HARGA
NO. URAIAN PEKERJA SATUAN UPAH KET.
(Rp)
1 Pekerja Hr 70,000
2 Mandor Hr 100,000
10 T u k a n g c a t Hr 95,000
11 K e p . t k . c a t Hr 110,000
12 T u k a n g g a l i Hr 75,000
14 T k . l e i d e n g Hr 95,000
15 M a s i n i s Hr 150,000
16 P e m b . M a s i n i s Hr 100,000
17 P e n j a g a a p i Hr 75,000
18 P e n j a g a m a l a m Hr 75,000
19 Sopir Hr 140,000
HARGA
NO. J E N I S B A H A N SAT BAHAN KET
(Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000
Bulat Belah m3 260,000
Pecah 10/15 m3 250,000
Pecah 5/7 m3 300,000
Pecah 3/5 m3 330,000
2 KERIKIL Timbun m3 180,000
Sawur / Koral m3 160,000
Beton 0,5/1 m3 300,000
Beton 1/2 m3 300,000
Beton 2/3 m3 300,000
Biasa m3 240,000
Tras Giling m3 290,000
3 BATU BATA ex lokal bh 600
5 Keramik 30 X 30 cm m2 37,000
20 X 20 cm m2 46,500
33 x 33 cm m2 52,000
25 x 25 cm m2 49,000
15 x 20 cm m2 52,000
2,250
6 Parquet Jati m2 210,000
7 Batu Paros m2 110,000
8 Batu Tempel Hitam m2 105,000
9 GRANITO 40 x 40 cm m2 220,000
30 x 30 cm m2 300,000
10 Marmer m2 475,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 29,000
Ø 20 cm - 100 cm bh 35,000
Ø 30 cm - 100 cm bh 55,000
Ø 50 cm - 100 cm bh 70,000
Ø 60 cm - 100 cm bh 80,000
Ø 70 cm - 100 cm bh 100,000
U 10 cm - 100 cm bh 22,000
U 15 cm - 100 cm bh 35,000
U 20 cm - 100 cm bh 36,000
U 30 cm - 100 cm bh 40,000
U 50 cm - 100 cm bh 65,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 7,500
20 X 20 cm bh 8,000
25 X 25 cm bh 11,000
30 X 30 cm bh 15,000
15 X 25 cm bh 8,500
15 X 30 cm bh 8,500
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 9,500
besi beton prestress kg 13,000
besi beton ulir kg 12,500
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 56,000 panjang 4 m
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800
30 X 60 lbr 13,200
60 X 120 lbr 42,000
List Kayu Profil m' 4,800
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000
GYPROC uk.120cmx240cmx9mm lbr 60,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 55,000
. 120 X 240 X 3 mm lbr 75,000
. 90 X 210 X 4 mm lbr 65,000
. 90 X 210 X 9 mm lbr 95,000
. 90 X 210 X 12 mm lbr 135,000
. 90 X 210 X 15 mm lbr 165,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 23,000
Dempul plamur kg 16,000
Ambril/amplas lbr 3,000
Batu Apung kg 35,000
Cat dasar kg 35,000
. Emco kg 55,000
. Yunior 66 (nippon paint) kg 55,000
- Koas bh 7,500
. Deculux kg 55,000
. Siralax ons 15,000
. Spiritus ltr 10,000
. Plitur jadi ltr 61,000
2 TEMBOK
Kalkarium kg 4,200
Kapur sirih kg 4,250
Plamur kg 16,000
Cat Tembok kg 23,000
Sintex 5 kg 115,000
Danabride 5 kg 110,000
Catylac 5 kg 125,000
Mowilex 2,50 kg 310,000
3 BESI
Menie kg 20,000
X.BAHAN KACA
1 POLOS 3 mm m2 70,000
5 mm m2 90,000
2 ES KABUR 3 mm m2 75,000
5 mm m2 88,000
3 RAY BAND 3 mm m2 75,000
5 mm m2 85,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 4,200
2 SKAKELAR
Out bauw . Seri bh 15,000
. Engkel bh 13,000
. Engkel bh 11,000
2 group bh 220,000
3 group bh 325,000
Arde bh 15,000
T Biasa bh 12,500
Gantung bh 12,500
Kap bh 12,500
Kombinasi bh 25,000
Arde IB bh 21,000
XV . POMPA AIR.
