BOBOT PROGRES
NO. URAIAN PEKERJAAN KESELURUHA
N % BOBOT
Pengawas Teknis
Universitas Kristen Indonesia
1 / 22
PROGRES PEKERJAAN CIVIL DAN MEKANIKAL ELEKTRIKAL
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
I PEKERJAAN PERSIAPAN
1 Tinjauan ke lapangan
-Pengukuran dan persiapan bedeng kerja 1 ls 0.0332 1 100% 0.0332
2 Mobilisasi & Demobilisasi 1 lot 0.3715 1 100% 0.3715
4 Approval Material, Shop Drawing, Asbuild Drawing rangkap 3 1 lot 0.0663 1 100% 0.0663
Form standart As Build dari Owner
5 Site Management 3 bln 0.3981 3 100% 0.3981
7 Peralatan Kerja, penggadaan Helmet, Sepatu Kerja,serta Perlengkapan 1 lot 0.1709 1 100% 0.1709
Bantu lainnya.
2 Pekerjaan Plafon
-Pasang rangka hollow galvalum sistem metal puring 2x4, 4x4 + gypsum jayaboard 904.68 m2 1.6145 904.68 100% 1.6145
1. Pekerjaan Plafon Variasi Gantung
- Bahan Gypsum Jaya Board WR 175 m2 0.3771 175 100% 0.3771
- Bahan Hollow uk 4 x 4 Galvanis
- Kawat Gantury, Skrup, Kompon, Kain Kasa
2. Pekerjaan Pengecatan Plafon
- Pengecatan Plafon Variasi Gantury 175 m2 0.0701 175 100% 0.0701
dengan Cat Waterbased setara ICI Dulux x Interior
- Pengecatan WF dan Kawat Gantury 1 ls 0.0307 1 100% 0.0307
dengan Cat Oil Based "Kansai Paint Zincromate"
- Pengecatan cat besi Plafond Bondex 310 m2 0.1728 310 100% 0.1728
3. Pekerjaan Type Balok dan Kolom type Balok PJ = 6m' 10.5 unit 0.1358 10.5 100% 0.1358
- Bahan Gypsum Jayaboard WR
- Bahan Hollow uk 4 x 4 Galvalum dan Aksesorisnya
4. Pekerjaan Type Balok dan Kolom type Balok PJ = 3,6m' 10 unit 0.0776 10 100% 0.0776
- Bahan Gypsum Jayaboard WR
- Bahan Hollow uk 4 x 4 Galvalum dan Aksesorisnya
5. Pekerjaan Type Balok dan Kolom type Balok PJ = 3,2m' 10 unit 0.0690 10 100% 0.0690
- Bahan Gypsum Jayaboard WR
- Bahan Hollow uk 4 x 4 Galvalum dan Aksesorisnya
6. Kolom Pedestal (0,4 x 0,4 x 0,6) 8.64 m2 0.0302 8.64 100% 0.0302
- Bahan Hebel tebal 7,5 cm
- Plester dan Aci
7. Pekerjaan Pengecatan Plafon
- Type Balok PJ 6m' 57 m' 0.0160 57 100% 0.0160
- Type Balok PJ 3,6m' 3.6 m' 0.0010 3.6 100% 0.0010
- Type Balok PJ 3,2m' 32 m' 0.0090 32 100% 0.0090
- Type Pedestal Tinggi 60cm 10 unit 0.0028 10 100% 0.0028
-Pasang box Lampu variasi plafon dengan bahan multi pleks dilapisa HPL, 0.00 ea
Khusus pada area ruang koridor
-Pasang list Gypsum minimalis, type T 12 393.24 m' 0.1414 393.24 100% 0.1414
-Pekerjaan Pembersihan Lokasi 583.2 m2 0.0859 583.2 100% 0.0859
3 Pekerjaan Partisi
-Pasang Partisi Gypsum Jayaboard tbl.12mm + Rangka Metal stud 76 + runner 0.00 m2
