6 Mandor oh 100,000.00
Jumlah 799,037.00
Jumlah 43,154.12
Analisis Harga Satuan 1 m3 Sloof Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12 ring 8-15
No. Uraian Satuan Volume Harga Satuan Harga
(Rp.) (Rp.)
1 Kayu papan terentang m3 0.27 2,850,000 769,500
2 Paku Biasa 2" - 5" kg 2 23,400 46,800
3 Besi Beton kg 180 16,500 2,970,000
4 Kawat Beton kg 3 27,700 83,100
5 Semen Portland kg 323 1,406 454,138
6 Pasir Beton m3 0.52 225,000 117,000
7 Koral Beton 2/3 m3 0.78 250,000 195,000
8 Pekerja oh 4.85 65,000 315,250
9 Tukang Batu oh 0.35 80,000 28,000
10 Tukang Kayu oh 1.56 80,000 124,800
11 Tukang Besi oh 1.4 80,000 112,000
12 Kepala Tukang oh 0.331 90,000 29,790
13 Mandor oh 0.17 100,000 17,000
Jumlah 5,262,378.00
Analisis Harga Satuan 1 m3 Kolom Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12 ring 8-15
No. Uraian Satuan Volume Harga Satuan Harga
(Rp.) (Rp.)
1 Kayu papan terentang m3 0.4 2,850,000 1,140,000
2 Paku Biasa 2" - 5" kg 4 23,400 93,600
3 Minyak Bekisting ltr 40,500 0
4 Besi Beton kg 180 16,500 2,970,000
5 Kawat Beton kg 1.8 27,700 49,860
6 Semen Portland kg 323 1,406 454,138
7 Pasir Beton m3 0.52 225,000 117,000
8 Koral Beton 2/3 m3 0.78 250,000 195,000
9 Kayu Balok Terentang M3 0.15 2,640,000 396,000
10 Dolken Ø-8-10/4m Btg 20 15,000 300,000
11 Pekerja oh 7.3 65,000 474,500
12 Tukang Batu oh 0.35 80,000 28,000
13 Tukang Kayu oh 3.3 80,000 264,000
14 Tukang Besi oh 2.1 80,000 168,000
15 Kepala Tukang oh 0.57 90,000 51,300
16 Mandor oh 0.25 100,000 25,000
Jumlah 6,726,398.00
Analisis Harga Satuan Pemasangan Pintu Angkat Lebar 50 cm, Tinggi 70 cm, Tebal Plat 6 mm.
No. Uraian Satuan Volume Harga Satuan Harga
(Rp.) (Rp.)
1 Sloof Beton Tulang 15/20 m3 0.03 5,262,378.00 157,871.34
2 Kolom Beton Tulang 15/20 m3 0.048 6,726,398.00 322,867.10
3 Pekerja oh 0.9 65,000.00 58,500.00
4 Tukang Batu oh 0.45 80,000.00 36,000.00
5 Kepala Tukang oh 0.045 90,000.00 4,050.00
6 Mandor oh 0.09 100,000.00 9,000.00
Jumlah 588,288.44