1 POMPA AIR TANGAN
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 75,000
Merah/hitam m2 85,000
2 HOLLAND Abu-abu m2 75,000
Merah/hitam m2 85,000
3 UNIDECOR Abu-abu m2 75,000
Merah/hitam m2 85,000
4 UNI Abu-abu m2 75,000
Merah/hitam m2 85,000
5 TRIHEX Abu-abu m2 75,000
Merah/hitam m2 85,000
6 OLYMPIA HEXA Abu-abu m2 75,000
7 HEXAGONAL Abu-abu m2 85,000
Merah/hitam m2 75,000
8 CASTLE Abu-abu m2 85,000
9 TRAPEZ Abu-abu m2 75,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 75,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500
12 BATACO BH 5,000
13 KANSTEEN m' 15,000
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000
2 Sliding Pintu J4 bh 180,000
3 Naco per Daun bh 32,500
4 Rolling door Besi m2 300,000
Rolling door Almunium m2 230,000
5 Awning Almunium m2 210,000
6 Kusen Almunium 4" Putih m' 80,000
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000
0.070
0.050
4
1,000,000 0.0140 71
1
1.05 3 3.15
###
###
###
50
0.02
0.1
0.2
###
0.72
###
Tenaga
1.000 m3 galian Tanah
36.000 oh Tukang
6.000 oh Kepala Tukang
3.000 oh Mandor
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
Tenaga
1 m' Galian Tanah
1 m' Urugan Pasir
1 m' Urugan Tanah Kembali
1 m' Ongkos Pemasangan
1 m' Pengetesan Pipa
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF! 48000
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF! 51000
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Urugan Tanah Kembali #REF! #REF! #REF! #REF!
Ongkos Pemasangan #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
40000
50000
50000
180000
55488
46240
57800
57800
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 135,038.20
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 79,706.00
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 101,134.00
22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 51,375.50
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,430,429.27
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 135,038.20
A Tenaga 18,100.00
L.01 0.1 OH Pekerja 70,000.00 7,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 100,000.00 500.00
B Bahan 104,662.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 5,051,000.00 60,612.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 300.00
0.007 m3 Kayu Papan 3/20 Kruing 6,250,000.00 43,750.00
C PERALATAN
D Jumlah A + B + C 122,762.00
E Overhead & Profit (contah 10%) 10% 12,276.20
F Harga Satuan Pekerjaan (D+E) 135,038.20
file:///conversion/tmp/scratch/469226324.xls 1-20-61
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 153,560.00
A Tenaga 70,500.00
B. Bahan 69,100.00
0.150 m3 Batu Belah 260,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 139,600.00
E Overhead & Profit (contah 10%) 10% 13,960.00
F Harga Satuan Pekerjaan (D+E) 153,560.00
file:///conversion/tmp/scratch/469226324.xls 1-20-62
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
0.525 Btg Kolom Beton Pracetak 145,000.00 76,125.00
45.000 Kg Semen (SM) 1,050.00 47,250.00
0.146 m3 Koral 250,000.00 36,500.00
C PERALATAN
D Jumlah A + B + C 265,310.00
E Overhead & Profit (contah 10%) 10% 26,531.00
F Harga Satuan Pekerjaan (D+E) 291,841.00
file:///conversion/tmp/scratch/469226324.xls 1-20-63
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
0.03
33.3
file:///conversion/tmp/scratch/469226324.xls 1-20-64
0.06
### ###
#REF! #REF!
0.2
0.2
0.08
###
#REF!
