I. PEKERJAAN STRUKTUR
A Pile Cap dan Lantai Basement
1 Cor lantai kerja m2 16,253.65 16,734.06 32,861.50 549,906,250 0.783% 16,734.06 100% 0.783%
2 Pasang & bongkar bekisting
- Pile Cap m2 2,667.71 1,837.87 82,557.08 151,729,177 0.216% 1,837.87 100% 0.216%
- Pelat Lantai m2 - 137.66 82,557.08 11,365,014 0.016% 137.66 100% 0.016%
- Kolom m2 2,184.71 2,850.78 80,395.75 229,190,186 0.326% 2,850.78 100% 0.326%
- Dinding m2 7,557.48 7,585.35 112,459.34 853,043,004 1.215% 7,585.35 100% 1.215%
- Balok STP m2 43.96 53.84 98,457.48 5,301,197 0.008% - 0% 0.000%
- Pelat STP m2 71.57 55.49 101,585.44 5,636,640 0.008% - 0% 0.000%
- Pelat GWT m2 - 95.52 101,585.44 9,703,741 0.014% - 0% 0.000%
- Tangga m2 125.25 184.19 111,271.13 20,494,869 0.029% - 0% 0.000%
- Ramp m2 542.03 1,013.99 98,457.48 99,834,719 0.142% 1,013.99 100% 0.142%
3 Pembesian kg 1,105,127.51 1,706,688.94 8,462.40 14,442,684,507 20.573% 1,699,418.22 100% 20.486%
4 Pengecoran m3 9,115.86 8,327.11 1,017,420.00 8,472,170,728 12.068% 8,263.10 99% 11.976%
5 Floor Hardener m2 16,254.00 16,090.60 34,841.67 560,623,469 0.799% 16,090.60 100% 0.799%
6 Waterproofing m3 8,561.82 8,561.82 105,000.00 898,991,100 1.281% 8,561.82 100% 1.281%
7 Man hole bh 3.00 3.00 1,500,000.00 4,500,000 0.006% - 0% 0.000%
8 Tangga service bh 3.00 3.00 2,000,000.00 6,000,000 0.009% - 0% 0.000%
9 Saluran m1 508.00 564.28 350,000.00 197,497,855 0.281% 564.28 100% 0.281%
10 Sumpit bh 11.00 3.00 3,500,000.00 10,500,000 0.015% 3.00 100% 0.015%
###
Sub Total Pile Cap dan Lantai Basement 26,529,172,455 37.790% 99% 37.536%
###
B Lantai Semi Basement ###
1 Pemasangan Bekisting ###
- Balok dan Pelat Lantai m2 20,772.23 21,893.84 98,457.48 2,155,612,708 3.071% 21,557.48 98% 3.023%
- Kolom m2 2,192.65 2,464.00 80,395.75 198,095,121 0.282% 2,205.95 90% 0.253%
- Dinding dan Tangga m2 975.75 1,961.14 112,459.34 220,548,116 0.314% 1,772.91 90% 0.284%
- Ramp m2 - 558.32 98,457.48 54,970,587 0.078% 558.32 100% 0.078%
2 Pembesian kg 412,076.70 549,475.57 8,462.40 4,649,882,045 6.624% 540,473.92 98% 6.515%
3 Pengecoran m3 3,727.15 4,224.54 1,017,420.00 4,298,129,244 6.123% 4,111.02 97% 5.958%
4 Floor Hardener m2 - 7,679.22 34,841.67 267,556,723 0.381% 7,679.22 100% 0.381%
###
Sub Total Lantai Semi Basement 11,844,794,544 16.873% 98% 16.493%
###
C Lantai 1 ###
1 Pemasangan Bekisting ###
- Balok m2 6,371.88 6,256.21 98,457.48 615,970,244 0.877% 4,859.78 78% 0.682%
- Pelat Lantai m2 8,789.68 9,204.73 101,585.44 935,066,430 1.332% 6,968.68 76% 1.008%
- Kolom m2 1,456.32 1,711.01 80,395.75 137,557,766 0.196% 1,711.01 100% 0.196%
- Dinding m2 829.38 884.08 112,459.34 99,423,211 0.142% 884.08 100% 0.142%
- Tangga m2 75.04 118.44 111,271.13 13,179,468 0.019% - 0% 0.000%
2 Pembesian kg 324,010.57 396,673.11 8,462.40 3,356,806,489 4.782% 339,541.24 86% 4.093%
3 Pengecoran m3 2,502.65 2,512.18 1,017,420.00 2,555,937,641 3.641% 2,007.28 80% 2.909%
