Type 1
p = 1.00 m
l = 1.00 m
t = 0.30 m
n = 14.00 buah
V1 = (p x l x t )n
= 4.20 m³
5 Pek. Aanstamping
p = 87.50 m
l = 1.00 m
t = 0.20 m
v = pxlxt
= 17.50 m³
- Type 1
p = 36.90 m
l1 = 0.30 m
l2 = 0.85 m
t = 0.80 m
V2 = p ((l1 + l2)/2) t
= 16.97 m³
LANTAI 1
IV PEKERJAAN BETON
1 Pek. Beton Rabat tbl. 5 cm
Ix = 3.25 m Ix = 2.10 m
Iy = 1.75 m Iy = 1.35 m
t = 0.05 m t = 0.05 m
V1 = Ix x Iy x t V2 = Ix x Iy x t
= 0.28 m³ = 0.14 m³
Ix = 3.30 m Ix = 2.50 m
Iy = 4.85 m Iy = 2.25 m
t = 0.05 m t = 0.05 m
V3 = Ix x Iy x t V4 = Ix x Iy x t
= 0.80 m³ = 0.28 m³
Ix = 5.00 m Ix = 3.25 m
Iy = 2.10 m Iy = 5.55 m
t = 0.05 m t = 0.05 m
V5 = Ix x Iy x t V6 = Ix x Iy x t
= 0.53 m³ = 0.90 m³
Ix = 1.78 m Ix = 3.60 m
Iy = 1.75 m Iy = 2.80 m
t = 0.05 m t = 0.05 m
V7 = Ix x Iy x t V8 = Ix x Iy x t
= 0.16 m³ = 0.50 m³
Ix = 1.80 m Ix = 2.35 m
Iy = 3.20 m Iy = 3.00 m
t = 0.05 m t = 0.05 m
V9 = Ix x Iy x t V10 = Ix x Iy x t
= 0.29 m³ = 0.35 m³
Ix = 1.43 m Ix = 2.28 m
Iy = 1.85 m Iy = 1.78 m
t = 0.05 m t = 0.05 m
V11 = Ix x Iy x t V12 = Ix x Iy x t
= 0.13 m³ = 0.20 m³
Ix = 1.43 m Ix = 2.28 m
Iy = 1.85 m Iy = 1.78 m
t = 0.05 m t = 0.05 m
V13 = Ix x Iy x t V14 = Ix x Iy x t
= 0.13 m³ = 0.20 m³
Ix = 1.00 m Ix = 1.25 m
Iy = 1.85 m Iy = 1.25 m
t = 0.05 m t = 0.05 m
V15 = Ix x Iy x t V16 = Ix x Iy x t
= 0.09 m³ = 0.08 m³
Ix = 3.10 m
Iy = 1.00 m
t = 0.05 m
V17 = Ix x Iy x t
= 0.16 m³
8 Pek. Tangga
- Pek. Plat Tangga t = 10 cm - Bekistng
p = 6.10 m K1 = 7.02 m²
l = 0.95 m
t = 0.10 m
V1 = pxlxt
= 0.58 m³
- Pek. Plat Anak Tangga - Bekistng
p = 0.56 m K2 = 1.81 m²
l = 0.95 m
t = 0.18 m
n = 18 m
V2 = 0,5 x p x l x t x n
= 0.86 m³
V PEKERJAAN DINDING
1 Pek. Pasangan 1/2 Bata 1 Pc : 4 Pp
- Luas Dinding
- C1-C3 - E1-E2
p = 3.13 m p = 1.68 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 10.00 m² = 5.36 m²
- G1-G2 - E2-E3
p = 1.68 m p = 1.30 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 5.36 m² = 4.16 m²
- H2-H4 - C3-C4
p = 3.50 m p = 2.00 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 11.20 m² = 6.40 m²
- B3-B4 - B'4-B'5
p = 2.00 m p = 3.10 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 6.40 m² = 9.92 m²
- F5-F6 - H'5-H'6
p = 2.68 m p = 2.63 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 8.56 m² = 8.40 m²
- H''5'-H''6 - H'''1-H'''6
p = 2.13 m p = 11.55 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 6.80 m² = 36.96 m²
- A'1-H'''6 - E2-H2
p = 16.70 m p = 2.65 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 53.44 m² = 8.48 m²
- B3-E3 - B4-D4
p = 5.75 m p = 3.35 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 18.40 m² = 10.72 m²
- G4-H4 - B'5-E5
p = 0.75 m p = 4.80 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 2.40 m² = 15.36 m²
- G5-H'5 - H''5'-H'''5'
p = 1.30 m p = 1.85 m
t = 3.20 m t = 3.20 m
L = pxt L = pxt
= 4.16 m² = 5.92 m²
- H'5''-H''5''
p = 1.85 m
t = 3.20 m
L = pxt
= 5.92 m²
- Luas Gewel
p = 2.43 m
t = 2.60 m
L = (0,5 x p x t) 3
= 9.46 m²
- Luas Kusen
P1 = 5.74 m²
P2 = 3.12 m²
P3 = 3.78 m²
J1 = 3.57 m²
J1a = 2.30 m²
J2 = 2.52 m²
J3 = 4.15 m²
BV = 0.56 m² +
L2 = 25.73 m²
- G1-G2 - E2-E3
p = 1.68 m p = 1.30 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.34 m² = 0.26 m²
- H2-H4 - C3-C4
p = 3.50 m p = 2.00 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.70 m² = 0.40 m²
- B3-B4 - B'4-B'5
p = 2.00 m p = 3.10 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.40 m² = 0.62 m²
- F5-F6 - H'5-H'6
p = 2.68 m p = 2.63 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.54 m² = 0.53 m²
- H''5'-H''6 - H'''1-H'''6
p = 2.13 m p = 11.55 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.43 m² = 2.31 m²
- A'1-H'''6 - E2-H2
p = 16.70 m p = 2.65 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 3.34 m² = 0.53 m²
- B3-E3 - B4-D4
p = 5.75 m p = 3.35 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 1.15 m² = 0.67 m²
- G4-H4 - B'5-E5
p = 0.75 m p = 4.80 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.15 m² = 0.96 m²
- G5-H'5 - H''5'-H'''5'
p = 1.30 m p = 1.85 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.26 m² = 0.37 m²
- H'5''-H''5''
p = 1.85 m
t = 0.20 m
L = pxt
= 0.37 m²
- Luas Kusen
P1 = 0.60 m²
P2 = 0.33 m²
P3 = 1.26 m² +
L2 = 2.19 m²
- G1-G2 - E2-E3
p = 1.68 m p = 1.30 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 5.70 m² = 4.42 m²
- H2-H4 - C3-C4
p = 3.50 m p = 2.00 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 11.90 m² = 6.80 m²
- B3-B4 - B'4-B'5
p = 2.00 m p = 3.10 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 6.80 m² = 10.54 m²
- F5-F6 - H'5-H'6
p = 2.68 m p = 2.63 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 9.10 m² = 8.93 m²
- H''5'-H''6 - H'''1-H'''6
p = 2.13 m p = 11.55 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 7.23 m² = 39.27 m²
- A'1-H'''6 - E2-H2
p = 16.70 m p = 2.65 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 56.78 m² = 9.01 m²
- B3-E3 - B4-D4
p = 5.75 m p = 3.35 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 19.55 m² = 11.39 m²
- G4-H4 - B'5-E5
p = 0.75 m p = 4.80 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 2.55 m² = 16.32 m²
- G5-H'5 - H''5'-H'''5'
p = 1.30 m p = 1.85 m
t = 3.40 m t = 3.40 m
L = pxt L = pxt
= 4.42 m² = 6.29 m²
- H'5''-H''5''
p = 1.85 m
t = 3.40 m
L = pxt
= 6.29 m²
- Total Luas Dinding
L1 = 259.59
- Luas Kusen
P1 = 6.34 m²
P2 = 3.44 m²
P3 = 5.04 m²
J1 = 3.57 m²
J1a = 2.30 m²
J2 = 2.52 m²
J3 = 4.15 m²
BV = 0.56 m² +
L2 = 27.92 m²
t = 1.00 m
l = 3.20 m
L2 = txl
= 3.20 m²
t = 2.60 m
l = 0.25 m
L3 = txl
= 0.65 m²
VI PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant
p = 3.25 m p = 2.10 m
l = 1.75 m l = 1.35 m
L1 = pxl L2 = pxl
= 5.69 m² = 2.84 m²
p = 1.78 m p = 1.28 m
l = 1.85 m l = 1.85 m
L3 = pxl L4 = pxl
= 3.29 m² = 2.37 m²
p = 1.78 m p = 1.00 m
l = 2.28 m l = 1.10 m
L5 = pxl L6 = pxl
= 4.06 m² = 1.10 m²
p = 0.75 m p = 0.75 m
l = 1.50 m l = 1.25 m
L3 = pxl L8 = pxl
L7 = 1.13 m² = 0.94 m²
p = 1.00 m p = 2.35 m
l = 3.10 m l = 2.80 m
L9 = pxl L10 = pxl
= 3.10 m² = 6.58 m²
p = 2.80 m p = 3.10 m
l = 6.10 m l = 7.35 m
L3 = pxl L12 = pxl
L11 = 17.08 m² = 22.79 m²
p = 2.10 m p = 3.30 m
l = 5.00 m l = 4.85 m
L13 = pxl L14 = pxl
= 10.50 m² = 16.01 m²
p = 2.80 m
l = 3.70 m
L15 = pxl
= 10.36 m²
Total Pek. Rangka Plafond Kayu Merant
L = L1 + L2 + L3 + L4 + L5 + L6 + L7 + L8 + L9 + L10 + L11 + L12 + L13
+ L14 + L15
= 107.81 m²
p = 1.78 m p = 1.28 m
l = 1.85 m l = 1.85 m
