BAR CHART

REVITALISASI PUSDIKLAT BATAN


ID Task Mode Task Name Duration Start Finish Predecessors
11 August 21 August 01 September 11 September 21 September 01 October 11 October 21 October 01 November 11 November 21 November 01 December 11 December 21 December 01 January
1 PEKERJAAN PERSIAPAN 135 days Mon 19/08/19 Tue 31/12/19
2 PEKERJAAN BONGKARAN
3 LANTAI 1 3 days Fri 04/10/19 Sun 06/10/19 20
4 LANTAI 2 3 days Sun 20/10/19 Tue 22/10/19 24
5 LANTAI 3 4 days Thu 31/10/19 Sun 03/11/19 30
6 LANTAI 4 4 days Fri 08/11/19 Mon 11/11/19 34
7 LANTAI ATAP 10 days Tue 29/10/19 Thu 07/11/19 5FS-6 days
8 PEKERJAAN STRUKTUR
9 PEKERJAAN TANAH DAN PONDASI
10 Pek. Pengukuran dan Pasang Bouwplank 3 days Mon 19/08/19 Wed 21/08/19 1SS
11 galian top soil 6 days Thu 22/08/19 Tue 27/08/19 10
12 Pek. Galian Tanah Pondasi Poor dan Tie Beam Sedalam 1 m 6 days Sat 14/09/19 Thu 19/09/19 16
13 Tiang Pancang Square uk. 25 x 25 L = 20 m' 7 days Wed 28/08/19 Tue 03/09/19 11
14 pemancangan dan penyambungan tiang pancang 17 days Wed 28/08/19 Fri 13/09/19 15SS
15 Mobilisasi dan Demobilisasi Alat Pancang 3 days Wed 28/08/19 Fri 30/08/19 13SS
16 Loading Test PDA 3 days Wed 11/09/19 Fri 13/09/19 14FS-3 days
17 Lateral Test 2 days Wed 11/09/19 Thu 12/09/19 16SS
18 Pek. Pile Cap (termasuk lantai kerja dan urugan pasir) 20 days Sat 14/09/19 Thu 03/10/19 16
19 Pek. Tie Beam 20 days Sat 14/09/19 Thu 03/10/19 18SS
20 Pek. Suspended Slab t = 15 cm 20 days Sat 14/09/19 Thu 03/10/19 19SS
21 PEKERJAAN STRUKTUR LANTAI 1
22 Pek. Kolom lantai 1 8 days Fri 04/10/19 Fri 11/10/19 18
23 Pek. Balok Struktur lantai 1 8 days Fri 04/10/19 Fri 11/10/19 22SS
24 Pek. Plat Lantai Beton, t = 12 cm lantai 1 8 days Fri 04/10/19 Fri 11/10/19 22SS
25 PEKERJAAN STRUKTUR LANTAI 2
26 Pek. Kolom lantai 2 8 days Sat 12/10/19 Sat 19/10/19 24
27 Pek. Balok Struktur lantai 2 8 days Sat 12/10/19 Sat 19/10/19 26SS
28 Pek. Plat Lantai Beton, t = 12 cm lantai 2 8 days Sat 12/10/19 Sat 19/10/19 26SS
29 PEKERJAAN STRUKTUR LANTAI 3
30 Pek. Kolom lantai 3 11 days Sun 20/10/19 Wed 30/10/19 28
31 Pek. Balok Struktur lantai 3 11 days Sun 20/10/19 Wed 30/10/19 30SS
32 Pek. Plat Lantai Beton, t = 12 cm lantai 3 11 days Sun 20/10/19 Wed 30/10/19 30SS
33 PEKERJAAN STRUKTUR LANTAI 4
34 Pek. Kolom lantai 4 8 days Thu 31/10/19 Thu 07/11/19 31
35 Pek. Balok Struktur lantai 4 8 days Thu 31/10/19 Thu 07/11/19 31
36 Pek. Plat Lantai Beton, t = 12 cm lantai 4 8 days Thu 31/10/19 Thu 07/11/19 31
37 PEKERJAAN ERECTION STRUKTUR ATAP
38 Pek. Pedestal Kolom ( baut, baseplat dan grouting) 14 days Thu 31/10/19 Wed 13/11/19 35SS
39 Pek. Kolom (C1) Baja WF 250x125x6x9 (termasuk Plat dan Baut 16 days Fri 08/11/19 Sat 23/11/19 35
40 Pek. Balok (B1) Baja I WF200x100x5,5x8 (termasuk Plat dan 16 days Fri 08/11/19 Sat 23/11/19 39SS
41 Pek. Rafter (R1) Baja I WF250x125x6x9 (termasuk Plat dan Baut 16 days Fri 08/11/19 Sat 23/11/19 40SS
42 Pek. Gording CNP 150x50x20x2,3 (termasuk Plat dan Baut) 16 days Fri 08/11/19 Sat 23/11/19 40SS
43 Pek. Besi Ikatan Angin Kuda - kuda Ø 16 mm (termasuk Plat 16 days Fri 08/11/19 Sat 23/11/19 40SS