4 Waterproofing m3 198.09 198.09 105,000.00 20,799,450 0.030% - 0% 0.000%
5 Floor Hardener m2 - 1,910.08 34,841.67 66,550,445 0.095% 1,910.08 100% 0.095%
###
Sub Total Lantai 1 7,801,291,143 11.113% 82% 9.124%
###
D Lantai 2 ###
1 Pemasangan Bekisting ###
- Balok m2 3,847.45 3,705.94 98,457.48 364,877,340 0.520% 3,514.77 95% 0.493%
- Pelat Lantai m2 5,201.63 5,496.06 101,585.44 558,319,842 0.795% 5,390.87 98% 0.780%
- Kolom m2 782.58 1,052.06 80,395.75 84,581,471 0.120% 954.72 91% 0.109%
- Dinding m2 829.38 881.17 112,459.34 99,095,768 0.141% 881.17 100% 0.141%
- Tangga m2 61.91 95.12 111,271.13 10,583,637 0.015% - 0% 0.000%
2 Pembesian kg 196,485.58 268,744.02 8,462.40 2,274,219,416 3.240% 267,250.77 99% 3.222%
3 Pengecoran m3 1,504.23 1,566.35 1,017,420.00 1,593,640,591 2.270% 1,263.50 81% 1.831%
4 Waterproofing m3 487.47 487.47 105,000.00 51,184,350 0.073% - 0% 0.000%
5 Pekerjaan Baja Atap Ballroom ###
- Kolom baja WF 300x150x6,5x9 kg 1,541.40 1,541.40 17,645.00 27,198,003 0.039% - 0% 0.000%
- Kap baja WF 200x100x5,5x8 kg 8,905.60 8,905.60 17,645.00 157,139,312 0.224% - 0% 0.000%
- Kap baja WF 150x75x5x7 kg 2,853.73 2,853.73 17,645.00 50,354,066 0.072% - 0% 0.000%
- Kap baja WF 200x100x5,5x8 kg 588.80 588.80 17,645.00 10,389,376 0.015% - 0% 0.000%
- Balok baja WF 150x75x5x7 kg 9,788.80 9,788.80 17,645.00 172,723,376 0.246% - 0% 0.000%
- Jurai baja WF 250x125x6x9 kg 2,389.61 2,389.61 17,645.00 42,164,668 0.060% - 0% 0.000%
- Gording baja CNP 200x75x20 t = 3,2 mm kg 21,875.35 21,875.35 17,645.00 385,990,551 0.550% - 0% 0.000%
- Trekstang dia 13 mm m1 306.40 306.40 17,045.00 5,222,588 0.007% - 0% 0.000%
###
Sub Total Lantai 2 5,887,684,357 8.387% 78% 6.576%
###
E Lantai 3 ###
1 Pemasangan Bekisting ###
- Balok m2 1,676.49 1,699.56 98,457.48 167,334,793 0.238% 1,690.32 99% 0.237%
- Pelat Lantai m2 2,245.15 2,482.76 101,585.44 252,212,475 0.359% 2,412.13 97% 0.349%
- Kolom m2 507.64 465.76 80,395.75 37,445,123 0.053% 465.76 100% 0.053%
- Dinding m2 768.93 622.83 112,459.34 70,042,758 0.100% 622.83 100% 0.100%
- Tangga m2 40.80 86.87 111,271.13 9,666,579 0.014% - 0% 0.000%
2 Pembesian kg 99,171.66 119,212.37 8,462.40 1,008,822,718 1.437% 116,205.58 97% 1.401%
3 Pengecoran m3 699.99 780.49 1,017,420.00 794,088,480 1.131% 756.99 97% 1.097%
4 Waterproofing m3 94.58 94.58 105,000.00 9,930,900 0.014% - 0% 0.000%
###
Sub Total Lantai 3 2,349,543,827 3.347% 97% 3.237%
RINCIAN PROGRESS PEKERJAAN STRUKTUR
PROYEK RADISSON HOTEL BATAM
Rp 178,296,693.91 5,090,653,466 - 0
Rp 266,703,380.30 1,162,724,179 - (0)
Rp 1,395,783,189.76 614,899,442 - -
Rp 1,271,051,636.53 611,479,844 - -
Rp 77,043,058.80 169,592,462 - 0
Rp 34,122,945.59 88,165,446 - (0)
Rp 46,446,948.68 88,165,446 - (0)
Rp 1,013,920,444.10 88,165,446 - -
Rp 1,540,901,437.48 37,988,108 - -
Rp 1,541,356,540.26 37,988,108 - -
Rp 1,866,656,037.05 212,588,359 - -
Rp 1,191,591,732.76 50,635,569 - -
Rp 1,191,237,190.41 50,635,569 - -
Rp 1,191,237,190.41 20,170,929 - -