-Pasang Plin Aluminium pd sudut Lantai 194.40 m' 0.1584 194.4 100% 0.1584
2 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
3 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
13 PEKERJAAN PENGECATAN
1 -Pengecatan Plafon dengan setara ICI Dulux Interior 909.72 m2 0.3645 909.72 100% 0.3645
SUB TOTAL XV
2 Pekerjaan Plafon
-Pasang rangka hollow galvalum sistem metal puring 2x4, 4x4 + gypsum jayaboard 1336.00 m2 2.3843 1336 100% 2.3843
-Pasang list gypsum minimalis, type T 12 892.20 m' 0.3208 892.2 100% 0.3208
3 Pekerjaan Partisi
-Pasang Plin Aluminium pd sudut Lantai 525.80 m' 0.4284 525.8 100% 0.4284
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
4 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
12 PEKERJAAN PENGECATAN
1 -Pengecatan Plafon dengan setara ICI Dulux Interior 1648.28 m2 0.6605 1648.28 100% 0.6605
5 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
3 Pekerjaan Partisi
-Pasang Partisi Gypsum Jayaboard tbl.12mm + Rangka Metal stud 76 + runner 754.715 m2 2.0839 754.715 100% 2.0839
-Pasang Partisi Gypsum Jayaboard tbl 12mm +Rangka metal stud 76 pd dinding sudut Lob 75.040 m2 0.2072 75.04 100% 0.2072
-Pasang Plin Aluminium pd sudut Lantai 1045.80 m' 0.8520 1045.8 100% 0.8520
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
3 Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
6 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
3 Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0007 1 100% 0.0007
dengan cat Dulux
c Pekerjaan Pengecatan
- Pengecatan bekas bongkaran Opening Pintu 1 ls 0.0252 1 100% 0.0252
dengan cat Dulux
12 PEKERJAAN PENGECATAN
1 -Pengecatan Plafon dengan setara ICI Dulux Interior 2292.25 m2 0.9185 2292.25 100% 0.9185
14 PEKERJAAN KEBERSIHAN
1. Pembersihan pada lokasi kerja 1 ls 0.1990 1 100% 0.1990
V.1 LANTAI -1
V.1.1 LAMPU & FITTING
1 Lampu TL LED 2 x 14,5 Watt, V-Shape Type 8 bh 0.0504 8 100% 0.0504
2 Lampu TL LED 2 x 14,5 Watt, V-Shape Type c/w Battery Nicad 4 bh 0.0665 4 100% 0.0665
3 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted c/w Aluminium Louver 317 bh 4.3711 317 100% 4.3711
4 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted Aluminium Louver c/w Battery Nicad 15 bh 0.3225 15 100% 0.3225
5 Lampu TL LED 3 x 8 Watt Recessed Mounted c/w Aluminium Louver 33 bh 0.5051 33 100% 0.5051
6 Lampu TL LED 1 x 14,5 Watt Wall Mounted c/w Cover Acrilic + Battery Nicad 5 bh 0.0869 5 100% 0.0869
7 Lampu Down Light LED 12 Watt 49 bh 0.1858 49 100% 0.1858
8 Lampu Down Light LED 12 Watt 4" + E27 72 bh 0.2914 72 100% 0.2914
