Anda di halaman 1dari 193

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI III 2018
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)

1 Dump Truck 3 ton Jam 85,000 100,000

2 Dump Truck 9 ton Jam 110,000 115,000

3 Truk Bak Terbuka Engkel Jam 125,000 130,000

4 Truk Tanki Air Jam 280,000 290,000

5 Bulldozer 100 - 150 hp Jam 675,000 700,000

6 Motor Grader Jam 625,000 640,000


7 Wheel Loader Jam 270,000 280,000

8 Excavator Jam 650,000 660,000

9 Crane 35 ton Jam 550,000 600,000

10 Flat Bed Truck jam 430,000 440,000

11 Baby Roller / Pedestrian Jam 110,000 120,000


12 P.Tire Roller 8 - 10 ton Jam 500,000 550,000

13 Baby Roller jam 40,000 42,000

14 Vibrator Roller self 7 ton Jam 500,000 510,000

15 Pile Driver / Hammer jam 150,000 160,000

16 Water Pump Jam 40,000 42,500

17 Asphalt Sprayer Jam 135,000 140,000

18 Pick Up single cabin Jam 40,000 55,000

19 A M P Jam 5,500,000 5,600,000

20 Asphalt Finisher Jam 340,000 350,000

21 Concrete Vibrator Jam 55,000 60,000

22 Compressor Jam 310,000 320,000

23 Concrete Mixer 0,125m3 Jam 75,000 80,000

24 Concrete Cutter jam 35,000 40,000

25 Stamper Jam 40,000 45,000

26 Genset 5-25kva+bbm Jam 180,000 183,000

27 Alat Pengecat Marka Jam 300,000 310,000


28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 850,000 900,000

30 Truck Trailler trip 7,250,000 7,400,000


DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI III 2018

HARGA
NO. URAIAN PEKERJA SATUAN UPAH KET.
(Rp)
1 Pekerja Hr 70,000

2 Mandor Hr 100,000

3 Tukang listrik Hr 95,000

4 Tukang kayu Hr 95,000

5 Kep. tk. kayu Hr 110,000

6 Tukang batu Hr 95,000

7 Kep. tk. batu Hr 110,000

8 Tukang besi Hr 95,000

9 Kep. tk. besi Hr 110,000

10 T u k a n g c a t Hr 95,000

11 K e p . t k . c a t Hr 110,000

12 T u k a n g g a l i Hr 75,000

13 Tukang masak aspal Hr 75,000

14 T k . l e i d e n g Hr 95,000

15 M a s i n i s Hr 150,000

16 P e m b . M a s i n i s Hr 100,000

17 P e n j a g a a p i Hr 75,000

18 P e n j a g a m a l a m Hr 75,000

19 Sopir Hr 140,000

20 Pembantu Sopir Hr 85,000

469226324.xls 193 utk


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI III 2018

HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000
Bulat Belah m3 260,000
Pecah 10/15 m3 250,000
Pecah 5/7 m3 300,000
Pecah 3/5 m3 330,000
2 KERIKIL Timbun m3 180,000
Sawur / Koral m3 160,000
Beton 0,5/1 m3 300,000
Beton 1/2 m3 300,000
Beton 2/3 m3 300,000
Biasa m3 240,000
Tras Giling m3 290,000
3 BATU BATA ex lokal bh 600

4 PASIR Urug m3 160,000


Pasang m3 310,000
Beton m3 350,000
5 TANAH Padas m3 120,000
Liat m3 120,000
6 KAPUR Pasang m3 300,000
Semen Merah m3 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 42,000
Merk I 50 kg zak 52,500
Merk II 40 kg zak 42,000
Merk II 50 kg zak 52,000
Semen Putih 40 kg zak 80,000
Semen Putih 50 kg zak 90,000
Semen warna kg 11,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000

file:///conversion/tmp/scratch/469226324.xls 3/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)

2 GENTENG BETON Genteng Beton Warna standard bh 6,000


Genteng Beton Warna Special bh 9,500
Genteng Beton Warna Khusus bh 14,000
Kerpus Beton Warna Standard bh 10,000
Kerpus Beton Warna Special bh 11,500
Kerpus Beton Warna Khusus bh 13,000
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,300
Kodok bh 2,500
Kodok Glasur bh 4,250
Nok kerpus Kodok bh 6,500
Nok kerpus Kodok Glasur bh 8,000
Plentong super besar 18 bh/m2 bh 5,100
Nok kerpus plentong super bh 9,000
4 GENTENG KACA
Vlaam tebal 2 mm bh 12,500
Vlaam tebal 3 mm bh 13,500
Kodok tebal 2 mm bh 12,500
Kodok tebal 3 mm bh 14,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 85,000
. 225 cm X 102 cm X 5 mm bh 98,000
. 250 cm X 102 cm X 5 mm bh 108,000
. 200 cm X 102 cm X 6 mm bh 120,000
. 225 cm X 102 cm X 6 mm bh 130,000
. 250 cm X 102 cm X 6 mm bh 140,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,000
. 180 cm X 105 cm X 4 mm bh 50,000
. 210 cm X 105 cm X 4 mm bh 59,500
. 240 cm X 105 cm X 4 mm bh 65,000
. 270 cm X 105 cm X 4 mm bh 75,000
. 300 cm X 105 cm X 4 mm bh 84,500
ONDULINE : 95 cm x 200cm x 0.3mm lbr 160,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 95,000
NOK Jabes nok

file:///conversion/tmp/scratch/469226324.xls 4/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
. Kerpus Genteng bh 31,000
. Stel Besar bh 45,000
. Paten Besar bh 43,000
Nokstel gelombang harflex
. Stel Besar bh 44,000
. Patent Besar bh 27,000
. Plat besar bh 51,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 115,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 15,500
. 100cm X 100 cm X 4 mm bh 16,000
. 50 cm X 200 cm X 3 mm bh 14,500
. 40 cm X 200 cm X 3 mm bh 14,000
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 75,000
uk. 122cm x 244cm x 4mm lbr 77,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000
uk.122cm x 244cm x 6mm lbr 130,000
uk.122cm x 244cm x 8mm lbr 199,500
uk.122cm x 244cm x 10mm lbr 255,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 55,000
200 X 92 cm bh 60,000
250 X 92 cm bh 68,000
180 X 105 cm bh 68,000
210 X 105 cm bh 70,000
250 X 105 cm bh 80,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 20,000
BJLS 0,20 lebar 55 cm m' 22,000
BJLS 0,28 lebar 55 cm m' 26,000
BJLS 0,30 lebar 55 cm m' 30,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 40,000
BJLS 0,20 panjang 180 cm lbr 42,000
BJLS 0,30 panjang 180 cm lbr 59,000
BJLS 0,40 panjang 180 cm lbr 69,000

file:///conversion/tmp/scratch/469226324.xls 5/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000
Balok/pesagen m3 20,000,000
2 KAMPER Papan m3 7,200,000
Balok/pesagen m3 6,100,000
3 KRUING Papan m3 6,250,000
Balok/pesagen m3 5,051,000
4 MERANTI Papan m3 4,800,000
Balok/pesagen m3 4,500,000
5 LANAN Papan m3 3,290,000
Balok/pesagen m3 2,000,000
6 BENGKIRAI Papan m3 8,750,000
Balok/pesagen m3 9,000,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000
Kecil 6 x 7 x 400 cm bt 18,000
Besar 10 x 12 x 400 cm bt 31,000
Kayu cetakan m3 2,200,000
Kayu bakar m3 150,000
Bambu bt 10,000
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 35,000
20 X 20 cm m2 34,000
PC warna 30 X 30 cm m2 40,000
20 X 20 cm m2 39,500
Teraso 30 X 30 cm m2 52,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200
PC abu-abu 15 x 20 bh 5,100
3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000
11 X 11 warna dos 45,000
Lokal 15 X 15 putih dos 45,000
15 X 15 warna dos 46,000
4 MOZAIK PORSELIN
10 X 20 cm m2 35,000
15 X 15 cm m2 45,000
20 X 20 cm m2 52,000

file:///conversion/tmp/scratch/469226324.xls 6/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
20 X 25 cm m2 52,000

5 Keramik 30 X 30 cm m2 37,000
20 X 20 cm m2 46,500
33 x 33 cm m2 52,000
25 x 25 cm m2 49,000
15 x 20 cm m2 52,000
2,250
6 Parquet Jati m2 210,000
7 Batu Paros m2 110,000
8 Batu Tempel Hitam m2 105,000
9 GRANITO 40 x 40 cm m2 220,000
30 x 30 cm m2 300,000
10 Marmer m2 475,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 29,000
Ø 20 cm - 100 cm bh 35,000
Ø 30 cm - 100 cm bh 55,000
Ø 50 cm - 100 cm bh 70,000
Ø 60 cm - 100 cm bh 80,000
Ø 70 cm - 100 cm bh 100,000
U 10 cm - 100 cm bh 22,000
U 15 cm - 100 cm bh 35,000
U 20 cm - 100 cm bh 36,000
U 30 cm - 100 cm bh 40,000
U 50 cm - 100 cm bh 65,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 7,500
20 X 20 cm bh 8,000
25 X 25 cm bh 11,000
30 X 30 cm bh 15,000
15 X 25 cm bh 8,500
15 X 30 cm bh 8,500
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 9,500
besi beton prestress kg 13,000
besi beton ulir kg 12,500

file:///conversion/tmp/scratch/469226324.xls 7/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
2 BESI PLAT Besi Strip kg 13,000

3 BESI PROFIL Besi Profil kg 13,500


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 135,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 105,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 95,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 50,000 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 45,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 20,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 27,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000
Diameter 6 - 15 kg 14,000
Kawat Bronjong kg 12,500
5 BESI SIKU L 40 X 40 X 4 btg 133,500
L 50 X 50 X 5 btg 215,500
L 60 X 60 X 6 btg 353,500

6 KAWAT - Ikat beton/bendrat kg 18,000


- Harmonika 12 X 45 mm m2 20,000
- Harmonika 12 X 24 mm m2 18,000
- Harmonika 14 X 30 mm m2 15,000
- Harmonika 14 X 35 mm m2 21,000
- Kawat Nyamuk Nylon m2 18,000
- Kawat Kasa m2 14,000
- Saringan pasir m2 18,000
- Kawat loket m2 17,000
- Kawat duri rol 110,000
- Kawat bronjong kg 25,000

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 56,000 panjang 4 m

file:///conversion/tmp/scratch/469226324.xls 8/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
Pipa PVC DN 63 ( 2" ) btg 65,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 125,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 180,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 350,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - panjang 4 m

2 Pipa Medium A Galvanis - SII


Pipa Medium Galvanis 0,50" btg 150,000 panjang 6 m
Pipa Medium Galvanis 0,75" btg 190,000 panjang 6 m
Pipa Medium Galvanis 1" btg 300,000 panjang 6 m
Pipa Medium Galvanis 1,25" btg 375,000 panjang 6 m
Pipa Medium Galvanis 1,50" btg 435,000 panjang 6 m
Pipa Medium Galvanis 2" btg 585,000 panjang 6 m
Pipa Medium Galvanis 2,50" btg 735,000 panjang 6 m
Pipa Medium Galvanis 3" btg 970,000 panjang 6 m
Pipa Medium Galvanis 4" btg 1,425,000 panjang 6 m
Pipa Medium Galvanis 5" btg 1,900,000 panjang 6 m
Pipa Medium Galvanis 6" btg - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800
30 X 60 lbr 13,200
60 X 120 lbr 42,000
List Kayu Profil m' 4,800
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000
GYPROC uk.120cmx240cmx9mm lbr 60,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 55,000
. 120 X 240 X 3 mm lbr 75,000
. 90 X 210 X 4 mm lbr 65,000
. 90 X 210 X 9 mm lbr 95,000
. 90 X 210 X 12 mm lbr 135,000
. 90 X 210 X 15 mm lbr 165,000

file:///conversion/tmp/scratch/469226324.xls 9/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
. 90 X 210 X 18 mm lbr 200,000
Tripleks
. 120 X 240 X 3 mm lbr 52,000
. 120 X 240 X 4 mm lbr 60,000
. 120 X 240 X 6 mm lbr 75,000
Multipleks
. 120 X 240 X 9 mm lbr 121,000
. 120 X 240 X 12 mm lbr 142,000
. 120 X 240 X 15 mm lbr 165,000
. 120 X 240 X 18 mm lbr 210,000
Formika ukuran pintu lbr 68,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 23,000
Dempul plamur kg 16,000
Ambril/amplas lbr 3,000
Batu Apung kg 35,000
Cat dasar kg 35,000
. Emco kg 55,000
. Yunior 66 (nippon paint) kg 55,000
- Koas bh 7,500
. Deculux kg 55,000
. Siralax ons 15,000
. Spiritus ltr 10,000
. Plitur jadi ltr 61,000

2 TEMBOK
Kalkarium kg 4,200
Kapur sirih kg 4,250
Plamur kg 16,000
Cat Tembok kg 23,000
Sintex 5 kg 115,000
Danabride 5 kg 110,000
Catylac 5 kg 125,000
Mowilex 2,50 kg 310,000

3 BESI
Menie kg 20,000

file:///conversion/tmp/scratch/469226324.xls 10/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
Cat mengkilat kg 55,000
Cat kg 40,000
Thinner A ltr 15,000
Minyak cat ltr 10,000
Thinner Super ltr 17,500
Residu (teer/aspal) drum 55,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 950,000
kapasitas 1100 liter. bh 1,625,000
Lem Aica Aibon kg 55,000

X.BAHAN KACA
1 POLOS 3 mm m2 70,000
5 mm m2 90,000
2 ES KABUR 3 mm m2 75,000
5 mm m2 88,000
3 RAY BAND 3 mm m2 75,000
5 mm m2 85,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 4,200

SPLN LMK 1 X 2 1/2 mm2 m' 4,600

. 1X4 mm2 m' 6,250

1X6 mm2 m' 9,100

NYY :. 2 X 1 1/2 mm2 m' 9,450

PRIMA 2 X 2 1/2 mm2 m' 15,200

. 2X4 mm2 m' 27,500

2X6 mm2 m' 36,000

3 X 1 1/2 mm2 m' 13,500

3 X 2 1/2 mm2 m' 20,000

3X4 mm2 m' 34,500

3X6 mm2 m' 50,000

NYM :. 2 X 1 1/2 mm2 m' 7,000

PRIMA 2 X 2 1/2 mm2 m' 10,900

. 2X4 mm2 m' 21,000

3 X 1 1/2 mm2 m' 12,500

file:///conversion/tmp/scratch/469226324.xls 11/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
3 X 2 1/2 mm2 m' 19,000

3X4 mm2 m' 30,000

3X6 mm2 m' 43,000

2 SKAKELAR
Out bauw . Seri bh 15,000

. Engkel bh 13,000

In bauw . Seri bh 15,000

. Engkel bh 11,000

3 FUSE BOX (SEKERING KASA)


1 group bh 115,000

2 group bh 220,000

3 group bh 325,000

4 STEKER - Biasa bh 10,000

Arde bh 15,000

T Biasa bh 12,500

T dengan Arde bh 17,000

5 FITING Flaon bh 15,500

Gantung bh 12,500

Kap bh 12,500

Kombinasi bh 25,000

6 STOP KONTAK - Arde Outbow putih bh 12,500

Arde Outbow hitam bh 20,000

Arde IB bh 21,000

Arde Putar bh 31,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 100,000
2 X slag bh 165,000
Yale : 1 X slag bh 90,000
2 X slag bh 110,000
Kuda : 1 X slag bh 70,000
2 X slag bh 110,000

file:///conversion/tmp/scratch/469226324.xls 12/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
2 ENGSEL DAN GERENDEL
Engsel Angin bh 15,000
Kupu-kupu biasa bh 4,000
Nylon kupu-kupu bh 6,000
Espagnoled - dalam negeri bh 40,000
Grendel Tanam luar negeri bh 11,000
Grendel biasa bh 8,000
Kait Angin bh 15,000
Door Stop bh 275,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,300,000
2 KLOSET JONGKOK bh 135,000
3 WASTAFEL PEDESTAL bh 850,000
4 WASTAFEL MEJA OVAL bh 700,000
5 WASTAFEL GANTUNG BULAT bh 275,000
6 WASTAFEL GANTUNG SUDUT bh 240,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 230,000
8 WASTAFEL BAK CUCI bh 145,000
9 TEMPAT SABUN GANTUNG bh 35,000
10 TEMPAT SABUN TANAM bh 20,000
11 LAIN - LAIN
Kran Air bh 25,000
Seal tape bh 2,000
Floor drain bh 25,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 15,000
2 PAKU - payung kg 20,000
3 PAKU - sekrup kg 6,000
4 PAKU - beton kg 25,000
5 MUR BAUT (kuda-kuda) kg 13,000
6 ANGKUR BAUT bh 13,000
7 LEM KAYU bh 12,500
8 Tali Ijuk kg 7,000

XV . POMPA AIR.
1 POMPA AIR TANGAN

file:///conversion/tmp/scratch/469226324.xls 13/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
Dragon buatan Indonesia bh 275,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000
Fuji 250 watt bh 1,450,000
Shimizu . 100 watt bh 450,000
. 90 watt bh 350,000
Dab . 125 watt bh 375,000
. 175 watt bh 425,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 75,000
Merah/hitam m2 85,000
2 HOLLAND Abu-abu m2 75,000
Merah/hitam m2 85,000
3 UNIDECOR Abu-abu m2 75,000
Merah/hitam m2 85,000
4 UNI Abu-abu m2 75,000
Merah/hitam m2 85,000
5 TRIHEX Abu-abu m2 75,000
Merah/hitam m2 85,000
6 OLYMPIA HEXA Abu-abu m2 75,000
7 HEXAGONAL Abu-abu m2 85,000
Merah/hitam m2 75,000
8 CASTLE Abu-abu m2 85,000
9 TRAPEZ Abu-abu m2 75,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 75,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500
12 BATACO BH 5,000
13 KANSTEEN m' 15,000
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000
2 Sliding Pintu J4 bh 180,000
3 Naco per Daun bh 32,500
4 Rolling door Besi m2 300,000
Rolling door Almunium m2 230,000
5 Awning Almunium m2 210,000
6 Kusen Almunium 4" Putih m' 80,000

file:///conversion/tmp/scratch/469226324.xls 14/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,380,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000

Hotmix Tebal = 4 Cm m2 65,000


Hotmix Tebal = 5 Cm m2 80,000
Hotmix Tebal = 6 Cm m2 95,000
Hotmix Tebal = 7 Cm m2 110,000
Binder Course ton 1,300,000
Wearing Course ton 1,300,000
Hot Roller Sheet ton 1,150,000
Sand Sheet ton 1,100,000
Sand Sheet Emulsi ton 1,450,000
Cold Mix ton 1,750,000
Prime / Tack Coard RC liter 7,200
Prime Coat MC liter 7,200
Prime / Tack Coat Emulsi liter 7,200
10 K A C A
Cermin tebal 5 mm m2 225,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 250,000


Pagar BRC 120 A2 /lb 325,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000
Pintu Lipat Besi m2 380,000
Sunscreen Allumunim m2 310,000
Allumunium Foil m2 7,500
Soda api kg 12,000
Sabun kg 11,000
Air m3 15,000
Koas Alang-alang ikat 1,250
Solar (Industri) ltr 7,000
Premium (Industri) ltr 6,200
Pelumas ltr 37,500
Vynil 30x30 cm bh 6,200

file:///conversion/tmp/scratch/469226324.xls 15/193 hdb


HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)

0.070
0.050
4
1,000,000 0.0140 71
1

file:///conversion/tmp/scratch/469226324.xls 16/193 hdb


1.02 2.25 2.30 88392.1568627451

0.92 2.25 2.07 112745.098039216

1.05 3 3.15

file:///conversion/tmp/scratch/469226324.xls 17/193 hdb


###

###

file:///conversion/tmp/scratch/469226324.xls 18/193 hdb


###

###

###

50

0.02

0.1

0.2

###

file:///conversion/tmp/scratch/469226324.xls 19/193 hdb


0.09

0.72

###

file:///conversion/tmp/scratch/469226324.xls 20/193 hdb


#REF!
#REF!
#REF!

file:///conversion/tmp/scratch/469226324.xls 21/193 hdb


file:///conversion/tmp/scratch/469226324.xls 22/193 hdb
file:///conversion/tmp/scratch/469226324.xls 23/193 hdb
file:///conversion/tmp/scratch/469226324.xls 24/193 hdb
file:///conversion/tmp/scratch/469226324.xls 25/193 hdb
file:///conversion/tmp/scratch/469226324.xls 26/193 hdb
file:///conversion/tmp/scratch/469226324.xls 27/193 hdb
XV PEKERJAAN PERPIPAAN (Refe

1 S-005 1 m' Galian tanah untuk Pemasangan P


S-005.a 0.600 m3 Pipa Ø 6"
S-005.b 0.400 m3 Pipa Ø 4"
S-005.c 0.300 m3 Pipa Ø 3"
S-005.d 0.200 m3 Pipa Ø 2"
S-005.e 0.150 m3 Pipa Ø 1,5" ; 1,25"
S-005.f 0.100 m3 Pipa Ø 1" ; 0,75' ; 0,5"

2 S-010 1 m' Urugan tanah kembali untuk Pema


S-010.a 0.700 m3 Pipa Ø 6"
S-010.b 0.400 m3 Pipa Ø 4"
S-010.c 0.300 m3 Pipa Ø 3"
S-010.d 0.200 m3 Pipa Ø 2"
S-010.e 0.150 m3 Pipa Ø 1,5" ; 1,25"
S-010.f 0.100 m3 Pipa Ø 1" ; 0,75' ; 0,5"

3 S-012 1 m' Urugan Pasir untuk Pemasangan P


S-012.a 0.1500 m' Pipa Ø 6"

file:///conversion/tmp/scratch/469226324.xls 28/193 hdb


S-012.b 0.1000 m' Pipa Ø 4"
S-012.c 0.0800 m' Pipa Ø 3"
S-012.d 0.0650 m' Pipa Ø 2"
S-012.e 0.0600 m' Pipa Ø 1,5" ; 1,25"
S-012.f 0.0500 m' Pipa Ø 1" ; 0,75' ; 0,5"

4 P- 01 1 m' Ongkos Pasang Pipa PVC


0.1500 oh Pekerja
0.0900 oh Tukang
0.0090 oh Kepala Tukang
0.0150 oh Mandor

5 1 m' Ongkos Pasang Pipa PVC DN


P-01.a 1.5000 m' Pipa Ø 6"
P-01.b 1.0000 m' Pipa Ø 4"
P-01.c 0.6500 m' Pipa Ø 3"
P-01.d 0.5000 m' Pipa Ø 2"
P-01.e 0.4000 m' Pipa Ø 1,5" ; 1,25"
P-01.f 0.2500 m' Pipa Ø 1" ; 0,75' ; 0,5"

6 P - 02 1 m' Ongkos Pasang Pipa GIP DN


0.1300 oh Pekerja
0.3900 oh Tukang
0.0390 oh Kepala Tukang
0.0650 oh Mandor

7 1 m' Ongkos Pasang Pipa GIP DN


P-02.a 1.2500 m3 Pipa Ø 6"
P-02.b 1.0000 m3 Pipa Ø 4"
P-02.c 0.6500 m3 Pipa Ø 3"
P-02.d 0.5000 m3 Pipa Ø 2"
P-02.e 0.4000 m3 Pipa Ø 1,5" ; 1,25"
P-02.f 0.2500 m3 Pipa Ø 1" ; 0,75' ; 0,5"

8 1 m' Pengetesan Pipa


9 500 m' Pengetesan Pipa
Bahan
1.000 m3 Air
0.150 m3 Kayu Lokal

Tenaga
1.000 m3 galian Tanah
36.000 oh Tukang
6.000 oh Kepala Tukang
3.000 oh Mandor

1.000 alat Test (ls)

10 P- 026 1 m' Pekerjaan Pemasangan Pipa GIP 6


Bahan
1 m' Pipa GIP 6"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan

file:///conversion/tmp/scratch/469226324.xls 29/193 hdb


1 m' Pengetesan Pipa

11 P- 024 1 m' Pekerjaan Pemasangan Pipa GIP 4


Bahan
1 m' Pipa GIP 4"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

12 P- 023 1 m' Pekerjaan Pemasangan Pipa GIP 3


Bahan
1 m' Pipa GIP 3"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

13 P- 022 1 m' Pekerjaan Pemasangan Pipa GIP 2


Bahan
1 m' Pipa GIP 2"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

14 P- 021a 1 m' Pekerjaan Pemasangan Pipa GIP 1


Bahan
1 m' Pipa GIP 1,5"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

15 P- 021b 1 m' Pekerjaan Pemasangan Pipa GIP ¾


Bahan
1 m' Pipa GIP ¾"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

16 P- 014 1 m' Pekerjaan Pemasangan Pipa PVC 4

file:///conversion/tmp/scratch/469226324.xls 30/193 hdb


Bahan
1 m' Pipa PVC 4"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

17 P- 013 1 m' Pekerjaan Pemasangan Pipa PVC 3


Bahan
1 m' Pipa PVC 3"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

18 P- 011 1 m' Pekerjaan Pemasangan Pipa PVC 1


Bahan
1 m' Pipa PVC 1"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

19 P- 011d 1 m' Pekerjaan Pemasangan Pipa PVC ¾


Bahan
1 m' Pipa PVC ¾"

Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa

file:///conversion/tmp/scratch/469226324.xls 31/193 hdb


PEKERJAAN PERPIPAAN (Referensi PDAM)

Galian tanah untuk Pemasangan Pipa


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Pipa Ø 1,5" ; 1,25" #REF! #REF! #REF! #REF!
Pipa Ø 1" ; 0,75' ; 0,5" #REF! #REF! #REF! #REF!

Urugan tanah kembali untuk Pemasangan Pipa


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Pipa Ø 1,5" ; 1,25" #REF! #REF! #REF! #REF!
Pipa Ø 1" ; 0,75' ; 0,5" #REF! #REF! #REF! #REF!

Urugan Pasir untuk Pemasangan Pipa


#REF! #REF! #REF! #REF!

file:///conversion/tmp/scratch/469226324.xls 32/193 hdb


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Pipa Ø 1,5" ; 1,25" #REF! #REF! #REF! #REF!
Pipa Ø 1" ; 0,75' ; 0,5" #REF! #REF! #REF! #REF!

Ongkos Pasang Pipa PVC #REF! #REF!


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Ongkos Pasang Pipa PVC DN


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Pipa Ø 1,5" ; 1,25" #REF! #REF! #REF! #REF!
Pipa Ø 1" ; 0,75' ; 0,5" #REF! #REF! #REF! #REF!

Ongkos Pasang Pipa GIP DN #REF! #REF!


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Ongkos Pasang Pipa GIP DN


#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Pipa Ø 1,5" ; 1,25" #REF! #REF! #REF! #REF!
Pipa Ø 1" ; 0,75' ; 0,5" #REF! #REF! #REF! #REF!

Pengetesan Pipa #REF! #REF!


Pengetesan Pipa #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

45,000.00 45,000.00 45,000.00 45,000.00

Pekerjaan Pemasangan Pipa GIP 6" #REF! #REF!


1,425,000.00 1,430,000.00
1,425,000.00 1,430,000.00 1,425,000.00 1,430,000.00

#REF! #REF!
#REF! #REF! #REF! #REF! 48000
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!

file:///conversion/tmp/scratch/469226324.xls 33/193 hdb


#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa GIP 4" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF! 51000
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa GIP 3" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa GIP 2" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa GIP 1,5" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa GIP ¾" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa PVC 4" #REF! #REF!

file:///conversion/tmp/scratch/469226324.xls 34/193 hdb


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa PVC 3" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa PVC 1" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Pekerjaan Pemasangan Pipa PVC ¾" #REF! #REF!


#REF! #REF!
#REF! #REF! #REF! #REF!

#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

file:///conversion/tmp/scratch/469226324.xls 35/193 hdb


50000

40000

50000

50000

file:///conversion/tmp/scratch/469226324.xls 36/193 hdb


2500

file:///conversion/tmp/scratch/469226324.xls 37/193 hdb


45000

file:///conversion/tmp/scratch/469226324.xls 38/193 hdb


0.33
0.33
0.1089
1
9.1827364555

file:///conversion/tmp/scratch/469226324.xls 39/193 hdb


0.03 0.024
4 1
0.2 41.666666667

file:///conversion/tmp/scratch/469226324.xls 40/193 hdb


190000

180000

file:///conversion/tmp/scratch/469226324.xls 41/193 hdb


49000 56644

55488

file:///conversion/tmp/scratch/469226324.xls 42/193 hdb


58956

file:///conversion/tmp/scratch/469226324.xls 43/193 hdb


57800

46240

57800

57800

file:///conversion/tmp/scratch/469226324.xls 44/193 hdb


2890

file:///conversion/tmp/scratch/469226324.xls 45/193 hdb


52020

file:///conversion/tmp/scratch/469226324.xls 46/193 hdb


25000

file:///conversion/tmp/scratch/469226324.xls 47/193 hdb


DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI III 2018

DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 135,038.20

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 13,200.00

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 60,500.00
Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 14,666.67
Pekerjaan galian
11 A.2.3.1.11 Urugan Pasir m3 235,400.00

14 A.2.3.1.14 Mengurug Sirtu Padat m3 259,600.00

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 883,784.00

9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 515,856.00

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 940,313.00
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 965,710.78
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 985,523.00
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 881,949.44
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,008,916.33
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,031,460.22
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,048,241.33
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,059,650.78
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,079,683.00
(K275), slum (12±2)cm, w/c = 0,53

469226324.xls 193/48 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum
10 A.4.1.1.10 m3 1,085,720.78
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,154,813.61
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,162,916.94
(12±2)cm, w/c = 0,48

13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 12,668.70

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 16,214.00

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,637.95

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 167,156.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 178,156.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 365,634.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 382,302.80

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 458,034.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 416,515.00

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 343,139.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 97,790.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 79,706.00

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 101,134.00

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 80,723.87
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 100,935.08
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 118,489.80
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 151,386.13
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 116,469.72
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 38,936.00
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 34,510.00
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 5,920.00
Komponen Plat Beton Pracetak

469226324.xls 193/49 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan dan Membuka Bekisting untuk
9 A.4.1.2.9 bh 9,580.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 7,750.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 55,946.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 57,530.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 51,727.50
Kolom Pracetak

14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 564,060.20

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 555,742.00

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 800,127.90

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 147,134.90

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 120,256.40

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 120,256.40

20 A.4.1.2.20 Bahan Grout Campuran m3 3,415,775.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,059,100.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 51,375.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 109,754.70

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 43,439.00

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 29,023.50

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 21,433.50

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 96,646.00

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 804,815.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,247.30

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 219,903.20

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 562,980.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 505,604.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 440,880.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 452,100.00

469226324.xls 193/50 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 110,305.80

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 476,388.00

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 443,866.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 174,240.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 487,715.67

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 93,693.05

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 122,155.00

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 184,992.50
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 111,430.00
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 140,140.00
Modul 60x60 cm dinding plafond

Pemasangan Atap Pelana Rangka Atap Baja Canal


21 A.4.2.1.22 m2 205,293.83
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 229,573.85
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 242,742.50
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 234,308.25
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 227,598.25
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 225,643.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 228,189.50
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 217,479.90
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 117,455.25
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 112,847.35
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 110,555.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

469226324.xls 193/51 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan Dinding Bata Merah Ukuran
10 A.4.4.1.10 m2 109,135.40
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 108,928.60
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 107,167.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 109,807.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 98,648.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran


15 A.4.4.1.15 m2 99,858.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


16 A.4.4.1.16 m2 387,613.60
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 395,618.30
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 305,257.70
3PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


19 A.4.4.1.19 m2 310,926.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 249,719.80
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 254,404.15
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 308,550.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 308,550.00
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 140,492.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 262,648.54
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 265,774.74
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 65,603.12

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 60,868.72

469226324.xls 193/52 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 59,064.28

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 57,631.20

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 57,093.52

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 56,547.48

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 56,334.08

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 56,120.68

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 55,767.80
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 55,627.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 51,711.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 52,657.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 81,491.96

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 61,196.40

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 77,061.60

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 76,458.36

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 75,616.64

Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20


18 A.4.4.2.18 m2 73,040.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 36,089.02

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 58,250.50
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 91,525.50
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 91,525.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 43,445.60

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 24,825.24
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 11,819.50
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 53,654.70
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 31,913.75

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 40,713.20

469226324.xls 193/53 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 34,595.00

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 103,755.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 105,132.50

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 129,133.00

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 131,147.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 345,119.50

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 64,484.20

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 36,681.70

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 197,449.45

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 202,894.45
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 206,522.01

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 187,524.00

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 199,738.00

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 407,016.50
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 35,191.20

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 81,550.70

16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 79,218.70

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 685,079.45

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 199,452.00

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 377,410.00

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 239,408.16

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 217,684.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 226,561.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 217,684.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 227,705.50


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 767,763.82

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 257,166.25
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 143,592.90

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 113,459.50

469226324.xls 193/54 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 45,342.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 166,083.50

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 218,245.50

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 178,304.50

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 230,466.50

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 29,832.00
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 101,277.00
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 104,951.00
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 90,035.00
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 45,155.00
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati, tebal


6 A.4.5.1.6 m2 522,445.00
6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 39,919.00
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 208,615.00
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 15,719.00


HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 84,425.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 138,110.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 122,215.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 97,867.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 110,242.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 114,092.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 102,723.50


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 61,836.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 63,668.00
x 5 mm

469226324.xls 193/55 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan Atap Asbes Gelombang (2,00x0,92 m)
10 A.4.5.2.10 m2 63,998.00
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 71,258.00
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 54,290.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 56,408.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 53,218.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 55,137.50
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 58,718.00
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 63,679.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 67,034.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 63,866.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 64,878.00
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 68,783.00
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 101,255.00

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 217,503.00

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 87,560.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 107,162.00

26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 119,031.00

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 121,306.35

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 63,195.00

29 A.4.5.2.38 Pemasangan Nok Sirap m' 52,690.00

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 37,246.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 29,612.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 26,922.50

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

469226324.xls 193/56 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 m3 27,260,475.00
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 10,680,175.00
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 468,985.00
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 468,985.00
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 749,787.50
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 540,045.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 1,987,975.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 579,480.00
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 627,462.00
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 1,776,115.00
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,026,960.00
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 676,005.00
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 9,417,100.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 29,603,310.00
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 8,682,520.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 142,131.00
Klas II

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 m2 166,287.00
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 121,132.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 161,414.00
kayu Klas II atau III

469226324.xls 193/57 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan Rangka Langit-langit (60x60) cm, kayu
20 A.4.6.1.20 m2 164,978.00
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 294,580.00
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 119,515.00
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 255,255.00
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 324,445.00
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 332,145.00
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 431,420.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 38,065.50
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 121,213.84
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 175,780.00

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 152,515.00

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 174,515.00

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 26,070.00

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 17,380.00

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 47,575.00

7 A.4.6.2.9 Pemasangan Kait Angin Buah 36,025.00

8 A.4.6.2.10 Pasang Door Closer Buah 364,925.00

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 33,770.00

10 A.4.6.2.13 Pemasangan Door Stop Buah 314,985.00

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 272,910.00

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 44,968.00

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 103,427.50

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 127,627.50

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 290,977.50

469226324.xls 193/58 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
HARGA SATUAN PEKERJAAN
XIII A.4.7.1
PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 12,540.00
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 12,485.00
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 13,035.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 38,434.00
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 53,669.00
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 33,852.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 53,242.20

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 9,418.75

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 36,641.00

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 18,873.80
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 13,521.20
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 7,845.20

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 13,852.85

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 6,344.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 83,435.00

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 25,762.00

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 50,792.50
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 1,902,571.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 591,690.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 715,440.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 540,292.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,083,555.00

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,145,100.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,430,429.27

469226324.xls 193/59 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,059,703.90

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 341,440.00

10 A.5.1.1.14 Pemasangan Floor Drain buah 40,480.00

Pemasangan Bak Kontrol Pas.Batu Bata 30x30


11 A.5.1.1.15 bh 416,448.91
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 611,357.91
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 744,527.51
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 60,247.00

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 75,465.50

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 71,613.67

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 102,872.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 136,416.50

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 246,323.00

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 450,923.00

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 21,923.00

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 24,480.50

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 29,169.25

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 30,895.33

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 33,452.83

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 57,938.83

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 61,138.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 76,527.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 36,751.00
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 103,274.60

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 576,251.50

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 338,360.00


2 A.8.4.6.2 Pemasangan MCB buah 459,140.00

469226324.xls 193/60 hspk


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI III 2018

HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 135,038.20
A Tenaga 18,100.00
L.01 0.1 OH Pekerja 70,000.00 7,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 100,000.00 500.00
B Bahan 104,662.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 5,051,000.00 60,612.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 300.00
0.007 m3 Kayu Papan 3/20 Kruing 6,250,000.00 43,750.00
C PERALATAN
D Jumlah A + B + C 122,762.00
E Overhead & Profit (contah 10%) 10% 12,276.20
F Harga Satuan Pekerjaan (D+E) 135,038.20

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 13,200.00


A Tenaga 12,000.00
L.01 0.1 OH Pekerja 70,000.00 7,000.00
L.04 0.05 OH Mandor 100,000.00 5,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C 12,000.00
E Overhead & Profit (contah 10%) 10% 1,200.00
F Harga Satuan Pekerjaan (D+E) 13,200.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 330,882.20


A Tenaga 287,000.00
L.01 1.00 OH Pekerja 70,000.00 70,000.00
L.02 2.00 OH Tukang Kayu 95,000.00 190,000.00
L.03 0.20 OH Kepala Tukang 110,000.00 22,000.00
L.04 0.05 OH Mandor 100,000.00 5,000.00
B Bahan 13,802.00
1.250 Btg Bambu diameter 6 - 8 / 600 cm 10,000.00 12,500.00
0.186 Kg Tali Ijuk 7,000.00 1,302.00
C PERALATAN
D Jumlah A + B + C 300,802.00
E Overhead & Profit (contah 10%) 10% 30,080.20
F Harga Satuan Pekerjaan (D+E) 330,882.20

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 483,819.60
40cmx50cmx25cm
A Tenaga 31,800.00
L.02 0.30 OH Tukang Kayu 95,000.00 28,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 3,300.00
B Bahan 408,036.00
0.036 m3 Kayu Papan Kelas III 6,250,000.00 225,000.00
0.036 m3 Kayu Balok Kelas III 5,051,000.00 181,836.00
0.080 kg Paku Biasa 15,000.00 1,200.00
C PERALATAN
D Jumlah A + B + C 439,836.00
E Overhead & Profit (contah 10%) 10% 43,983.60
F Harga Satuan Pekerjaan (D+E) 483,819.60

file:///conversion/tmp/scratch/469226324.xls 1-20-61
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 153,560.00
A Tenaga 70,500.00

L.01 1 OH Pekerja 70,000.00 70,000.00

L.04 0.005 OH Mandor 100,000.00 500.00

B. Bahan 69,100.00
0.150 m3 Batu Belah 260,000.00 39,000.00

0.090 m3 Batu Pecah 300,000.00 27,000.00

0.010 m3 Pasir Pasang 310,000.00 3,100.00

C PERALATAN
D Jumlah A + B + C 139,600.00
E Overhead & Profit (contah 10%) 10% 13,960.00
F Harga Satuan Pekerjaan (D+E) 153,560.00

11 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,099,978.00


A Tenaga 999,980.00
L.01 13.334 OH Pekerja 70,000.00 933,380.00
L.04 0.666 OH Mandor 100,000.00 66,600.00
B Bahan
C PERALATAN
D Jumlah A + B + C 999,980.00
E Overhead & Profit (contah 10%) 10% 99,998.00
F Harga Satuan Pekerjaan (D+E) 1,099,978.00

12 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 516,989.00


A Tenaga 469,990.00
L.01 6.667 OH Pekerja 70,000.00 466,690.00
L.04 0.033 OH Mandor 100,000.00 3,300.00
B Bahan
C PERALATAN
D Jumlah A + B + C 469,990.00
E Overhead & Profit (contah 10%) 10% 46,999.00
F Harga Satuan Pekerjaan (D+E) 516,989.00

13 A.2.2.1.15 1 m2 Pagar Kawat Jaring Galvanis Panjang 240 cm 47,949.00


A Tenaga 7,740.00

L.01 0.042 OH Pekerja 70,000.00 2,940.00


L.02 0.004 OH Tukang 95,000.00 380.00
L.03 0.002 OH Kepala Tukang 110,000.00 220.00
L.04 0.042 OH Mandor 100,000.00 4,200.00
B Bahan 35,850.00

0.1434 Lbr Kawat Jaring 250,000 35,850.00


C PERALATAN
D Jumlah A + B + C 43,590.00
E Overhead & Profit (contah 10%) 10% 4,359.00
F Harga Satuan Pekerjaan (D+E) 47,949.00

Pemasangan Pagar Panel Beton Pracetak 5 x 50 x


14 A.2.2.1.16 1 m2 291,841.00
240 cm
A Tenaga 41,345.00
L.01 0.375 OH Pekerja 70,000.00 26,250.00
L.02 0.125 OH Tukang Batu 95,000.00 11,875.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.019 OH Mandor 100,000.00 1,900.00
B Bahan 223,965.00
0.986 Lbr Panel Beton Pracetak 65,000.00 64,090.00

file:///conversion/tmp/scratch/469226324.xls 1-20-62
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
0.525 Btg Kolom Beton Pracetak 145,000.00 76,125.00
45.000 Kg Semen (SM) 1,050.00 47,250.00
0.146 m3 Koral 250,000.00 36,500.00
C PERALATAN
D Jumlah A + B + C 265,310.00
E Overhead & Profit (contah 10%) 10% 26,531.00
F Harga Satuan Pekerjaan (D+E) 291,841.00

file:///conversion/tmp/scratch/469226324.xls 1-20-63
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

0.03
33.3

file:///conversion/tmp/scratch/469226324.xls 1-20-64
0.06

### ###
#REF! #REF!

0.2

0.2

0.08
###

#REF!

