Anda di halaman 1dari 1

A

KONTRAKTOR PELAKSANA

CV. LEMBAK INDAH


WAY KANAN

R E V I S I
NO TANGGAL KETERANGAN

N N

PEMBERI TUGAS

C C
INSTITUT TEKNOLOGI SUMATERA
Ttd
Jl. Terusan Ryacudu, Lampung Selatan 35365

N A M A PEKERJAAN

LANJUTAN PEMBANGUNAN
GEDUNG LABORATORIUM TEKNIK 2
KAMPUS INSTITUT TEKNOLOGI SUMATERA
TAHUN ANGGARAN 2019

DISETUJUI
1 2
PEJABAT PEMBUAT KOMITMEN

Prof. Dr. Sukrasno, M.S.


NIP: 19580910 198503 1 004

DIPERIKSA
PROJECT IMPLEMENTATIONT UNIT (PIU)

Kardo Rajagukguk
KETUA

DIBUAT
KONTRAKTOR PELAKSANA
CV. LEMBAK INDAH

R.INSTRUKTUR R.SECURITY R.INSTRUKTUR


R.INSTRUKTUR
±0.0
±0.0 BENGKEL REKAYASA MATERIAL R.DOSEN ±0.0 ±0.0
LOBBY ±0.0 LOBBY
±0.0
±0.0 ±0.0

BENGKEL REKAYASA MATERIAL R.DOSEN R. PANEL BENGKEL ARSITEKTUR


R.DOSEN ±0.0 R.INSTRUKTUR
±0.0 R.BAHAN ±0.0 R.BAHAN ±0.0
±0.0 LAB. TAMBANG ±0.0
±0.0 ±0.0 R.DOSEN
±0.0 R.LABORAN R.KA.LAB ±0.0
R. BERSIH
±0.0 ±0.0
R.ALAT ±0.0
R.ALAT R.DOSEN R.ALAT
±0.0 ±0.0
±0.0 ±0.0
YULIANTI
Direktris

PERHATIAN
R.ALAT R.BAHAN DAN ALAT
±0.0 R.DOSEN R.DOSEN R.BAHAN DAN ALAT
R. TOOLS R. MEETING R.DOSEN ±0.0
±0.0 TOILET PRIA ±0.0
R.DOSEN ±0.0
±0.0 ±0.0 ±0.0 -0.05 ±0.0
TOILET PRIA
WORKSHOP MESIN -0.05 1. SEMUA UKURAN DALAM MILIMETER KECUALI DITENTUKAN
±0.0 R.INSTRUKTUR LAB. T S E
R. T U K ±0.0 BENGKEL KONVERSI ENERGI BENGKEL MANUFAKTUR LAIN.
±0.0
±0.0
TOILET WANITA ±0.0
±0.0 JAN -0.05
TOILET WANITA R.DOSEN
-0.05 ±0.0
R. INSTRUKTUR 2. SEBELUM PELAKSANAAN PEKERJAAN DIMULAI, PELAKSANA
±0.0 R.INSTRUKTUR R.DOSEN ±0.0
R.DOSEN
R.DOSEN R.KA LAB + LABORAN R.DOSEN R.KA LAB + LABORAN DIWAJIBKAN MEMERIKSA, MEMBANDINGKAN SEMUA
±0.0 ±0.0
±0.0
TOILET DIFABLE ±0.0
±0.0
±0.0
-0.05
GAMBAR ARSITEKTUR, STRUKTUR, MEP, SERTA
MELAPORKAN KEPADA DIREKSI LAPANGAN/PERENCANA
APABILA TERDAPAT GAMBAR YANG TIDAK COCOK/TIDAK
SESUAI TERMASUK DIMENSI ATAU UKURAN.

3. GAMBAR ARSITEKTUR DIPAKAI SEBAGAI GAMBAR ACUAN


STRUKTUR & MEP DAN JIKA TERJADI KETIDAKCOCOKAN
GAMBAR - GAMBAR TERSEBUT TERMASUK DIMENSI ATAU
TULISAN MAKA SEGERA MELAPORKAN KEPADA DIREKSI
LAPANGAN / PERENCANA SEBELUM PELAKSANAAN
LAPANGAN DIMULAI.

JENIS GAMBAR

ASBUILT DRAWING

JALUR MENUJU KE GLT 2 (LANTAI 1 DAN 2) JUDUL GAMBAR

JALUR DARI LANTAI 2 GLT MENUJU GKU 1

Anda mungkin juga menyukai