9 Lampu EXIT LED 3 W c/w Batery & Charger 10 bh 0.1232 10 100% 0.1232
8 Lampu Wall LED 3 W 20 bh 0.1107 20 100% 0.1107
V.1.2 KONTAK-KONTAK
1 Stop kontak 1 phase Dinding, type 1 Gang 13A 317 bh 0.2086 190.2 60% 0.1252
2 Stop kontak 1 phase Plafon, type 1 Gang 16A For proyektor 6 bh 0.0039 6 100% 0.0039
3 Stop kontak 1 phase Dinding, type 1 Gang 16A 500VA 5 bh 0.0033 5 100% 0.0033
4 Saklar engkel, type 1 Gang 10AX SP Switch 76 bh 0.0500 76 100% 0.0500
5 Saklar seri, type 2 Gang 10AX SP Switch 41 bh 0.0305 41 100% 0.0305
6 Stop kontak AC 1 phase 86 bh 0.2567 86 100% 0.2567
6 Gridswitch, type 8 Gang 1 bh 0.0245 1 100% 0.0245
4 Saklar engkel, type 1 Gang untuk Proyektor 2 bh 0.0013 2 100% 0.0013
7 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
V.2 LANTAI -2
V.2.1 LAMPU & FITTING
1 Lampu TL LED 2 x 14,5 Watt, V-Shape Type 7 bh 0.0441 7 100% 0.0441
2 Lampu TL LED 2 x 14,5 Watt, V-Shape Type c/w Battery Nicad 4 bh 0.0665 4 100% 0.0665
3 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted c/w Aluminium Louver 304 bh 4.1918 304 100% 4.1918
4 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted Aluminium Louver c/w Battery Nicad 62 bh 1.3330 62 100% 1.3330
5 Lampu TL LED 1 x 14,5 Watt Wall Mounted c/w Cover Acrilic + Battery Nicad 5 bh 0.0869 5 100% 0.0869
6 Lampu Down Light LED 12 Watt 110 bh 0.4171 110 100% 0.4171
7 Lampu Wall LED 3 W 24 bh 0.1328 24 100% 0.1328
8 Lampu EXIT LED 3 W c/w Batery & Charger 10 bh 0.1232 10 100% 0.1232
V.2.2 KONTAK-KONTAK
1 Stop kontak 1 phase Dinding, type 1 Gang 13A 439 bh 0.2889 373.15 85% 0.2456
2 Stop kontak 1 phase Plafon, type 1 Gang 16A For proyektor 32 bh 0.0211 32 100% 0.0211
3 Stop kontak 1 phase Plafon, type 1 Gang 16A For Acess Point 5 bh 0.0033 5 100% 0.0033
4 Saklar engkel, type 1 Gang 10AX SP Switch 98 bh 0.0645 98 100% 0.0645
5 Saklar seri, type 2 Gang 10AX SP Switch 79 bh 0.0587 79 100% 0.0587
6 Stop kontak AC 1 phase 124 bh 0.3702 124 100% 0.3702
4 Saklar engkel For Proyektor, type 1 Gang 10AX SP Switch 32 bh 0.0211 32 100% 0.0211
V.3 LANTAI -3
V.3.1 LAMPU & FITTING
1 Lampu TL LED 2 x 14,5 Watt, V-Shape Type 6 bh 0.0378 6 100% 0.0378
2 Lampu TL LED 2 x 14,5 Watt, V-Shape Type c/w Battery Nicad 4 bh 0.0665 4 100% 0.0665
3 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted c/w Aluminium Louver 304 bh 4.1918 304 100% 4.1918
4 Lampu TL LED 2 x 14,5 Watt, Recessed Mounted Aluminium Louver c/w Battery Nicad 63 bh 1.3545 63 100% 1.3545
5 Lampu TL LED 3 x 8 Watt Recessed Mounted c/w Aluminium Louver 30 bh 0.4592 30 100% 0.4592