0.05
0.5

2.4

0.06
64,781

file:///conversion/tmp/scratch/469226324.xls 1-20-65
1079683 1214978.50397

64780.98 72898.7102381

0.15

0.4

2.2

0.132

142518.156 160377.162524
140000 160000

file:///conversion/tmp/scratch/469226324.xls 1-20-66
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 60,500.00


A TENAGA 55,000.00
L.01 0.75 OH Pekerja 70,000.00 52,500.00
L.04 0.025 OH Mandor 100,000.00 2,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 55,000.00
E Overhead & Profit (contah 10%) 10% 5,500.00
F Harga Satuan Pekerjaan (D+E) 60,500.00
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 74,250.00
A TENAGA 67,500.00
L.01 0.90 OH Pekerja 70,000.00 63,000.00
L.04 0.045 OH Mandor 100,000.00 4,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 67,500.00
E Overhead & Profit (contah 10%) 10% 6,750.00
F Harga Satuan Pekerjaan (D+E) 74,250.00

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 88,220.00


A TENAGA 80,200.00
L.01 1.05 OH Pekerja 70,000.00 73,500.00
L.04 0.067 OH Mandor 100,000.00 6,700.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 80,200.00
E Overhead & Profit (contah 10%) 10% 8,020.00
F Harga Satuan Pekerjaan (D+E) 88,220.00

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 80,520.00


TENAGA 73,200.00
L.01 1.000 OH Pekerja 70,000.00 70,000.00
L.04 0.032 OH Mandor 100,000.00 3,200.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 73,200.00
E Overhead & Profit (contah 10%) 10% 7,320.00
F Harga Satuan Pekerjaan (D+E) 80,520.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 122,100.00


A TENAGA 111,000.00
L.01 1.50 OH Pekerja 70,000.00 105,000.00
L.04 0.060 OH Mandor 100,000.00 6,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 111,000.00
E Overhead & Profit (contah 10%) 10% 11,100.00
F Harga Satuan Pekerjaan (D+E) 122,100.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 97,350.00


A TENAGA 88,500.00
L.01 1.200 OH Pekerja 70,000.00 84,000.00
L.04 0.045 OH Mandor 100,000.00 4,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 88,500.00
E Overhead & Profit (contah 10%) 10% 8,850.00
F Harga Satuan Pekerjaan (D+E) 97,350.00

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 4,400.00


A TENAGA 4,000.00
L.01 0.05 OH Pekerja 70,000.00 3,500.00
L.04 0.005 OH Mandor 100,000.00 500.00
B BAHAN

file:///conversion/tmp/scratch/469226324.xls 193/67 2-20


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
C PERALATAN
D Jumlah A + B + C 4,000.00
E Overhead & Profit (contah 10%) 10% 400.00
F Harga Satuan Pekerjaan (D+E) 4,400.00

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 26,510.00


A TENAGA 24,100.00
L.01 0.330 OH Pekerja 70,000.00 23,100.00
L.04 0.010 OH Mandor 100,000.00 1,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 24,100.00
E Overhead & Profit (contah 10%) 10% 2,410.00
F Harga Satuan Pekerjaan (D+E) 26,510.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 14,666.67
Pekerjaan galian
A TENAGA 40,000.00
L.01 0.50 OH Pekerja 70,000.00 35,000.00
L.04 0.050 OH Mandor 100,000.00 5,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 40,000.00
E Overhead & Profit (contah 10%) 10% 4,000.00
F Harga Satuan Pekerjaan (D+E) 44,000.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 44,000.00


A TENAGA 40,000.00
L.01 0.5 OH Pekerja 70,000.00 35,000.00
L.04 0.05 OH Mandor 100,000.00 5,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 40,000.00
E Overhead & Profit (contah 10%) 10% 4,000.00
F Harga Satuan Pekerjaan (D+E) 44,000.00

11 A.2.3.1.11 1 m3 Urugan Pasir 235,400.00


A TENAGA 22,000.00
L.01 0.30 OH Pekerja 70,000.00 21,000.00
L.04 0.01 OH Mandor 100,000.00 1,000.00
B BAHAN 192,000.00
1.2 m3 Pasir Urug 160,000.00 192,000.00
C PERALATAN
D Jumlah A + B + C 214,000.00
E Overhead & Profit (contah 10%) 10% 21,400.00
F Harga Satuan Pekerjaan (D+E) 235,400.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 420,211.00


A TENAGA 106,400.00
L.01 0.800 OH Pekerja 70,000.00 56,000.00
L.02 0.400 OH Tukang Batu 95,000.00 38,000.00
L.03 0.04 OH Kepala Tukang 110,000.00 4,400.00
L.04 0.080 OH Mandor 100,000.00 8,000.00
B BAHAN 275,610.00
0.135 m3 Pasir Pasang 310,000.00 41,850.00
0.400 m3 Kapur Padam 300,000.00 120,000.00
0.948 m3 Tanah Liat 120,000.00 113,760.00
C PERALATAN
D Jumlah A + B + C 382,010.00
E Overhead & Profit (contah 10%) 10% 38,201.00
F Harga Satuan Pekerjaan (D+E) 420,211.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 59,400.00
Resapan
A TENAGA 12,000.00
0.15 OH Pekerja 70,000.00 10,500.00

file:///conversion/tmp/scratch/469226324.xls 193/68 2-20


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
0.015 OH Mandor 100,000.00 1,500.00
B BAHAN 42,000.00
6.00 kg Ijuk 7,000.00 42,000.00
C PERALATAN
D Jumlah A + B + C 54,000.00
E Overhead & Profit (contah 10%) 10% 5,400.00
F Harga Satuan Pekerjaan (D+E) 59,400.00

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 259,600.00


A TENAGA 20,000.00
0.25 OH Pekerja 70,000.00 17,500.00
0.025 OH Mandor 100,000.00 2,500.00
B BAHAN 216,000.00
1.2 m3 Sirtu 180,000.00 216,000.00
C PERALATAN
D Jumlah A + B + C 236,000.00
E Overhead & Profit (contah 10%) 10% 23,600.00
F Harga Satuan Pekerjaan (D+E) 259,600.00

file:///conversion/tmp/scratch/469226324.xls 193/69 2-20


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 939,895.00
A TENAGA 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B BAHAN 662,450.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
202 Kg Portland Sement 1,050.00 212,100.00
0.485 m3 Pasir Pasang 310,000.00 150,350.00
C PERALATAN
D Jumlah A + B + C 854,450.00
E Overhead & Profit (contoh 10%) 10% 85,445.00
F Harga Satuan Pekerjaan (D+E) 939,895.00
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 906,785.00
A TENAGA 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B BAHAN 632,350.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
163 Kg Portland Sement 1,050.00 171,150.00
0.52 m3 Pasir Pasang 310,000.00 161,200.00
C PERALATAN
D Jumlah A + B + C 824,350.00
E Overhead & Profit (contoh 10%) 10% 82,435.00
F Harga Satuan Pekerjaan (D+E) 906,785.00

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 883,784.00


A TENAGA 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B BAHAN 611,440.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
136 Kg Portland Sement 1,050.00 142,800.00
0.544 m3 Pasir Pasang 310,000.00 168,640.00
C PERALATAN
D Jumlah A + B + C 803,440.00
E Overhead & Profit (contoh 10%) 10% 80,344.00
F Harga Satuan Pekerjaan (D+E) 883,784.00

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 867,636.00


A TENAGA 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B BAHAN 596,760.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
117 Kg Portland Sement 1,050.00 122,850.00
0.561 m3 Pasir Pasang 310,000.00 173,910.00
C PERALATAN
D Jumlah A + B + C 788,760.00
E Overhead & Profit (contoh 10%) 10% 78,876.00
F Harga Satuan Pekerjaan (D+E) 867,636.00

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 845,449.00


A Tenaga 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B Bahan 576,590.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
91 Kg Portland Sement 1,050.00 95,550.00
0.584 m3 Pasir Pasang 310,000.00 181,040.00

file:///conversion/tmp/scratch/469226324.xls 193/70 3-20


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
C PERALATAN
D Jumlah A + B + C 768,590.00
E Overhead & Profit (contoh 10%) 10% 76,859.00
F Harga Satuan Pekerjaan (D+E) 845,449.00

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 750,640.00


A Tenaga 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B Bahan 490,400.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 51,000.00
0.17 Kg Semen Merah (SM) 200,000.00 34,000.00
0.340 m3 Pasir Pasang 310,000.00 105,400.00
C PERALATAN
D Jumlah A + B + C 682,400.00
E Overhead & Profit (contoh 10%) 10% 68,240.00
F Harga Satuan Pekerjaan (D+E) 750,640.00

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 827,937.00


A Tenaga 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B Bahan 560,670.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
61 kg Portland Sement 1,050.00 64,050.00
0.147 m3 Kapur Pasang 300,000.00 44,100.00
0.492 m3 Pasir Pasang 310,000.00 152,520.00
C PERALATAN
D Jumlah A + B + C 752,670.00
E Overhead & Profit (contoh 10%) 10% 75,267.00
F Harga Satuan Pekerjaan (D+E) 827,937.00

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 810,128.00


A Tenaga 192,000.00
L.01 1.5 OH Pekerja 70,000.00 105,000.00
L.02 0.750 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 100,000.00 7,500.00
B Bahan 544,480.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
41 kg Portland Sement 1,050.00 43,050.00
0.131 m3 Kapur Pasang 300,000.00 39,300.00
0.523 m3 Pasir 310,000.00 162,130.00
C PERALATAN
D Jumlah A + B + C 736,480.00
E Overhead & Profit (contoh 10%) 10% 73,648.00
F Harga Satuan Pekerjaan (D+E) 810,128.00

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 515,856.00


A Tenaga 99,840.00
L.01 0.78 OH Pekerja 70,000.00 54,600.00
L.02 0.39 OH Tukang Batu 95,000.00 37,050.00
L.03 0.039 OH Kepala Tukang 110,000.00 4,290.00
L.04 0.039 OH Mandor 100,000.00 3,900.00
B Bahan 369,120.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00
0.432 m3 Pasir Urug 160,000.00 69,120.00
C PERALATAN
D Jumlah A + B + C 468,960.00
E Overhead & Profit (contoh 10%) 10% 46,896.00
F Harga Satuan Pekerjaan (D+E) 515,856.00

Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :


10 A.3.2.1.10 1 m3 2,329,492.00
3KR & 40% Batu Belah
A Tenaga 343,100.00
L.01 3.4 OH Pekerja 70,000.00 238,000.00
L.02 0.85 OH Tukang Batu 95,000.00 80,750.00

file:///conversion/tmp/scratch/469226324.xls 193/71 3-20


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
L.03 0.085 OH Kepala Tukang 110,000.00 9,350.00
L.04 0.15 OH Mandor 100,000.00 15,000.00
B Bahan 1,774,620.00
0.480 m3 Batu Belah 15/20 cm 250,000.00 120,000.00
126 Kg Besi Beton 9,500.00 1,197,000.00
194 Kg Portland Semen 1,050.00 203,700.00
0.312 m3 Pasir Beton 350,000.00 109,200.00
0.468 m3 Koral Beton 240,000.00 112,320.00
1.8 Kg Kawat Beton 18,000.00 32,400.00
C PERALATAN
D Jumlah A + B + C 2,117,720.00
E Overhead & Profit (contoh 10%) 10% 211,772.00
F Harga Satuan Pekerjaan (D+E) 2,329,492.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 882,662.00


A Tenaga 264,700.00
L.01 2.40 OH Pekerja 70,000.00 168,000.00
L.02 0.8 OH Tukang Batu 95,000.00 76,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 8,800.00
L.04 0.119 OH Mandor 100,000.00 11,900.00
B Bahan 537,720.00
0.45 m3 Batu Belah 15/20 cm 250,000.00 112,500.00
194 Kg Portland Semen 1,050.00 203,700.00
0.312 m3 Pasir Beton 350,000.00 109,200.00
0.468 m3 Koral Beton 240,000.00 112,320.00
C PERALATAN
D Jumlah A + B + C 802,420.00
E Overhead & Profit (contoh 10%) 10% 80,242.00
F Harga Satuan Pekerjaan (D+E) 882,662.00

file:///conversion/tmp/scratch/469226324.xls 193/72 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 940,313.00 1,070,106.32
= 0,87
A Tenaga 153,005.00 181,615.00
L.01 1.65 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 701,825.00 791,208.93
247 Kg Portland Semen 1,050.00 1,062.50 259,350.00 262,437.50
869 Kg Pasir Beton 250.00 271.43 217,250.00 235,871.43
999 Kg Kerikil (maksimum 30 mm) 222.22 288.89 222,000.00 288,600.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 854,830.00 972,823.93
E Overhead & Profit (contoh 10%) 10% 85,483.00 97,282.39
F Harga Satuan Pekerjaan (D+E) 940,313.00 1,070,106.32
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 965,710.78 1,095,889.75
= 0,78
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 724,913.89 814,648.41
276 Kg Portland Semen 1,050.00 1,062.50 289,800.00 293,250.00
828 kg Pasir Beton 250.00 271.43 207,000.00 224,742.86
1,012 kg Kerikil (maksimum 30 mm) 222.22 288.89 224,888.89 292,355.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 877,918.89 996,263.41
E Overhead & Profit (contoh 10%) 10% 87,791.89 99,626.34
F Harga Satuan Pekerjaan (D+E) 965,710.78 1,095,889.75

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 985,523.00 1,115,701.32
w/c = 0,72
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 742,925.00 832,658.93
299 Kg Portland Semen 1,050.00 1,062.50 313,950.00 317,687.50
799 kg Pasir Beton 250.00 271.43 199,750.00 216,871.43
1,017 kg Kerikil (maksimum 30 mm) 222.22 288.89 226,000.00 293,800.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 895,930.00 1,014,273.93
E Overhead & Profit (contoh 10%) 10% 89,593.00 101,427.39
F Harga Satuan Pekerjaan (D+E) 985,523.00 1,115,701.32

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 881,949.44 1,004,860.56
(3-6)cm, w/c = 0,87
A Tenaga 105,800.00 126,060.00
L.01 1.200 OH Pekerja 70,000.00 85,000.00 84,000.00 102,000.00
L.02 0.200 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 695,972.22 787,449.60
230 Kg Portland Semen 1,050.00 1,062.50 241,500.00 244,375.00
893 kg Pasir Beton 250.00 271.43 223,250.00 242,385.71
1,027 kg Kerikil (maksimum 30 mm) 222.22 288.89 228,222.22 296,688.89
200 ltr Air 15.00 20.00 3,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 801,772.22 913,509.60
E Overhead & Profit (contoh 10%) 10% 80,177.22 91,350.96
F Harga Satuan Pekerjaan (D+E) 881,949.44 1,004,860.56

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,008,916.33 1,139,426.62
w/c = 0,66
A Tenaga 153,005.00 181,615.00
L.01 1.65 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00

file:///conversion/tmp/scratch/469226324.xls 193/73 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 764,191.67 854,227.38
326 Kg Portland Semen 1,050.00 1,062.50 342,300.00 346,375.00
760 Kg Pasir Beton 250.00 271.43 190,000.00 206,285.71
1,029 Kg Kerikil (maksimum 30 mm) 222.22 288.89 228,666.67 297,266.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 917,196.67 1,035,842.38
E Overhead & Profit (contoh 10%) 10% 91,719.67 103,584.24
F Harga Satuan Pekerjaan (D+E) 1,008,916.33 1,139,426.62

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,031,460.22 1,161,791.10
w/c = 0,61
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 784,686.11 874,558.73
352 Kg Portland Semen 1,050.00 1,062.50 369,600.00 374,000.00
731 Kg Pasir Beton 250.00 271.43 182,750.00 198,414.29
1,031 Kg Kerikil (maksimum 30 mm) 222.22 288.89 229,111.11 297,844.44
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 937,691.11 1,056,173.73
E Overhead & Profit (contoh 10%) 10% 93,769.11 105,617.37
F Harga Satuan Pekerjaan (D+E) 1,031,460.22 1,161,791.10

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,048,241.33 1,179,228.94
w/c = 0,58
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 799,941.67 890,411.31
371 Kg Portland Semen 1,050.00 1,062.50 389,550.00 394,187.50
698 Kg Pasir Beton 250.00 271.43 174,500.00 189,457.14
1,047 Kg Kerikil (maksimum 30 mm) 222.22 288.89 232,666.67 302,466.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 952,946.67 1,072,026.31
E Overhead & Profit (contoh 10%) 10% 95,294.67 107,202.63
F Harga Satuan Pekerjaan (D+E) 1,048,241.33 1,179,228.94

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,059,650.78 1,190,089.04
w/c = 0,56
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 810,313.89 900,284.13
384 Kg Portland Semen 1,050.00 1,062.50 403,200.00 408,000.00
692 Kg Pasir Beton 250.00 271.43 173,000.00 187,828.57
1,039 Kg Kerikil (maksimum 30 mm) 222.22 288.89 230,888.89 300,155.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 963,318.89 1,081,899.13
E Overhead & Profit (contoh 10%) 10% 96,331.89 108,189.91
F Harga Satuan Pekerjaan (D+E) 1,059,650.78 1,190,089.04

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,079,683.00 1,209,281.86
(12±2)cm, w/c = 0,53
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 828,525.00 917,732.14
406 Kg Portland Semen 1,050.00 1,062.50 426,300.00 431,375.00
684 kg Pasir Beton 250.00 271.43 171,000.00 185,657.14
1,026 kg Kerikil (maksimum 30 mm) 222.22 288.89 228,000.00 296,400.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 981,530.00 1,099,347.14
E Overhead & Profit (contoh 10%) 10% 98,153.00 109,934.71
F Harga Satuan Pekerjaan (D+E) 1,079,683.00 1,209,281.86

file:///conversion/tmp/scratch/469226324.xls 193/74 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,085,720.78 1,214,978.50
w/c = 0,52
A Tenaga 153,005.00 181,615.00
L.01 1.650 OH Pekerja 70,000.00 85,000.00 115,500.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 834,013.89 922,910.91
413 Kg Portland Semen 1,050.00 1,062.50 433,650.00 438,812.50
681 Kg Pasir Beton 250.00 271.43 170,250.00 184,842.86
1,021 Kg Kerikil (maksimum 30 mm) 222.22 288.89 226,888.89 294,955.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 987,018.89 1,104,525.91
E Overhead & Profit (contoh 10%) 10% 98,701.89 110,452.59
F Harga Satuan Pekerjaan (D+E) 1,085,720.78 1,214,978.50

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,154,813.61 1,291,638.55
w/c = 0,49
A Tenaga 194,600.00 231,000.00
L.01 2.1 OH Pekerja 70,000.00 85,000.00 147,000.00 178,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.105 OH Mandor 100,000.00 110,000.00 10,500.00 11,550.00
B Bahan 855,230.56 943,216.87
439 Kg Portland Semen 1,050.00 1,062.50 460,950.00 466,437.50
670 Kg Pasir Beton 250.00 271.43 167,500.00 181,857.14
1,006 Kg Kerikil (maksimum 30 mm) 222.22 288.89 223,555.56 290,622.22
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,049,830.56 1,174,216.87
E Overhead & Profit (contoh 10%) 10% 104,983.06 117,421.69
F Harga Satuan Pekerjaan (D+E) 1,154,813.61 1,291,638.55

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,162,916.94 1,299,354.92
w/c = 0,48
A Tenaga 194,600.00 231,000.00
L.01 2.10 OH Pekerja 70,000.00 85,000.00 147,000.00 178,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.105 OH Mandor 100,000.00 110,000.00 10,500.00 11,550.00
B Bahan 862,597.22 950,231.75
448 Kg Portland Semen 1,050.00 1,062.50 470,400.00 476,000.00
667 Kg Pasir Beton 250.00 271.43 166,750.00 181,042.86
1,000 Kg Kerikil (maksimum 30 mm) 222.22 288.89 222,222.22 288,888.89
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,057,197.22 1,181,231.75
E Overhead & Profit (contoh 10%) 10% 105,719.72 118,123.17
F Harga Satuan Pekerjaan (D+E) 1,162,916.94 1,299,354.92

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 126,687.00 140,613.00


A Tenaga 12,720.00 14,580.00
L.01 0.07 OH Pekerja 70,000.00 85,000.00 4,900.00 5,950.00
L.02 0.07 OH Tukang Besi 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 102,450.00 113,250.00
10.50 Kg Besi Beton (polos/ulir) 9,500.00 10,500.00 99,750.00 110,250.00
0.150 Kg Kawat Beton 18,000.00 20,000.00 2,700.00 3,000.00
C PERALATAN
D Jumlah A + B + C 115,170.00 127,830.00
E Overhead & Profit (contoh 10%) 10% 11,517.00 12,783.00
F Harga Satuan Pekerjaan (D+E) 126,687.00 140,613.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 162,140.00 181,148.00


A Tenaga 9,100.00 10,430.00
L.01 0.05 OH Pekerja 70,000.00 85,000.00 3,500.00 4,250.00
L.02 0.05 OH Tukang Besi 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 138,300.00 154,250.00
10.5 Kg Besi presstred polos 13,000.00 14,500.00 136,500.00 152,250.00
0.1 Kg Kawat Beton 18,000.00 20,000.00 1,800.00 2,000.00

file:///conversion/tmp/scratch/469226324.xls 193/75 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 147,400.00 164,680.00
E Overhead & Profit (contoh 10%) 10% 14,740.00 16,468.00
F Harga Satuan Pekerjaan (D+E) 162,140.00 181,148.00

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 286,379.50 315,260.00


A Tenaga 4,445.00 5,100.00
L.01 0.025 OH Pekerja 70,000.00 85,000.00 1,750.00 2,125.00
L.02 0.025 OH Tukang Besi 95,000.00 105,000.00 2,375.00 2,625.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 255,900.00 281,500.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 27,500.00 255,000.00 280,500.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 260,345.00 286,600.00
E Overhead & Profit (contoh 10%) 10% 26,034.50 28,660.00
F Harga Satuan Pekerjaan (D+E) 286,379.50 315,260.00

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 167,156.00 188,903.00


A Tenaga 66,560.00 77,480.00
L.01 0.52 OH Pekerja 70,000.00 85,000.00 36,400.00 44,200.00
L.02 0.26 OH Tukang Kayu 95,000.00 105,000.00 24,700.00 27,300.00
L.03 0.026 OH Kepala Tukang 110,000.00 120,000.00 2,860.00 3,120.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 85,400.00 94,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 151,960.00 171,730.00
E Overhead & Profit (contoh 10%) 10% 15,196.00 17,173.00
F Harga Satuan Pekerjaan (D+E) 167,156.00 188,903.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 178,156.00 201,003.00


A Tenaga 66,560.00 77,480.00
L.01 0.52 OH Pekerja 70,000.00 85,000.00 36,400.00 44,200.00
L.02 0.26 OH Tukang Kayu 95,000.00 105,000.00 24,700.00 27,300.00
L.03 0.026 OH Kepala Tukang 110,000.00 120,000.00 2,860.00 3,120.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 95,400.00 105,250.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 161,960.00 182,730.00
E Overhead & Profit (contoh 10%) 10% 16,196.00 18,273.00
F Harga Satuan Pekerjaan (D+E) 178,156.00 201,003.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 365,634.50 428,274.00


A Tenaga 84,480.00 98,340.00
L.01 0.66 OH Pekerja 70,000.00 85,000.00 46,200.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 247,915.00 291,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 5,051,000.00 6,000,000.00 75,765.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 332,395.00 389,340.00
E Overhead & Profit (contoh 10%) 10% 33,239.50 38,934.00
F Harga Satuan Pekerjaan (D+E) 365,634.50 428,274.00

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 382,302.80 448,074.00


A Tenaga 84,480.00 98,340.00
L.01 0.66 OH Pekerja 70,000.00 85,000.00 46,200.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

file:///conversion/tmp/scratch/469226324.xls 193/76 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 263,068.00 309,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 5,051,000.00 6,000,000.00 90,918.00 108,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 347,548.00 407,340.00
E Overhead & Profit (contoh 10%) 10% 34,754.80 40,734.00
F Harga Satuan Pekerjaan (D+E) 382,302.80 448,074.00

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 458,034.50 533,874.00


A Tenaga 84,480.00 98,340.00
L.01 0.66 OH Pekerja 70,000.00 85,000.00 46,200.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 331,915.00 387,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 5,051,000.00 6,000,000.00 75,765.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 416,395.00 485,340.00
E Overhead & Profit (contoh 10%) 10% 41,639.50 48,534.00
F Harga Satuan Pekerjaan (D+E) 458,034.50 533,874.00

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 416,515.00 487,674.00


A Tenaga 84,480.00 98,340.00
L.01 0.66 OH Pekerja 70,000.00 85,000.00 46,200.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 294,170.00 345,000.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 5,051,000.00 6,000,000.00 101,020.00 120,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 378,650.00 443,340.00
E Overhead & Profit (contoh 10%) 10% 37,865.00 44,334.00
F Harga Satuan Pekerjaan (D+E) 416,515.00 487,674.00

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 343,139.50 403,524.00


A Tenaga 84,480.00 98,340.00
L.01 0.66 OH Pekerja 70,000.00 85,000.00 46,200.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 227,465.00 268,500.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 5,051,000.00 6,000,000.00 75,765.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 311,945.00 366,840.00
E Overhead & Profit (contoh 10%) 10% 31,194.50 36,684.00
F Harga Satuan Pekerjaan (D+E) 343,139.50 403,524.00

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 97,790.00 110,066.00


A Tenaga 16,600.00 19,480.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 72,300.00 80,580.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 9,000.00 10,500.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/scratch/469226324.xls 193/77 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 88,900.00 100,060.00
E Overhead & Profit (contoh 10%) 10% 8,890.00 10,006.00
F Harga Satuan Pekerjaan (D+E) 97,790.00 110,066.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 79,706.00 88,390.50
A Tenaga 19,860.00 23,310.00
L.01 0.180 OH Pekerja 70,000.00 85,000.00 12,600.00 15,300.00
L.02 0.020 OH Tukang batu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Kayu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Besi 95,000.00 105,000.00 1,900.00 2,100.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 52,600.00 57,045.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 150.00 175.00
3.0 Kg Besi Beton Polos 9,500.00 10,500.00 28,500.00 31,500.00
0.45 Kg Kawat Beton 18,000.00 20,000.00 8,100.00 9,000.00
4.0 Kg Portland Semen 1,050.00 1,062.50 4,200.00 4,250.00
0.006 m3 Pasir Beton 350,000.00 380,000.00 2,100.00 2,280.00
0.009 m3 Kerikil 330,000.00 360,000.00 2,970.00 3,240.00
C PERALATAN
D Jumlah A + B + C 72,460.00 80,355.00
E Overhead & Profit (contoh 10%) 10% 7,246.00 8,035.50
F Harga Satuan Pekerjaan (D+E) 79,706.00 88,390.50

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 101,134.00 112,424.13
A Tenaga 32,795.00 38,490.00
L.01 0.297 OH Pekerja 70,000.00 85,000.00 20,790.00 25,245.00
L.02 0.033 OH Tukang batu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Kayu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Besi 95,000.00 105,000.00 3,135.00 3,465.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 59,145.00 63,713.75
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
3.6 Kg Besi Beton Polos 9,500.00 10,500.00 34,200.00 37,800.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
5.5 Kg Portland Semen 1,050.00 1,062.50 5,775.00 5,843.75
0.009 m3 Pasir Beton 350,000.00 380,000.00 3,150.00 3,420.00
0.015 m3 Kerikil 330,000.00 360,000.00 4,950.00 5,400.00
C PERALATAN
D Jumlah A + B + C 91,940.00 102,203.75
E Overhead & Profit (contoh 10%) 10% 9,194.00 10,220.38
F Harga Satuan Pekerjaan (D+E) 101,134.00 112,424.13

file:///conversion/tmp/scratch/469226324.xls 193/78 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
UNTUK PRODUKSI PRACETAK BISA DILAKUKAN DI PABRIK (COR DI PLANT) ATAU DI LAPANGAN (CAST IN PLACE). INDEKS YANG ADA DALAM PEDOMAN INI
HANYA UNTUK PEKERJAAN PRODUKSI YANG DILAKUKAN DI LAPANGAN, TERUTAMA UNTUK ANALISA CETAKAN (BEKISTING) PRACETAK BAIK UNTUK
KOMPONEN KOLOM, BALOK DAN PELAT.

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5 Mpa,


1 A.4.1.2.1 1 m2 80,723.87 91,166.01
Slump (120 ± 20) mm K3
A Tenaga 12,250.00 14,540.00
L.01 0.132 OH Pekerja 70,000.00 85,000.00 9,240.00 11,220.00
L.02 0.022 OH Tukang Batu 95,000.00 105,000.00 2,090.00 2,310.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 61,135.33 68,338.19
26.080 Kg Portland Semen 1,050.00 1,062.50 27,384.00 27,710.00
60.800 Kg Pasir Beton 250.00 271.43 15,200.00 16,502.86
82.320 Kg Kerikil (maksimum 30 mm) 222.22 288.89 18,293.33 23,781.33
17.200 ltr Air 15.00 20.00 258.00 344.00
C PERALATAN
D Jumlah A + B + C 73,385.33 82,878.19
E Overhead & Profit (contoh 10%) 10% 7,338.53 8,287.82
F Harga Satuan Pekerjaan (D+E) 80,723.87 91,166.01
10%
Overhead & Profit (contoh 10%)
Pembuatan Lahan Produksi Tebal 10 cm Beton f'c = 14,5 Mpa
2 A.4.1.2.2 1 m2 100,935.08 113,990.51
slum (120 ± 20 ) mm K3
A Tenaga 15,340.00 18,205.00
L.01 0.165 OH Pekerja 70,000.00 85,000.00 11,550.00 14,025.00
L.02 0.028 OH Tukang Batu 95,000.00 105,000.00 2,660.00 2,940.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 76,419.17 85,422.74
32.60 Kg Portland Semen 1,050.00 1,062.50 34,230.00 34,637.50
76.00 kg Pasir Beton 250.00 271.43 19,000.00 20,628.57
102.90 kg Kerikil (maksimum 30 mm) 222.22 288.89 22,866.67 29,726.67
21.50 ltr Air 15.00 20.00 322.50 430.00
C PERALATAN
D Jumlah A + B + C 91,759.17 103,627.74
E Overhead & Profit (contoh 10%) 10% 9,175.92 10,362.77
F Harga Satuan Pekerjaan (D+E) 100,935.08 113,990.51

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5 Mpa,


3 A.4.1.2.3 1 m2 118,489.80 133,603.01
slum (120±20)mm, K3
A Tenaga 16,015.00 18,950.00
L.01 0.165 OH Pekerja 70,000.00 85,000.00 11,550.00 14,025.00
L.02 0.033 OH Tukang Batu 95,000.00 105,000.00 3,135.00 3,465.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 91,703.00 102,507.29
39.120 Kg Portland Semen 1,050.00 1,062.50 41,076.00 41,565.00
91.200 kg Pasir Beton 250.00 271.43 22,800.00 24,754.29
123.480 kg Kerikil (maksimum 30 mm) 222.22 288.89 27,440.00 35,672.00
25.800 ltr Air 15.00 20.00 387.00 516.00
C PERALATAN
D Jumlah A + B + C 107,718.00 121,457.29
E Overhead & Profit (contoh 10%) 10% 10,771.80 12,145.73
F Harga Satuan Pekerjaan (D+E) 118,489.80 133,603.01

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5 Mpa,


4 A.4.1.2.4 1.00 m2 151,386.13 170,972.02
slum (120±20)mm, K3
A Tenaga 22,995.00 27,295.00
L.01 0.248 OH Pekerja 70,000.00 85,000.00 17,360.00 21,080.00
L.02 0.041 OH Tukang Batu 95,000.00 105,000.00 3,895.00 4,305.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 114,628.75 128,134.11
48.900 Kg Portland Semen 1,050.00 1,062.50 51,345.00 51,956.25
114.000 kg Pasir Beton 250.00 271.43 28,500.00 30,942.86
154.350 kg Kerikil (maksimum 30 mm) 222.22 288.89 34,300.00 44,590.00
32.250 ltr Air 15.00 20.00 483.75 645.00
C PERALATAN
D Jumlah A + B + C 137,623.75 155,429.11
E Overhead & Profit (contoh 10%) 10% 13,762.38 15,542.91
F Harga Satuan Pekerjaan (D+E) 151,386.13 170,972.02

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 1 m2 116,469.72 129,528.62
Pakai)
A Tenaga 8,690.00 9,645.00
L.01 0.007 OH Pekerja 70,000.00 85,000.00 490.00 595.00
L.02 0.076 OH Tukang Batu 95,000.00 105,000.00 7,220.00 7,980.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00

file:///conversion/tmp/scratch/469226324.xls 193/79 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 97,191.56 108,108.29
0.008 m3 Lantai Kerja Tebal 10 cm 88,194.94 100,486.06 705.56 803.89
9.394 Kg Besi Hollow (50x50x3) mm 5,500.00 6,000.00 51,667.00 56,364.00
0.005 m3 Kayu Kaso 5/7 5,051,000.00 6,000,000.00 25,255.00 30,000.00
0.080 lbr Phenol film 12 mm 125,000.00 130,000.00 10,000.00 10,400.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
3.882 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 7,764.00 8,540.40
C PERALATAN
D Jumlah A + B + C 105,881.56 117,753.29
E Overhead & Profit (contoh 10%) 10% 10,588.16 11,775.33
F Harga Satuan Pekerjaan (D+E) 116,469.72 129,528.62

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 - 12


6 A.4.1.2.6 1 m2 38,936.00 44,839.60
kali Pakai)
A Tenaga 4,430.00 4,920.00
L.01 0.004 OH Pekerja 70,000.00 85,000.00 280.00 340.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 34,506.00 39,919.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.005 m3 Kayu Kaso 5/7 5,051,000.00 6,000,000.00 25,255.00 30,000.00
0.043 lbr Phenol film 12 mm 125,000.00 130,000.00 5,375.00 5,590.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 38,936.00 44,839.60
E Overhead & Profit (contoh 10%) 10% 3,893.60 4,483.96
F Harga Satuan Pekerjaan (D+E) 42,829.60 49,323.56

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 - 12


7 A.4.1.2.7 1 m2 34,510.00 39,489.60
kali Pakai)
A Tenaga 4,430.00 4,920.00
L.01 0.004 OH Pekerja 70,000.00 85,000.00 280.00 340.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 30,080.00 34,569.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.004 m3 Kayu Kaso 5/7 5,051,000.00 6,000,000.00 20,204.00 24,000.00
0.048 lbr Phenol film 12 mm 125,000.00 130,000.00 6,000.00 6,240.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 34,510.00 39,489.60
E Overhead & Profit (contoh 10%) 10% 3,451.00 3,948.96
F Harga Satuan Pekerjaan (D+E) 37,961.00 43,438.56

Pemasangan dan Membuka Bekisting untuk Komponen Plat


8 A.4.1.2.8 1 bh 5,920.00 6,945.00
Beton Pracetak
A Tenaga 5,920.00 6,945.00
L.01 0.053 OH Pekerja 70,000.00 85,000.00 3,710.00 4,505.00
L.02 0.018 OH Tukang Batu 95,000.00 105,000.00 1,710.00 1,890.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 5,920.00 6,945.00
E Overhead & Profit (contoh 10%) 10% 592.00 694.50
F Harga Satuan Pekerjaan (D+E) 6,512.00 7,639.50

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 1 bh 9,580.00 11,265.00
Balok Beton Pracetak
A Tenaga 9,580.00 11,265.00
L.01 0.089 OH Pekerja 70,000.00 85,000.00 6,230.00 7,565.00
L.02 0.030 OH Tukang Batu 95,000.00 105,000.00 2,850.00 3,150.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 9,580.00 11,265.00
E Overhead & Profit (contoh 10%) 10% 958.00 1,126.50
F Harga Satuan Pekerjaan (D+E) 10,538.00 12,391.50

file:///conversion/tmp/scratch/469226324.xls 193/80 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan dan Membuka Bekisting untuk Komponen
10 A.4.1.2.10 1 bh 7,750.00 9,105.00
Kolom Beton Pracetak
A Tenaga 7,750.00 9,105.00
L.01 0.071 OH Pekerja 70,000.00 85,000.00 4,970.00 6,035.00
L.02 0.024 OH Tukang Batu 95,000.00 105,000.00 2,280.00 2,520.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 7,750.00 9,105.00
E Overhead & Profit (contoh 10%) 10% 775.00 910.50
F Harga Satuan Pekerjaan (D+E) 8,525.00 10,015.50

11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 55,946.00 56,610.00

A Tenaga 50,860.00 56,610.00


L.01 0.064 OH Pekerja 70,000.00 85,000.00 4,480.00 5,440.00
L.02 0.244 OH Tukang Batu 95,000.00 105,000.00 23,180.00 25,620.00
L.02 0.128 OH Tukang Vibrator 95,000.00 105,000.00 12,160.00 13,440.00
L.03 0.034 OH Kapala Tukang 110,000.00 120,000.00 3,740.00 4,080.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 50,860.00 56,610.00
E Overhead & Profit (contoh 10%) 10% 5,086.00 5,661.00
F Harga Satuan Pekerjaan (D+E) 55,946.00 62,271.00

12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 57,530.00 58,235.00

A Tenaga 52,300.00 58,235.00


L.01 0.069 OH Pekerja 70,000.00 85,000.00 4,830.00 5,865.00
L.02 0.242 OH Tukang Batu 95,000.00 105,000.00 22,990.00 25,410.00
L.02 0.138 OH Tukang Vibrator 95,000.00 105,000.00 13,110.00 14,490.00
L.03 0.037 OH Kapala Tukang 110,000.00 120,000.00 4,070.00 4,440.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 52,300.00 58,235.00
E Overhead & Profit (contoh 10%) 10% 5,230.00 5,823.50
F Harga Satuan Pekerjaan (D+E) 57,530.00 64,058.50

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 1 m3 51,727.50 52,350.00
Pracetak
A Tenaga 47,025.00 52,350.00
L.01 0.061 OH Pekerja 70,000.00 85,000.00 4,270.00 5,185.00
L.02 0.213 OH Tukang Batu 95,000.00 105,000.00 20,235.00 22,365.00
L.02 0.122 OH Tukang Vibrator 95,000.00 105,000.00 11,590.00 12,810.00
L.03 0.033 OH Kapala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 47,025.00 52,350.00
E Overhead & Profit (contoh 10%) 10% 4,702.50 5,235.00
F Harga Satuan Pekerjaan (D+E) 51,727.50 57,585.00

14 A.4.1.2.14 1 bh Ereksi Komponen Untuk Plat Pracetak 564,060.20 588,683.92


A Tenaga 40,200.00 45,560.00
L.08 0.067 OH Operator Crane 150,000.00 175,000.00 10,050.00 11,725.00
L.09 0.067 OH Pembantu Operator Crane 95,000.00 105,000.00 6,365.00 7,035.00
L.01 0.067 OH Pekerja 70,000.00 85,000.00 4,690.00 5,695.00
L.02 0.067 OH Tukang Batu 95,000.00 105,000.00 6,365.00 7,035.00
L.02 0.134 OH Tukang Ereksi 95,000.00 105,000.00 12,730.00 14,070.00
L.03 0.067 OH Kepala Tukang 110,000.00 120,000.00 7,370.00 8,040.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00
B Bahan 46,732.00 48,067.20
6.676 Ltr Solar 7,000.00 7,200.00 46,732.00 48,067.20
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 512,782.00 535,167.20
E Overhead & Profit (contoh 10%) 10% 51,278.20 53,516.72
F Harga Satuan Pekerjaan (D+E) 564,060.20 588,683.92

file:///conversion/tmp/scratch/469226324.xls 193/81 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Plat Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Plat Ereksi Plat

1 1.0000 13 1.114
2 1.0000 14 1.134

3 1.0000 15 1.155

4 1.0000 16 1.176
5 1.0000 17 1.197

6 1.0000 18 1.219
7 1.0000 19 1.241

8 1.0180 20 1.264
9 1.0370 21 1.287

10 1.0550 22 1.310
11 1.0750 23 1.334

12 1.0940 24 1.358

15 A.4.1.2.15 1 bh Ereksi Komponen Untuk Balok Pracetak 555,742.00 579,713.20


A Tenaga 36,600.00 41,480.00
L.08 0.061 OH Operator Crane 150,000.00 175,000.00 9,150.00 10,675.00
L.09 0.061 OH Pembantu Operator Crane 95,000.00 105,000.00 5,795.00 6,405.00
L.01 0.061 OH Pekerja 70,000.00 85,000.00 4,270.00 5,185.00
L.02 0.061 OH Tukang Batu 95,000.00 105,000.00 5,795.00 6,405.00
L.02 0.122 OH Tukang Ereksi 95,000.00 105,000.00 11,590.00 12,810.00
L.03 0.061 OH Kepala Tukang 110,000.00 120,000.00 6,710.00 7,320.00
L.04 0.061 OH Mandor 100,000.00 110,000.00 6,100.00 6,710.00
B Bahan 42,770.00 43,992.00
6.110 Ltr Solar 7,000.00 7,200.00 42,770.00 43,992.00
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 505,220.00 527,012.00
E Overhead & Profit (contoh 10%) 10% 50,522.00 52,701.20
F Harga Satuan Pekerjaan (D+E) 555,742.00 579,713.20

Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak


Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok
1 1.0000 13 1.068

2 1.0000 14 1.080
3 1.0000 15 1.092

4 1.0000 16 1.104
5 1.0000 17 1.116

6 1.0000 18 1.129
7 1.0000 19 1.141

8 1.0110 20 1.154
9 1.0220 21 1.166

10 1.0340 22 1.179

11 1.0450 23 1.192
12 1.0570 24 1.206

16 A.4.1.2.16 1 bh Ereksi Komponen Untuk Kolom Pracetak 800,127.90 839,843.84


A Tenaga 49,800.00 56,440.00
L.08 0.083 OH Operator Crane 150,000.00 175,000.00 12,450.00 14,525.00
L.09 0.083 OH Pembantu Operator Crane 95,000.00 105,000.00 7,885.00 8,715.00
L.01 0.083 OH Pekerja 70,000.00 85,000.00 5,810.00 7,055.00
L.02 0.083 OH Tukang Batu 95,000.00 105,000.00 7,885.00 8,715.00
L.02 0.166 OH Tukang Ereksi 95,000.00 105,000.00 15,770.00 17,430.00
L.03 0.083 OH Kepala Tukang 110,000.00 120,000.00 9,130.00 9,960.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 57,939.00 59,594.40
8.277 Ltr Solar 7,000.00 7,200.00 57,939.00 59,594.40
C PERALATAN 619,650.00 647,460.00
0.083 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 377,650.00 383,460.00
2.200 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 242,000.00 264,000.00
D Jumlah A + B + C 727,389.00 763,494.40
E Overhead & Profit (contoh 10%) 10% 72,738.90 76,349.44
F Harga Satuan Pekerjaan (D+E) 800,127.90 839,843.84

file:///conversion/tmp/scratch/469226324.xls 193/82 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok

1 1.0000 13 1.162
2 1.0000 14 1.191

3 1.0000 15 1.221

4 1.0000 16 1.252
5 1.0000 17 1.284

6 1.0000 18 1.318
7 1.0000 19 1.350

8 1.0250 20 1.384
9 1.0510 21 1.419

10 1.0780 22 1.455
11 1.1050 23 1.492

12 1.1330 24 1.530

17 A.4.1.2.17 1 bh Langsiran Komponen untuk Plat Pracetak (± 20 m) 147,134.90 154,493.24


A Tenaga 34,030.00 39,010.00
L.08 0.083 OH Operator Crane 150,000.00 175,000.00 12,450.00 14,525.00
L.09 0.083 OH Pembantu Operator Crane 95,000.00 105,000.00 7,885.00 8,715.00
L.01 0.083 OH Pekerja 70,000.00 85,000.00 5,810.00 7,055.00
L.02 0.083 OH Tukang Batu 95,000.00 105,000.00 7,885.00 8,715.00
B Bahan 13,279.00 13,658.40
1.897 Ltr Solar 7,000.00 7,200.00 13,279.00 13,658.40
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 133,759.00 140,448.40
E Overhead & Profit (contoh 10%) 10% 13,375.90 14,044.84
F Harga Satuan Pekerjaan (D+E) 147,134.90 154,493.24

18 A.4.1.2.18 1 bh Langsiran Komponen untuk Balok Pracetak (± 20 m) 120,256.40 123,599.74


A Tenaga 9,595.00 10,925.00
L.08 0.019 OH Operator Crane 150,000.00 175,000.00 2,850.00 3,325.00
L.09 0.019 OH Pembantu Operator Crane 95,000.00 105,000.00 1,805.00 1,995.00
L.01 0.019 OH Pekerja 70,000.00 85,000.00 1,330.00 1,615.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
B Bahan 13,279.00 13,658.40
1.897 Ltr Solar 7,000.00 7,200.00 13,279.00 13,658.40
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 109,324.00 112,363.40
E Overhead & Profit (contoh 10%) 10% 10,932.40 11,236.34
F Harga Satuan Pekerjaan (D+E) 120,256.40 123,599.74

19 A.4.1.2.19 1 bh Langsiran Komponen untuk Kolom Pracetak (± 20 m) 120,256.40 123,599.74


A Tenaga 9,595.00 10,925.00
L.08 0.019 OH Operator Crane 150,000.00 175,000.00 2,850.00 3,325.00
L.09 0.019 OH Pembantu Operator Crane 95,000.00 105,000.00 1,805.00 1,995.00
L.01 0.019 OH Pekerja 70,000.00 85,000.00 1,330.00 1,615.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
B Bahan 13,279.00 13,658.40
1.897 Ltr Solar 7,000.00 7,200.00 13,279.00 13,658.40
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 109,324.00 112,363.40
E Overhead & Profit (contoh 10%) 10% 10,932.40 11,236.34
F Harga Satuan Pekerjaan (D+E) 120,256.40 123,599.74

20 A.4.1.2.20 1 m3 Bahan Grout Campuran 3,415,775.00 3,687,200.00


A Tenaga - -

B Bahan 3,105,250.00 3,352,000.00


1,200 Kg Semen Grout 1,500.00 1,650.00 1,800,000.00 1,980,000.00
650 kg Screening 2,000.00 2,100.00 1,300,000.00 1,365,000.00
350 Ltr Air 15.00 20.00 5,250.00 7,000.00
C PERALATAN - -
D Jumlah A + B + C 3,105,250.00 3,352,000.00
E Overhead & Profit (contoh 10%) 10% 310,525.00 335,200.00
F Harga Satuan Pekerjaan (D+E) 3,415,775.00 3,687,200.00

file:///conversion/tmp/scratch/469226324.xls 193/83 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.1.2.21 1 m3 Bahan Grout Campuran (tidak Campuran) 3,059,100.00 3,366,550.00
A Tenaga - -

B Bahan 2,781,000.00 3,060,500.00


1,850 Kg Semen Grout 1,500.00 1,650.00 2,775,000.00 3,052,500.00
400 Ltr Air 15.00 20.00 6,000.00 8,000.00
C PERALATAN - -
D Jumlah A + B + C 2,781,000.00 3,060,500.00
E Overhead & Profit (contoh 10%) 10% 278,100.00 306,050.00
F Harga Satuan Pekerjaan (D+E) 3,059,100.00 3,366,550.00

22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 51,375.50 56,633.50
A Tenaga 46,705.00 51,485.00
L.02 0.367 OH Tukang Batu 95,000.000 105,000.000 34,865.000 38,535.000
L.03 0.074 OH Kepala Tukang 110,000.000 120,000.000 8,140.000 8,880.000
L.04 0.037 OH Mandor 100,000.000 110,000.000 3,700.000 4,070.000

B Bahan - -

C PERALATAN - -
D Jumlah A + B + C 46,705.00 51,485.00
E Overhead & Profit (contoh 10%) 10% 4,670.50 5,148.50
F Harga Satuan Pekerjaan (D+E) 51,375.50 56,633.50

23 A.4.1.2.23 1 ttk Pemasangan Bekisting Joint Pra Cetak 109,754.70 129,470.00


A Tenaga 26,405.00 30,280.00
L.01 0.147 OH Pekerja 70,000.00 85,000.00 10,290.000 12,495.000
L.02 0.147 OH Tukang Batu 95,000.000 105,000.000 13,965.000 15,435.000
L.03 0.015 OH Kepala Tukang 110,000.000 120,000.000 1,650.000 1,800.000
L.04 0.005 OH Mandor 100,000.000 110,000.000 500.000 550.000
B Bahan 73,372.00 87,420.00
0.012 m3 Kayu Kaso 5/7 5,051,000.00 6,000,000.00 60,612.00 72,000.00
0.004 m3 Papan Cor 2,200,000.00 2,700,000.00 8,800.00 10,800.00
0.264 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 3,960.00 4,620.00
C PERALATAN - -
D Jumlah A + B + C 99,777.00 117,700.00
E Overhead & Profit (contoh 10%) 10% 9,977.70 11,770.00
F Harga Satuan Pekerjaan (D+E) 109,754.70 129,470.00

24 A.4.1.2.24 1 ttk Upah Pemasangan Joint dengan Sling 43,439.00 49,852.00


A Tenaga 39,490.00 45,320.00
L.01 0.220 OH Pekerja 70,000.00 85,000.00 15,400.000 18,700.000
L.02 0.022 OH Tukang Batu 95,000.000 105,000.000 2,090.000 2,310.000
L.02 0.220 OH Tukang Besi 95,000.000 105,000.000 20,900.000 23,100.000
L.04 0.011 OH Mandor 100,000.000 110,000.000 1,100.000 1,210.000
B Bahan

C PERALATAN - -
D Jumlah A + B + C 39,490.00 45,320.00
E Overhead & Profit (contoh 10%) 10% 3,949.00 4,532.00
F Harga Satuan Pekerjaan (D+E) 43,439.00 49,852.00

file:///conversion/tmp/scratch/469226324.xls 193/84 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 29,023.50 32,037.50
A Tenaga 10,860.00 12,450.00
L.01 0.06 OH Pekerja 70,000.00 85,000.00 4,200.00 5,100.00
L.02 0.06 OH Tukang Besi 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 15,525.00 16,675.00
1.15 Kg Besi Profil 13,500.00 14,500.00 15,525.00 16,675.00
C PERALATAN
D Jumlah A + B + C 26,385.00 29,125.00
E Overhead & Profit (contoh 10%) 10% 2,638.50 2,912.50
F Harga Satuan Pekerjaan (D+E) 29,023.50 32,037.50

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 21,433.50 23,815.00


A Tenaga 10,860.00 12,450.00
L.01 0.06 OH Pekerja 70,000.00 85,000.00 4,200.00 5,100.00
L.02 0.06 OH Tukang Besi 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 8,625.00 9,200.00
1.15 kg Besi Baja IWF 7,500.00 8,000.00 8,625.00 9,200.00
C PERALATAN
D Jumlah A + B + C 19,485.00 21,650.00
E Overhead & Profit (contoh 10%) 10% 1,948.50 2,165.00
F Harga Satuan Pekerjaan (D+E) 21,433.50 23,815.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 96,646.00 113,707.00


A Tenaga 17,110.00 19,670.00
L.01 0.100 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.100 OH Tukang Besi 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 120,000.00 110.00 120.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 10,750.00 11,700.00
1 ltr Solar 7,000.00 7,200.00 7,000.00 7,200.00
0.1 ltr Minyak Pelumas 37,500.00 45,000.00 3,750.00 4,500.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 87,860.00 103,370.00
E Overhead & Profit (contoh 10%) 10% 8,786.00 10,337.00
F Harga Satuan Pekerjaan (D+E) 96,646.00 113,707.00

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 804,815.00 880,022.00
rangka baja Siku
A Tenaga 190,000.00 217,820.00
L.01 1.05 OH Pekerja 70,000.00 85,000.00 73,500.00 89,250.00
L.02 1.05 OH Tukang Besi 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.052 OH Mandor 100,000.00 110,000.00 5,200.00 5,720.00
B Bahan 541,650.00 582,200.00
15 Kg Besi Siku L.30.30.3 7,500.00 8,000.00 112,500.00 120,000.00
32.8 Kg Besi Plat Baja 13,000.00 14,000.00 426,400.00 459,200.00
0.05 Kg Kawat Las 55,000.00 60,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 731,650.00 800,020.00
E Overhead & Profit (contoh 10%) 10% 73,165.00 80,002.00
F Harga Satuan Pekerjaan (D+E) 804,815.00 880,022.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 22,473.00 26,461.60


A Tenaga 5,120.00 5,960.00
L.01 0.04 OH Pekerja 70,000.00 85,000.00 2,800.00 3,400.00
L.02 0.02 OH Tukang Besi 95,000.00 105,000.00 1,900.00 2,100.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 2,560.00 2,796.00
0.04 kg Kawat Las 55,000.00 60,000.00 2,200.00 2,400.00
0.03 ltr Solar 7,000.00 7,200.00 210.00 216.00
0.004 ltr Minyak Pelumas 37,500.00 45,000.00 150.00 180.00

file:///conversion/tmp/scratch/469226324.xls 193/85 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 20,430.00 24,056.00
E Overhead & Profit (contoh 10%) 10% 2,043.00 2,405.60
F Harga Satuan Pekerjaan (D+E) 22,473.00 26,461.60

