NIM : 171111058
Kelas : 3B-TKGE
soal
Biaya Proyek Rp 110,000,000,000
Pengembalian uang
Skedul Pembayaran Pembayaran Progres Retensi
muka
Uang Muka (15%) - - -
Termijn 1: 20% Rp 22,000,000,000 Rp 3,300,000,000 Rp 1,100,000,000
Termijn 2: 30% Rp 33,000,000,000 Rp 4,950,000,000 Rp 1,650,000,000
Termijn 3: 30% Rp 33,000,000,000 Rp 4,950,000,000 Rp 1,650,000,000
Termijn 4: 20% Rp 22,000,000,000 Rp 3,300,000,000 Rp 1,100,000,000
Jumlah ST Pertama Rp 110,000,000,000 Rp 16,500,000,000 Rp 5,500,000,000
Jumlah ST Kedua - - Rp 5,500,000,000
Pembayaran Bersih Pajak Total Pembayaran
Rp 16,500,000,000 - Rp 16,500,000,000
Rp 17,600,000,000 Rp 2,200,000,000 Rp 19,800,000,000
Rp 26,400,000,000 Rp 3,300,000,000 Rp 29,700,000,000
Rp 26,400,000,000 Rp 3,300,000,000 Rp 29,700,000,000
Rp 17,600,000,000 Rp 2,200,000,000 Rp 19,800,000,000
Rp 104,500,000,000 Rp 11,000,000,000 Rp 115,500,000,000
Rp 110,000,000,000 - Rp 121,000,000,000