KURVA S DAN BOBOT PELAKSANAAN

WAKTU PELAKSANAAN
BOBOT
NO JENIS PEKERJAAN MINGGU KE
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1 PEK. PENDAHULUAN 3.69 2.217 0.739 0.739

2 PEK. TANAH, PONDASI DAN URUGAN 7.41 2.222 2.222 2.22 0.741

3 PEK. DINDNG DAN BETON 31.57 6.31 6.31 6.31 4.74 4.74 3.16

4 PEK. KAYU,KUSEN,ALMUNIUM DAN KACA 9.48 1.90 2.84 2.84 1.90

5 PEK. RANGKA ATAP DAN PLAFOND 26.54 2.654 3.98 5.31 6.64 3.98 3.98

6 PEK. ANCHOR DAN BAUT 0.95 0.14 0.38 0.43

7 PEK. LANTAI DAN DINDING KERAMIK 8.00 0.80 1.60 2.00 2.00 1.60

8 PEK. INSTALASI LISTRIK 2.03 0.406 0.813 0.609 0.20

9 PEK. SANITASI 2.44 0.73 0.97 0.49 0.244

10 PEK. FINISHING 7.89 0.79 3.16 3.94

TOTAL (%) 100

RENCANA FISIK PERMINGGU 2.22 0.74 2.96 2.22 2.22 7.05 6.31 6.31 5.47 7.39 7.14 5.31 7.58 5.96 6.41 2.00 2.01 2.71 3.45 4.02 3.17 3.40 3.94

RENCANA FISIK KOMULATIF 2.22 2.96 5.92 8.14 10.36 17.41 23.73 30.04 35.51 42.90 50.04 55.34 62.92 68.88 75.29 77.29 79.30 82.01 85.46 89.48 92.66 96.06 100.00