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 219,903.20 255,343.22


A Tenaga 117,600.00 134,820.00
L.01 0.65 OH Pekerja 70,000.00 85,000.00 45,500.00 55,250.00
L.02 0.65 OH Tukang Las Biasa 95,000.00 105,000.00 61,750.00 68,250.00
L.03 0.065 OH Kepala Tukang 110,000.00 120,000.00 7,150.00 7,800.00
L.04 0.032 OH Mandor 100,000.00 110,000.00 3,200.00 3,520.00
B Bahan 82,312.00 97,310.20
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,247.30 2,646.16 44,946.00 52,923.20
C PERALATAN
D Jumlah A + B + C 199,912.00 232,130.20
E Overhead & Profit (contoh 10%) 10% 19,991.20 23,213.02
F Harga Satuan Pekerjaan (D+E) 219,903.20 255,343.22

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 562,980.00 624,866.00


A Tenaga 211,800.00 243,060.00
L.01 1.2 OH Pekerja 70,000.00 85,000.00 84,000.00 102,000.00
L.02 1.2 OH Tukang Besi 95,000.00 105,000.00 114,000.00 126,000.00
L.03 0.12 OH Kepala Tukang 110,000.00 120,000.00 13,200.00 14,400.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 300,000.00 325,000.00
1 m2 Pintu Gulung Besi 300,000.00 325,000.00 300,000.00 325,000.00
C PERALATAN
D Jumlah A + B + C 511,800.00 568,060.00
E Overhead & Profit (contoh 10%) 10% 51,180.00 56,806.00
F Harga Satuan Pekerjaan (D+E) 562,980.00 624,866.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 505,604.00 567,930.00


A Tenaga 79,640.00 91,300.00
L.01 0.44 OH Pekerja 70,000.00 85,000.00 30,800.00 37,400.00
L.02 0.44 OH Tukang Besi 95,000.00 105,000.00 41,800.00 46,200.00
L.03 0.044 OH Kepala Tukang 110,000.00 120,000.00 4,840.00 5,280.00
L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00
B Bahan 380,000.00 425,000.00
1 m2 Pintu Lipat 380,000.00 425,000.00 380,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 459,640.00 516,300.00
E Overhead & Profit (contoh 10%) 10% 45,964.00 51,630.00
F Harga Satuan Pekerjaan (D+E) 505,604.00 567,930.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 440,880.00 495,924.00


A Tenaga 90,800.00 100,840.00
L.01 0.08 OH Pekerja 70,000.00 85,000.00 5,600.00 6,800.00
L.02 0.8 OH Tukang Besi 95,000.00 105,000.00 76,000.00 84,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 120,000.00 8,800.00 9,600.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 310,000.00 350,000.00
1 m2 Sunscreen Allumunium 310,000.00 350,000.00 310,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 400,800.00 450,840.00
E Overhead & Profit (contoh 10%) 10% 40,080.00 45,084.00
F Harga Satuan Pekerjaan (D+E) 440,880.00 495,924.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 452,100.00 530,750.00


A Tenaga 181,000.00 207,500.00
L.01 1 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 1 OH Tukang Besi 95,000.00 105,000.00 95,000.00 105,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 120,000.00 11,000.00 12,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

file:///conversion/tmp/scratch/469226324.xls 193/86 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 230,000.00 275,000.00


1 m2 Rolling Allumunium 230,000.00 275,000.00 230,000.00 275,000.00
C PERALATAN
D Jumlah A + B + C 411,000.00 482,500.00
E Overhead & Profit (contoh 10%) 10% 41,100.00 48,250.00
F Harga Satuan Pekerjaan (D+E) 452,100.00 530,750.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 110,305.80 118,378.70


A Tenaga 7,778.00 8,917.00
L.01 0.043 OH Pekerja 70,000.00 85,000.00 3,010.00 3,655.00
L.02 0.043 OH Tukang Besi 95,000.00 105,000.00 4,085.00 4,515.00
L.03 0.0043 OH Kepala Tukang 110,000.00 120,000.00 473.00 516.00
L.04 0.0021 OH Mandor 100,000.00 110,000.00 210.00 231.00
B Bahan 92,500.00 98,700.00
1.1 m' Profil Allumunium 80,000.00 85,000.00 88,000.00 93,500.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 100,278.00 107,617.00
E Overhead & Profit (contoh 10%) 10% 10,027.80 10,761.70
F Harga Satuan Pekerjaan (D+E) 110,305.80 118,378.70

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 476,388.00 511,095.20


A Tenaga 15,380.00 17,632.00
L.01 0.085 OH Pekerja 70,000.00 85,000.00 5,950.00 7,225.00
L.02 0.085 OH Tukang Besi 95,000.00 105,000.00 8,075.00 8,925.00
L.03 0.0085 OH Kepala Tukang 110,000.00 120,000.00 935.00 1,020.00
L.04 0.0042 OH Mandor 100,000.00 110,000.00 420.00 462.00
B Bahan 417,700.00 447,000.00
4.4 m' Profil Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 433,080.00 464,632.00
E Overhead & Profit (contoh 10%) 10% 43,308.00 46,463.20
F Harga Satuan Pekerjaan (D+E) 476,388.00 511,095.20

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 443,866.50 478,478.00


A Tenaga 15,515.00 17,780.00
L.01 0.085 OH Pekerja 70,000.00 85,000.00 5,950.00 7,225.00
L.02 0.085 OH Tukang Besi 95,000.00 105,000.00 8,075.00 8,925.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 388,000.00 417,200.00
4.4 m' Pintu Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 403,515.00 434,980.00
E Overhead & Profit (contoh 10%) 10% 40,351.50 43,498.00
F Harga Satuan Pekerjaan (D+E) 443,866.50 478,478.00

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 174,240.00 189,948.00


A Tenaga 63,400.00 72,680.00
L.01 0.35 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.35 OH Tukang Besi 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 158,400.00 172,680.00
E Overhead & Profit (contoh 10%) 10% 15,840.00 17,268.00
F Harga Satuan Pekerjaan (D+E) 174,240.00 189,948.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 487,715.67 555,066.61


A Tenaga 302,220.00 346,470.00
L.01 1.67 OH Pekerja 70,000.00 85,000.00 116,900.00 141,950.00
L.02 1.67 OH Tukang Las 95,000.00 105,000.00 158,650.00 175,350.00
L.03 0.167 OH Kepala Tukang 110,000.00 120,000.00 18,370.00 20,040.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00

file:///conversion/tmp/scratch/469226324.xls 193/87 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 141,157.88 158,136.01


6.177 kg Besi Strip 13,000.00 14,000.00 80,301.00 86,478.00
27.08 cm Pengelasan 2,247.30 2,646.16 60,856.88 71,658.01
C PERALATAN
D Jumlah A + B + C 443,377.88 504,606.01
E Overhead & Profit (contoh 10%) 10% 44,337.79 50,460.60
F Harga Satuan Pekerjaan (D+E) 487,715.67 555,066.61

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 93,693.05 111,840.12


A Tenaga 18,100.00 20,750.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.1 OH Tukang 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 67,075.50 80,922.84
1.1 m2 Kawat Nyamuk nylon 18,000.00 25,000.00 19,800.00 27,500.00
11.11 cm Pengelasan 2,247.30 2,646.16 24,967.50 29,398.84
1.716 kg Baja Strip (0,2x2) cm 13,000.00 14,000.00 22,308.00 24,024.00
C PERALATAN
D Jumlah A + B + C 85,175.50 101,672.84
E Overhead & Profit (contoh 10%) 10% 8,517.55 10,167.28
F Harga Satuan Pekerjaan (D+E) 93,693.05 111,840.12

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 122,155.00 135,861.00


A Tenaga 35,300.00 40,510.00
L.01 0.2 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 75,750.00 83,000.00
1.1 m2 Jendela Nako 32,500.00 35,000.00 35,750.00 38,500.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 111,050.00 123,510.00
E Overhead & Profit (contoh 10%) 10% 11,105.00 12,351.00
F Harga Satuan Pekerjaan (D+E) 122,155.00 135,861.00

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 184,992.50 217,126.25
cm
A Tenaga 55,750.00 63,100.00
L.01 0.20 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.4 OH Tukang Kayu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 112,425.00 134,287.50
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 225.00 262.50
0.019 m3 Kayu Papan Klas II atau III 4,800,000.00 5,700,000.00 91,200.00 108,300.00
C PERALATAN
D Jumlah A + B + C 168,175.00 197,387.50
E Overhead & Profit (contoh 10%) 10% 16,817.50 19,738.75
F Harga Satuan Pekerjaan (D+E) 184,992.50 217,126.25

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 69,245.00 80,751.00
BJLS 30 Lebar 45 cm
A Tenaga 35,300.00 40,510.00
L.01 0.20 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.20 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 27,650.00 32,900.00
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 150.00 175.00
0.5 Kg Besi strip 13,000.00 14,000.00 6,500.00 7,000.00
C PERALATAN
D Jumlah A + B + C 62,950.00 73,410.00
E Overhead & Profit (contoh 10%) 10% 6,295.00 7,341.00
F Harga Satuan Pekerjaan (D+E) 69,245.00 80,751.00

file:///conversion/tmp/scratch/469226324.xls 193/88 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 111,430.00 122,573.00
60x120 cm dinding partisi
A Tenaga 45,300.00 51,930.00
L.01 0.250 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.250 OH Tukang Besi 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 101,300.00 111,430.00
E Overhead & Profit (contoh 10%) 10% 10,130.00 11,143.00
F Harga Satuan Pekerjaan (D+E) 111,430.00 122,573.00

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 140,140.00 154,748.00
60x60 cm dinding plafond
A Tenaga 63,400.00 72,680.00
L.01 0.350 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.350 OH Tukang Besi 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 127,400.00 140,680.00
E Overhead & Profit (contoh 10%) 10% 12,740.00 14,068.00
F Harga Satuan Pekerjaan (D+E) 140,140.00 154,748.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 205,293.83 231,071.78
dingin Profil C75
A Tenaga 132,840.00 152,290.00
L.01 0.734 OH Pekerja 70,000.00 85,000.00 51,380.00 62,390.00
L.02 0.734 OH Tukang Besi 95,000.00 105,000.00 69,730.00 77,070.00
L.03 0.073 OH Kepala Tukang 110,000.00 120,000.00 8,030.00 8,760.00
L.04 0.037 OH Mandor 100,000.00 110,000.00 3,700.00 4,070.00
B Bahan 49,653.00 53,331.00
3.065 kg Baja Ringan Canal Dingin C75 13,500.00 14,500.00 41,377.50 44,442.50
C PERALATAN 4,137.75 4,444.25
10 % Peralatan *) harga bahan 41,377.50 44,442.50 4,137.75 4,444.25
D Jumlah A + B + C 186,630.75 210,065.25
E Overhead & Profit (contoh 10%) 10% 18,663.08 21,006.53
F Harga Satuan Pekerjaan (D+E) 205,293.83 231,071.78

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 229,573.85 257,530.35
Profil C75
A Tenaga 137,626.00 157,776.00
L.01 0.7604 OH Pekerja 70,000.00 85,000.00 53,228.00 64,634.00
L.02 0.7604 OH Tukang Besi 95,000.00 105,000.00 72,238.00 79,842.00
L.03 0.0760 OH Kepala Tukang 110,000.00 120,000.00 8,360.00 9,120.00
L.04 0.0380 OH Mandor 100,000.00 110,000.00 3,800.00 4,180.00
B Bahan 65,610.00 70,470.00
4.05 kg Baja Ringan Canal Dingin C75 13,500.00 14,500.00 54,675.00 58,725.00
C PERALATAN 5,467.50 5,872.50
10 % Peralatan *) harga bahan 54,675.00 58,725.00 5,467.50 5,872.50
D Jumlah A + B + C 208,703.50 234,118.50
E Overhead & Profit (contoh 10%) 10% 20,870.35 23,411.85
F Harga Satuan Pekerjaan (D+E) 229,573.85 257,530.35

file:///conversion/tmp/scratch/469226324.xls 193/89 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 242,742.50 268,970.63
Tebal 1 bata Camp. 1SP: 2PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 154,475.00 166,818.75
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
43.5 Kg Portland Semen (PC) 1,050.00 1,062.50 45,675.00 46,218.75
0.08 m3 Pasir Pasang (PP) 310,000.00 370,000.00 24,800.00 29,600.00
C PERALATAN
D Jumlah A + B + C 220,675.00 244,518.75
E Overhead & Profit (contoh 10%) 10% 22,067.50 24,451.88
F Harga Satuan Pekerjaan (D+E) 242,742.50 268,970.63
Overhead & Profit (contoh 10%)
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
2 A.4.4.1.2 1 m2 234,308.25 261,117.31
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 146,807.50 159,679.38
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
32.95 Kg Portland Semen (PC) 1,050.00 1,062.50 34,597.50 35,009.38
0.091 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,210.00 33,670.00
C PERALATAN
D Jumlah A + B + C 213,007.50 237,379.38
E Overhead & Profit (contoh 10%) 10% 21,300.75 23,737.94
F Harga Satuan Pekerjaan (D+E) 234,308.25 261,117.31

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 227,598.25 254,451.31
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 140,707.50 153,619.38
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
26.55 Kg Portland Semen (PC) 1,050.00 1,062.50 27,877.50 28,209.38
0.093 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,830.00 34,410.00
C PERALATAN
D Jumlah A + B + C 206,907.50 231,319.38
E Overhead & Profit (contoh 10%) 10% 20,690.75 23,131.94
F Harga Satuan Pekerjaan (D+E) 227,598.25 254,451.31

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 225,643.00 253,030.25
Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 138,930.00 152,327.50
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
22.2 Kg Portland Semen (PC) 1,050.00 1,062.50 23,310.00 23,587.50
0.102 m3 Pasir Pasang (PP) 310,000.00 370,000.00 31,620.00 37,740.00
C PERALATAN
D Jumlah A + B + C 205,130.00 230,027.50
E Overhead & Profit (contoh 10%) 10% 20,513.00 23,002.75
F Harga Satuan Pekerjaan (D+E) 225,643.00 253,030.25

file:///conversion/tmp/scratch/469226324.xls 193/90 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 228,189.50 256,845.88
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 141,245.00 155,796.25
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
18.5 Kg Portland Semen (PC) 1,050.00 1,062.50 19,425.00 19,656.25
0.122 m3 Pasir Pasang (PP) 310,000.00 370,000.00 37,820.00 45,140.00
C PERALATAN
D Jumlah A + B + C 207,445.00 233,496.25
E Overhead & Profit (contoh 10%) 10% 20,744.50 23,349.63
F Harga Satuan Pekerjaan (D+E) 228,189.50 256,845.88

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 217,479.90 244,376.00
Tebal 1 Bata Camp. 1SP : 3 KP :10PP
A Tenaga 66,200.00 77,700.00
L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 131,509.00 144,460.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
10.08 Kg Portland Semen (PC) 1,050.00 1,062.50 10,584.00 10,710.00
0.0925 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,675.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 197,709.00 222,160.00
E Overhead & Profit (contoh 10%) 10% 19,770.90 22,216.00
F Harga Satuan Pekerjaan (D+E) 217,479.90 244,376.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 117,455.25 130,398.81
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 73,677.50 79,694.38
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
18.95 Kg Portland Semen 1,050.00 1,062.50 19,897.50 20,134.38
0.038 m3 Pasir Pasang 310,000.00 370,000.00 11,780.00 14,060.00
C PERALATAN
D Jumlah A + B + C 106,777.50 118,544.38
E Overhead & Profit (contoh 10%) 10% 10,677.75 11,854.44
F Harga Satuan Pekerjaan (D+E) 117,455.25 130,398.81

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 112,847.35 125,859.94
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 69,488.50 75,568.13
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
14.37 Kg Portland Semen 1,050.00 1,062.50 15,088.50 15,268.13
0.04 m3 Pasir Pasang 310,000.00 370,000.00 12,400.00 14,800.00

file:///conversion/tmp/scratch/469226324.xls 193/91 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 102,588.50 114,418.13
E Overhead & Profit (contoh 10%) 10% 10,258.85 11,441.81
F Harga Satuan Pekerjaan (D+E) 112,847.35 125,859.94

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 110,555.50 123,726.63
Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 67,405.00 73,628.75
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
11.50 Kg Portland Semen 1,050.00 1,062.50 12,075.00 12,218.75
0.043 m3 Pasir Pasang 310,000.00 370,000.00 13,330.00 15,910.00
C PERALATAN
D Jumlah A + B + C 100,505.00 112,478.75
E Overhead & Profit (contoh 10%) 10% 10,050.50 11,247.88
F Harga Satuan Pekerjaan (D+E) 110,555.50 123,726.63

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 109,135.40 122,413.50
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 66,114.00 72,435.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
9.68 Kg Portland Semen 1,050.00 1,062.50 10,164.00 10,285.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 99,214.00 111,285.00
E Overhead & Profit (contoh 10%) 10% 9,921.40 11,128.50
F Harga Satuan Pekerjaan (D+E) 109,135.40 122,413.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 108,928.60 122,452.00
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 65,926.00 72,470.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
8.32 Kg Portland Semen 1,050.00 1,062.50 8,736.00 8,840.00
0.049 m3 Pasir Pasang 310,000.00 370,000.00 15,190.00 18,130.00
C PERALATAN
D Jumlah A + B + C 99,026.00 111,320.00
E Overhead & Profit (contoh 10%) 10% 9,902.60 11,132.00
F Harga Satuan Pekerjaan (D+E) 108,928.60 122,452.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 107,167.50 120,731.88
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 64,325.00 70,906.25
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
6.50 Kg Portland Semen 1,050.00 1,062.50 6,825.00 6,906.25
0.05 m3 Pasir Pasang 310,000.00 370,000.00 15,500.00 18,500.00

file:///conversion/tmp/scratch/469226324.xls 193/92 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 97,425.00 109,756.25
E Overhead & Profit (contoh 10%) 10% 9,742.50 10,975.63
F Harga Satuan Pekerjaan (D+E) 107,167.50 120,731.88

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 109,807.50 123,509.38
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 66,725.00 73,431.25
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
4.5 Kg Portland Semen 1,050.00 1,062.50 4,725.00 4,781.25
0.05 m3 Pasir Pasang 310,000.00 370,000.00 15,500.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 99,825.00 112,281.25
E Overhead & Profit (contoh 10%) 10% 9,982.50 11,228.13
F Harga Satuan Pekerjaan (D+E) 109,807.50 123,509.38

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 98,648.00 110,209.00
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 56,580.00 61,340.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.018 m3 Semen Merah 200,000.00 200,000.00 3,600.00 3,600.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 89,680.00 100,190.00
E Overhead & Profit (contoh 10%) 10% 8,968.00 10,019.00
F Harga Satuan Pekerjaan (D+E) 98,648.00 110,209.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 99,858.00 112,035.00
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 57,680.00 63,000.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.014 m3 Semen Merah 200,000.00 200,000.00 2,800.00 2,800.00
0.028 m3 Pasir Pasang 310,000.00 370,000.00 8,680.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 90,780.00 101,850.00
E Overhead & Profit (contoh 10%) 10% 9,078.00 10,185.00
F Harga Satuan Pekerjaan (D+E) 99,858.00 112,035.00

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 387,613.60 447,612.00
A Tenaga 42,200.00 49,280.00
L.01 0.350 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

file:///conversion/tmp/scratch/469226324.xls 193/93 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 310,176.00 357,640.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,050.00 1,062.50 31,836.00 32,215.00
0.728 m3 Pasir Pasang 310,000.00 370,000.00 225,680.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 352,376.00 406,920.00
E Overhead & Profit (contoh 10%) 10% 35,237.60 40,692.00
F Harga Satuan Pekerjaan (D+E) 387,613.60 447,612.00

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 395,618.30 458,437.38
A Tenaga 42,200.00 49,280.00
L.01 0.350 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

B Bahan 317,453.00 367,481.25


12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,050.00 1,062.50 25,473.00 25,776.25
0.772 m3 Pasir Pasang 310,000.00 370,000.00 239,320.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 359,653.00 416,761.25
E Overhead & Profit (contoh 10%) 10% 35,965.30 41,676.13
F Harga Satuan Pekerjaan (D+E) 395,618.30 458,437.38

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 305,257.70 351,836.38
A Tenaga 36,720.00 43,000.00
L.01 0.320 OH Pekerja 70,000.00 85,000.00 22,400.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 240,787.00 276,851.25
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,050.00 1,062.50 23,877.00 24,161.25
0.550 m3 Pasir Pasang 310,000.00 370,000.00 170,500.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 277,507.00 319,851.25
E Overhead & Profit (contoh 10%) 10% 27,750.70 31,985.13
F Harga Satuan Pekerjaan (D+E) 305,257.70 351,836.38

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 310,926.00 359,554.25
A Tenaga 36,720.00 43,000.00
L.01 0.320 OH Pekerja 70,000.00 85,000.00 22,400.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 245,940.00 283,867.50
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,050.00 1,062.50 19,110.00 19,337.50
0.582 m3 Pasir Pasang 310,000.00 370,000.00 180,420.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 282,660.00 326,867.50
E Overhead & Profit (contoh 10%) 10% 28,266.00 32,686.75
F Harga Satuan Pekerjaan (D+E) 310,926.00 359,554.25

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 249,719.80 287,460.25
A Tenaga 33,100.00 38,850.00
L.01 0.300 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

file:///conversion/tmp/scratch/469226324.xls 193/94 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 193,918.00 222,477.50
12.500 buah Batako 5,000.00 5,500.00 62,500.00 68,750.00
15.160 kg PC 1,050.00 1,062.50 15,918.00 16,107.50
0.364 m3 Pasir Pasang 310,000.00 370,000.00 112,840.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 227,018.00 261,327.50
E Overhead & Profit (contoh 10%) 10% 22,701.80 26,132.75
F Harga Satuan Pekerjaan (D+E) 249,719.80 287,460.25

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 254,404.15 293,686.94
A Tenaga 33,100.00 38,850.00
L.01 0.300 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

B Bahan 198,176.50 228,138.13


12.500 buah Batako 5,000.00 5,500.00 62,500.00 68,750.00
12.130 kg PC 1,050.00 1,062.50 12,736.50 12,888.13
0.388 m3 Pasir Pasang 310,000.00 370,000.00 120,280.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 231,276.50 266,988.13
E Overhead & Profit (contoh 10%) 10% 23,127.65 26,698.81
F Harga Satuan Pekerjaan (D+E) 254,404.15 293,686.94

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 308,550.00 465,836.25
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 247,400.00 384,637.50
30 Buah Terawang / Roster 7,500.00 12,000.00 225,000.00 360,000.00
11 kg Portland Semen 1,050.00 1,062.50 11,550.00 11,687.50
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 280,500.00 423,487.50
E Overhead & Profit (contoh 10%) 10% 28,050.00 42,348.75
F Harga Satuan Pekerjaan (D+E) 308,550.00 465,836.25

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 308,550.00 465,836.25
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 247,400.00 384,637.50
30 Buah Terawang / Roster 7,500.00 12,000.00 225,000.00 360,000.00
11 kg Portland Semen 1,050.00 1,062.50 11,550.00 11,687.50
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 280,500.00 423,487.50
E Overhead & Profit (contoh 10%) 10% 28,050.00 42,348.75
F Harga Satuan Pekerjaan (D+E) 308,550.00 465,836.25

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 140,492.00 152,971.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 33,100.00 38,850.00
L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

file:///conversion/tmp/scratch/469226324.xls 193/95 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 94,620.00 100,215.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,050.00 1,062.50 14,700.00 14,875.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 127,720.00 139,065.00
E Overhead & Profit (contoh 10%) 10% 12,772.00 13,906.50
F Harga Satuan Pekerjaan (D+E) 140,492.00 152,971.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 262,648.54 291,571.56
Mortar Siap Pakai
m2 Tenaga 0.075 185,000.00 209,380.00
L.01 0.67 OH Pekerja 0.12 725000 70,000.00 85,000.00 46,900.00 56,950.00
L.02 1.3 OH Tukang Batu 1 6525 95,000.00 105,000.00 123,500.00 136,500.00
L.03 0.13 OH Kepala Tukang 13.3333333333333 110,000.00 120,000.00 14,300.00 15,600.00
L.04 0.003 OH Mandor 111.111111111111 100,000.00 110,000.00 300.00 330.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 238,771.40 265,065.05
E Overhead & Profit (contoh 10%) 10% 23,877.14 26,506.51
F Harga Satuan Pekerjaan (D+E) 262,648.54 291,571.56

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 265,774.74 292,711.71
Mortar Siap Pakai
m2 Tenaga 0.075 172,200.00 195,425.00
L.01 0.671 OH Pekerja 0.12 700000 70,000.00 85,000.00 46,970.00 57,035.00
L.02 1.300 OH Tukang Batu 0.1 8400 95,000.00 105,000.00 123,500.00 136,500.00
L.03 0.013 OH Kepala Tukang 10 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.003 OH Mandor 83.3333333333333 100,000.00 110,000.00 300.00 330.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 241,613.40 266,101.55
E Overhead & Profit (contoh 10%) 10% 24,161.34 26,610.16
F Harga Satuan Pekerjaan (D+E) 265,774.74 292,711.71

file:///conversion/tmp/scratch/469226324.xls 193/96 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 65,603.12 73,802.30
A Tenaga 38,400.00 44,700.00
L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 21,239.20 22,393.00
15.504 Kg Portland Semen 1,050.00 1,062.50 16,279.20 16,473.00
0.016 m3 Pasir Pasang 310,000.00 370,000.00 4,960.00 5,920.00
C PERALATAN
D Jumlah A + B + C 59,639.20 67,093.00
E Overhead & Profit (contoh 10%) 10% 5,963.92 6,709.30
F Harga Satuan Pekerjaan (D+E) 65,603.12 73,802.30
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 60,868.72 69,259.30
A Tenaga 38,400.00 44,700.00
L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00


L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 16,935.20 18,263.00
10.224 Kg Portland Semen 1,050.00 1,062.50 10,735.20 10,863.00
0.020 m3 Pasir Pasang 310,000.00 370,000.00 6,200.00 7,400.00
C PERALATAN
D Jumlah A + B + C 55,335.20 62,963.00
E Overhead & Profit (contoh 10%) 10% 5,533.52 6,296.30
F Harga Satuan Pekerjaan (D+E) 60,868.72 69,259.30

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 59,064.28 67,619.20


A Tenaga 38,400.00 44,700.00

L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00


L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 15,294.80 16,772.00
7.776 Kg Portland Semen 1,050.00 1,062.50 8,164.80 8,262.00
0.023 m3 Pasir Pasang 310,000.00 370,000.00 7,130.00 8,510.00
C PERALATAN
D Jumlah A + B + C 53,694.80 61,472.00
E Overhead & Profit (contoh 10%) 10% 5,369.48 6,147.20
F Harga Satuan Pekerjaan (D+E) 59,064.28 67,619.20

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 57,631.20 66,231.00


A Tenaga 38,400.00 44,700.00

L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00


L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 13,992.00 15,510.00
6.240 Kg Portland Semen 1,050.00 1,062.50 6,552.00 6,630.00
0.024 m3 Pasir Pasang 310,000.00 370,000.00 7,440.00 8,880.00
C PERALATAN
D Jumlah A + B + C 52,392.00 60,210.00
E Overhead & Profit (contoh 10%) 10% 5,239.20 6,021.00
F Harga Satuan Pekerjaan (D+E) 57,631.20 66,231.00

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 57,093.52 65,810.80


A Tenaga 38,400.00 44,700.00
L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 13,503.20 15,128.00
5.184 Kg Portland Semen 1,050.00 1,062.50 5,443.20 5,508.00
0.026 m3 Pasir Pasang 310,000.00 370,000.00 8,060.00 9,620.00
C PERALATAN
D Jumlah A + B + C 51,903.20 59,828.00
E Overhead & Profit (contoh 10%) 10% 5,190.32 5,982.80
F Harga Satuan Pekerjaan (D+E) 57,093.52 65,810.80

file:///conversion/tmp/scratch/469226324.xls 193/97 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 56,547.48 65,320.20
Tenaga 38,400.00 44,700.00

L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 13,006.80 14,682.00
4.416 Kg Portland Semen 1,050.00 1,062.50 4,636.80 4,692.00
0.027 m3 Pasir Pasang 310,000.00 370,000.00 8,370.00 9,990.00
C PERALATAN
D Jumlah A + B + C 51,406.80 59,382.00
E Overhead & Profit (contoh 10%) 10% 5,140.68 5,938.20
F Harga Satuan Pekerjaan (D+E) 56,547.48 65,320.20

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 56,334.08 65,166.20


A Tenaga 38,400.00 44,700.00

L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 12,812.80 14,542.00
3.936 Kg Portland Semen 1,050.00 1,062.50 4,132.80 4,182.00
0.028 m3 Pasir Pasang 310,000.00 370,000.00 8,680.00 10,360.00
C PERALATAN
D Jumlah A + B + C 51,212.80 59,242.00
E Overhead & Profit (contoh 10%) 10% 5,121.28 5,924.20
F Harga Satuan Pekerjaan (D+E) 56,334.08 65,166.20

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 56,120.68 65,012.20


A Tenaga 38,400.00 44,700.00

L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00


L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 12,618.80 14,402.00
3.456 Kg Portland Semen 1,050.00 1,062.50 3,628.80 3,672.00
0.029 m3 Pasir Pasang 310,000.00 370,000.00 8,990.00 10,730.00
C PERALATAN
D Jumlah A + B + C 51,018.80 59,102.00
E Overhead & Profit (contoh 10%) 10% 5,101.88 5,910.20
F Harga Satuan Pekerjaan (D+E) 56,120.68 65,012.20

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 55,767.80 64,328.00


A Tenaga 39,720.00 46,620.00

L.01 0.36 OH Pekerja 70,000.00 85,000.00 25,200.00 30,600.00


L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00

L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00


B Bahan 10,978.00 11,860.00
5.760 Kg Portland Semen 1,050.00 1,062.50 6,048.00 6,120.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
C PERALATAN
D Jumlah A + B + C 50,698.00 58,480.00
E Overhead & Profit (contoh 10%) 10% 5,069.80 5,848.00
F Harga Satuan Pekerjaan (D+E) 55,767.80 64,328.00

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 55,627.00 64,633.25


A Tenaga 39,720.00 46,620.00
L.01 0.36 OH Pekerja 70,000.00 85,000.00 25,200.00 30,600.00
L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 10,850.00 12,137.50
3 kg Portland Semen 1,050.00 1,062.50 3,150.00 3,187.50
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 310,000.00 370,000.00 6,200.00 7,400.00
C PERALATAN
D Jumlah A + B + C 50,570.00 58,757.50
E Overhead & Profit (contoh 10%) 10% 5,057.00 5,875.75
F Harga Satuan Pekerjaan (D+E) 55,627.00 64,633.25

file:///conversion/tmp/scratch/469226324.xls 193/98 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 51,711.00 59,994.00
A Tenaga 39,720.00 46,620.00

L.01 0.36 OH Pekerja 70,000.00 85,000.00 25,200.00 30,600.00

L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00

L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00


B Bahan 7,290.00 7,920.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 310,000.00 370,000.00 2,790.00 3,330.00
C PERALATAN
D Jumlah A + B + C 47,010.00 54,540.00
E Overhead & Profit (contoh 10%) 10% 4,701.00 5,454.00
F Harga Satuan Pekerjaan (D+E) 51,711.00 59,994.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 52,657.00 61,314.00


A Tenaga 39,720.00 46,620.00

L.01 0.36 OH Pekerja 70,000.00 85,000.00 25,200.00 30,600.00

L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00

L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00


B Bahan 8,150.00 9,120.00
0.007 m3 Semen Merah 200,000.00 200,000.00 1,400.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 310,000.00 370,000.00 4,650.00 5,550.00
C PERALATAN
D Jumlah A + B + C 47,870.00 55,740.00
E Overhead & Profit (contoh 10%) 10% 4,787.00 5,574.00
F Harga Satuan Pekerjaan (D+E) 52,657.00 61,314.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 81,491.96 92,723.40


A Tenaga 51,400.00 59,820.00

L.01 0.40 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00

L.02 0.20 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 22,683.60 24,474.00
13.632 kg Portland Semen 1,050.00 1,062.50 14,313.60 14,484.00
0.027 m3 Pasir Pasang 310,000.00 370,000.00 8,370.00 9,990.00
C PERALATAN
D Jumlah A + B + C 74,083.60 84,294.00
E Overhead & Profit (contoh 10%) 10% 7,408.36 8,429.40
F Harga Satuan Pekerjaan (D+E) 81,491.96 92,723.40

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 61,196.40 69,416.00


A Tenaga 40,700.00 46,930.00
L.01 0.26 OH Pekerja 70,000.00 85,000.00 18,200.00 22,100.00
L.02 0.2 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 20,496.40 22,486.00
10.368 Kg Portland Semen 1,050.00 1,062.50 10,886.40 11,016.00
0.031 m3 Pasir Pasang 310,000.00 370,000.00 9,610.00 11,470.00
C PERALATAN
D Jumlah A + B + C 62,496.40 70,846.00
E Overhead & Profit (contoh 10%) 10% 6,249.64 7,084.60
F Harga Satuan Pekerjaan (D+E) 68,746.04 77,930.60

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 77,061.60 88,550.00


A Tenaga 51,400.00 59,820.00

L.01 0.40 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00

L.02 0.20 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00


L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 18,656.00 20,680.00
8.320 kg Portland Semen 1,050.00 1,062.50 8,736.00 8,840.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00

file:///conversion/tmp/scratch/469226324.xls 193/99 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 70,056.00 80,500.00
E Overhead & Profit (contoh 10%) 10% 7,005.60 8,050.00
F Harga Satuan Pekerjaan (D+E) 77,061.60 88,550.00

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 76,458.36 88,125.40


A Tenaga 51,400.00 59,820.00

L.01 0.400 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00

L.02 0.200 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 18,107.60 20,294.00
6.912 Kg Portland Semen 1,050.00 1,062.50 7,257.60 7,344.00
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 69,507.60 80,114.00
E Overhead & Profit (contoh 10%) 10% 6,950.76 8,011.40
F Harga Satuan Pekerjaan (D+E) 76,458.36 88,125.40

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 75,616.64 87,335.60


A Tenaga 51,400.00 59,820.00

L.01 0.40 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00

L.02 0.2 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00


L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00
B Bahan 17,342.40 19,576.00
5.888 Kg Portland Semen 1,050.00 1,062.50 6,182.40 6,256.00
0.036 m3 Pasir Pasang 310,000.00 370,000.00 11,160.00 13,320.00
C PERALATAN
D Jumlah A + B + C 68,742.40 79,396.00
E Overhead & Profit (contoh 10%) 10% 6,874.24 7,939.60
F Harga Satuan Pekerjaan (D+E) 75,616.64 87,335.60

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 73,040.00 84,491.00


A Tenaga 56,320.00 65,560.00

L.01 0.440 OH Pekerja 70,000.00 85,000.00 30,800.00 37,400.00

L.02 0.22 OH Tukang batu 95,000.00 105,000.00 20,900.00 23,100.00

L.03 0.022 OH Kepala Tukang 110,000.00 120,000.00 2,420.00 2,640.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 10,080.00 11,250.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
C PERALATAN
D Jumlah A + B + C 66,400.00 76,810.00
E Overhead & Profit (contoh 10%) 10% 6,640.00 7,681.00
F Harga Satuan Pekerjaan (D+E) 73,040.00 84,491.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 36,089.02 41,352.30


A Tenaga 19,305.00 22,465.00

L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00


L.02 0.075 OH Tukang batu 95,000.00 105,000.00 7,125.00 7,875.00

L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00


L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 13,503.20 15,128.00
5.184 Kg Portland Semen 1,050.00 1,062.50 5,443.20 5,508.00
0.026 m3 Pasir Pasang 310,000.00 370,000.00 8,060.00 9,620.00
C PERALATAN
D Jumlah A + B + C 32,808.20 37,593.00
E Overhead & Profit (contoh 10%) 10% 3,280.82 3,759.30
F Harga Satuan Pekerjaan (D+E) 36,089.02 41,352.30

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 58,250.50 65,319.38

A Tenaga 48,400.00 54,040.00

L.01 0.080 OH Pekerja 70,000.00 85,000.00 5,600.00 6,800.00

L.02 0.40 OH Tukang batu 95,000.00 105,000.00 38,000.00 42,000.00

L.03 0.040 OH Kepala Tukang 110,000.00 120,000.00 4,400.00 4,800.00

L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00

file:///conversion/tmp/scratch/469226324.xls 193/100 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,555.00 5,341.25
0.5 Kg Portland Semen 1,050.00 1,062.50 525.00 531.25
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
C PERALATAN
D Jumlah A + B + C 52,955.00 59,381.25
E Overhead & Profit (contoh 10%) 10% 5,295.50 5,938.13
F Harga Satuan Pekerjaan (D+E) 58,250.50 65,319.38

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 91,525.50 103,719.00
mm
A Tenaga 57,705.00 67,165.00
L.01 0.450 OH Pekerja 70,000.00 85,000.00 31,500.00 38,250.00
L.02 0.225 OH Tukang batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
B Bahan 25,500.00 27,125.00
10 Kg Portland Semen 1,050.00 1,062.50 10,500.00 10,625.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 83,205.00 94,290.00
E Overhead & Profit (contoh 10%) 10% 8,320.50 9,429.00
F Harga Satuan Pekerjaan (D+E) 91,525.50 103,719.00

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 91,525.50 103,719.00

A Tenaga 57,705.00 67,165.00


L.01 0.450 OH Pekerja 70,000.00 85,000.00 31,500.00 38,250.00
L.02 0.225 OH Tukang batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
B Bahan 25,500.00 27,125.00
10 Kg Portland Semen 1,050.00 1,062.50 10,500.00 10,625.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 83,205.00 94,290.00
E Overhead & Profit (contoh 10%) 10% 8,320.50 9,429.00
F Harga Satuan Pekerjaan (D+E) 91,525.50 103,719.00

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 43,445.60 50,226.00


Tenaga 33,100.00 38,850.00

L.01 0.30 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.1 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00

L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 6,396.00 6,810.00
4.32 Kg Portland Semen 1,050.00 1,062.50 4,536.00 4,590.00
0.006 m3 Pasir Pasang 310,000.00 370,000.00 1,860.00 2,220.00
C PERALATAN
D Jumlah A + B + C 39,496.00 45,660.00
E Overhead & Profit (contoh 10%) 10% 3,949.60 4,566.00
F Harga Satuan Pekerjaan (D+E) 43,445.60 50,226.00

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 24,825.24 28,343.98
Merah
A Tenaga 19,305.00 22,465.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00

L.02 0.075 OH Tukang batu 95,000.00 105,000.00 7,125.00 7,875.00

L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00


L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 3,263.40 3,302.25
3.108 Kg Portland Semen 1,050.00 1,062.50 3,263.40 3,302.25
C PERALATAN
D Jumlah A + B + C 22,568.40 25,767.25
E Overhead & Profit (contoh 10%) 10% 2,256.84 2,576.73
F Harga Satuan Pekerjaan (D+E) 24,825.24 28,343.98

file:///conversion/tmp/scratch/469226324.xls 193/101 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 11,819.50 13,469.50
ekspose
A Tenaga 9,065.00 10,545.00
L.01 0.070 OH Pekerja 70,000.00 85,000.00 4,900.00 5,950.00

L.02 0.035 OH Tukang batu 95,000.00 105,000.00 3,325.00 3,675.00

L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00

L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00


B Bahan 1,680.00 1,700.00
1.600 Kg Portland Semen 1,050.00 1,062.50 1,680.00 1,700.00
C PERALATAN
D Jumlah A + B + C 10,745.00 12,245.00
E Overhead & Profit (contoh 10%) 10% 1,074.50 1,224.50
F Harga Satuan Pekerjaan (D+E) 11,819.50 13,469.50

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 53,654.70 61,463.88
2Pp
Tenaga 38,400.00 44,700.00

L.01 0.3 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 10,377.00 11,176.25
6.34 Kg Portland Semen 1,050.00 1,062.50 6,657.00 6,736.25
0.012 m3 Pasir Pasang 310,000.00 370,000.00 3,720.00 4,440.00
C PERALATAN
D Jumlah A + B + C 48,777.00 55,876.25
E Overhead & Profit (contoh 10%) 10% 4,877.70 5,587.63
F Harga Satuan Pekerjaan (D+E) 53,654.70 61,463.88

27 A.4.4.2.27 1 m2 Pemasangan Acian 31,913.75 36,578.44

Tenaga 25,600.00 29,800.00


L.01 0.20 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 3,412.50 3,453.13
3.25 Kg Portland Semen 1,050.00 1,062.50 3,412.50 3,453.13
C PERALATAN
D Jumlah A + B + C 29,012.50 33,253.13
E Overhead & Profit (contoh 10%) 10% 2,901.25 3,325.31
F Harga Satuan Pekerjaan (D+E) 31,913.75 36,578.44

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 40,713.20 45,681.90

Tenaga 25,600.00 29,800.00


L.01 0.20 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 37,012.00 41,529.00
E Overhead & Profit (contoh 10%) 10% 3,701.20 4,152.90
F Harga Satuan Pekerjaan (D+E) 40,713.20 45,681.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 34,595.00 39,393.75


Tenaga 25,600.00 29,800.00
L.01 0.20 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 31,450.00 35,812.50
E Overhead & Profit (contoh 10%) 10% 3,145.00 3,581.25
F Harga Satuan Pekerjaan (D+E) 34,595.00 39,393.75

file:///conversion/tmp/scratch/469226324.xls 193/102 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3
dan DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 103,755.50 116,210.00


A Tenaga 32,105.00 37,365.00
L.01 0.25 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.125 OH Tukang Batu 95,000.00 105,000.00 11,875.00 13,125.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 62,218.18 68,280.45
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,181.82 3,454.55 37,768.18 41,005.45
10.0 Kg Portland Semen 0.3 1,050.00 1,062.50 10,500.00 10,625.00
0.0450 m3 Pasir Pasang 0.09 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN

D Jumlah A + B + C 94,323.18 105,645.45


E Overhead & Profit (contoh 10%) 10% 9,432.32 10,564.55
F Harga Satuan Pekerjaan (D+E) 103,755.50 116,210.00

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 105,132.50 117,991.50


A Tenaga 34,665.00 40,345.00
L.01 0.27 OH Pekerja 70,000.00 85,000.00 18,900.00 22,950.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.014 OH Kepala Tukang 110,000.00 120,000.00 1,540.00 1,680.00
L.04 0.014 OH Mandor 100,000.00 110,000.00 1,400.00 1,540.00
B Bahan 60,910.00 66,920.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 1,480.00 36,040.00 39,220.00
10.4 Kg Portland Semen 1,050.00 1,062.50 10,920.00 11,050.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 95,575.00 107,265.00
E Overhead & Profit (contoh 10%) 10% 9,557.50 10,726.50
F Harga Satuan Pekerjaan (D+E) 105,132.50 117,991.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 129,133.00 154,342.50


A Tenaga 33,280.00 38,740.00
L.01 0.26 OH Pekerja 70,000.00 85,000.00 18,200.00 22,100.00
L.02 0.130 OH Tukang Batu 95,000.00 105,000.00 12,350.00 13,650.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 84,113.64 101,571.36
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,363.64 43,163.64 51,796.36
10.0 Kg Portland Semen 1,050.00 1,062.50 10,500.00 10,625.00
1.50 Kg Semen warna 11,000.00 15,000.00 16,500.00 22,500.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 117,393.64 140,311.36
E Overhead & Profit (contoh 10%) 10% 11,739.36 14,031.14
F Harga Satuan Pekerjaan (D+E) 129,133.00 154,342.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 131,147.50 154,049.50


A Tenaga 34,665.00 40,345.00
L.01 0.27 OH Pekerja 70,000.00 85,000.00 18,900.00 22,950.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.014 OH Kepala Tukang 110,000.00 120,000.00 1,540.00 1,680.00
L.04 0.014 OH Mandor 100,000.00 110,000.00 1,400.00 1,540.00
B Bahan 84,560.00 99,700.00
26.5 Buah Ubin Warna 20x20 cm 1,580.00 1,800.00 41,870.00 47,700.00
10.4 Kg Portland Semen 1,050.00 1,062.50 10,920.00 11,050.00
1.62 Kg Semen warna 11,000.00 15,000.00 17,820.00 24,300.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 119,225.00 140,045.00
E Overhead & Profit (contoh 10%) 10% 11,922.50 14,004.50
F Harga Satuan Pekerjaan (D+E) 131,147.50 154,049.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 345,119.50 396,195.25
A Tenaga 32,105.00 37,365.00
L.01 0.250 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.125 OH Tukang Batu 95,000.00 105,000.00 11,875.00 13,125.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 281,640.00 322,812.50
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 41,666.67 243,100.00 276,250.00

9.8 Kg Portland Semen 0.16 1,050.00 1,062.50 10,290.00 10,412.50


1.300 Kg Semen warna 6.25 11,000.00 15,000.00 14,300.00 19,500.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 313,745.00 360,177.50
E Overhead & Profit (contoh 10%) 10% 31,374.50 36,017.75
F Harga Satuan Pekerjaan (D+E) 345,119.50 396,195.25

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 64,484.20 75,347.25

A Tenaga 16,340.00 18,730.00


L.01 0.090 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 42,282.00 49,767.50
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,050.00 1,062.50 1,302.00 1,317.50
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 58,622.00 68,497.50
E Overhead & Profit (contoh 10%) 10% 5,862.20 6,849.75
F Harga Satuan Pekerjaan (D+E) 64,484.20 75,347.25

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 36,681.70 40,838.88


A Tenaga 16,340.00 18,730.00
L.01 0.090 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 17,007.00 18,396.25
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,050.00 1,062.50 1,197.00 1,211.25
0.100 Kg Semen Warna 11,000.00 15,000.00 1,100.00 1,500.00
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
C PERALATAN
D Jumlah A + B + C 33,347.00 37,126.25
E Overhead & Profit (contoh 10%) 10% 3,334.70 3,712.63
F Harga Satuan Pekerjaan (D+E) 36,681.70 40,838.88

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 197,449.45 252,122.06


A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 89,899.50 124,901.88
53.00 Buah Keramik 10 x 20 cm 700.00 1,100.00 37,100.00 58,300.00

8.19 Kg Portland Semen 1,050.00 1,062.50 8,599.50 8,701.88


2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 179,499.50 229,201.88
E Overhead & Profit (contoh 10%) 10% 17,949.95 22,920.19
F Harga Satuan Pekerjaan (D+E) 197,449.45 252,122.06
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 202,894.45 259,547.06
A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 94,849.50 131,651.88
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 350.00 550.00 37,100.00 58,300.00
8.19 Kg Portland Semen 1,050.00 1,062.50 8,599.50 8,701.88
3.20 Kg Semen Warna 11,000.00 15,000.00 35,200.00 48,000.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 184,449.50 235,951.88
E Overhead & Profit (contoh 10%) 10% 18,444.95 23,595.19
F Harga Satuan Pekerjaan (D+E) 202,894.45 259,547.06