0.05
0.5
2.4
0.06
64,781
file:///conversion/tmp/scratch/469226324.xls 1-20-65
1079683 1214978.50397
64780.98 72898.7102381
0.15
0.4
2.2
0.132
142518.156 160377.162524
140000 160000
file:///conversion/tmp/scratch/469226324.xls 1-20-66
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 79,706.00 88,390.50
A Tenaga 19,860.00 23,310.00
L.01 0.180 OH Pekerja 70,000.00 85,000.00 12,600.00 15,300.00
L.02 0.020 OH Tukang batu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Kayu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Besi 95,000.00 105,000.00 1,900.00 2,100.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 52,600.00 57,045.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 150.00 175.00
3.0 Kg Besi Beton Polos 9,500.00 10,500.00 28,500.00 31,500.00
0.45 Kg Kawat Beton 18,000.00 20,000.00 8,100.00 9,000.00
4.0 Kg Portland Semen 1,050.00 1,062.50 4,200.00 4,250.00
0.006 m3 Pasir Beton 350,000.00 380,000.00 2,100.00 2,280.00
0.009 m3 Kerikil 330,000.00 360,000.00 2,970.00 3,240.00
C PERALATAN
D Jumlah A + B + C 72,460.00 80,355.00
E Overhead & Profit (contoh 10%) 10% 7,246.00 8,035.50
F Harga Satuan Pekerjaan (D+E) 79,706.00 88,390.50
25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 101,134.00 112,424.13
A Tenaga 32,795.00 38,490.00
L.01 0.297 OH Pekerja 70,000.00 85,000.00 20,790.00 25,245.00
L.02 0.033 OH Tukang batu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Kayu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Besi 95,000.00 105,000.00 3,135.00 3,465.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 59,145.00 63,713.75
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
3.6 Kg Besi Beton Polos 9,500.00 10,500.00 34,200.00 37,800.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
5.5 Kg Portland Semen 1,050.00 1,062.50 5,775.00 5,843.75
0.009 m3 Pasir Beton 350,000.00 380,000.00 3,150.00 3,420.00
0.015 m3 Kerikil 330,000.00 360,000.00 4,950.00 5,400.00
C PERALATAN
D Jumlah A + B + C 91,940.00 102,203.75
E Overhead & Profit (contoh 10%) 10% 9,194.00 10,220.38
F Harga Satuan Pekerjaan (D+E) 101,134.00 112,424.13
11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 55,946.00 56,610.00
12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 57,530.00 58,235.00
1 1.0000 13 1.114
2 1.0000 14 1.134
3 1.0000 15 1.155
4 1.0000 16 1.176
5 1.0000 17 1.197
6 1.0000 18 1.219
7 1.0000 19 1.241
8 1.0180 20 1.264
9 1.0370 21 1.287
10 1.0550 22 1.310
11 1.0750 23 1.334
12 1.0940 24 1.358
2 1.0000 14 1.080
3 1.0000 15 1.092
4 1.0000 16 1.104
5 1.0000 17 1.116
6 1.0000 18 1.129
7 1.0000 19 1.141
8 1.0110 20 1.154
9 1.0220 21 1.166
10 1.0340 22 1.179
11 1.0450 23 1.192
12 1.0570 24 1.206
1 1.0000 13 1.162
2 1.0000 14 1.191
3 1.0000 15 1.221
4 1.0000 16 1.252
5 1.0000 17 1.284
6 1.0000 18 1.318
7 1.0000 19 1.350
8 1.0250 20 1.384
9 1.0510 21 1.419
10 1.0780 22 1.455
11 1.1050 23 1.492
12 1.1330 24 1.530
22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 51,375.50 56,633.50
A Tenaga 46,705.00 51,485.00
L.02 0.367 OH Tukang Batu 95,000.000 105,000.000 34,865.000 38,535.000
L.03 0.074 OH Kepala Tukang 110,000.000 120,000.000 8,140.000 8,880.000
L.04 0.037 OH Mandor 100,000.000 110,000.000 3,700.000 4,070.000
B Bahan - -
C PERALATAN - -
D Jumlah A + B + C 46,705.00 51,485.00
E Overhead & Profit (contoh 10%) 10% 4,670.50 5,148.50
F Harga Satuan Pekerjaan (D+E) 51,375.50 56,633.50
