304,00)
B. PEKERJAAN TANAH
GALIAN TANAH BIASA SEDALAM 1 METER / M3
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
B Tenaga Kerja
1 Pekerja OH 0,750 58.800,00 44.100,00
2 Mandor OH 0,025 68.600,00 1.715,00
B Tenaga Kerja
1 Pekerja OH 0,500 58.800,00 29.400,00
2 Mandor OH 0,050 68.600,00 3.430,00
B Tenaga Kerja
1 Pekerja OH 0,500 58.800,00 29.400,00
2 Mandor OH 0,050 68.600,00 3.430,00
B Tenaga Kerja
1 Pekerja OH 0,300 58.800,00 17.640,00
2 Mandor OH 0,010 68.600,00 686,00
B Tenaga Kerja
1 Pekerja OH 1,500 58.800,00 88.200,00
2 Tukang Batu OH 0,750 68.600,00 51.450,00
3 Kepala Tukang OH 0,075 78.400,00 5.880,00
4 Mandor OH 0,075 68.600,00 5.145,00
Jumlah Harga Bahan dan Tenaga Kerja (A+B) 597.331,00
Overhead & Profit 10% 59.733,10
Total 657.064,10
Dibulatkan 657.000,00
D. PEKERJAAN BETON
MEMBUAT LANTAI KERJA BETON MUTU K.100 SLUMP (3 - 6)cm / M3
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
1 Portland Cement (PC) Kg 230,000 1.039,36 239.052,80
2 Pasir Beton (PB) M3 0,638 119.616,00 76.297,92
3 Kerikil max 30 mm (KR) M3 0,761 289.408,00 220.164,46
4 Air Liter 200,000 107,52 21.504,00
B Tenaga Kerja
1 Pekerja OH 1,200 58.800,00 70.560,00
2 Tukang Batu OH 0,200 68.600,00 13.720,00
3 Kepala Tukang OH 0,020 78.400,00 1.568,00
4 Mandor OH 0,060 68.600,00 4.116,00
Jumlah Harga Bahan dan Tenaga Kerja (A+B) 646.983,18
Overhead & Profit 10% 64.698,32
Total 711.681,49
Dibulatkan 711.600,00
MEMBUAT 1 M3 BETON MUTU f'c = 14,5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0,66
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
1 Semen Portland Kg 326,000 1.039,36 338.831,36
2 Pasir Beton Kg 760,000 85,44 64.934,40
3 Kerikil Kg 1.029,000 214,38 220.593,21
4 Air L 215,000 107,52 23.116,80
B Tenaga Kerja
1 Pekerja OH 1,650 58.800,00 97.020,00
2 Tukang batu OH 0,275 68.600,00 18.865,00
3 Kepala Tukang OH 0,028 78.400,00 2.195,20
4 Mandor OH 0,083 68.600,00 5.693,80
B Tenaga Kerja
1 Pekerja OH 1,650 58.800,00 97.020,00
2 Tukang batu OH 0,275 68.600,00 18.865,00
3 Kepala Tukang OH 0,028 78.400,00 2.195,20
4 Mandor OH 0,083 68.600,00 5.693,80
Pekerjaan Sloof
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
KAYU KELAS III m3 0,270 1.980.160,00 534.643,20
PAKU 5 - 12 CM kg 2,000 17.740,80 35.481,60
MINYAK BEKISTING liter 0,600 12.992,00 7.795,20
BESI BETON POLOS kg 157,000 10.752,00 1.688.064,00
KAWAT BETON kg 3,000 17.920,00 53.760,00
PC kg 336,000 1.039,36 349.224,96
PLYWOOD 8 MM lbr 2,800 110.656,00 309.836,80
PB kg 0,540 119.616,00 64.592,64
KR kg 0,810 289.408,00 234.420,48
PEKERJA oh 5,650 58.800,00 332.220,00
TUKANG BATU oh 0,275 68.600,00 18.865,00
TUKANG KAYU oh 0,560 68.600,00 38.416,00
TUKANG BESI oh 1,400 68.600,00 96.040,00
KEPALA TUKANG oh 0,323 78.400,00 25.323,20
MANDOR oh 0,283 68.600,00 19.413,80
total 3.808.096,88
3.808.096,88
B BAHAN
Kayu Kelas III m3 0,0 1.980.160,00 5.940,48
Paku 5 cm-12 cm kg 0,0 17.740,80 354,82
Minyak Bekisting liter -
Besi Beton Polos kg 3,6 10.752,00 38.707,20
Kawat Beton kg 0,1 17.920,00 896,00
Semen Portland kg 5,5 1.039,36 5.716,48
Pasir Beton m3 0,0 119.616,00 1.076,54