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 206,522.01 242,680.40


A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 98,147.28 116,318.54
10 Buah Ubin Keramik 33 x 33 cm 5,777.78 6,666.67 57,777.78 66,666.67
8.19 Kg Portland Semen 1,050.00 1,062.50 8,599.50 8,701.88

0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00


1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
C PERALATAN
D Jumlah A + B + C 187,747.28 220,618.54
E Overhead & Profit (contoh 10%) 10% 18,774.73 22,061.85
F Harga Satuan Pekerjaan (D+E) 206,522.01 242,680.40

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 187,524.00 235,954.50


A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 80,876.36 110,204.09
11.87 Buah Ubin Keramik 30 x 30 cm 3,363.64 5,090.91 39,926.36 60,429.09
10.00 Kg Portland Semen 1,050.00 1,062.50 10,500.00 10,625.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
1.50 Kg Semen Warna 11,000.00 15,000.00 16,500.00 22,500.00
C PERALATAN
D Jumlah A + B + C 170,476.36 214,504.09
E Overhead & Profit (contoh 10%) 10% 17,047.64 21,450.41
F Harga Satuan Pekerjaan (D+E) 187,524.00 235,954.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 199,738.00 237,226.00


A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 91,980.00 111,360.00
26.5 Buah Ubin Keramik 20 x 20 cm 1,860.00 2,240.00 49,290.00 59,360.00
10.40 Kg Portland Semen 1,050.00 1,062.50 10,920.00 11,050.00
1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 181,580.00 215,660.00
E Overhead & Profit (contoh 10%) 10% 18,158.00 21,566.00
F Harga Satuan Pekerjaan (D+E) 199,738.00 237,226.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 407,016.50 460,677.25
variasi / border
A Tenaga 132,705.00 154,585.00
L.01 1.05 OH Pekerja 70,000.00 85,000.00 73,500.00 89,250.00
L.02 0.525 OH Tukang Batu 95,000.00 105,000.00 49,875.00 55,125.00
L.03 0.053 OH Kepala Tukang 110,000.00 120,000.00 5,830.00 6,360.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 237,310.00 264,212.50
33.0 Buah Ubin Keramik 5,000.00 5,200.00 165,000.00 171,600.00
9.80 Kg Portland Semen 1,050.00 1,062.50 10,290.00 10,412.50
4.37 Kg Semen Warna 11,000.00 15,000.00 48,070.00 65,550.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 370,015.00 418,797.50
E Overhead & Profit (contoh 10%) 10% 37,001.50 41,879.75
F Harga Satuan Pekerjaan (D+E) 407,016.50 460,677.25

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 35,191.20 41,058.88


A Tenaga 16,340.00 18,730.00
L.01 0.09 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 15,652.00 18,596.25
5.3 Buah Ubin Keramik 2,500.00 3,000.00 13,250.00 15,900.00
1.14 Kg Portland Semen 1,050.00 1,062.50 1,197.00 1,211.25
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.025 Kg Semen Warna 11,000.00 15,000.00 275.00 375.00
C PERALATAN
D Jumlah A + B + C 31,992.00 37,326.25
E Overhead & Profit (contoh 10%) 10% 3,199.20 3,732.63
F Harga Satuan Pekerjaan (D+E) 35,191.20 41,058.88

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 81,550.70 88,111.38


A Tenaga 16,340.00 18,730.00
L.01 0.09 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 57,797.00 61,371.25
10.6 Buah Ubin Keramik 5,200.00 5,500.00 55,120.00 58,300.00
1.14 Kg Portland Semen 1,050.00 1,062.50 1,197.00 1,211.25
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 74,137.00 80,101.25
E Overhead & Profit (contoh 10%) 10% 7,413.70 8,010.13
F Harga Satuan Pekerjaan (D+E) 81,550.70 88,111.38

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 79,218.70 86,945.38


A Tenaga 16,340.00 18,730.00
L.01 0.09 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 55,677.00 60,311.25
10.6 Buah Ubin Keramik 5,000.00 5,400.00 53,000.00 57,240.00
1.14 Kg Portland Semen 1,050.00 1,062.50 1,197.00 1,211.25
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 72,017.00 79,041.25
E Overhead & Profit (contoh 10%) 10% 7,201.70 7,904.13
F Harga Satuan Pekerjaan (D+E) 79,218.70 86,945.38
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 685,079.45 713,022.06
A Tenaga 89,600.00 104,300.00
L.01 0.7 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 533,199.50 543,901.88
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,050.00 1,062.50 8,599.50 8,701.88
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 622,799.50 648,201.88
E Overhead & Profit (contoh 10%) 10% 62,279.95 64,820.19
F Harga Satuan Pekerjaan (D+E) 685,079.45 713,022.06

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 199,452.00 214,038.00


A Tenaga 30,820.00 35,330.00
L.01 0.17 OH Pekerja 70,000.00 85,000.00 11,900.00 14,450.00
L.02 0.17 OH Tukang Batu 95,000.00 105,000.00 16,150.00 17,850.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 181,320.00 194,580.00
E Overhead & Profit (contoh 10%) 10% 18,132.00 19,458.00
F Harga Satuan Pekerjaan (D+E) 199,452.00 214,038.00

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 377,410.00 515,680.00


A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 253,500.00 364,500.00
1.05 m2 Parquet Jati 210,000.00 310,000.00 220,500.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 343,100.00 468,800.00
E Overhead & Profit (contoh 10%) 10% 34,310.00 46,880.00
F Harga Satuan Pekerjaan (D+E) 377,410.00 515,680.00

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 239,408.16 277,077.69


A Tenaga 128,000.00 149,000.00
L.01 1.00 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 0.50 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.050 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 89,643.78 102,888.81
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,050.00 1,062.50 9,765.00 9,881.25

2.750 Kg Semen Warna 0.0121 11,000.00 15,000.00 30,250.00 41,250.00

0.018 m3 Pasir Pasang 0.11 310,000.00 370,000.00 5,580.00 6,660.00


C PERALATAN
D Jumlah A + B + C 217,643.78 251,888.81
E Overhead & Profit (contoh 10%) 10% 21,764.38 25,188.88
F Harga Satuan Pekerjaan (D+E) 239,408.16 277,077.69

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 217,684.50 275,210.38


A Tenaga 115,200.00 134,100.00
L.01 0.9 OH Pekerja 70,000.00 85,000.00 63,000.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 82,695.00 116,091.25
53 Buah Keramik 700.00 1,100.00 37,100.00 58,300.00
9.3 Kg Portland Semen 1,050.00 1,062.50 9,765.00 9,881.25
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 197,895.00 250,191.25
E Overhead & Profit (contoh 10%) 10% 19,789.50 25,019.13
F Harga Satuan Pekerjaan (D+E) 217,684.50 275,210.38

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 226,561.50 266,355.38


A Tenaga 115,200.00 134,100.00
L.01 0.9 OH Pekerja 70,000.00 85,000.00 63,000.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 90,765.00 108,041.25
26.0 Buah Keramik 2,080.00 2,400.00 54,080.00 62,400.00
9.3 Kg Portland Semen 1,050.00 1,062.50 9,765.00 9,881.25
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 205,965.00 242,141.25
E Overhead & Profit (contoh 10%) 10% 20,596.50 24,214.13
F Harga Satuan Pekerjaan (D+E) 226,561.50 266,355.38

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 217,684.50 275,210.38


A Tenaga 115,200.00 134,100.00
L.01 0.9 OH Pekerja 70,000.00 85,000.00 63,000.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 82,695.00 116,091.25
53.0 Buah Keramik 700.00 1,100.00 37,100.00 58,300.00
9.3 Kg Portland Semen 1,050.00 1,062.50 9,765.00 9,881.25
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 197,895.00 250,191.25
E Overhead & Profit (contoh 10%) 10% 19,789.50 25,019.13
F Harga Satuan Pekerjaan (D+E) 217,684.50 275,210.38

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 227,705.50 267,675.38


A Tenaga 115,200.00 134,100.00
L.01 0.9 OH Pekerja 70,000.00 85,000.00 63,000.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 91,805.00 109,241.25
26.5 Buah Keramik 2,080.00 2,400.00 55,120.00 63,600.00
9.3 Kg Portland Semen 1,050.00 1,062.50 9,765.00 9,881.25
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 207,005.00 243,341.25
E Overhead & Profit (contoh 10%) 10% 20,700.50 24,334.13
F Harga Satuan Pekerjaan (D+E) 227,705.50 267,675.38

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 767,763.82 808,304.87


A Tenaga 166,400.00 193,700.00
L.01 1.3 OH Pekerja 70,000.00 85,000.00 91,000.00 110,500.00
L.02 0.65 OH Tukang Batu 95,000.00 105,000.00 61,750.00 68,250.00
L.03 0.065 OH Kepala Tukang 110,000.00 120,000.00 7,150.00 7,800.00
L.04 0.065 OH Mandor 100,000.00 110,000.00 6,500.00 7,150.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 531,567.11 541,122.61
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 35.00 35.00 105.11 105.11
12.44 kg Portlan Semen 1,050.00 1,062.50 13,062.00 13,217.50
0.025 m3 Pasir Pasang 310,000.00 370,000.00 7,750.00 9,250.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 697,967.11 734,822.61
E Overhead & Profit (contoh 10%) 10% 69,796.71 73,482.26
F Harga Satuan Pekerjaan (D+E) 767,763.82 808,304.87

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 257,166.25 281,857.81
A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 144,187.50 151,934.38
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,050.00 1,062.50 12,337.50 12,484.38
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 233,787.50 256,234.38
E Overhead & Profit (contoh 10%) 10% 23,378.75 25,623.44
F Harga Satuan Pekerjaan (D+E) 257,166.25 281,857.81

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 143,592.90 158,169.00


A Tenaga 43,195.00 50,385.00
L.01 0.35 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.175 OH Tukang Batu 95,000.00 105,000.00 16,625.00 18,375.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 130,539.00 143,790.00
E Overhead & Profit (contoh 10%) 10% 13,053.90 14,379.00
F Harga Satuan Pekerjaan (D+E) 143,592.90 158,169.00

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 113,459.50 124,888.50


A Tenaga 43,195.00 50,385.00
L.01 0.35 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.175 OH Tukang Batu 95,000.00 105,000.00 16,625.00 18,375.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 59,950.00 63,150.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 11,000.00 15,000.00 2,750.00 3,750.00
C PERALATAN
D Jumlah A + B + C 103,145.00 113,535.00
E Overhead & Profit (contoh 10%) 10% 10,314.50 11,353.50
F Harga Satuan Pekerjaan (D+E) 113,459.50 124,888.50

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 45,342.00 57,310.00
Tenaga 21,720.00 24,900.00
L.01 0.12 OH Pekerja 70,000.00 85,000.00 8,400.00 10,200.00
L.02 0.12 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
Bahan 19,500.00 27,200.00
0.003 m3 Papan Kayu Klas II 6,250,000.00 8,800,000.00 18,750.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 41,220.00 52,100.00
E Overhead & Profit (contoh 10%) 10% 4,122.00 5,210.00
F Harga Satuan Pekerjaan (D+E) 45,342.00 57,310.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 166,083.50 184,198.30


Tenaga 70,630.00 79,893.00
L.01 0.25 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 73,050.00 79,600.00
1.01 m2 Paving Block Tebal 6 Cm 55,000.00 60,000.00 55,550.00 60,600.00
0.05 m3 Pasir Beton 350,000.00 380,000.00 17,500.00 19,000.00
C PERALATAN 7,305.00 7,960.00
10 % Peralatan 73,050.00 79,600.00 7,305.00 7,960.00
D Jumlah A + B + C 150,985.00 167,453.00
E Overhead & Profit (contoh 10%) 10% 15,098.50 16,745.30
F Harga Satuan Pekerjaan (D+E) 166,083.50 184,198.30

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 218,245.50 241,211.30


Tenaga 88,130.00 101,143.00
L.01 0.5 OH Pekerja 70,000.00 85,000.00 35,000.00 42,500.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 100,250.00 107,400.00
1.01 m2 Paving Block Tebal 8 Cm 75,000.00 80,000.00 75,750.00 80,800.00
0.07 m3 Pasir Beton 350,000.00 380,000.00 24,500.00 26,600.00
C PERALATAN 10,025.00 10,740.00
10 % Peralatan 100,250.00 107,400.00 10,025.00 10,740.00
D Jumlah A + B + C 198,405.00 219,283.00
E Overhead & Profit (contoh 10%) 10% 19,840.50 21,928.30
F Harga Satuan Pekerjaan (D+E) 218,245.50 241,211.30

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 178,304.50 196,419.30


Tenaga 70,630.00 79,893.00
L.01 0.25 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 83,150.00 89,700.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 65,000.00 70,000.00 65,650.00 70,700.00
0.05 m3 Pasir Beton 350,000.00 380,000.00 17,500.00 19,000.00
C PERALATAN 8,315.00 8,970.00
10 % Peralatan 83,150.00 89,700.00 8,315.00 8,970.00
D Jumlah A + B + C 162,095.00 178,563.00
E Overhead & Profit (contoh 10%) 10% 16,209.50 17,856.30
F Harga Satuan Pekerjaan (D+E) 178,304.50 196,419.30

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 230,466.50 253,432.30


Tenaga 88,130.00 101,143.00
L.01 0.5 OH Pekerja 70,000.00 85,000.00 35,000.00 42,500.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 110,350.00 117,500.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 85,000.00 90,000.00 85,850.00 90,900.00
0.07 m3 Pasir Beton 350,000.00 380,000.00 24,500.00 26,600.00
C PERALATAN 11,035.00 11,750.00
10 % Peralatan 110,350.00 117,500.00 11,035.00 11,750.00
D Jumlah A + B + C 209,515.00 230,393.00
E Overhead & Profit (contoh 10%) 10% 20,951.50 23,039.30
F Harga Satuan Pekerjaan (D+E) 230,466.50 253,432.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 29,832.00 33,060.50
mm, 5 mm & 6 mm

A Tenaga 9,920.00 11,180.00


L.01 0.03 OH Pekerja 70,000.00 85,000.00 2,100.00 2,550.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 17,200.00 18,875.00
1.1 Lbr Plat Asbes 15,500.00 17,000.00 17,050.00 18,700.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 27,120.00 30,055.00
E Overhead & Profit (contoh 10%) 10% 2,712.00 3,005.50
F Harga Satuan Pekerjaan (D+E) 29,832.00 33,060.50
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 101,277.00 110,192.50
A Tenaga 21,720.00 24,900.00
L.01 0.12 OH Pekerja 70,000.00 85,000.00 8,400.00 10,200.00
L.02 0.12 OH Tukang Kayu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 70,350.00 75,275.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,200.00 69,600.00 74,400.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 92,070.00 100,175.00
E Overhead & Profit (contoh 10%) 10% 9,207.00 10,017.50
F Harga Satuan Pekerjaan (D+E) 101,277.00 110,192.50

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 104,951.00 114,383.50


A Tenaga 18,100.00 20,750.00
L.01 0.10 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 77,310.00 83,235.00
5.80 Lbr Akustik 13,200.00 14,200.00 76,560.00 82,360.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 95,410.00 103,985.00
E Overhead & Profit (contoh 10%) 10% 9,541.00 10,398.50
F Harga Satuan Pekerjaan (D+E) 104,951.00 114,383.50

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 90,035.00 99,687.50


A Tenaga 18,100.00 20,750.00
L.01 0.10 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 63,750.00 69,875.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 81,850.00 90,625.00
E Overhead & Profit (contoh 10%) 10% 8,185.00 9,062.50
F Harga Satuan Pekerjaan (D+E) 90,035.00 99,687.50

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 45,155.00 54,340.00
mm, 4 mm & 6 mm

A Tenaga 18,100.00 20,750.00


L.01 0.10 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00

file:///conversion/tmp/scratch/469226324.xls 193/111 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 22,950.00 28,650.00
0.375 Lbr Tripleks (4 mm) 60,000.00 75,000.00 22,500.00 28,125.00
0.03 Kg Paku Tripleks 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 41,050.00 49,400.00
E Overhead & Profit (contoh 10%) 10% 4,105.00 4,940.00
F Harga Satuan Pekerjaan (D+E) 45,155.00 54,340.00

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 522,445.00 562,292.50


A Tenaga 144,800.00 166,000.00
L.01 0.8 OH Pekerja 70,000.00 85,000.00 56,000.00 68,000.00
L.02 0.8 OH Tukang Kayu 95,000.00 105,000.00 76,000.00 84,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 120,000.00 8,800.00 9,600.00
L.04 0.04 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 330,150.00 345,175.00
0.015 m3 Kayu Jati,Papan 22,000,000.00 23,000,000.00 330,000.00 345,000.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 474,950.00 511,175.00
E Overhead & Profit (contoh 10%) 10% 47,495.00 51,117.50
F Harga Satuan Pekerjaan (D+E) 522,445.00 562,292.50

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 39,919.00 45,492.70
tebal 9 mm

A Tenaga 12,800.00 14,900.00


L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 23,490.00 26,457.00
0.364 Lbr Gypsum Board 60,000.00 68,000.00 21,840.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 36,290.00 41,357.00
E Overhead & Profit (contoh 10%) 10% 3,629.00 4,135.70
F Harga Satuan Pekerjaan (D+E) 39,919.00 45,492.70

Memasang Langit-langit Akustik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 208,615.00 232,430.00
Rangka Allumunium

A Tenaga 90,500.00 103,750.00


L.01 0.5 OH Pekerja 70,000.00 85,000.00 35,000.00 42,500.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.025 OH Mandor 100,000.00 110,000.00 2,500.00 2,750.00
B Bahan 99,150.00 107,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 189,650.00 211,300.00
E Overhead & Profit (contoh 10%) 10% 18,965.00 21,130.00
F Harga Satuan Pekerjaan (D+E) 208,615.00 232,430.00

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 15,719.00 17,440.50


A Tenaga 9,100.00 10,430.00
L.01 0.05 OH Pekerja 70,000.00 85,000.00 3,500.00 4,250.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 5,190.00 5,425.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 14,290.00 15,855.00
E Overhead & Profit (contoh 10%) 10% 1,429.00 1,585.50
F Harga Satuan Pekerjaan (D+E) 15,719.00 17,440.50

file:///conversion/tmp/scratch/469226324.xls 193/112 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 84,425.00 96,145.50
A Tenaga 19,250.00 22,405.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.0075 OH Kepala Tukang 110,000.00 120,000.00 825.00 900.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 57,500.00 65,000.00
25 Buah Genteng Plentong 2,300.00 2,600.00 57,500.00 65,000.00
C PERALATAN
D Jumlah A + B + C 76,750.00 87,405.00
E Overhead & Profit (contoh 10%) 10% 7,675.00 8,740.50
F Harga Satuan Pekerjaan (D+E) 84,425.00 96,145.50
Overhead & Profit (contoh 10%)
2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 138,110.50 144,336.50
A Tenaga 19,305.00 22,465.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 106,250.00 108,750.00
25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00
C PERALATAN
D Jumlah A + B + C 125,555.00 131,215.00
E Overhead & Profit (contoh 10%) 10% 12,555.50 13,121.50
F Harga Satuan Pekerjaan (D+E) 138,110.50 144,336.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 122,215.50 130,641.50


A Tenaga 19,305.00 22,465.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 91,800.00 96,300.00
12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 111,105.00 118,765.00
E Overhead & Profit (contoh 10%) 10% 11,110.50 11,876.50
F Harga Satuan Pekerjaan (D+E) 122,215.50 130,641.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 97,867.00 109,681.00


A Tenaga 49,400.00 57,620.00
L.01 0.4 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 39,570.00 42,090.00
5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00
8 Kg Portland Semen 1,050.00 1,062.50 8,400.00 8,500.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 88,970.00 99,710.00
E Overhead & Profit (contoh 10%) 10% 8,897.00 9,971.00
F Harga Satuan Pekerjaan (D+E) 97,867.00 109,681.00

file:///conversion/tmp/scratch/469226324.xls 193/113 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 110,242.00 123,156.00
A Tenaga 49,400.00 57,620.00
L.01 0.4 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 50,820.00 54,340.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,050.00 1,062.50 8,400.00 8,500.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 100,220.00 111,960.00
E Overhead & Profit (contoh 10%) 10% 10,022.00 11,196.00
F Harga Satuan Pekerjaan (D+E) 110,242.00 123,156.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 114,092.00 126,236.00


A Tenaga 49,400.00 57,620.00
L.01 0.4 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 54,320.00 57,140.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,050.00 1,062.50 8,400.00 8,500.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 103,720.00 114,760.00
E Overhead & Profit (contoh 10%) 10% 10,372.00 11,476.00
F Harga Satuan Pekerjaan (D+E) 114,092.00 126,236.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 102,723.50 115,962.00


A Tenaga 17,635.00 20,545.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.067 OH Tukang Kayu 95,000.00 105,000.00 6,365.00 7,035.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 75,750.00 84,875.00
0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00
0.05 Kg Paku Biasa 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 93,385.00 105,420.00
E Overhead & Profit (contoh 10%) 10% 9,338.50 10,542.00
F Harga Satuan Pekerjaan (D+E) 102,723.50 115,962.00

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 61,836.50 70,614.50
mm

A Tenaga 18,605.00 21,615.00


L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 37,610.00 42,580.00
0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,215.00 64,195.00
E Overhead & Profit (contoh 10%) 10% 5,621.50 6,419.50
F Harga Satuan Pekerjaan (D+E) 61,836.50 70,614.50

file:///conversion/tmp/scratch/469226324.xls 193/114 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 63,668.00 72,776.00
mm

A Tenaga 17,920.00 20,860.00


L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 57,880.00 66,160.00
E Overhead & Profit (contoh 10%) 10% 5,788.00 6,616.00
F Harga Satuan Pekerjaan (D+E) 63,668.00 72,776.00

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 63,998.00 73,436.00
mm

A Tenaga 17,920.00 20,860.00


L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 40,260.00 45,900.00
0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,180.00 66,760.00
E Overhead & Profit (contoh 10%) 10% 5,818.00 6,676.00
F Harga Satuan Pekerjaan (D+E) 63,998.00 73,436.00

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 71,258.00 76,274.00
mm

A Tenaga 17,920.00 20,860.00


L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 46,860.00 48,480.00
0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 64,780.00 69,340.00
E Overhead & Profit (contoh 10%) 10% 6,478.00 6,934.00
F Harga Satuan Pekerjaan (D+E) 71,258.00 76,274.00

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 54,290.50 58,619.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 31,435.00 32,430.00
0.35 Lbr Asbes Gelombang 84,500.00 87,000.00 29,575.00 30,450.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 49,355.00 53,290.00
E Overhead & Profit (contoh 10%) 10% 4,935.50 5,329.00
F Harga Satuan Pekerjaan (D+E) 54,290.50 58,619.00

file:///conversion/tmp/scratch/469226324.xls 193/115 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 56,408.00 62,546.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 33,360.00 36,000.00
0.42 Lbr Asbes Gelombang 75,000.00 81,000.00 31,500.00 34,020.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 51,280.00 56,860.00
E Overhead & Profit (contoh 10%) 10% 5,128.00 5,686.00
F Harga Satuan Pekerjaan (D+E) 56,408.00 62,546.00

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 53,218.00 59,972.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 30,460.00 33,660.00
0.44 Lbr Asbes Gelombang 65,000.00 72,000.00 28,600.00 31,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 48,380.00 54,520.00
E Overhead & Profit (contoh 10%) 10% 4,838.00 5,452.00
F Harga Satuan Pekerjaan (D+E) 53,218.00 59,972.00

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 55,137.50 60,467.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 32,205.00 34,110.00
0.51 Lbr Asbes Gelombang 59,500.00 63,000.00 30,345.00 32,130.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 50,125.00 54,970.00
E Overhead & Profit (contoh 10%) 10% 5,012.50 5,497.00
F Harga Satuan Pekerjaan (D+E) 55,137.50 60,467.00

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 58,718.00 66,484.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 35,460.00 39,580.00
0.80 Lbr Asbes Gelombang 42,000.00 47,000.00 33,600.00 37,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 53,380.00 60,440.00
E Overhead & Profit (contoh 10%) 10% 5,338.00 6,044.00
F Harga Satuan Pekerjaan (D+E) 58,718.00 66,484.00

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 63,679.00 67,859.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/scratch/469226324.xls 193/116 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 57,890.00 61,690.00
E Overhead & Profit (contoh 10%) 10% 5,789.00 6,169.00
F Harga Satuan Pekerjaan (D+E) 63,679.00 67,859.00

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 67,034.00 71,324.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 60,940.00 64,840.00
E Overhead & Profit (contoh 10%) 10% 6,094.00 6,484.00
F Harga Satuan Pekerjaan (D+E) 67,034.00 71,324.00

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 63,866.00 68,684.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,060.00 62,440.00
E Overhead & Profit (contoh 10%) 10% 5,806.00 6,244.00
F Harga Satuan Pekerjaan (D+E) 63,866.00 68,684.00

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 64,878.00 69,861.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,980.00 63,510.00
E Overhead & Profit (contoh 10%) 10% 5,898.00 6,351.00
F Harga Satuan Pekerjaan (D+E) 64,878.00 69,861.00

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 68,783.00 73,403.00
mm
A Tenaga 17,920.00 20,860.00
L.01 0.14 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 62,530.00 66,730.00
E Overhead & Profit (contoh 10%) 10% 6,253.00 6,673.00
F Harga Satuan Pekerjaan (D+E) 68,783.00 73,403.00

file:///conversion/tmp/scratch/469226324.xls 193/117 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 101,255.00 118,057.50
A Tenaga 25,600.00 29,800.00
L.01 0.2 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 66,450.00 77,525.00
11 Lbr Genteng Beton Standrad 6,000.00 7,000.00 66,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 92,050.00 107,325.00
E Overhead & Profit (contoh 10%) 10% 9,205.00 10,732.50
F Harga Satuan Pekerjaan (D+E) 101,255.00 118,057.50

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 217,503.00 244,293.50


A Tenaga 43,830.00 49,960.00
L.01 0.2 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 153,900.00 172,125.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 86,000.00 26,250.00 30,100.00
0.03 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 197,730.00 222,085.00
E Overhead & Profit (contoh 10%) 10% 19,773.00 22,208.50
F Harga Satuan Pekerjaan (D+E) 217,503.00 244,293.50

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 87,560.00 103,950.00


A Tenaga 25,600.00 29,800.00
L.01 0.2 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 54,000.00 64,700.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 79,600.00 94,500.00
E Overhead & Profit (contoh 10%) 10% 7,960.00 9,450.00
F Harga Satuan Pekerjaan (D+E) 87,560.00 103,950.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 107,162.00 115,214.00


A Tenaga 38,920.00 44,240.00
L.01 0.166 OH Pekerja 70,000.00 85,000.00 11,620.00 14,110.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 58,500.00 60,500.00
30 Lbr Genteng Sirap 1,850.00 1,900.00 55,500.00 57,000.00
0.2 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 97,420.00 104,740.00
E Overhead & Profit (contoh 10%) 10% 9,742.00 10,474.00
F Harga Satuan Pekerjaan (D+E) 107,162.00 115,214.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 119,031.00 130,861.50


A Tenaga 51,200.00 59,600.00
L.01 0.4 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.02 OH Mandor 100,000.00 110,000.00 2,000.00 2,200.00
B Bahan 57,010.00 59,365.00
3.5 Buah Nok Genteng Beton 10,000.00 10,050.00 35,000.00 35,175.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
10.8 Kg Portland Semen 1,050.00 1,062.50 11,340.00 11,475.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
1 Kg Semen Warna 11,000.00 15,000.00 11,000.00 15,000.00

file:///conversion/tmp/scratch/469226324.xls 193/118 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 108,210.00 118,965.00
E Overhead & Profit (contoh 10%) 10% 10,821.00 11,896.50
F Harga Satuan Pekerjaan (D+E) 119,031.00 130,861.50

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 121,306.35 134,651.00


A Tenaga 35,850.00 40,535.00
L.01 0.125 OH Pekerja 70,000.00 85,000.00 8,750.00 10,625.00
L.02 0.250 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 74,428.50 81,875.00
2.0 Buah Nok Genteng Beton 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
0.0035 m3 Balok Kayu 5,051,000.00 6,000,000.00 17,678.50 21,000.00
C PERALATAN
D Jumlah A + B + C 110,278.50 122,410.00
E Overhead & Profit (contoh 10%) 10% 11,027.85 12,241.00
F Harga Satuan Pekerjaan (D+E) 121,306.35 134,651.00

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 63,195.00 72,440.50


A Tenaga 34,700.00 40,230.00
L.01 0.250 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.150 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 22,750.00 25,625.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 57,450.00 65,855.00
E Overhead & Profit (contoh 10%) 10% 5,745.00 6,585.50
F Harga Satuan Pekerjaan (D+E) 63,195.00 72,440.50

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 52,690.00 59,906.00


A Tenaga 35,850.00 40,535.00
L.01 0.125 OH Pekerja 70,000.00 85,000.00 8,750.00 10,625.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 12,050.00 13,925.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 10,400.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 900.00 1,050.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 47,900.00 54,460.00
E Overhead & Profit (contoh 10%) 10% 4,790.00 5,446.00
F Harga Satuan Pekerjaan (D+E) 52,690.00 59,906.00

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 37,246.00 43,153.00


A Tenaga 15,360.00 17,880.00
L.01 0.12 OH Pekerja 70,000.00 85,000.00 8,400.00 10,200.00
L.02 0.06 OH Tukang Kayu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 18,500.00 21,350.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,000.00 30,000.00 18,200.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 300.00 350.00
C PERALATAN
D Jumlah A + B + C 33,860.00 39,230.00
E Overhead & Profit (contoh 10%) 10% 3,386.00 3,923.00
F Harga Satuan Pekerjaan (D+E) 37,246.00 43,153.00

file:///conversion/tmp/scratch/469226324.xls 193/119 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 29,612.00 34,430.00
A Tenaga 18,520.00 21,600.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 8,400.00 9,700.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 7,800.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 600.00 700.00
C PERALATAN
D Jumlah A + B + C 26,920.00 31,300.00
E Overhead & Profit (contoh 10%) 10% 2,692.00 3,130.00
F Harga Satuan Pekerjaan (D+E) 29,612.00 34,430.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 26,922.50 50,303.00


A Tenaga 16,600.00 19,480.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 7,875.00 26,250.00
1.05 m2 Sisalation / Allumunium Foil 7,500.00 25,000.00 7,875.00 26,250.00
C PERALATAN
D Jumlah A + B + C 24,475.00 45,730.00
E Overhead & Profit (contoh 10%) 10% 2,447.50 4,573.00
F Harga Satuan Pekerjaan (D+E) 26,922.50 50,303.00

file:///conversion/tmp/scratch/469226324.xls 193/120 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 27,260,475.00 28,250,612.50
Kayu klas I
A Tenaga 2,751,000.00 3,090,500.00
L.01 7 OH Pekerja 70,000.00 85,000.00 490,000.00 595,000.00
L.02 21 OH Tukang Kayu 95,000.00 105,000.00 1,995,000.00 2,205,000.00
L.03 2.10 OH Kepala Tukang 110,000.00 120,000.00 231,000.00 252,000.00
L.04 0.35 OH Mandor 100,000.00 110,000.00 35,000.00 38,500.00
B Bahan 22,031,250.00 22,591,875.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,000,000.00 20,500,000.00 22,000,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 24,782,250.00 25,682,375.00
E Overhead & Profit (contoh 10%) 10% 2,478,225.00 2,568,237.50
F Harga Satuan Pekerjaan (D+E) 27,260,475.00 28,250,612.50

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 10,680,175.00 12,859,962.50
Kayu klas II atau III
Tenaga 2,358,000.00 2,649,000.00
L.01 6.00 OH Pekerja 70,000.00 85,000.00 420,000.00 510,000.00
L.02 18.00 OH Tukang Kayu 95,000.00 105,000.00 1,710,000.00 1,890,000.00
L.03 1.80 OH Kepala Tukang 110,000.00 120,000.00 198,000.00 216,000.00
L.04 0.30 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
Bahan 7,351,250.00 9,041,875.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,100,000.00 7,500,000.00 7,320,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 9,709,250.00 11,690,875.00
E Overhead & Profit (contoh 10%) 10% 970,925.00 1,169,087.50
F Harga Satuan Pekerjaan (D+E) 10,680,175.00 12,859,962.50

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 468,985.00 514,200.50
Kayu Klas II (Kayu Kamfer)
A Tenaga 137,600.00 154,580.00
L.01 0.35 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 1.05 OH Tukang Kayu 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 426,350.00 467,455.00
E Overhead & Profit (contoh 10%) 10% 42,635.00 46,745.50
F Harga Satuan Pekerjaan (D+E) 468,985.00 514,200.50

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 468,985.00 514,200.50
Sederhana Kayu Klas III
Tenaga 137,600.00 154,580.00
L.01 0.35 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 1.05 OH Tukang Kayu 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 426,350.00 467,455.00
E Overhead & Profit (contoh 10%) 10% 42,635.00 46,745.50
F Harga Satuan Pekerjaan (D+E) 468,985.00 514,200.50

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 749,787.50 829,950.00
Klas I atau II
A Tenaga 393,000.00 441,500.00
L.01 1.00 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 3.00 OH Tukang Kayu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 288,625.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 681,625.00 754,500.00
E Overhead & Profit (contoh 10%) 10% 68,162.50 75,450.00
F Harga Satuan Pekerjaan (D+E) 749,787.50 829,950.00

file:///conversion/tmp/scratch/469226324.xls 193/121 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 540,045.00 601,040.00
Kayu Klas I atau II
A Tenaga 314,400.00 353,200.00
L.01 0.800 OH Pekerja 70,000.00 85,000.00 56,000.00 68,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 176,550.00 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 172,800.00 187,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 490,950.00 546,400.00
E Overhead & Profit (contoh 10%) 10% 49,095.00 54,640.00
F Harga Satuan Pekerjaan (D+E) 540,045.00 601,040.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 1,987,975.00 2,115,850.00
Kayu Klas I atau II (jati)
A Tenaga 393,000.00 441,500.00
L.01 1 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 3 OH Tukang Kayu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,414,250.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,807,250.00 1,923,500.00
E Overhead & Profit (contoh 10%) 10% 180,725.00 192,350.00
F Harga Satuan Pekerjaan (D+E) 1,987,975.00 2,115,850.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 579,480.00 654,032.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 275,100.00 309,050.00


L.01 0.700 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 2.100 OH Tukang Kayu 95,000.00 105,000.00 199,500.00 220,500.00
L.03 0.210 OH Kepala Tukang 110,000.00 120,000.00 23,100.00 25,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 251,700.00 285,525.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 526,800.00 594,575.00
E Overhead & Profit (contoh 10%) 10% 52,680.00 59,457.50
F Harga Satuan Pekerjaan (D+E) 579,480.00 654,032.50

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 627,462.00 707,745.50
rangka expose kayu klas I atau II
A Tenaga 314,400.00 353,200.00
L.01 0.800 OH Pekerja 70,000.00 85,000.00 56,000.00 68,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 256,020.00 290,205.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 184,320.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 570,420.00 643,405.00
E Overhead & Profit (contoh 10%) 10% 57,042.00 64,340.50
F Harga Satuan Pekerjaan (D+E) 627,462.00 707,745.50

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 1,776,115.00 1,881,467.50
Klas I atau II
A Tenaga 292,400.00 327,800.00
L.01 0.670 OH Pekerja 70,000.00 85,000.00 46,900.00 56,950.00
L.02 2.000 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.03 0.200 OH Kepala Tukang 110,000.00 120,000.00 22,000.00 24,000.00
L.04 0.335 OH Mandor 100,000.00 110,000.00 33,500.00 36,850.00
B Bahan 1,322,250.00 1,382,625.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 1,614,650.00 1,710,425.00
E Overhead & Profit (contoh 10%) 10% 161,465.00 171,042.50
F Harga Satuan Pekerjaan (D+E) 1,776,115.00 1,881,467.50

file:///conversion/tmp/scratch/469226324.xls 193/122 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,026,960.00 1,116,197.50
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 314,400.00 353,200.00
L.01 0.80 OH Pekerja 70,000.00 85,000.00 56,000.00 68,000.00
L.02 2.40 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.24 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.04 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 619,200.00 661,525.00
0.025 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 550,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 933,600.00 1,014,725.00
E Overhead & Profit (contoh 10%) 10% 93,360.00 101,472.50
F Harga Satuan Pekerjaan (D+E) 1,026,960.00 1,116,197.50

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 676,005.00 758,950.50
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 334,100.00 375,330.00


L.01 0.850 OH Pekerja 70,000.00 85,000.00 59,500.00 72,250.00
L.02 2.550 OH Tukang Kayu 95,000.00 105,000.00 242,250.00 267,750.00
L.03 0.255 OH Kepala Tukang 110,000.00 120,000.00 28,050.00 30,600.00
L.04 0.043 OH Mandor 100,000.00 110,000.00 4,300.00 4,730.00
B Bahan 280,450.00 314,625.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
0.5 Lbr Formika 68,000.00 75,000.00 34,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 614,550.00 689,955.00
E Overhead & Profit (contoh 10%) 10% 61,455.00 68,995.50
F Harga Satuan Pekerjaan (D+E) 676,005.00 758,950.50

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 9,417,100.00 11,356,400.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,572,000.00 1,766,000.00
L.01 4 OH Pekerja 70,000.00 85,000.00 280,000.00 340,000.00
L.02 12 OH Tukang Kayu 95,000.00 105,000.00 1,140,000.00 1,260,000.00
L.03 1.2 OH Kepala Tukang 110,000.00 120,000.00 132,000.00 144,000.00
L.04 0.2 OH Mandor 100,000.00 110,000.00 20,000.00 22,000.00
B Bahan 6,989,000.00 8,558,000.00
1.1 m3 Kayu Kamfer, balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 13,000.00 14,000.00 195,000.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 8,561,000.00 10,324,000.00
E Overhead & Profit (contoh 10%) 10% 856,100.00 1,032,400.00
F Harga Satuan Pekerjaan (D+E) 9,417,100.00 11,356,400.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 29,603,310.00 30,652,655.00
Expose, Kayu Klas I
A Tenaga 2,633,100.00 2,958,050.00
L.01 6.7 OH Pekerja 70,000.00 85,000.00 469,000.00 569,500.00
L.02 20.1 OH Tukang Kayu 95,000.00 105,000.00 1,909,500.00 2,110,500.00
L.03 2.01 OH Kepala Tukang 110,000.00 120,000.00 221,100.00 241,200.00
L.04 0.335 OH Mandor 100,000.00 110,000.00 33,500.00 36,850.00
B Bahan 24,279,000.00 24,908,000.00
1.2 m3 Kayu Klas I (jati), balok 20,000,000.00 20,500,000.00 24,000,000.00 24,600,000.00
15 Kg Besi Strip 13,000.00 14,000.00 195,000.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 26,912,100.00 27,866,050.00
E Overhead & Profit (contoh 10%) 10% 2,691,210.00 2,786,605.00
F Harga Satuan Pekerjaan (D+E) 29,603,310.00 30,652,655.00

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 8,682,520.00 10,529,310.00


A Tenaga 943,200.00 1,059,600.00
L.01 2.4 OH Pekerja 70,000.00 85,000.00 168,000.00 204,000.00
L.02 7.2 OH Tukang Kayu 95,000.00 105,000.00 684,000.00 756,000.00
L.03 0.72 OH Kepala Tukang 110,000.00 120,000.00 79,200.00 86,400.00
L.04 0.12 OH Mandor 100,000.00 110,000.00 12,000.00 13,200.00

file:///conversion/tmp/scratch/469226324.xls 193/123 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 6,950,000.00 8,512,500.00
1.1 m3 Kayu Klas I (Kamfer), balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 13,000.00 14,000.00 195,000.00 210,000.00
3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 45,000.00 52,500.00
C PERALATAN
D Jumlah A + B + C 7,893,200.00 9,572,100.00
E Overhead & Profit (contoh 10%) 10% 789,320.00 957,210.00
F Harga Satuan Pekerjaan (D+E) 8,682,520.00 10,529,310.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 142,131.00 172,837.50
Klas II
A Tenaga 18,100.00 20,750.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 111,110.00 136,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0036 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 21,960.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 129,210.00 157,125.00
E Overhead & Profit (contoh 10%) 10% 12,921.00 15,712.50
F Harga Satuan Pekerjaan (D+E) 142,131.00 172,837.50

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 1 m2 166,287.00 202,537.50
Klas II
A Tenaga 18,100.00 20,750.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 133,070.00 163,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 43,920.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 151,170.00 184,125.00
E Overhead & Profit (contoh 10%) 10% 15,117.00 18,412.50
F Harga Satuan Pekerjaan (D+E) 166,287.00 202,537.50

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 121,132.00 146,740.00


A Tenaga 21,720.00 24,900.00
L.01 0.12 OH Pekerja 70,000.00 85,000.00 8,400.00 10,200.00
L.02 0.12 OH Tukang Kayu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 88,400.00 108,500.00
0.014 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 110,120.00 133,400.00
E Overhead & Profit (contoh 10%) 10% 11,012.00 13,340.00
F Harga Satuan Pekerjaan (D+E) 121,132.00 146,740.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 161,414.00 192,610.00
Klas II atau III
A Tenaga 49,800.00 56,100.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.30 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 96,940.00 119,000.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 93,940.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 146,740.00 175,100.00
E Overhead & Profit (contoh 10%) 10% 14,674.00 17,510.00
F Harga Satuan Pekerjaan (D+E) 161,414.00 192,610.00

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 164,978.00 197,807.50
Klas II atau III
A Tenaga 46,800.00 53,200.00
L.01 0.2 OH Pekerja 70,000.00 85,000.00 14,000.00 17,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

file:///conversion/tmp/scratch/469226324.xls 193/124 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 103,180.00 126,625.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 99,430.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 149,980.00 179,825.00
E Overhead & Profit (contoh 10%) 10% 14,998.00 17,982.50
F Harga Satuan Pekerjaan (D+E) 164,978.00 197,807.50

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 294,580.00 310,860.00
II
A Tenaga 28,700.00 32,450.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 239,100.00 250,150.00
0.0108 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 237,600.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
C PERALATAN
D Jumlah A + B + C 267,800.00 282,600.00
E Overhead & Profit (contoh 10%) 10% 26,780.00 28,260.00
F Harga Satuan Pekerjaan (D+E) 294,580.00 310,860.00

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 119,515.00 131,037.50
klas II
A Tenaga 28,700.00 32,450.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 79,950.00 86,675.00
0.011 m3 Kayu klas II (Kamfer), papan 7,200,000.00 7,800,000.00 79,200.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 108,650.00 119,125.00
E Overhead & Profit (contoh 10%) 10% 10,865.00 11,912.50
F Harga Satuan Pekerjaan (D+E) 119,515.00 131,037.50

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 255,255.00 306,795.50
Kayu klas II atau III
A Tenaga 59,000.00 66,280.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.45 OH Tukang Kayu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 173,050.00 212,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 232,050.00 278,905.00
E Overhead & Profit (contoh 10%) 10% 23,205.00 27,890.50
F Harga Satuan Pekerjaan (D+E) 255,255.00 306,795.50

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 324,445.00 394,795.50
Rangka Kayu Klas II
A Tenaga 59,000.00 66,280.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.45 OH Tukang Kayu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 235,950.00 292,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 294,950.00 358,905.00
E Overhead & Profit (contoh 10%) 10% 29,495.00 35,890.50
F Harga Satuan Pekerjaan (D+E) 324,445.00 394,795.50

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 332,145.00 402,187.50
Rangka Kayu Klas II
A Tenaga 66,000.00 73,000.00
L.01 0.020 OH Pekerja 70,000.00 85,000.00 1,400.00 1,700.00
L.02 0.600 OH Tukang Kayu 95,000.00 105,000.00 57,000.00 63,000.00
L.03 0.060 OH Kepala Tukang 110,000.00 120,000.00 6,600.00 7,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

file:///conversion/tmp/scratch/469226324.xls 193/125 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 235,950.00 292,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 301,950.00 365,625.00
E Overhead & Profit (contoh 10%) 10% 30,195.00 36,562.50
F Harga Satuan Pekerjaan (D+E) 332,145.00 402,187.50

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 431,420.00 471,735.00

A Tenaga 235,800.00 264,900.00


L.01 0.6 OH Pekerja 70,000.00 85,000.00 42,000.00 51,000.00
L.02 1.8 OH Tukang Kayu 95,000.00 105,000.00 171,000.00 189,000.00
L.03 0.18 OH Kepala Tukang 110,000.00 120,000.00 19,800.00 21,600.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 156,400.00 163,950.00
0.007 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 154,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
0.15 Kg Paku Sekrup 3,5" 6,000.00 8,000.00 900.00 1,200.00
C PERALATAN
D Jumlah A + B + C 392,200.00 428,850.00
E Overhead & Profit (contoh 10%) 10% 39,220.00 42,885.00
F Harga Satuan Pekerjaan (D+E) 431,420.00 471,735.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 38,065.50 46,139.50
ukuran (120x240) cm
A Tenaga 9,855.00 11,070.00
L.01 0.025 OH Pekerja 70,000.00 85,000.00 1,750.00 2,125.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.0080 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.0010 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 24,750.00 30,875.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 60,000.00 75,000.00 24,000.00 30,000.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 34,605.00 41,945.00
E Overhead & Profit (contoh 10%) 10% 3,460.50 4,194.50
F Harga Satuan Pekerjaan (D+E) 38,065.50 46,139.50

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 121,213.84 141,542.50
IV
A Tenaga 12,800.00 14,900.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 97,394.40 113,775.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,700,000.00 67,200.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 180.00 210.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 110,194.40 128,675.00
E Overhead & Profit (contoh 10%) 10% 11,019.44 12,867.50
F Harga Satuan Pekerjaan (D+E) 121,213.84 141,542.50

file:///conversion/tmp/scratch/469226324.xls 193/126 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 175,780.00 231,110.00
A Tenaga 49,800.00 55,100.00
L.01 0.01 OH Pekerja 70,000.00 85,000.00 700.00 850.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 110,000.00 155,000.00
1 Buah Kunci Tanam Biasa 110,000.00 155,000.00 110,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 159,800.00 210,100.00
E Overhead & Profit (contoh 10%) 10% 15,980.00 21,010.00
F Harga Satuan Pekerjaan (D+E) 175,780.00 231,110.00
Overhead & Profit (contoh 10%)
2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 152,515.00 163,680.00
A Tenaga 48,650.00 53,800.00
L.01 0.005 OH Pekerja 70,000.00 85,000.00 350.00 425.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 90,000.00 95,000.00
1 Buah Kunci Tanam Kamar Mandi 90,000.00 95,000.00 90,000.00 95,000.00
C PERALATAN
D Jumlah A + B + C 138,650.00 148,800.00
E Overhead & Profit (contoh 10%) 10% 13,865.00 14,880.00
F Harga Satuan Pekerjaan (D+E) 152,515.00 163,680.00

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 174,515.00 229,680.00


A Tenaga 48,650.00 53,800.00
L.01 0.005 OH Pekerja 70,000.00 85,000.00 350.00 425.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 110,000.00 155,000.00
1 Buah Kunci Selinder 110,000.00 155,000.00 110,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 158,650.00 208,800.00
E Overhead & Profit (contoh 10%) 10% 15,865.00 20,880.00
F Harga Satuan Pekerjaan (D+E) 174,515.00 229,680.00