6 Lampu TL LED 1 x 14,5 Watt Wall Mounted c/w Cover Acrilic + Battery Nicad 5 bh 0.0869 5 100% 0.0869
7 Lampu Down Light LED 12 Watt 59 bh 0.2237 59 100% 0.2237
8 Lampu Down Light LED 12 Watt c/w Battery 3 bh 0.0121 3 100% 0.0121
9 Lampu Down Light LED 5 Watt MR 16 1 bh 0.0030 1 100% 0.0030
10 Lampu Wall LED 3 W 18 bh 0.0996 18 100% 0.0996
11 Lampu EXIT LED 3 W c/w Batery & Charger 11 bh 0.1355 11 100% 0.1355
V.3.2 KONTAK-KONTAK
1 Stop kontak 1 phase Dinding, type 1 Gang 13A 248 bh 0.1632 243.04 98% 0.1600
2 Stop kontak 1 phase Plafon, type 1 Gang 16A For proyektor 49 bh 0.0322 49 100% 0.0322
3 Stop kontak 1 phase Plafon, type 1 Gang 16A For Acess Point 7 bh 0.0046 7 100% 0.0046
4 Stop kontak 1 phase Dinding, type 1 Gang 16A For Lampu sorot (1500VA) 2 bh 0.0013 2 100% 0.0013
Conector 3P type 1 MCB 3P, 16A For AC Standing 4 bh 0.0515 4 100% 0.0515
5 Saklar engkel, type 1 Gang 10AX SP Switch 76 bh 0.0500 76 100% 0.0500
6 Saklar seri, type 2 Gang 10AX SP Switch 67 bh 0.0498 67 100% 0.0498
7 Gridswitch, type 8 Gang 2 bh 0.0491 2 100% 0.0491
Stop kontak AC 1 phase 148 bh 0.4418 148 100% 0.4418
9 Saklar engkel For Proyektor, type 1 Gang 10AX SP Switch 49 bh 0.0322 49 100% 0.0322
8 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
VI PEKERJAAN PANEL
Pengadaan dan pemasangan panel-panel
tegangan rendah lengkap dengan sistem pentanahan,
accessories atau perlengkapan lainnya sesuai dengan
spesifikasi teknis dan gambar rencana
SITEPLAN + LANTAI 1
LANTAI 2
2 P-AC.2A.1 1 unit 0.2180 1 100% 0.2180
3 P-LP.2A.1 1 unit 0.1525 1 100% 0.1525
4 MDB-2A 1 unit 0.1563 1 100% 0.1563
5 P-LP.2A.K 1 unit 0.1350 1 100% 0.1350
7 P-AC.2A.2 1 unit 0.2559 1 100% 0.2559
8 P-LP.2A.2 1 unit 0.1618 1 100% 0.1618
10 P-AC.2B.1 1 unit 0.3213 1 100% 0.3213
11 P-LP.2B.1 1 unit 0.1388 1 100% 0.1388
12 P-LP.2B.K 1 unit 0.1523 1 100% 0.1523
13 P-LAB.2B 1 unit 0.0888 1 100% 0.0888
15 P-AC.2B.2 1 unit 0.2356 1 100% 0.2356
16 P-LP.2B.2 1 unit 0.1618 1 100% 0.1618
17 MDB-2B 1 unit 0.2919 1 100% 0.2919
LANTAI 3
1 P-AULA.3A 1 unit 0.1533 1 100% 0.1533
MCCB 3P 50A 10KA , EZC100F3050 , SCHNEIDER ( SOUNDSYSTEM ) 1 unit 0.0464 0 0% 0.0000
2 P-LP.3A.1 1 unit 0.1525 1 100% 0.1525
3 P-AC.3A.1 1 unit 0.2180 1 100% 0.2180
4 MDB-3A 1 unit 0.2705 1 100% 0.2705
5 P-LP.3A.K 1 unit 0.1518 1 100% 0.1518
6 P-SEMINAR.3A 1 unit 0.1518 1 100% 0.1518
7 P-STUDIO 1 unit 0.1518 1 100% 0.1518
9 P-AC.3B.1 1 unit 0.2547 1 100% 0.2547
10 P-LP.3B.1 1 unit 0.1732 1 100% 0.1732