Rp 1,247,612,796.57 76,423,046 - -
Rp 1,120,602,793.35 60,314,293 - -
Rp 15,174,564,015.94 -
Proyek : HOTEL SUKAJADI - BATAM
Paket : STRUKTUR
Tanggal : 20 JUNI 2013
Revisi : R0
UPAH KERJA
1 Mandor 1.00 Oh
2 Kepala Tukang (Batu, Kayu, Besi) 1.00 Oh
3 Tukang (Batu, Kayu, Besi) 1.00 Oh
4 Pekerja (Batu, Kayu, Besi) 1.00 Oh
5 Pekerja (Galian) 1.00 Oh
6 Operator alat berat 1.00 Oh
7 Supir 1.00 Oh
SEWA ALAT
95,000.00
80,000.00
70,000.00
60,000.00
SEWA
Rp.
657,142.86
31,500.00
46,000.00
5,000.00
25,000.00
17,857.14
Proyek : HOTEL SUKAJADI - BATAM
Paket : STRUKTUR
Tanggal : 20 JUNI 2013
Revisi : R0
HARGA BAHAN / MATERIAL 1 $ SIN =
H. BAHAN
Rp.
890,400.00
6,888.00
6,888.00
105,000.00
15,700.00
60,000.00
2,800,000.00
2,800,000.00
15,000.00
155,000.00
9,000.00
190,000.00
210,000.00
7,200.00
5,500.00
ANALISA HARGA SATUAN PEKERJAAN STRUKTUR R0 (20 Juni 2013) - ATELIER 6 STR
ANALISA NO. URAIAN BAHAN / MATERIAL VOLUME UNIT
Bahan
Floor Hardener warna Natural 5.00 Kg
Upah
Tukang Batu 0.01 Oh
Kepala Tukang 0.01 Oh
Pekerja 0.02 Oh
Mandor 0.01 Oh
Alat :
Throwel 0.23 Jam
17. Saluran
1.00 M
18. Sumpit
1.00 BH
R0 (20 Juni 2013) - ATELIER 6 STR
BAHAN / UPAH JUMLAH H. SATUAN LT. BASEMENT LT. SEMI BASEMENT
Rp. Rp. Rp. VOLUME HARGA (RP) VOLUME
8,462.40
6,888.00 7,232.40
15,700.00 235.50
60,000.00 420.00
70,000.00 490.00
80,000.00 56.00
95,000.00 28.50
- - Masuk OHC
657,230.00 836.70
32,861.50
- Tidak Pakai
- Masuk OHC
- Masuk OHC
- Masuk OHC
- Masuk OHC
- Masuk OHC
17,645.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
800.00 800.00
17,045.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
200.00 200.00
105,000.00 8,561.82
1,500,000.00 3.00
1,500,000.00 1,500,000.00 3.00 4,500,000.00
2,000,000.00 3.00
2,000,000.00 2,000,000.00 3.00 6,000,000.00
350,000.00 564.28
350,000.00 350,000.00 564.28 197,497,855.07
3,500,000.00 3.00
3,500,000.00 3,500,000.00 3.00 10,500,000.00
TOTAL 21,438,518,989.34
LT. SEMI BASEMENT LT. 1 LT. 2 LT. 3
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
47,943.29
55,134.78 396,970,441.20
2,876.60 172,595,844.00
2,876.60 201,361,818.00
287.66 23,012,779.20
143.83 13,663,837.65
47,943.29 38,354,632.00
306.40
352.36 2,536,992.00
18.38 1,103,040.00
18.38 1,286,880.00
1.84 147,072.00
0.92 87,324.00
306.40 61,280.00
9,930,900.00
2,179,951,364.72 1,544,441,307.76 1,544,441,307.76
TOTAL WORK LANTAI BASEMENT - LANTAI ATAP
LT. 6 LT. 7 LT. 8 LT. 9
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
-
-
-
-
-
-
376.49 354.65
636.73
533.82
192,441.67
209.18
20.92
1,045.88
50.20
243.34
16.79
251.78
493.88
780.34
266.70
26.67
26.67
128,399.52
256.80
256.80
513.60
128.40
5,991.98
249.28
622.83 630.82
11,891,076.74 76.72 11,891,076.74 77.70 12,043,576.72 2,374.67
29,206,245.27 10.43 29,206,245.27 10.56 29,580,807.80 322.87
3,129,240.56 208.62 3,129,240.56 211.29 3,169,372.26 6,457.45
1,401,361.65 155.71 1,401,361.65 157.70 1,419,333.75 4,819.71
873.05 873.05