C PERALATAN - -
D Jumlah A + B + C 39,490.00 45,320.00
E Overhead & Profit (contoh 10%) 10% 3,949.00 4,532.00
F Harga Satuan Pekerjaan (D+E) 43,439.00 49,852.00
16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 387,613.60 447,612.00
A Tenaga 42,200.00 49,280.00
L.01 0.350 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 395,618.30 458,437.38
A Tenaga 42,200.00 49,280.00
L.01 0.350 OH Pekerja 70,000.00 85,000.00 24,500.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 305,257.70 351,836.38
A Tenaga 36,720.00 43,000.00
L.01 0.320 OH Pekerja 70,000.00 85,000.00 22,400.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 240,787.00 276,851.25
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,050.00 1,062.50 23,877.00 24,161.25
0.550 m3 Pasir Pasang 310,000.00 370,000.00 170,500.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 277,507.00 319,851.25
E Overhead & Profit (contoh 10%) 10% 27,750.70 31,985.13
F Harga Satuan Pekerjaan (D+E) 305,257.70 351,836.38
19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 310,926.00 359,554.25
A Tenaga 36,720.00 43,000.00
L.01 0.320 OH Pekerja 70,000.00 85,000.00 22,400.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 245,940.00 283,867.50
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,050.00 1,062.50 19,110.00 19,337.50
0.582 m3 Pasir Pasang 310,000.00 370,000.00 180,420.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 282,660.00 326,867.50
E Overhead & Profit (contoh 10%) 10% 28,266.00 32,686.75
F Harga Satuan Pekerjaan (D+E) 310,926.00 359,554.25
20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 249,719.80 287,460.25
A Tenaga 33,100.00 38,850.00
L.01 0.300 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 254,404.15 293,686.94
A Tenaga 33,100.00 38,850.00
L.01 0.300 OH Pekerja 70,000.00 85,000.00 21,000.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
C PERALATAN
D Jumlah A + B + C 238,771.40 265,065.05
E Overhead & Profit (contoh 10%) 10% 23,877.14 26,506.51
F Harga Satuan Pekerjaan (D+E) 262,648.54 291,571.56
C PERALATAN
D Jumlah A + B + C 241,613.40 266,101.55
E Overhead & Profit (contoh 10%) 10% 24,161.34 26,610.16
F Harga Satuan Pekerjaan (D+E) 265,774.74 292,711.71
22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 91,525.50 103,719.00
26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 257,166.25 281,857.81
A Tenaga 89,600.00 104,300.00
L.01 0.70 OH Pekerja 70,000.00 85,000.00 49,000.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 144,187.50 151,934.38
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,050.00 1,062.50 12,337.50 12,484.38
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 233,787.50 256,234.38
E Overhead & Profit (contoh 10%) 10% 23,378.75 25,623.44
F Harga Satuan Pekerjaan (D+E) 257,166.25 281,857.81
C PERALATAN
D Jumlah A + B + C 130,539.00 143,790.00
E Overhead & Profit (contoh 10%) 10% 13,053.90 14,379.00
F Harga Satuan Pekerjaan (D+E) 143,592.90 158,169.00
29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 45,342.00 57,310.00
Tenaga 21,720.00 24,900.00
L.01 0.12 OH Pekerja 70,000.00 85,000.00 8,400.00 10,200.00
L.02 0.12 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
Bahan 19,500.00 27,200.00
0.003 m3 Papan Kayu Klas II 6,250,000.00 8,800,000.00 18,750.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 41,220.00 52,100.00