Kerikil m3 0,0 289.408,00 4.341,12
C PERALATAN
B BAHAN
Kayu Kelas III m3 0,0 1.980.160,00 3.960,32
Paku 5 cm-12 cm kg 0,0 17.740,80 177,41
Minyak Bekisting liter -
Besi Beton Polos kg 3,0 10.752,00 32.256,00
Kawat Beton kg 0,5 17.920,00 8.064,00
Semen Portland kg 4,0 1.039,36 4.157,44
Pasir Beton m3 0,0 119.616,00 717,70
Kerikil m3 0,0 289.408,00 2.604,67
C PERALATAN
Panel Beton P1
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan / 10 kg
1 Panel Beton P1 unit 1,000 120.960,00 120.960,00
Aksesoris % 20,000 120.960,00 24.192,00
B Tenaga Kerja / 10 kg
1 Jasa Pemasangan uni1 1,000 17.920,00 17.920,00
Panel Beton P2
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan / 10 kg
1 Panel Beton P1 unit 1,000 107.520,00 107.520,00
Aksesoris % 20,000 107.520,00 21.504,00
B Tenaga Kerja / 10 kg
1 Jasa Pemasangan uni1 1,000 17.920,00 17.920,00
Panel Beton P3
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan / 10 kg
1 Panel Beton P1 unit 1,000 89.600,00 89.600,00
Aksesoris % 20,000 89.600,00 17.920,00
B Tenaga Kerja / 10 kg
1 Jasa Pemasangan uni1 1,000 17.920,00 17.920,00
B Tenaga Kerja / 10 kg
1 Pekerja OH 0,070 58.800,00 4.116,00
2 Tukang Besi OH 0,070 68.600,00 4.802,00
3 Kepala Tukang OH 0,007 78.400,00 548,80
4 Mandor OH 0,004 68.600,00 274,40
D. PEKERJAAN DINDING
Pemasangan 1 m² dinding bataco campuran 1SP :3PP
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A TENAGA
Pekerja OH 0,3 58.800,00 17.640,00
Tukang Batu OH 0,1 68.600,00 6.860,00
Kepala Tukang OH 0,0 78.400,00 784,00
Mandor OH 0,0 68.600,00 1.029,00
B BAHAN
Batako bh 13,00 3.584,00 46.592,00
PC kg 5,83 1.039,36 6.062,59
Pasir Pasang m3 0,01 119.616,00 1.590,89
C PERALATAN
B Tenaga Kerja
1 Pekerja OH 0,300 58.800,00 17.640,00
2 Tukang Batu OH 0,100 68.600,00 6.860,00
3 Kepala Tukang OH 0,010 78.400,00 784,00
4 Mandor OH 0,015 68.600,00 1.029,00
B Tenaga Kerja
1 Pekerja OH 0,200 58.800,00 11.760,00
2 Tukang Batu OH 0,100 68.600,00 6.860,00
3 Kepala Tukang OH 0,010 78.400,00 784,00
4 Mandor OH 0,010 68.600,00 686,00
BAJA RINGAN
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
Main truss C-75-75 m 2,500 14.336,00 35.840,00
Roof Bottom/Reng R 33-0.45 m' 2,000 6.122,67 12.245,33
Self drilling screw dia 6 x 20 mm (truss Screw) bh 25,000 358,00 8.950,00
Dynabol dia 12 x 120 mm bh 0,500 4.480,00 2.240,00
B Tenaga Kerja
Tukang kayu OH 0,300 58.800,00 17.640,00
Kepala Tukang OH 0,030 78.400,00 2.352,00
Mandor OH 0,030 68.600,00 2.058,00
ATAP SPANDEK
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
Atap metal polos m 1,010 33.152,00 33.483,52
Paku berbagai ukuran (1/2" - 1") m' 0,050 24.998,40 1.249,92
B Tenaga Kerja
Pekerja OH 0,200 58.800,00 11.760,00
Tukang kayu OH 0,100 68.600,00 6.860,00
Kepala tukang OH 0,010 78.400,00 784,00
Mandor OH 0,001 68.600,00 68,60
B Tenaga Kerja
1 Pekerja OH 0,500 58.800,00 29.400,00
2 Tukang Batu OH 0,400 68.600,00 27.440,00
3 Kepala Tukang OH 0,075 78.400,00 5.880,00
4 Mandor OH 0,025 68.600,00 1.715,00
B Tenaga Kerja
1 Pekerja OH 0,036 58.800,00 2.116,80
2 Tukang Batu OH 0,060 68.600,00 4.116,00
3 Kepala Tukang OH 0,006 78.400,00 470,40
