PERHITUNGAN LAMA KEGIATAN PERKIRAAN PERHITUNGAN UMUR R

LPER = (LO + 4 LM + LP)/6


Kegiatan LO (Optimis) LM (most likely) LP (Pesimis) LPER Kegiatan LP
A 15 16 29 18 B 14
B 6 13 14 12 E 36
C 7 9 11 9 H 17
D 11 12 31 15
E 14 15 22 16
F 11 18 19 17
G 6 7 14 8
H 22 23 36 25
I 9 16 17 15
J 11 12 19 13
K 9 10 17 11
L 6 7 14 8
M 12 13 20 14
N 6 7 8 7
O 4 6 8 6
P 8 10 12 10
TUNGAN UMUR RENCANA PROYEK

LO LP - LO ds ds^2
6 8 1.333333 1.777778 ds =(LP - LO)/LO
22 14 0.636364 0.404959
9 8 0.888889 0.790123 dp = ∑(ds^2)

2.97286 dn = (UREN - UPER)/dp

0.85 = ( UREN - 52 )/ 3

UREN = 52 + 0.85 X 3

= 54.55

`
PERHITUNGAN LAMA KEGIATAN PERKIRAAN

LPER = (LO + 4 LM + LP)/6

Kegiatan LO (Optimis) LM (most likely) LP (Pesimis) LPER

A 7 9 11 9

B 6 13 14 12

C 6 7 8 7

D 6 7 14 8

E 22 23 36 25

F 11 12 19 13

G 9 10 17 11

H 9 16 17 15

I 15 16 29 18
PERHITUNGAN UMUR RENCANA PROYEK

Kegiatan LP LO LP - LO ds ds^2

A 29 15 14 2 5 ds =(LP - LO)/6

H 36 22 14 2 5

K 17 9 8 1 2 dp = ∑(ds^2)

P 12 10 2 0 0

13 dn = (UREN - UPER)/dp

3.5746017649212

0.85

UREN

Kegiatan Kritis LP LO LP - LO ds ds^2

A 29 15 14 14/6 196/36 196


H 36 22 14 14/6 196/36
K 17 9 8 8/6 64/36 `
P 12 10 2 2/6 4/36
Total 460/36 12.77778
ds =(LP - LO)/6

dp = ∑(ds^2)

dn = (UREN - UPER)/dp

= ( UREN - 64 )/ 4

= 64 + 0.85 X 4

= 67.4

74.861