JADWAL PELAKSANAAN PEKERJAAN

Kegiatan : Peningkatan Jalan


Pekerjaan : Peningkatan Jalan Bandungrejo - Setren

MASA PELAKSANAAN 180 HARI KALENDER


BOBOT BULAN BULAN BULAN BULAN BULAN BULAN
NO URAIAN I II III IV V VI SKALA KET.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 20 21 22 23
%

1.2.4 Mobilisasi Dan Demobilisasi 0.23% 0.11% 0.11%


1.8.(1) Manajemen dan Keselamatan Lalu Lintas 0.40% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 100
1.19 Keselamatan dan Kesehatan Kerja 0.30% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

MASA
1.21 Manajemen Mutu 0.26% 0.06% 0.06% 0.06% 0.06%

3.1.(1) Galian Biasa 0.11% 0.11%

PEMELIHARAAN
3.2.(1b) Timbunan Biasa dari hasil galian 0.06% 0.06%
3.2.(2a) Timbunan Pilihan dari sumber galian 0.11% 0.11%
3.3.(1) Penyiapan Badan Jalan 0.750% 0.750%

5.1.(1) Lapis Pondasi Agregat Kelas A 7.85% 1.57% 1.57% 2.36% 2.36%
5.1.(3) Lapis Pondasi Agregat Kelas S 0.83% 0.21% 0.21% 0.21% 0.21%
5.3.(3) Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 12.44% 3.11% 3.11% 3.11% 3.11%

180
6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi 0.01% 0.00% 0.00%
6.3(5a) Laston Lapis Aus (AC-WC) 0.09% 0.04% 0.04%

HARI
7.1 (7).a Beton strukur, fc’20 MPa 3.36% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42%
7.1 (5).b Beton struktur, fc’30 MPa 38.14% 4.24% 4.24% 4.24% 4.24% 4.24% 4.24% 4.24% 4.24% 4.24%

KALENDER
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) 17.53% 2.92% 2.92% 2.92% 2.92% 2.92% 2.92%
7.3 (1) Baja Tulangan Polos-BjTP 280 11.28% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25%
7.3 (2) Baja Tulangan Sirip BjTS 280 1.82% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30%
7.6.(19b) Tiang Bor Beton, diameter 250 mm 4.43% 1.11% 1.11% 1.11% 1.11%

Jumlah Nilai Pekerjaan 100%


PRESTASI FISIK MINGGUAN % 0.14% 1.60% 2.71% 3.56% 9.97% 7.62% 4.51% 4.27% 4.27% 4.27% 4.33% 4.27% 0.14% 2.03% 2.39% 1.56% 8.04% 8.04% 4.99% 5.94% 4.89% 4.89% 4.94% 0.64%
RENCANA
PRESTASI FISIK MINGGUAN KOMULATIF % 0.14% 1.74% 4.45% 8.01% 17.98% 25.60% 30.11% 34.38% 38.64% 42.91% 47.24% 51.51% 51.64% 53.68% 56.07% 57.62% 65.66% 73.70% 78.69% 84.63% 89.53% 94.42% 99.36% 100.00%
PRESTASI FISIK MINGGUAN %
REALISASI
PRESTASI FISIK MINGGUAN KOMULATIF %
DEVIASI %
KETERANGAN :
RENCANA
REALISASI

Bojonegoro
DIBUAT OLEH
Kontraktor Pelaksana
PT. TEDUH KARYA UTAMA

Anwar Pramono, ST
dierektur 0