44 Pek. Pengecatan Permukaan Baja Dengan Cat Meni 16 days Fri 08/11/19 Sat 23/11/19 40SS
45 Pek. Pasangan Rangka Atap Baja Ringan (material CNP 0,75 16 days Fri 08/11/19 Sat 23/11/19 40SS
46 Pek. Pasangan Penutup Atap Spandek 16 days Fri 08/11/19 Sat 23/11/19 40SS
47 Pek. Pasangan Nok Alumunium 16 days Fri 08/11/19 Sat 23/11/19 40SS
48 Pek. Pasangan Listplank GRC tebal 15 mm lebar 30 cm 16 days Fri 08/11/19 Sat 23/11/19 40SS
49 Pek. Pasangan Penutup Atap Baru Spandek ( Area Bangunan 16 days Fri 08/11/19 Sat 23/11/19 40SS
50 ARSITEKTUR LANTAI 1
51 PEK. PENUTUP LANTAI DAN CAT MARKA TEMPAT PARKIR 7 days Tue 17/12/19 Mon 23/12/19 101FS+3
52 PEK. PLAFOND 8 days Sun 20/10/19 Sun 27/10/19 26
53 PEK. PENGECATAN 14 days Sun 20/10/19 Sat 02/11/19 26
54 ARSITEKTUR LANTAI 2
55 PEK. PASANGAN DINDING BATA DAN PARTISI 21 days Sun 27/10/19 Sat 16/11/19 52FS-1 day
56 PEK. KUSEN PINTU DAN JENDELA 21 days Sun 27/10/19 Sat 16/11/19 55SS
57 PEK. PENUTUP LANTAI DAN DINDING 21 days Sun 27/10/19 Sat 16/11/19 55SS
58 PEK. PLAFOND 21 days Sun 03/11/19 Sat 23/11/19 85FS-7 days
59 PEK. PENGECATAN 20 days Sun 03/11/19 Fri 22/11/19 55SS+7 days
60 PEK. SANITARY 7 days Sun 10/11/19 Sat 16/11/19 56FS-7 days
61 ARSITEKTUR LANTAI 3
62 PEK. PASANGAN DINDING BATA DAN PARTISI 21 days Sun 10/11/19 Sat 30/11/19 55FS-7 days
63 PEK. KUSEN PINTU DAN JENDELA 21 days Sun 10/11/19 Sat 30/11/19 55FS-7 days
64 PEK. PENUTUP LANTAI DAN DINDING 21 days Sun 27/10/19 Sat 16/11/19 55SS
65 PEK. PLAFOND 21 days Mon 11/11/19 Sun 01/12/19 86FS-7 days
66 PEK. PENGECATAN 20 days Sun 17/11/19 Fri 06/12/19 62SS+7 days
67 PEK. SANITARY 7 days Sun 10/11/19 Sat 16/11/19 64FS-7 days
68 ARSITEKTUR LANTAI 4
69 PEK. PASANGAN DINDING BATA DAN PARTISI 8 days Sun 24/11/19 Sun 01/12/19 48
70 PEK. KUSEN PINTU DAN JENDELA 8 days Sun 24/11/19 Sun 01/12/19 69SS
71 PEK. PENUTUP LANTAI DAN DINDING 8 days Sun 24/11/19 Sun 01/12/19 69SS
72 PEK. PLAFOND 8 days Sun 24/11/19 Sun 01/12/19 69SS
73 PEK. PENGECATAN 8 days Sun 01/12/19 Sun 08/12/19 69SS+7 days
74 PEK. SANITARY 7 days Tue 29/10/19 Mon 04/11/19 7FS-10 days
75 PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR
76 LANTAI 2 (DUA) 10 days Thu 31/10/19 Sat 09/11/19 32
77 LANTAI 3 (TIGA) 10 days Fri 08/11/19 Sun 17/11/19 36
78 LANTAI 4 (EMPAT) 10 days Sun 24/11/19 Tue 03/12/19 48
79 SHAFT 10 days Sun 20/10/19 Tue 29/10/19 32SS
80 TESTING COMMISIONING 1 day Wed 04/12/19 Wed 04/12/19 78
81 PEKERJAAN PANEL LISTRIK 7 days Wed 04/12/19 Tue 10/12/19 87
82 PEKERJAAN INSTALASI KABEL DAYA 2 days Wed 11/12/19 Thu 12/12/19 81
83 PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK
84 LANTAI 1 (SATU) 10 days Sun 20/10/19 Tue 29/10/19 28
85 LANTAI 2 (DUA) 10 days Thu 31/10/19 Sat 09/11/19 32
86 LANTAI 3 ( TIGA ) 10 days Fri 08/11/19 Sun 17/11/19 36
87 LANTAI 4 ( EMPAT ) 10 days Sun 24/11/19 Tue 03/12/19 48
88 PEKERJAAN TRAY KABEL
89 LANTAI 2 (DUA) 10 days Thu 31/10/19 Sat 09/11/19 32
90 LANTAI 3 (TIGA) 10 days Fri 08/11/19 Sun 17/11/19 36
91 LANTAI 4 (EMPAT) 10 days Sun 24/11/19 Tue 03/12/19 48