4 Mandor OH 0,0020 68.600,00 137,20
B Tenaga Kerja
1 Pekerja OH 0,081 58.800,00 4.762,80
2 Tukang Batu OH 0,135 68.600,00 9.261,00
3 Kepala Tukang OH 0,0135 78.400,00 1.058,40
4 Mandor OH 0,0040 68.600,00 274,40
B Tenaga Kerja
1 Pekerja OH 0,010 58.800,00 588,00
2 Tukang Batu OH 0,400 68.600,00 27.440,00
3 Kepala Tukang OH 0,040 78.400,00 3.136,00
4 Mandor OH 0,005 68.600,00 343,00
B Tenaga Kerja
1 Pekerja OH 0,010 58.800,00 588,00
2 Tukang Batu OH 0,100 68.600,00 6.860,00
3 Kepala Tukang OH 0,010 78.400,00 784,00
4 Mandor OH 0,005 68.600,00 343,00
O. PEKERJAAN ELEKTRIKAL
INSTALASI PENERANGAN / TITIK
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
1 Kabel Distribusi, Tipe NYM 3 x 2.5 mm² M' 20,0 4.480,00 89.600,00
2 Konduit PVC High Impact f 20 mm² Bt 2,0 3.136,00 6.272,00
3 T Dus Buah 1,0 2.688,00 2.688,00
4 L Bow Buah 4,0 8,00 32,00
5 Las Dop Buah 3,0 246,00 738,00
6 Klem Buah 24,0 672,00 16.128,00
7 Mangkok Buah 1,0 448,00 448,00
8 Saklar Buah 1,0 18.099,20
9 Fitting Buah 1,0 17.920,00 17.920,00
10 Upah Instalasi Ls 1,0 44.800,00 44.800,00
SAKLAR TUNGGAL / BH
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SAT UNIT
( Rp. ) ( Rp. )
A Bahan
1 Frame + Saklar 1 Gang, 1 Way Buah 1,0 18.099,20 18.099,20
2 Inbouwdoos Buah 1,0 2.419,00 2.419,00
3 Upah Pasang Ls 1,0 3.584,00 3.584,00
SAKLAR GANDA / BH
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SAT UNIT
( Rp. ) ( Rp. )
A Bahan
1 Frame + Saklar 2 Gang, 1 Way Buah 1,0 24.281,60 24.281,60
2 Inbouwdoos Buah 1,0 2.419,00 2.419,00
3 Upah Pasang Ls 1,0 5.376,00 5.376,00
LAMPU 15 W / BH
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SAT UNIT
( Rp. ) ( Rp. )
A Bahan
1 Armature, Fitting, Holder Set 1,0 22.400,00 22.400,00
2 Lampu Bohlam 15 W Buah 1,0 10.752,00 10.752,00
3 Mur, Paku, Isolasi serta aksesoris penunjang Lot 1,0 3.136,00 3.136,00
4 Upah Pasang Ls 1,0 4.480,00 4.480,00
B Bahan
1 Pipa Listrik 5/8" Btg 3,0 4.480,00 13.440,00
2 Kabel m 15,0 3.136,00 47.040,00
3 T Dus Buah 1,0 2.688,00 2.688,00
4 L Bow Buah 2,0 35,00 70,00
5 Klem Biasa Buah 24,0 672,00 16.128,00
6 MCB Buah 1,0 40.768,00 40.768,00
Jumlah Harga 568.134,00
Overhead & Profit 10% 56.813,40
Total 624.947,40
Dibulatkan 624.900,00
Koral Sikat
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
1 Koral sikat Kg 7,000 Rp 4.800,00 33.600,00
B Tenaga Kerja
1 Pekerja OH 0,500 Rp 58.800,00 29.400,00
2 Mandor OH 0,300 Rp 68.600,00 20.580,00
B Tenaga Kerja
1 Pekerja OH 0,400 Rp 58.800,00 23.520,00
Tukang Batu OH 0,300 Rp 68.600,00 20.580,00
Kepala Tukang OH 0,100 Rp 78.400,00 7.840,00
2 Mandor OH 0,010 Rp 68.600,00 686,00
Laston Lapis Aus (AC-WC).t= 4 cm, dengan aditif Anti Strpping Agent
HARGA SATUAN JUMLAH HARGA
NO. KEBUTUHAN SATUAN INDEKS
( Rp. ) ( Rp. )
A Bahan
Asphalt Hot Mix AC-WC Ton 1,050 Rp 1.380.000,00 1.449.000,00
Adhesion promoter untuk hotmix (Anti Stripping
Kg Agent) 0,500 Rp 95.000,00 47.500,00
B Tenaga Kerja
Pekerja OH 0,500 Rp 58.800,00 29.400,00
Mandor OH 0,050 Rp 68.600,00 3.430,00
C PERALATAN
Babby Roller Hari 0,200 Rp 695.000,00 139.000,00
Alat Bantu ls 1,000 Rp 5.000,00 5.000,00