L3 = pxl L4 = pxl
= 7.26 m' = 6.26 m'
p = 1.78 m p = 1.00 m
l = 2.28 m l = 1.10 m
L5 = pxl L6 = pxl
= 8.12 m' = 3.20 m'
p = 0.75 m p = 0.75 m
l = 1.50 m l = 1.25 m
L3 = pxl L8 = pxl
L7 = 2.75 m' = 2.50 m'
p = 1.00 m p = 2.35 m
l = 3.10 m l = 2.80 m
L9 = pxl L10 = pxl
= 7.45 m' = 9.50 m'
p = 2.80 m p = 3.10 m
l = 6.10 m l = 7.35 m
L3 = pxl L12 = pxl
L11 = 17.00 m' = 15.05 m'
p = 2.10 m p = 3.30 m
l = 5.00 m l = 4.85 m
L13 = pxl L14 = pxl
= 9.65 m' = 15.50 m'
p = 2.85 m
l = 3.70 m
L15 = pxl
= 9.20 m'
p = 5.00 m p = 7.85 m
l = 3.25 m l = 2.10 m
L3 = pxl L4 = pxl
= 16.25 m² 16.49 m²
p = 5.00 m p = 7.85 m
l = 3.25 m l = 2.10 m
L5 = pxl L6 = pxl
= 16.25 m² 16.49 m²
p = 7.30 m p = 3.10 m
l = 3.20 m l = 1.00 m
L7 = pxl L8 = pxl
= 23.36 m² 3.10 m²
p = 1.25 m p = 1.50 m
l = 0.75 m l = 0.75 m
L9 = pxl L10 = pxl
= 0.94 m² 1.13 m²
p = 1.10 m p = 2.30 m
l = 1.00 m l = 1.90 m
L11 = pxl L12 = pxl
= 1.10 m² 4.37 m²
p = 1.00 m p = 1.85 m
l = 0.93 m l = 0.85 m
L3 = pxl L4 = pxl
= 0.93 m² 1.57 m²
p = 1.00 m p = 1.30 m
l = 0.93 m l = 1.05 m
L5 = pxl L6 = pxl
= 0.93 m² 1.37 m²
p = 2.58 m² p = 4.71 m
l = 1.40 m² l = 0.80 m
L3 = 7.11 L4 = pxl
= 3.61 m² 3.77 m²
p = 4.07 m p = 0.54 m
l = 0.80 m l = 0.70 m
L5 = pxl L6 = pxl
= 3.26 m² 0.38 m²
p = 0.75 m p = 0.55 m
l = 0.83 m l = 0.70 m
L7 = pxl L8 = pxl
= 0.62 m² 0.39 m²
- P2 - J1
b = 0.06 m b = 0.06 m
h = 0.15 m h = 0.15 m
p = 4.72 m p = 4.52 m
n = 2.00 buah n = 4.00 buah
V3 = bxhxpxn V4 = bxhxpxn
= 0.08 m³ 0.16 m³
- J1a - J2
b = 0.06 m b = 0.06 m
h = 0.15 m h = 0.15 m
p = 4.56 m p = 6.38 m
n = 2.00 buah n = 1.00 buah
V5 = bxhxpxn V6 = bxhxpxn
= 0.08 m³ 0.06 m³
- J3 - BV
b = 0.06 m b = 0.06 m
h = 0.15 m h = 0.15 m
p = 8.16 m p = 2.30 m
n = 1.00 buah n = 2.00 buah
V7 = bxhxpxn V8 = bxhxpxn
= 0.07 m³ 0.04 m³
Total Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/15
V = V1+V2+V3+V4+V5+V6+V7+V8
= 0.66 m³
- P2
l = 0.71 m
t = 2.04 m
n = 2.00 buah
L3 = pxlxn
= 2.90 m²
L1 = La - Lb
= 0.73 m²
- J2 - Kaca J2
l = 0.63 m l = 0.43 m
t = 1.63 m t = 1.43 m
n = 2.00 buah n = 2.00 buah
La = lxtxn Lb = lxtxn
= 2.05 m² 1.23 m²
L2 = La - Lb
= 0.82 m²
- J3 - Kaca J3
l = 0.63 m l = 0.43 m
t = 1.83 m t = 1.63 m
n = 3.00 buah n = 3.00 buah
La = lxtxn Lb = lxtxn
= 3.46 m² 2.10 m²
L3 = La - Lb
= 1.36 m²
Total Pek. Pasang Daun Jendela Kayu
L = L1+L2+L3
= 2.91 m²
- J2 - J3
l = 0.43 m l = 0.43 m
t = 1.43 m t = 1.63 m
n = 2.00 buah n = 3.00 buah
L3 = pxlxn L4 = pxlxn
= 1.23 m² 2.10 m²
- BV
l = 0.15 m
t = 0.68 m
n = 4.00 buah
L5 = pxlxn
= 0.41 m²
X PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam
Total Pek. Plesteran Dinding 1 Pc : 4 Ps
L1 = L/2
= 228.045 m²
p = 3.00 m p = 1.75 m
l = 3.25 m l = 3.25 m
L3 = pxl L4 = pxl
= 9.75 m² = 5.69 m²
p = 3.25 m p = 2.25 m
l = 4.50 m l = 6.50 m
L5 = pxl L6 = pxl
= 14.63 m² = 14.63 m²
p = 1.50 m
l = 3.75 m
L7 = pxl
= 5.63 m²
p = 1.78 m p = 1.28 m
l = 1.85 m l = 1.85 m
K = (p + l) 2 K = (p + l) 2
= 7.26 m = 6.26 m
L3 = 2.90 m² L4 = 2.50 m²
p = 1.78 m p = 1.00 m
l = 2.28 m l = 1.10 m
K = (p + l) 2 K = (p + l) 2
= 8.12 m = 3.20 m
L5 = 3.25 m² L6 = 1.28 m²
p = 0.75 m p = 0.75 m
l = 1.50 m l = 1.25 m
K = (p + l) 2 K = (p + l) 2
= 2.75 m = 2.50 m
L7 = 1.10 m² L8 = 1.00 m²
p = 1.00 m p = 2.35 m
l = 3.10 m l = 2.80 m
K = (p + l) 2 K = (p + l) 2
= 7.45 m = 9.50 m
L9 = 2.98 m² L10 = 3.80 m²
p = 2.80 m p = 3.10 m
l = 6.10 m l = 7.35 m
K = (p + l) 2 K = (p + l) 2
= 17.00 m = 15.05 m
L11 = 6.80 m² L12 = 6.02 m²
p = 2.10 m p = 3.30 m
l = 5.00 m l = 4.85 m
K = (p + l) 2 K = (p + l) 2
= 9.65 m = 15.50 m
L13 = 3.86 m² L14 = 6.20 m²
p = 2.85 m
l = 3.70 m
K = (p + l) 2
= 9.20 m
L15 = 3.68 m²
- PG
l = 2.54 m
t = 2.15 m
L3 = lxt
= 5.461 m²
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 5.40 m p = 6.40 m
V3 = bxhxp V4 = bxhxp
= 0.065 m³ = 0.077 m³
p = 0.60 m p = 1.90 m
l = 1.05 m l = 1.90 m
L3 = pxl L4 = pxl
= 0.63 m² = 1.805 m²
p = 1.97 m
l = 1.97 m
L5 = pxl
= 1.94 m²
p = 0.60 m p = 1.90 m
l = 1.05 m l = 1.90 m
L3 = pxl L4 = pxl
= 0.63 m² = 1.805 m²
p = 1.97 m
l = 1.97 m
L5 = pxl
= 1.94 m²
LANTAI 2
I PEKERJAAN BETON
1 Pek. Plat Lantai tbl. 12 cm
Ix = 2.00 m Ix = 3.50 m
Iy = 2.00 m Iy = 2.50 m
t = 0.12 m t = 0.12 m
V1 = Ix x Iy x t V2 = Ix x Iy x t
= 0.48 m³ = 1.05 m³
- Bekistng - Bekistng
L1 = Ix x Iy L2 = Ix x Iy
= 4.00 m² = 8.75 m²
Ix = 3.50 m Ix = 2.50 m
Iy = 2.50 m Iy = 2.25 m
t = 0.12 m t = 0.12 m
V3 = Ix x Iy x t V4 = Ix x Iy x t
= 1.05 m³ = 0.68 m³
- Bekistng - Bekistng
L3 = Ix x Iy L4 = Ix x Iy
= 8.75 m² = 5.63 m²
Ix = 3.25 m Ix = 3.25 m
Iy = 2.00 m Iy = 1.75 m
t = 0.12 m t = 0.12 m
V5 = Ix x Iy x t V6 = Ix x Iy x t
= 0.78 m³ = 0.68 m³
- Bekistng - Bekistng
L5 = Ix x Iy L6 = Ix x Iy
= 6.50 m² = 5.69 m²
Ix = 3.25 m Ix = 3.00 m
Iy = 2.50 m Iy = 2.50 m
t = 0.12 m t = 0.12 m
V7 = Ix x Iy x t V8 = Ix x Iy x t
= 0.98 m³ = 0.90 m³
- Bekistng - Bekistng
L7 = Ix x Iy L8 = Ix x Iy
= 8.13 m² = 7.50 m²
Ix = 3.50 m
Iy = 3.00 m
t = 0.12 m
V9 = Ix x Iy x t
= 1.26 m³
- Bekistng
L9 = Ix x Iy
= 10.50 m²
II PEKERJAAN DINDING
1 Pek. Pasangan 1/2 bata 1 Pc : 4 Pp
- Luas Dinding
- G1-G2 - E1-E2
p = 1.68 m p = 1.68 m
t = 3.10 m t = 3.10 m
L = pxt L = pxt
= 5.19 m² = 5.19 m²
- E1-G1 - E1-G2
p = 1.50 m p = 1.85 m
t = 3.10 m t = 3.10 m
L = pxt L = pxt
= 4.65 m² = 5.74 m²
- G2-H2 - E2-E3
p = 0.85 m p = 1.35 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 2.81 m² = 4.46 m²
- C1-C3 - H2-H4
p = 3.13 m p = 3.60 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 10.31 m² = 11.88 m²
- B3-B4 - B'4-B'5
p = 2.00 m p = 3.10 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 6.60 m² = 10.23 m²
- D'4-D'5 - G4-G5
p = 3.10 m p = 3.00 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 10.23 m² = 9.90 m²
- C1-E1 - B3-E3
p = 4.50 m p = 6.05 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 14.85 m² = 19.97 m²
- B4-D4 - D'4-H4
p = 3.40 m p = 3.60 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 11.22 m² = 11.88 m²
- B'5-G5 - Gewel 1
p = 6.40 m p = 8.45 m
t = 3.30 m t = 2.60 m
L = pxt L = pxt
= 21.12 m² = 10.60 m²
- Gewel 2 - Gewel 3
p = 8.45 m p = 7.50 m
t = 2.60 m t = 2.60 m
L = pxt L = pxt
= 10.60 m² = 9.36 m²
- Luas Kusen
P1 = 2.87 m²
P2 = 3.12 m²
P3 = 1.26 m²
J1 = 1.79 m²
J1b = 2.13 m²
J2 = 5.04 m²
J3 = 4.15 m²
BV = 0.28 m² +
L2 = 20.63 m²
- E1-G1 - E2-G2
p = 1.50 m p = 1.85 m
t = 0.20 m t = 0.20 m
L = pxt L = pxt
= 0.30 m² = 0.37 m²
L = pxt L = pxt
= 5.53 m² = 5.53 m²
- E1-G1 - E1-G2