- 1,290.86
1,147.95
55,134.78
2,876.60
2,876.60
287.66
143.83
47,943.29
352.36
18.38
18.38
1.84
0.92
306.40
161.08
3.00
3.00
564.28
3.00
1,171,066,261.53 1,171,189,750.78 1,060,288,500.17
TOTAL
HARGA
20,655,421,671.02
672,577,816.98
1,199,501,839.20
1,399,418,812.40
159,933,578.56
81,394,767.66
-
-
-
-
-
-
20,863,126,327.36
702,935,523.16
111,577,067.17
1,026,509,017.95
133,713,491.15
101,425,126.07
230,930,001.61
14,642,300.83
1,673,405.81
62,752,717.83
4,769,206.56
83,837,631.02
37,717,044.17
46,999,366.23
3,776,734.79
4,444,948.13
46,820,120.25
18,668,782.13
2,133,575.10
2,533,620.43
706,197,345.78
17,975,932.44
20,543,922.79
30,815,884.18
12,197,954.15
106,999,597.85
237,235,083.03
133,950,458.18
88,873,711.64
23,874,018.19
27,958,119.75
313,130,941.20
139,169,307.20
15,905,063.68
18,887,263.12
368,073,271.71
904,042,458.66
96,861,692.00
43,377,381.10
485,826,668.33
215,922,963.70
24,676,910.14
29,303,830.79
1,050,544,933.86
670,774,855.69
361,525,285.43
495,806,105.74
91,856,934.77
105,400,957.85
1,180,490,727.94
524,662,545.75
59,961,433.80
71,204,202.64
695,083,225.13
601,293,550.84
239,199,822.18
273,371,225.34
54,918,326.52
69,737,557.49
781,060,643.84
347,138,063.93
39,672,921.59
47,111,594.39
53,490,216.20
45,538,134.09
25,712,275.98
35,262,549.91
6,533,017.06
5,366,662.43
60,106,619.16
26,714,052.96
3,053,034.62
3,625,478.62
396,970,441.20
172,595,844.00
201,361,818.00
23,012,779.20
13,663,837.65
38,354,632.00
2,536,992.00
1,103,040.00
1,286,880.00
147,072.00
87,324.00
61,280.00
997,819,200.00
4,500,000.00
6,000,000.00
197,497,855.07
10,500,000.00
61,824,750,224.01
ANALISA HARGA SATUAN PEKERJAAN STRUKTUR R0 (20 Juni 2013) - ATELIER 6 STR
ANALISA NO. URAIAN BAHAN / MATERIAL VOLUME UNIT
Bahan
Floor Hardener warna Natural 5.0000 Kg
Upah
Tukang Batu 0.0100 Oh
Kepala Tukang 0.0100 Oh
Pekerja 0.0200 Oh
Mandor 0.0050 Oh
Alat :
Throwel 0.2333 Jam
17. Saluran
1.0000 M
18. Sumpit
1.0000 BH
R0 (20 Juni 2013) - ATELIER 6 STR
BAHAN / UPAH JUMLAH H. SATUAN LT. BASEMENT LT. SEMI BASEMENT
Rp. Rp. Rp. VOLUME HARGA (RP) VOLUME
8,462.40
6,888.00 7,232.40
15,700.00 235.50
60,000.00 420.00
70,000.00 490.00
80,000.00 56.00
95,000.00 28.50
- - Masuk OHC
657,230.00 836.70
32,861.50
- Tidak Pakai
- Masuk OHC
- Masuk OHC
- Masuk OHC
25,000.00 22,426.04 - -
210,000.00 19,400.03 - -
2,800,000.00 7,717.50 - -
2,800,000.00 8,820.00 - -
15,000.00 1,771.88 - -
9,000.00 2,250.00 - -
60,000.00 25,200.00 - -
70,000.00 11,200.00 - -
80,000.00 1,280.00 - -
95,000.00 1,520.00 - -
- Masuk OHC
25,000.00 22,426.04 - -
155,000.00 19,092.09 - -
2,800,000.00 10,780.00 - -
2,800,000.00 14,784.00 - -
15,000.00 2,739.00 - -
9,000.00 2,250.00 - -
60,000.00 25,200.00 - -
70,000.00 11,200.00 - -
80,000.00 1,280.00 - -
95,000.00 1,520.00 - -
- Masuk OHC
17,645.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
800.00 800.00
17,045.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
200.00 200.00
