Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: PUSDIKLAT BATAN
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress Slack
Page 1
BAR CHART
REVITALISASI PUSDIKLAT BATAN
ID Task Mode Task Name Duration Start Finish Predecessors
11 August 21 August 01 September 11 September 21 September 01 October 11 October 21 October 01 November 11 November 21 November 01 December 11 December 21 December 01 January
92 PEKERJAAN INSTALASI TATA UDARA/AC
93 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
94 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
95 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
96 PEKERJAAN INSTALASI TATA UDARA/AC EKSISTING 7 days Sat 14/12/19 Fri 20/12/19 95
97 PEKERJAAN FIRE ALARM
98 LANTAI 1 (SATU) 10 days Wed 30/10/19 Fri 08/11/19 84
99 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
100 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
101 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
102 PEKERJAAN TELEPON / PABX
103 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
104 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
105 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
106 PEKERJAAN DATA LAN
107 LANTAI 2 (DUA) 10 days Sun 10/11/19 Tue 19/11/19 85
108 LANTAI 3 (TIGA) 10 days Mon 18/11/19 Wed 27/11/19 86
109 LANTAI 4 (EMPAT) 10 days Wed 04/12/19 Fri 13/12/19 87
110 PEKERJAAN SOUND SISTEM
111 LANTAI 1 (SATU) 10 days Sun 10/11/19 Tue 19/11/19 85
112 LANTAI 2 (DUA) 10 days Mon 18/11/19 Wed 27/11/19 86
113 LANTAI 3 (TIGA) 10 days Wed 04/12/19 Fri 13/12/19 87
114 LANTAI 4 (EMPAT) 10 days Sat 14/12/19 Mon 23/12/19 95
115 PEKERJAAN PEMASANGAN KABEL PLN 6 days Sat 14/12/19 Thu 19/12/19 101
116 PEKERJAAN PENANGKAL PETIR 7 days Sat 14/12/19 Fri 20/12/19 101
117 TEST COMMISIONING DAN DEFECTLIST 7 days Tue 24/12/19 Mon 30/12/19 114
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: PUSDIKLAT BATAN
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress Slack
Page 2