E Overhead & Profit (contoh 10%) 10% 4,122.00 5,210.00
F Harga Satuan Pekerjaan (D+E) 45,342.00 57,310.00
C PERALATAN
D Jumlah A + B + C 57,450.00 65,855.00
E Overhead & Profit (contoh 10%) 10% 5,745.00 6,585.50
F Harga Satuan Pekerjaan (D+E) 63,195.00 72,440.50
C PERALATAN
D Jumlah A + B + C 47,900.00 54,460.00
E Overhead & Profit (contoh 10%) 10% 4,790.00 5,446.00
F Harga Satuan Pekerjaan (D+E) 52,690.00 59,906.00
8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 9,418.75 11,231.00
A Tenaga 7,600.00 9,160.00
L.01 0.1 OH Pekerja 70,000.00 85,000.00 7,000.00 8,500.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 8,562.50 10,210.00
E Overhead & Profit (contoh 10%) 10% 856.25 1,021.00
F Harga Satuan Pekerjaan (D+E) 9,418.75 11,231.00
C PERALATAN
D Jumlah A + B + C 75,850.00 86,375.00
E Overhead & Profit (contoh 10%) 10% 7,585.00 8,637.50
F Harga Satuan Pekerjaan (D+E) 83,435.00 95,012.50
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,430,429.27 1,626,988.54
A Tenaga 741,000.00 864,300.00
L.01 6.00 OH Pekerja 70,000.00 85,000.00 420,000.00 510,000.00
L.02 3.00 OH Tukang Batu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 559,390.24 614,780.49
150.0 bh Batu Bata 600.00 650.00 90,000.00 97,500.00
120 Kg Portland Semen 0.11 1,050.00 1,062.50 126,000.00 127,500.00
0.3 m3 Pasir Pasang 0.0121 310,000.00 370,000.00 93,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,300,390.24 1,479,080.49
E Overhead & Profit (contoh 10%) 10% 130,039.02 147,908.05
F Harga Satuan Pekerjaan (D+E) 1,430,429.27 1,626,988.54
9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 341,440.00 384,230.00
A Tenaga 35,400.00 39,300.00
L.01 0.030 OH Pekerja 70,000.00 85,000.00 2,100.00 2,550.00
L.02 0.300 OH Tukang Batu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 310,400.00 349,300.00
E Overhead & Profit (contoh 10%) 10% 31,040.00 34,930.00
F Harga Satuan Pekerjaan (D+E) 341,440.00 384,230.00
C PERALATAN
D Jumlah A + B + C 36,800.00 48,100.00
E Overhead & Profit (contoh 10%) 10% 3,680.00 4,810.00
F Harga Satuan Pekerjaan (D+E) 40,480.00 52,910.00
28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 76,527.00 84,378.25
cm
A Tenaga 10,240.00 11,920.00
L.01 0.080 OH Pekerja 70,000.00 85,000.00 5,600.00 6,800.00
L.02 0.040 OH Tukang Batu 95,000.00 105,000.00 3,800.00 4,200.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 59,330.00 64,787.50
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,050.00 1,062.50 36,750.00 37,187.50
0.014 m3 Pasir Pasang 310,000.00 370,000.00 4,340.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 230,000.00 2,240.00 3,220.00
- -
C PERALATAN
D Jumlah A + B + C 307,600.00 344,280.00
E Overhead & Profit (contoh 10%) 10% 30,760.00 34,428.00
F Harga Satuan Pekerjaan (D+E) 338,360.00 378,708.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 459,140.00 503,448.00
A Tenaga 208,700.00 228,840.00
L.01 100 % Pekerja 208,700.00 228,840.00 208,700.00 228,840.00
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
D Jumlah A + B + C 58,890.00 68,625.00
E Overhead & Profit (contoh 10%) 10% 5,889.00 6,862.50
F Harga Satuan Pekerjaan (D+E) 64,779.00 75,487.50
34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 77,183.33 92,840.00
A Tenaga 51,000.00 59,400.00
L.01 0.400 OH Pekerja 70,000.00 85,000.00 28,000.00 34,000.00