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: PUSDIKLAT BATAN
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress Slack

Page 1
BAR CHART
REVITALISASI PUSDIKLAT BATAN
ID Task Mode Task Name Duration Start Finish Predecessors
11 August 21 August 01 September 11 September 21 September 01 October 11 October 21 October 01 November 11 November 21 November 01 December 11 December 21 December 01 January
92 PEKERJAAN INSTALASI TATA UDARA/AC
93 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
94 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
95 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
96 PEKERJAAN INSTALASI TATA UDARA/AC EKSISTING 7 days Sat 14/12/19 Fri 20/12/19 95
97 PEKERJAAN FIRE ALARM
98 LANTAI 1 (SATU) 10 days Wed 30/10/19 Fri 08/11/19 84
99 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
100 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
101 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
102 PEKERJAAN TELEPON / PABX
103 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
104 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
105 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
106 PEKERJAAN DATA LAN
107 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
108 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
109 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
110 PEKERJAAN SOUND SISTEM
111 LANTAI 1 (SATU) 10 days Sun 10/11/19 Tue 19/11/19 85
112 LANTAI 2 (DUA) 10 days Mon 18/11/19 Wed 27/11/19 86
113 LANTAI 3 (TIGA) 10 days Wed 04/12/19 Fri 13/12/19 87
114 LANTAI 4 (EMPAT) 10 days Sat 14/12/19 Mon 23/12/19 95
115 PEKERJAAN PEMASANGAN KABEL PLN 6 days Sat 14/12/19 Thu 19/12/19 101
116 PEKERJAAN PENANGKAL PETIR 7 days Sat 14/12/19 Fri 20/12/19 101
117 TEST COMMISIONING DAN DEFECTLIST 7 days Tue 24/12/19 Mon 30/12/19 114

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: PUSDIKLAT BATAN
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress Slack

Page 2