11 P-LP.3B.K 1 unit 0.1618 1 100% 0.1618
12 P-AC.3B.2 1 unit 0.2341 1 100% 0.2341
13 P-LP.3B.2 1 unit 0.1595 1 100% 0.1595
14 MDB-3B 1 unit 0.2888 1 100% 0.2888
9 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
LANTAI 2
1 Kabel dari MDB-1A ke MDB-2A
NYY 4 x 185 mm2 + NYA 95 mm2 20.9 m' 0.4331 19.855 95% 0.4115
2 Kabel dari MDB-2A ke P-LP.2A.1
NYY 4 x 35 mm2 + NYA 16 mm2 13.3 m' 0.0554 13.3 100% 0.0554
3 Kabel dari MDB-2A ke P-AC.2A.1
NYY 4 x 50 mm2 + NYA 25 mm2 13.3 m' 0.0763 13.3 100% 0.0763
4 Kabel dari MDB-2A ke P-LP.2A.2
NYY 4 x 50 mm2 + NYA 25 mm2 132 m' 0.7583 132.2 100% 0.7583
5 Kabel dari MDB-2A ke P-AC.2A.2
NYY 4 x 50 mm2 + NYA 25 mm2 134 m' 0.7698 134.2 100% 0.7698
6 Kabel dari MDB-LP.K-A ke P-LP.2A.K
NYY 4 x 4 mm2 + NYA 4 mm2 18.3 m' 0.0111 18.3 100% 0.0111
8 Kabel dari MDB-1B ke MDB-2B
NYY 4 x 1c x 240 mm2 + NYA 95 mm2 21.9 m' 0.5886 20.805 95% 0.5592
9 Kabel dari MDB-2B ke P-LP.2B.1
NYY 4 x 35 mm2 + NYA 16 mm2 132 m' 0.5478 131.6 100% 0.5478
10 Kabel dari MDB-2B ke P-AC.2B.1
NYY 4 x 120 mm2 + NYA 70 mm2 134 m' 1.8126 133.6 100% 1.8126
11 Kabel dari MDB-2B ke P-LP.2B.2
NYY 4 x 35 mm2 + NYA 16 mm2 13.3 m' 0.0554 13.3 100% 0.0554
12 Kabel dari MDB-2B ke P-AC.2B.2
NYY 4 x 120 mm2 + NYA 70 mm2 13.3 m' 0.1804 13.3 100% 0.1804
13 Kabel dari MDB-2B ke P-LAB.2B
NYY 4 x 10 mm2 + NYA 10 mm2 133 m' 0.1845 133.2 100% 0.1845
14 Kabel dari MDB-LP.K-B ke P-LP.2B.K
NYY 4 x 4 mm2 + NYA 4 mm2 126 m' 0.0766 126 100% 0.0766
LANTAI 3
1 Kabel dari MDB-1A ke MDB-3A
NYY 4 x 50 mm2 + NYA 25 mm2 26.4 m' 0.1514 25.08 95% 0.1439
2 Kabel dari MDB-3A ke P-LP.3A.1
NYY 4 x 6 mm2 + NYA 6 mm2 10.2 m' 0.0084 10.2 100% 0.0084
3 Kabel dari MDB-LP.K-A ke P-LP.3A.K
NYY 4 x 4 mm2 + NYA 4 mm2 22.8 m' 0.0139 22.8 100% 0.0139
5 Kabel dari MDB-3A ke P-AC.3A.1
NYY 4 x 16 mm2 + NYA 16 mm2 13.3 m' 0.0302 13.3 100% 0.0302
6 Kabel dari MDB-1A ke P-AULA.3A
NYY 4 x 120 mm2 + NYA 70 mm2 29.1 m' 0.3948 27.645 95% 0.3751
7 Kabel dari MDB-1A ke P-SEMINAR.3A
NYY 4 x 35 mm2 + NYA 16 mm2 106 m' 0.4400 100.415 95% 0.4180
8 Kabel dari MDB-1B ke MDB-3B
NYY 4 x 1c x 240 mm2 + NYA 95 mm2 22.4 m' 0.6021 21.28 95% 0.5720
9 Kabel dari MDB-3B ke P-LP.3B.1
NYY 4 x 50 mm2 + NYA 25 mm2 109 m' 0.6270 109.3 100% 0.6270
10 Kabel dari MDB-3B ke P-LP.3B.2
NYY 4 x 50 mm2 + NYA 25 mm2 18 m' 0.1032 18 100% 0.1032
11 Kabel dari MDB-3B ke P-AC.3B.1
NYY 4 x 120 mm2 + NYA 70 mm2 108 m' 1.4680 108.2 100% 1.4680
12 Kabel dari MDB-3B ke P-AC.3B.2
NYY 4 x 70 mm2 + NYA 35 mm2 18 m' 0.1434 18 100% 0.1434
13 Kabel dari MDB-LP.K-B ke P-LP.3B.K