p = 1.50 m p = 1.85 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 4.95 m² = 6.11 m²
- G2-H2 - E2-E3
p = 0.85 m p = 1.35 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 2.81 m² = 4.46 m²
- C1-C3 - H2-H4
p = 3.13 m p = 3.60 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 10.31 m² = 11.88 m²
- B3-B4 - B'4-B'5
p = 2.00 m p = 3.10 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 6.60 m² = 10.23 m²
- D'4-D'5 - G4-G5
p = 3.10 m p = 3.00 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 10.23 m² = 9.90 m²
- C1-E1 - B3-E3
p = 4.50 m p = 6.05 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 14.85 m² = 19.97 m²
- B4-D4 - D'4-H4
p = 3.40 m p = 3.60 m
t = 3.30 m t = 3.30 m
L = pxt L = pxt
= 11.22 m² = 11.88 m²
- B'5-G5 - Gewel 1
p = 6.40 m p = 8.45 m
t = 3.30 m t = 2.60 m
L = pxt L = pxt
= 21.12 m² = 10.60 m²
- Gewel 2 - Gewel 3
p = 8.45 m p = 7.50 m
t = 2.60 m t = 2.60 m
L = pxt L = pxt
= 10.60 m² = 9.36 m²
- Luas Kusen
P1 = 3.17 m²
P2 = 3.44 m²
P3 = 1.68 m²
J1 = 1.79 m²
J1b = 2.13 m²
J2 = 5.04 m²
J3 = 4.15 m²
BV = 0.28 m² +
L2 = 21.68 m²
p = 3.00 m p = 1.75 m
l = 3.25 m l = 3.25 m
L3 = pxl L4 = pxl
= 9.75 m² = 5.69 m²
p = 3.25 m p = 2.25 m
l = 4.50 m l = 6.50 m
L5 = pxl L6 = pxl
= 14.63 m² = 14.63 m²
p = 1.50 m
l = 3.75 m
L3 = pxl
L7 = 5.63 m²
Total Pek. Rangka Plafond Kayu Merant
L = L1 + L2 + L3 + L4 + L5 + L6 + L7
= 71.81 m²
p = 3.00 m p = 1.75 m
l = 3.25 m l = 3.25 m
K3 = 2 x (p + l) K4 = 2 x (p + l)
= 12.50 m' = 10.00 m'
p = 3.25 m p = 2.25 m
l = 4.50 m l = 6.50 m
K5 = 2 x (p + l) K6 = 2 x (p + l)
= 14.15 m' = 13.90 m'
p = 2.95 m
l = 3.75 m
K7 = 2 x (p + l)
= 11.15 m'
IV PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30
p = 4.85 m p = 3.60 m
l = 3.30 m l = 1.40 m
L1 = pxl L2 = pxl
= 16.01 m² 5.04 m²
p = 3.60 m p = 4.35 m
l = 2.10 m l = 3.25 m
L3 = pxl L4 = pxl
= 7.56 m² 14.14 m²
p = 3.25 m p = 3.25 m
l = 1.60 m l = 2.85 m
L5 = pxl L6 = pxl
= 5.20 m² 9.26 m²
- J1 - J1b
b = 0.06 m b = 0.06 m
h = 0.15 m h = 0.15 m
p = 8.16 m p = 4.52 m
n = 1.00 buah n = 2.00 buah
V3 = bxhxpxn V4 = bxhxpxn
= 0.07 m³ 0.08 m³
- J2 - J3
b = 0.06 m b = 0.06 m
h = 0.15 m h = 0.15 m
p = 6.38 m p = 8.16 m
n = 1.00 buah n = 1.00 buah
V5 = bxhxpxn V6 = bxhxpxn
= 0.06 m³ 0.07 m³
- BV
b = 0.06 m
h = 0.15 m
p = 2.30 m
n = 1.00 buah
V7 = bxhxpxn
= 0.02 m³
Total Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/15
V = V1+V2+V3+V4+V5+V6+V7
= 0.44 m³
L1 = La - Lb
= 0.82 m²
- J3 - Kaca J3
l = 0.63 m l = 0.43 m
t = 1.83 m t = 1.63 m
n = 1.00 buah n = 1.00 buah
La = lxtxn Lb = lxtxn
= 1.15 m² 0.70 m²
L2 = La - Lb
= 0.45 m²
- J2 - J3
l = 0.43 m l = 0.43 m
t = 1.43 m t = 1.63 m
n = 1.00 buah n = 1.00 buah
L3 = pxlxn L4 = pxlxn
= 0.61 m² 0.70 m²
- BV
l = 0.15 m
t = 0.68 m
n = 1.00 buah
L5 = pxlxn
= 0.10 m²
p = 3.00 m p = 1.75 m
l = 3.25 m l = 3.25 m
L3 = pxl L4 = pxl
= 9.75 m = 5.69 m
p = 3.25 m p = 2.25 m
l = 4.50 m l = 6.50 m
L5 = pxl L6 = pxl
= 14.63 m = 14.63 m
p = 1.50 m
l = 3.75 m
L7 = pxl
= 5.63 m
p = 3.00 m p = 1.75 m
l = 3.25 m l = 3.25 m
K = (p + l) 2 K = (p + l) 2
= 12.50 m = 10.00 m
L3 = 5.00 m² L4 = 4.00 m²
p = 3.25 m p = 2.25 m
l = 4.50 m l = 6.50 m
K = (p + l) 2 K = (p + l) 2
= 14.15 m = 13.90 m
L5 = 5.66 m² L6 = 5.56 m²
p = 2.95 m
l = 3.75 m
K = (p + l) 2
= 11.15 m
L7 = 4.46 m²
IX PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 "
P = 2.64 m'
X PEKERJAAN ATAP
1 Pek. Pasangan Kuda-kuda (8/12)
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 8.70 m p = 5.00 m
V1 = bxhxp V2 = bxhxp
= 0.104 m³ = 0.060 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 5.00 m p = 2.85 m
V3 = bxhxp V4 = bxhxp
= 0.060 m³ = 0.034 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 2.00 m p = 2.00 m
V5 = bxhxp V6 = bxhxp
= 0.024 m³ = 0.024 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 1.70 m p = 1.70 m
V7 = bxhxp V8 = bxhxp
= 0.020 m³ = 0.020 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 0.90 m p = 1.25 m
V9 = bxhxp V10 = bxhxp
= 0.054 m³ = 0.015 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 1.25 m p = 2.10 m
V11 = bxhxp V12 = bxhxp
= 0.030 m³ = 0.050 m³
b = 0.08 m
h = 0.15 m
p = 2.10 m
V13 = bxhxp
= 0.050 m³
Total Pek. Pasangan Kuda-kuda (8/12)
V = V1+V2+V3+V4+V5+V6+V7+V8+V9+10+V11+V12+V13
= 0.55 m³
b = 0.08 m b = 0.08 m
h = 0.15 m h = 0.15 m
p = 5.20 m p = 4.85 m
V3 = bxhxp V4 = bxhxp
= 0.062 m³ = 0.058 m³
b = 0.08 m
h = 0.15 m
p = 3.90 m
V5 = bxhxp
= 0.140 m³
p = 3.55 m p = 4.35 m
l = 5.05 m l = 4.55 m
L3 = pxl L4 = pxl
= 17.93 m² = 9.90 m²
p = 1.25 m p = 1.00 m
l = 3.75 m l = 1.10 m
L3 = pxl L4 = pxl
= 4.69 m² = 0.55 m²
Total Pek. Pasangan Usuk dan Reng
L = L1 + L2 + L3 + L4 + +L6
= 76.20 m²
p = 3.55 m p = 4.35 m
l = 5.05 m l = 4.55 m
L3 = pxl L4 = pxl
= 17.93 m² = 9.90 m²
p = 1.25 m p = 1.00 m
l = 3.75 m l = 1.10 m
L3 = pxl L4 = pxl
= 4.69 m² = 0.55 m²
IV PEKERJAAN BETON
1 Pek. Beton Rabat tbl. 5 cm 5.23 m³
2 Pek. Sloof 15/20 2.88 m³
3 Pek. Kolom K1 25/25 7.43 m³
4 Pek. Kolom KP 15/15 2.07 m³
5 Pek. Balok B1 25/35 5.84 m³
6 Pek. Balok B2 20/20 0.61 m³
7 Pek. Balok B3 15/20 1.26 m³
8 Pek. Tangga 1.63 m³
V PEKERJAAN DINDING
1 Pek. Pasangan 1/2 Bata 1 Pc : 4 Pp 228.05 m²
2 Pek. Pasangan 1/2 Bata 1 Pc : 2 Pp 13.08 m²
3 Pek. Plesteran Dinding 1 Pc : 4 Ps 456.09 m²
4 Pek. Plesteran Dinding 1 Pc : 2 Ps 26.16 m²
5 Pek. Acian Dinding dan Beton 463.33 m²
6 Pek. Pasang Batu Tempel Marmo 6.69 m²
VI PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant 107.81 m²
2 Pek. Profil List Palfond Kayu 130.34 m'
3 Pek. Plafond Gypsum Board tbl. 9 mm 107.81 m²
VII PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30 122.23 m²
2 Pek. Lantai Keramik 20 x 20 7.11 m²
3 Pek. Keramik Dinding Kamar Mandi 20 x 20 23.85 m²
4 Pek. List Keramik Dinding Kamar Mandi 1.10 m²
5 Pek. Paving Stone 15.12 m²
VIII PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/ 0.66 m³
2 Pek. Pasang Pintu PVC 3.00 buah
3 Pek. Pasang Daun Pintu Panil 14.07 m²
4 Pek. Pasang Daun Jendela Kayu 2.91 m²
5 Pek. Pasang Kaca 5 mm 7.32 m²
IX PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pasangan Kunci Tanam Pintu 7.00 buah
2 Pek. Pasangan Engsel Pintu 4.00 stel
3 Pek. Pasangan Engsel Jendela 7.00 stel
4 Pek. Pasangan Grendel Pintu 7.00 stel
5 Pek. Pasangan Hak Angin 4.00 stel
X PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam 241.12 m²
2 Pek. Pengecatan Dinding Luar 241.12 m²
3 Pek. Pengecatan Plafond 71.81 m²