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 26,070.00 31,515.00


A Tenaga 17,700.00 19,650.00
L.01 0.015 OH Pekerja 70,000.00 85,000.00 1,050.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.0075 OH Mandor 100,000.00 110,000.00 750.00 825.00
B Bahan 6,000.00 9,000.00
1 Buah Engsel pintu 6,000.00 9,000.00 6,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 23,700.00 28,650.00
E Overhead & Profit (contoh 10%) 10% 2,370.00 2,865.00
F Harga Satuan Pekerjaan (D+E) 26,070.00 31,515.00

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 17,380.00 21,010.00


A Tenaga 11,800.00 13,100.00
L.01 0.01 OH Pekerja 70,000.00 85,000.00 700.00 850.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 4,000.00 6,000.00
1 Buah Engsel Jendela 4,000.00 6,000.00 4,000.00 6,000.00
C PERALATAN
D Jumlah A + B + C 15,800.00 19,100.00
E Overhead & Profit (contoh 10%) 10% 1,580.00 1,910.00
F Harga Satuan Pekerjaan (D+E) 17,380.00 21,010.00

file:///conversion/tmp/scratch/469226324.xls 193/127 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 47,575.00 62,650.50
A Tenaga 28,250.00 31,955.00
L.01 0.10 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.02 0.20 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00
B Bahan 15,000.00 25,000.00
1 Buah Engsel Angin 15,000.00 25,000.00 15,000.00 25,000.00
C PERALATAN
D Jumlah A + B + C 43,250.00 56,955.00
E Overhead & Profit (contoh 10%) 10% 4,325.00 5,695.50
F Harga Satuan Pekerjaan (D+E) 47,575.00 62,650.50

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 36,025.00 40,925.50


A Tenaga 17,750.00 19,705.00
L.01 0.015 OH Pekerja 70,000.00 85,000.00 1,050.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 15,000.00 17,500.00
1 Buah Kait Angin 15,000.00 17,500.00 15,000.00 17,500.00
C PERALATAN
D Jumlah A + B + C 32,750.00 37,205.00
E Overhead & Profit (contoh 10%) 10% 3,275.00 3,720.50
F Harga Satuan Pekerjaan (D+E) 36,025.00 40,925.50

8 A.4.6.2.10 1 Buah Pasang Door Closer 364,925.00 454,327.50


A Tenaga 56,750.00 63,025.00
L.01 0.05 OH Pekerja 70,000.00 85,000.00 3,500.00 4,250.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 331,750.00 413,025.00
E Overhead & Profit (contoh 10%) 10% 33,175.00 41,302.50
F Harga Satuan Pekerjaan (D+E) 364,925.00 454,327.50

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 33,770.00 38,731.00


A Tenaga 22,700.00 25,210.00
L.01 0.02 OH Pekerja 70,000.00 85,000.00 1,400.00 1,700.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 8,000.00 10,000.00
1 Buah Kunci Selot 8,000.00 10,000.00 8,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 30,700.00 35,210.00
E Overhead & Profit (contoh 10%) 10% 3,070.00 3,521.00
F Harga Satuan Pekerjaan (D+E) 33,770.00 38,731.00

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 314,985.00 398,865.50


A Tenaga 11,350.00 12,605.00
L.01 0.01 OH Pekerja 70,000.00 85,000.00 700.00 850.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 286,350.00 362,605.00
E Overhead & Profit (contoh 10%) 10% 28,635.00 36,260.50
F Harga Satuan Pekerjaan (D+E) 314,985.00 398,865.50

file:///conversion/tmp/scratch/469226324.xls 193/128 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 272,910.00 341,693.00
A Tenaga 68,100.00 75,630.00
L.01 0.06 OH Pekerja 70,000.00 85,000.00 4,200.00 5,100.00
L.02 0.6 OH Tukang Kayu 95,000.00 105,000.00 57,000.00 63,000.00
L.03 0.06 OH Kepala Tukang 110,000.00 120,000.00 6,600.00 7,200.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 180,000.00 235,000.00
1 Buah Rel Pintu Dorong 180,000.00 235,000.00 180,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 248,100.00 310,630.00
E Overhead & Profit (contoh 10%) 10% 24,810.00 31,063.00
F Harga Satuan Pekerjaan (D+E) 272,910.00 341,693.00

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 44,968.00 51,169.80


A Tenaga 28,380.00 31,518.00
L.01 0.025 OH Pekerja 70,000.00 85,000.00 1,750.00 2,125.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.00130 OH Mandor 100,000.00 110,000.00 130.00 143.00
B Bahan 12,500.00 15,000.00
1 Buah Kunci Lemari 12,500.00 15,000.00 12,500.00 15,000.00
C PERALATAN
D Jumlah A + B + C 40,880.00 46,518.00
E Overhead & Profit (contoh 10%) 10% 4,088.00 4,651.80
F Harga Satuan Pekerjaan (D+E) 44,968.00 51,169.80

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 103,427.50 123,648.25


A Tenaga 17,025.00 18,907.50
L.01 0.015 OH Pekerja 70,000.00 85,000.00 1,050.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 77,000.00 93,500.00
1.1 m2 Kaca tebal 3mm 70,000.00 85,000.00 77,000.00 93,500.00
C PERALATAN
D Jumlah A + B + C 94,025.00 112,407.50
E Overhead & Profit (contoh 10%) 10% 9,402.50 11,240.75
F Harga Satuan Pekerjaan (D+E) 103,427.50 123,648.25

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 127,627.50 135,748.25


A Tenaga 17,025.00 18,907.50
L.01 0.015 OH Pekerja 70,000.00 85,000.00 1,050.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 99,000.00 104,500.00
1.1 m2 Kaca tebal 5mm 90,000.00 95,000.00 99,000.00 104,500.00
C PERALATAN
D Jumlah A + B + C 116,025.00 123,407.50
E Overhead & Profit (contoh 10%) 10% 11,602.50 12,340.75
F Harga Satuan Pekerjaan (D+E) 127,627.50 135,748.25

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 290,977.50 353,548.25


A Tenaga 17,025.00 18,907.50
L.01 0.015 OH Pekerja 70,000.00 85,000.00 1,050.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 247,500.00 302,500.00
1.1 m2 Kaca Cermin 225,000.00 275,000.00 247,500.00 302,500.00
C PERALATAN
D Jumlah A + B + C 264,525.00 321,407.50
E Overhead & Profit (contoh 10%) 10% 26,452.50 32,140.75
F Harga Satuan Pekerjaan (D+E) 290,977.50 353,548.25

file:///conversion/tmp/scratch/469226324.xls 193/129 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 12,540.00 15,213.00
Lama
A Tenaga 10,800.00 13,080.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 600.00 750.00
0.05 Kg Soda Api 12,000.00 15,000.00 600.00 750.00
C PERALATAN
D Jumlah A + B + C 11,400.00 13,830.00
E Overhead & Profit (contoh 10%) 10% 1,140.00 1,383.00
F Harga Satuan Pekerjaan (D+E) 12,540.00 15,213.00

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 12,485.00 15,103.00
dicat
A Tenaga 10,800.00 13,080.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 11,350.00 13,730.00
E Overhead & Profit (contoh 10%) 10% 1,135.00 1,373.00
F Harga Satuan Pekerjaan (D+E) 12,485.00 15,103.00

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 13,035.00 15,708.00
manual
A Tenaga 11,300.00 13,630.00
L.01 0.15 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.04 0.0080 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 11,850.00 14,280.00
E Overhead & Profit (contoh 10%) 10% 1,185.00 1,428.00
F Harga Satuan Pekerjaan (D+E) 13,035.00 15,708.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 38,434.00 47,294.50
dasar, 2 Lp Cat Penutup)
A Tenaga 6,715.00 7,945.00
L.01 0.070 OH Pekerja 70,000.00 85,000.00 4,900.00 5,950.00
L.02 0.009 OH Tukang Cat 95,000.00 105,000.00 855.00 945.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 28,225.00 35,050.00
0.2000 kg Cat Menie 23,000.00 30,000.00 4,600.00 6,000.00
0.1500 kg Plamuur 16,000.00 30,000.00 2,400.00 4,500.00
0.1700 kg Cat Dasar 35,000.00 40,000.00 5,950.00 6,800.00
0.2600 kg Cat Penutup 55,000.00 62,500.00 14,300.00 16,250.00
0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00
0.0300 kg Pengencer 10,000.00 20,000.00 300.00 600.00
0.2000 lbr Amplas 3,000.00 4,100.00 600.00 820.00
C PERALATAN
D Jumlah A + B + C 34,940.00 42,995.00
E Overhead & Profit (contoh 10%) 10% 3,494.00 4,299.50
F Harga Satuan Pekerjaan (D+E) 38,434.00 47,294.50

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 53,669.00 64,306.00
dasar, 3 Lp Cat Penutup)
A Tenaga 15,615.00 17,785.00
L.01 0.070 OH Pekerja 70,000.00 85,000.00 4,900.00 5,950.00
L.02 0.105 OH Tukang Cat 95,000.00 105,000.00 9,975.00 11,025.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

file:///conversion/tmp/scratch/469226324.xls 193/130 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 33,175.00 40,675.00
0.2000 kg Cat Menie 23,000.00 30,000.00 4,600.00 6,000.00
0.1500 kg Plamuur 16,000.00 30,000.00 2,400.00 4,500.00
0.1700 kg Cat Dasar 35,000.00 40,000.00 5,950.00 6,800.00
0.3500 kg Cat Penutup 55,000.00 62,500.00 19,250.00 21,875.00
0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00
0.0300 kg Pengencer 10,000.00 20,000.00 300.00 600.00
0.2000 lbr Amplas 3,000.00 4,100.00 600.00 820.00
C PERALATAN
D Jumlah A + B + C 48,790.00 58,460.00
E Overhead & Profit (contoh 10%) 10% 4,879.00 5,846.00
F Harga Satuan Pekerjaan (D+E) 53,669.00 64,306.00

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 33,852.50 36,327.50


A Tenaga 16,015.00 17,905.00
L.01 0.04 OH Pekerja 70,000.00 85,000.00 2,800.00 3,400.00
L.02 0.063 OH Tukang Cat 95,000.00 105,000.00 5,985.00 6,615.00
L.03 0.063 OH Kepala Tukang 110,000.00 120,000.00 6,930.00 7,560.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 30,775.00 33,025.00
E Overhead & Profit (contoh 10%) 10% 3,077.50 3,302.50
F Harga Satuan Pekerjaan (D+E) 33,852.50 36,327.50

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 53,242.20 59,488.00


A Tenaga 10,560.00 11,950.00
L.01 0.04 OH Pekerja 70,000.00 85,000.00 2,800.00 3,400.00
L.02 0.06 OH Tukang Cat 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.016 OH Kepala Tukang 110,000.00 120,000.00 1,760.00 1,920.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 37,842.00 42,130.00
0.15 Ltr Politur 61,000.00 65,000.00 9,150.00 9,750.00
0.372 Ltr Politur Jadi 61,000.00 65,000.00 22,692.00 24,180.00
2 Lbr Ampelas 3,000.00 4,100.00 6,000.00 8,200.00
C PERALATAN
D Jumlah A + B + C 48,402.00 54,080.00
E Overhead & Profit (contoh 10%) 10% 4,840.20 5,408.00
F Harga Satuan Pekerjaan (D+E) 53,242.20 59,488.00

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 9,418.75 11,231.00
A Tenaga 7,600.00 9,160.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 8,562.50 10,210.00
E Overhead & Profit (contoh 10%) 10% 856.25 1,021.00
F Harga Satuan Pekerjaan (D+E) 9,418.75 11,231.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 36,641.00 42,141.00


A Tenaga 28,460.00 32,650.00
L.01 0.16 OH Pekerja 70,000.00 85,000.00 11,200.00 13,600.00
L.02 0.16 OH Tukang Cat 95,000.00 105,000.00 15,200.00 16,800.00
L.03 0.016 OH Kepala Tukang 110,000.00 120,000.00 1,760.00 1,920.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 4,850.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 16,000.00 30,000.00 800.00 1,500.00
0.1 Lbr Ampelas 3,000.00 4,100.00 300.00 410.00
C PERALATAN
D Jumlah A + B + C 33,310.00 38,310.00
E Overhead & Profit (contoh 10%) 10% 3,331.00 3,831.00
F Harga Satuan Pekerjaan (D+E) 36,641.00 42,141.00

file:///conversion/tmp/scratch/469226324.xls 193/131 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 18,873.80 22,947.10
Lap.Cat Penutup)
A Tenaga 8,378.00 9,401.00
L.01 0.02 OH Pekerja 70,000.00 85,000.00 1,400.00 1,700.00
L.02 0.063 OH Tukang Cat 95,000.00 105,000.00 5,985.00 6,615.00
L.03 0.0063 OH Kepala Tukang 110,000.00 120,000.00 693.00 756.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 8,780.00 11,460.00
0.1 Kg Plamir 16,000.00 32,000.00 1,600.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 26,000.00 5,980.00 6,760.00
C PERALATAN
D Jumlah A + B + C 17,158.00 20,861.00
E Overhead & Profit (contoh 10%) 10% 1,715.80 2,086.10
F Harga Satuan Pekerjaan (D+E) 18,873.80 22,947.10

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 13,521.20 15,514.40
Penutup)
A Tenaga 6,712.00 7,624.00
L.01 0.028 OH Pekerja 70,000.00 85,000.00 1,960.00 2,380.00
L.02 0.042 OH Tukang Cat 95,000.00 105,000.00 3,990.00 4,410.00
L.03 0.0042 OH Kepala Tukang 110,000.00 120,000.00 462.00 504.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 5,580.00 6,480.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 26,000.00 4,140.00 4,680.00
C PERALATAN
D Jumlah A + B + C 12,292.00 14,104.00
E Overhead & Profit (contoh 10%) 10% 1,229.20 1,410.40
F Harga Satuan Pekerjaan (D+E) 13,521.20 15,514.40

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 7,845.20 8,936.40


A Tenaga 6,712.00 7,624.00
L.01 0.028 OH Pekerja 70,000.00 85,000.00 1,960.00 2,380.00
L.02 0.042 OH Tukang Cat 95,000.00 105,000.00 3,990.00 4,410.00
L.03 0.0042 OH Kepala Tukang 110,000.00 120,000.00 462.00 504.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 420.00 500.00
0.1 Kg Kalkarium 4,200.00 5,000.00 420.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 7,132.00 8,124.00
E Overhead & Profit (contoh 10%) 10% 713.20 812.40
F Harga Satuan Pekerjaan (D+E) 7,845.20 8,936.40

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 13,852.85 16,777.20


A Tenaga 10,856.00 13,142.00
L.01 0.150 OH Pekerja 70,000.00 85,000.00 10,500.00 12,750.00
L.02 0.001 OH Tukang Cat 95,000.00 105,000.00 95.00 105.00
L.03 0.0001 OH Kepala Tukang 110,000.00 120,000.00 11.00 12.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 1,737.50 2,110.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,000.00 4,100.00 300.00 410.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 12,593.50 15,252.00
E Overhead & Profit (contoh 10%) 10% 1,259.35 1,525.20
F Harga Satuan Pekerjaan (D+E) 13,852.85 16,777.20

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 6,344.25 7,705.50
(pemeliharaan)
A Tenaga 3,580.00 4,260.00
L.01 0.040 OH Pekerja 70,000.00 85,000.00 2,800.00 3,400.00
L.02 0.005 OH Tukang Cat 95,000.00 105,000.00 475.00 525.00
L.03 0.0005 OH Kepala Tukang 110,000.00 120,000.00 55.00 60.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00

file:///conversion/tmp/scratch/469226324.xls 193/132 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,187.50 2,745.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,000.00 4,100.00 600.00 820.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 5,767.50 7,005.00
E Overhead & Profit (contoh 10%) 10% 576.75 700.50
F Harga Satuan Pekerjaan (D+E) 6,344.25 7,705.50

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 83,435.00 95,012.50


A Tenaga 22,850.00 25,375.00
L.01 0.020 OH Pekerja 70,000.00 85,000.00 1,400.00 1,700.00
L.02 0.200 OH Tukang Cat 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.0200 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 75,850.00 86,375.00
E Overhead & Profit (contoh 10%) 10% 7,585.00 8,637.50
F Harga Satuan Pekerjaan (D+E) 83,435.00 95,012.50

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 25,762.00 30,211.50


A Tenaga 20,870.00 23,215.00
L.01 0.02 OH Pekerja 70,000.00 85,000.00 1,400.00 1,700.00
L.02 0.2 OH Tukang Cat 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 2,550.00 4,250.00
0.1 Kg Meni Besi 20,000.00 36,000.00 2,000.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 23,420.00 27,465.00
E Overhead & Profit (contoh 10%) 10% 2,342.00 2,746.50
F Harga Satuan Pekerjaan (D+E) 25,762.00 30,211.50

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 50,792.50 59,785.00
Perancah
A Tenaga 39,625.00 45,700.00
L.01 0.25 OH Pekerja 70,000.00 85,000.00 17,500.00 21,250.00
L.02 0.225 OH Tukang Cat 95,000.00 105,000.00 21,375.00 23,625.00
L.04 0.0075 OH Mandor 100,000.00 110,000.00 750.00 825.00
B Bahan 6,550.00 8,650.00
0.1 Kg Meni Besi 20,000.00 36,000.00 2,000.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 46,175.00 54,350.00
E Overhead & Profit (contoh 10%) 10% 4,617.50 5,435.00
F Harga Satuan Pekerjaan (D+E) 50,792.50 59,785.00

file:///conversion/tmp/scratch/469226324.xls 193/133 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 1,902,571.00 2,612,192.00
A Tenaga 351,610.00 413,720.00
L.01 3.3 OH Pekerja 70,000.00 85,000.00 231,000.00 280,500.00
L.02 1.1 OH Tukang Batu 95,000.00 105,000.00 104,500.00 115,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 120,000.00 110.00 120.00
L.04 0.16 OH Mandor 100,000.00 110,000.00 16,000.00 17,600.00
Buah Bahan 1,378,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,300,000.00 1,850,000.00 1,300,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,300,000.00 1,850,000.00 78,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 1,729,610.00 2,374,720.00
E Overhead & Profit (contoh 10%) 10% 172,961.00 237,472.00
F Harga Satuan Pekerjaan (D+E) 1,902,571.00 2,612,192.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 591,690.00 660,192.50
A Tenaga 393,500.00 440,100.00
L.01 1 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 1.5 OH Tukang Batu 95,000.00 105,000.00 142,500.00 157,500.00
L.03 1.5 OH Kepala Tukang 110,000.00 120,000.00 165,000.00 180,000.00
L.04 0.16 OH Mandor 100,000.00 110,000.00 16,000.00 17,600.00
B Bahan 144,400.00 160,075.00
1 Buah Kloset Jongkok 135,000.00 150,000.00 135,000.00 150,000.00
6 Kg Portland Semen 1,050.00 1,062.50 6,300.00 6,375.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 537,900.00 600,175.00
E Overhead & Profit (contoh 10%) 10% 53,790.00 60,017.50
F Harga Satuan Pekerjaan (D+E) 591,690.00 660,192.50

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 715,440.00 781,632.50


A Tenaga 186,000.00 213,000.00
L.01 1 OH Pekerja 70,000.00 85,000.00 70,000.00 85,000.00
L.02 1 OH Tukang Batu 95,000.00 105,000.00 95,000.00 105,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 120,000.00 11,000.00 12,000.00
L.04 0.1 OH Mandor 100,000.00 110,000.00 10,000.00 11,000.00
B Bahan 464,400.00 497,575.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,050.00 1,062.50 6,300.00 6,375.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 650,400.00 710,575.00
E Overhead & Profit (contoh 10%) 10% 65,040.00 71,057.50
F Harga Satuan Pekerjaan (D+E) 715,440.00 781,632.50

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 540,292.50 615,230.00


A Tenaga 124,275.00 146,225.00
L.01 1.2 OH Pekerja 70,000.00 85,000.00 84,000.00 102,000.00
L.02 0.145 OH Tukang Batu 95,000.00 105,000.00 13,775.00 15,225.00
L.03 0.15 OH Kepala Tukang 110,000.00 120,000.00 16,500.00 18,000.00
L.04 0.1 OH Mandor 100,000.00 110,000.00 10,000.00 11,000.00
B Bahan 366,900.00 413,075.00
1 Buah Wastafel 275,000.00 310,000.00 275,000.00 310,000.00
0.3 - Perlengkapan 30% Harga Wastafel 275,000.00 310,000.00 82,500.00 93,000.00
6 Kg Portland Semen 1,050.00 1,062.50 6,300.00 6,375.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 491,175.00 559,300.00
E Overhead & Profit (contoh 10%) 10% 49,117.50 55,930.00
F Harga Satuan Pekerjaan (D+E) 540,292.50 615,230.00

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,083,555.00 1,159,900.50


A Tenaga 85,050.00 94,455.00
L.01 0.075 OH Pekerja 70,000.00 85,000.00 5,250.00 6,375.00
L.02 0.75 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

file:///conversion/tmp/scratch/469226324.xls 193/134 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 985,050.00 1,054,455.00
E Overhead & Profit (contoh 10%) 10% 98,505.00 105,445.50
F Harga Satuan Pekerjaan (D+E) 1,083,555.00 1,159,900.50

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,145,100.00 1,285,350.00


A Tenaga 733,000.00 832,500.00

L.01 3 OH Pekerja 70,000.00 85,000.00 210,000.00 255,000.00


L.02 4.5 OH Tukang Batu 95,000.00 105,000.00 427,500.00 472,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.9 OH Mandor 100,000.00 110,000.00 90,000.00 99,000.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,041,000.00 1,168,500.00
E Overhead & Profit (contoh 10%) 10% 104,100.00 116,850.00
F Harga Satuan Pekerjaan (D+E) 1,145,100.00 1,285,350.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,430,429.27 1,626,988.54
A Tenaga 741,000.00 864,300.00
L.01 6.00 OH Pekerja 70,000.00 85,000.00 420,000.00 510,000.00
L.02 3.00 OH Tukang Batu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 559,390.24 614,780.49
150.0 bh Batu Bata 600.00 650.00 90,000.00 97,500.00
120 Kg Portland Semen 0.11 1,050.00 1,062.50 126,000.00 127,500.00
0.3 m3 Pasir Pasang 0.0121 310,000.00 370,000.00 93,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,300,390.24 1,479,080.49
E Overhead & Profit (contoh 10%) 10% 130,039.02 147,908.05
F Harga Satuan Pekerjaan (D+E) 1,430,429.27 1,626,988.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,059,703.90 6,843,079.33


A Tenaga 679,800.00 777,980.00
L.01 3.50 OH Pekerja 70,000.00 85,000.00 245,000.00 297,500.00
L.02 4.50 OH Tukang Batu 95,000.00 105,000.00 427,500.00 472,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 1,109,533.16 1,266,165.06 4,829,021.72 5,443,001.21
0.9 m3 Beton K.150 985,523.00 1,115,701.32 886,970.70 1,004,131.19
180 Kg Baja Tulangan 0.11 12,668.70 14,061.30 2,280,366.00 2,531,034.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,341.46 1,402.44 670,731.71 701,219.51
10 % Perlengkapan 1,109,533.16 1,266,165.06 110,953.32 126,616.51
C PERALATAN
D Jumlah A + B + C 5,508,821.72 6,220,981.21
E Overhead & Profit (contoh 10%) 10% 550,882.17 622,098.12
F Harga Satuan Pekerjaan (D+E) 6,059,703.90 6,843,079.33

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 341,440.00 384,230.00
A Tenaga 35,400.00 39,300.00
L.01 0.030 OH Pekerja 70,000.00 85,000.00 2,100.00 2,550.00
L.02 0.300 OH Tukang Batu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 310,400.00 349,300.00
E Overhead & Profit (contoh 10%) 10% 31,040.00 34,930.00
F Harga Satuan Pekerjaan (D+E) 341,440.00 384,230.00

file:///conversion/tmp/scratch/469226324.xls 193/135 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 40,480.00 52,910.00
A Tenaga 11,800.00 13,100.00
L.01 0.010 OH Pekerja 70,000.00 85,000.00 700.00 850.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 25,000.00 35,000.00
1 bh Floor Drain 25,000.00 35,000.00 25,000.00 35,000.00

C PERALATAN
D Jumlah A + B + C 36,800.00 48,100.00
E Overhead & Profit (contoh 10%) 10% 3,680.00 4,810.00
F Harga Satuan Pekerjaan (D+E) 40,480.00 52,910.00

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 416,448.91 474,317.89
35 cm
A Tenaga 228,620.00 269,050.00
L.01 2.160 OH Pekerja 70,000.00 85,000.00 151,200.00 183,600.00
L.02 0.720 OH Tukang Batu 95,000.00 105,000.00 68,400.00 75,600.00
L.03 0.072 OH Kepala Tukang 110,000.00 120,000.00 7,920.00 8,640.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00
B Bahan 149,969.92 162,148.08
40.00 bh Batu Bata 600.00 650.00 24,000.00 26,000.00
44.00 kg Semen Portland 1,050.00 1,062.50 46,200.00 46,750.00
0.07 m3 Pasir Pasang 310,000.00 370,000.00 21,700.00 25,900.00
0.06 m3 Pasir Beton 350,000.00 380,000.00 21,000.00 22,800.00
0.07 m3 Kerikil 240,000.00 260,000.00 16,800.00 18,200.00
1.60 kg Baja Tulangan 12,668.70 14,061.30 20,269.92 22,498.08
C PERALATAN
D Jumlah A + B + C 378,589.92 431,198.08
E Overhead & Profit (contoh 10%) 10% 37,858.99 43,119.81
F Harga Satuan Pekerjaan (D+E) 416,448.91 474,317.89

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 611,357.91 696,454.64
tinggi 50 cm
A Tenaga 336,060.00 395,830.00
L.01 3.200 OH Pekerja 70,000.00 85,000.00 224,000.00 272,000.00
L.02 1.150 OH Tukang Batu 95,000.00 105,000.00 109,250.00 120,750.00
L.03 0.011 OH Kepala Tukang 110,000.00 120,000.00 1,210.00 1,320.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 219,719.92 237,310.58
70.00 bh Batu Bata 600.00 650.00 42,000.00 45,500.00
77.00 kg Semen Portland 1,050.00 1,062.50 80,850.00 81,812.50
0.13 m3 Pasir Pasang 310,000.00 370,000.00 40,300.00 48,100.00
0.09 m3 Pasir Beton 350,000.00 380,000.00 31,500.00 34,200.00
0.02 m3 Kerikil 240,000.00 260,000.00 4,800.00 5,200.00
1.60 kg Baja Tulangan 12,668.70 14,061.30 20,269.92 22,498.08
C PERALATAN
D Jumlah A + B + C 555,779.92 633,140.58
E Overhead & Profit (contoh 10%) 10% 55,577.99 63,314.06
F Harga Satuan Pekerjaan (D+E) 611,357.91 696,454.64

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 744,527.51 840,820.54
60 cm
A Tenaga 336,060.00 395,830.00
L.01 3.200 OH Pekerja 70,000.00 85,000.00 224,000.00 272,000.00
L.02 1.150 OH Tukang Batu 95,000.00 105,000.00 109,250.00 120,750.00
L.03 0.011 OH Kepala Tukang 110,000.00 120,000.00 1,210.00 1,320.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 340,783.20 368,552.31
123.00 bh Batu Bata 600.00 650.00 73,800.00 79,950.00
114.00 kg Semen Portland 1,050.00 1,062.50 119,700.00 121,125.00
0.18 m3 Pasir Pasang 310,000.00 370,000.00 57,040.00 68,080.00
0.12 m3 Pasir Beton 240,000.00 260,000.00 28,800.00 31,200.00
4.85 kg Baja Tulangan 12,668.70 14,061.30 61,443.20 68,197.31
C PERALATAN
D Jumlah A + B + C 676,843.20 764,382.31
E Overhead & Profit (contoh 10%) 10% 67,684.32 76,438.23
F Harga Satuan Pekerjaan (D+E) 744,527.51 840,820.54

file:///conversion/tmp/scratch/469226324.xls 193/136 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 60,247.00 63,944.83
A Tenaga 16,020.00 18,090.00
L.01 0.054 OH Pekerja 70,000.00 85,000.00 3,780.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 38,750.00 40,041.67
1.20 m' Pipa Galvanis Ø ½" 25,000.00 25,833.33 30,000.00 31,000.00
0.35 Ls Perlengkapan 35% x pipa 25,000.00 25,833.33 8,750.00 9,041.67
C PERALATAN
D Jumlah A + B + C 54,770.00 58,131.67
E Overhead & Profit (contoh 10%) 10% 5,477.00 5,813.17
F Harga Satuan Pekerjaan (D+E) 60,247.00 63,944.83

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 75,465.50 102,531.00


A Tenaga 43,600.00 48,200.00
L.01 0.010 OH Pekerja 70,000.00 85,000.00 700.00 850.00
L.02 0.400 OH Tukang Batu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.040 OH Kepala Tukang 110,000.00 120,000.00 4,400.00 4,800.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 25,005.00 45,010.00
1.00 bh Kran Air 25,000.00 45,000.00 25,000.00 45,000.00
0.0025 bh Sealtape 2,000.00 4,000.00 5.00 10.00
C PERALATAN
D Jumlah A + B + C 68,605.00 93,210.00
E Overhead & Profit (contoh 10%) 10% 6,860.50 9,321.00
F Harga Satuan Pekerjaan (D+E) 75,465.50 102,531.00

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 71,613.67 75,311.50


A Tenaga 16,020.00 18,090.00
L.01 0.054 OH Pekerja 70,000.00 85,000.00 3,780.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 49,083.33 50,375.00
1.20 m' Pipa Galvanis Ø ¾" 31,666.67 32,500.00 38,000.00 39,000.00
0.35 Ls Perlengkapan 35% x pipa 31,666.67 32,500.00 11,083.33 11,375.00
C PERALATAN
D Jumlah A + B + C 65,103.33 68,465.00
E Overhead & Profit (contoh 10%) 10% 6,510.33 6,846.50
F Harga Satuan Pekerjaan (D+E) 71,613.67 75,311.50

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 102,872.00 106,569.83


A Tenaga 16,020.00 18,090.00
L.01 0.054 OH Pekerja 70,000.00 85,000.00 3,780.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 77,500.00 78,791.67
1.20 m' Pipa Galvanis Ø 1" 50,000.00 50,833.33 60,000.00 61,000.00
0.35 Ls Perlengkapan 35% x pipa 50,000.00 50,833.33 17,500.00 17,791.67
C PERALATAN
D Jumlah A + B + C 93,520.00 96,881.67
E Overhead & Profit (contoh 10%) 10% 9,352.00 9,688.17
F Harga Satuan Pekerjaan (D+E) 102,872.00 106,569.83

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 136,416.50 141,852.33


A Tenaga 27,140.00 30,790.00
L.01 0.108 OH Pekerja 70,000.00 85,000.00 7,560.00 9,180.00
L.02 0.180 OH Tukang Batu 95,000.00 105,000.00 17,100.00 18,900.00
L.03 0.018 OH Kepala Tukang 110,000.00 120,000.00 1,980.00 2,160.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 96,875.00 98,166.67
1.20 m' Pipa Galvanis Ø 1½" 62,500.00 63,333.33 75,000.00 76,000.00
0.35 Ls Perlengkapan 35% x pipa 62,500.00 63,333.33 21,875.00 22,166.67
C PERALATAN
D Jumlah A + B + C 124,015.00 128,956.67
E Overhead & Profit (contoh 10%) 10% 12,401.50 12,895.67
F Harga Satuan Pekerjaan (D+E) 136,416.50 141,852.33

file:///conversion/tmp/scratch/469226324.xls 193/137 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 246,323.00 252,776.33
A Tenaga 34,055.00 38,630.00
L.01 0.135 OH Pekerja 70,000.00 85,000.00 9,450.00 11,475.00
L.02 0.225 OH Tukang Batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 189,875.00 191,166.67
1.20 m' Pipa Galvanis Ø 3" 122,500.00 123,333.33 147,000.00 148,000.00
0.35 Ls Perlengkapan 35% x pipa 122,500.00 123,333.33 42,875.00 43,166.67
C PERALATAN
D Jumlah A + B + C 223,930.00 229,796.67
E Overhead & Profit (contoh 10%) 10% 22,393.00 22,979.67
F Harga Satuan Pekerjaan (D+E) 246,323.00 252,776.33

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 450,923.00 458,086.75


A Tenaga 34,055.00 38,630.00
L.01 0.135 OH Pekerja 70,000.00 85,000.00 9,450.00 11,475.00
L.02 0.225 OH Tukang Batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 375,875.00 377,812.50
1.20 m' Pipa Galvanis Ø 4" 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A + B + C 409,930.00 416,442.50
E Overhead & Profit (contoh 10%) 10% 40,993.00 41,644.25
F Harga Satuan Pekerjaan (D+E) 450,923.00 458,086.75

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 21,923.00 24,117.50


A Tenaga 9,080.00 10,300.00
L.01 0.036 OH Pekerja 70,000.00 85,000.00 2,520.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 10,850.00 11,625.00
1.20 m' Pipa PVC Ø ½" 7,000.00 7,500.00 8,400.00 9,000.00
0.35 Ls Perlengkapan 35% x pipa 7,000.00 7,500.00 2,450.00 2,625.00
C PERALATAN
D Jumlah A + B + C 19,930.00 21,925.00
E Overhead & Profit (contoh 10%) 10% 1,993.00 2,192.50
F Harga Satuan Pekerjaan (D+E) 21,923.00 24,117.50

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 24,480.50 26,248.75


A Tenaga 9,080.00 10,300.00
L.01 0.036 OH Pekerja 70,000.00 85,000.00 2,520.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 13,175.00 13,562.50
1.20 m' Pipa PVC Ø ¾" 8,500.00 8,750.00 10,200.00 10,500.00
0.35 Ls Perlengkapan 35% x pipa 8,500.00 8,750.00 2,975.00 3,062.50
C PERALATAN
D Jumlah A + B + C 22,255.00 23,862.50
E Overhead & Profit (contoh 10%) 10% 2,225.50 2,386.25
F Harga Satuan Pekerjaan (D+E) 24,480.50 26,248.75

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 29,169.25 33,495.00


A Tenaga 9,080.00 10,300.00
L.01 0.036 OH Pekerja 70,000.00 85,000.00 2,520.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 17,437.50 20,150.00
1.20 m' Pipa PVC Ø 1" 11,250.00 13,000.00 13,500.00 15,600.00
0.35 Ls Perlengkapan 35% x pipa 11,250.00 13,000.00 3,937.50 4,550.00
C PERALATAN
D Jumlah A + B + C 26,517.50 30,450.00
E Overhead & Profit (contoh 10%) 10% 2,651.75 3,045.00
F Harga Satuan Pekerjaan (D+E) 29,169.25 33,495.00

file:///conversion/tmp/scratch/469226324.xls 193/138 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 30,895.33 36,318.33
A Tenaga 13,620.00 15,450.00
L.01 0.054 OH Pekerja 70,000.00 85,000.00 3,780.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 14,466.67 17,566.67
1.20 m' Pipa PVC Ø 1½" 9,333.33 11,333.33 11,200.00 13,600.00
0.35 Ls Perlengkapan 35% x pipa 9,333.33 11,333.33 3,266.67 3,966.67
C PERALATAN
D Jumlah A + B + C 28,086.67 33,016.67
E Overhead & Profit (contoh 10%) 10% 2,808.67 3,301.67
F Harga Satuan Pekerjaan (D+E) 30,895.33 36,318.33

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 33,452.83 46,832.50


A Tenaga 13,620.00 15,450.00
L.01 0.054 OH Pekerja 70,000.00 85,000.00 3,780.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 16,791.67 27,125.00
1.20 m' Pipa PVC Ø 2" 10,833.33 17,500.00 13,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 10,833.33 17,500.00 3,791.67 6,125.00
C PERALATAN
D Jumlah A + B + C 30,411.67 42,575.00
E Overhead & Profit (contoh 10%) 10% 3,041.17 4,257.50
F Harga Satuan Pekerjaan (D+E) 33,452.83 46,832.50

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 57,938.83 78,002.83


A Tenaga 20,380.00 23,120.00
L.01 0.081 OH Pekerja 70,000.00 85,000.00 5,670.00 6,885.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.0135 OH Kepala Tukang 110,000.00 120,000.00 1,485.00 1,620.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 32,291.67 47,791.67
1.20 m' Pipa PVC Ø 3" 20,833.33 30,833.33 25,000.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 20,833.33 30,833.33 7,291.67 10,791.67
C PERALATAN
D Jumlah A + B + C 52,671.67 70,911.67
E Overhead & Profit (contoh 10%) 10% 5,267.17 7,091.17
F Harga Satuan Pekerjaan (D+E) 57,938.83 78,002.83

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 61,138.00 90,896.67


A Tenaga 9,080.00 10,300.00
L.01 0.036 OH Pekerja 70,000.00 85,000.00 2,520.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 46,500.00 72,333.33
1.20 m' Pipa PVC Ø 4" 30,000.00 46,666.67 36,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 30,000.00 46,666.67 10,500.00 16,333.33
C PERALATAN
D Jumlah A + B + C 55,580.00 82,633.33
E Overhead & Profit (contoh 10%) 10% 5,558.00 8,263.33
F Harga Satuan Pekerjaan (D+E) 61,138.00 90,896.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 76,527.00 84,378.25
cm
A Tenaga 10,240.00 11,920.00
L.01 0.080 OH Pekerja 70,000.00 85,000.00 5,600.00 6,800.00
L.02 0.040 OH Tukang Batu 95,000.00 105,000.00 3,800.00 4,200.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 59,330.00 64,787.50
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,050.00 1,062.50 36,750.00 37,187.50
0.014 m3 Pasir Pasang 310,000.00 370,000.00 4,340.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 230,000.00 2,240.00 3,220.00
- -

file:///conversion/tmp/scratch/469226324.xls 193/139 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 69,570.00 76,707.50
E Overhead & Profit (contoh 10%) 10% 6,957.00 7,670.75
F Harga Satuan Pekerjaan (D+E) 76,527.00 84,378.25

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 36,751.00 42,575.50
cm
A Tenaga 7,680.00 8,940.00
L.01 0.060 OH Pekerja 70,000.00 85,000.00 4,200.00 5,100.00
L.02 0.030 OH Tukang Batu 95,000.00 105,000.00 2,850.00 3,150.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 25,730.00 29,765.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,050.00 1,062.50 7,140.00 7,225.00
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 230,000.00 1,760.00 2,530.00
,
C PERALATAN
D Jumlah A + B + C 33,410.00 38,705.00
E Overhead & Profit (contoh 10%) 10% 3,341.00 3,870.50
F Harga Satuan Pekerjaan (D+E) 36,751.00 42,575.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 103,274.60 131,370.25


A Tenaga 17,920.00 20,860.00
L.01 0.140 OH Pekerja 70,000.00 85,000.00 9,800.00 11,900.00
L.02 0.070 OH Tukang Batu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 75,966.00 98,567.50
1.10 bh pipa beton 35,000.00 50,000.00 38,500.00 55,000.00
0.027 m3 Batu Bata 450,000.00 487,500.00 12,150.00 13,162.50
3.920 kg Semen Portlan 1,050.00 1,062.50 4,116.00 4,165.00
0.056 m3 Pasir Pasang 310,000.00 370,000.00 17,360.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 230,000.00 3,840.00 5,520.00
C PERALATAN
D Jumlah A + B + C 93,886.00 119,427.50
E Overhead & Profit (contoh 10%) 10% 9,388.60 11,942.75
F Harga Satuan Pekerjaan (D+E) 103,274.60 131,370.25

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 576,251.50 623,984.63


A Tenaga 48,640.00 56,620.00
L.01 0.380 OH Pekerja 70,000.00 85,000.00 26,600.00 32,300.00
L.02 0.190 OH Tukang Batu 95,000.00 105,000.00 18,050.00 19,950.00
L.03 0.019 OH Kepala Tukang 110,000.00 120,000.00 2,090.00 2,280.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00
B Bahan 475,225.00 510,638.75
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 450,000.00 487,500.00 247,500.00 268,125.00
10.300 kg Semen Portlan 1,050.00 1,062.50 10,815.00 10,943.75
0.061 m3 Pasir Pasang 310,000.00 370,000.00 18,910.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 230,000.00 11,040.00 15,870.00
C PERALATAN
D Jumlah A + B + C 523,865.00 567,258.75
E Overhead & Profit (contoh 10%) 10% 52,386.50 56,725.88
F Harga Satuan Pekerjaan (D+E) 576,251.50 623,984.63

file:///conversion/tmp/scratch/469226324.xls 193/140 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 1 Titik Pemasangan Lampu 338,360.00 378,708.00


A Tenaga 153,800.00 172,140.00
100 % Pekerja 153,800.00 172,140.00 153,800.00 172,140.00

Bahan 153,800.00 172,140.00


3.00 btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
24.00 m Kabel **) 4,600.00 5,200.00 110,400.00 124,800.00
3.00 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4.00 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3.00 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24.00 buah Klem 50.00 60.00 1,200.00 1,440.00
1.00 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1.00 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00

1.00 buah Pitting 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 307,600.00 344,280.00
E Overhead & Profit (contoh 10%) 10% 30,760.00 34,428.00
F Harga Satuan Pekerjaan (D+E) 338,360.00 378,708.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 459,140.00 503,448.00
A Tenaga 208,700.00 228,840.00
L.01 100 % Pekerja 208,700.00 228,840.00 208,700.00 228,840.00

B Bahan 208,700.00 228,840.00


3 Kg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 4,600.00 5,200.00 69,000.00 78,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A + B + C 417,400.00 457,680.00
E Overhead & Profit (contoh 10%) 10% 41,740.00 45,768.00
F Harga Satuan Pekerjaan (D+E) 459,140.00 503,448.00

file:///conversion/tmp/scratch/469226324.xls 193/141 15-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN PEMASANGAN
XVI A.8.4.1
PIPA
1 A.8.4.1.1 1 m' Pemasangan Pipa PVC Ø 63 mm 14,486.45 17,344.25
A Tenaga 6,859.50 8,195.50
L.01 0.081 OH Pekerja 70,000.00 85,000.00 5,670.00 6,885.00
L.02 0.0041 OH Tukang Pipa 95,000.00 105,000.00 389.50 430.50
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 6,250.00 7,500.00
1 m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 6,250.00 7,500.00
C PERALATAN 60.00 72.00
0.006 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 60.00 72.00
D Jumlah A + B + C 13,169.50 15,767.50
E Overhead & Profit (contoh 10%) 10% 1,316.95 1,576.75
F Harga Satuan Pekerjaan (D+E) 14,486.45 17,344.25

2 A.8.4.1.2 1 m' Pemasangan Pipa PVC Ø 90 mm 21,477.50 25,037.10


A Tenaga 11,945.00 13,915.00
L.01 0.094 OH Pekerja 70,000.00 85,000.00 6,580.00 7,990.00
L.02 0.047 OH Tukang Pipa 95,000.00 105,000.00 4,465.00 4,935.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 7,500.00 8,750.00
1 m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 7,500.00 8,750.00
C PERALATAN 80.00 96.00
0.008 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 80.00 96.00
D Jumlah A + B + C 19,525.00 22,761.00
E Overhead & Profit (contoh 10%) 10% 1,952.50 2,276.10
F Harga Satuan Pekerjaan (D+E) 21,477.50 25,037.10

3 A.8.4.1.3 1 m' Pemasangan Pipa PVC Ø 110 mm 25,118.50 31,702.00


A Tenaga 13,485.00 15,700.00
L.01 0.105 OH Pekerja 70,000.00 85,000.00 7,350.00 8,925.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00
B Bahan 9,250.00 13,000.00
1 m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 9,250.00 13,000.00
C PERALATAN 100.00 120.00
0.01 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 100.00 120.00
D Jumlah A + B + C 22,835.00 28,820.00
E Overhead & Profit (contoh 10%) 10% 2,283.50 2,882.00
F Harga Satuan Pekerjaan (D+E) 25,118.50 31,702.00

4 A.8.4.1.4 1 m' Pemasangan Pipa PVC Ø 150 mm 29,353.50 38,157.90


A Tenaga 15,065.00 17,545.00
L.01 0.118 OH Pekerja 70,000.00 85,000.00 8,260.00 10,030.00
L.02 0.059 OH Tukang Pipa 95,000.00 105,000.00 5,605.00 6,195.00
L.04 0.012 OH Mandor 100,000.00 110,000.00 1,200.00 1,320.00
B Bahan 11,500.00 17,000.00
1 m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 11,500.00 17,000.00
C PERALATAN 120.00 144.00
0.012 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 120.00 144.00
D Jumlah A + B + C 26,685.00 34,689.00
E Overhead & Profit (contoh 10%) 10% 2,668.50 3,468.90
F Harga Satuan Pekerjaan (D+E) 29,353.50 38,157.90

5 A.8.4.1.5 1 m' Pemasangan Pipa PVC Ø 200 mm 43,334.50 60,134.80


A Tenaga 24,155.00 28,130.00
L.01 0.189 OH Pekerja 70,000.00 85,000.00 13,230.00 16,065.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00
B Bahan 15,000.00 26,250.00
1 m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 15,000.00 26,250.00
C PERALATAN 240.00 288.00
0.024 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 240.00 288.00
D Jumlah A + B + C 39,395.00 54,668.00
E Overhead & Profit (contoh 10%) 10% 3,939.50 5,466.80
F Harga Satuan Pekerjaan (D+E) 43,334.50 60,134.80

6 A.8.4.1.6 1 m' Pemasangan Pipa PVC Ø 250 mm 58,322.00 93,189.80


A Tenaga 32,680.00 38,060.00
L.01 0.256 OH Pekerja 70,000.00 85,000.00 17,920.00 21,760.00
L.02 0.128 OH Tukang Pipa 95,000.00 105,000.00 12,160.00 13,440.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 20,000.00 46,250.00
1 m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 20,000.00 46,250.00
C PERALATAN 340.00 408.00
0.034 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 340.00 408.00
D Jumlah A + B + C 53,020.00 84,718.00
E Overhead & Profit (contoh 10%) 10% 5,302.00 8,471.80
F Harga Satuan Pekerjaan (D+E) 58,322.00 93,189.80

7 A.8.4.1.7 1 m' Pemasangan Pipa PVC Ø 300 mm 91,129.50 125,504.50


A Tenaga 37,445.00 43,615.00
L.01 0.294 OH Pekerja 70,000.00 85,000.00 20,580.00 24,990.00
L.02 0.147 OH Tukang Pipa 95,000.00 105,000.00 13,965.00 15,435.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00
B Bahan 45,000.00 70,000.00
1 m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 45,000.00 70,000.00
C PERALATAN 400.00 480.00
0.040 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 400.00 480.00
D Jumlah A + B + C 82,845.00 114,095.00
E Overhead & Profit (contoh 10%) 10% 8,284.50 11,409.50
F Harga Satuan Pekerjaan (D+E) 91,129.50 125,504.50

8 A.8.4.1.8 1 m' Pemasangan Pipa PVC Ø 400 mm 173,382.00 241,120.00


A Tenaga 69,320.00 80,740.00
L.01 0.544 OH Pekerja 70,000.00 85,000.00 38,080.00 46,240.00
L.02 0.272 OH Tukang Pipa 95,000.00 105,000.00 25,840.00 28,560.00
L.04 0.054 OH Mandor 100,000.00 110,000.00 5,400.00 5,940.00
B Bahan 87,500.00 137,500.00
1 m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 87,500.00 137,500.00
C PERALATAN 800.00 960.00
0.080 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 800.00 960.00
D Jumlah A + B + C 157,620.00 219,200.00
E Overhead & Profit (contoh 10%) 10% 15,762.00 21,920.00
F Harga Satuan Pekerjaan (D+E) 173,382.00 241,120.00