NYY 4 x 4 mm2 + NYA 4 mm2 135 m' 0.0820 135 100% 0.0820
15 Kabel dari MDB-3B ke P-STUDIO
NYY 4 x 16 mm2 + NYA 16 mm2 93 m' 0.0767 92.9 100% 0.0767
16 Kabel dari MDB-1B ke P-LIFT
FRC 4 x 10 mm + NYA 10 mm 51 m' 0.0570 50.5 100% 0.0570
10 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
LANTAI 1
1 Kabel dari P-AC.1A.1 ke IU-1.1(0,633 KW)
NYY 3 x 2,5 mm2 63 m' 0.0206 63 100% 0.0206
2 Kabel dari P-AC.1A.1 ke IU-1.2(0,39 KW)
NYY 3 x 2,5 mm2 57 m' 0.0186 57 100% 0.0186
3 Kabel dari P-AC.1A.1 ke IU-1.3(1,063 KW)
NYY 3 x 2,5 mm2 54 m' 0.0176 54 100% 0.0176
4 Kabel dari P-AC.1A.1 ke IU-1.4(0,819 KW)
NYY 3 x 2,5 mm2 51 m' 0.0166 51 100% 0.0166
5 Kabel dari P-AC.1A.1 ke IU-1.5(0,633 KW)
NYY 3 x 2,5 mm2 61 m' 0.0199 61 100% 0.0199
6 Kabel dari P-AC.1A.1 ke IU-1.6(1,650 KW)
NYY 3 x 2,5 mm2 56 m' 0.0183 56 100% 0.0183
7 Kabel dari P-AC.1A.1 ke IU-1.7(1,650 KW)
NYY 3 x 2,5 mm2 51 m' 0.0166 51 100% 0.0166
8 Kabel dari P-AC.1A.1 ke IU-1.8(1,063 KW)
NYY 3 x 2,5 mm2 61 m' 0.0199 61 100% 0.0199
9 Kabel dari P-AC.1A.1 ke IU-1.9(2,032 KW)
NYY 3 x 2,5 mm2 57 m' 0.0186 57 100% 0.0186
10 Kabel dari P-AC.1A.1 ke IU-1.10(1,063 KW)
NYY 3 x 2,5 mm2 49 m' 0.0160 49 100% 0.0160
11 Kabel dari P-AC.1A.1 ke IU-1.11(1,063 KW)
NYY 3 x 2,5 mm2 52 m' 0.0170 52 100% 0.0170
12 Kabel dari P-AC.1A.1 ke IU-1.12(1,650 KW)
NYY 3 x 2,5 mm2 48 m' 0.0157 48 100% 0.0157
13 Kabel dari P-AC.1A.1 ke IU-1.13(1,650 KW)
NYY 3 x 2,5 mm2 45 m' 0.0147 45 100% 0.0147
14 Kabel dari P-AC.1A.1 ke IU-1.14(1,650 KW)
NYY 3 x 2,5 mm2 49 m' 0.0160 49 100% 0.0160
15 Kabel dari P-AC.1B.1 ke IU-1.15(0,39 KW)
NYY 3 x 2,5 mm2 96 m' 0.0313 96 100% 0.0313
16 Kabel dari P-AC.1B.1 ke IU-1.16(0,39 KW)
NYY 3 x 2,5 mm2 93 m' 0.0304 93 100% 0.0304
17 Kabel dari P-AC.1B.1 ke IU-1.17(1,063 KW)
NYY 3 x 2,5 mm2 90 m' 0.0294 90 100% 0.0294
18 Kabel dari P-AC.1B.1 ke IU-1.18(0,39 KW)
NYY 3 x 2,5 mm2 87 m' 0.0284 87 100% 0.0284
19 Kabel dari P-AC.1B.1 ke IU-1.19(0,39 KW)
NYY 3 x 2,5 mm2 83 m' 0.0271 83 100% 0.0271
20 Kabel dari P-AC.1B.1 ke IU-1.27(1,063 KW)
NYY 3 x 2,5 mm2 45 m' 0.0147 45 100% 0.0147
21 Kabel dari P-AC.1B.1 ke IU-1.28(1,063 KW)
NYY 3 x 2,5 mm2 41 m' 0.0134 41 100% 0.0134
22 Kabel dari P-AC.1B.1 ke IU-1.29(0,39 KW)
NYY 3 x 2,5 mm2 35 m' 0.0114 35 100% 0.0114
23 Kabel dari P-AC.1A.1 ke IU-1.30(0,39 KW)
NYY 3 x 2,5 mm2 42 m' 0.0137 42 100% 0.0137
24 Kabel dari P-AC.1A.1 ke IU-1.31(0,39 KW)
NYY 3 x 2,5 mm2 47 m' 0.0153 47 100% 0.0153
25 Kabel dari P-AC.1A.1 ke IU-1.32(0,39 KW)
NYY 3 x 2,5 mm2 46 m' 0.0150 46 100% 0.0150