4 Pek. Pengecatan List Plafond Kayu 52.14 m²
5 Pek. Pengecatan Kusen Pintu & Jendela 18.10 m²
6 Pek. Pengecatan Daun Pintu 14.0698 m²
XI PEKERJAAN INSTALASI LISTRIK
1 Pek. Pemasangan Box Sekring 1.00 buah
2 Pek. Pemasangan Titk Lampu 14.00 buah
3 Pek. Pemasangan Stop Kontak 5.00 buah
4 Pek. Pemasangan Saklar Tunggal 6.00 buah
5 Pek. Pemasangan Saklar Ganda 4.00 buah
XII PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 " 41.64 m'
2 Pek. Instalasi Air Bekas Pipa PVC 2,5 " 37.39 m'
3 Pek. Instalasi Air Kotor Pipa PVC 3 " 37.73 m'
4 Pek. Kloset Duduk Porselen 2.00 buah
5 Pek. Kloset Jongkok Porselen 1.00 buah
6 Pek. Kran Air 7.00 buah
7 Pek. Floor Drain 3.00 buah
8 Pek. Bak Kontrol 1.00 buah
XIII PEKERJAAN RAILLING
1 Pek. Pasang Railling Pagar Besi Hollow Fins Cat Besi 3.00 unit
LANTAI 2
I PEKERJAAN BETON
1 Pek. Plat Lantai tbl. 12 cm 7.85 m³
2 Pek. Kolom K2 20/20 2.38 m³
3 Pek. Kolom KP 15/15 0.87 m³
4 Pek. Balok B1 25/35 0.40 m³
5 Pek. Balok B3 15/20 1.53 m³
6 Pek. Ring Gewel 15/15 0.56 m³
II PEKERJAAN DINDING
1 Pek. Pasangan 1/2 bata 1 Pc : 4 Pp 176.13 m²
2 Pek. Pasangan 1/2 bata 1 Pc : 2 Pp 0.92 m²
3 Pek. Plesteran Dinding 1 Pc : 4 Ps 352.27 m²
4 Pek. Plesteran Dinding 1 Pc : 2 Ps 1.84 m²
5 Pek. Acian Dinding dan Beton 352.85 m²
III PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant 71.81 m²
2 Pek. Profil List Palfond Gypsum 86.70 m'
3 Pek. Plafond Gypsum Board tbl. 9 mm 71.81 m²
IV PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30 57.21 m²
2 Pek. Lantai Keramik 20 x 20 2.52 m²
3 Pek. Keramik Dinding Kamar Mandi 20 x 20 13.44 m²
4 Pek. List Keramik Dinding Kamar Mandi 0.64 m²
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela Kayu Kelas II 6/ 0.44 m³
2 Pek. Pasang Pintu PVC 1.00 buah
3 Pek. Pasang Daun Pintu Panil 5.75 m²
4 Pek. Pasang Daun Jendela Kayu 1.28 m²
5 Pek. Pasang Kaca 5 mm 4.39 m²
VI PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pemasangan Kunci Tanam Pintu 3.00 buah
2 Pek. Pemasangan Engsel Pintu 9.00 buah
3 Pek. Pemasangan Engsel Jendela 4.00 stel
4 Pasangan Grendel Pintu 2.50 stel
5 Pasangan Hak Angin 10.00 buah
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam 177.05 m²
2 Pek. Pengecatan Dinding Luar 177.05 m²
3 Pek. Pengecatan Plafond 71.81 m
4 Pek. Pengecatan List Plafond Kayu 34.68 m
5 Pek. Pengecatan Kusen Pintu & Jendela 12.73 m²
6 Pek. Pengecatan Daun Pintu 5.75 m
VIII PEKERJAAN INSTALASI LISTRIK
1 Pek. Pemasangan Titk Lampu 7.00 buah
2 Pek. Pemasangan Stop Kontak 4.00 buah
3 Pek. Pemasangan Saklar Tunggal 3.00 buah
4 Pek. Pemasangan Saklar Ganda 2.00 buah
IX PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 " 2.64 m'
2 Pek. Instalasi Air Bekas Pipa PVC 2,5 " 1.84 m'
3 Pek. Instalasi Air Kotor Pipa PVC 3 " 0.65 m'
4 Pek. Kloset Duduk Porselen 1.00 buah
5 Pek. Kran Air 2.00 buah
6 Pek. Floor Drain 1.00 buah
X PEKERJAAN ATAP
1 Pek. Pasangan Kuda-kuda (8/12) 0.55 m³
2 Pek. Pasangan Balok Tembok + Nok + Gording 0.82 m³
+ Jurai (8/12)
3 Pek. Pasangan Usuk dan Reng 76.20 m²
4 Pek. Pasangan Lisplank (2/20) 35.75 m'
5 Pek. Penutup Atap Genteng 76.20 m²
6 Pek. Pasangan Bubungan 9.45 m'
TABEL BERAT BESI
Polos Ulir
Diameter Panjang Berat Diameter Panjang Berat
(mm) (m) (kg) (mm) (m) (kg)
6 1 0.22 6 1 0.22
8 1 0.39 8 1 0.39
9 1 0.50 9 1 0.50
10 1 0.62 10 1 0.62
12 1 0.89 12 1 0.89
13 1 1.04 13 1 1.04
14 1 1.21 14 1 1.21
16 1 1.58 16 1 1.58
19 1 2.23 19 1 2.23
22 1 2.98 22 1 2.98
25 1 3.85 25 1 3.85
28 1 4.83 28 1 4.83
32 1 6.31 32 1 6.31
36 1 7.99 36 1 7.99
BAR BENDING SCHEDULE (BESTAT)
0.096
0.200
0.900
0.200
0.900
0.096
0.096
0.200
0.900
0.200
0.900
0.096
3 Strouss (p = 3 m ; d = 30 cm)
n = 21 Buah
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Polos
1 K = 0.942 0.008 0.39 0.94 441.00 415.42 163.91 12.74 0.696 36.75
12.00 37.00
Besi Ulir
2 0.078 0.013 1.04 3.23 168.00 542.81 565.54 3.71 2.307 56.00
0.15 3.00 56.00
2.925
0.078
4 Sloof
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen N1-J1 17.00 Besi Ulir
0.012 0.89 12.00 4.00 48.00 42.61 1.00 12 4.00
11.92 1.00 4.00
0.08
Besi Ulir
5.56 0.012 0.89 5.64 4.00 22.56 20.03 2.13 12 2.00
0.08 2.00 2.00
Besi Polos
0.05 0.008 0.39 0.48 114.33 55.20 21.78 25.00 12 4.57
0.05 115.00 25.00 5.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 17.33 8.64 3.41 25.00 12 0.69
0.05 18.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 37.67 18.24 7.20 25.00 12 1.51
0.05 38.00 25.00 2.00
0.07
0.07
0.12
0.12
4 Segmen A4-D4 3.60 Besi Ulir
0.012 0.89 3.68 4.00 14.72 13.07 3.26 12 1.33
3.52 3.00 2.00
0.08
0.08
Besi Polos
0.05 0.008 0.39 0.48 25.00 12.00 4.73 25.00 12 1.00
0.05 25.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 4.33 2.40 0.95 25.00 12 0.17
0.05 5.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 51.33 24.96 9.85 25.00 12 2.05
0.05 52.00 25.00 3.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 11.00 5.28 2.08 25.00 12 0.44
0.05 11.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Ulir
5.06 0.012 0.89 5.14 4.00 20.56 18.25 2.33 1.72 2.00
0.08 2.00 2.00
Besi Polos
0.05 0.008 0.39 0.48 111.00 53.28 21.02 25.00 0 4.44
0.05 111.00 25.00 5.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 12.67 6.24 2.46 25.00 12 0.51
0.05 13.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 31.00 14.88 5.87 25.00 12 1.24
0.05 31.00 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 20.67 10.08 3.98 25.00 12 0.83
0.05 21.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 17.67 8.64 3.41 25.00 12 0.71
0.05 18.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 18.33 9.12 3.60 25.00 12 0.73
0.05 19.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 11.67 5.76 2.27 25.00 12 0.47
0.05 12.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 22.67 11.04 4.36 25.00 12 0.91
0.05 23.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 18.00 8.64 3.41 25.00 12 0.72
0.05 18.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 14.67 7.20 2.84 25.00 12 0.59
0.05 15.00 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 78.00 37.44 14.77 25.00 12 3.12
0.05 78.00 25.00 4.00
0.07
0.07
0.12
0.12
Total Berat Besi Polos 126.13
5 Kolom K1
n = 22 Buah
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)+(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Ulir
1 5.70 0.016 1.58 6.13 176.00 1078.53 1702.18 1.96 5.9 176.00
0.64 1.00
5.20
0.192
0.096
Besi Polos
0.06 0.01 0.62 0.80 177.00 141.60 87.30 15.00 0.0 11.80
