Januari 2020 Februari 2020 Maret 2020

etc etc M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15


NO Jenis Pekerjaan Harga Total (Rp) Bobot (%) Duration START FINISH 01 - 04 05 - 11 12 - 18 19 - 25 26 - 31 01 02 - 08 09 - 15 16 - 22 23 - 29 01 - 07 08 - 14 15 - 21 22 - 28 29 - 31
1 Pekerjaan pendahuluan 14,014,814 6.40% 10 1-Jan 12-Jan 16.00% 2.13% 2.13% 2.13%
2 Pekerjaan tanah dan pondasi 35,911,192 16.40% 28 6-Jan 2-Feb 2.7% 2.73% 2.73% 2.73% 2.73% 2.73%
14.00%
3 Pekerjaan beton / beton bertulang 50,300,784 22.98% 28 25-Jan 21-Feb 3.83% 3.83% 3.83% 3.83% 3.83% 3.83%
4 Pekerjaan pasangan bata 3,746,279 1.71% 20 9-Feb 29-Feb 12.00% 0.57% 0.57% 0.57%
5 Pekerjaan atap 6,740,046 3.08% 14 2-Mar 15-Mar 0.77% 0.77% 0.77% 0.77%
10.00%
6 Pekerjaan plafond 3,209,313 1.47% 14 14-Mar 27-Mar 0.49% 0.49% 0.49%
7 Pekerjaan kusen, pintu dan jendela 1,890,064 0.86% 28 29-Feb 27-Mar 8.00% 0.17% 0.17% 0.17% 0.17% 0.17%
8 Pekerjaan instalasi listrik 4,722,894 2.16% 28 2-Feb 29-Feb 6.00% 0.54% 0.54% 0.54% 0.54%
9 Pekerjaan instalasi air 62,753,795 28.66% 30 9-Feb 9-Mar 5.73% 5.73% 5.73% 5.73% 5.73%
4.00%
10 Pekerjaan lantai 29,127,171 13.30% 21 16-Feb 7-Mar 4.43% 4.43% 4.43%
11 Pekerjaan pengecatan 6,445,000 2.94% 14 8-Mar 21-Mar 2.00% 1.47% 1.47%
12 Pembersihan lahan bangunan jadi 62,944.00 0.03% 3 29-Mar 31-Mar 0.00% 0.03%
HARGA TOTAL KESELURUHAN PENGERJAAN 218,924,296 100% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Jumlah bobot rencana 2.13% 4.87% 4.87% 6.56% 6.56% 6.56% 7.10% 10.67% 15.11% 12.22% 11.11% 8.64% 2.90% 0.66% 0.03%
Kumulatif bobot rencana 2.13% 7.00% 11.87% 18.43% 25.00% 31.56% 38.66% 49.33% 64.44% 76.66% 87.77% 96.41% 99.31% 99.97% 100.00%
Jumlah bobot realisasi
Kumulatif bobot realisasi
Selisih

TUGAS CPMK 03
ABDUL ROJAK
41118110146
Januari 2020
etc etc W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W
NO Jenis Pekerjaan Harga Total (Rp) Bobot (%) Duration START FINISH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

1 Pekerjaan pendahuluan 14,014,814 6.40 7 1-Jan 7-Jan


2 Pekerjaan tanah dan pondasi 35,911,192 16.40 28 6-Jan 2-Feb
3 Pekerjaan beton / beton bertulang 50,300,784 22.98 21 1-Feb 21-Feb
4 Pekerjaan pasangan bata 3,746,279 1.71 21 18-Feb 3-Mar
5 Pekerjaan atap 6,740,046 3.08 14 2-Mar 15-Mar
6 Pekerjaan plafond 3,209,313 1.47 14 14-Mar 27-Mar
7 Pekerjaan kusen, pintu dan jendela 1,890,064 0.86 28 29-Feb 27-Mar
8 Pekerjaan instalasi listrik 4,722,894 2.16 28 26-Feb 24-Mar
9 Pekerjaan instalasi air 62,753,795 28.66 21 7-Mar 27-Mar
10 Pekerjaan lantai 29,127,171 13.30 21 4-Mar 24-Mar
11 Pekerjaan pengecatan 6,445,000 2.94 14 17-Mar 30-Mar
12 Pembersihan lahan bangunan jadi 62,944.00 0.03 7 25-Mar 31-Mar
HARGA TOTAL KESELURUHAN PENGERJAAN 218,924,296 100.00
Februari 2020 Maret 2020
TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T W TH F ST SD M T
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31