L.02 0.200 OH Tukang Pipa 95,000.00 105,000.00 19,000.00 21,000.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
D Jumlah A + B + C 79,640.00 96,550.00
E Overhead & Profit (contoh 10%) 10% 7,964.00 9,655.00
F Harga Satuan Pekerjaan (D+E) 87,604.00 106,205.00
C PERALATAN
D Jumlah A + B + C 92,888.33 111,851.67
E Overhead & Profit (contoh 10%) 10% 9,288.83 11,185.17
F Harga Satuan Pekerjaan (D+E) 102,177.17 123,036.83
C PERALATAN
D Jumlah A + B + C 139,030.00 166,583.33
E Overhead & Profit (contoh 10%) 10% 13,903.00 16,658.33
F Harga Satuan Pekerjaan (D+E) 152,933.00 183,241.67
C PERALATAN
D Jumlah A + B + C 166,055.00 199,323.33
E Overhead & Profit (contoh 10%) 10% 16,605.50 19,932.33
F Harga Satuan Pekerjaan (D+E) 182,660.50 219,255.67
C PERALATAN
D Jumlah A + B + C 192,165.00 223,951.67
E Overhead & Profit (contoh 10%) 10% 19,216.50 22,395.17
F Harga Satuan Pekerjaan (D+E) 211,381.50 246,346.83
C PERALATAN
D Jumlah A + B + C 247,843.33 276,626.67
E Overhead & Profit (contoh 10%) 10% 24,784.33 27,662.67
F Harga Satuan Pekerjaan (D+E) 272,627.67 304,289.33
C PERALATAN
D Jumlah A + B + C 282,430.00 320,835.00
E Overhead & Profit (contoh 10%) 10% 28,243.00 32,083.50
F Harga Satuan Pekerjaan (D+E) 310,673.00 352,918.50
C PERALATAN
D Jumlah A + B + C 327,355.00 368,210.00
E Overhead & Profit (contoh 10%) 10% 32,735.50 36,821.00
F Harga Satuan Pekerjaan (D+E) 360,090.50 405,031.00
43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 362,197.00 403,859.50
A Tenaga 169,270.00 197,145.00
L.01 1.327 OH Pekerja 70,000.00 85,000.00 92,890.00 112,795.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00
C PERALATAN
D Jumlah A + B + C 329,270.00 367,145.00
E Overhead & Profit (contoh 10%) 10% 32,927.00 36,714.50
F Harga Satuan Pekerjaan (D+E) 362,197.00 403,859.50
C PERALATAN
D Jumlah A + B + C 496,675.00 555,540.00
E Overhead & Profit (contoh 10%) 10% 49,667.50 55,554.00
F Harga Satuan Pekerjaan (D+E) 546,342.50 611,094.00
C PERALATAN
D Jumlah A + B + C 564,450.00 639,535.00
E Overhead & Profit (contoh 10%) 10% 56,445.00 63,953.50
F Harga Satuan Pekerjaan (D+E) 620,895.00 703,488.50
B Bahan - -
- m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 - -
B Bahan - -
- m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 - -
B Bahan - -
- m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 - -
B Bahan - -
- m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
C PERALATAN 4,000.00 4,800.00
0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00
D Jumlah A + B + C 142,905.00 166,580.00
E Overhead & Profit (contoh 10%) 10% 14,290.50 16,658.00
F Harga Satuan Pekerjaan (D+E) 157,195.50 183,238.00
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 164,686.50 191,972.00
A Tenaga 145,515.00 169,480.00
L.01 1.141 OH Pekerja 70,000.00 85,000.00 79,870.00 96,985.00
L.02 0.571 OH Tukang Pipa 95,000.00 105,000.00 54,245.00 59,955.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00
B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 - -
C PERALATAN - -
B Bahan - -
- m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 16,740.00 19,495.00
E Overhead & Profit (contoh 10%) 10% 1,674.00 1,949.50
F Harga Satuan Pekerjaan (D+E) 18,414.00 21,444.50
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 47,685.00 55,539.00
A Tenaga 43,350.00 50,490.00
L.01 0.340 OH Pekerja 70,000.00 85,000.00 23,800.00 28,900.00