0.06 177.00 15.00 12.00
0.17
0.17
0.17
0.17
6 Kolom KP
n = 17 Buah
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)+(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Polos
1 5.70 0.01 0.62 6.20 68.00 421.60 259.92 1.94 5.8 68.00
0.06 1.00
5.62
0.12
0.4
Besi Polos
0.048 0.008 0.39 0.38 114.33 42.99 16.96 31.91 0.3 3.69
0.048 115.00 31.00 4.00
0.07
0.07
0.07
0.07
7 Balok Type B1
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen C1-G1 6.00 Besi Ulir
0.016 1.58 6.65 4.00 26.61 41.99 1.80 5.35 4.00
0.096 1.00 4.00
6.46
0.096
Besi Ulir
0.096 0.016 1.58 3.73 2.00 7.46 11.78 3.22 12 0.67
3.54 3.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 2.15 4.00 8.61 13.59 5.58 1.24 0.80
1.960 5.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 49.00 49.00 30.21 12.00 0 4.08
0.06 12.00 5.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 3.48 2.00 6.96 10.99 3.45 1.55 0.67
3.29 3.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 2.03 4.00 8.11 12.80 5.92 1.87 0.80
1.835 5.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 45.00 45.00 27.74 12.00 0.00 3.75
0.06 12.00 4.00
0.17
0.17
0.27
0.27
3 Segmen A4-H4 8.60 Besi Ulir
0.016 1.58 9.25 4.00 37.01 58.41 1.30 2.75 4.00
0.096 1.00 4.00
9.06
0.096
Besi Ulir
0.096 0.016 1.58 5.03 2.00 10.06 15.88 2.38 1.94 1.00
4.84 2.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 2.80 4.00 11.21 17.69 4.28 0.79 1.00
2.610 4.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 69.80 69.80 43.03 12.00 0.00 5.82
0.06 12.00 6.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 3.83 2.00 7.66 12.10 3.13 0.50 0.67
3.64 3.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 2.20 4.00 8.81 13.90 5.45 0.99 0.80
2.010 5.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 50.60 50.60 31.19 12.00 0.00 4.22
0.06 12.00 5.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 4.53 2.00 9.06 14.31 2.65 2.94 1.00
4.34 2.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 2.55 4.00 10.21 16.11 4.70 1.79 1.00
2.360 4.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 61.80 61.80 38.10 12.00 0.00 5.15
0.06 12.00 6.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 1.61 2.00 3.21 5.07 7.47 0.75 0.29
1.415 7.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.09 4.00 4.36 6.88 11.01 0.02 0.36
0.898 11.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 15.00 15.00 9.25 12.00 0.00 1.25
0.06 12.00 2.00
0.17
0.17
0.27
0.27
7 Segmen C1-C3 3.00 Besi Ulir
0.016 1.58 3.65 4.00 14.61 23.05 3.29 1.04 1.33
0.096 3.00 2.00
3.46
0.096
Besi Ulir
0.096 0.016 1.58 2.23 2.00 4.46 7.05 5.38 0.84 0.40
2.04 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.40 4.00 5.61 8.85 8.56 0.78 0.50
1.210 8.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 25.00 25.00 15.41 12.00 0.00 2.08
0.06 12.00 3.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 2.03 4.00 8.11 12.80 5.92 1.87 0.80
1.835 5.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 45.00 45.00 27.74 12.00 0.00 3.75
0.06 12.00 4.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 6.11 2.00 12.21 19.28 1.96 5.89 2.00
5.915 1.00 2.00
0.096
Besi Ulir
0.096 0.016 1.58 3.34 4.00 13.36 21.08 3.59 1.98 1.33
3.148 3.00 2.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 87.00 87.00 53.64 12.00 0.00 7.25
0.06 12.00 8.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 1.53 2.00 3.06 4.84 7.83 1.28 0.29
1.34 7.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.05 4.00 4.21 6.64 11.41 0.43 0.36
0.860 11.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 13.80 13.80 8.51 12.00 0.00 1.15
0.06 12.00 2.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 2.03 2.00 4.06 6.41 5.91 1.84 0.40
1.84 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.30 4.00 5.21 8.22 9.22 0.28 0.44
1.110 9.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 21.80 21.80 13.44 12.00 0.00 1.82
0.06 12.00 2.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 1.53 2.00 3.06 4.84 7.83 1.28 0.29
1.34 7.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.05 4.00 4.21 6.64 11.41 0.43 0.36
0.860 11.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 13.80 13.80 8.51 12.00 0.00 1.15
0.06 12.00 2.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 2.36 2.00 4.71 7.44 5.09 0.22 0.40
2.165 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.46 4.00 5.86 9.25 8.19 0.28 0.50
1.273 8.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 27.00 27.00 16.65 12.00 0.00 2.25
0.06 12.00 3.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 2.11 2.00 4.21 6.65 5.70 1.47 0.40
1.915 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.34 4.00 5.36 8.46 8.96 1.28 0.50
1.148 8.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 23.00 23.00 14.18 12.00 0.00 1.92
0.06 12.00 2.00
0.17
0.17
0.27
0.27
8 Balok Type B2
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen A4-A5 3.00 Besi Ulir
0.016 1.58 3.65 4.00 14.61 23.05 3.29 1.04 1.33
0.096 3.00 2.00
3.46
0.096
Besi Ulir
0.096 0.016 1.58 2.23 1.00 2.23 3.52 5.38 0.84 0.20
2.04 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.40 2.00 2.80 4.43 8.56 0.78 0.25
1.210 8.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 0.60 25.00 15.00 9.25 20.00 0.00 1.25
0.06 20.00 2.00
0.12
0.12
0.12
0.12
Besi Ulir
0.096 0.016 1.58 1.41 1.00 1.41 2.22 8.53 0.74 0.13
1.215 8.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 0.99 2.00 1.98 3.12 12.13 0.13 0.17
0.798 12.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 0.60 11.80 7.08 4.36 20.00 0.00 0.59
0.06 20.00 1.00
0.12
0.12
0.12
0.12
Besi Ulir
0.096 0.016 1.58 3.16 1.00 3.16 4.98 3.80 2.53 0.33
2.965 3.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.86 2.00 3.73 5.89 6.44 0.81 0.33
1.673 6.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 0.60 39.80 23.88 14.72 20.00 0.00 1.99
0.06 20.00 2.00
0.12
0.12
0.12
0.12
Besi Ulir
0.096 0.016 1.58 2.61 1.00 2.61 4.11 4.60 1.57 0.25
2.415 4.00 1.00
0.096
Besi Ulir
0.096 0.016 0.62 1.59 2.00 3.18 5.05 7.55 0.87 0.29
1.398 7.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 0.60 31.00 18.60 11.47 20.00 0.00 1.55
0.06 20.00 2.00
0.12
0.12
0.12
0.12
Besi Ulir
0.096 0.016 1.58 1.86 1.00 1.86 2.93 6.46 0.86 0.17
1.665 6.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.21 2.00 2.43 3.83 9.88 1.07 0.22
1.023 9.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 0.60 19.00 11.40 7.03 20.00 0.00 0.95