9 A.8.4.1.9 1 m' Pemasangan Pipa PVC Ø 450 mm 342,490.50 399,421.00


A Tenaga 85,355.00 99,410.00
L.01 0.669 OH Pekerja 70,000.00 85,000.00 46,830.00 56,865.00
L.02 0.335 OH Tukang Pipa 95,000.00 105,000.00 31,825.00 35,175.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00
B Bahan 225,000.00 262,500.00
1 m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 225,000.00 262,500.00
C PERALATAN 1,000.00 1,200.00
0.100 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00
D Jumlah A + B + C 311,355.00 363,110.00
E Overhead & Profit (contoh 10%) 10% 31,135.50 36,311.00
F Harga Satuan Pekerjaan (D+E) 342,490.50 399,421.00

10 A.8.4.1.10 1 m' Pemasangan Pipa PVC Ø 500 mm 422,867.50 447,330.40


A Tenaga 103,205.00 120,200.00
L.01 0.809 OH Pekerja 70,000.00 85,000.00 56,630.00 68,765.00
L.02 0.405 OH Tukang Pipa 95,000.00 105,000.00 38,475.00 42,525.00
L.04 0.081 OH Mandor 100,000.00 110,000.00 8,100.00 8,910.00
B Bahan 280,000.00 285,000.00
1 m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 280,000.00 285,000.00
C PERALATAN 1,220.00 1,464.00
0.122 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,220.00 1,464.00
D Jumlah A + B + C 384,425.00 406,664.00
E Overhead & Profit (contoh 10%) 10% 38,442.50 40,666.40
F Harga Satuan Pekerjaan (D+E) 422,867.50 447,330.40

11 A.8.4.1.11 1 m' Pemasangan Pipa PVC Ø 600 mm 493,086.00 537,487.50


A Tenaga 121,810.00 141,885.00
L.01 0.957 OH Pekerja 70,000.00 85,000.00 66,990.00 81,345.00
L.02 0.476 OH Tukang Pipa 95,000.00 105,000.00 45,220.00 49,980.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan 325,000.00 345,000.00
1 m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 325,000.00 345,000.00
C PERALATAN 1,450.00 1,740.00
0.145 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,450.00 1,740.00
D Jumlah A + B + C 448,260.00 488,625.00
E Overhead & Profit (contoh 10%) 10% 44,826.00 48,862.50
F Harga Satuan Pekerjaan (D+E) 493,086.00 537,487.50

12 A.8.4.1.12 1 m' Pemasangan Pipa PVC Ø 800 mm 697,196.50 762,624.50


A Tenaga 206,315.00 240,295.00
L.01 1.618 OH Pekerja 70,000.00 85,000.00 113,260.00 137,530.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00
B Bahan 425,000.00 450,000.00
1 m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 425,000.00 450,000.00
C PERALATAN 2,500.00 3,000.00
0.250 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,500.00 3,000.00
D Jumlah A + B + C 633,815.00 693,295.00
E Overhead & Profit (contoh 10%) 10% 63,381.50 69,329.50
F Harga Satuan Pekerjaan (D+E) 697,196.50 762,624.50

13 A.8.4.1.13 1 m' Pemasangan Pipa PVC Ø 900 mm 927,586.00 994,728.90


A Tenaga 215,640.00 251,155.00
L.01 1.691 OH Pekerja 70,000.00 85,000.00 118,370.00 143,735.00
L.02 0.846 OH Tukang Pipa 95,000.00 105,000.00 80,370.00 88,830.00
L.04 0.169 OH Mandor 100,000.00 110,000.00 16,900.00 18,590.00
B Bahan 625,000.00 650,000.00
1 m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 625,000.00 650,000.00
C PERALATAN 2,620.00 3,144.00
0.262 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,620.00 3,144.00
D Jumlah A + B + C 843,260.00 904,299.00
E Overhead & Profit (contoh 10%) 10% 84,326.00 90,429.90
F Harga Satuan Pekerjaan (D+E) 927,586.00 994,728.90

14 A.8.4.1.14 1 m' Pemasangan Pipa PVC Ø 1.000 mm 1,072,115.00 1,138,547.30


A Tenaga 241,710.00 281,515.00
L.01 1.895 OH Pekerja 70,000.00 85,000.00 132,650.00 161,075.00
L.02 0.948 OH Tukang Pipa 95,000.00 105,000.00 90,060.00 99,540.00
L.04 0.190 OH Mandor 100,000.00 110,000.00 19,000.00 20,900.00
B Bahan 730,000.00 750,000.00
1 m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 730,000.00 750,000.00
C PERALATAN 2,940.00 3,528.00
0.294 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,940.00 3,528.00
D Jumlah A + B + C 974,650.00 1,035,043.00
E Overhead & Profit (contoh 10%) 10% 97,465.00 103,504.30
F Harga Satuan Pekerjaan (D+E) 1,072,115.00 1,138,547.30

15 A.8.4.1.15 1 m' Pemasangan Pipa PVC Ø 1.100 mm 1,178,045.00 1,282,257.90


A Tenaga 267,680.00 311,765.00
L.01 2.099 OH Pekerja 70,000.00 85,000.00 146,930.00 178,415.00
L.02 1.050 OH Tukang Pipa 95,000.00 105,000.00 99,750.00 110,250.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 800,000.00 850,000.00
1 m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 800,000.00 850,000.00
C PERALATAN 3,270.00 3,924.00
0.327 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,270.00 3,924.00
D Jumlah A + B + C 1,070,950.00 1,165,689.00
E Overhead & Profit (contoh 10%) 10% 107,095.00 116,568.90
F Harga Satuan Pekerjaan (D+E) 1,178,045.00 1,282,257.90

16 A.8.4.1.16 1 m' Pemasangan Pipa PVC Ø 1.200 mm 1,261,964.00 1,370,955.30


A Tenaga 293,650.00 342,015.00
L.01 2.303 OH Pekerja 70,000.00 85,000.00 161,210.00 195,755.00
L.02 1.152 OH Tukang Pipa 95,000.00 105,000.00 109,440.00 120,960.00
L.04 0.230 OH Mandor 100,000.00 110,000.00 23,000.00 25,300.00
B Bahan 850,000.00 900,000.00
1 m' Pipa PVC Ø 1.200 mm 850,000.00 900,000.00 850,000.00 900,000.00
C PERALATAN 3,590.00 4,308.00
0.359 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,590.00 4,308.00
D Jumlah A + B + C 1,147,240.00 1,246,323.00
E Overhead & Profit (contoh 10%) 10% 114,724.00 124,632.30
F Harga Satuan Pekerjaan (D+E) 1,261,964.00 1,370,955.30

17 A.8.4.1.17 1 m' Pemasangan Pipa HDPE Ø 63 mm 32,510.50 38,849.80


A Tenaga 4,365.00 5,090.00
L.01 0.035 OH Pekerja 70,000.00 85,000.00 2,450.00 2,975.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 25,000.00 30,000.00
1 m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 29,555.00 35,318.00
E Overhead & Profit (contoh 10%) 10% 2,955.50 3,531.80
F Harga Satuan Pekerjaan (D+E) 32,510.50 38,849.80

18 A.8.4.1.18 1 m' Pemasangan Pipa HDPE Ø 100 mm 44,319.00 50,784.80


A Tenaga 5,100.00 5,940.00
L.01 0.040 OH Pekerja 70,000.00 85,000.00 2,800.00 3,400.00
L.02 0.020 OH Tukang Pipa 95,000.00 105,000.00 1,900.00 2,100.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 35,000.00 40,000.00
1 m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 35,000.00 40,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 40,290.00 46,168.00
E Overhead & Profit (contoh 10%) 10% 4,029.00 4,616.80
F Harga Satuan Pekerjaan (D+E) 44,319.00 50,784.80

19 A.8.4.1.19 1 m' Pemasangan Pipa HDPE Ø 125 mm 56,127.50 62,719.80


A Tenaga 5,835.00 6,790.00
L.01 0.045 OH Pekerja 70,000.00 85,000.00 3,150.00 3,825.00
L.02 0.023 OH Tukang Pipa 95,000.00 105,000.00 2,185.00 2,415.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 45,000.00 50,000.00
1 m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 51,025.00 57,018.00
E Overhead & Profit (contoh 10%) 10% 5,102.50 5,701.80
F Harga Satuan Pekerjaan (D+E) 56,127.50 62,719.80

20 A.8.4.1.20 1 m' Pemasangan Pipa HDPE Ø 150 mm 80,382.50 87,354.30


A Tenaga 7,885.00 9,185.00
L.01 0.062 OH Pekerja 70,000.00 85,000.00 4,340.00 5,270.00
L.02 0.031 OH Tukang Pipa 95,000.00 105,000.00 2,945.00 3,255.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 65,000.00 70,000.00
1 m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 73,075.00 79,413.00
E Overhead & Profit (contoh 10%) 10% 7,307.50 7,941.30
F Harga Satuan Pekerjaan (D+E) 80,382.50 87,354.30

21 A.8.4.1.21 1 m' Pemasangan Pipa HDPE Ø 200 mm 135,492.50 148,888.30


A Tenaga 12,985.00 15,125.00
L.01 0.102 OH Pekerja 70,000.00 85,000.00 7,140.00 8,670.00
L.02 0.051 OH Tukang Pipa 95,000.00 105,000.00 4,845.00 5,355.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 110,000.00 120,000.00
1 m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 110,000.00 120,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 123,175.00 135,353.00
E Overhead & Profit (contoh 10%) 10% 12,317.50 13,535.30
F Harga Satuan Pekerjaan (D+E) 135,492.50 148,888.30

22 A.8.4.1.22 1 m' Pemasangan Pipa HDPE Ø 250 mm 167,634.50 176,301.40


A Tenaga 16,975.00 19,770.00
L.01 0.133 OH Pekerja 70,000.00 85,000.00 9,310.00 11,305.00
L.02 0.067 OH Tukang Pipa 95,000.00 105,000.00 6,365.00 7,035.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 135,000.00 140,000.00
1 m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 135,000.00 140,000.00
C PERALATAN 420.00 504.00
0.042 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 420.00 504.00
D Jumlah A + B + C 152,395.00 160,274.00
E Overhead & Profit (contoh 10%) 10% 15,239.50 16,027.40
F Harga Satuan Pekerjaan (D+E) 167,634.50 176,301.40

23 A.8.4.1.23 1 m' Pemasangan Pipa HDPE Ø 300 mm 200,557.50 215,627.50


A Tenaga 21,675.00 25,245.00
L.01 0.170 OH Pekerja 70,000.00 85,000.00 11,900.00 14,450.00
L.02 0.085 OH Tukang Pipa 95,000.00 105,000.00 8,075.00 8,925.00
L.04 0.017 OH Mandor 100,000.00 110,000.00 1,700.00 1,870.00
B Bahan 160,000.00 170,000.00
1 m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 160,000.00 170,000.00
C PERALATAN 650.00 780.00
0.065 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 650.00 780.00
D Jumlah A + B + C 182,325.00 196,025.00
E Overhead & Profit (contoh 10%) 10% 18,232.50 19,602.50
F Harga Satuan Pekerjaan (D+E) 200,557.50 215,627.50

24 A.8.4.1.24 1 m' Pemasangan Pipa HDPE Ø 400 mm 262,344.50 280,377.90


A Tenaga 36,975.00 43,065.00
L.01 0.290 OH Pekerja 70,000.00 85,000.00 20,300.00 24,650.00
L.02 0.145 OH Tukang Pipa 95,000.00 105,000.00 13,775.00 15,225.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00
B Bahan 200,000.00 210,000.00
1 m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 1,520.00 1,824.00
0.152 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,520.00 1,824.00
D Jumlah A + B + C 238,495.00 254,889.00
E Overhead & Profit (contoh 10%) 10% 23,849.50 25,488.90
F Harga Satuan Pekerjaan (D+E) 262,344.50 280,377.90

25 A.8.4.1.25 1 m' Pemasangan Pipa HDPE Ø 450 mm 316,613.00 336,352.50


A Tenaga 45,830.00 53,375.00
L.01 0.359 OH Pekerja 70,000.00 85,000.00 25,130.00 30,515.00
L.02 0.180 OH Tukang Pipa 95,000.00 105,000.00 17,100.00 18,900.00
L.04 0.036 OH Mandor 100,000.00 110,000.00 3,600.00 3,960.00
B Bahan 240,000.00 250,000.00
1 m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 2,000.00 2,400.00
0.200 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,000.00 2,400.00
D Jumlah A + B + C 287,830.00 305,775.00
E Overhead & Profit (contoh 10%) 10% 28,783.00 30,577.50
F Harga Satuan Pekerjaan (D+E) 316,613.00 336,352.50

26 A.8.4.1.26 1 m' Pemasangan Pipa HDPE Ø 500 mm 393,404.00 425,949.70


A Tenaga 55,130.00 64,215.00
L.01 0.433 OH Pekerja 70,000.00 85,000.00 30,310.00 36,805.00
L.02 0.216 OH Tukang Pipa 95,000.00 105,000.00 20,520.00 22,680.00
L.04 0.043 OH Mandor 100,000.00 110,000.00 4,300.00 4,730.00

B Bahan 300,000.00 320,000.00


1 m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 2,510.00 3,012.00


0.251 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,510.00 3,012.00

D Jumlah A + B + C 357,640.00 387,227.00


E Overhead & Profit (contoh 10%) 10% 35,764.00 38,722.70
F Harga Satuan Pekerjaan (D+E) 393,404.00 425,949.70

27 A.8.4.1.27 1 m' Pemasangan Pipa HDPE Ø 600 mm 548,163.00 582,663.40


A Tenaga 65,260.00 76,010.00
L.01 0.512 OH Pekerja 70,000.00 85,000.00 35,840.00 43,520.00
L.02 0.256 OH Tukang Pipa 95,000.00 105,000.00 24,320.00 26,880.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 430,000.00 450,000.00


1 m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 3,070.00 3,684.00


0.307 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,070.00 3,684.00

D Jumlah A + B + C 498,330.00 529,694.00


E Overhead & Profit (contoh 10%) 10% 49,833.00 52,969.40
F Harga Satuan Pekerjaan (D+E) 548,163.00 582,663.40

28 A.8.4.1.28 1 m' Pemasangan Pipa HDPE Ø 800 mm 846,461.00 895,841.10


A Tenaga 113,780.00 132,525.00
L.01 0.893 OH Pekerja 70,000.00 85,000.00 62,510.00 75,905.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.089 OH Mandor 100,000.00 110,000.00 8,900.00 9,790.00

B Bahan 650,000.00 675,000.00


1 m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 650,000.00 675,000.00

C PERALATAN 5,730.00 6,876.00


0.573 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,730.00 6,876.00

D Jumlah A + B + C 769,510.00 814,401.00


E Overhead & Profit (contoh 10%) 10% 76,951.00 81,440.10
F Harga Satuan Pekerjaan (D+E) 846,461.00 895,841.10

29 A.8.4.1.29 1 m' Pemasangan Pipa HDPE Ø 900 mm 1,024,490.50 1,112,689.60


A Tenaga 172,525.00 200,940.00
L.01 1.353 OH Pekerja 70,000.00 85,000.00 94,710.00 115,005.00
L.02 0.677 OH Tukang Pipa 95,000.00 105,000.00 64,315.00 71,085.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 750,000.00 800,000.00


1 m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 750,000.00 800,000.00
C PERALATAN 8,830.00 10,596.00
0.883 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,830.00 10,596.00

D Jumlah A + B + C 931,355.00 1,011,536.00


E Overhead & Profit (contoh 10%) 10% 93,135.50 101,153.60
F Harga Satuan Pekerjaan (D+E) 1,024,490.50 1,112,689.60

30 A.8.4.1.30 1 m' Pemasangan Pipa HDPE Ø 1.000 mm 1,234,761.00 1,302,995.10


A 211,580.00 246,425.00
L.01 1.659 OH Pekerja 70,000.00 85,000.00 116,130.00 141,015.00
L.02 0.830 OH Tukang Pipa 95,000.00 105,000.00 78,850.00 87,150.00
L.04 0.166 OH Mandor 100,000.00 110,000.00 16,600.00 18,260.00

B Bahan 900,000.00 925,000.00


1 m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 900,000.00 925,000.00

C PERALATAN 10,930.00 13,116.00


1.093 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,930.00 13,116.00

D Jumlah A + B + C 1,122,510.00 1,184,541.00


E Overhead & Profit (contoh 10%) 10% 112,251.00 118,454.10
F Harga Satuan Pekerjaan (D+E) 1,234,761.00 1,302,995.10

31 A.8.4.1.31 1 m' Pemasangan Pipa HDPE Ø 1.100 mm 1,368,251.50 1,467,900.50


A Tenaga 231,815.00 269,995.00
L.01 1.818 OH Pekerja 70,000.00 85,000.00 127,260.00 154,530.00
L.02 0.909 OH Tukang Pipa 95,000.00 105,000.00 86,355.00 95,445.00
L.04 0.182 OH Mandor 100,000.00 110,000.00 18,200.00 20,020.00

B Bahan 1,000,000.00 1,050,000.00


1 m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 1,000,000.00 1,050,000.00

C PERALATAN 12,050.00 14,460.00


1.205 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,050.00 14,460.00

D Jumlah A + B + C 1,243,865.00 1,334,455.00


E Overhead & Profit (contoh 10%) 10% 124,386.50 133,445.50
F Harga Satuan Pekerjaan (D+E) 1,368,251.50 1,467,900.50

32 A.8.4.1.32 1 m' Pemasangan Pipa HDPE Ø 1.200 mm 1,559,816.50 1,673,048.30


A Tenaga 302,175.00 351,945.00
L.01 2.370 OH Pekerja 70,000.00 85,000.00 165,900.00 201,450.00
L.02 1.185 OH Tukang Pipa 95,000.00 105,000.00 112,575.00 124,425.00
L.04 0.237 OH Mandor 100,000.00 110,000.00 23,700.00 26,070.00

B Bahan 1,100,000.00 1,150,000.00


1 m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 1,100,000.00 1,150,000.00
C PERALATAN 15,840.00 19,008.00
1.584 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 15,840.00 19,008.00
D Jumlah A + B + C 1,418,015.00 1,520,953.00
E Overhead & Profit (contoh 10%) 10% 141,801.50 152,095.30
F Harga Satuan Pekerjaan (D+E) 1,559,816.50 1,673,048.30

33 A.8.4.1.33 1 m' Pemasangan Pipa GIP Ø 63 mm 64,779.00 75,487.50


A Tenaga 43,890.00 51,125.00
L.01 0.345 OH Pekerja 70,000.00 85,000.00 24,150.00 29,325.00
L.02 0.172 OH Tukang Pipa 95,000.00 105,000.00 16,340.00 18,060.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan 15,000.00 17,500.00
1 m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 15,000.00 17,500.00
C PERALATAN - -

hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
D Jumlah A + B + C 58,890.00 68,625.00
E Overhead & Profit (contoh 10%) 10% 5,889.00 6,862.50
F Harga Satuan Pekerjaan (D+E) 64,779.00 75,487.50
34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 77,183.33 92,840.00
A Tenaga 51,000.00 59,400.00
L.01 0.400 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.200 OH Tukang Pipa 95,000.00 105,000.00 19,000.00 21,000.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00

B Bahan 19,166.67 25,000.00


1 m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 19,166.67 25,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 70,166.67 84,400.00


E Overhead & Profit (contoh 10%) 10% 7,016.67 8,440.00
F Harga Satuan Pekerjaan (D+E) 77,183.33 92,840.00

35 A.8.4.1.35 1 m' Pemasangan Pipa GIP Ø 125 mm 87,604.00 106,205.00


A Tenaga 57,140.00 66,550.00
L.01 0.448 OH Pekerja 70,000.00 85,000.00 31,360.00 38,080.00
L.02 0.224 OH Tukang Pipa 95,000.00 105,000.00 21,280.00 23,520.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00

B Bahan 22,500.00 30,000.00


1 m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 22,500.00 30,000.00

C PERALATAN
D Jumlah A + B + C 79,640.00 96,550.00
E Overhead & Profit (contoh 10%) 10% 7,964.00 9,655.00
F Harga Satuan Pekerjaan (D+E) 87,604.00 106,205.00

36 A.8.4.1.36 1 m' Pemasangan Pipa GIP Ø 150 mm 102,177.17 123,036.83


A Tenaga 64,555.00 75,185.00
L.01 0.506 OH Pekerja 70,000.00 85,000.00 35,420.00 43,010.00
L.02 0.253 OH Tukang Pipa 95,000.00 105,000.00 24,035.00 26,565.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 28,333.33 36,666.67


1 m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 28,333.33 36,666.67

C PERALATAN
D Jumlah A + B + C 92,888.33 111,851.67
E Overhead & Profit (contoh 10%) 10% 9,288.83 11,185.17
F Harga Satuan Pekerjaan (D+E) 102,177.17 123,036.83

37 A.8.4.1.37 1 m' Pemasangan Pipa GIP Ø 200 mm 152,933.00 183,241.67


A Tenaga 101,530.00 118,250.00
L.01 0.796 OH Pekerja 70,000.00 85,000.00 55,720.00 67,660.00
L.02 0.398 OH Tukang Pipa 95,000.00 105,000.00 37,810.00 41,790.00
L.04 0.080 OH Mandor 100,000.00 110,000.00 8,000.00 8,800.00

B Bahan 37,500.00 48,333.33


1 m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 37,500.00 48,333.33

C PERALATAN
D Jumlah A + B + C 139,030.00 166,583.33
E Overhead & Profit (contoh 10%) 10% 13,903.00 16,658.33
F Harga Satuan Pekerjaan (D+E) 152,933.00 183,241.67

38 A.8.4.1.38 1 m' Pemasangan Pipa GIP Ø 250 mm 182,660.50 219,255.67


A Tenaga 121,055.00 140,990.00
L.01 0.949 OH Pekerja 70,000.00 85,000.00 66,430.00 80,665.00
L.02 0.475 OH Tukang Pipa 95,000.00 105,000.00 45,125.00 49,875.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00
B Bahan 45,000.00 58,333.33
1 m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 45,000.00 58,333.33

C PERALATAN
D Jumlah A + B + C 166,055.00 199,323.33
E Overhead & Profit (contoh 10%) 10% 16,605.50 19,932.33
F Harga Satuan Pekerjaan (D+E) 182,660.50 219,255.67

39 A.8.4.1.39 1 m' Pemasangan Pipa GIP Ø 300 mm 211,381.50 246,346.83


A Tenaga 122,165.00 142,285.00
L.01 0.958 OH Pekerja 70,000.00 85,000.00 67,060.00 81,430.00
L.02 0.479 OH Tukang Pipa 95,000.00 105,000.00 45,505.00 50,295.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00

B Bahan 70,000.00 81,666.67


1 m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 70,000.00 81,666.67

C PERALATAN
D Jumlah A + B + C 192,165.00 223,951.67
E Overhead & Profit (contoh 10%) 10% 19,216.50 22,395.17
F Harga Satuan Pekerjaan (D+E) 211,381.50 246,346.83

40 A.8.4.1.40 1 m' Pemasangan Pipa GIP Ø 400 mm 272,627.67 304,289.33


A Tenaga 154,510.00 179,960.00
L.01 1.212 OH Pekerja 70,000.00 85,000.00 84,840.00 103,020.00
L.02 0.606 OH Tukang Pipa 95,000.00 105,000.00 57,570.00 63,630.00
L.04 0.121 OH Mandor 100,000.00 110,000.00 12,100.00 13,310.00

B Bahan 93,333.33 96,666.67


1 m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 93,333.33 96,666.67

C PERALATAN
D Jumlah A + B + C 247,843.33 276,626.67
E Overhead & Profit (contoh 10%) 10% 24,784.33 27,662.67
F Harga Satuan Pekerjaan (D+E) 272,627.67 304,289.33

41 A.8.4.1.41 1 m' Pemasangan Pipa GIP Ø 450 mm 310,673.00 352,918.50


A Tenaga 172,430.00 200,835.00
L.01 1.353 OH Pekerja 70,000.00 85,000.00 94,710.00 115,005.00
L.02 0.676 OH Tukang Pipa 95,000.00 105,000.00 64,220.00 70,980.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 110,000.00 120,000.00


1 m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 110,000.00 120,000.00

C PERALATAN
D Jumlah A + B + C 282,430.00 320,835.00
E Overhead & Profit (contoh 10%) 10% 28,243.00 32,083.50
F Harga Satuan Pekerjaan (D+E) 310,673.00 352,918.50

42 A.8.4.1.42 1 m' Pemasangan Pipa GIP Ø 500 mm 360,090.50 405,031.00


A Tenaga 187,355.00 218,210.00
L.01 1.469 OH Pekerja 70,000.00 85,000.00 102,830.00 124,865.00
L.02 0.735 OH Tukang Pipa 95,000.00 105,000.00 69,825.00 77,175.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 140,000.00 150,000.00


1 m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN
D Jumlah A + B + C 327,355.00 368,210.00
E Overhead & Profit (contoh 10%) 10% 32,735.50 36,821.00
F Harga Satuan Pekerjaan (D+E) 360,090.50 405,031.00
43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 362,197.00 403,859.50
A Tenaga 169,270.00 197,145.00
L.01 1.327 OH Pekerja 70,000.00 85,000.00 92,890.00 112,795.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 160,000.00 170,000.00


1 m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN
D Jumlah A + B + C 329,270.00 367,145.00
E Overhead & Profit (contoh 10%) 10% 32,927.00 36,714.50
F Harga Satuan Pekerjaan (D+E) 362,197.00 403,859.50

44 A.8.4.1.44 1 m' Pemasangan Pipa GIP Ø 800 mm 546,342.50 611,094.00


A Tenaga 296,675.00 345,540.00
L.01 2.327 OH Pekerja 70,000.00 85,000.00 162,890.00 197,795.00
L.02 1.163 OH Tukang Pipa 95,000.00 105,000.00 110,485.00 122,115.00
L.04 0.233 OH Mandor 100,000.00 110,000.00 23,300.00 25,630.00

B Bahan 200,000.00 210,000.00


1 m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN
D Jumlah A + B + C 496,675.00 555,540.00
E Overhead & Profit (contoh 10%) 10% 49,667.50 55,554.00
F Harga Satuan Pekerjaan (D+E) 546,342.50 611,094.00

45 A.8.4.1.45 1 m' Pemasangan Pipa GIP Ø 900 mm 620,895.00 703,488.50


A Tenaga 334,450.00 389,535.00
L.01 2.623 OH Pekerja 70,000.00 85,000.00 183,610.00 222,955.00
L.02 1.312 OH Tukang Pipa 95,000.00 105,000.00 124,640.00 137,760.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan 230,000.00 250,000.00


1 m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 230,000.00 250,000.00

C PERALATAN
D Jumlah A + B + C 564,450.00 639,535.00
E Overhead & Profit (contoh 10%) 10% 56,445.00 63,953.50
F Harga Satuan Pekerjaan (D+E) 620,895.00 703,488.50

46 A.8.4.1.46 1 m' Pemasangan Pipa GIP Ø 1.000 mm 694,309.00 772,557.50


A Tenaga 371,190.00 432,325.00
L.01 2.911 OH Pekerja 70,000.00 85,000.00 203,770.00 247,435.00
L.02 1.456 OH Tukang Pipa 95,000.00 105,000.00 138,320.00 152,880.00
L.04 0.291 OH Mandor 100,000.00 110,000.00 29,100.00 32,010.00
B Bahan 260,000.00 270,000.00
1 m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 260,000.00 270,000.00
C PERALATAN
D Jumlah A + B + C 631,190.00 702,325.00
E Overhead & Profit (contoh 10%) 10% 63,119.00 70,232.50
F Harga Satuan Pekerjaan (D+E) 694,309.00 772,557.50

47 A.8.4.1.47 1 m' Pemasangan Pipa GIP Ø 1.100 mm 756,800.00 841,720.00


A Tenaga 408,000.00 475,200.00
L.01 3.200 OH Pekerja 70,000.00 85,000.00 224,000.00 272,000.00
L.02 1.600 OH Tukang Pipa 95,000.00 105,000.00 152,000.00 168,000.00
L.04 0.320 OH Mandor 100,000.00 110,000.00 32,000.00 35,200.00
B Bahan 280,000.00 290,000.00
1 m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 280,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 688,000.00 765,200.00
E Overhead & Profit (contoh 10%) 10% 68,800.00 76,520.00
F Harga Satuan Pekerjaan (D+E) 756,800.00 841,720.00
48 A.8.4.1.48 1 m' Pemasangan Pipa GIP Ø 1.200 mm 830,214.00 921,789.00
A Tenaga 444,740.00 517,990.00
L.01 3.488 OH Pekerja 70,000.00 85,000.00 244,160.00 296,480.00
L.02 1.744 OH Tukang Pipa 95,000.00 105,000.00 165,680.00 183,120.00
L.04 0.349 OH Mandor 100,000.00 110,000.00 34,900.00 38,390.00

B Bahan 310,000.00 320,000.00


1 m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 310,000.00 320,000.00
C PERALATAN
D Jumlah A + B + C 754,740.00 837,990.00
E Overhead & Profit (contoh 10%) 10% 75,474.00 83,799.00
F Harga Satuan Pekerjaan (D+E) 830,214.00 921,789.00

49 A.8.4.1.49 1 m' Pemasangan Pipa DCI Ø 100 mm 81,202.00 96,471.10


A Tenaga 48,440.00 57,245.00
L.01 0.489 OH Pekerja 70,000.00 85,000.00 34,230.00 41,565.00
L.02 0.098 OH Tukang Pipa 95,000.00 105,000.00 9,310.00 10,290.00
L.04 0.049 OH Mandor 100,000.00 110,000.00 4,900.00 5,390.00
B Bahan 25,000.00 30,000.00
1 m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 73,820.00 87,701.00
E Overhead & Profit (contoh 10%) 10% 7,382.00 8,770.10
F Harga Satuan Pekerjaan (D+E) 81,202.00 96,471.10

50 A.8.4.1.50 1 m' Pemasangan Pipa DCI Ø 125 mm 103,977.50 120,390.60


A Tenaga 54,145.00 63,990.00
L.01 0.547 OH Pekerja 70,000.00 85,000.00 38,290.00 46,495.00
L.02 0.109 OH Tukang Pipa 95,000.00 105,000.00 10,355.00 11,445.00
L.04 0.055 OH Mandor 100,000.00 110,000.00 5,500.00 6,050.00
B Bahan 40,000.00 45,000.00
1 m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 40,000.00 45,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 94,525.00 109,446.00
E Overhead & Profit (contoh 10%) 10% 9,452.50 10,944.60
F Harga Satuan Pekerjaan (D+E) 103,977.50 120,390.60

51 A.8.4.1.51 1 m' Pemasangan Pipa DCI Ø 150 mm 133,182.50 156,404.60


A Tenaga 60,695.00 71,730.00
L.01 0.613 OH Pekerja 70,000.00 85,000.00 42,910.00 52,105.00
L.02 0.123 OH Tukang Pipa 95,000.00 105,000.00 11,685.00 12,915.00
L.04 0.061 OH Mandor 100,000.00 110,000.00 6,100.00 6,710.00
B Bahan 60,000.00 70,000.00
1 m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 60,000.00 70,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 121,075.00 142,186.00
E Overhead & Profit (contoh 10%) 10% 12,107.50 14,218.60
F Harga Satuan Pekerjaan (D+E) 133,182.50 156,404.60

52 A.8.4.1.52 1 m' Pemasangan Pipa DCI Ø 200 mm 181,472.50 209,479.60


A Tenaga 84,595.00 99,980.00
L.01 0.855 OH Pekerja 70,000.00 85,000.00 59,850.00 72,675.00
L.02 0.171 OH Tukang Pipa 95,000.00 105,000.00 16,245.00 17,955.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00
B Bahan 80,000.00 90,000.00
1 m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 80,000.00 90,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 164,975.00 190,436.00
E Overhead & Profit (contoh 10%) 10% 16,497.50 19,043.60
F Harga Satuan Pekerjaan (D+E) 181,472.50 209,479.60
53 A.8.4.1.53 1 m' Pemasangan Pipa DCI Ø 250 mm 214,082.00 244,018.50
A Tenaga 94,120.00 111,235.00
L.01 0.951 OH Pekerja 70,000.00 85,000.00 66,570.00 80,835.00
L.02 0.190 OH Tukang Pipa 95,000.00 105,000.00 18,050.00 19,950.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00

B Bahan 100,000.00 110,000.00


1 m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 500.00 600.00


0.050 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 500.00 600.00

D Jumlah A + B + C 194,620.00 221,835.00


E Overhead & Profit (contoh 10%) 10% 19,462.00 22,183.50
F Harga Satuan Pekerjaan (D+E) 214,082.00 244,018.50

54 A.8.4.1.54 1 m' Pemasangan Pipa DCI Ø 300 mm 238,749.50 269,172.20


A Tenaga 96,335.00 113,850.00
L.01 0.973 OH Pekerja 70,000.00 85,000.00 68,110.00 82,705.00
L.02 0.195 OH Tukang Pipa 95,000.00 105,000.00 18,525.00 20,475.00
L.04 0.097 OH Mandor 100,000.00 110,000.00 9,700.00 10,670.00

B Bahan 120,000.00 130,000.00


1 m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 120,000.00 130,000.00

C PERALATAN 710.00 852.00


0.071 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 710.00 852.00

D Jumlah A + B + C 217,045.00 244,702.00


E Overhead & Profit (contoh 10%) 10% 21,704.50 24,470.20
F Harga Satuan Pekerjaan (D+E) 238,749.50 269,172.20

55 A.8.4.1.55 1 m' Pemasangan Pipa DCI Ø 400 mm 358,127.00 401,441.70


A Tenaga 167,785.00 196,985.00
L.01 1.545 OH Pekerja 70,000.00 85,000.00 108,150.00 131,325.00
L.02 0.309 OH Tukang Pipa 95,000.00 105,000.00 29,355.00 32,445.00
L.08 0.093 OH Operator Alat Berat 160,000.00 175,000.00 14,880.00 16,275.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00
B Bahan 150,000.00 160,000.00
1 m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 150,000.00 160,000.00

C PERALATAN 7,785.00 7,962.00


0.023 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 7,475.00 7,590.00
0.031 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 310.00 372.00
D Jumlah A + B + C 325,570.00 364,947.00
E Overhead & Profit (contoh 10%) 10% 32,557.00 36,494.70
F Harga Satuan Pekerjaan (D+E) 358,127.00 401,441.70

56 A.8.4.1.56 1 m' Pemasangan Pipa DCI Ø 450 mm 420,409.00 464,412.30


A Tenaga 202,375.00 237,155.00
L.01 1.813 OH Pekerja 70,000.00 85,000.00 126,910.00 154,105.00
L.02 0.363 OH Tukang Pipa 95,000.00 105,000.00 34,485.00 38,115.00
L.08 0.143 OH Operator Alat Berat 160,000.00 175,000.00 22,880.00 25,025.00
L.04 0.181 OH Mandor 100,000.00 110,000.00 18,100.00 19,910.00
B Bahan 170,000.00 175,000.00
1 m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 170,000.00 175,000.00

C PERALATAN 9,815.00 10,038.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 382,190.00 422,193.00
E Overhead & Profit (contoh 10%) 10% 38,219.00 42,219.30
F Harga Satuan Pekerjaan (D+E) 420,409.00 464,412.30
57 A.8.4.1.57 1 m' Pemasangan Pipa DCI Ø 500 mm 478,527.50 533,527.50
A Tenaga 233,525.00 273,265.00
L.01 2.047 OH Pekerja 70,000.00 85,000.00 143,290.00 173,995.00
L.02 0.409 OH Tukang Pipa 95,000.00 105,000.00 38,855.00 42,945.00
L.08 0.193 OH Operator Alat Berat 160,000.00 175,000.00 30,880.00 33,775.00
L.04 0.205 OH Mandor 100,000.00 110,000.00 20,500.00 22,550.00
B Bahan 190,000.00 200,000.00
1 m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 190,000.00 200,000.00

C PERALATAN 11,500.00 11,760.00


0.034 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 11,050.00 11,220.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 435,025.00 485,025.00
E Overhead & Profit (contoh 10%) 10% 43,502.50 48,502.50
F Harga Satuan Pekerjaan (D+E) 478,527.50 533,527.50

58 A.8.4.1.58 1 m' Pemasangan Pipa DCI Ø 600 mm 539,616.00 612,253.40


A Tenaga 245,940.00 286,530.00
L.01 2.011 OH Pekerja 70,000.00 85,000.00 140,770.00 170,935.00
L.02 0.402 OH Tukang Pipa 95,000.00 105,000.00 38,190.00 42,210.00
L.08 0.293 OH Operator Alat Berat 160,000.00 175,000.00 46,880.00 51,275.00
L.04 0.201 OH Mandor 100,000.00 110,000.00 20,100.00 22,110.00
B Bahan 225,000.00 250,000.00
1 m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 225,000.00 250,000.00

C PERALATAN 19,620.00 20,064.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.077 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 770.00 924.00
D Jumlah A + B + C 490,560.00 556,594.00
E Overhead & Profit (contoh 10%) 10% 49,056.00 55,659.40
F Harga Satuan Pekerjaan (D+E) 539,616.00 612,253.40

59 A.8.4.1.59 1 m' Pemasangan Pipa DCI Ø 800 mm 814,550.00 916,553.00


A Tenaga 460,950.00 537,810.00
L.01 3.859 OH Pekerja 70,000.00 85,000.00 270,130.00 328,015.00
L.02 0.772 OH Tukang Pipa 95,000.00 105,000.00 73,340.00 81,060.00
L.08 0.493 OH Operator Alat Berat 160,000.00 175,000.00 78,880.00 86,275.00
L.04 0.386 OH Mandor 100,000.00 110,000.00 38,600.00 42,460.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 29,550.00 30,420.00


0.084 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 27,300.00 27,720.00
0.225 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,250.00 2,700.00
D Jumlah A + B + C 740,500.00 833,230.00
E Overhead & Profit (contoh 10%) 10% 74,050.00 83,323.00
F Harga Satuan Pekerjaan (D+E) 814,550.00 916,553.00

60 A.8.4.1.60 1 m' Pemasangan Pipa DCI Ø 900 mm 959,244.00 1,085,481.10


A Tenaga 589,335.00 688,135.00
L.01 4.995 OH Pekerja 70,000.00 85,000.00 349,650.00 424,575.00
L.02 0.999 OH Tukang Pipa 95,000.00 105,000.00 94,905.00 104,895.00
L.08 0.593 OH Operator Alat Berat 160,000.00 175,000.00 94,880.00 103,775.00
L.04 0.499 OH Mandor 100,000.00 110,000.00 49,900.00 54,890.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 32,705.00 33,666.00


0.093 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 30,225.00 30,690.00
0.248 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,480.00 2,976.00
D Jumlah A + B + C 872,040.00 986,801.00
E Overhead & Profit (contoh 10%) 10% 87,204.00 98,680.10
F Harga Satuan Pekerjaan (D+E) 959,244.00 1,085,481.10
61 A.8.4.1.61 1 m' Pemasangan Pipa DCI Ø 1.000 mm 1,147,740.00 1,291,626.60
A Tenaga 724,020.00 843,670.00
L.01 5.931 OH Pekerja 70,000.00 85,000.00 415,170.00 504,135.00
L.02 1.186 OH Tukang Pipa 95,000.00 105,000.00 112,670.00 124,530.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.693 OH Mandor 100,000.00 110,000.00 69,300.00 76,230.00
B Bahan 280,000.00 290,000.00
1 m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 280,000.00 290,000.00

C PERALATAN 39,380.00 40,536.00


0.112 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 36,400.00 36,960.00
0.298 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,980.00 3,576.00
D Jumlah A + B + C 1,043,400.00 1,174,206.00
E Overhead & Profit (contoh 10%) 10% 104,340.00 117,420.60
F Harga Satuan Pekerjaan (D+E) 1,147,740.00 1,291,626.60

62 A.8.4.1.62 1 m' Pemasangan Pipa DCI Ø 1.100 mm 1,284,030.00 1,458,212.80


A Tenaga 814,860.00 951,840.00
L.01 6.949 OH Pekerja 70,000.00 85,000.00 486,430.00 590,665.00
L.02 1.390 OH Tukang Pipa 95,000.00 105,000.00 132,050.00 145,950.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.695 OH Mandor 100,000.00 110,000.00 69,500.00 76,450.00
B Bahan 300,000.00 320,000.00
1 m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 52,440.00 53,808.00


0.152 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 49,400.00 50,160.00
0.304 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,040.00 3,648.00
D Jumlah A + B + C 1,167,300.00 1,325,648.00
E Overhead & Profit (contoh 10%) 10% 116,730.00 132,564.80
F Harga Satuan Pekerjaan (D+E) 1,284,030.00 1,458,212.80

63 A.8.4.1.63 1 m' Pemasangan Pipa DCI Ø 1.200 mm 1,454,799.50 1,652,827.00


A Tenaga 940,445.00 1,098,850.00
L.01 8.056 OH Pekerja 70,000.00 85,000.00 563,920.00 684,760.00
L.02 1.611 OH Tukang Pipa 95,000.00 105,000.00 153,045.00 169,155.00
L.08 0.893 OH Operator Alat Berat 160,000.00 175,000.00 142,880.00 156,275.00
L.04 0.806 OH Mandor 100,000.00 110,000.00 80,600.00 88,660.00
B Bahan 320,000.00 340,000.00
1 m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 320,000.00 340,000.00

C PERALATAN 62,100.00 63,720.00


0.180 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 58,500.00 59,400.00
0.360 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,600.00 4,320.00
D Jumlah A + B + C 1,322,545.00 1,502,570.00
E Overhead & Profit (contoh 10%) 10% 132,254.50 150,257.00
F Harga Satuan Pekerjaan (D+E) 1,454,799.50 1,652,827.00

64 A.8.4.1.64 1 m' Pemasangan Baja PVC Ø 63 mm 67,617.00 78,609.30


A Tenaga 49,430.00 58,415.00
L.01 0.499 OH Pekerja 70,000.00 85,000.00 34,930.00 42,415.00
L.02 0.100 OH Tukang Pipa 95,000.00 105,000.00 9,500.00 10,500.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan 12,000.00 13,000.00


1 m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 61,470.00 71,463.00


E Overhead & Profit (contoh 10%) 10% 6,147.00 7,146.30
F Harga Satuan Pekerjaan (D+E) 67,617.00 78,609.30
65 A.8.4.1.65 1 m' Pemasangan Pipa Baja Ø 100 mm 76,879.00 91,105.30
A Tenaga 57,350.00 67,775.00
L.01 0.579 OH Pekerja 70,000.00 85,000.00 40,530.00 49,215.00
L.02 0.116 OH Tukang Pipa 95,000.00 105,000.00 11,020.00 12,180.00
L.04 0.058 OH Mandor 100,000.00 110,000.00 5,800.00 6,380.00

B Bahan 12,500.00 15,000.00


1 m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 12,500.00 15,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 69,890.00 82,823.00


E Overhead & Profit (contoh 10%) 10% 6,989.00 8,282.30
F Harga Satuan Pekerjaan (D+E) 76,879.00 91,105.30

66 A.8.4.1.66 1 m' Pemasangan Pipa Baja Ø 125 mm 87,175.00 102,220.80


A Tenaga 64,210.00 75,880.00
L.01 0.648 OH Pekerja 70,000.00 85,000.00 45,360.00 55,080.00
L.02 0.130 OH Tukang Pipa 95,000.00 105,000.00 12,350.00 13,650.00
L.04 0.065 OH Mandor 100,000.00 110,000.00 6,500.00 7,150.00

B Bahan 15,000.00 17,000.00


1 m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 15,000.00 17,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 79,250.00 92,928.00


E Overhead & Profit (contoh 10%) 10% 7,925.00 9,292.80
F Harga Satuan Pekerjaan (D+E) 87,175.00 102,220.80

67 A.8.4.1.67 1 m' Pemasangan Pipa Baja Ø 150 mm 99,209.00 118,742.80


A Tenaga 70,150.00 82,900.00
L.01 0.708 OH Pekerja 70,000.00 85,000.00 49,560.00 60,180.00
L.02 0.142 OH Tukang Pipa 95,000.00 105,000.00 13,490.00 14,910.00
L.04 0.071 OH Mandor 100,000.00 110,000.00 7,100.00 7,810.00

B Bahan 20,000.00 25,000.00


1 m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 20,000.00 25,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 90,190.00 107,948.00


E Overhead & Profit (contoh 10%) 10% 9,019.00 10,794.80
F Harga Satuan Pekerjaan (D+E) 99,209.00 118,742.80

68 A.8.4.1.68 1 m' Pemasangan Pipa Baja Ø 200 mm 154,258.50 181,805.80


A Tenaga 110,195.00 130,230.00
L.01 1.113 OH Pekerja 70,000.00 85,000.00 77,910.00 94,605.00
L.02 0.223 OH Tukang Pipa 95,000.00 105,000.00 21,185.00 23,415.00
L.04 0.111 OH Mandor 100,000.00 110,000.00 11,100.00 12,210.00

B Bahan 30,000.00 35,000.00


1 m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 30,000.00 35,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 140,235.00 165,278.00


E Overhead & Profit (contoh 10%) 10% 14,023.50 16,527.80
F Harga Satuan Pekerjaan (D+E) 154,258.50 181,805.80
69 A.8.4.1.69 1 m' Pemasangan Pipa Baja Ø 250 mm 199,391.50 236,640.80
A Tenaga 131,225.00 155,080.00
L.01 1.325 OH Pekerja 70,000.00 85,000.00 92,750.00 112,625.00
L.02 0.265 OH Tukang Pipa 95,000.00 105,000.00 25,175.00 27,825.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 50,000.00 60,000.00


1 m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 50,000.00 60,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 181,265.00 215,128.00


E Overhead & Profit (contoh 10%) 10% 18,126.50 21,512.80
F Harga Satuan Pekerjaan (D+E) 199,391.50 236,640.80

70 A.8.4.1.70 1 m' Pemasangan Pipa Baja Ø 300 mm 231,082.50 264,602.80


A Tenaga 140,035.00 165,500.00
L.01 1.415 OH Pekerja 70,000.00 85,000.00 99,050.00 120,275.00
L.02 0.283 OH Tukang Pipa 95,000.00 105,000.00 26,885.00 29,715.00
L.04 0.141 OH Mandor 100,000.00 110,000.00 14,100.00 15,510.00

B Bahan 70,000.00 75,000.00


1 m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 70,000.00 75,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 210,075.00 240,548.00


E Overhead & Profit (contoh 10%) 10% 21,007.50 24,054.80
F Harga Satuan Pekerjaan (D+E) 231,082.50 264,602.80

71 A.8.4.1.71 1 m' Pemasangan Pipa Baja Ø 400 mm 346,505.50 396,410.30


A Tenaga 220,840.00 260,995.00
L.01 2.231 OH Pekerja 70,000.00 85,000.00 156,170.00 189,635.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 85,000.00 90,000.00


1 m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 85,000.00 90,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 315,005.00 360,373.00
E Overhead & Profit (contoh 10%) 10% 31,500.50 36,037.30
F Harga Satuan Pekerjaan (D+E) 346,505.50 396,410.30

72 A.8.4.1.72 1 m' Pemasangan Pipa Baja Ø 450 mm 362,626.00 418,020.90


A Tenaga 220,840.00 260,995.00
L.01 2.231 OH Pekerja 70,000.00 85,000.00 156,170.00 189,635.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 100,000.00 110,000.00


