Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
1 Pekerja O / Hari 0.04837 110,000.00 5,321.03
###
3 Mandor O / Hari 0.01791 1,964.29 35.18
B. Bahan
C. Alat
1 Bulldozer Jam 0.03329 298,000.00 9,920.42
1 Alat Bantu Ls 1.00000 1,500.00 1,500.00
Jumlah 16,776.63
Overhead 15% 2,516.49
Total Harga 19,293.12
ANALISA HARGA SATUAN PEKERJAAN
Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
1 Pekerja O / Hari 0.56000 110,000.00 61,600.00
2 Mandor O / Hari 0.04800 1,964.29 94.29
B. Bahan
C. Alat
1 Excavator Jam 0.04028 727,000.00 29,286.13
Jumlah 90,980.42
Overhead 15% 13,647.06
Total Harga 104,627.48
ANALISA HARGA SATUAN PEKERJAAN
Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
1 Pekerja O / Hari 0.43000 110,000.00 47,300.00
2 Mandor O / Hari 0.05000 1,964.29 98.21
B. Bahan
C. Alat
1 Excavator Jam 0.01910 727,000.00 13,885.70
2 Vibrator Roller Jam 0.02713 38,500.00 1,044.63
Jumlah 62,328.55
Overhead 15% 9,349.28
Total Harga 71,677.83
ANALISA HARGA SATUAN PEKERJAAN
Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
Menganyam
1 Pekerja O / Hari 0.06000 110,000.00 6,600.00
2 Kepala Tukang O / Hari 0.03700 130,000.00 4,810.00
Mengisi
1 Pekerja O / Hari 0.12000 110,000.00 13,200.00
2 Mandor O / Hari 1.33000 1,964.29 2,612.50
B. Bahan
1 Batu Kali M3 1.20000 9,500.00 11,400.00
2 Bronjong Buah 1.00000 12,000.00 12,000.00
C. Alat
1 Alat Bantu Ls 1.00000 1,500.00 1,500.00
Jumlah 52,122.50
Overhead 15% 7,818.38
Total Harga 59,940.88
ANALISA HARGA SATUAN PEKERJAAN
Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
1 Pekerja O / Hari 0.30000 110,000.00 33,000.00
2 Tukang O / Hari 0.10000 120,000.00 12,000.00
3 Kepala Tukang O / Hari 0.02000 130,000.00 2,600.00
4 Mandor O / Hari 0.01000 1,964.29 19.64
B Bahan
1 Kayu Nani Ø10-12 cm m' 1.05000 15,182.00 15,941.10
C Alat
1 Alat Bantu Ls 1.00000 45,000.00 45,000.00
Jumlah 108,560.74
Overhead 15% 16,284.11
Total Harga 124,844.85
Harga Total
No. Uraian Satuan Kuantitas Satuan Harga
Rp. Rp.
A. Upah
1 Pekerja Jam 4.01606 15,714.29 63,109.58
2 Tukang Jam 1.20482 17,142.86 20,654.04
3 Mandor Jam 0.40161 280.61 112.70
B Bahan
1 Batu M3 1.08000 9,500.00 10,260.00
2 Semen (PC) Sak 161.00000 368,750.00 59,368,750.00
3 Pasir M3 0.48287 210,000.00 101,403.59
C Peralatan
1 Conc. Mixer Jam 0.40161 45,000.00 18,072.29
2 Alat Bantu Ls 1.00000 15,000.00 15,000.00
Jumlah 59,597,362.20
Overhead 15% 8,939,604.33
Total Harga 68,536,966.53
REKAPITULASI
Terbilang : " SERATUS SEBELAS JUTA DUA RATUS TUJUH PULU RIBU RUPIAH "
Catatan :
Harga tersebut sudah termasuk keuntungan pemborong, IMB dan Dobo,…………………..2021
Dibuat Oleh
Konsultan Perencana
CV. PUTRA TUNGGAL DESIGN
Harga
UPAH
1 MANDOR O/H 187,000.00
2 KEPALA TUKANG O/H 161,000.00
3 TUKAN KAYU O/H 107,000.00
4 TUKANG BATU O/H 107,000.00
5 TUKANG BESI O/H 107,000.00
6 TUKANG CAT O/H 107,000.00
11 PEKERJAAN FISIK SETAPAK O/H 86,000.00
PEKERJAAN FISIK SETAPAK
A BAHAN BANGUNAN
Dibuat Oleh :
Konsultan Perencana
CV. PUTRA TUNGAL DESIGN
No Uraian Pekerjaan Satuan Volume Harga Satuan JUMLAH HARGA PAJAK 10 % TOTAL HARGA
Harga
UPAH
1 MANDOR O/H 175,000.00
2 KEPALA TUKANG O/H 150,000.00
3 TUKAN KAYU O/H 100,000.00
4 TUKANG BATU O/H 100,000.00
5 TUKANG BESI O/H 100,000.00
6 TUKANG CAT O/H 100,000.00
11 PEKERJA O/H 80,000.00
A BAHAN BANGUNAN
VOLUME
SEKSION ITEM KEGIATAN SKETSA
P x L x T
A. Rabat Beton
58 x 3 x 0.15
26.1
Bakesting 199
0.2 x 199.41 39.882
VOLUME
SEKSION ITEM KEGIATAN SKETSA
P x L x T
B. Rabat Beton
141 x 2 x 0.15
42.42
TOTAL GALIAN TANAH = M3
TOTAL PASIR URUG =
TOTAL BATU KOSONG = M3
TOTAL PAS. BATU = M3
TOTAL RABAT = 68.523 M3
TOTAL PLESTERAN = M2
6,858.11
Rp 200,000,000.00000