0.06 20.00 1.00
0.12
0.12
0.12
0.12
9 Balok Type B3
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen N1-C1 5.10 Besi Ulir
0.016 1.58 5.75 4.00 23.01 36.31 2.09 0.50 2.00
0.096 2.00 2.00
5.56
0.096
Besi Polos
0.05 0.008 0.39 0.48 35.00 16.66 6.57 25.21 0.10 1.40
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 34.00 16.18 6.39 25.21 0.10 1.36
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 20.67 9.84 3.88 25.21 0.10 0.83
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 8.33 3.97 1.57 25.21 0.10 0.33
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 35.00 16.66 6.57 25.21 0.10 1.40
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 18.00 8.57 3.38 25.21 0.10 0.72
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 12.33 5.87 2.32 25.21 0.10 0.49
0.05 25.00 1.00
0.07
0.07
0.12
0.12
8 Segmen K8-J8 3.55 Besi Ulir
0.016 1.58 4.20 4.00 16.81 26.53 2.86 3.60 2.00
0.096 2.00 2.00
4.01
0.096
Besi Polos
0.05 0.008 0.39 0.48 24.67 11.74 4.63 25.21 0.10 0.99
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 14.67 6.98 2.75 25.21 0.10 0.59
0.05 25.00 1.00
0.07
0.07
0.12
0.12
10 Segmen I6-J6 1.70 Besi Ulir
0.016 1.58 2.35 4.00 9.41 14.85 5.10 0.24 0.80
0.096 5.00 1.00
2.16
0.096
Besi Polos
0.05 0.008 0.39 0.48 12.33 5.87 2.32 25.21 0.10 0.49
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 76.33 36.33 14.34 25.21 0.10 3.05
0.05 25.00 4.00
0.07
0.07
0.12
0.12
10 Plat Lantai
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Tulangan Ix Lapangan 2.00 0.01 0.62 1.12 7.67 8.59 5.29 10.71 0.80 0.77
1.00 8.00 10.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 2.00 0.01 0.62 0.72 15.33 11.04 6.81 16.67 0.48 0.96
0.50 16.00 16.00 1.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.00 0.01 0.62 0.72 15.33 11.04 6.81 16.67 0.48 0.96
0.50 16.00 16.00 1.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.50 0.01 0.62 1.37 6.00 8.22 5.07 8.76 1.04 0.75
1.25 6.00 8.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 3.50 0.01 0.62 0.85 32.00 27.04 16.67 14.20 0.17 2.29
0.63 32.00 14.00 3.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.50 0.01 0.62 0.85 18.67 15.77 9.72 14.20 0.17 1.33
0.63 19.00 14.00 2.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.50 0.01 0.62 1.37 6.00 8.22 5.07 8.76 1.04 0.75
1.25 6.00 8.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 3.50 0.01 0.62 0.85 32.00 27.04 16.67 14.20 0.17 2.29
0.63 32.00 14.00 3.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.50 0.01 0.62 0.85 18.67 15.77 9.72 14.20 0.17 1.33
0.63 19.00 14.00 2.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.25 0.01 0.62 1.25 7.67 9.55 5.88 9.64 0.79 0.85
1.13 8.00 9.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 2.50 0.01 0.62 0.78 20.33 15.91 9.81 15.34 0.26 1.36
0.56 21.00 15.00 2.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.25 0.01 0.62 0.78 17.00 13.30 8.20 15.34 0.26 1.13
0.56 17.00 15.00 2.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.00 0.01 0.62 1.12 3.50 3.92 2.42 10.71 0.80 0.35
1.00 4.00 10.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 3.25 0.01 0.62 0.72 32.00 23.04 14.20 16.67 0.48 2.00
0.50 32.00 16.00 2.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.00 0.01 0.62 0.72 15.33 11.04 6.81 16.67 0.48 0.96
0.50 16.00 16.00 1.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 1.75 0.01 0.62 0.66 13.67 8.99 5.54 18.25 0.17 0.76
0.44 14.00 18.00 1.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.50 0.01 0.62 1.37 6.83 9.36 5.77 8.76 1.04 0.85
1.25 7.00 8.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 3.25 0.01 0.62 0.85 28.67 24.22 14.93 14.20 0.17 2.05
0.63 29.00 14.00 3.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.50 0.01 0.62 0.85 18.67 15.77 9.72 14.20 0.17 1.33
0.63 19.00 14.00 2.00
0.06
0.10
0.06
Tulangan Ix Lapangan 2.50 0.01 0.62 1.37 7.67 10.50 6.48 8.76 1.04 0.96
1.25 8.00 8.00 1.00
0.06
0.06
Tulangan Iy Tumpuan 3.00 0.01 0.62 0.85 25.33 21.41 13.20 14.20 0.17 1.81
0.63 26.00 14.00 2.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 2.50 0.01 0.62 0.85 18.67 15.77 9.72 14.20 0.17 1.33
0.63 19.00 14.00 2.00
0.06
0.10
0.06
Tulangan Ix Lapangan 3.00 0.01 0.62 1.62 9.33 15.12 9.32 7.41 0.66 1.33
1.50 10.00 7.00 2.00
0.06
0.06
Tulangan Iy Tumpuan 3.50 0.01 0.62 0.97 28.67 27.81 17.14 12.37 0.36 2.39
0.75 29.00 12.00 3.00
0.06
0.10
0.06
Tulangan Ix Tumpuan 3.00 0.01 0.62 0.97 22.00 21.34 13.16 12.37 0.36 1.83
0.75 22.00 12.00 2.00
0.06
0.10
0.06
11 Tangga
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Polos
1 0.01 0.62 4.12 32.00 131.84 81.28 2.91 1.46 16.00
0.06 32.00 2.00 16.00
4.00
0.06
Besi Polos
2 0.008 0.39 0.95 102.00 96.49 38.07 12.68 1.06 8.50
0.05 102.00 12.00 9.00
0.85
0.05
Besi Polos
3 0.008 0.39 0.67 115.00 76.59 30.22 18.02 1.00 6.39
0.05 115.00 18.00 7.00
0.22
0.35
0.05
Besi Polos
4 Bordes 0.01 0.62 4.12 17.00 70.04 43.18 2.91 1.46 8.50
0.06 17.00 2.00 9.00
4.00
0.06
Besi Polos
5 0.008 0.39 0.95 17.00 16.08 6.35 12.68 1.06 1.42
0.05 17.00 12.00 2.00
0.85
0.05
12 Kolom K2
n = 17 Buah
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
No Sketsa Pemotongan
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)+(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Ulir
1 3.50 0.016 1.58 3.90 136.00 530.13 836.67 3.08 0.3 45.33
0.192 3.00 46.00
3.61
0.096
Besi Polos
2.65 0.01 0.62 0.60 377.40 226.44 139.60 20.00 0.0 18.87
0.06 378.00 20.00 19.00
0.06
0.12
0.12
0.12
0.12
13 Kolom K3
n = 11 Buah
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)+(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
Besi Ulir
1 3.50 0.01 0.62 3.79 88.00 333.52 205.62 3.17 0.63 29.33
0.12 3.00 30.00
3.61
0.06
Besi Polos
2.65 0.008 0.39 0.38 205.33 77.21 30.46 31.91 0.34 6.62
0.048 206.00 31.00 7.00
0.048
0.07
0.07
0.07
0.07
14 Balok Type B1
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen A4-A5 3.00 Besi Ulir
0.016 1.58 3.65 4.00 14.61 23.05 3.29 1.04 1.33
0.096 3.00 2.00
3.46
0.096
Besi Ulir
0.096 0.016 1.58 2.23 2.00 4.46 7.05 5.38 0.84 0.40
2.04 5.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.40 4.00 5.61 8.85 8.56 0.78 0.50
1.210 8.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 25.00 25.00 15.41 12.00 0.00 2.08
0.06 12.00 3.00
0.17
0.17
0.27
0.27
Besi Ulir
0.096 0.016 1.58 1.53 2.00 3.06 4.84 7.83 1.276 0.29
1.34 7.00 1.00
0.096
Besi Ulir
