1 2 3 4
PEKERJAAN TAMAN
I. PEKERJAAN PERSIAPAN
1.1 Pembersihan Lokasi Ls 1 Unit
1.2 Pemasangan Bowplank A.2.2.1.4 82 M
1.3 Pemasangan Papan Nama Proyek Ls 1 Unit
V. PEKERJAAN STRUKTUR
5.1 Pekerjaan Rabat Beton A.4.1.1.8 2.2 M3
15.38333
Harga Satuan Jumlah Harga
5 6
Rp 2,000,000 Rp 2,000,000
Rp 69,000 Rp 5,658,000
Rp 150,000 Rp 150,000
TOTAL I Rp 7,808,000
Rp 135,000 Rp 40,500
Rp 192,000 Rp 28,800
Rp 98,000 Rp 1,303,400
TOTAL II Rp 1,372,700
Rp 159,000 Rp 6,887,000
Rp 182,000 Rp 6,370,000
Rp 100,000 Rp 4,300,000
Rp 60,000 Rp 2,580,000
Rp 111,000 Rp 1,998,000
TOTAL III Rp 22,135,000
Rp 241,500 Rp 724,500
Rp 165,000 Rp 1,980,000
Rp 65,000 Rp 6,230,250
Rp 42,000 Rp 2,520,000
Rp 147,000 Rp 3,528,000
Rp 250,000 Rp 11,537,500
TOTAL IV Rp 26,520,250
Rp 1,048,000 Rp 2,305,600
TOTAL V Rp 2,305,600
Rp 32,000 Rp 984,000
TOTAL VI Rp 984,000
Rp 1,500,000 Rp 4,500,000
TOTAL VII Rp 4,500,000
Rp 65,625,550 65625550 9375000
Rp 8,203,194 0.142856
Rp 73,828,744
Rp 73,829,000
RENCANA ANGGARAN BIAYA TAMAN
1 2 3 4 5 6
PEKERJAAN TAMAN
I. PEKERJAAN PERSIAPAN
1.1 Pembersihan Lokasi Ls 1 Unit Rp 2,000,000 Rp 2,000,000
1.2 Pemasangan Bowplank A.2.2.1.4 59 M Rp 69,000 Rp 4,071,000
1.3 Pemasangan Papan Nama Proyek Ls 1 Unit Rp 150,000 Rp 150,000
TOTAL I Rp 6,221,000
II. PEKERJAAN TANAH
2.1 Pekerjaan Galian Kanstin Pracetak 40x20x10 cm A.2.3.1.1 0.3 M3 Rp 135,000 Rp 40,500
2.2 Pasir Urug di Bawah Kanstin A.2.3.1.11 0.15 M3 Rp 192,000 Rp 28,800
2.3 Pekerjaan Urug Tanah A.2.3.1.9 13.3 M3 Rp 98,000 Rp 1,303,400
TOTAL II Rp 1,372,700
III. PEKERJAAN PASANGAN
3.1 Pasangan 1/2 Bata Merah A.4.4.1.10 43.31 M2 Rp 159,000 Rp 6,887,000
3.2 Pemasangan Kanstin Pracetak 20x45x30 cm Ls 39.5 M' Rp 182,000 Rp 7,189,000
3.3 Pekerjaan Plesteran A.4.4.2.14 43 M2 Rp 100,000 Rp 4,300,000
3.4 Pekerjaan Acian A.4.4.2.27 43 M2 Rp 60,000 Rp 2,580,000
3.5 Pasang Pipa PVC Saluran 3 inch (Sedang) A.5.1.1.31 10 M Rp 111,000 Rp 1,110,000
TOTAL III Rp 22,066,000
IV. PEKERJAAN TAMAN
4.1 Penanaman Bintaro (Tinggi 2m) Ls 1 Phn Rp 241,500 Rp 241,500
4.2 Penanaman Palem Raja Ls 8 Phn Rp 165,000 Rp 1,320,000
4.2 Penanaman Rumput Gajah Manila Ls 74.51 M2 Rp 65,000 Rp 4,843,150
4.3 Penanaman Rombusa Mini Ls 75 Phn Rp 42,000 Rp 3,150,000
4.4 Penanaman Pucuk Merah (Tinggi 1.25 m Ls 24 Phn Rp 147,000 Rp 3,528,000
4.5 Tanah Subur Ls 45.21 M3 Rp 250,000 Rp 11,301,500
TOTAL IV Rp 24,384,150
V. PEKERJAAN STRUKTUR
5.1 Pekerjaan Rabat Beton A.4.1.1.8 2.2 M3 Rp 1,048,000 Rp 2,305,600
TOTAL V Rp 2,305,600
VI. PEKERJAAN PENGECATAN
6.1 Pengecatan Kursi Taman A.4.7.1.10 30.75 M2 Rp 32,000 Rp 984,000
TOTAL VI Rp 984,000
JUMLAH I, II, III,I IV, V, VI Rp 57,333,450
PPN 12,5% Rp 7,166,681
TOTAL KESELURUHAN Rp 64,500,131
DIBULATKAN Rp 64,500,000