105,000.00 8,561.82
1,500,000.00 -
1,500,000.00 1,500,000.00 - -
2,000,000.00 -
2,000,000.00 2,000,000.00 - -
350,000.00 564.28
350,000.00 350,000.00 564.28 197,497,855.07
3,500,000.00 3.00
3,500,000.00 3,500,000.00 3.00 10,500,000.00
TOTAL 26,350,875,761.45
LT. SEMI BASEMENT LT. 1 LT. 2 LT. 3
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
- - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- - -
- - - - -
11,578,091,163.80 6,405,507,953.45 4,616,632,720.16
REALI
LT. 3 LT. 4 LT. 5 LT. 6
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
622.83 622.83 -
11,891,076.74 76.72 11,891,076.74 76.72 11,891,076.74 -
29,206,245.27 10.43 29,206,245.27 10.43 29,206,245.27 -
3,129,240.56 208.62 3,129,240.56 208.62 3,129,240.56 -
1,401,361.65 155.71 1,401,361.65 155.71 1,401,361.65 -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
-
2,272,500,768.06 1,598,483,808.63 1,586,159,805.53
REALISASI WORK LANTAI BASEMENT - LANTAI ATAP
LT. 6 LT. 7 LT. 8 LT. 9
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
- - -
258,253,517.93 - - - - -
8,409,200.75 - - - - -
14,997,300.69 - - - - -
17,496,850.81 - - - - -
1,999,640.09 - - - - -
1,017,673.98 - - - - -
- - -
117,481,730.76 - - - - -
3,958,279.34 - - - - -
628,298.31 - - - - -
5,780,344.43 - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
ada dimensi balok yg berubah)
18,615,896.36 - - - - -
11,886,283.77 - - - - -
6,406,310.69 - - - - -
8,785,797.52 - - - - -
1,627,725.88 - - - - -
1,867,729.07 - - - - -
20,918,565.53 - - - - -
9,297,140.24 - - - - -
1,062,530.31 - - - - -
1,261,754.75 - - - - -
- - -
da dimensi balok yg berubah)
23,606,732.08 - - - - -
20,421,404.58 - - - - -
8,123,812.97 - - - - -
9,284,357.68 - - - - -
1,865,161.14 - - - - -
2,368,458.59 - - - - -
26,526,736.22 - - - - -
11,789,660.54 - - - - -
1,347,389.78 - - - - -
1,600,025.36 - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
618,686,310.12 - -
LT. 9 LT. 10 LT. 11 LT. 12
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
LT. 12 LT. 13 LT. ATAP TOTAL
HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
- -
- - - - - 3,325,869.74
- - - - - 47,512.42
- - - - - 22,172.46
- - - - - 22,172.46
- - - - - 2,217.25
- - - - - 950.25
- -
- - - - - 18,377.54
- - - - - 17,502.42
- - - - - 17,502.42
- - - - - 17,502.42
636.73
533.82
192,441.67
209.18
20.92
1,045.88
50.20
243.34
16.79
251.78
493.88
780.34
266.70
26.67
26.67
128,399.52
256.80
256.80
513.60
128.40
5,991.98
- - - 1,123.32
- - - 35.11
- - - 23.30
- - - 1,168.13
- - - 2,279.93
- - - 3,830.29
- - - 1,459.16
- - - 145.92
- - - 145.92
- -
- - - - - 1,600.29
- - - - - 217.58
- - - - - 4,351.67
- - - - - 3,248.00
- - - - - 5,456.64
- - - - - 2,078.72
- - - - - 207.87
- - - - - 207.87
- -
- - - - - 32,702.91
- - - - - 3,367.88
- - - - - 100.48
- - - - - 137.81
- - - - - 4,765.76
- - - - - 9,114.10
- - - - - 15,311.69
- - - - - 5,833.02
- - - - - 583.30
- - - - - 583.30
- -