0.096 0.016 1.58 1.05 4.00 4.21 6.64 11.41 0.43 0.36
0.860 11.00 1.00
0.096
Besi Polos
0.06 0.01 0.62 1.00 13.80 13.80 8.51 12.00 0.00 1.15
0.06 12.00 2.00
0.17
0.17
0.27
0.27
15 Balok Type B3
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen C1-G1 6.00 Besi Ulir
0.012 0.89 6.08 4.00 24.32 21.59 1.97 5.92 4.00
5.92 1.00 4.00
0.08
0.080
Besi Polos
0.05 0.008 0.39 0.48 41.00 19.52 7.70 25.21 0.00 1.64
0.05 25.00 2.00
0.07
0.07
0.12
0.12
2 Segmen E2-H2 2.55 Besi Ulir
0.012 0.89 2.63 4.00 10.52 9.34 4.56 1.48 1.00
2.47 4.00 1.00
0.08
0.080
Besi Polos
0.05 0.008 0.39 0.48 18.00 8.57 3.38 25.21 0.00 0.72
0.05 25.00 1.00
0.07
0.07
0.12
0.12
3 Segmen B3-E3 5.60 Besi Ulir
0.012 0.89 5.68 4.00 22.72 20.17 2.11 0.64 2.00
5.52 2.00 2.00
0.08
0.080
Besi Polos
0.05 0.008 0.39 0.48 38.33 18.25 7.20 25.21 0.00 1.53
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 25.67 12.22 4.82 25.21 0.00 1.03
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 24.00 11.42 4.51 25.21 0.00 0.96
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 12.67 6.03 2.38 25.21 0.00 0.51
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 20.67 9.84 3.88 25.21 0.00 0.83
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 34.33 16.34 6.45 25.21 0.00 1.37
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 20.67 9.84 3.88 25.21 0.00 0.83
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 24.00 11.42 4.51 25.21 0.00 0.96
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 11.67 5.55 2.19 25.21 0.00 0.47
0.05 25.00 1.00
0.07
0.07
0.12
0.12
13 Segmen G4-G5 2.75 Besi Ulir
0.012 0.89 2.83 4.00 11.32 10.05 4.24 0.68 1.00
2.67 4.00 1.00
0.08
0.080
Besi Polos
0.05 0.008 0.39 0.48 19.33 9.20 3.63 25.21 0.00 0.77
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 24.00 11.42 4.51 25.21 0.00 0.96
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Total Berat Besi Polos 66.67
16 Ring Gewel
Berat Panjang Jumlah Total Total Jumlah Kebutuhan
Dia. Besi Sisa
No Sketsa Pemotongan Besi Pot. Pot. Panjang Berat Pot. Besi
(m) (kg/m) (m) (buah) (m) (kg) (m) (lonjor)
(1) (2) (3) (4) (5) (6) (7)=(5)x(6)(8)=(7)x(4) (9)=12/(5) (10)=12-(5)x(9) (11)=(6)/(9)
1 Segmen 1 4.67 Besi Ulir
0.012 0.89 4.75 4.00 19.00 16.87 2.53 2.50 2.00
4.59 2.00 2.00
0.08
0.08
Besi Polos
0.05 0.008 0.39 0.48 32.13 15.30 6.03 25.21 0.00 1.29
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 32.13 15.30 6.03 25.21 0.00 1.29
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 40.27 19.17 7.56 25.21 0.00 1.61
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 17.27 8.22 3.24 25.21 0.00 0.69
0.05 25.00 1.00
0.07
0.07
0.12
0.12
Besi Polos
0.05 0.008 0.39 0.48 32.13 15.30 6.03 25.21 0.00 1.29
0.05 25.00 2.00
0.07
0.07
0.12
0.12
Harga Jumlah
No Uraian Pekerjaan Volume Satuan
Satuan (Rp.) Harga (Rp.)
(1) (2) (3) (4) (5) (6) = (3) x (5)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 216.00 m² 20,533.00 4,435,128.00
2 Pembuatan Bouwplank/Uitzet 60.00 m' 126226 7,573,560.00
Sub Total 12,008,688.00
II PEKERJAAN TANAH
1 Pek. Galian Tanah 111.99 m³ 95,782.00 10,726,147.27
2 Pek. Bor Strouss dia. 30 cm 4.45 m³ 202,420.00 900,961.30
3 Pek. Urugan Pasir Bawah Pondasi 4.54 m³ 128,072.00 581,158.72
4 Pek. Urugan Tanah Kembali 39.24 m³ 69,399.00 2,723,077.96
5 Pek. Urugan Sirtu 10.80 m³ 112,360.00 1,213,488.00
Sub Total 16,144,833.25
III PEKERJAAN PONDASI
1 Pek. Lantai Kerja Bawah Pondasi 1.05 m³ 934,472.00 981,195.60
2 Pek. Strouss dia. 30 cm 4.45 m³ 5,875,618.00 26,152,081.94
3 Pek. Pile Cap Type 1 4.20 m³ 6,938,714.00 29,142,598.80
4 Pek. Pile Cap Type 2 2.10 m³ 5,620,161.00 11,802,338.10
5 Pek. Aanstamping 17.50 m³ 363,679.00 6,364,382.50
6 Pek. Pondasi Batu Kali 1 Pp : 4 Ps 39.24 m³ 626,523.00 24,583,509.47
7 Pek. Rollag Bata 0.27 m² 259,270.00 70,842.93
Sub Total 99,096,949.35
LANTAI 1
IV PEKERJAAN BETON
1 Pek. Beton Rabat tbl. 5 cm 5.23 m³ 1,107,525.00 5,793,203.01
2 Pek. Sloof 15/20 2.88 m³ 12,658,840.00 36,457,459.20
3 Pek. Kolom K1 25/25 7.43 m³ 9,292,784.00 68,998,921.20
4 Pek. Kolom KP 15/15 2.07 m³ 5,674,095.00 11,719,843.22
5 Pek. Balok B1 25/35 5.84 m³ 16,776,373.00 97,911,106.92
6 Pek. Balok B2 20/20 0.61 m³ 14,782,795.00 8,987,939.36
7 Pek. Balok B3 15/20 1.26 m³ 10,771,251.00 13,587,933.14
8 Pek. Tangga 1.63 m³ 6,865,671.00 11,193,378.06
Sub Total 254,649,784.11
V PEKERJAAN DINDING
1 Pek. Pasangan 1/2 Bata 1 Pc : 4 Pp 228.05 m² 99,515.00 22,693,898.18
2 Pek. Pasangan 1/2 Bata 1 Pc : 2 Pp 13.08 m² 117,933.00 1,542,327.77
3 Pek. Plesteran Dinding 1 Pc : 4 Ps 456.09 m² 73,740.00 33,632,076.60
4 Pek. Plesteran Dinding 1 Pc : 2 Ps 26.16 m² 79,461.00 2,078,381.92
5 Pek. Acian Dinding dan Beton 463.33 m² 71,544.00 33,148,553.06
6 Pek. Pasang Batu Tempel Marmo 6.69 m² 28,647.00 191,648.43
Sub Total 93,286,885.96
VI PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant 107.81 m² 62,656.00 6,755,219.05
2 Pek. Profil List Palfond Kayu 130.34 m' 23,947.00 3,121,251.98
3 Pek. Plafond Gypsum Board tbl. 9 mm 107.81 m² 46,972.00 5,064,258.00
Sub Total 14,940,729.02
VII PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30 122.23 m² 268,273.00 32,791,008.79
2 Pek. Lantai Keramik 20 x 20 7.11 m² 237,738.00 1,690,911.53
3 Pek. Keramik Dinding Kamar 23.85 m² 237,738.00 5,670,407.91
Mandi 20 x 20
4 Pek. List Keramik Dinding 1.10 m² 279,592.00 308,389.98
Kamar Mandi
5 Pek. Paving Stone 15.12 m² 736,322.40 11,133,194.69
Sub Total 51,593,912.89
VIII PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela 0.66 m³ 13,196,466.00 8,731,243.78
Kayu Kelas II (6/15)
2 Pek. Pasang Pintu PVC 3.00 buah 404,855.00 1,214,565.00
3 Pek. Pasang Daun Pintu Panil 14.07 m² 941,928.00 13,252,738.57
Pek. Pasang Daun Jendela Kayu 2.91 m² 683,527.00 1,990,430.62
4 Pek. Pasang Kaca 5 mm 7.32 m² 223,921.00 1,638,049.29
Sub Total 26,827,027.27
IX PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pasangan Kunci Tanam Pintu 7.00 buah 207,696.00 1,453,872.00
2 Pek. Pasangan Engsel Pintu 4.00 stel 64,971.00 259,884.00
3 Pek. Pasangan Engsel Jendela 7.00 stel 48,625.00 340,375.00
4 Pek. Pasangan Grendel Pintu 7.00 stel 42,561.00 297,927.00
5 Pek. Pasangan Hak Angin 4.00 stel 44,918.00 179,672.00
Sub Total 2,531,730.00
X PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam 241.12 m² 23,318.00 5,622,506.11
2 Pek. Pengecatan Dinding Luar 241.12 m² 23,318.00 5,622,506.11
3 Pek. Pengecatan Plafond 71.81 m² 27,701.00 1,989,278.06
