PEKERJAAN TANAH (SNI 2835 : 2008)
1 1 M3 GALIAN TANAH BIASA DALAM 1 METER
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7500 80,000.00 60,000.00
Mandor OH 0.0250 130,000.00 3,250.00
JUMLAH TENAGA KERJA 63,250.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 63,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 63,250.00

2 1 M3 GALIAN TANAH BIASA DALAM 2 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.9000 80,000.00 72,000.00
Mandor OH 0.0450 130,000.00 5,850.00
JUMLAH TENAGA KERJA 77,850.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,850.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 77,850.00

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0500 80,000.00 84,000.00
Mandor OH 0.0670 130,000.00 8,710.00
JUMLAH TENAGA KERJA 92,710.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 92,710.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 92,710.00
4 1 M3 URUGAN PASIR
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 80,000.00 24,000.00
Mandor OH 0.0100 130,000.00 1,300.00
JUMLAH TENAGA KERJA 25,300.00
B. BAHAN
Pasur Urug m3 1.2000 345,000.00 414,000.00
JUMLAH HARGA BAHAN 414,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 439,300.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 439,300.00

5 1 M3 PEMADATAN TANAH ( Per 20 Cm )


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5000 80,000.00 40,000.00
Mandor OH 0.0500 130,000.00 6,500.00
JUMLAH TENAGA KERJA 46,500.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 46,500.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 46,500.00

6 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 80,000.00 20,000.00
Mandor OH 0.0250 130,000.00 3,250.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Sirtu m3 1.2000 320,000.00 384,000.00
JUMLAH HARGA BAHAN 384,000.00
C. PERALATAN -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 407,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 407,250.00
REKAP VOLUME

NO URAIAN PEKERJAAN SATUAN VOLUME


I PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi Menerus m³ 57.73095
2 Galian Tanah Pondasi Setempat m³ 129.6
3 Urugan Pasir dibawah Pondasi Menerus m³ 9.122375
4 Urugan Tanah Pondasi Menerus m³ 0.117
5 Pek. Urugan Tanah Peninggi Lantai m³ 168.3
6 Pek. Urugan Pasir dibawah Lantai m³ 14.3861
PERHITUNGAN VOLUME PEKERJAAN

No. Uraian Pekerjaan Volume Satuan Gambar


1 Pekerjaan Pondasi Footplat
a Pekerjaan Galian 129.600 m3 Volume Galian = (p x l x t) x Jumlah Pondasi Footplat
V = (1.5 x 1.5 x 2.4) x 24 titik
V = (1.5 x 1.5 x 2.4) x 24 titik
Luas Penampang =
129.6
2 Pekerjaan Pondasi Menerus
a Pekerjaan Galian 57.731 m3 Panjang Galian Pondasi Penuh Menerus tipe 1
P = 1500 + 500 + 280 + 427+ 200 + 200 + 1650 + 107 + 127.5 + 200 + 200 + 300 + 300 + 300
P = 6291.5 cm
Luas Penampang = =pxl
0.8 x 0.35
0.28
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.28 x 62.915
Volume = 17.6162

Panjang Galian Pondasi Penuh Menerus tipe 2


P = 300 cm
P= 3 m
Luas Penampang = =pxl TYPE 1
0.525 x 0.35
0.18375
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.183 x 3
Volume = 0.549

Panjang Galian Pondasi Penuh Menerus tipe 3


P = 300 + 427.5
P = 7.275 m
Luas Penampang = =pxl
(0.3+0.3+0.3) x (0.35)
0.315
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
1.25 x 7.275
Volume = 9.094

Panjang Galian Pondasi Penuh Menerus tipe 4


P = 300 + 300 + 300 + 300 + 1500 + 100 + 100
P = 29 m
Luas Penampang = =pxl
0.8 x 0.01
0.001
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.008 x 29
Volume = 0.232

Panjang Galian Pondasi Penuh Menerus tipe 5


TYPE 2
P = (300 x 4) + (300x2) + (300x2) + (300x4)
P = 36 m
Luas Penampang = =pxl
0.3 x 2.8
0.840
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.84 x 36
Volume = 30.240