26 Kabel dari P-AC.1A.1 ke IU-1.33(0,819 KW)
NYY 3 x 2,5 mm2 44 m' 0.0144 44 100% 0.0144
27 Kabel dari P-AC.1A.1 ke IU-1.34(1,063 KW)
NYY 3 x 2,5 mm2 48 m' 0.0157 48 100% 0.0157
28 Kabel dari P-AC.1A.1 ke IU-1.35(1,063 KW)
NYY 3 x 2,5 mm2 51 m' 0.0166 51 100% 0.0166
29 Kabel dari P-AC.1A.1 ke IU-1.36(1,650 KW)
NYY 3 x 2,5 mm2 56 m' 0.0183 56 100% 0.0183
30 Kabel dari P-AC.1B.1 ke IU-1.20(1,063 KW)
NYY 3 x 2,5 mm2 70 m' 0.0230 70.4 100% 0.0230
31 Kabel dari P-AC.1B.1 ke IU-1.21(0,39 KW)
NYY 3 x 2,5 mm2 64 m' 0.0209 64 100% 0.0209
32 Kabel dari P-AC.1B.1 ke IU-1.22(2,032 KW)
NYY 3 x 2,5 mm2 51 m' 0.0166 51 100% 0.0166
33 Kabel dari P-AC.1B.1 ke IU-1.23(0,633 KW)
NYY 3 x 2,5 mm2 51 m' 0.0166 51 100% 0.0166
34 Kabel dari P-AC.1B.1 ke IU-1.24(0,39 KW)
NYY 3 x 2,5 mm2 43 m' 0.0140 43 100% 0.0140
35 Kabel dari P-AC.1B.1 ke IU-1.25(0,39 KW)
NYY 3 x 2,5 mm2 41 m' 0.0134 41 100% 0.0134
36 Kabel dari P-AC.1B.1 ke IU-1.26(1,063 KW)
NYY 3 x 2,5 mm2 39 m' 0.0127 39 100% 0.0127
37 Kabel dari P-AC.1A.1 ke IU-1.37(1,650 KW)
NYY 3 x 2,5 mm2 58 m' 0.0189 58 100% 0.0189
11 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
12 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
LANTAI 2
1 Kabel dari P-AC.2A.1 ke IU-2.3(1,063 KW)CASSETTE 1 PHASE
NYY 3 x 2,5 mm2 66 m' 0.0215 65.8 100% 0.0215
2 Kabel dari P-AC.2A.1 ke IU-2.4(1,063 KW)CASSETE 1 PHASE
NYY 3 x 2,5 mm2 58 m' 0.0189 58 100% 0.0189
3 Kabel dari P-AC.2A.1 ke IU-2.5(1,650 KW)
NYY 3 x 2,5 mm2 63 m' 0.0206 63 100% 0.0206
4 Kabel dari P-AC.2A.1 ke IU-2.6(1,650 KW)
NYY 3 x 2,5 mm2 60 m' 0.0196 60 100% 0.0196
5 Kabel dari P-AC.2A.1 ke IU-2.1(1,650 KW)
NYY 3 x 2,5 mm2 73 m' 0.0237 72.7 100% 0.0237
6 Kabel dari P-AC.2A.1 ke IU-2.2(1,063 KW)
NYY 3 x 2,5 mm2 64 m' 0.0209 64 100% 0.0209
7 Kabel dari P-AC.2A.1 ke IU-2.13(1,650 KW)
NYY 3 x 2,5 mm2 60 m' 0.0196 60.05 100% 0.0196
8 Kabel dari P-AC.2A.1 ke IU-2.14(1,063 KW)
NYY 3 x 2,5 mm2 41 m' 0.0134 41 100% 0.0134
9 Kabel dari P-AC.2A.1 ke IU-2.7(1,063 KW)CASSETE 1 PHASE
NYY 3 x 2,5 mm2 54 m' 0.0176 54 100% 0.0176
10 Kabel dari P-AC.2A.1 ke IU-2.8(1,063 KW)
NYY 3 x 2,5 mm2 41 m' 0.0134 41 100% 0.0134
11 Kabel dari P-AC.2A.1 ke IU-2.9(0,633 KW)
NYY 3 x 2,5 mm2 40 m' 0.0131 40 100% 0.0131
12 Kabel dari P-AC.2A.1 ke IU-2.10(0,633 KW)
NYY 3 x 2,5 mm2 38 m' 0.0124 38 100% 0.0124
13 Kabel dari P-AC.2A.1 ke IU-2.11(0,633 KW)
NYY 3 x 2,5 mm2 41 m' 0.0134 41 100% 0.0134
14 Kabel dari P-AC.2A.1 ke IU-2.12(0,633 KW)
NYY 3 x 2,5 mm2 61 m' 0.0199 61 100% 0.0199