1 m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 8,820.00 9,024.00


0.026 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,450.00 8,580.00
0.037 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 370.00 444.00
D Jumlah A + B + C 329,660.00 380,019.00
E Overhead & Profit (contoh 10%) 10% 32,966.00 38,001.90
F Harga Satuan Pekerjaan (D+E) 362,626.00 418,020.90
73 A.8.4.1.73 1 m' Pemasangan Pipa Baja Ø 500 mm 413,143.50 489,049.00
A Tenaga 240,710.00 284,480.00
L.01 2.432 OH Pekerja 70,000.00 85,000.00 170,240.00 206,720.00
L.02 0.486 OH Tukang Pipa 95,000.00 105,000.00 46,170.00 51,030.00
L.04 0.243 OH Mandor 100,000.00 110,000.00 24,300.00 26,730.00

B Bahan 125,000.00 150,000.00


1 m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 125,000.00 150,000.00

C PERALATAN 9,875.00 10,110.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 375,585.00 444,590.00
E Overhead & Profit (contoh 10%) 10% 37,558.50 44,459.00
F Harga Satuan Pekerjaan (D+E) 413,143.50 489,049.00

74 A.8.4.1.74 1 m' Pemasangan Pipa Baja Ø 600 mm 448,596.50 514,555.80


A Tenaga 218,650.00 258,400.00
L.01 2.208 OH Pekerja 70,000.00 85,000.00 154,560.00 187,680.00
L.02 0.442 OH Tukang Pipa 95,000.00 105,000.00 41,990.00 46,410.00
L.04 0.221 OH Mandor 100,000.00 110,000.00 22,100.00 24,310.00

B Bahan 180,000.00 200,000.00


1 m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 180,000.00 200,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 407,815.00 467,778.00
E Overhead & Profit (contoh 10%) 10% 40,781.50 46,777.80
F Harga Satuan Pekerjaan (D+E) 448,596.50 514,555.80

75 A.8.4.1.75 1 m' Pemasangan Pipa Baja Ø 800 mm 716,897.50 822,025.60


A Tenaga 385,795.00 455,940.00
L.01 3.897 OH Pekerja 70,000.00 85,000.00 272,790.00 331,245.00
L.02 0.779 OH Tukang Pipa 95,000.00 105,000.00 74,005.00 81,795.00
L.04 0.390 OH Mandor 100,000.00 110,000.00 39,000.00 42,900.00

B Bahan 250,000.00 275,000.00


1 m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 250,000.00 275,000.00

C PERALATAN 15,930.00 16,356.00


0.046 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 14,950.00 15,180.00
0.098 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 980.00 1,176.00
D Jumlah A + B + C 651,725.00 747,296.00
E Overhead & Profit (contoh 10%) 10% 65,172.50 74,729.60
F Harga Satuan Pekerjaan (D+E) 716,897.50 822,025.60

76 A.8.4.1.76 1 m' Pemasangan Pipa Baja Ø 900 mm 821,931.00 930,869.50


A Tenaga 429,160.00 507,705.00
L.01 4.403 OH Pekerja 70,000.00 85,000.00 308,210.00 374,255.00
L.02 0.810 OH Tukang Pipa 95,000.00 105,000.00 76,950.00 85,050.00
L.04 0.440 OH Mandor 100,000.00 110,000.00 44,000.00 48,400.00

B Bahan 300,000.00 320,000.00


1 m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 18,050.00 18,540.00


0.052 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 16,900.00 17,160.00
0.115 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,150.00 1,380.00
D Jumlah A + B + C 747,210.00 846,245.00
E Overhead & Profit (contoh 10%) 10% 74,721.00 84,624.50
F Harga Satuan Pekerjaan (D+E) 821,931.00 930,869.50
77 A.8.4.1.77 1 m' Pemasangan Pipa Baja Ø 1.000 mm 940,208.50 1,065,235.60
A Tenaga 484,555.00 572,660.00
L.01 4.895 OH Pekerja 70,000.00 85,000.00 342,650.00 416,075.00
L.02 0.979 OH Tukang Pipa 95,000.00 105,000.00 93,005.00 102,795.00
L.04 0.489 OH Mandor 100,000.00 110,000.00 48,900.00 53,790.00

B Bahan 350,000.00 375,000.00


1 m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 350,000.00 375,000.00

C PERALATAN 20,180.00 20,736.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.133 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,330.00 1,596.00
D Jumlah A + B + C 854,735.00 968,396.00
E Overhead & Profit (contoh 10%) 10% 85,473.50 96,839.60
F Harga Satuan Pekerjaan (D+E) 940,208.50 1,065,235.60

78 A.8.4.1.78 1 m' Pemasangan Pipa Baja Ø 1.100 mm 1,051,165.50 1,186,009.00


A Tenaga 533,305.00 630,270.00
L.01 5.387 OH Pekerja 70,000.00 85,000.00 377,090.00 457,895.00
L.02 1.077 OH Tukang Pipa 95,000.00 105,000.00 102,315.00 113,085.00
L.04 0.539 OH Mandor 100,000.00 110,000.00 53,900.00 59,290.00

B Bahan 400,000.00 425,000.00


1 m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 400,000.00 425,000.00

C PERALATAN 22,300.00 22,920.00


0.064 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 20,800.00 21,120.00
0.15 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,500.00 1,800.00
D Jumlah A + B + C 955,605.00 1,078,190.00
E Overhead & Profit (contoh 10%) 10% 95,560.50 107,819.00
F Harga Satuan Pekerjaan (D+E) 1,051,165.50 1,186,009.00

79 A.8.4.1.79 1 m' Pemasangan Pipa Baja Ø 1.200 mm 1,163,503.00 1,308,459.90


A Tenaga 583,310.00 689,405.00
L.01 5.897 OH Pekerja 70,000.00 85,000.00 412,790.00 501,245.00
L.02 1.176 OH Tukang Pipa 95,000.00 105,000.00 111,720.00 123,480.00
L.04 0.588 OH Mandor 100,000.00 110,000.00 58,800.00 64,680.00

B Bahan 450,000.00 475,000.00


1 m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 450,000.00 475,000.00

C PERALATAN 24,420.00 25,104.00


0.070 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 22,750.00 23,100.00
0.167 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,670.00 2,004.00
D Jumlah A + B + C 1,057,730.00 1,189,509.00
E Overhead & Profit (contoh 10%) 10% 105,773.00 118,950.90
F Harga Satuan Pekerjaan (D+E) 1,163,503.00 1,308,459.90
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA
1 A.8.4.2.1 1 bh Pemotongan Pipa PVC Ø 63 mm 675.40 792.00
A Tenaga 590.00 690.00
L.01 0.005 OH Pekerja 70,000.00 85,000.00 350.00 425.00
L.02 0.002 OH Tukang Pipa 95,000.00 105,000.00 190.00 210.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00

B Bahan - -
- m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 614.00 720.00


E Overhead & Profit (contoh 10%) 10% 61.40 72.00
F Harga Satuan Pekerjaan (D+E) 675.40 792.00

2 A.8.4.2.2 1 bh Pemotongan Pipa PVC Ø 90 mm 1,945.90 2,271.50


A Tenaga 1,745.00 2,035.00
L.01 0.014 OH Pekerja 70,000.00 85,000.00 980.00 1,190.00
L.02 0.007 OH Tukang Pipa 95,000.00 105,000.00 665.00 735.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00

B Bahan - -
- m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 1,769.00 2,065.00


E Overhead & Profit (contoh 10%) 10% 176.90 206.50
F Harga Satuan Pekerjaan (D+E) 1,945.90 2,271.50

3 A.8.4.2.3 1 bh Pemotongan Pipa PVC Ø 110 mm 3,089.90 3,602.50


A Tenaga 2,785.00 3,245.00
L.01 0.022 OH Pekerja 70,000.00 85,000.00 1,540.00 1,870.00
L.02 0.011 OH Tukang Pipa 95,000.00 105,000.00 1,045.00 1,155.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan - -
- m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 2,809.00 3,275.00
E Overhead & Profit (contoh 10%) 10% 280.90 327.50
F Harga Satuan Pekerjaan (D+E) 3,089.90 3,602.50

4 A.8.4.2.4 1 bh Pemotongan Pipa PVC Ø 150 mm 4,310.90 5,027.00


A Tenaga 3,895.00 4,540.00
L.01 0.031 OH Pekerja 70,000.00 85,000.00 2,170.00 2,635.00
L.02 0.015 OH Tukang Pipa 95,000.00 105,000.00 1,425.00 1,575.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan - -
- m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 - -
C PERALATAN 24.00 30.00
0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 3,919.00 4,570.00
E Overhead & Profit (contoh 10%) 10% 391.90 457.00
F Harga Satuan Pekerjaan (D+E) 4,310.90 5,027.00
5 A.8.4.2.5 1 bh Pemotongan Pipa PVC Ø 200 mm 11,446.60 13,348.50
A Tenaga 10,270.00 11,965.00
L.01 0.081 OH Pekerja 70,000.00 85,000.00 5,670.00 6,885.00
L.02 0.040 OH Tukang Pipa 95,000.00 105,000.00 3,800.00 4,200.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
- m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 - -

C PERALATAN 136.00 170.00


0.017 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 136.00 170.00

D Jumlah A + B + C 10,406.00 12,135.00


E Overhead & Profit (contoh 10%) 10% 1,040.60 1,213.50
F Harga Satuan Pekerjaan (D+E) 11,446.60 13,348.50

6 A.8.4.2.6 1 bh Pemotongan Pipa PVC Ø 250 mm 18,238.00 21,263.00


A Tenaga 16,340.00 19,030.00
L.01 0.128 OH Pekerja 70,000.00 85,000.00 8,960.00 10,880.00
L.02 0.064 OH Tukang Pipa 95,000.00 105,000.00 6,080.00 6,720.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 - -

C PERALATAN 240.00 300.00


0.03 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 240.00 300.00

D Jumlah A + B + C 16,580.00 19,330.00


E Overhead & Profit (contoh 10%) 10% 1,658.00 1,933.00
F Harga Satuan Pekerjaan (D+E) 18,238.00 21,263.00

7 A.8.4.2.7 1 bh Pemotongan Pipa PVC Ø 300 mm 21,957.10 25,608.00


A Tenaga 19,665.00 22,910.00
L.01 0.155 OH Pekerja 70,000.00 85,000.00 10,850.00 13,175.00
L.02 0.077 OH Tukang Pipa 95,000.00 105,000.00 7,315.00 8,085.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

B Bahan - -
- m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 - -

C PERALATAN 296.00 370.00


0.037 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 296.00 370.00

D Jumlah A + B + C 19,961.00 23,280.00


E Overhead & Profit (contoh 10%) 10% 1,996.10 2,328.00
F Harga Satuan Pekerjaan (D+E) 21,957.10 25,608.00

8 A.8.4.2.8 1 bh Pemotongan Pipa PVC Ø 400 mm 47,220.80 55,060.50


A Tenaga 42,240.00 49,195.00
L.01 0.331 OH Pekerja 70,000.00 85,000.00 23,170.00 28,135.00
L.02 0.166 OH Tukang Pipa 95,000.00 105,000.00 15,770.00 17,430.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan - -
- m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 - -

C PERALATAN 688.00 860.00


0.086 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 688.00 860.00

D Jumlah A + B + C 42,928.00 50,055.00


E Overhead & Profit (contoh 10%) 10% 4,292.80 5,005.50
F Harga Satuan Pekerjaan (D+E) 47,220.80 55,060.50
9 A.8.4.2.9 1 bh Pemotongan Pipa PVC Ø 450 mm 60,390.00 70,389.00
A Tenaga 53,550.00 62,370.00
L.01 0.420 OH Pekerja 70,000.00 85,000.00 29,400.00 35,700.00
L.02 0.210 OH Tukang Pipa 95,000.00 105,000.00 19,950.00 22,050.00
L.04 0.042 OH Mandor 100,000.00 110,000.00 4,200.00 4,620.00

B Bahan - -
- m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 - -

C PERALATAN 1,350.00 1,620.00


0.054 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,350.00 1,620.00

D Jumlah A + B + C 54,900.00 63,990.00


E Overhead & Profit (contoh 10%) 10% 5,490.00 6,399.00
F Harga Satuan Pekerjaan (D+E) 60,390.00 70,389.00

10 A.8.4.2.10 1 bh Pemotongan Pipa PVC Ø 500 mm 74,569.00 86,916.50


A Tenaga 66,065.00 76,945.00
L.01 0.518 OH Pekerja 70,000.00 85,000.00 36,260.00 44,030.00
L.02 0.259 OH Tukang Pipa 95,000.00 105,000.00 24,605.00 27,195.00
L.04 0.052 OH Mandor 100,000.00 110,000.00 5,200.00 5,720.00

B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -

C PERALATAN 1,725.00 2,070.00


0.069 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,725.00 2,070.00

D Jumlah A + B + C 67,790.00 79,015.00


E Overhead & Profit (contoh 10%) 10% 6,779.00 7,901.50
F Harga Satuan Pekerjaan (D+E) 74,569.00 86,916.50

11 A.8.4.2.11 1 bh Pemotongan Pipa PVC Ø 600 mm 89,655.50 104,511.00


A Tenaga 79,355.00 92,430.00
L.01 0.623 OH Pekerja 70,000.00 85,000.00 43,610.00 52,955.00
L.02 0.311 OH Tukang Pipa 95,000.00 105,000.00 29,545.00 32,655.00
L.04 0.062 OH Mandor 100,000.00 110,000.00 6,200.00 6,820.00

B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -

C PERALATAN 2,150.00 2,580.00


0.086 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,150.00 2,580.00

D Jumlah A + B + C 81,505.00 95,010.00


E Overhead & Profit (contoh 10%) 10% 8,150.50 9,501.00
F Harga Satuan Pekerjaan (D+E) 89,655.50 104,511.00

12 A.8.4.2.12 1 bh Pemasangan Pipa PVC Ø 800 mm 157,195.50 183,238.00


A Tenaga 138,905.00 161,780.00
L.01 1.089 OH Pekerja 70,000.00 85,000.00 76,230.00 92,565.00
L.02 0.545 OH Tukang Pipa 95,000.00 105,000.00 51,775.00 57,225.00
L.04 0.109 OH Mandor 100,000.00 110,000.00 10,900.00 11,990.00

B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
C PERALATAN 4,000.00 4,800.00
0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00
D Jumlah A + B + C 142,905.00 166,580.00
E Overhead & Profit (contoh 10%) 10% 14,290.50 16,658.00
F Harga Satuan Pekerjaan (D+E) 157,195.50 183,238.00
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 164,686.50 191,972.00
A Tenaga 145,515.00 169,480.00
L.01 1.141 OH Pekerja 70,000.00 85,000.00 79,870.00 96,985.00
L.02 0.571 OH Tukang Pipa 95,000.00 105,000.00 54,245.00 59,955.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00

B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -

C PERALATAN 4,200.00 5,040.00


0.168 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,200.00 5,040.00

D Jumlah A + B + C 149,715.00 174,520.00


E Overhead & Profit (contoh 10%) 10% 14,971.50 17,452.00
F Harga Satuan Pekerjaan (D+E) 164,686.50 191,972.00

14 A.8.4.2.14 1 bh Pemotongan Pipa PVC Ø 1.000 mm 185,581.00 216,326.00


A , 163,935.00 190,930.00
L.01 1.285 OH Pekerja 70,000.00 85,000.00 89,950.00 109,225.00
L.02 0.643 OH Tukang Pipa 95,000.00 105,000.00 61,085.00 67,515.00
L.04 0.129 OH Mandor 100,000.00 110,000.00 12,900.00 14,190.00

B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -

C PERALATAN 4,775.00 5,730.00


0.191 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,775.00 5,730.00

D Jumlah A + B + C 168,710.00 196,660.00


E Overhead & Profit (contoh 10%) 10% 16,871.00 19,666.00
F Harga Satuan Pekerjaan (D+E) 185,581.00 216,326.00

15 A.8.4.2.15 1 bh Pemotongan Pipa PVC Ø 1.100 mm 206,338.00 240,526.00


A Tenaga 182,255.00 212,270.00
L.01 1.429 OH Pekerja 70,000.00 85,000.00 100,030.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -

C PERALATAN 5,325.00 6,390.00


0.213 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,325.00 6,390.00

D Jumlah A + B + C 187,580.00 218,660.00


E Overhead & Profit (contoh 10%) 10% 18,758.00 21,866.00
F Harga Satuan Pekerjaan (D+E) 206,338.00 240,526.00

16 A.8.4.2.16 1 bh Pemotongan Pipa PVC Ø 1.200 mm 227,122.50 264,759.00


A Tenaga 200,575.00 233,610.00
L.01 1.573 OH Pekerja 70,000.00 85,000.00 110,110.00 133,705.00
L.02 0.787 OH Tukang Pipa 95,000.00 105,000.00 74,765.00 82,635.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -

C PERALATAN 5,900.00 7,080.00


0.236 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,900.00 7,080.00
D Jumlah A + B + C 206,475.00 240,690.00
E Overhead & Profit (contoh 10%) 10% 20,647.50 24,069.00
F Harga Satuan Pekerjaan (D+E) 227,122.50 264,759.00
17 A.8.4.2.17 1 bh Pemotongan Pipa HDPE Ø 63 mm 4,130.50 4,572.70
A Tenaga 3,655.00 4,037.00
L.01 0.002 OH Pekerja 70,000.00 85,000.00 140.00 170.00
L.02 0.001 OH Tukang Pipa 95,000.00 105,000.00 95.00 105.00
L.04 0.0002 OH Mandor 100,000.00 110,000.00 20.00 22.00
L.08 0.0340 OH Operator 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan - -
- m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 - -

C PERALATAN 100.00 120.00


0.004 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 100.00 120.00

D Jumlah A + B + C 3,755.00 4,157.00


E Overhead & Profit (contoh 10%) 10% 375.50 415.70
F Harga Satuan Pekerjaan (D+E) 4,130.50 4,572.70

18 A.8.4.2.18 1 bh Pemotongan Pipa HDPE Ø 100 mm 8,833.00 9,784.50


A Tenaga 7,905.00 8,745.00
L.01 0.006 OH Pekerja 70,000.00 85,000.00 420.00 510.00
L.02 0.003 OH Tukang Pipa 95,000.00 105,000.00 285.00 315.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.071 OH Operator 100,000.00 110,000.00 7,100.00 7,810.00
B Bahan - -
- m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 - -

C PERALATAN 125.00 150.00


0.005 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 125.00 150.00

D Jumlah A + B + C 8,030.00 8,895.00


E Overhead & Profit (contoh 10%) 10% 803.00 889.50
F Harga Satuan Pekerjaan (D+E) 8,833.00 9,784.50

19 A.8.4.2.19 1 bh Pemotongan Pipa HDPE Ø 125 mm 12,050.50 13,354.00


A Tenaga 10,805.00 11,960.00
L.01 0.009 OH Pekerja 70,000.00 85,000.00 630.00 765.00
L.02 0.005 OH Tukang Pipa 95,000.00 105,000.00 475.00 525.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.096 OH Operator 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan - -
- m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 - -

C PERALATAN 150.00 180.00


0.006 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 150.00 180.00

D Jumlah A + B + C 10,955.00 12,140.00


E Overhead & Profit (contoh 10%) 10% 1,095.50 1,214.00
F Harga Satuan Pekerjaan (D+E) 12,050.50 13,354.00

20 A.8.4.2.20 1 bh Pemotongan Pipa HDPE Ø 150 mm 15,845.50 17,600.00


A Tenaga 14,180.00 15,730.00
L.01 0.016 OH Pekerja 70,000.00 85,000.00 1,120.00 1,360.00
L.02 0.008 OH Tukang Pipa 95,000.00 105,000.00 760.00 840.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
L.08 0.121 OH Operator 100,000.00 110,000.00 12,100.00 13,310.00
B Bahan - -
- m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 - -

C PERALATAN 225.00 270.00


0.009 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 225.00 270.00
D Jumlah A + B + C 14,405.00 16,000.00
E Overhead & Profit (contoh 10%) 10% 1,440.50 1,600.00
F Harga Satuan Pekerjaan (D+E) 15,845.50 17,600.00
21 A.8.4.2.21 1 bh Pemotongan Pipa HDPE Ø 200 mm 25,404.50 28,391.00
A Tenaga 22,670.00 25,300.00
L.01 0.044 OH Pekerja 70,000.00 85,000.00 3,080.00 3,740.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
L.08 0.171 OH Operator 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan - -
m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 - -

C PERALATAN 425.00 510.00


0.017 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 425.00 510.00

D Jumlah A + B + C 23,095.00 25,810.00


E Overhead & Profit (contoh 10%) 10% 2,309.50 2,581.00
F Harga Satuan Pekerjaan (D+E) 25,404.50 28,391.00

22 A.8.4.2.22 1 bh Pemotongan Pipa HDPE Ø 250 mm 34,320.00 38,423.00


A Tenaga 30,625.00 34,240.00
L.01 0.067 OH Pekerja 70,000.00 85,000.00 4,690.00 5,695.00
L.02 0.033 OH Tukang Pipa 95,000.00 105,000.00 3,135.00 3,465.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
L.08 0.221 OH Operator 100,000.00 110,000.00 22,100.00 24,310.00
B Bahan - -
- m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 - -

C PERALATAN 575.00 690.00


0.023 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 575.00 690.00

D Jumlah A + B + C 31,200.00 34,930.00


E Overhead & Profit (contoh 10%) 10% 3,120.00 3,493.00
F Harga Satuan Pekerjaan (D+E) 34,320.00 38,423.00

23 A.8.4.2.23 1 bh Pemotongan Pipa HDPE Ø 300 mm 43,257.50 48,482.50


A Tenaga 38,575.00 43,175.00
L.01 0.090 OH Pekerja 70,000.00 85,000.00 6,300.00 7,650.00
L.02 0.045 OH Tukang Pipa 95,000.00 105,000.00 4,275.00 4,725.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
L.08 0.271 OH Operator 100,000.00 110,000.00 27,100.00 29,810.00
B Bahan - -
- m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 - -

C PERALATAN 750.00 900.00


0.030 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 750.00 900.00

D Jumlah A + B + C 39,325.00 44,075.00


E Overhead & Profit (contoh 10%) 10% 3,932.50 4,407.50
F Harga Satuan Pekerjaan (D+E) 43,257.50 48,482.50

24 A.8.4.2.24 1 bh Pemotongan Pipa HDPE Ø 400 mm 67,127.50 75,597.50


A Tenaga 59,650.00 67,075.00
L.01 0.177 OH Pekerja 70,000.00 85,000.00 12,390.00 15,045.00
L.02 0.088 OH Tukang Pipa 95,000.00 105,000.00 8,360.00 9,240.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
L.08 0.371 OH Operator 100,000.00 110,000.00 37,100.00 40,810.00
B Bahan - -
- m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 - -
C PERALATAN 1,375.00 1,650.00
0.055 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,375.00 1,650.00

D Jumlah A + B + C 61,025.00 68,725.00


E Overhead & Profit (contoh 10%) 10% 6,102.50 6,872.50
F Harga Satuan Pekerjaan (D+E) 67,127.50 75,597.50
25 A.8.4.2.25 1 bh Pemotongan Pipa HDPE Ø 450 mm 79,898.50 90,123.00
A Tenaga 70,885.00 79,830.00
L.01 0.225 OH Pekerja 70,000.00 85,000.00 15,750.00 19,125.00
L.02 0.113 OH Tukang Pipa 95,000.00 105,000.00 10,735.00 11,865.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
L.08 0.421 OH Operator 100,000.00 110,000.00 42,100.00 46,310.00
B Bahan - -
- m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 - -

C PERALATAN 1,750.00 2,100.00


0.070 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,750.00 2,100.00

D Jumlah A + B + C 72,635.00 81,930.00


E Overhead & Profit (contoh 10%) 10% 7,263.50 8,193.00
F Harga Satuan Pekerjaan (D+E) 79,898.50 90,123.00

26 A.8.4.2.26 1 bh Pemotongan Pipa HDPE Ø 500 mm 89,232.00 100,463.00


A Tenaga 78,995.00 88,780.00
L.01 0.227 OH Pekerja 70,000.00 85,000.00 15,890.00 19,295.00
L.02 0.139 OH Tukang Pipa 95,000.00 105,000.00 13,205.00 14,595.00
L.04 0.028 OH Mandor 100,000.00 110,000.00 2,800.00 3,080.00
L.08 0.471 OH Operator 100,000.00 110,000.00 47,100.00 51,810.00
B Bahan - -
- m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 - -

C PERALATAN 2,125.00 2,550.00


0.085 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,125.00 2,550.00
-
D Jumlah A + B + C 81,120.00 91,330.00
E Overhead & Profit (contoh 10%) 10% 8,112.00 9,133.00
F Harga Satuan Pekerjaan (D+E) 89,232.00 100,463.00

27 A.8.4.2.27 1 bh Pemotongan Pipa HDPE Ø 600 mm 112,310.00 126,841.00


A Tenaga 99,575.00 112,280.00
L.01 0.333 OH Pekerja 70,000.00 85,000.00 23,310.00 28,305.00
L.02 0.167 OH Tukang Pipa 95,000.00 105,000.00 15,865.00 17,535.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
L.08 0.571 OH Operator 100,000.00 110,000.00 57,100.00 62,810.00
B Bahan - -
- m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 - -

C PERALATAN 2,525.00 3,030.00


0.101 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,525.00 3,030.00

D Jumlah A + B + C 102,100.00 115,310.00


E Overhead & Profit (contoh 10%) 10% 10,210.00 11,531.00
F Harga Satuan Pekerjaan (D+E) 112,310.00 126,841.00

28 A.8.4.2.28 1 bh Pemotongan Pipa HDPE Ø 800 mm 174,064.00 197,417.00


A Tenaga 153,765.00 174,100.00
L.01 0.601 OH Pekerja 70,000.00 85,000.00 42,070.00 51,085.00
L.02 0.301 OH Tukang Pipa 95,000.00 105,000.00 28,595.00 31,605.00
L.04 0.060 OH Mandor 100,000.00 110,000.00 6,000.00 6,600.00
L.08 0.771 OH Operator 100,000.00 110,000.00 77,100.00 84,810.00
B Bahan - -
- m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 - -

C PERALATAN 4,475.00 5,370.00


0.179 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,475.00 5,370.00
D Jumlah A + B + C 158,240.00 179,470.00
E Overhead & Profit (contoh 10%) 10% 15,824.00 17,947.00
F Harga Satuan Pekerjaan (D+E) 174,064.00 197,417.00
29 A.8.4.2.29 1 bh Pemotongan Pipa HDPE Ø 900 mm 231,198.00 263,345.50
A Tenaga 203,430.00 231,305.00
L.01 0.913 OH Pekerja 70,000.00 85,000.00 63,910.00 77,605.00
L.02 0.456 OH Tukang Pipa 95,000.00 105,000.00 43,320.00 47,880.00
L.04 0.091 OH Mandor 100,000.00 110,000.00 9,100.00 10,010.00
L.08 0.871 OH Operator 100,000.00 110,000.00 87,100.00 95,810.00
B Bahan - -
- m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 - -

C PERALATAN 6,750.00 8,100.00


0.270 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 6,750.00 8,100.00

D Jumlah A + B + C 210,180.00 239,405.00


E Overhead & Profit (contoh 10%) 10% 21,018.00 23,940.50
F Harga Satuan Pekerjaan (D+E) 231,198.00 263,345.50

30 A.8.4.2.30 1 bh Pemotongan Pipa HDPE Ø 1.000 mm 273,614.00 312,097.50


A Tenaga 240,440.00 273,765.00
L.01 1.125 OH Pekerja 70,000.00 85,000.00 78,750.00 95,625.00
L.02 0.562 OH Tukang Pipa 95,000.00 105,000.00 53,390.00 59,010.00
L.04 0.112 OH Mandor 100,000.00 110,000.00 11,200.00 12,320.00
L.08 0.971 OH Operator 100,000.00 110,000.00 97,100.00 106,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 - -

C PERALATAN 8,300.00 9,960.00


0.332 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 8,300.00 9,960.00

D Jumlah A + B + C 248,740.00 283,725.00


E Overhead & Profit (contoh 10%) 10% 24,874.00 28,372.50
F Harga Satuan Pekerjaan (D+E) 273,614.00 312,097.50

31 A.8.4.2.31 1 bh Pemotongan Pipa HDPE Ø 1.100 mm 301,499.00 343,887.50


A Tenaga 264,965.00 301,675.00
L.01 1.238 OH Pekerja 70,000.00 85,000.00 86,660.00 105,230.00
L.02 0.619 OH Tukang Pipa 95,000.00 105,000.00 58,805.00 64,995.00
L.04 0.124 OH Mandor 100,000.00 110,000.00 12,400.00 13,640.00
L.08 1.071 OH Operator 100,000.00 110,000.00 107,100.00 117,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 - -

C PERALATAN 9,125.00 10,950.00


0.365 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 9,125.00 10,950.00

D Jumlah A + B + C 274,090.00 312,625.00


E Overhead & Profit (contoh 10%) 10% 27,409.00 31,262.50
F Harga Satuan Pekerjaan (D+E) 301,499.00 343,887.50

32 A.8.4.2.32 1 bh Pemotongan Pipa HDPE Ø 1.200 mm 368,951.00 421,850.00


A Tenaga 323,485.00 369,190.00
L.01 1.619 OH Pekerja 70,000.00 85,000.00 113,330.00 137,615.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00
L.08 1.171 OH Operator 100,000.00 110,000.00 117,100.00 128,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 - -

C PERALATAN 11,925.00 14,310.00


0.477 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 11,925.00 14,310.00
D Jumlah A + B + C 335,410.00 383,500.00
E Overhead & Profit (contoh 10%) 10% 33,541.00 38,350.00
F Harga Satuan Pekerjaan (D+E) 368,951.00 421,850.00
33 A.8.4.2.33 1 bh Pemotongan Pipa GIP Ø 63 mm 2,728.00 3,173.50
A Tenaga 2,480.00 2,885.00
L.01 0.019 OH Pekerja 70,000.00 85,000.00 1,330.00 1,615.00
L.02 0.010 OH Tukang Pipa 95,000.00 105,000.00 950.00 1,050.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00

B Bahan - -
- m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 - -

C PERALATAN - -

hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 2,480.00 2,885.00


E Overhead & Profit (contoh 10%) 10% 248.00 288.50
F Harga Satuan Pekerjaan (D+E) 2,728.00 3,173.50

34 A.8.4.2.34 1 bh Pemotongan Pipa GIP Ø 100 mm 8,156.50 9,498.50


A Tenaga 7,415.00 8,635.00
L.01 0.058 OH Pekerja 70,000.00 85,000.00 4,060.00 4,930.00
L.02 0.029 OH Tukang Pipa 95,000.00 105,000.00 2,755.00 3,045.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00

B Bahan - -
- m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 7,415.00 8,635.00


E Overhead & Profit (contoh 10%) 10% 741.50 863.50
F Harga Satuan Pekerjaan (D+E) 8,156.50 9,498.50

35 A.8.4.2.35 1 bh Pemotongan Pipa GIP Ø 125 mm 12,881.00 15,004.00


A Tenaga 11,710.00 13,640.00
L.01 0.092 OH Pekerja 70,000.00 85,000.00 6,440.00 7,820.00
L.02 0.046 OH Tukang Pipa 95,000.00 105,000.00 4,370.00 4,830.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00

B Bahan - -
- m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 11,710.00 13,640.00


E Overhead & Profit (contoh 10%) 10% 1,171.00 1,364.00
F Harga Satuan Pekerjaan (D+E) 12,881.00 15,004.00

36 A.8.4.2.36 1 bh Pemotongan Pipa GIP Ø 150 mm 18,414.00 21,444.50


A Tenaga 16,740.00 19,495.00
L.01 0.131 OH Pekerja 70,000.00 85,000.00 9,170.00 11,135.00
L.02 0.066 OH Tukang Pipa 95,000.00 105,000.00 6,270.00 6,930.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 16,740.00 19,495.00
E Overhead & Profit (contoh 10%) 10% 1,674.00 1,949.50
F Harga Satuan Pekerjaan (D+E) 18,414.00 21,444.50
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 47,685.00 55,539.00
A Tenaga 43,350.00 50,490.00
L.01 0.340 OH Pekerja 70,000.00 85,000.00 23,800.00 28,900.00
L.02 0.170 OH Tukang Pipa 95,000.00 105,000.00 16,150.00 17,850.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00

B Bahan - -
- m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 43,350.00 50,490.00


E Overhead & Profit (contoh 10%) 10% 4,335.00 5,049.00
F Harga Satuan Pekerjaan (D+E) 47,685.00 55,539.00

38 A.8.4.2.38 1 bh Pemotongan Pipa GIP Ø 250 mm 66,511.50 77,473.00


A Tenaga 60,465.00 70,430.00
L.01 0.475 OH Pekerja 70,000.00 85,000.00 33,250.00 40,375.00
L.02 0.237 OH Tukang Pipa 95,000.00 105,000.00 22,515.00 24,885.00
L.04 0.047 OH Mandor 100,000.00 110,000.00 4,700.00 5,170.00

B Bahan - -
- m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 60,465.00 70,430.00


E Overhead & Profit (contoh 10%) 10% 6,046.50 7,043.00
F Harga Satuan Pekerjaan (D+E) 66,511.50 77,473.00

39 A.8.4.2.39 1 bh Pemotongan Pipa GIP Ø 300 mm 70,642.00 82,280.00


A Tenaga 64,220.00 74,800.00
L.01 0.504 OH Pekerja 70,000.00 85,000.00 35,280.00 42,840.00
L.02 0.252 OH Tukang Pipa 95,000.00 105,000.00 23,940.00 26,460.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan - -
- m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 64,220.00 74,800.00


E Overhead & Profit (contoh 10%) 10% 6,422.00 7,480.00
F Harga Satuan Pekerjaan (D+E) 70,642.00 82,280.00

40 A.8.4.2.40 1 bh Pemotongan Pipa GIP Ø 400 mm 103,526.50 120,576.50


A Tenaga 94,115.00 109,615.00
L.01 0.738 OH Pekerja 70,000.00 85,000.00 51,660.00 62,730.00
L.02 0.369 OH Tukang Pipa 95,000.00 105,000.00 35,055.00 38,745.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
- m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 94,115.00 109,615.00


E Overhead & Profit (contoh 10%) 10% 9,411.50 10,961.50
F Harga Satuan Pekerjaan (D+E) 103,526.50 120,576.50
41 A.8.4.2.41 1 bh Pemotongan Pipa GIP Ø 450 mm 118,954.00 138,545.00
A Tenaga 108,140.00 125,950.00
L.01 0.848 OH Pekerja 70,000.00 85,000.00 59,360.00 72,080.00
L.02 0.424 OH Tukang Pipa 95,000.00 105,000.00 40,280.00 44,520.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00

B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 108,140.00 125,950.00


E Overhead & Profit (contoh 10%) 10% 10,814.00 12,595.00
F Harga Satuan Pekerjaan (D+E) 118,954.00 138,545.00

42 A.8.4.2.42 1 bh Pemotongan Pipa GIP Ø 500 mm 121,132.00 141,086.00


A Tenaga 110,120.00 128,260.00
L.01 0.864 OH Pekerja 70,000.00 85,000.00 60,480.00 73,440.00
L.02 0.432 OH Tukang Pipa 95,000.00 105,000.00 41,040.00 45,360.00
L.04 0.086 OH Mandor 100,000.00 110,000.00 8,600.00 9,460.00

B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 110,120.00 128,260.00


E Overhead & Profit (contoh 10%) 10% 11,012.00 12,826.00
F Harga Satuan Pekerjaan (D+E) 121,132.00 141,086.00

43 A.8.4.2.43 1 bh Pemotongan Pipa GIP Ø 600 mm 132,016.50 153,758.00


A Tenaga 120,015.00 139,780.00
L.01 0.941 OH Pekerja 70,000.00 85,000.00 65,870.00 79,985.00
L.02 0.471 OH Tukang Pipa 95,000.00 105,000.00 44,745.00 49,455.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00

B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 120,015.00 139,780.00


E Overhead & Profit (contoh 10%) 10% 12,001.50 13,978.00
F Harga Satuan Pekerjaan (D+E) 132,016.50 153,758.00

44 A.8.4.2.44 1 bh Pemotongan Pipa GIP Ø 800 mm 219,752.50 255,948.00


A Tenaga 199,775.00 232,680.00
L.01 1.567 OH Pekerja 70,000.00 85,000.00 109,690.00 133,195.00
L.02 0.783 OH Tukang Pipa 95,000.00 105,000.00 74,385.00 82,215.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 199,775.00 232,680.00
E Overhead & Profit (contoh 10%) 10% 19,977.50 23,268.00
F Harga Satuan Pekerjaan (D+E) 219,752.50 255,948.00
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 248,242.50 289,129.50
A Tenaga 225,675.00 262,845.00
L.01 1.770 OH Pekerja 70,000.00 85,000.00 123,900.00 150,450.00
L.02 0.885 OH Tukang Pipa 95,000.00 105,000.00 84,075.00 92,925.00
L.04 0.177 OH Mandor 100,000.00 110,000.00 17,700.00 19,470.00

B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 225,675.00 262,845.00


E Overhead & Profit (contoh 10%) 10% 22,567.50 26,284.50
F Harga Satuan Pekerjaan (D+E) 248,242.50 289,129.50

46 A.8.4.2.46 1 bh Pemotongan Pipa GIP Ø 1.000 mm 276,809.50 322,404.50


A Tenaga 251,645.00 293,095.00
L.01 1.974 OH Pekerja 70,000.00 85,000.00 138,180.00 167,790.00
L.02 0.987 OH Tukang Pipa 95,000.00 105,000.00 93,765.00 103,635.00
L.04 0.197 OH Mandor 100,000.00 110,000.00 19,700.00 21,670.00

B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 251,645.00 293,095.00


E Overhead & Profit (contoh 10%) 10% 25,164.50 29,309.50
F Harga Satuan Pekerjaan (D+E) 276,809.50 322,404.50

47 A.8.4.2.47 1 bh Pemotongan Pipa GIP Ø 1.100 mm 305,266.50 355,558.50


A Tenaga 277,515.00 323,235.00
L.01 2.178 OH Pekerja 70,000.00 85,000.00 152,460.00 185,130.00
L.02 1.089 OH Tukang Pipa 95,000.00 105,000.00 103,455.00 114,345.00
L.04 0.216 OH Mandor 100,000.00 110,000.00 21,600.00 23,760.00

B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 277,515.00 323,235.00


E Overhead & Profit (contoh 10%) 10% 27,751.50 32,323.50
F Harga Satuan Pekerjaan (D+E) 305,266.50 355,558.50

48 A.8.4.2.48 1 bh Pemotongan Pipa GIP Ø 1.200 mm 334,053.50 389,075.50


A Tenaga 303,685.00 353,705.00
L.01 2.382 OH Pekerja 70,000.00 85,000.00 166,740.00 202,470.00
L.02 1.191 OH Tukang Pipa 95,000.00 105,000.00 113,145.00 125,055.00
L.04 0.238 OH Mandor 100,000.00 110,000.00 23,800.00 26,180.00

B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 303,685.00 353,705.00
E Overhead & Profit (contoh 10%) 10% 30,368.50 35,370.50
F Harga Satuan Pekerjaan (D+E) 334,053.50 389,075.50
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 7,733.00 9,142.10
A Tenaga 7,000.00 8,275.00
L.01 0.071 OH Pekerja 70,000.00 85,000.00 4,970.00 6,035.00
L.02 0.014 OH Tukang Pipa 95,000.00 105,000.00 1,330.00 1,470.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00

B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -

C PERALATAN 30.00 36.00


0.003 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 30.00 36.00

D Jumlah A + B + C 7,030.00 8,311.00


E Overhead & Profit (contoh 10%) 10% 703.00 831.10
F Harga Satuan Pekerjaan (D+E) 7,733.00 9,142.10

50 A.8.4.2.50 1 bh Pemotongan Pipa DCI Ø 125 mm 12,243.00 14,476.00


A Tenaga 11,030.00 13,040.00
L.01 0.112 OH Pekerja 70,000.00 85,000.00 7,840.00 9,520.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -

C PERALATAN 100.00 120.00


0.010 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 100.00 120.00

D Jumlah A + B + C 11,130.00 13,160.00


E Overhead & Profit (contoh 10%) 10% 1,113.00 1,316.00
F Harga Satuan Pekerjaan (D+E) 12,243.00 14,476.00

51 A.8.4.2.51 1 bh Pemotongan Pipa DCI Ø 150 mm 17,545.00 20,736.10


A Tenaga 15,770.00 18,635.00
L.01 0.159 OH Pekerja 70,000.00 85,000.00 11,130.00 13,515.00
L.02 0.032 OH Tukang Pipa 95,000.00 105,000.00 3,040.00 3,360.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00

B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -

C PERALATAN 180.00 216.00


0.018 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 180.00 216.00

D Jumlah A + B + C 15,950.00 18,851.00


E Overhead & Profit (contoh 10%) 10% 1,595.00 1,885.10
F Harga Satuan Pekerjaan (D+E) 17,545.00 20,736.10

52 A.8.4.2.52 1 bh Pemotongan Pipa DCI Ø 200 mm 40,474.50 47,842.30


A Tenaga 36,255.00 42,845.00
L.01 0.366 OH Pekerja 70,000.00 85,000.00 25,620.00 31,110.00
L.02 0.073 OH Tukang Pipa 95,000.00 105,000.00 6,935.00 7,665.00
L.04 0.037 OH Mandor 100,000.00 110,000.00 3,700.00 4,070.00

B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -

C PERALATAN 540.00 648.00


0.054 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 540.00 648.00

D Jumlah A + B + C 36,795.00 43,493.00


E Overhead & Profit (contoh 10%) 10% 3,679.50 4,349.30
F Harga Satuan Pekerjaan (D+E) 40,474.50 47,842.30
53 A.8.4.2.53 1 bh Pemotongan Pipa DCI Ø 250 mm 52,662.50 62,250.10
A Tenaga 47,145.00 55,715.00
L.01 0.476 OH Pekerja 70,000.00 85,000.00 33,320.00 40,460.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -

C PERALATAN 730.00 876.00


0.073 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 730.00 876.00

D Jumlah A + B + C 47,875.00 56,591.00


E Overhead & Profit (contoh 10%) 10% 4,787.50 5,659.10
F Harga Satuan Pekerjaan (D+E) 52,662.50 62,250.10

54 A.8.4.2.54 1 bh Pemotongan Pipa DCI Ø 300 mm 56,562.00 66,866.80


A Tenaga 50,630.00 59,840.00
L.01 0.512 OH Pekerja 70,000.00 85,000.00 35,840.00 43,520.00
L.02 0.102 OH Tukang Pipa 95,000.00 105,000.00 9,690.00 10,710.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -

C PERALATAN 790.00 948.00


0.079 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 790.00 948.00

D Jumlah A + B + C 51,420.00 60,788.00


E Overhead & Profit (contoh 10%) 10% 5,142.00 6,078.80
F Harga Satuan Pekerjaan (D+E) 56,562.00 66,866.80

55 A.8.4.2.55 1 bh Pemotongan Pipa DCI Ø 400 mm 104,181.00 123,157.10


A Tenaga 93,130.00 110,065.00
L.01 0.941 OH Pekerja 70,000.00 85,000.00 65,870.00 79,985.00
L.02 0.188 OH Tukang Pipa 95,000.00 105,000.00 17,860.00 19,740.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00
- -
B Bahan - -
m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 - -

C PERALATAN 1,580.00 1,896.00


0.158 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,580.00 1,896.00
- -
D Jumlah A + B + C 94,710.00 111,961.00
E Overhead & Profit (contoh 10%) 10% 9,471.00 11,196.10
F Harga Satuan Pekerjaan (D+E) 104,181.00 123,157.10

56 A.8.4.2.56 1 bh Pemotongan Pipa DCI Ø 450 mm 125,746.50 148,645.20


A Tenaga 112,555.00 133,020.00
L.01 1.137 OH Pekerja 70,000.00 85,000.00 79,590.00 96,645.00
L.02 0.227 OH Tukang Pipa 95,000.00 105,000.00 21,565.00 23,835.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00
- -
B Bahan - -
m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 - -

C PERALATAN 1,760.00 2,112.00


0.176 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,760.00 2,112.00
- - - -
D Jumlah A + B + C 114,315.00 135,132.00
E Overhead & Profit (contoh 10%) 10% 11,431.50 13,513.20
F Harga Satuan Pekerjaan (D+E) 125,746.50 148,645.20
57 A.8.4.2.57 1 bh Pemotongan Pipa DCI Ø 500 mm 144,925.00 171,318.40
A Tenaga 129,830.00 153,440.00
L.01 1.312 OH Pekerja 70,000.00 85,000.00 91,840.00 111,520.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 131,750.00 155,744.00
E Overhead & Profit (contoh 10%) 10% 13,175.00 15,574.40
F Harga Satuan Pekerjaan (D+E) 144,925.00 171,318.40

58 A.8.4.2.58 1 bh Pemotongan Pipa DCI Ø 600 mm 144,925.00 171,318.40


A Tenaga 129,830.00 153,440.00
L.01 1.312 OH Pekerja 70,000.00 85,000.00 91,840.00 111,520.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 131,750.00 155,744.00
E Overhead & Profit (contoh 10%) 10% 13,175.00 15,574.40
F Harga Satuan Pekerjaan (D+E) 144,925.00 171,318.40

59 A.8.4.2.59 1 bh Pemotongan Pipa DCI Ø 800 mm 286,396.00 338,525.00


A Tenaga 257,260.00 304,030.00
L.01 2.598 OH Pekerja 70,000.00 85,000.00 181,860.00 220,830.00
L.02 0.520 OH Tukang Pipa 95,000.00 105,000.00 49,400.00 54,600.00
L.04 0.260 OH Mandor 100,000.00 110,000.00 26,000.00 28,600.00
- -
B Bahan - -
m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 - -

C PERALATAN 3,100.00 3,720.00


0.310 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,100.00 3,720.00
- - - -
D Jumlah A + B + C 260,360.00 307,750.00
E Overhead & Profit (contoh 10%) 10% 26,036.00 30,775.00
F Harga Satuan Pekerjaan (D+E) 286,396.00 338,525.00

60 A.8.4.2.60 1 bh Pemotongan Pipa DCI Ø 900 mm 371,184.00 438,748.20


A Tenaga 333,630.00 394,290.00
L.01 3.370 OH Pekerja 70,000.00 85,000.00 235,900.00 286,450.00
L.02 0.674 OH Tukang Pipa 95,000.00 105,000.00 64,030.00 70,770.00
L.04 0.337 OH Mandor 100,000.00 110,000.00 33,700.00 37,070.00
- -
B Bahan - -
m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 - -

C PERALATAN 3,810.00 4,572.00


0.381 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,810.00 4,572.00
- - - -
D Jumlah A + B + C 337,440.00 398,862.00
E Overhead & Profit (contoh 10%) 10% 33,744.00 39,886.20
F Harga Satuan Pekerjaan (D+E) 371,184.00 438,748.20
61 A.8.4.2.61 1 bh Pemotongan Pipa DCI Ø 1.000 mm 442,706.00 523,288.70
A Tenaga 398,050.00 470,425.00
L.01 4.021 OH Pekerja 70,000.00 85,000.00 281,470.00 341,785.00
L.02 0.804 OH Tukang Pipa 95,000.00 105,000.00 76,380.00 84,420.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00
- -
B Bahan - -
m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 - -