L.02 0.170 OH Tukang Pipa 95,000.00 105,000.00 16,150.00 17,850.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan - -
- m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 199,775.00 232,680.00
E Overhead & Profit (contoh 10%) 10% 19,977.50 23,268.00
F Harga Satuan Pekerjaan (D+E) 219,752.50 255,948.00
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 248,242.50 289,129.50
A Tenaga 225,675.00 262,845.00
L.01 1.770 OH Pekerja 70,000.00 85,000.00 123,900.00 150,450.00
L.02 0.885 OH Tukang Pipa 95,000.00 105,000.00 84,075.00 92,925.00
L.04 0.177 OH Mandor 100,000.00 110,000.00 17,700.00 19,470.00
B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 303,685.00 353,705.00
E Overhead & Profit (contoh 10%) 10% 30,368.50 35,370.50
F Harga Satuan Pekerjaan (D+E) 334,053.50 389,075.50
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 7,733.00 9,142.10
A Tenaga 7,000.00 8,275.00
L.01 0.071 OH Pekerja 70,000.00 85,000.00 4,970.00 6,035.00
L.02 0.014 OH Tukang Pipa 95,000.00 105,000.00 1,330.00 1,470.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -
B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -
B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -
B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -
B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -
B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -
B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -
B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -
B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -
B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -
B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -
B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -
B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -
1 A.8.4.4.1 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 432,305.50 516,180.50
80 mm
A Tenaga 186,955.00 217,745.00
L.01 1.466 OH Pekerja 70,000.00 85,000.00 102,620.00 124,610.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00
2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 519,304.50 598,000.70
100 mm
A Tenaga 218,135.00 244,475.00
L.01 1.646 OH Pekerja 75,000.00 85,000.00 123,450.00 139,910.00
L.02 0.823 OH Tukang Pipa 95,000.00 105,000.00 78,185.00 86,415.00
L.04 0.165 OH Mandor 100,000.00 110,000.00 16,500.00 18,150.00
3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 749,644.50 849,301.20
150 mm
A Tenaga 277,760.00 311,300.00
L.01 2.096 OH Pekerja 75,000.00 85,000.00 157,200.00 178,160.00
L.02 1.048 OH Tukang Pipa 95,000.00 105,000.00 99,560.00 110,040.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 681,495.00 772,092.00
E Overhead & Profit (contoh 10%) 10% 68,149.50 77,209.20
F Harga Satuan Pekerjaan (D+E) 749,644.50 849,301.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 946,984.50 1,078,601.70
200 mm
A Tenaga 337,385.00 378,125.00
L.01 2.546 OH Pekerja 75,000.00 85,000.00 190,950.00 216,410.00
L.02 1.273 OH Tukang Pipa 95,000.00 105,000.00 120,935.00 133,665.00
L.04 0.255 OH Mandor 100,000.00 110,000.00 25,500.00 28,050.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 860,895.00 980,547.00
E Overhead & Profit (contoh 10%) 10% 86,089.50 98,054.70
F Harga Satuan Pekerjaan (D+E) 946,984.50 1,078,601.70
5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,116,824.50 1,263,902.20
250 mm
A Tenaga 397,010.00 444,950.00
L.01 2.996 OH Pekerja 75,000.00 85,000.00 224,700.00 254,660.00