VOLUME TOTAL = Tipe 1 + Tipe 2 + Tipe 3 + Tipe 4 + Tipe 5


VOLUME TOTAL = 17.6176 + 0.546 + 9.093 + 0.232 + 30.24
57.731 TYPE 3
b
Urugan Pasir dibawah Pondasi Menerus 9.122 m3 Urugan Pasir dibawah Pondasi Tipe 1
Volume = Luas penampang x panjang
Volume = (0.05 x 0.80) x 62.925
Volume =
2.517
Urugan Pasir dibawah Pondasi Tipe 2
Volume = Luas penampang x panjang
Volume = (0.05 x 0.52) x 3
Volume =
0.078
Urugan Pasir dibawah Pondasi Tipe 3
Volume = Luas penampang x panjang
Volume = (0.05 x 0.90) x 7.275
Volume =
0.327
Urugan Pasir dibawah Pondasi Tipe 4
Volume = Luas penampang x panjang
Volume = (0.05 x 0.80) x 29
Volume =
1.160
Urugan Pasir dibawah Pondasi Tipe 5
Volume = Luas penampang x panjang
Volume = (0.05 x 2.80) x 36
Volume =
5.040 TYPE 4
VOLUME TOTAL = Tipe 1 + Tipe 2 + Tipe 3 + Tipe 4 + Tipe 5
VOLUME TOTAL =
9.122

c Urugan Tanah Kembali 0.117 m3 Urugan Tanah PondasiMenerus tipe 1


V = Luas Penampang x Panjang Pondasi x 2 sisi
V = (a+b)/2 x t x p x 2 sisi
V = (0.0287+0.01) / 2 x 0.0475 x 62.925 x 2
Volume :
0.032
Urugan Tanah Pondasi Penuh Menerus tipe 2
V = Luas Penampang x Panjang Pondasi
V = (a+b)/2 x t x p x 2 sisi TYPE 5
V = (0.0287+0.01) / 2 x 0.0475 x 3
Volume :
0.029
Urugan Tanah
Kembali Tipe 1 & 2
VOLUME TOTAL = Volume Tipe 1 + Volume Tipe 2
volume :
0.061

d Urugan Tanah Peninggi Lantai 168.300 m3 Urugan Tanah Peninggi Lantai Luas 1
V=pxlxt
V = ((1 x 3)+(20x3)) x 0.85
Volume :
54
Urugan Tanah Peninggi Lantai Luas 2
V=pxlxt
V = (2 x 3) x 0.80
Volume :
4.8
Urugan Tanah Peninggi Lantai Luas 3
V=pxlxt
V = ((15 x 3)+(15x3)+(1x5)) x 1.3
Volume :
96.500
Urugan Tanah Peninggi Lantai Luas 4
V=pxlxt
V = (3x2.35)-(1x5)+(2x3)+(5x2) x 0.45
Volume :
13.000
VOLUME TOTAL :
168.300
e Urugan Pasir dibawah Lantai 14.386 m3 V = Luas Total Tanah Peninggi Lantai x tinggi
V = 287.722 x 0.05
Volume :
14.386
HRG SATUAN
NO JENIS PEKERJAAN VOLUME SAT
( Rp )
1 2 3 4 5

I PEKERJAAN TANAH DAN PONDASI


1 Galian tanah pondasi menerus 57.731 m3 63,250.00
2 Galian tanah pondasi setempat 129.600 m3 92,710.00
3 Urugan pasir dibawah pondasi menerus 9.122 m3 439,300.00
4 Urugan tanah kembali pondasi menerus 0.117 m3 46,500.00
5 Pek. Urugan Tanah Peninggian Lantai 168.300 m3 407,250.00
6 Pek. Urugan pasir di bawah lantai 14.386 m3 439,300.00
TOTAL
JML HARGA
( Rp )
6

3,651,482.59
12,015,216.00
4,007,459.34
5,440.50
68,540,175.00
6,319,813.73
94,539,587.16