C PERALATAN 4,410.00 5,292.00


0.441 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 4,410.00 5,292.00
- - - -
D Jumlah A + B + C 402,460.00 475,717.00
E Overhead & Profit (contoh 10%) 10% 40,246.00 47,571.70
F Harga Satuan Pekerjaan (D+E) 442,706.00 523,288.70

62 A.8.4.2.62 1 bh Pemotongan Pipa DCI Ø 1.100 mm 520,740.00 615,523.70


A Tenaga 468,340.00 553,495.00
L.01 4.731 OH Pekerja 70,000.00 85,000.00 331,170.00 402,135.00
L.02 0.946 OH Tukang Pipa 95,000.00 105,000.00 89,870.00 99,330.00
L.04 0.473 OH Mandor 100,000.00 110,000.00 47,300.00 52,030.00
- -
B Bahan - -
m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 - -

C PERALATAN 5,060.00 6,072.00


0.506 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,060.00 6,072.00
- - - -
D Jumlah A + B + C 473,400.00 559,567.00
E Overhead & Profit (contoh 10%) 10% 47,340.00 55,956.70
F Harga Satuan Pekerjaan (D+E) 520,740.00 615,523.70

63 A.8.4.2.63 1 bh Pemotongan Pipa DCI Ø 1.200 mm 605,440.00 715,640.20


A Tenaga 544,640.00 643,670.00
L.01 5.502 OH Pekerja 70,000.00 85,000.00 385,140.00 467,670.00
L.02 1.100 OH Tukang Pipa 95,000.00 105,000.00 104,500.00 115,500.00
L.04 0.550 OH Mandor 100,000.00 110,000.00 55,000.00 60,500.00
- -
B Bahan - -
m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 - -

C PERALATAN 5,760.00 6,912.00


0.576 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,760.00 6,912.00
- - - -
D Jumlah A + B + C 550,400.00 650,582.00
E Overhead & Profit (contoh 10%) 10% 55,040.00 65,058.20
F Harga Satuan Pekerjaan (D+E) 605,440.00 715,640.20

64 A.8.4.2.64 1 bh Pemotongan pipa Baja Ø 63 mm 4,334.00 5,098.50


A Tenaga 2,830.00 3,340.00
L.01 0.028 OH Pekerja 70,000.00 85,000.00 1,960.00 2,380.00
L.02 0.006 OH Tukang Pipa 95,000.00 105,000.00 570.00 630.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -

C PERALATAN 1,110.00 1,295.00


0.037 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,110.00 1,295.00

D Jumlah A + B + C 3,940.00 4,635.00


E Overhead & Profit (contoh 10%) 10% 394.00 463.50
F Harga Satuan Pekerjaan (D+E) 4,334.00 5,098.50
65 A.8.4.2.65 1 bh Pemotongan Pipa Baja Ø 100 mm 10,521.50 12,419.00
A Tenaga 8,365.00 9,890.00
L.01 0.085 OH Pekerja 70,000.00 85,000.00 5,950.00 7,225.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -

C PERALATAN 1,200.00 1,400.00


0.04 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,200.00 1,400.00

D Jumlah A + B + C 9,565.00 11,290.00


E Overhead & Profit (contoh 10%) 10% 956.50 1,129.00
F Harga Satuan Pekerjaan (D+E) 10,521.50 12,419.00

66 A.8.4.2.66 1 bh Pemotongan Pipa Baja Ø 125 mm 15,878.50 18,744.00


A Tenaga 13,175.00 15,570.00
L.01 0.133 OH Pekerja 70,000.00 85,000.00 9,310.00 11,305.00
L.02 0.027 OH Tukang Pipa 95,000.00 105,000.00 2,565.00 2,835.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -

C PERALATAN 1,260.00 1,470.00


0.042 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,260.00 1,470.00

D Jumlah A + B + C 14,435.00 17,040.00


E Overhead & Profit (contoh 10%) 10% 1,443.50 1,704.00
F Harga Satuan Pekerjaan (D+E) 15,878.50 18,744.00

67 A.8.4.2.67 1 bh Pemotongan Pipa Baja Ø 150 mm 21,499.50 25,388.00


A Tenaga 18,195.00 21,505.00
L.01 0.184 OH Pekerja 70,000.00 85,000.00 12,880.00 15,640.00
L.02 0.037 OH Tukang Pipa 95,000.00 105,000.00 3,515.00 3,885.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -

C PERALATAN 1,350.00 1,575.00


0.045 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,350.00 1,575.00

D Jumlah A + B + C 19,545.00 23,080.00


E Overhead & Profit (contoh 10%) 10% 1,954.50 2,308.00
F Harga Satuan Pekerjaan (D+E) 21,499.50 25,388.00

68 A.8.4.2.68 1 bh Pemotongan Pipa Baja Ø 200 mm 53,839.50 63,596.50


A Tenaga 47,145.00 55,715.00
L.01 0.476 OH Pekerja 70,000.00 85,000.00 33,320.00 40,460.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -

C PERALATAN 1,800.00 2,100.00


0.06 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,800.00 2,100.00

D Jumlah A + B + C 48,945.00 57,815.00


E Overhead & Profit (contoh 10%) 10% 4,894.50 5,781.50
F Harga Satuan Pekerjaan (D+E) 53,839.50 63,596.50
69 A.8.4.2.69 1 bh Pemotongan Pipa Baja Ø 250 mm 74,453.50 87,956.00
A Tenaga 65,645.00 77,580.00
L.01 0.663 OH Pekerja 70,000.00 85,000.00 46,410.00 56,355.00
L.02 0.133 OH Tukang Pipa 95,000.00 105,000.00 12,635.00 13,965.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -

C PERALATAN 2,040.00 2,380.00


0.068 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,040.00 2,380.00

D Jumlah A + B + C 67,685.00 79,960.00


E Overhead & Profit (contoh 10%) 10% 6,768.50 7,996.00
F Harga Satuan Pekerjaan (D+E) 74,453.50 87,956.00

70 A.8.4.2.70 1 bh Pemotongan Pipa Baja Ø 300 mm 83,451.50 98,593.00


A Tenaga 73,705.00 87,110.00
L.01 0.745 OH Pekerja 70,000.00 85,000.00 52,150.00 63,325.00
L.02 0.149 OH Tukang Pipa 95,000.00 105,000.00 14,155.00 15,645.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -

C PERALATAN 2,160.00 2,520.00


0.072 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,160.00 2,520.00

D Jumlah A + B + C 75,865.00 89,630.00


E Overhead & Profit (contoh 10%) 10% 7,586.50 8,963.00
F Harga Satuan Pekerjaan (D+E) 83,451.50 98,593.00

71 A.8.4.2.71 1 bh Pemotongan Pipa Baja Ø 400 mm 160,281.00 189,370.50


A Tenaga 142,560.00 168,480.00
L.01 1.440 OH Pekerja 70,000.00 85,000.00 100,800.00 122,400.00
L.02 0.288 OH Tukang Pipa 95,000.00 105,000.00 27,360.00 30,240.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -

C PERALATAN 3,150.00 3,675.00


0.105 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,150.00 3,675.00
- -
D Jumlah A + B + C 145,710.00 172,155.00
E Overhead & Profit (contoh 10%) 10% 14,571.00 17,215.50
F Harga Satuan Pekerjaan (D+E) 160,281.00 189,370.50

72 A.8.4.2.72 1 bh Pemotongan Pipa Baja Ø 450 mm 151,294.00 178,596.00


A Tenaga 134,330.00 158,615.00
L.01 1.339 OH Pekerja 70,000.00 85,000.00 93,730.00 113,815.00
L.02 0.280 OH Tukang Pipa 95,000.00 105,000.00 26,600.00 29,400.00
L.04 0.140 OH Mandor 100,000.00 110,000.00 14,000.00 15,400.00

B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 137,540.00 162,360.00
E Overhead & Profit (contoh 10%) 10% 13,754.00 16,236.00
F Harga Satuan Pekerjaan (D+E) 151,294.00 178,596.00
73 A.8.4.2.73 1 bh Pemotongan Pipa Baja Ø 500 mm 162,783.50 192,417.50
A Tenaga 144,775.00 171,180.00
L.01 1.473 OH Pekerja 70,000.00 85,000.00 103,110.00 125,205.00
L.02 0.287 OH Tukang Pipa 95,000.00 105,000.00 27,265.00 30,135.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 147,985.00 174,925.00
E Overhead & Profit (contoh 10%) 10% 14,798.50 17,492.50
F Harga Satuan Pekerjaan (D+E) 162,783.50 192,417.50

74 A.8.4.2.74 1 bh Pemotongan Pipa Baja Ø 600 mm 173,459.00 204,935.50


A Tenaga 154,300.00 182,350.00
L.01 1.558 OH Pekerja 70,000.00 85,000.00 109,060.00 132,430.00
L.02 0.312 OH Tukang Pipa 95,000.00 105,000.00 29,640.00 32,760.00
L.04 0.156 OH Mandor 100,000.00 110,000.00 15,600.00 17,160.00

B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -

C PERALATAN 3,390.00 3,955.00


0.113 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,390.00 3,955.00
- - - -
D Jumlah A + B + C 157,690.00 186,305.00
E Overhead & Profit (contoh 10%) 10% 15,769.00 18,630.50
F Harga Satuan Pekerjaan (D+E) 173,459.00 204,935.50

75 A.8.4.2.75 1 bh Pemotongan Pipa Baja Ø 800 mm 291,208.50 344,074.50


A Tenaga 259,755.00 306,985.00
L.01 2.624 OH Pekerja 70,000.00 85,000.00 183,680.00 223,040.00
L.02 0.525 OH Tukang Pipa 95,000.00 105,000.00 49,875.00 55,125.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -

C PERALATAN 4,980.00 5,810.00


0.166 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 4,980.00 5,810.00
- - - -
D Jumlah A + B + C 264,735.00 312,795.00
E Overhead & Profit (contoh 10%) 10% 26,473.50 31,279.50
F Harga Satuan Pekerjaan (D+E) 291,208.50 344,074.50

76 A.8.4.2.76 1 bh Pemotongan Pipa Baja Ø 900 mm 329,549.00 389,378.00


A Tenaga 294,100.00 347,575.00
L.01 2.971 OH Pekerja 70,000.00 85,000.00 207,970.00 252,535.00
L.02 0.594 OH Tukang Pipa 95,000.00 105,000.00 56,430.00 62,370.00
L.04 0.297 OH Mandor 100,000.00 110,000.00 29,700.00 32,670.00

B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -

C PERALATAN 5,490.00 6,405.00


0.183 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 5,490.00 6,405.00
- - - -
D Jumlah A + B + C 299,590.00 353,980.00
E Overhead & Profit (contoh 10%) 10% 29,959.00 35,398.00
F Harga Satuan Pekerjaan (D+E) 329,549.00 389,378.00
77 A.8.4.2.77 1 bh Pemotongan Pipa Baja Ø 1.000 mm 368,104.00 434,929.00
A Tenaga 328,610.00 388,355.00
L.01 3.319 OH Pekerja 70,000.00 85,000.00 232,330.00 282,115.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.332 OH Mandor 100,000.00 110,000.00 33,200.00 36,520.00

B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -

C PERALATAN 6,030.00 7,035.00


0.201 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,030.00 7,035.00
- - - -
D Jumlah A + B + C 334,640.00 395,390.00
E Overhead & Profit (contoh 10%) 10% 33,464.00 39,539.00
F Harga Satuan Pekerjaan (D+E) 368,104.00 434,929.00

78 A.8.4.2.78 1 bh Pemotongan Pipa Baja Ø 1.100 mm 406,521.50 480,326.00


A Tenaga 363,025.00 429,030.00
L.01 3.667 OH Pekerja 70,000.00 85,000.00 256,690.00 311,695.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.367 OH Mandor 100,000.00 110,000.00 36,700.00 40,370.00

B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -

C PERALATAN 6,540.00 7,630.00


0.218 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,540.00 7,630.00
- - - -
D Jumlah A + B + C 369,565.00 436,660.00
E Overhead & Profit (contoh 10%) 10% 36,956.50 43,666.00
F Harga Satuan Pekerjaan (D+E) 406,521.50 480,326.00

79 A.8.4.2.79 1 bh Pemotongan Pipa Baja Ø 1.200 mm 445,076.50 525,877.00


A Tenaga 397,535.00 469,810.00
L.01 4.015 OH Pekerja 70,000.00 85,000.00 281,050.00 341,275.00
L.02 0.803 OH Tukang Pipa 95,000.00 105,000.00 76,285.00 84,315.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00

B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -

C PERALATAN 7,080.00 8,260.00


0.236 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 7,080.00 8,260.00
- - - -
D Jumlah A + B + C 404,615.00 478,070.00
E Overhead & Profit (contoh 10%) 10% 40,461.50 47,807.00
F Harga Satuan Pekerjaan (D+E) 445,076.50 525,877.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN


XVIII A.8.4.3
AKSESORIS PIPA
1 A.8.4.3.1 1 bh Pemasangan Valve Ø 150 mm 256,580.50 306,317.00
A Tenaga 182,255.00 212,270.00
L.01 1.429 OH Pekerja 70,000.00 85,000.00 100,030.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00
B Bahan 50,000.00 65,000.00
1 bh Valve Ø 150 mm 50,000.00 65,000.00 50,000.00 65,000.00
C PERALATAN 1,000.00 1,200.00
0.1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00

D Jumlah A + B + C 233,255.00 278,470.00


E Overhead & Profit (contoh 10%) 10% 23,325.50 27,847.00
F Harga Satuan Pekerjaan (D+E) 256,580.50 306,317.00

2 A.8.4.3.2 1 bh Pemasangan Valve Ø 200 mm 326,144.50 382,893.50


A Tenaga 218,495.00 254,485.00
L.01 1.714 OH Pekerja 70,000.00 85,000.00 119,980.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 75,000.00 90,000.00


1 bh Valve Ø 200 mm 75,000.00 90,000.00 75,000.00 90,000.00

C PERALATAN 3,000.00 3,600.00


0.3 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,000.00 3,600.00

D Jumlah A + B + C 296,495.00 348,085.00


E Overhead & Profit (contoh 10%) 10% 29,649.50 34,808.50
F Harga Satuan Pekerjaan (D+E) 326,144.50 382,893.50

3 A.8.4.3.3 1 bh Pemasangan Valve Ø 250 mm 382,244.50 433,713.50


A Tenaga 218,495.00 254,485.00
L.01 1.714 OH Pekerja 70,000.00 85,000.00 119,980.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 125,000.00 135,000.00


1 bh Valve Ø 250 mm 125,000.00 135,000.00 125,000.00 135,000.00

C PERALATAN 4,000.00 4,800.00


0.4 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,000.00 4,800.00

D Jumlah A + B + C 347,495.00 394,285.00


E Overhead & Profit (contoh 10%) 10% 34,749.50 39,428.50
F Harga Satuan Pekerjaan (D+E) 382,244.50 433,713.50

4 A.8.4.3.4 1 bh Pemasangan Valve Ø 300 mm 451,000.00 520,300.00


A Tenaga 255,000.00 297,000.00
L.01 2.000 OH Pekerja 70,000.00 85,000.00 140,000.00 170,000.00
L.02 1.000 OH Tukang Pipa 95,000.00 105,000.00 95,000.00 105,000.00
L.04 0.200 OH Mandor 100,000.00 110,000.00 20,000.00 22,000.00

B Bahan 150,000.00 170,000.00


1 bh Valve Ø 300 mm 150,000.00 170,000.00 150,000.00 170,000.00

C PERALATAN 5,000.00 6,000.00


0.5 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
D Jumlah A + B + C 410,000.00 473,000.00
E Overhead & Profit (contoh 10%) 10% 41,000.00 47,300.00
F Harga Satuan Pekerjaan (D+E) 451,000.00 520,300.00
5 A.8.4.3.5 1 bh Pemasangan Valve Ø 400 mm 794,480.50 903,397.00
A Tenaga 437,255.00 509,270.00
L.01 3.429 OH Pekerja 70,000.00 85,000.00 240,030.00 291,465.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 275,000.00 300,000.00


1 bh Valve Ø 400 mm 275,000.00 300,000.00 275,000.00 300,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 722,255.00 821,270.00


E Overhead & Profit (contoh 10%) 10% 72,225.50 82,127.00
F Harga Satuan Pekerjaan (D+E) 794,480.50 903,397.00

6 A.8.4.3.6 1 bh Pemasangan Valve Ø 450 mm 849,480.50 958,397.00


A Tenaga 437,255.00 509,270.00
L.01 3.429 OH Pekerja 70,000.00 85,000.00 240,030.00 291,465.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 325,000.00 350,000.00


1 bh Valve Ø 450 mm 325,000.00 350,000.00 325,000.00 350,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 772,255.00 871,270.00


E Overhead & Profit (contoh 10%) 10% 77,225.50 87,127.00
F Harga Satuan Pekerjaan (D+E) 849,480.50 958,397.00

7 A.8.4.3.7 1 bh Pemasangan Valve Ø 500 mm 984,500.00 1,106,600.00


A Tenaga 510,000.00 594,000.00
L.01 4.000 OH Pekerja 70,000.00 85,000.00 280,000.00 340,000.00
L.02 2.000 OH Tukang Pipa 95,000.00 105,000.00 190,000.00 210,000.00
L.04 0.400 OH Mandor 100,000.00 110,000.00 40,000.00 44,000.00

B Bahan 375,000.00 400,000.00


1 bh Valve Ø 500 mm 375,000.00 400,000.00 375,000.00 400,000.00

C PERALATAN 10,000.00 12,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 895,000.00 1,006,000.00


E Overhead & Profit (contoh 10%) 10% 89,500.00 100,600.00
F Harga Satuan Pekerjaan (D+E) 984,500.00 1,106,600.00

8 A.8.4.3.8 1 bh Pemasangan Valve Ø 600 mm 722,936.50 791,186.00


A Tenaga 181,215.00 211,060.00
L.01 1.421 OH Pekerja 70,000.00 85,000.00 99,470.00 120,785.00
L.02 0.711 OH Tukang Pipa 95,000.00 105,000.00 67,545.00 74,655.00
L.04 0.142 OH Mandor 100,000.00 110,000.00 14,200.00 15,620.00

B Bahan 425,000.00 450,000.00


1 bh Valve Ø 600 mm 425,000.00 450,000.00 425,000.00 450,000.00

C PERALATAN 51,000.00 58,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00
0.300 hari Mobile crane = < 3 ton 150,000.00 170,000.00 45,000.00 51,000.00
D Jumlah A + B + C 657,215.00 719,260.00
E Overhead & Profit (contoh 10%) 10% 65,721.50 71,926.00
F Harga Satuan Pekerjaan (D+E) 722,936.50 791,186.00
9 A.8.4.3.9 1 bh Pemasangan Valve Ø 700 mm 838,480.50 905,597.00
A Tenaga 182,255.00 212,270.00
L.01 1.429 OH Pekerja 70,000.00 85,000.00 100,030.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan 500,000.00 520,000.00


1 bh Valve Ø 700 mm 500,000.00 520,000.00 500,000.00 520,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 762,255.00 823,270.00
E Overhead & Profit (contoh 10%) 10% 76,225.50 82,327.00
F Harga Satuan Pekerjaan (D+E) 838,480.50 905,597.00

10 A.8.4.3.10 1 bh Pemasangan Valve Ø 800 mm 943,530.50 1,024,391.50


A Tenaga 227,755.00 265,265.00
L.01 1.786 OH Pekerja 70,000.00 85,000.00 125,020.00 151,810.00
L.02 0.893 OH Tukang Pipa 95,000.00 105,000.00 84,835.00 93,765.00
L.04 0.179 OH Mandor 100,000.00 110,000.00 17,900.00 19,690.00

B Bahan 550,000.00 575,000.00


1 bh Valve Ø 800 mm 550,000.00 575,000.00 550,000.00 575,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 857,755.00 931,265.00
E Overhead & Profit (contoh 10%) 10% 85,775.50 93,126.50
F Harga Satuan Pekerjaan (D+E) 943,530.50 1,024,391.50

11 A.8.4.3.11 1 bh Pemasangan Valve Ø 900 mm 1,032,344.50 1,117,583.50


A Tenaga 218,495.00 254,485.00
L.01 1.714 OH Pekerja 70,000.00 85,000.00 119,980.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan 600,000.00 625,000.00
1 bh Valve Ø 900 mm 600,000.00 625,000.00 600,000.00 625,000.00
C PERALATAN 120,000.00 136,500.00
0.750 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 7,500.00 9,000.00
0.750 hari Mobile crane = < 3 ton 150,000.00 170,000.00 112,500.00 127,500.00
D Jumlah A + B + C 938,495.00 1,015,985.00
E Overhead & Profit (contoh 10%) 10% 93,849.50 101,598.50
F Harga Satuan Pekerjaan (D+E) 1,032,344.50 1,117,583.50

12 A.8.4.3.12 1 bh Pemasangan Valve Ø 1.000 mm 1,251,624.00 1,346,218.50


A Tenaga 327,840.00 381,835.00
L.01 2.571 OH Pekerja 70,000.00 85,000.00 179,970.00 218,535.00
L.02 1.286 OH Tukang Pipa 95,000.00 105,000.00 122,170.00 135,030.00
L.04 0.257 OH Mandor 100,000.00 110,000.00 25,700.00 28,270.00

B Bahan 650,000.00 660,000.00


1 bh Valve Ø 1.000 mm 650,000.00 660,000.00 650,000.00 660,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,137,840.00 1,223,835.00
E Overhead & Profit (contoh 10%) 10% 113,784.00 122,383.50
F Harga Satuan Pekerjaan (D+E) 1,251,624.00 1,346,218.50
13 A.8.4.3.13 1 bh Pemasangan Valve Ø 1.100 mm 1,366,750.00 1,471,250.00
A Tenaga 382,500.00 445,500.00
L.01 3.000 OH Pekerja 70,000.00 85,000.00 210,000.00 255,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 700,000.00 710,000.00


1 bh Valve Ø 1.100 mm 700,000.00 710,000.00 700,000.00 710,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,242,500.00 1,337,500.00
E Overhead & Profit (contoh 10%) 10% 124,250.00 133,750.00
F Harga Satuan Pekerjaan (D+E) 1,366,750.00 1,471,250.00

14 A.8.4.3.14 1 bh Pemasangan Valve Ø 1.200 mm 1,399,750.00 1,515,250.00


A 382,500.00 445,500.00
L.01 3.000 OH Pekerja 70,000.00 85,000.00 210,000.00 255,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 730,000.00 750,000.00


1 bh Valve Ø 1.200 mm 730,000.00 750,000.00 730,000.00 750,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,272,500.00 1,377,500.00
E Overhead & Profit (contoh 10%) 10% 127,250.00 137,750.00
F Harga Satuan Pekerjaan (D+E) 1,399,750.00 1,515,250.00

15 A.8.4.3.15 1 bh Pemasangan Tee Ø 150 mm 28,418.50 34,233.10


A Tenaga 13,555.00 15,785.00
L.01 0.106 OH Pekerja 70,000.00 85,000.00 7,420.00 9,010.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan 12,000.00 15,000.00


1 bh Tee Ø 150 mm 12,000.00 15,000.00 12,000.00 15,000.00

C PERALATAN 280.00 336.00


0.028 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 280.00 336.00

D Jumlah A + B + C 25,835.00 31,121.00


E Overhead & Profit (contoh 10%) 10% 2,583.50 3,112.10
F Harga Satuan Pekerjaan (D+E) 28,418.50 34,233.10

16 A.8.4.3.16 1 bh Pemasangan Tee Ø 200 mm 47,157.00 57,714.80


A Tenaga 27,580.00 32,120.00
L.01 0.216 OH Pekerja 70,000.00 85,000.00 15,120.00 18,360.00
L.02 0.108 OH Tukang Pipa 95,000.00 105,000.00 10,260.00 11,340.00
L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00
B Bahan 15,000.00 20,000.00
1 bh Tee Ø 200 mm 15,000.00 20,000.00 15,000.00 20,000.00

C PERALATAN 290.00 348.00


0.029 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 290.00 348.00
D Jumlah A + B + C 42,870.00 52,468.00
E Overhead & Profit (contoh 10%) 10% 4,287.00 5,246.80
F Harga Satuan Pekerjaan (D+E) 47,157.00 57,714.80
17 A.8.4.3.17 1 bh Pemasangan Tee Ø 250 mm 73,694.50 86,815.30
A Tenaga 41,605.00 48,455.00
L.01 0.326 OH Pekerja 70,000.00 85,000.00 22,820.00 27,710.00
L.02 0.163 OH Tukang Pipa 95,000.00 105,000.00 15,485.00 17,115.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan 25,000.00 30,000.00


1 BH Tee Ø 250 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 390.00 468.00


0.039 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 390.00 468.00

D Jumlah A + B + C 66,995.00 78,923.00


E Overhead & Profit (contoh 10%) 10% 6,699.50 7,892.30
F Harga Satuan Pekerjaan (D+E) 73,694.50 86,815.30

18 A.8.4.3.18 1 bh Pemasangan Tee Ø 300 mm 105,193.00 121,869.00


A Tenaga 55,630.00 64,790.00
L.01 0.436 OH Pekerja 70,000.00 85,000.00 30,520.00 37,060.00
L.02 0.218 OH Tukang Pipa 95,000.00 105,000.00 20,710.00 22,890.00
L.04 0.044 OH Mandor 100,000.00 110,000.00 4,400.00 4,840.00

B Bahan 35,000.00 40,000.00


1 bh Tee Ø 300 mm 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 95,630.00 110,790.00


E Overhead & Profit (contoh 10%) 10% 9,563.00 11,079.00
F Harga Satuan Pekerjaan (D+E) 105,193.00 121,869.00

19 A.8.4.3.19 1 bh Pemasangan Tee Ø 400 mm 147,048.00 168,806.00


A Tenaga 83,680.00 97,460.00
L.01 0.656 OH Pekerja 70,000.00 85,000.00 45,920.00 55,760.00
L.02 0.328 OH Tukang Pipa 95,000.00 105,000.00 31,160.00 34,440.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan 45,000.00 50,000.00


1 bh Tee Ø 400 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 5,000.00 6,000.00
0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 133,680.00 153,460.00


E Overhead & Profit (contoh 10%) 10% 13,368.00 15,346.00
F Harga Satuan Pekerjaan (D+E) 147,048.00 168,806.00

20 A.8.4.3.20 1 bh Pemasangan Tee Ø 450 mm 184,475.50 208,774.50


A Tenaga 97,705.00 113,795.00
L.01 0.766 OH Pekerja 70,000.00 85,000.00 53,620.00 65,110.00
L.02 0.383 OH Tukang Pipa 95,000.00 105,000.00 36,385.00 40,215.00
L.04 0.077 OH Mandor 100,000.00 110,000.00 7,700.00 8,470.00

B Bahan 65,000.00 70,000.00


1 bh Tee Ø 450 mm 65,000.00 70,000.00 65,000.00 70,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 167,705.00 189,795.00


E Overhead & Profit (contoh 10%) 10% 16,770.50 18,979.50
F Harga Satuan Pekerjaan (D+E) 184,475.50 208,774.50
21 A.8.4.3.21 1 bh Pemasangan Tee Ø 500 mm 212,003.00 239,063.00
A Tenaga 111,730.00 130,130.00
L.01 0.876 OH Pekerja 70,000.00 85,000.00 61,320.00 74,460.00
L.02 0.438 OH Tukang Pipa 95,000.00 105,000.00 41,610.00 45,990.00
L.04 0.088 OH Mandor 100,000.00 110,000.00 8,800.00 9,680.00

B Bahan 75,000.00 80,000.00


1 bh Tee Ø 500 mm 75,000.00 80,000.00 75,000.00 80,000.00

C PERALATAN 6,000.00 7,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00

D Jumlah A + B + C 192,730.00 217,330.00


E Overhead & Profit (contoh 10%) 10% 19,273.00 21,733.00
F Harga Satuan Pekerjaan (D+E) 212,003.00 239,063.00

22 A.8.4.3.22 1 bh Pemasangan Tee Ø 600 mm 270,721.00 309,579.60


A Tenaga 139,780.00 162,800.00
L.01 1.096 OH Pekerja 70,000.00 85,000.00 76,720.00 93,160.00
L.02 0.548 OH Tukang Pipa 95,000.00 105,000.00 52,060.00 57,540.00
L.04 0.110 OH Mandor 100,000.00 110,000.00 11,000.00 12,100.00

B Bahan 90,000.00 100,000.00


1 bh Tee Ø 600 mm 90,000.00 100,000.00 90,000.00 100,000.00

C PERALATAN 16,330.00 18,636.00


0.193 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,930.00 2,316.00
0.096 hari Mobile crane = < 3 ton 150,000.00 170,000.00 14,400.00 16,320.00
D Jumlah A + B + C 246,110.00 281,436.00
E Overhead & Profit (contoh 10%) 10% 24,611.00 28,143.60
F Harga Satuan Pekerjaan (D+E) 270,721.00 309,579.60

23 A.8.4.3.23 1 bh Pemasangan Tee Ø 700 mm 326,733.00 365,618.00


A Tenaga 167,830.00 195,470.00
L.01 1.316 OH Pekerja 70,000.00 85,000.00 92,120.00 111,860.00
L.02 0.658 OH Tukang Pipa 95,000.00 105,000.00 62,510.00 69,090.00
L.04 0.132 OH Mandor 100,000.00 110,000.00 13,200.00 14,520.00

B Bahan 110,000.00 115,000.00


1 bh Tee Ø 700 mm 110,000.00 115,000.00 110,000.00 115,000.00

C PERALATAN 19,200.00 21,910.00


0.225 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,250.00 2,700.00
0.113 hari Mobile crane = < 3 ton 150,000.00 170,000.00 16,950.00 19,210.00
D Jumlah A + B + C 297,030.00 332,380.00
E Overhead & Profit (contoh 10%) 10% 29,703.00 33,238.00
F Harga Satuan Pekerjaan (D+E) 326,733.00 365,618.00

24 A.8.4.3.24 1 bh Pemasangan Tee Ø 800 mm 371,580.00 421,469.40


A Tenaga 195,880.00 228,140.00
L.01 1.536 OH Pekerja 70,000.00 85,000.00 107,520.00 130,560.00
L.02 0.768 OH Tukang Pipa 95,000.00 105,000.00 72,960.00 80,640.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00
B Bahan 120,000.00 130,000.00
1 bh Tee Ø 800 mm 120,000.00 130,000.00 120,000.00 130,000.00
C PERALATAN 21,920.00 25,014.00
0.257 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,570.00 3,084.00
0.129 hari Mobile crane = < 3 ton 150,000.00 170,000.00 19,350.00 21,930.00
D Jumlah A + B + C 337,800.00 383,154.00
E Overhead & Profit (contoh 10%) 10% 33,780.00 38,315.40
F Harga Satuan Pekerjaan (D+E) 371,580.00 421,469.40
25 A.8.4.3.25 1 bh Pemasangan Tee Ø 900 mm 430,419.00 486,235.20
A Tenaga 223,930.00 260,810.00
L.01 1.756 OH Pekerja 70,000.00 85,000.00 122,920.00 149,260.00
L.02 0.878 OH Tukang Pipa 95,000.00 105,000.00 83,410.00 92,190.00
L.04 0.176 OH Mandor 100,000.00 110,000.00 17,600.00 19,360.00

B Bahan 140,000.00 150,000.00


1 bh Tee Ø 900 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN 27,360.00 31,222.00


0.321 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,210.00 3,852.00
0.161 hari Mobile crane = < 3 ton 150,000.00 170,000.00 24,150.00 27,370.00
D Jumlah A + B + C 391,290.00 442,032.00
E Overhead & Profit (contoh 10%) 10% 39,129.00 44,203.20
F Harga Satuan Pekerjaan (D+E) 430,419.00 486,235.20

26 A.8.4.3.26 1 bh Pemasangan Tee Ø 1.000 mm 487,399.00 548,880.20


A Tenaga 251,980.00 293,480.00
L.01 1.976 OH Pekerja 70,000.00 85,000.00 138,320.00 167,960.00
L.02 0.988 OH Tukang Pipa 95,000.00 105,000.00 93,860.00 103,740.00
L.04 0.198 OH Mandor 100,000.00 110,000.00 19,800.00 21,780.00

B Bahan 160,000.00 170,000.00


1 bh Tee Ø 1.000 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN 31,110.00 35,502.00


0.366 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,660.00 4,392.00
0.183 hari Mobile crane = < 3 ton 150,000.00 170,000.00 27,450.00 31,110.00
D Jumlah A + B + C 443,090.00 498,982.00
E Overhead & Profit (contoh 10%) 10% 44,309.00 49,898.20
F Harga Satuan Pekerjaan (D+E) 487,399.00 548,880.20

27 A.8.4.3.27 1 bh Pemasangan Tee Ø 1.100 mm 542,124.00 608,951.20


A Tenaga 280,030.00 326,150.00
L.01 2.196 OH Pekerja 70,000.00 85,000.00 153,720.00 186,660.00
L.02 1.098 OH Tukang Pipa 95,000.00 105,000.00 104,310.00 115,290.00
L.04 0.220 OH Mandor 100,000.00 110,000.00 22,000.00 24,200.00

B Bahan 180,000.00 190,000.00


1 bh Tee Ø 1.100 mm 180,000.00 190,000.00 180,000.00 190,000.00

C PERALATAN 32,810.00 37,442.00


0.386 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,860.00 4,632.00
0.193 hari Mobile crane = < 3 ton 150,000.00 170,000.00 28,950.00 32,810.00
D Jumlah A + B + C 492,840.00 553,592.00
E Overhead & Profit (contoh 10%) 10% 49,284.00 55,359.20
F Harga Satuan Pekerjaan (D+E) 542,124.00 608,951.20

28 A.8.4.3.28 1 bh Pemasangan Tee Ø 1.200 mm 600,963.00 673,717.00


A Tenaga 308,080.00 358,820.00
L.01 2.416 OH Pekerja 70,000.00 85,000.00 169,120.00 205,360.00
L.02 1.208 OH Tukang Pipa 95,000.00 105,000.00 114,760.00 126,840.00
L.04 0.242 OH Mandor 100,000.00 110,000.00 24,200.00 26,620.00
B Bahan 200,000.00 210,000.00
1 bh Tee Ø 1.200 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 38,250.00 43,650.00
0.450 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,500.00 5,400.00
0.225 hari Mobile crane = < 3 ton 150,000.00 170,000.00 33,750.00 38,250.00
D Jumlah A + B + C 546,330.00 612,470.00
E Overhead & Profit (contoh 10%) 10% 54,633.00 61,247.00
F Harga Satuan Pekerjaan (D+E) 600,963.00 673,717.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

1 A.8.4.4.1 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 432,305.50 516,180.50
80 mm
A Tenaga 186,955.00 217,745.00
L.01 1.466 OH Pekerja 70,000.00 85,000.00 102,620.00 124,610.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 50,000.00 65,000.00


1 bh Pipa Ø 80 mm 50,000.00 65,000.00 50,000.00 65,000.00

C PERALATAN 156,050.00 186,510.00


0.606 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 15,150.00 18,180.00
0.075 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 11,250.00 12,750.00
0.968 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 121,000.00 145,200.00
0.865 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,650.00 10,380.00

D Jumlah A + B + C 393,005.00 469,255.00


E Overhead & Profit (contoh 10%) 10% 39,300.50 46,925.50
F Harga Satuan Pekerjaan (D+E) 432,305.50 516,180.50

2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 519,304.50 598,000.70
100 mm
A Tenaga 218,135.00 244,475.00
L.01 1.646 OH Pekerja 75,000.00 85,000.00 123,450.00 139,910.00
L.02 0.823 OH Tukang Pipa 95,000.00 105,000.00 78,185.00 86,415.00
L.04 0.165 OH Mandor 100,000.00 110,000.00 16,500.00 18,150.00

B Bahan 70,000.00 80,000.00


1 bh Pipa Ø 100 mm 70,000.00 80,000.00 70,000.00 80,000.00

C PERALATAN 183,960.00 219,162.00


0.650 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 16,250.00 19,500.00
0.159 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 23,850.00 27,030.00
1.078 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 134,750.00 161,700.00
0.911 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 9,110.00 10,932.00

D Jumlah A + B + C 472,095.00 543,637.00


E Overhead & Profit (contoh 10%) 10% 47,209.50 54,363.70
F Harga Satuan Pekerjaan (D+E) 519,304.50 598,000.70

3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 749,644.50 849,301.20
150 mm
A Tenaga 277,760.00 311,300.00
L.01 2.096 OH Pekerja 75,000.00 85,000.00 157,200.00 178,160.00
L.02 1.048 OH Tukang Pipa 95,000.00 105,000.00 99,560.00 110,040.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 681,495.00 772,092.00
E Overhead & Profit (contoh 10%) 10% 68,149.50 77,209.20
F Harga Satuan Pekerjaan (D+E) 749,644.50 849,301.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 946,984.50 1,078,601.70
200 mm
A Tenaga 337,385.00 378,125.00
L.01 2.546 OH Pekerja 75,000.00 85,000.00 190,950.00 216,410.00
L.02 1.273 OH Tukang Pipa 95,000.00 105,000.00 120,935.00 133,665.00
L.04 0.255 OH Mandor 100,000.00 110,000.00 25,500.00 28,050.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 860,895.00 980,547.00
E Overhead & Profit (contoh 10%) 10% 86,089.50 98,054.70
F Harga Satuan Pekerjaan (D+E) 946,984.50 1,078,601.70

5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,116,824.50 1,263,902.20
250 mm
A Tenaga 397,010.00 444,950.00
L.01 2.996 OH Pekerja 75,000.00 85,000.00 224,700.00 254,660.00
L.02 1.498 OH Tukang Pipa 95,000.00 105,000.00 142,310.00 157,290.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
B Bahan 225,000.00 240,000.00
1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00
C PERALATAN 393,285.00 464,052.00
0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00
D Jumlah A + B + C 1,015,295.00 1,149,002.00
E Overhead & Profit (contoh 10%) 10% 101,529.50 114,900.20
F Harga Satuan Pekerjaan (D+E) 1,116,824.50 1,263,902.20

6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,275,664.50 1,438,202.70
300 mm
A Tenaga 456,635.00 511,775.00
L.01 3.446 OH Pekerja 75,000.00 85,000.00 258,450.00 292,910.00
L.02 1.723 OH Tukang Pipa 95,000.00 105,000.00 163,685.00 180,915.00
L.04 0.345 OH Mandor 100,000.00 110,000.00 34,500.00 37,950.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,159,695.00 1,307,457.00
E Overhead & Profit (contoh 10%) 10% 115,969.50 130,745.70
F Harga Satuan Pekerjaan (D+E) 1,275,664.50 1,438,202.70

7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,593,344.50 1,797,803.70
400 mm
A Tenaga 575,885.00 645,425.00
L.01 4.346 OH Pekerja 75,000.00 85,000.00 325,950.00 369,410.00
L.02 2.173 OH Tukang Pipa 95,000.00 105,000.00 206,435.00 228,165.00
L.04 0.435 OH Mandor 100,000.00 110,000.00 43,500.00 47,850.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,448,495.00 1,634,367.00
E Overhead & Profit (contoh 10%) 10% 144,849.50 163,436.70
F Harga Satuan Pekerjaan (D+E) 1,593,344.50 1,797,803.70

8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,757,684.50 1,983,104.20
450 mm
A Tenaga 635,510.00 712,250.00
L.01 4.796 OH Pekerja 75,000.00 85,000.00 359,700.00 407,660.00
L.02 2.398 OH Tukang Pipa 95,000.00 105,000.00 227,810.00 251,790.00
L.04 0.480 OH Mandor 100,000.00 110,000.00 48,000.00 52,800.00

B Bahan 290,000.00 300,000.00


1 bh Pipa Ø 450 mm 290,000.00 300,000.00 290,000.00 300,000.00

C PERALATAN 672,385.00 790,572.00


1.420 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 35,500.00 42,600.00
1.629 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 244,350.00 276,930.00
3.003 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 375,375.00 450,450.00
1.716 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 17,160.00 20,592.00

D Jumlah A + B + C 1,597,895.00 1,802,822.00


E Overhead & Profit (contoh 10%) 10% 159,789.50 180,282.20
F Harga Satuan Pekerjaan (D+E) 1,757,684.50 1,983,104.20

9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,933,024.50 2,179,404.70
500 mm
A Tenaga 695,135.00 779,075.00
L.01 5.246 OH Pekerja 75,000.00 85,000.00 393,450.00 445,910.00
L.02 2.623 OH Tukang Pipa 95,000.00 105,000.00 249,185.00 275,415.00
L.04 0.525 OH Mandor 100,000.00 110,000.00 52,500.00 57,750.00

B Bahan 320,000.00 330,000.00


1 bh Pipa Ø 500 mm 320,000.00 330,000.00 320,000.00 330,000.00

C PERALATAN 742,160.00 872,202.00


1.530 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 38,250.00 45,900.00
1.839 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 275,850.00 312,630.00
3.278 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 409,750.00 491,700.00
1.831 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 18,310.00 21,972.00

D Jumlah A + B + C 1,757,295.00 1,981,277.00


E Overhead & Profit (contoh 10%) 10% 175,729.50 198,127.70
F Harga Satuan Pekerjaan (D+E) 1,933,024.50 2,179,404.70

10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,250,704.50 2,539,005.70
600 mm
A Tenaga 814,385.00 912,725.00
L.01 6.146 OH Pekerja 75,000.00 85,000.00 460,950.00 522,410.00
L.02 3.073 OH Tukang Pipa 95,000.00 105,000.00 291,935.00 322,665.00
L.04 0.615 OH Mandor 100,000.00 110,000.00 61,500.00 67,650.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
D Jumlah A + B + C 2,046,095.00 2,308,187.00
E Overhead & Profit (contoh 10%) 10% 204,609.50 230,818.70
F Harga Satuan Pekerjaan (D+E) 2,250,704.50 2,539,005.70
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,601,384.50 2,931,606.70
700 mm
A Tenaga 933,635.00 1,046,375.00
L.01 7.046 OH Pekerja 75,000.00 85,000.00 528,450.00 598,910.00
L.02 3.523 OH Tukang Pipa 95,000.00 105,000.00 334,685.00 369,915.00
L.04 0.705 OH Mandor 100,000.00 110,000.00 70,500.00 77,550.00
B Bahan 410,000.00 420,000.00
1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00

D Jumlah A + B + C 2,364,895.00 2,665,097.00


E Overhead & Profit (contoh 10%) 10% 236,489.50 266,509.70
F Harga Satuan Pekerjaan (D+E) 2,601,384.50 2,931,606.70

12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,908,064.50 3,291,207.70
800 mm
A Tenaga 1,052,885.00 1,180,025.00
L.01 7.946 OH Pekerja 75,000.00 85,000.00 595,950.00 675,410.00
L.02 3.973 OH Tukang Pipa 95,000.00 105,000.00 377,435.00 417,165.00
L.04 0.795 OH Mandor 100,000.00 110,000.00 79,500.00 87,450.00

B Bahan 430,000.00 450,000.00


1 bh Pipa Ø 800 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 1,160,810.00 1,361,982.00


2.190 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 54,750.00 65,700.00
3.099 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 464,850.00 526,830.00
4.928 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 616,000.00 739,200.00
2.521 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 25,210.00 30,252.00

D Jumlah A + B + C 2,643,695.00 2,992,007.00


E Overhead & Profit (contoh 10%) 10% 264,369.50 299,200.70
F Harga Satuan Pekerjaan (D+E) 2,908,064.50 3,291,207.70
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XX A.8.4.5
PENGETESAN
1 A.8.4.5.1 1 m' Pengetesan Pipa Ø 50 mm 1,292.83 1,419.44
A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 495.30 522.40


0.002 m³ Air Bersih 150.00 200.00 0.30 0.40
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,175.30 1,290.40
E Overhead & Profit (contoh 10%) 10% 117.53 129.04
F Harga Satuan Pekerjaan (D+E) 1,292.83 1,419.44

2 A.8.4.5.2 1 m' Pengetesan Pipa Ø 75 mm 1,293.16 1,419.88


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 495.60 522.80


0.004 m³ Air Bersih 150.00 200.00 0.60 0.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,175.60 1,290.80
E Overhead & Profit (contoh 10%) 10% 117.56 129.08
F Harga Satuan Pekerjaan (D+E) 1,293.16 1,419.88

3 A.8.4.5.3 1 m' Pengetesan Pipa Ø 100 mm 1,293.82 1,420.76


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 496.20 523.60


0.008 m³ Air Bersih 150.00 200.00 1.20 1.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,176.20 1,291.60
E Overhead & Profit (contoh 10%) 10% 117.62 129.16
F Harga Satuan Pekerjaan (D+E) 1,293.82 1,420.76

4 A.8.4.5.4 1 m' Pengetesan Pipa Ø 150 mm 1,295.47 1,422.96


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 497.70 525.60


0.0180 m³ Air Bersih 150.00 200.00 2.70 3.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,177.70 1,293.60
E Overhead & Profit (contoh 10%) 10% 117.77 129.36
F Harga Satuan Pekerjaan (D+E) 1,295.47 1,422.96
5 A.8.4.5.5 1 m' Pengetesan Pipa Ø 200 mm 1,297.62 1,425.82
A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 499.65 528.20
0.031 m³ Air Bersih 150.00 200.00 4.65 6.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,179.65 1,296.20
E Overhead & Profit (contoh 10%) 10% 117.97 129.62
F Harga Satuan Pekerjaan (D+E) 1,297.62 1,425.82

6 A.8.4.5.6 1 m' Pengetesan Pipa Ø 250 mm 1,300.59 1,429.78


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 502.35 531.80
0.049 m³ Air Bersih 150.00 200.00 7.35 9.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,182.35 1,299.80
E Overhead & Profit (contoh 10%) 10% 118.24 129.98
F Harga Satuan Pekerjaan (D+E) 1,300.59 1,429.78

7 A.8.4.5.7 1 m' Pengetesan Pipa Ø 300 mm 1,304.22 1,434.62


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 505.65 536.20
0.071 m³ Air Bersih 150.00 200.00 10.65 14.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,185.65 1,304.20
E Overhead & Profit (contoh 10%) 10% 118.57 130.42
F Harga Satuan Pekerjaan (D+E) 1,304.22 1,434.62

8 A.8.4.5.8 1 m' Pengetesan Pipa Ø 400 mm 1,313.29 1,446.72


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 513.90 547.20
0.126 m³ Air Bersih 150.00 200.00 18.90 25.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,193.90 1,315.20
E Overhead & Profit (contoh 10%) 10% 119.39 131.52
F Harga Satuan Pekerjaan (D+E) 1,313.29 1,446.72

9 A.8.4.5.9 1 m' Pengetesan Pipa Ø 500 mm 1,318.57 1,453.76


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 518.70 553.60
0.158 m³ Air Bersih 150.00 200.00 23.70 31.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,198.70 1,321.60
E Overhead & Profit (contoh 10%) 10% 119.87 132.16
F Harga Satuan Pekerjaan (D+E) 1,318.57 1,453.76

10 A.8.4.5.10 1 m' Pengetesan Pipa Ø 600 mm 1,339.20 1,481.26


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 537.45 578.60
0.283 m³ Air Bersih 150.00 200.00 42.45 56.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,217.45 1,346.60


E Overhead & Profit (contoh 10%) 10% 121.75 134.66
F Harga Satuan Pekerjaan (D+E) 1,339.20 1,481.26

Anda mungkin juga menyukai