- - - - - 16,924.67
- - - - - 1,742.97
- - - - - 52.00
- - - - - 59.43
- - - - - 2,228.69
- - - - - 4,716.80
- - - - - 7,924.23
- - - - - 3,018.75
- - - - - 301.88
- - - - - 301.88
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
-
-
-
-
-
-
-
-
-
-
- - 8,561.82
564.28
3.00
- - -
TOTAL
HARGA
22,908,590,750.10
745,945,069.64
1,330,347,894.90
1,552,072,544.04
177,379,719.32
90,273,607.15
16,363,362,132.30
551,326,217.40
87,512,098.00
805,111,301.59
133,713,491.15
101,425,126.07
230,930,001.61
14,642,300.83
1,673,405.81
62,752,717.83
4,769,206.56
37,717,044.17
46,999,366.23
3,776,734.79
4,444,948.13
46,820,120.25
18,668,782.13
2,133,575.10
2,533,620.43
706,197,345.78
17,975,932.44
20,543,922.79
30,815,884.18
12,197,954.15
106,999,597.85
174,114,800.85
98,310,743.30
65,227,403.99
17,521,944.35
20,519,403.75
229,817,322.00
102,141,032.00
11,673,260.80
13,861,997.20
248,044,225.35
609,233,347.21
65,275,001.49
29,231,975.59
327,398,126.58
145,510,278.48
16,629,746.11
19,747,823.51
817,572,650.15
522,021,627.77
281,352,254.61
385,854,520.61
71,486,440.20
82,026,896.39
918,701,239.54
408,311,662.02
46,664,189.94
55,413,725.56
423,116,678.56
366,024,270.00
145,607,649.00
166,408,741.72
33,430,327.58
42,451,209.62
475,453,547.76
211,312,687.89
24,150,021.47
28,678,150.50
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
898,991,100.00
197,497,855.07
10,500,000.00
55,026,938,291.21
ANALISA HARGA SATUAN PEKERJAAN STRUKTUR R0 (20 Juni 2013) - ATELIER 6
ANALISA NO. URAIAN BAHAN / MATERIAL VOLUME UNIT
Bahan
Floor Hardener warna Natural 5.0000 Kg
Upah
Tukang Batu 0.0100 Oh
Kepala Tukang 0.0100 Oh
Pekerja 0.0200 Oh
Mandor 0.0050 Oh
Alat :
Throwel 0.2333 Jam
17. Saluran
1.0000 M
18. Sumpit
1.0000 BH
RUKTUR R0 (20 Juni 2013) - ATELIER 6 STR
BAHAN / UPAH JUMLAH H. SATUAN LT. BASEMENT
Rp. Rp. Rp. VOLUME HARGA (RP)
8,462.40 7,270.72
8,462.40
6,888.00 7,232.40
15,700.00 235.50
60,000.00 420.00
70,000.00 490.00
80,000.00 56.00
95,000.00 28.50
- - Masuk OHC
1,017,420.00 64.02
657,230.00 -
32,861.50
210,000.00 159,810.00 - -
190,000.00 121,220.00 - -
1,200.00 276,000.00 - -
70,000.00 17,500.00 - -
80,000.00 2,000.00 - -
60,000.00 75,000.00 - -
95,000.00 5,700.00 - -
3 x Pakai 82,557.08 -
155,000.00 19,092.09 - -
2,800,000.00 23,790.73 - -
15,000.00 1,911.76 - -
9,000.00 2,250.00 - -
60,000.00 23,700.00 - -
70,000.00 9,450.00 - -
80,000.00 1,080.00 - -
95,000.00 1,282.50 - -
- Tidak Pakai
34,841.67 -
5,500.00 27,500.00 - -
- -
70,000.00 700.00 - -
80,000.00 800.00 - -
60,000.00 1,200.00 - -
95,000.00 475.00 - -
17,857.14 4,166.67 - -
3 x Pakai 80,395.75 -
155,000.00 19,092.09 - -
2,800,000.00 10,780.00 - -
2,800,000.00 7,152.34 - -
15,000.00 1,921.32 - -
9,000.00 2,250.00 - -
60,000.00 25,200.00 - -
70,000.00 11,200.00 - -
80,000.00 1,280.00 - -
95,000.00 1,520.00 - -
- Masuk OHC
3 x Pakai 112,459.34 -
155,000.00 19,092.09 - -
2,800,000.00 46,893.00 - -
15,000.00 5,024.25 - -
9,000.00 2,250.00 - -