4 Pek. Pengecatan List Plafond Kayu 52.14 m² 76,550.00 3,991,010.80
5 Pek. Pengecatan Kusen Pintu 18.10 m² 76,550.00 1,385,616.24
& Jendela
6 Pek. Pengecatan Daun Pintu 14.07 m² 76,550.00 1,077,043.19
Sub Total 19,687,960.52
XI PEKERJAAN INSTALASI LISTRIK
1 Pek. Pemasangan Box Sekring 1.00 buah 4,006,860.00 4,006,860.00
2 Pek. Pemasangan Titk Lampu 14.00 buah 855,597.00 11,978,358.00
3 Pek. Pemasangan Stop Kontak 5.00 buah 242,425.00 1,212,125.00
4 Pek. Pemasangan Saklar Tunggal 6.00 buah 67,525.00 405,150.00
5 Pek. Pemasangan Saklar Ganda 4.00 buah 74,675.00 298,700.00
Sub Total 17,901,193.00
XII PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 " 41.64 m' 26,494.00 1,103,210.16
2 Pek. Instalasi Air Bekas Pipa PVC 2,5 " 37.39 m' 74,089.00 2,770,187.71
3 Pek. Instalasi Air Kotor Pipa PVC 3 " 37.73 m' 74,089.00 2,795,377.97
4 Pek. Kloset Duduk Porselen 2.00 buah 1,006,899.00 2,013,798.00
5 Pek. Kloset Jongkok Porselen 1.00 buah 257,556.00 257,556.00
7 Pek. Kran Air 7.00 buah 96,467.00 675,269.00
8 Pek. Floor Drain 3.00 buah 38,775.00 116,325.00
9 Pek. Bak Kontrol 1.00 buah 1,114,095.00 1,114,095.00
Sub Total 10,845,818.84
XIII PEKERJAAN RAILLING
1 Pek. Pasang Railling Pagar Besi Hollow Fin 3.00 unit 716,144.00 2,148,432.00
Sub Total 2,148,432.00
XIV PEKERJAAN ATAP
1 Pek. Pasangan Gording (8/12) 0.25 m³ 18,720,957.00 4,650,285.72
2 Pek. Pasangan Usuk dan Reng 23.94 m² 219,268.00 5,249,922.76
3 Pek. Pasangan Lisplank (2/20) 9.50 m' 156,624.00 1,487,928.00
4 Pek. Penutup Atap Genteng 23.94 m² 154,636.00 3,702,442.02
Sub Total 15,090,578.50
LANTAI 2
I PEKERJAAN BETON
1 Pek. Plat Lantai tbl. 12 cm 7.85 m³ 17,123,321.00 134,460,878.15
2 Pek. Kolom K2 20/20 2.38 m³ 13,518,686.00 32,174,472.68
3 Pek. Kolom KP 15/15 0.87 m³ 5,461,737.00 4,731,229.68
4 Pek. Balok B1 25/35 0.40 m³ 8,469,086.00 3,408,807.12
5 Pek. Balok B3 15/20 1.53 m³ 10,771,251.00 16,528,484.66
6 Pek. Ring Gewel 15/15 0.56 m³ 9,132,212.00 5,091,664.80
Sub Total 196,395,537.08
II PEKERJAAN DINDING
1 Pek. Pasangan 1/2 bata 1 Pc : 4 Pp 176.13 m² 99,515.00 17,527,975.01
2 Pek. Pasangan 1/2 bata 1 Pc : 2 Pp 0.92 m² 117,933.00 108,498.36
3 Pek. Plesteran Dinding 1 Pc : 4 Ps 352.27 m² 73,740.00 25,976,242.32
4 Pek. Plesteran Dinding 1 Pc : 2 Ps 1.84 m² 79,461.00 146,208.24
5 Pek. Acian Dinding dan Beton 352.85 m² 71,544.00 25,244,157.31
Sub Total 69,003,081.24
III PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant 71.81 m² 62,656.00 4,499,484.00
2 Pek. Profil List Palfond Gypsum 86.70 m' 23,947.00 2,076,204.90
3 Pek. Plafond Gypsum Board tbl. 9 mm 71.81 m² 46,972.00 3,373,176.75
Sub Total 9,948,865.65
IV PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30 x 30 57.21 m² 268,273.00 15,346,556.97
2 Pek. Lantai Keramik 20 x 20 2.52 m² 237,738.00 599,694.11
3 Pek. Keramik Dinding Kamar 13.44 m² 237,738.00 3,195,198.72
Mandi 20 x 20
4 Pek. List Keramik Dinding Kamar 0.64 m² 279,592.00 178,938.88
Mandi
Sub Total 19,320,388.67
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Pasang Kusen Pintu & Jendela 0.44 m³ 13,196,466.00 5,805,389.32
Kayu Kelas II (6/15)
2 Pek. Pasang Pintu PVC 1.00 buah 404,855.00 404,855.00
3 Pek. Pasang Daun Pintu Panil 5.75 m² 941,928.00 5,418,723.40
4 Pek. Pasang Daun Jendela Kayu 1.28 m² 683,527.00 872,180.45
5 Pek. Pasang Kaca 5 mm 4.39 m² 223,921.00 982,654.92
Sub Total 13,483,803.09
VI PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pemasangan Kunci Tanam Pintu 3.00 buah 207,696.00 623,088.00
2 Pek. Pemasangan Engsel Pintu 9.00 buah 64,971.00 584,739.00
3 Pek. Pemasangan Engsel Jendela 4.00 stel 48,625.00 194,500.00
4 Pasangan Grendel Pintu 2.50 stel 42,561.00 106,402.50
5 Pasangan Hak Angin 10.00 buah 44,918.00 449,180.00
Sub Total 1,957,909.50
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam 177.05 m² 23,318.00 4,128,545.17
2 Pek. Pengecatan Dinding Luar 177.05 m² 23,318.00 4,128,545.17
3 Pek. Pengecatan Plafond 71.81 m 27,701.00 1,989,278.06
4 Pek. Pengecatan List Plafond Kayu 34.68 m 76,550.00 2,654,754.00
5 Pek. Pengecatan Kusen Pintu & Jendela 12.73 m² 76,550.00 974,726.46
6 Pek. Pengecatan Daun Pintu 5.75 m 76,550.00 440,376.84
Sub Total 14,316,225.71
VIII PEKERJAAN INSTALASI LISTRIK
1 Pek. Pemasangan Titk Lampu 7.00 buah 855,597.00 5,989,179.00
2 Pek. Pemasangan Stop Kontak 4.00 buah 242,425.00 969,700.00
3 Pek. Pemasangan Saklar Tunggal 3.00 buah 67,525.00 202,575.00
4 Pek. Pemasangan Saklar Ganda 2.00 buah 74,675.00 149,350.00
Sub Total 7,310,804.00
IX PEKERJAAN SANITASI
1 Pek. Instalasi Air Bersih Pipa PVC 3/4 " 2.64 m' 26,494.00 69,944.16
2 Pek. Instalasi Air Bekas Pipa PVC 2,5 " 1.84 m' 74,089.00 136,323.76
3 Pek. Instalasi Air Kotor Pipa PVC 3 " 0.65 m' 74,089.00 48,157.85
4 Pek. Kloset Duduk Porselen 1.00 buah 1,006,899.00 1,006,899.00
5 Pek. Kran Air 2.00 buah 96,467.00 192,934.00
7 Pek. Floor Drain 1.00 buah 38,775.00 38,775.00
Sub Total 1,493,033.77
X PEKERJAAN ATAP
1 Pek. Pasangan Kuda-kuda (8/12) 0.55 m³ 19,780,217.00 10,823,734.74
2 Pek. Pasangan Balok Tembok + Nok 0.82 m³ 18,720,957.00 15,309,998.63
+ Gording + Jurai (8/12)
3 Pek. Pasangan Usuk dan Reng 76.20 m² 219,268.00 16,708,495.69
4 Pek. Pasangan Lisplank (2/20) 35.75 m' 156,624.00 5,599,308.00
5 Pek. Penutup Atap Genteng 76.20 m² 154,636.00 11,783,456.50
6 Pek. Pasangan Bubungan 9.45 m' 172,418.00 1,629,350.10
Sub Total 61,854,343.66
REKAPITULASI RENCANA ANGGARAN BIAYA
LANTAI 1
IV PEKERJAAN BETON
1 Pek. Beton Rabat tbl. 5 cm 5.23 m³
- Semen PC 40 Kg 9.2750 Zak 48.5153
- Pasir Cor 0.4363 m3 2.2819
- Batu Pecah Mesin 1/2 cm 0.5511 m3 2.8824
- Biaya Air 215.0000 Liter 1124.6145
8 Pek. Tangga
a. Pekerjaan Beton Strouss K-225 1.63 m²
- Semen PC 40 Kg 9.2750 Zak 15.1214
- Pasir Cor 0.4363 m3 0.7112
- Batu Pecah Mesin 1/2 cm 0.5511 m3 0.8984
- Biaya Air 215.0000 Liter 350.5231
V PEKERJAAN DINDING
1 Pek. Pasangan 1/2 Bata 1 Pc : 4 Pp 228.05 m²
- Semen PC 40 Kg 0.2300 Zak 52.4504
- Pasir Pasang 0.0430 m3 9.8059
- Batu Bata Merah Kelas 1 (Uk. 22 x 11 x 4.5 cm) 70.0000 Press 15963.1500
VI PEKERJAAN LANGIT-LANGIT
1 Pek. Rangka Plafond Kayu Merant 107.81 m²
- Paku Reng 0.1000 Kg 10.7814
- Kayu Merant Usuk 4/6, 5/7 0.0120 m3 1.2938
X PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Dalam 241.12 m²
- Cat Tembok Dalam 2.5 Kg 0.1040 Kaleng 25.0768
- Dempul Tembok 0.1000 Kg 24.1123
- Kertas Gosok Halus 0.1000 Lembar 24.1123