L.02 1.498 OH Tukang Pipa 95,000.00 105,000.00 142,310.00 157,290.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
B Bahan 225,000.00 240,000.00
1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00
C PERALATAN 393,285.00 464,052.00
0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00
D Jumlah A + B + C 1,015,295.00 1,149,002.00
E Overhead & Profit (contoh 10%) 10% 101,529.50 114,900.20
F Harga Satuan Pekerjaan (D+E) 1,116,824.50 1,263,902.20
6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,275,664.50 1,438,202.70
300 mm
A Tenaga 456,635.00 511,775.00
L.01 3.446 OH Pekerja 75,000.00 85,000.00 258,450.00 292,910.00
L.02 1.723 OH Tukang Pipa 95,000.00 105,000.00 163,685.00 180,915.00
L.04 0.345 OH Mandor 100,000.00 110,000.00 34,500.00 37,950.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,159,695.00 1,307,457.00
E Overhead & Profit (contoh 10%) 10% 115,969.50 130,745.70
F Harga Satuan Pekerjaan (D+E) 1,275,664.50 1,438,202.70
7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,593,344.50 1,797,803.70
400 mm
A Tenaga 575,885.00 645,425.00
L.01 4.346 OH Pekerja 75,000.00 85,000.00 325,950.00 369,410.00
L.02 2.173 OH Tukang Pipa 95,000.00 105,000.00 206,435.00 228,165.00
L.04 0.435 OH Mandor 100,000.00 110,000.00 43,500.00 47,850.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,448,495.00 1,634,367.00
E Overhead & Profit (contoh 10%) 10% 144,849.50 163,436.70
F Harga Satuan Pekerjaan (D+E) 1,593,344.50 1,797,803.70
8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,757,684.50 1,983,104.20
450 mm
A Tenaga 635,510.00 712,250.00
L.01 4.796 OH Pekerja 75,000.00 85,000.00 359,700.00 407,660.00
L.02 2.398 OH Tukang Pipa 95,000.00 105,000.00 227,810.00 251,790.00
L.04 0.480 OH Mandor 100,000.00 110,000.00 48,000.00 52,800.00
9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,933,024.50 2,179,404.70
500 mm
A Tenaga 695,135.00 779,075.00
L.01 5.246 OH Pekerja 75,000.00 85,000.00 393,450.00 445,910.00
L.02 2.623 OH Tukang Pipa 95,000.00 105,000.00 249,185.00 275,415.00
L.04 0.525 OH Mandor 100,000.00 110,000.00 52,500.00 57,750.00
10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,250,704.50 2,539,005.70
600 mm
A Tenaga 814,385.00 912,725.00
L.01 6.146 OH Pekerja 75,000.00 85,000.00 460,950.00 522,410.00
L.02 3.073 OH Tukang Pipa 95,000.00 105,000.00 291,935.00 322,665.00
L.04 0.615 OH Mandor 100,000.00 110,000.00 61,500.00 67,650.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
D Jumlah A + B + C 2,046,095.00 2,308,187.00
E Overhead & Profit (contoh 10%) 10% 204,609.50 230,818.70
F Harga Satuan Pekerjaan (D+E) 2,250,704.50 2,539,005.70
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,601,384.50 2,931,606.70
700 mm
A Tenaga 933,635.00 1,046,375.00
L.01 7.046 OH Pekerja 75,000.00 85,000.00 528,450.00 598,910.00
L.02 3.523 OH Tukang Pipa 95,000.00 105,000.00 334,685.00 369,915.00
L.04 0.705 OH Mandor 100,000.00 110,000.00 70,500.00 77,550.00
B Bahan 410,000.00 420,000.00
1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00
12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,908,064.50 3,291,207.70
800 mm
A Tenaga 1,052,885.00 1,180,025.00
L.01 7.946 OH Pekerja 75,000.00 85,000.00 595,950.00 675,410.00
L.02 3.973 OH Tukang Pipa 95,000.00 105,000.00 377,435.00 417,165.00
L.04 0.795 OH Mandor 100,000.00 110,000.00 79,500.00 87,450.00