16 Kabel dari P-AC.2A.1 ke IU-2.16(1,650 KW)
NYY 3 x 2,5 mm2 54 m' 0.0176 54 100% 0.0176
17 Kabel dari P-AC.2A.1 ke IU-2.40(0,39 KW)
NYY 3 x 2,5 mm2 45 m' 0.0147 45 100% 0.0147
18 Kabel dari P-AC.2A.1 ke IU-2.41(0,39 KW)
NYY 3 x 2,5 mm2 63 m' 0.0206 63 100% 0.0206
19 Kabel dari P-AC.2A.1 ke IU-2.42(0,39 KW)
NYY 3 x 2,5 mm2 60 m' 0.0196 60 100% 0.0196
20 Kabel dari P-AC.2A.1 ke IU-2.43(0,39 KW)
NYY 3 x 2,5 mm2 57 m' 0.0185 56.6 100% 0.0185
21 Kabel dari P-AC.2A.1 ke IU-2.17(0,819 KW)
NYY 3 x 2,5 mm2 49 m' 0.0160 49 100% 0.0160
22 Kabel dari P-AC.2A.1 ke IU-2.18(1,650 KW)CASSETE 1 PHASE
NYY 3 x 2,5 mm2 55 m' 0.0180 55 100% 0.0180
23 Kabel dari P-AC.2A.1 ke IU-2.19(0,39 KW)
NYY 3 x 2,5 mm2 54 m' 0.0176 54 100% 0.0176
24 Kabel dari P-AC.2A.1 ke IU-2.20(0,39 KW)CASEETE 1 PHASE
NYY 3 x 2,5 mm2 64 m' 0.0209 64 100% 0.0209
25 Kabel dari P-AC.2A.1 ke IU-2.21(0,39 KW) CASSETE 1 PHASE
NYY 3 x 2,5 mm2 64 m' 0.0209 64 100% 0.0209
26 Kabel dari P-AC.2A.1 ke IU-2.22(0,39 KW)
NYY 3 x 2,5 mm2 60 m' 0.0196 60 100% 0.0196
27 Kabel dari P-AC.2A.1 ke IU-2.23(0,39 KW)
NYY 3 x 2,5 mm2 66 m' 0.0215 66 100% 0.0215
28 Kabel dari P-AC.2A.1 ke IU-2.24(2,032 KW)
NYY 3 x 2,5 mm2 59 m' 0.0193 59 100% 0.0193
29 Kabel dari P-AC.2A.1 ke IU-2.25(1,063 KW)
NYY 3 x 2,5 mm2 59 m' 0.0193 59 100% 0.0193
13 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
14 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
15 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
LANTAI 3
1 Kabel dari P-AC.3A.1 ke IU-3.98(2,032 KW)
NYY 3 x 2,5 mm2 37 m' 0.0121 37 100% 0.0121
2 Kabel dari P-AC.3A.1 ke IU-3.99.1(2,032 KW)
NYY 3 x 2,5 mm2 47 m' 0.0153 47 100% 0.0153
3 Kabel dari P-AC.3A.1 ke IU-3.99.2(2,032 KW)
NYY 3 x 2,5 mm2 44 m' 0.0144 44 100% 0.0144
4 Kabel dari P-AC.3A.1 ke IU-3.100(0,819 KW)
NYY 3 x 2,5 mm2 50 m' 0.0163 50 100% 0.0163
16 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
17 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
18 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
19 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
20 / 22
BOBOT PROGRES
No. URAIAN PEKERJAAN VOL SAT KESELURUH
AN S/D MINGGU INI
Volume % BOBOT
21 / 22
BILL OF QUANTITY
PEKERJAAN TAMBAH CIVIL, MEKANIKAL & ELEKTRIKAL
JUMLAH 534,840,370.90
Discount 5% 26,742,018.54
Total 508,098,352.35
PPN 10 % 50,809,835.24
JUMLAH TOTAL 558,908,187.59
DI BULATKAN 558,900,000.00
TERBILANG :
( )
MENGETAHUI/MENYETUJUI,
Jakarta, 25 September 2019
Dibuat Oleh :
TIM TEKNIK UKI KONSULTAN PENGAWAS
PT. HANA HUBERTA
PT. BAYU BERLIAN MANDIRI