Anda di halaman 1dari 1

RINCIAN ANGGARAN BIAYA

PENGUKURAN GEOLOGI DASAR


ALAT SONDIR

RINCIAN VOLUME
VOLUME HARGA
NO JENIS BIAYA KEGIATAN JUMLAH
KEGIATAN SATUAN
ORG JMLH HR
I BIAYA PERSONIL
I TENAGA KERJA
1.1 Team Leader 1 14 14 350,000 4,900,000.00
1.2 Ahli Geoteknik 1 14 14 250,000 3,500,000.00
1.3 Laboran 2 14 28 225,000 6,300,000.00
1.4 Teknisi 2 14 28 200,000 5,600,000.00
1.5 Tenaga Pembantu 15 14 210 175,000 36,750,000.00
1.6 Sopir 1 14 14 150,000 2,100,000.00

JUMLAH 22 Sub Total 59,150,000.00

RINCIAN VOLUME VOLUME HARGA


NO JENIS BIAYA JUMLAH
UNIT JMLH HR KEGIATAN SATUAN
II BIAYA NON PERSONIL
I TRANSPORTASI
1.1 Sewa Kendaraan Roda Empat (PP) 1 2 2 1,500,000 3,000,000.00
1.2 Sewa Kendaraan Roda Dua 2 14 28 250,000 7,000,000.00
1.3 Sewa Perahu 3 14 42 150,000 6,300,000.00
JUMLAH 6 Sub Total 16,300,000.00

RINCIAN VOLUME VOLUME HARGA


NO JENIS BIAYA JUMLAH
UNIT JMLH HR KEGIATAN SATUAN
III BIAYA OPERASIONAL DAN SEWA ALAT
2.1 Alat Sondir 2 14 28 350,000 9,800,000.00
2.2 Alat Hand Bord 2 14 28 250,000 7,000,000.00
2.3 Kamera Digital 1 14 14 100,000 1,400,000.00
2.4 Akomodasi 22 14 308 50,000 15,400,000.00

JUMLAH Sub Total 33,600,000.00

RINCIAN VOLUME KEGIATAN HARGA


NO JENIS BIAYA JUMLAH
vol sat SATUAN
IV BIAYA PENGADAAN
3.1 Alat Tulis Kantor 1 Paket 750,000 750,000.00
3.2 Pembuatan rakit 2 Unit 4,500,000 9,000,000.00

JUMLAH Sub Total 9,750,000.00

JUMLAH TOTAL (I + I I+ III + IV) 118,800,000.00