60,000.00 25,200.00 - -
70,000.00 11,200.00 - -
80,000.00 1,280.00 - -
95,000.00 1,520.00 - -
- Masuk OHC
- Masuk OHC
- Masuk OHC
- Masuk OHC
17,645.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
800.00 800.00
17,045.00
7,200.00 8,280.00
60,000.00 3,600.00
70,000.00 4,200.00
80,000.00 480.00
95,000.00 285.00
200.00 200.00
105,000.00 -
105,000.00 105,000.00 - -
1,500,000.00 3.00
1,500,000.00 1,500,000.00 3.00 4,500,000.00
2,000,000.00 3.00
2,000,000.00 2,000,000.00 3.00 6,000,000.00
350,000.00 -
350,000.00 350,000.00 - -
3,500,000.00 -
3,500,000.00 3,500,000.00 - -
TOTAL 178,296,693.91
LT. SEMI BASEMENT LT. 1 LT. 2
VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME HARGA (RP)
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
258.05 - 97.34
188.23 - -
23.18 3,593,640.99 - - - -
3.15 8,826,514.41 - - - -
63.05 945,697.97 - - - -
47.06 423,510.06 - - - -
79.06 4,743,312.71 - - - -
30.12 2,108,138.98 - - - -
3.01 240,930.17 - - - -
3.01 286,104.58 - - - -
2,236.05 105.19
118.44 95.12
47,943.29
55,134.78 396,970,441.20
2,876.60 172,595,844.00
2,876.60 201,361,818.00
287.66 23,012,779.20
143.83 13,663,837.65
47,943.29 38,354,632.00
306.40
352.36 2,536,992.00
18.38 1,103,040.00
18.38 1,286,880.00
1.84 147,072.00
0.92 87,324.00
306.40 61,280.00
198.09 487.47
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
94.58
94.58 9,930,900.00
77,043,058.80 34,122,945.59 46,446,948.68
REMAIN WORK LANTAI BASEMENT - LANTAI ATAP
LT. 6 LT. 7 LT. 8
VOLUME HARGA (RP) VOLUME HARGA (RP) VOLUME
1,077.90 - 1,290.86
61.55 1,147.95
161.08
161.08
1,191,237,190.41 1,191,237,190.41 1,247,612,796.57
LT. ATAP TOTAL
HARGA (RP) VOLUME HARGA
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
407.23 63,120,282.18
12.73 35,639,714.88
8.45 23,646,307.64
423.47 6,352,073.84
826.52 7,438,716.00
1,388.56 83,313,619.20
528.98 37,028,275.20
52.90 4,231,802.88
52.90 5,025,265.92
12,043,576.72 774.38 120,029,046.36
29,580,807.80 105.29 294,809,111.45
3,169,372.26 2,105.78 31,586,690.51
1,419,333.75 1,571.71 14,145,405.51
2,139.61 53,490,216.20
293.79 45,538,134.09
9.18 25,712,275.98
12.59 35,262,549.91
435.53 6,533,017.06
596.30 5,366,662.43
1,001.78 60,106,619.16
381.63 26,714,052.96
38.16 3,053,034.62
38.16 3,625,478.62
55,134.78 396,970,441.20
2,876.60 172,595,844.00
2,876.60 201,361,818.00
287.66 23,012,779.20
143.83 13,663,837.65
47,943.29 38,354,632.00
352.36 2,536,992.00
18.38 1,103,040.00
18.38 1,286,880.00
1.84 147,072.00
0.92 87,324.00
306.40 61,280.00
3.00 4,500,000.00
3.00 6,000,000.00
- -
- -
1,120,602,793.35 15,174,564,015.94
Total Semua
Jenis Pekerjaan
Volume Harga
Bahan
Upah
Alat
Alat Bantu Pengecoran (Vibrator) 22,315.41 111,577,067.17
Concrete Pump 22,315.41 1,026,509,017.95
Throwel 5,991.98 106,999,597.85
Total 61,522,414,737.93
Total + Man hole + Tangga servis + Saluran + Sumpit 61,740,912,592.99
Realisasi Remain Work Koreksi
Volume Harga Volume Harga Volume Harga